Professional Documents
Culture Documents
OF BRIDGE BEAMS
April 2004
INDUSTRY STANDARD
On 18 June 2017, the Occupational Health and Safety Regulations 2017 (OHS
Regulations 2017) replaced the Occupational Health and Safety Regulations
2007 (OHS Regulations 2007), which expired on this date. This publication
has not yet been updated to reflect the changes introduced by the OHS
Regulations 2017 and should not be relied upon as a substitute for legal
advice.
Information on the key changes introduced by the OHS 2017 Regulations can
be found in the guidance titled Occupational Health and Safety Regulations
2017: Summary of changes - available at https://www.worksafe.vic.gov.au/
__data/assets/pdf_file/0011/207659/ISBN-OHS-regulations-summary-of-
changes-2017-04.pdf. However, this guidance document contains material of a
general nature only and is not to be used as a substitute for obtaining legal
advice.
CONTENTS
INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
SECTION 1 - GENERAL . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
1.1 Purpose . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
1.2 Scope . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
1.3 Exclusions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
1.4 Relationship to Australian Standards and
Bridge Design Code . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
1.5 Referenced Documents . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
1.6 Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4
1.7 Client Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
ILLUSTRATIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .65
APPENDIX C - MANUFACTURER’S
CERTIFICATE OF COMPLIANCE . . . . . . . . . . . . . . . . . . . .66
1.1 PURPOSE
This Industry Standard provides practical guidance for the design,
manufacture, transportation and erection of bridge beams (refer to
Figure 1.1) and associated precast concrete elements to ensure, so
far as practicable:
• a safe working environment for those in the industry
• the safety of the public.
1.2 SCOPE
This Industry Standard provides recommendations on the following:
• the safe design, manufacture, storage, transportation and
erection of precast concrete bridge beams and other precast
concrete elements used in bridge construction
• the safe erection of steel beams in bridge construction.
The emphasis of this Industry Standard is on the planning required
for safe methods of construction and erection of precast concrete
beams for bridges over road or rail.
The principles set out in this Industry Standard may also be applied
to other bridge construction activities not specifically addressed in
this document.
1.3 EXCLUSIONS
This Industry Standard does not cover:
• bridge beams assembled in place from individual segments
• in-situ concrete bridge beams or decks
• launched bridge beams
• the design, manufacture and transportation aspects of
steel bridge beams.
Precast and tilt-up elements not associated with bridge
construction are also excluded from the scope of this Industry
Standard. These are dealt with in the Victorian Industry Standard
for Precast and Tilt-up Concrete for Buildings.
1.6 DEFINITIONS
The definitions of terms used in this Industry Standard are given in
Appendix B.
2.1 GENERAL
A principal objective of the Victorian Occupational Health and Safety
Act 1985 (the Act) is to provide a safe working environment and
eliminate risks to the health of employees as far as practicable.
One of the employer's primary obligations under the Act is to
provide:
"such information, instruction, training and supervision to
employees as are necessary to enable the employees to perform
their work in a manner that is safe and without risks to health".
[Section 21(2)(e) of the Act]
Employers owe the same duty of care to independent contractors
and their employees working at the workplace. [Section 21(3) of the
Act]
In fulfilling this obligation, the industry should maintain a
structured system of education and training to enable both
employers and employees to:
• identify and manage risks involved in the manufacture,
transportation and erection of bridge beams
• keep abreast of the current state of knowledge within the
industry on the means of eliminating hazards and controlling
risks to health and safety.
2.3 TRAINING
Employees need to work safely. They must be trained and
instructed in safe systems of work and work practices.
Employers must ensure an appropriately experienced person
maintains a high level of supervision of employees who are not yet
deemed competent to carry out their work safely.
Training programs should address the identified occupational
health and safety needs for employees and their managers, and
should provide opportunities for individuals to have their existing
skills recognised and to develop new knowledge and skills.
Education and training programs should be structured to lead to
nationally recognised qualifications and should be delivered by a
registered training organisation. Such training should be in addition
to, and not replace:
• general construction industry occupational health and safety
induction training
• site-specific induction.
3.1.4 Pre-stressing
Pre-stressing of beams is achieved by either the pre-tensioning or
post-tensioning of tendons.
Pre-stress forces shall be specified as the jacking force before and
after all losses. The assumptions applied to calculate the jacking
values should be shown on the drawings.
Details to be nominated on the drawings should include:
• the post-tensioning sequence – i.e. the order in which tendons
are to be stressed
• whether post-tensioning tendons are single or double-end
tensioned. If double-end tensioned, whether stressing is to be
sequential or concurrent
• the de-stressing sequence, i.e. the order in which pre-
tensioned strands are to be released
• design jacking force for stressing
• allowance for losses in the jack
• allowance for pull-in at anchorage
• total elongation per tendon (measured behind the jack
before lock-off)
• tolerance assumed on elongation for the required jacking force
• for pre-tensioned concrete components, the force per strand
given as a force at the end of the pre-tensioning process, i.e.
after allowances for shortening in the bed and losses in
couplers, jacks and anchorages.
In accordance with Clause 5.16.3.5 of the AustRoads Bridge Design
Code, pre-tensioned tendons and post-tensioned tendons shall not
be stressed beyond 0.8 and 0.85 respectively of their minimum
breaking load during the stressing operations.
3.1.5 Reinforcement
Reinforcement projecting from the top of a beam should be
detailed in such a way as to provide the minimum possible tripping
risk, without compromising the structural integrity of the design,
e.g. use closed loops and not open hooks which can trap the foot.
Designers should check that every reinforcement detail actually
works in respect to cover and congestion. This is particularly
important for pre-tensioning strands, which tend to occur in a
fixed grid. Flexibility and adequate tolerances must be provided.
Prescribed bend radii of bars should be taken into account in all
applicable details by drawing accurately to scale, with real bar
thicknesses, including deformations. Three dimensional views
should be used where necessary.
3.2.2 Lifting
All components should be designed to allow for installation using
a method that is both safe, practical and in accordance with
occupational health and safety requirements. This might necessitate
consultation with all relevant parties to achieve both a safe and
efficient outcome.
Beams should be analysed by the design engineer for the
compressive forces applied by a one-crane lift. The design should
allow for an included sling angle of up to 90º. The maximum
included sling angle should be clearly stated on the drawings,
as it controls the size and capacity of the crane required and
dictates the tension in the lifting gear and lifting inserts.
If more than one lifting point (e.g. insert or loop) is required at
each end of the beam, they should be installed in pairs at right
angles to the beam centre line and at equal distance from the
centre of gravity line (refer to Figure 3.1). Due to the complexity
of the associated rigging, a combination of three lifting points at
each end should not be used.
If a beam cannot structurally withstand a one-crane lift, then this
should be clearly stated on the drawings.
Lifting inserts shall be designed to take all possible load
combinations during lifting, both in the precast yard and on the
construction site.
Although pre-stressing strands are still widely used as cast-in
lifting inserts, the AustRoads Guide to Bridge Construction Practice
discourages their use.
3.2.4 Bearings
Bearing design should take into account the beam erection phases
and the associated fixing and stability requirements. For example,
bearings should be generally placed horizontally, but if they are on a
slope, then temporary or permanent restraints should be designed
to prevent beam and/or bearing movement during construction
operations. Note: VicRoads specifies all bearings to be horizontal.
Particular attention should be paid to the bearing fixings, so that
adequate tolerances are provided for the placing of beams on the
bearings. The bearing supports should be of suitable size to allow
for ample tolerance in placing and adjusting the position of the
beams (refer to Figure 3.3). Bearing keepers should also be sized
to allow for similar tolerances.
Wherever possible, preference should be given to the use of bearings
that can be fixed to the beam prior to transport to the site.
3.2.5 Transport
Beam design should take into account the effect of load dynamics
from transportation. The geometry of the beam should be such that
it can be safely moved with readily available equipment.
A clear understanding of local road restrictions and readily
available equipment is vital. The designer and/or contractor should
establish any height, width or mass restrictions on the proposed
transport route.
Impact loads and load effects due to eccentricities applied to the
beams in transport shall be incorporated into the design.
Lateral stability during transport should be assessed, and where
necessary, temporary bracing should be provided.
Support points to be used during transport should be shown on the
design drawings, together with tolerance limits of these locations.
The tolerance limits on the locations of the beam support points
must provide adequate clearance to bearing plates.
A method for restraining beams on transport vehicles should be
incorporated into the beam design. The design of the restraints
should ensure that the beam can be rigged and that its initial
weight can be taken by the crane prior to the release of the
restraints.
The designer's approval should be obtained for the beam support
system to be used during transport.
3.3.1 General
The temporary works designs should include, but are not
limited to, the following:
• Detailed engineering designs and drawings for the temporary
support system.
Note: Off-the-shelf support systems are not generally suited
to complex support arrangements unless used as part of a
designed and documented system.
• Consideration of the stability of the temporary and permanent
structure during all stages of erection and dismantling.
• Details of methods to provide safe access to all working zones
of temporary and permanent structures.
• Fixings for temporary works cast into the beam during
manufacture.
• Methods to protect the temporary and permanent structures
against road and rail traffic impacts. Loadings for barriers should
be specified on a site-by-site basis and should be referred to the
relevant authority, such as VicRoads or VicTrack, for review.
• Consideration of the traffic management systems implemented
on the site. Temporary works designers should make
themselves aware of traffic management arrangements and
design the temporary works accordingly. For example, space
required for traffic management signs or barriers might need
to be provided within or around the temporary works.
4.1 PRE-PLANNING
Prior to manufacturing the precast elements, the parties involved in
the design, manufacture, transport and erection process should
have liaised and planned the complete construction and erection
sequences. Factors that need to be taken into account in this
process include:
• site limitations and local street access
• component size
• crane size, configuration, mobility and access
• delivery sequence
• transport requirements
• overhead obstructions, particularly tram or train wires,
overhead powerlines and construction-site overhead power
• occupancy arrangements for contractors operating on or over
roadways or railways
• underground obstructions (pits, etc.)
• timing (night or day).
4.2 DRAWINGS
The shop drawings for each precast concrete element should be
prepared and reviewed by the relevant parties prior to commencing
manufacture. This review should be in accordance with the
requirements of Section 3 - Design for Construction.
The effects of bridge cross-fall on the dimensions, grade and skew
of the individual components are important considerations for
bridge beam detailing.
To minimise multiple handling, the casting sequence, storage,
delivery sequence and erection requirements need to be considered
before commencing manufacture.
4.3 FORMWORK
Formwork must be designed and constructed in accordance with
AS 3610, Formwork for Concrete.
4.4 TOLERANCES
Unless otherwise specified, tolerances should be in accordance
with the appropriate Australian Standards.
In Victoria, the appropriate Standard for precast bridge beams is
the VicRoads Standard Specifications. For other precast concrete
elements, the appropriate Standard is AS 3610 or VicRoads
Standard Specifications.
4.6 PRE-STRESSING
Manufacturers of pre-stressed elements should be aware of the
inherent hazards and risks of the stressing operation and should
have adequate control measures in place to safeguard workers
from all such risks.
INDUSTRY STANDARD FOR THE CONSTRUCTION AND ERECTION OF BRIDGE BEAMS 25
SECTION 4 - MANUFACTURE
4.7 REINFORCEMENT
Reinforcement shall comply with the requirements of the
appropriate Australian Standards. Unless otherwise specified,
reinforcement shall be securely fixed in accordance with AS 3600,
Concrete structures, and supported in the correct position to
prevent displacement during concrete placement.
Where plastic-tipped metal bar chairs are used to support
reinforcement in external faces, care should be taken to ensure
that the plastic tips are not damaged during or after manufacture.
Note: VicRoads specifications do not permit the use of these chairs.
4.11 CURING
The strength, water tightness and durability of concrete depend
on the concrete being adequately cured.
Release agents used in the manufacture of precast concrete
elements should be checked for compatibility with the curing
compound and other applied finishes and joint sealants.
Formwork should be carefully stripped to prevent damage.
If the precast element is damaged, the proposed repair system
should be submitted to, and approved by, the design engineer
before the repair is attempted.
4.12 BEARINGS
Wherever possible, bearing plates (refer to Figure 4.1) should be
fixed to the underside of the beam before transporting to site.
An appropriate work procedure should be established that will
allow the items to be fixed to the underside of the beam in a safe
manner. This will require the beam to be supported on temporary
shoring, sufficiently clear of the ground to allow adequate access
and workspace.
Figure 4.1: Steel bearing plate fitted to the beam prior to transportation.
5.1 GENERAL
This section deals with:
• the handling and storage of precast concrete elements in the
factory or casting yard
• the storage of precast elements on the construction site.
As well as providing a safe workplace and protecting the concrete
element, the objective of a handling and storage system is to
ensure safe transfer of the element.
There is no standard method of handling and storage for precast
concrete elements. Methods will vary depending on the type and
shape of element and whether the element is in the factory or
on-site. The important criteria are:
• safety of the personnel
• protection of the concrete element.
At no time should a precast element be placed in position without
a positive restraint unless it is inherently stable. Inherently stable
elements are those elements that, due to their geometry, cannot
tip or rotate when stored and subjected to wind loads, construction
loads and impact loads generated during placement and removal
of the element and, where applicable, accidental impact from
vehicles.
5.2 HANDLING
The general requirements for rigging and lifting systems are
specified in documents referenced in Appendix A.
Prior to lifting, there should be an induction process for all
personnel involved.
Handling methods may vary, depending on the facilities available
and the types of elements being manufactured.
Pre-planning between manufacturer, principal contractor and
erector is vital, so as to minimise multiple handling.
Where elements require multiple handling for processing or finishing,
the rigging systems and lifting insert configurations should be agreed
upon by the manufacturer, principal contractor and erector, and
designed and detailed by a competent professional engineer.
The rigging system to be used and the method of handling for each
element should be shown on the drawings.
No element should be lifted without appropriate methods being
documented within the Work Method Statement, including:
• crane location for each lift
• rigging configuration
• types of lifting clutches
• fall prevention systems
• access systems.
5.4 STORAGE
The storage area should be large enough for elements to be
stored properly, with adequate room for lifting equipment and
for manoeuvring trucks and cranes.
The area should be reasonably level and hard surfaced with
adequate drainage to ensure that a safe workplace can be
maintained.
Elements should not be stored directly on the ground. Generally,
two discrete support points should be provided unless specifically
noted otherwise by the project design engineer.
It is recommended that geotechnical advice be obtained to assess
the ground conditions and advise on the suitability of the bearing
capacity of the foundation material.
Where elements are stacked on top of each other, the following
should apply:
• Support points should be directly above each other unless
specifically documented otherwise.
6.1 GENERAL
To prevent accidents and injuries, loads on vehicles should be
adequately restrained. It is the responsibility of the transporter to
ensure that the vehicle used is suitable to transport the elements
and that they are properly secured.
The transporter is responsible for obtaining the necessary permits
for all over-dimensional loads. Drivers must be able to produce the
permits upon request.
6.6 DELIVERY
Delivery of the precast elements onto the site requires co-operation
between the principal contractor, the transporter and the erector.
The principal contractor should provide a recognised traffic control
management plan that includes, where necessary, traffic
controllers (flagmen), barricades and road closure permits to allow
unimpeded access to the site.
The manufacturer should ensure that the transporter has detailed
instruction on how to enter the site.
The transporter should inspect the site prior to entry to verify that
there are no dangers such as backfilled excavations or overhead
services.
The area to receive the delivery vehicle should be firm and level,
and preferably proof checked for load capacity.
Where elements are delivered for direct placement on the
structure, the transporter should position the vehicle as directed by
the erector and should stabilise the vehicle prior to releasing the
element restraints. Where necessary, semi-trailers should be
stabilised by lowering their support legs onto a firm base.
The transporter should be aware of the beam orientation and know
which elements are to be unloaded first.
If the unloading sequence can lead to instability of loads:
• elements should be individually restrained and the loading
configuration checked to ensure that removing individual
elements does not result in instability of the load or the vehicle
• restraints should not be removed until the crane takes the
initial weight of the element.
Under no circumstances should a vehicle be moved without the
load being secured in the appropriate manner.
The transporter is responsible for ensuring that the load is secured
in the appropriate manner at all times, even during the unloading
operation.
7.1 GENERAL
Thorough pre-planning is vital to the safe erection of bridge
structures. All personnel should be aware that erection of any
element is hazardous and that the purpose of the pre-planning
process is to identify hazards and to eliminate or adequately control
any risk in the erection process.
Figure 7.1: Example of a fall prevention system (guardrail fixed to the beam prior to erection).
In some cases, dual crane lifts might not be practical due to:
• site limitations (crane positions)
• erecting elements over water or obstructions
• transporting elements to required lifting positions.
When a single crane is used for the erection of elements, an
auxiliary crane might be required to assist in the safe handling of
heavy rigging gear. Equalising triangles, compensating plates and
different lengths of rigging gear might also be required.
Taglines fixed at each end of the element should be used to control
its movement. In these cases, tagline movement should be
monitored to avoid snagging on obstructions.
Elements should not be erected in windy conditions. The JSA
should identify whether the element can be safely controlled by
taglines. Large elements can generate high loads on taglines and
this should not be underestimated.
Crane operation is permissible only up to the wind speed stated in
the operator’s manual (corresponding to the boom length being
used). The surface area and configuration of the element and
rigging should be taken into account in calculating the effects of
wind.
The erector should, prior to commencing operations, contact the
local meteorological office for information on the expected wind
speeds. If unacceptable wind speeds are expected during the time
of the proposed lift, the element should not be lifted.
Track-mounted (crawler) cranes might be required to ‘walk’
elements into position. This is permitted only if:
• the crane is designed for this application and has a rated
capacity chart to ‘walk’ with suspended loads
• the ground support is suitable for the crane's track loadings.
(Bog-mats might be required to achieve adequate ground
support.)
• a geotechnical engineer or other professional engineer has
checked and provided written verification of ground support
conditions.
In the event that the crane does contact live powerlines, the crane
operator should:
• remain inside the cabin
• warn all other personnel to keep away from the crane and not
to touch any part of the crane, rope or load
• try, unaided, and without anyone approaching the machine, to
move the crane until clear of the powerline
• if the machine cannot be moved away, remain inside the cabin,
notify the electricity distribution authority at once, take no
Figure 7.4: Access platform, fixed to the abutment, provides fall protection during the placement of beams.
7.9 RIGGING
Setting up a rigging system requires careful and thorough pre-
planning. The lifting configuration should be documented and should
not be altered without the approval of the erection design engineer.
The method of connecting the rigging system to the element should
be agreed to by the manufacturer, contractor and the erector.
The rigging system should distribute equal loads to all lifting points
unless specifically designated otherwise in the shop drawings. To
ensure equal distribution of loads when lifting precast elements
with multi-legged slings, consideration should be given to the
provision of load equalising gear as a part of the rigging system.
Figure 7.5: Beam being placed onto the pier-falsework and abutment.
Falsework should:
• be erected in accordance with the specification and design
drawings. It should be independently proof-checked prior to
beam erection (refer Section 3.3 for details)
• have an allowance for uneven loading during beam erection
and for incidental loadings, such as vibrations from passing
vehicles, trains or other heavy equipment
• be regularly inspected for its ongoing structural adequacy.
The principal contractor must ensure that no section of falsework
is removed without written instructions from the erection design
engineer.
Where beams are post-tensioned after erection, the stressing
process will change the shape of the element, thereby reducing
the load on some props and increasing the load on others. This
particularly applies where the stressing induces a camber into the
beam, which can lift the beam off props at mid-span, transferring
the entire load to the props at the ends. Similar effects might occur
due to a temperature gradient over the depth of the beam.
Propping systems should allow for possible changes to the
distribution of loads during the construction process. Props should
be of certified capacity and correctly specified for the purpose
intended.
7.14 MODIFICATIONS
Modifications to elements should be carried out only with the
approval of the design engineer, and following certification by the
proof engineer. Any such modifications should be recorded, and
drawings should be revised and re-issued.
REFERENCED DOCUMENTS
Victorian Health & Safety Legislation:
• Occupational Health and Safety Act 1985
• OHS (Certification of Plant Users and Operators) Regulations 1994
• OHS (Plant) Regulations 1995
• OHS (Incident Notification) Regulations 1997
• OHS (Manual Handling) Regulations 1999
WorkSafe Codes of Practice:
• Code of Practice for Building and Construction Workplaces
• Code of Practice for First Aid in the Workplace
• Code of Practice for Plant
• Code of Practice for Manual Handling
Other WorkSafe Publications:
• A Guide to Rigging
• Industry Standard for Precast and Tilt-up Concrete for Buildings
• Incident Notification – At a Glance
• Provision of Amenities on Mobile and Short Term Civil Construction Sites (Guidance Note)
Australian Standards:
• AS 1742.3, Manual of uniform traffic control devices, Part 3: Traffic control devices for works on roads
• AS 1418.1, Cranes, hoists and winches, Part 1: General requirements
• AS/NZS 1891.4, Industrial fall arrest systems and devices, Part 4: Selection, use and maintenance
• AS 2550, Cranes - Safe use
Part 1: General requirements
Part 5: Mobile and vehicle loading cranes
Part 7: Builders hoists
Part 10: Elevating work platforms
• AS 3600, Concrete structures
• AS 3610, Formwork for concrete
• AS 3850, Tilt-up concrete construction
• HB 77 Australian Bridge Design Code (set)
• HB 81 Parts 1 to 9 Field Guide for Traffic Control at Works on Roads
AustRoads Publications:
• Bridge Design Code (complete set)
• Guide to Bridge Construction Practice
Office of the Chief Electrical Inspector Publications:
• Rules for Operating Near Powerlines for Cranes, Concrete Placing Booms and Excavating Equipment
• Rules for Operating Elevating Work Platforms Near Overhead Powerlines
• Rules for Erecting Scaffolding Near Overhead Powerlines
VicRoads Publications:
• Standard Specification
• A Guide to Restraining Concrete Panels
• Worksite Traffic Management Code of Practice
• Bridge Technical Notes
Department of Transport, Federal Office of Road Safety:
• Load Restraint Guide
National Precast Concrete Association Australia and Concrete Institute of Australia:
•Precast Concrete Handbook
American Precast and Prestressed Concrete Institute:
• PCI Design Handbook
DEFINITIONS
General Definition:
Contractor The company or person responsible for the construction of all or part of the project.
The contractor will usually be responsible to the principal contractor.
Client The owner of the project or the Government body, company or person responsible for
developing the project.
Design Engineer The engineer responsible for the engineering design of the project. The design
engineer should be a person qualified for membership of the Institution of Engineers
Australia, who is competent to practise in the structural engineering field.
The design engineer will usually be responsible to the client.
Designer The engineer responsible for the design of the section of the works in question.
Erector The company or person responsible for erecting the precast elements. The erector
might be responsible either to the principal contractor, contractor or manufacturer.
The erection design engineer should be a person qualified for membership of the
Institution of Engineers Australia, who is competent to practise in the structural
engineering field.
The erection design engineer will usually be responsible to the principal contractor,
contractor or the manufacturer. The erection design engineer might also be the
design engineer.
Manufacturer The company or person responsible for manufacturing the precast concrete
elements. The manufacturer will usually be sub-contracting to (and be responsible
to) the principal contractor or contractor.
Principal Contractor The company or person in charge of, and responsible for, the construction of the
complete project and who has control of the construction site. The principal
contractor will be responsible to the client, but might also be the client.
Proof Engineer The engineer responsible for checking and certification of the design and
documentation produced by the design engineer and/or the erection design engineer.
The proof engineer should be a person qualified for membership of the Institution of
Engineers Australia, who is competent to practise in the structural engineering field.
The proof engineer will usually be responsible to the client, principal contractor
or contractor.
The proof engineer must be independent from the designer whose work is being
proof-checked.
Shop Detailer The person responsible for preparing the shop drawings of the elements. The shop
detailer might also be the manufacturer (or a company or person) responsible to
the manufacturer.
Transporter The company or person responsible for transportation of the element. The
transporter might also be the manufacturer (or a company or person) responsible
either to the principal contractor, contractor, manufacturer or erector.
Window (as in The timeframe in which construction activity can occur on or over
‘construction roadways or railways.
activity window’)
Technical Definitions:
Bracing Insert A component or system cast into, or fixed to, the element or into an element
supporting member, for later attachment of a temporary brace.
Connections A method by which one or more elements are joined together. (The purpose of
connections is to transfer load and/or provide stability.)
Design Drawings Drawings prepared by the design engineer showing the overall project and
(Working/Constr- assembled elements and details that reflect the design requirements. They form
uction Drawings) the basis for preparation of the shop drawings.
Design Factor The number by which the failure load is divided to give the working load limit.
This was previously known as the safety factor.
Erection Platform The base on which the crane is supported during erection of the elements.
Fixing Insert A component or system cast into, or fixed to, the element and used to tie the element
into the structure, or support other structural members.
Fixings The hardware component of connections. Fixings provide for load transfer between
the members being connected.
Joint The gap between adjoining elements or between an element and some other portion
of the structure. Joints might be horizontal, vertical or inclined.
Levelling Shim(s) A single or series of thin strips of appropriate material used under elements to
support the element in its correct position until the final connection is made.
Lifting Beam A device within the rigging system that spreads the load evenly for a given lift.
(Also known as
a spreader beam.)
Lifting Clutch A quick-release device used to connect the crane rigging to the lifting insert.
Lifting Insert A component or system cast into, or fixed to, the element for lifting the element
during erection.
Precast Concrete A concrete element manufactured under controlled conditions in a factory or casting
Element yard and subsequently transported and erected on a construction site. The casting
yard might or might not be on-site.
Props Temporary elements supporting loads, which produce compression forces. Both
ends of the prop are fitted with rigid foot plates that provide support between two
parallel surfaces.
Rated Capacity The maximum gross load that may be applied to the crane or hoist of the lifting
attachment while in a particular working configuration and under a particular
condition of use.
Reinforcement:
Structural Reinforcement, including reinforcing steel and pre-stressing tendons provided for
Reinforcement crack control or to resist forces caused by applied loads and thermal/shrinkage
movements.
Component Reinforcement placed in conjunction with lifting, bracing and fixing inserts so that
Reinforcement they can attain their design capacities. Note: Component reinforcement is normally
specified by the insert supplier and might not always be shown on the shop drawings.
Rigging System A mechanism that might include a series of slings, pulleys, lifting or spreader
beams (or other mechanical devices) to connect the crane to the element
being lifted.
Re-usable The lifting device which is directly connected to the lifting insert, e.g. lifting clutch,
Lifting Equipment bolt-on bracket.
Shop Drawing Detailed drawing of an element used in the manufacturing process. Note: The
preparation of separate shop drawings might not be required where all necessary
details are included on design drawings.
Tag Line (Tail Rope) A rope attached to the element being erected to help control the element
during placement.
ILLUSTRATIONS
Figure 1.1: Bridge constructed from precast concrete beams. 3
Figure 3.1: Rigging system attached to a pair of lifting inserts. 17
Figure 3.2: Non-proprietary lifting attachment. 18
Figure 3.3: Elastomeric bearing pad placed on adequately sized pedestal. 19
Figure 4.1: Steel bearing plate fitted to the beam prior to transportation. 29
Figure 6.1: Typical beam secured on truck for transportation. 39
Figure 7.1: Example of a fall prevention system (guardrail fixed to the beam prior to erection). 44
Figure 7.2: Dual crane lift. 46
Figure 7.3: Clearance of cranes from overhead powerlines. 49
Figure 7.4: Access platform, fixed to the abutment, provides fall protection during the
placement of beams. 53
Figure 7.5: Beam being placed onto the pier-falsework and abutment. 57
Figure 7.6: Falsework supported directly on pier concrete footing. 59
QA SIGN-OFF
This is to certify that the above precast concrete beam has been
manufactured in accordance with the approved design drawings
and/or client approved variations.
Name:
Signature:
Position:
Date:
WEBSITE
www.worksafe.vic.gov.au/construction
EMAIL
info@ workcover.vic.gov.au
VICTORIAN WORKCOVER ADVISORY SERVICE
24th Floor
222 Exhibition Street
Melbourne Victoria 3000
Phone. . . . . . . . . . . . . . . . . . . . 9641 1444
Fax . . . . . . . . . . . . . . . . . . . . . . 9641 1353
Toll-free . . . . . . . . . . . . . . . 1800 136 089
VWA155/01/04.04