HARGA BAHAN
NO NAMA BAHAN SATUAN
Rp.
A BATU
1 Batu Kali M3 155,300.00
2 Batu Pecah 1 - 2 Cm M3 271,200.00
B PASIR
1 Pasir Pasang M3 169,100.00
2 Pasir Beton M3 182,400.00
C KAYU
1 Kayu Meranti Papan 2/25 X 4 M' M3 1,890,000.00
2 Kayu Kamper Usuk 5/7, 4/6 X 4 M' M3 3,498,000.00
3 Kayu meranti usuk M3 3,498,000.00
4 Kayu Begisting M3 1,890,000.00
5 Balok Kayu Meranti M3 4,161,000.00
6 Multiplek tebal 12 mm lbr 175,400.00
7 Dolken Kayu Gelam 8-10/400 cm btg 15,000.00
D PORTLAND CEMENT ( PC )
1 Semen 40 Kg Zak 42,500.00
2 Semen PC Kg 1,200.00
E BESI
1 Besi beton polos U24 Kg 12,930.04
2 Besi beton ulir U39 Kg 13,245.04
3 Kawat Beton Kg 17,600.00
4 Kawat Beton Berderat Kg 17,600.00
5 Besi Hollow 4 x 6 x 2 m1 17,900.00
F Air
1 Air Tanki ltr 20.00
G Cat
1 Kuas Bh 10,500.00
2 Cat Meni Besi Kg 39,200.00
3 Cat besi Kg 49,100.00
H PAKU
1 Paku biasa 2" - 5 " Kg 15,900.00
2 Paku Skrup Bh 1,000.00
J TRIPLEK
1 Playwood 9 mm Lbr 119,800.00
2 Meni Besi/Flincote Kg 39,200.00
K KUAS
1 Alang - Alang / Saput Ikat -
L ASBES + ALUMUNIUM
1 Nok Standart 40 cm 18 SWG 22 M2 88,000.00
M PIPA
1 Pipa Besi 3" (Medium) M' 63,583.33
N Seng
Seng Galvalum 7,5x3,5 cm t= 0,75 mm M' 19,600.00
Seng Plat 3"x 6" BJLS 28 M' 88,000.00
I PEK. PERSIAPAN
1 1 M' Pengukuran dan pemasangan bouwplank 4 m' 49,433.00 197,732.00
2 Pembersihan / Pembuangan 5.000 m' 21,430.00 107,150.00
Jumlah 304,882.00
Jumlah 2,667,914.23
REKAPITULASI
RENCANA ANGGARAN BIAYA
PEKERJAAN
LOKASI :
TAHUN ANGGARAN :
: 2019
JUMLAH 23,944,102.95
PPN 10 % 2,394,410.29
JUMLAH TOTAL 26,338,513.24
DIBULATKAN 26,338,000.00
TERBILANG :
Kupang
Dibuat Oleh,