3 Design Methodology for Structural Trade-off


4.3.1 Design Process for Gravity Wall

INPUT PARAMETERS
VERIFICATION OF COMPLETE
NEEDED FOR ANALYSIS
WALL BY CHECKING SLIP
(GEOMETRY, SOIL, TERRAIN,
AND OVERTURNING
WATER, SURCHARGE, AND
STABILITY
STAGE SETTINGS)

ANALYSIS OF SLOPE CHECK BEARING CAPACITY


STABILITY USING BISHOP
FOR THE CROSS-SECTION
METHOD

4.3.2 Design Process for Cantilev

INPUT PARAMETERS NEEDED


FOR ANALYSIS (GEOMETRY, VERIFICATION OF COMPLETE
SOIL, TERRAIN, WATER, WALL BY CHECKING SLIP AND
SURCHARGE, AND STAGE OVERTURNING STABILITY
SETTINGS)

CHECK THE WALL STEM OF


ANALYSIS OF SLOPE FRONT REINFORCEMENT (Vu
STABILITY USING BISHOP and Mu), BACK
METHOD REINFORCEMENT, AND WALL
JUMP CHECK
4.3.3 Sheet pile

INPUT PARAMETERS NEEDED


DIMENSIONING: CHECK THE
FOR ANALYSIS (GEOMETRY,
SATISFACTORY OF BENDING
SOIL, TERRAIN, WATER,
& COMPRESSION AND SHEAR
SURCHARGE, AND STAGE
STRESS
SETTINGS)

STABILITY: ENTER THE


ANALYSIS OF SLOPE
DIMENSION OF DEPTH
STABILITY USING BISHOP
METHOD GREATER THAN THE GIVEN
MINIMUM VALUE
• Stability: enter the dimension of depth greater than the given minumum value.
STABILITY: ENTER THE DIMENSION OF DEPTH GREATER THAN THE GIVEN MINIMUM VALUE