Professional Documents
Culture Documents
Commissioning Manual
Distribution Transformers - Three-phase Oil Filled
1LPL000006A2110 – rev. 1 2/7
Table of contents
1 Commissioning and start-up ...................................................................................... 3
1.1 Transformer survey ............................................................................................... 3
1.2 Positioning the transformer for normal operation .................................................. 3
1.3 Connecting the transformer and preparing for start-up ......................................... 3
1.3.1 Measurement of the insulation level.............................................................. 4
1.3.2 Measurement of voltage ratio and phase displacement ............................... 5
1.3.3 Measurement of winding resistance.............................................................. 6
1.4 Transformer start-up.............................................................................................. 7
1LPL000006A2110 – rev. 1 3/7
• Check level of transformer oil; if required, add oil through filling orifice on the
cover or conservator. Note! Added oil must be of the same type as oil already in
the transformer.
Normal oil level indication in a Normal oil level indication in a free breathing
hermetically sealed transformer (conservator type) transformer
• In the event of small leakages (so called oil bleeding), eliminate them by
tightening appropriate screws and bolts
• Take measurement of insulation level. Measured values must not be lower than
80% of those given in the transformer’s test report.
• Check transformer ratio in all tap changer positions. In order to do that, apply
voltage 3x380V on LV side and take a series of measurements on HV side for
different tap changer positions
• Put tap changer dial in the position required for normal transformer operation
• Prior to installation of thermometer fill its pocket on the cover with transformer oil
• Inspect the whole transformer to double check for any errors in the connections
or faulty equipment
• measure transformer’s insulation level with all but star-point cables connected
• verify the choice of all protection devices as well as the validity of all connections
Measured values are reference values for comparison with later measurement in the
field. No limitations for the values are given.
1LPL000006A2110 – rev. 1 5/7
These measurements are made to verify the voltage ratio of the windings, their
interconnections and phase displacement, i. e. vector group. For purposes of
measurement, the transformer is exited by a low voltage (some tens of volts) and using a
null method, comparison is made with an accurate, adjustable voltage ratio standard.
The observed rations are accepted if they are within the tolerances of the relevant
standard.
All standards, which are adjusted to IEC, permit a tolerance of 1/200 of the ordered ratio
on the principal tapping and a percentage of deviation, which equals 1/10 of the
measured impedance.
An important error source during the resistance measurements is the induced voltage
due to the large inductance of the transformer windings. This induced voltage may be
created by the connection transient or by an unstable power source. The setting time of
the switching transient may be several minutes.
If a temperature rise test is carried out, the measurements of winding resistance are
repeated rapidly after the heat run test, in order to determine the temperature of the
windings.
1.4 Transformer start-up
Before energising the transformer, verify the following:
• Apply rated voltage to the transformer HV terminals and leave the unit in an idle
state (no-load) for 60 minutes. Only then transformer may be loaded up to
maximum value stated on the rating plate.
Document Title
Commissioning Manual
Document No. Date & Rev. Ind. No. of Pages Page
1LPL000006A2110 1 7 7