You are on page 1of 6

DC Hi Pot Testing

Excerpt
from
PRYSMIAN’S
WIRE AND CABLE
ENGINEERING GUIDE

(FOR INFORMATIONAL
PURPOSES ONLY)

700 Industrial Drive DC Hi-Pot Testing


Lexington, South Carolina 29072 Revision 1
Phone: 1.800.845.8507 March 09,2010
Fax: 1.803.951.1142 Page 1 of 6
www.na.prysmian.com/energy
DC HIGH POTENTIAL TESTING

DC Hi-Pot testing can be applied as a GENERAL INFORMATION:


withstand test (a Type I – Destructive Test) • DC Hi-Pot Testing is commonly applied at
or a leakage current measurement much higher voltage levels than megger
technique (a Type II – Non-Destructive test). testing. The elevated voltage levels place
The Hi-Pot withstand test is a Pass/Fail test more electrical stress on the dielectric†
that has been applied to many types of (megger testing is typically used at
cable and accessories. The Hi-Pot leakage voltages up to 5kV).
current technique is a diagnostic test which • DC Hi-Pot Testing is typically reserved for
involves the measurement of leakage shielded, medium-voltage cables †.
current when a high potential (above • Several types of currents are flowing at
nominal) is applied to the conductor while the beginning of this test.
the metallic shield of the cable is grounded. o Capacitive current – Current required to
The behavioral characteristics of the charge the capacitance of the insulation;
leakage current are evaluated to determine after all, cable is a long capacitor. This
the condition of the cable, specifically the current quickly declines to zero †.
insulation. o Absorption or Polarization current –
Current absorbed by the insulation
As part of any cable testing program, many during molecular changes in the
factors must be considered to properly insulation. This current may go to zero
characterize the test results obtained. Many quickly or possibly linger for an
of those factors are controllable as part of extended period of time†.
material testing, qualification testing, and o Leakage current – This current is the
production testing. Unfortunately, field primary current to be concerned with.
testing does not allow control over various This current quickly reaches and
factors, two of which are temperature and maintains a constant value †.
humidity. Keeping track of the factors that o Total Current – is comprised of the
influence cable testing results and Capacitive Current, the Absorption
accounting for them can be the difference Current and the Leakage Current †.
between passing or failing results. • In order to obtain leakage current readings
that are most representative of the cable
It is important to recognize that published system, and to insure against flashovers
documentation provides details showing DC to other structures, all bus ties and/or
hi-pot testing mostly finds conductive type aerial jumpers from the terminals should
gross workmanship errors in extruded be removed before performing such tests†.

dielectric cable systems . Consequently,
• It is sometimes necessary to “smooth” any
the practical use of the DC hi-pot testing is
sharp edges or points of the hardware on
recommended only for paper insulated cable
the terminal top fittings using a soft, putty-
systems and for performing a safety check
like insulating compound. This helps
before switching an extruded cable system
reduce stress concentration and corona
into service (to prove that the system is not
discharge off such sharp projections.
grounded).
Alternatively, or in addition, a clean, dry
plastic bucket or trashcan (containing NO
Additional details on DC high potential
metallic fittings) is placed over the top of
testing can be found by referencing IEEE
the terminals to effectively lengthen the
400.1 IEEE Guide for Field-Testing of
leakage path to a surrounding grounded
Laminated Dielectric, Shielded Power Cable
structure. Note that the far-end terminals
Systems Rated 5kV and Above with High
must be treated in the same manner.
Direct Current Voltage.

700 Industrial Drive DC Hi-Pot Testing


Lexington, South Carolina 29072 Revision 1
Phone: 1.800.845.8507 March 09,2010
Fax: 1.803.951.1142 Page 2 of 6
www.na.prysmian.com/energy
• Because surface contamination or should be cleared before the high voltage
moisture can significantly increase DC test is performed.
leakage current flow over the surface of • Connect output of test set to
the terminals, all surfaces of the terminal conductor/terminal to be tested and
insulators should be carefully wiped to connect ground terminal of test set to
remove any contamination and moisture ground.
and remain completely clean and dry • Bring DC voltage up to prescribed test
during the test. level in five equal steps. Raise the voltage
o For the same reason, such testing is at an even rate, so as to reach the
normally not performed in inclement required level in not less than 10 seconds.
weather (rain, snow, sleet, fog) when Hold the voltage at each step for 60
there are outdoor terminations involved. seconds. Read and record the leakage
The most representative test results will current at the end of each hold period.
be obtained when the tests are • Hold the full test voltage for not less than
performed under cool, dry weather 10 minutes or more than 15 minutes.
conditions. Read and record the leakage current at
• After each cable has been tested, its 15-second intervals for the first 2 minutes
conductor should be grounded, using a and then every minute for the duration of
properly terminated resistor, to drain off the test.
the electrical charge that has accumulated • Bring the test voltage control quickly and
in the cable. To ensure that this charge smoothly to zero. Read and record the
has been completely drained, the voltage remaining on the cable after 30
conductor should be grounded for a period and 60 seconds. Discharge the cable to
of time equal to or not less than 5 times ground using a properly terminated
the test period. resistor stick. When the test set voltmeter
o If there is any doubt that this has been indicates zero voltage on the cable, attach
done, ground the cable with a grounding a solid ground to the cable and then
stick before starting any work after such disconnect the test set and resistor stick.
testing has been performed. • Test each conductor/cable in the circuit in
the same manner.
STEP-BY-STEP PROCEDURE FOR • Record all data concerning the circuit and
DC FIELD TESTING test results.
• Ground all conductors, except the one to
be tested. LEAKAGE CURRENT BEHAVIOR:
• Connect cable shield to ground; ground ANALYZING THE RESULTS
any adjacent equipment. The following Leakage Current
• Ensure adequate clearance of the characteristics are of significance in
conductor/terminals to be tested from evaluating the condition of the cable:
ground to prevent flash over. ƒ Linearity of the leakage current at a
• Carefully wipe terminals to remove any number of incremental voltages between
contamination (i.e. dust, moisture, etc.) zero and the prescribed test voltage.
• Corona-proof conductor/terminal ends of ƒ The behavior of the leakage current when
cable by sufficiently taping them. If cable the prescribed test voltage is reached and
is terminated, cover termination with a maintained for the duration of the test.
polyethylene bucket or bag. ƒ With a sound system, the current will drop
• Fence test cable ends to ensure rapidly from the value indicated when the
personnel safety. test voltage is first reached, with the
• Preliminary step: ‘Megger’ cable to be decrease gradually diminishing until the
tested. Any cable that exhibits low current becomes stable at a value well
‘Megger’ readings is questionable and below the peak.

700 Industrial Drive DC Hi-Pot Testing


Lexington, South Carolina 29072 Revision 1
Phone: 1.800.845.8507 March 09,2010
Fax: 1.803.951.1142 Page 3 of 6
www.na.prysmian.com/energy
ƒ Instability of the leakage current (provided DC Hi-Pot testing can be used as a testing
that is not caused by test set supply method for On-Reel testing of shielded,
voltage fluctuations or corona discharge at medium voltage cables. The procedures
terminals) may be an indication of incipient above should be followed while utilizing the
breakdown. In such cases, an extension voltage limits as specifically listed in Table 1.
of the test period may be appropriate to
precipitate breakdown, thereby pinpointing It is important to note that any intention to
the problem and making location possible. On-Reel test cables should be pointed out to
ƒ If the leakage current does not decrease, the manufacturer. In order to facilitate On-
or begins increasing after an initial drop, it Reel testing by the end-user, the
is a strong sign of trouble in the cable manufacturer will have to ensure test ‘tails’
system. As noted above, one course of are present on the reel. Test tails will consist
action in such cases is to extend the test of allowing access to appropriate lengths of
so as to precipitate breakdown and make cable at the drum end of the cable. This will
location of the defective section possible. enable the connection of both cable ends to
ƒ In general, it is not considered meaningful the necessary test equipment. Test tails
to compare values of leakage current typically consist of a length of cable at the
measured on the same cable at different drum end that is approximately 24 inches
times, or on different but like cables at the long.
same time. The reason being, there are
many factors (cable temperature, number INSTALLATION TESTING
and type of splices, type of terminals or Installation testing is conducted after cable
terminations, cleanliness of terminal or installation but before jointing (splicing) or
termination surfaces, length of cable terminating. The test is intended to detect
circuit, air temperature, humidity, etc.) shipping, storage, or installation damage.
which can affect these measurements and Installation testing of cable offers the best
can make such direct comparisons less possible assurance that the cable has not
than meaningful. been damaged and will perform satisfactorily
when energized.
ON-REEL TESTING
On-Reel (field) testing is a rather uncommon There are many ways cables can be
practice that allows the end user or installer damaged during installation: pulling through
to test the integrity of the cable on the reel at ducts that are in poor condition, improper
the time of delivery and prior to installation. use of pulling equipment, exceeding
On-Reel (field) testing is uncommon due to minimum bending radii or training radii, or
the fact that prior to shipping, the cable exceeding maximum pulling tensions or
undergoes a thorough testing program at the maximum sidewall bearing pressures. If
factory. On-Reel testing by the end-user damage has occurred during installation, it is
insures that the cable has arrived without important to determine this prior to
sustaining any damage while in transit. energizing. Installation testing can prevent a
During shipment the cable may be loaded safety hazard or a potential cable or
and unloaded several times after it leaves accessory failure during inopportune times.
the manufacturer and before it arrives at its To test the integrity of only the cable, the
final destination. This extraneous, but installation test should be performed. Once
sometimes necessary, handling of the cable the cable tests satisfactorily, the accessories
provides added opportunity for the cable to can then be applied and the system can be
experience mechanical damage. If the cable ‘Acceptance Tested’ to ensure the
is damaged during transit and is not On- accessories were applied successfully and
Reel tested, the cable may then be installed, are of good quality.
prepared, and tested only to determine the
cable is failing installation test due to DC Hi-Pot testing can be used as a testing
damage incurred during shipping. method for installation testing of shielded,

700 Industrial Drive DC Hi-Pot Testing


Lexington, South Carolina 29072 Revision 1
Phone: 1.800.845.8507 March 09,2010
Fax: 1.803.951.1142 Page 4 of 6
www.na.prysmian.com/energy
medium voltage cables. The procedures While there are multiple maintenance test
above should be followed while utilizing the methods available, DC Hi-Pot Testing is not
voltage limits as specifically listed in Table 1. recommended as a maintenance test for any
solid dielectric insulated cable, especially for
ACCEPTANCE TESTING Cross-Linked Polyethylene (XLPE/TRXLPE)
Acceptance testing is conducted after the cables and definitely not after five years of
cable system installation, including all in-service life. Several sources indicate that
terminations and joints (splices), but before DC testing of power cables that have been
the cable system is placed into normal in service can result in premature failures as
service. The test is intended to detect a direct result of DC Hi-Pot testing. More
installation damage and to show any gross information concerning this issue can be
defects or errors in installation of other found in the Electric Power Research
system components/accessories. Institute (EPRI) project report TR-101245
“Effect of DC Testing on Extruded Cross-
DC Hi-Pot testing can be used as a testing Linked Polyethylene Insulated Cables” as
method for acceptance testing of shielded, well as EPRI project RP2436.
medium voltage cables. The procedures
above should be followed while utilizing the Maintenance testing of cables typically
voltage limits as specifically listed in Table 1 includes all the cable accessories as part of
for the cable in conjunction with the voltage the test results. Consequently, any test
limits for accessories. result must be interpreted to properly
determine if there may be a problem with the
As part of an Acceptance Test, the cable or an accessory. Maintenance testing
accessory manufacturer should be of cables can be accomplished through
contacted for appropriate testing practices. multiple test techniques: AC Hi-Pot testing,
In no case should the testing of the cable Tan Delta testing, PD testing, and/or VLF
system exceed the limits of the accessories testing. Each test offers unique advantages
or the cable. as well as disadvantages.

MAINTENANCE TESTING CABLE TESTING


Maintenance testing is conducted during the The interpretation of cable testing results is
operating life of a cable system. It is the key to properly assess the
intended to detect deterioration of the characteristics of a cable!
system (in cable or accessories) so that
suitable maintenance procedures can be †
initiated. Documentation references are available upon request.

700 Industrial Drive DC Hi-Pot Testing


Lexington, South Carolina 29072 Revision 1
Phone: 1.800.845.8507 March 09,2010
Fax: 1.803.951.1142 Page 5 of 6
www.na.prysmian.com/energy
TABLE 1
DC Test Voltages

Rated Installation Maintenance


Conductor Nominal On-Reel Testing
Voltage Testing Testing
Size Insulation Maximum DC Hi-
Phase Maximum DC Hi- Maximum DC Hi-
(AWG Thickness Pot Voltage
To Pot Voltage Pot Voltage
or (mils) (kV)
Phase (kV) (kV)*
kcm)
(kV) 100% 133% 100% 133% 100% 133% 100% 133%
8 - 1000 90 115 26 34 28 36 9 11
5
1001 - 3000 140 140 26 34 28 36 9 11
6 - 1000 115 140 34 41 36 44 11 14
8
1001 - 3000 175 175 34 41 36 44 11 14
2 - 1000 175 220 53 60 56 64 18 20
15
1001 - 3000 220 220 53 60 56 64 18 20
25 1 - 3000 260 320 75 90 80 96 25 30

28 1 - 3000 280 345 79 94 84 100 26 31

35 1/0 - 3000 345 420 94 116 100 124 31 39

46 4/0 - 3000 445 580 124 161 132 172 41 54

*Note: DC Hi-Pot Testing is not recommended as a maintenance test for any solid dielectric
insulated cable, especially for Cross-Linked Polyethylene (XLPE/TRXLPE) cables and
definitely not after five years of in-service life.

700 Industrial Drive DC Hi-Pot Testing


Lexington, South Carolina 29072 Revision 1
Phone: 1.800.845.8507 March 09,2010
Fax: 1.803.951.1142 Page 6 of 6
www.na.prysmian.com/energy

You might also like