You are on page 1of 90

SURVEI HARGA BAHAN BANGUNAN

( Tidak termasuk Perhitungan PPn dan Overhead )

SURVEI BULAN : JANUARI 2018


SUMBER DATA : TOKO BANGUNAN
DAERAH : KOTA SURAKARTA
PERIODE : BULAN MEI - AGUSTUS 2018

NO JENIS BAHAN SAT

1 2 3
A. B A H A N DASAR
1 BATU KALI Bulat m3
Belah m3
2 KERIKIL Sirtu m3
Pecah Mesin 0,5/1 m3
1/2 m3
2/3 m3
3/5 m3
5/7 m3
Split 2/3 pecah tangan m3
3 BATU BATA Bata merah bh
bata ringan 10 x 20 x 60 cm bh
4 PASIR Urug m3
Pasang m3
Beton m3
5 TANAH Padas m3
Liat/Urug m3
6 KAPUR Pasang zak
7 SEMEN
PC @ 50 kg Zak
PC @ 40 kg Zak
Semen Putih zak
Semen Warna kg
PC abu-abu ready mix kg
Mortar GE 280 kg

B. B A H A N BESI
1 BESI BETON (Panjang 12 meter)
Krakatau Steel Besi beton Ø 6 mm btg
Besi beton Ø 8 mm btg
Besi beton Ø 10 mm btg
Besi beton Ø 12 mm btg
Besi beton Ø 16 mm btg
Besi beton Ø 19 mm btg
Besi beton Ø 22 mm btg
Besi beton Ø 25 mm btg
Besi beton Ø 29 mm btg
Besi beton Ø 32 mm btg
Besi beton polos/ulir kg
Besi beton polos/ulir + pengerjaan kg
2 BESI SIKU 20 x 20 x 2 mm panjang 6 m' btg
30 x 30 x 3 mm panjang 6 m' btg
40 x 40 x 4 mm panjang 6 m' btg
50 x 50 x 5 mm panjang 6 m' btg
60 x 60 x 6 mm panjang 6 m' btg
70 x 70 x 6 mm panjang 6 m' btg
3 BESI PROFIL
31 Desember 1899 Kanal UNP - 10 cm - panjang 6 m' btg
Kanal UNP - 12 cm - panjang 6 m' btg
01 Januari 1900 Kanal IWF - 15 cm btg
Kanal IWF - 20 cm btg

02 Januari 1900 CNP 100 x 50 x 20 tebal 2,3 mm btg


CNP 100 x 50 x 20 tebal 3,2 mm btg
CNP 125 x 50 x 20 tebal 2,3 mm btg
CNP 125 x 50 x 20 tebal 3,2 mm btg
CNP 150 x 50 x 20 tebal 2,3 mm btg
CNP 150 x 50 x 20 tebal 3,2 mm btg
CNP 200 x 75 x 20 tebal 2,3 mm btg
CNP 200 x 75 x 20 tebal 3,2 mm btg

03 Januari 1900 H. BEAM


150 X 150 X 6,5 X 10 X 12 btg
04 Januari 1900 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg
175 X 90 X 5 X 8 X 12 btg
200 X 100 X 5,5 X 9 X 12 btg
250 X 125 X 6 X 9 X 12 btg
300 X 150 X 6,5 X 9 X 12 btg
350 X 175 X 7 X 11 X 12 btg
400 X 200 X 8 X 13 X 12 btg
500 X 200 X 10 X 16 X 12 btg
600 X 200 X 11 X 17 X 12 btg

Besi Profil UNP, IWF, CNP, H Beam dan Wide Flange Beam kg
Besi Profil + pengerjaan kg

4 BESI PLAT 3 ' X 6 ' tebal 0,6 mm lbr


4 ' X 6 ' tebal 0,8 mm lbr
Besi stall bus (40 x 20 x 2) mm m'
Besi stall bus (40 x 40 x 2) mm m'
5 JARING - JARING BAJA
Kawat Kasa kg
Di las/Wiremash kg
6 KAWAT - Ikat beton/bendrat kg
- Harmonika 12 X 45 mm m2
- Harmonika 12 X 24 mm m2
- Harmonika 14 X 30 mm m2
- Harmonika 14 X 35 mm m2
- Saringan pasir m2
- Kawat loket m2
- Kawat duri rol
- Kawat bronjong kg
7 FLOORDEC lebar 5,0 - 6,0 lbr
lebar 3,0 - 4,5 lbr

8 HOLLOW
2/4 tebal 0,25 mm panjang 6 m' btg
2/4 tebal 0,30 mm panjang 6 m' btg
2/4 tebal 0,35 mm panjang 6 m' btg
2/4 tebal 0,50 mm panjang 6 m' btg
4/4 tebal 0,25 mm panjang 4 m' btg
4/4 tebal 0,30 mm panjang 4 m' btg
4/4 tebal 0,35 mm panjang 4 m' btg
4/4 tebal 0,50 mm panjang 4 m' btg
9 CANOPY TANPA ATAP/GENTING
Minimalis dari Besi m2
Stainless Steel m2
Galvallum m2
10 PAGAR
Pagar Minimalis dari Besi m2
Balkon / Railing Balkon m2
Harga Pintu Pagar m2
Harga Pintu Pagar Tempa m2
Teralis Jendela Minimalis m2
Teralis Jendela Tempa m2
Railing Tangga m2
Tangga Putar dari Besi unit
Pintu Besi m2

C. B A H A N KAYU
II. BAHAN KAYU
1 JATI Papan m3
Balok/ pesagen m3
2 KAMPER Papan m3
Balok/ pesagen m3
3 KRUING Papan m3
Balok/ pesagen m3
4 MERANTI Papan m3
Balok/ pesagen m3
5 LANAN Papan m3
Balok/ pesagen m3
6 BENGKIRAI Papan m3
Balok/ pesagen m3
7 KAYU PUTIH Papan 2/20 x 200 cm lbr
Usuk 4/6 x 300 cm bh
Usuk 5/7 x 300 cm bh
8 SENGON m3
9 GLUGU/KELAPA m3
10 DOLKEN
Sedang dia 8 - 10 x 400 cm bt
Kecil dia 6 - 7 x 400 cm bt
Besar dia 10 - 12 x 400 cm bt
Kayu cetakan m3
Kayu bakar m3
Bambu Ori panjang 4.00 bt
Kayu cetakan Kayu Kalimantan m3
Kayu cetakan Kayu putih m3
minyak begesting ltr
6 LEM KAYU kg
- Plat baja penahan traves / Plat simpul bh
- Plat strip Vertikal type 1 bh
- Plat strip segitiga lima type 2 bh
KACA
1 POLOS 2 mm m2
3 mm m2
5 mm m2
8 mm m2
10 mm m2
2 ES KABUR 2 mm m2
3 mm m2
5 mm m2
3 RAY BAND 3 mm m2
5 mm m2
8 mm m2
10 mm m2
Dark Blue 5 mm m2
4 KACA CLEAR TEMPERED
5 mm m2
6 mm m2
8 mm m2
10 mm m2
Kaca Cermin m2

5 GLASS BLOCK Bromo bh


6 Kaca khusus tebal 3 mm Kaca Patry m2
Kaca Inlay m2
Kaca Grafir m2
Kaca Film Sandblasting 3 mm m2
Kaca Film Sandblasting 5 mm m2

E. B A H A N PIPA
VI. B A H A N PIPA
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS AW btg
Pipa PVC DN 25 ( ¾" ) AW JIS AW btg
Pipa PVC DN 32 ( 1" ) AW JIS AW btg
Pipa PVC DN 40 ( 11/4" ) AW btg
Pipa PVC DN 40 ( 1½" ) AW btg
Pipa PVC DN 63 ( 2" ) AW btg
2
Pipa PVC DN 40 ( 1 ⅟4" ) D btg
Pipa PVC DN 40 ( 1½" ) D btg
Pipa PVC DN 63 ( 2" ) D btg
Pipa PVC DN 90 ( 21/2" ) D btg
Pipa PVC DN 90 ( 3" ) D btg
Pipa PVC DN 110 ( 4" ) D btg
Pipa PVC DN 160 ( 5" ) D btg
Pipa PVC DN 160 ( 6" ) D btg
Pipa PVC DN 200 ( 8" ) D btg
Pipa PVC DN 250 ( 10" ) D btg
Pipa PVC DN 315 ( 12" ) D btg

3 Pipa Medium Gip Medium Galvanis - SII


Pipa Medium B Galvanis DN ½" btg
Pipa Medium B Galvanis DN 25 ( ¾" ) btg
Pipa Medium B Galvanis DN 32 ( 1" ) btg
Pipa Medium B Galvanis DN 32 ( 1,25" ) btg
Pipa Medium B Galvanis DN 50 ( 1½" ) btg
Pipa Medium B Galvanis DN 63 ( 2" ) btg
Pipa Medium B Galvanis DN 2½" btg
Pipa Medium B Galvanis DN 90 ( 3" ) btg
Pipa Medium B Galvanis DN 110 ( 4" ) btg
Pipa Medium B Galvanis DN 160 ( 6" ) btg
Pipa Medium B Galvanis DN 200 ( 8" ) btg
Pipa Medium B Galvanis DN 250 ( 10") btg
Lem Pipa wavin 60 gr btl
400 gr btl
4 PIPA STAINLESS
pipa stainless stell ø 2" m'
pipa stainless stell ø 3/4" m'
5 ACESORIS PIPA
Kran ½"" stainless steel bh
Kran 3/4" stainless steel bh
Kran 1" stainless steel bh
Kran bebek ½" stainless steel bh
Stop Kran Kuningan onda ½" bh
Stop Kran Kuningan onda ¾" bh
Stop Kran Kuningan onda 1" bh
Knie PVC 1/2" bh
Knie PVC 3/4" bh
Knie PVC 1" bh
Knie PVC 1/2" sudut 90 ° bh
Knie PVC 3/4" sudut 90 ° bh
Knie PVC 1" sudut 90 ° bh
Knie PVC 3" sudut 90 ° bh
Knie PVC 4" sudut 90 ° bh
Tee (PVC) ¾ " bh
Tee (PVC) 1" bh
Tee (PVC) 3" bh
Tee (PVC) 4 " bh

F. B A H A N PENUTUP ATAP
I. B A H A N PENUTUP ATAP
1 SIRAP (100 lbr) pak
2 GENTENG BETON
Genteng Beton tanpa warna (standar) bh
Genteng Beton Warna Special bh
Genteng Beton Warna Khusus bh
Kerpus Beton tanpa Warna bh
Kerpus Beton Warna Special bh
Kerpus Beton Warna Khusus bh
3 GENTENG KERAMIK
- Natural 32cmx31cm m2
- Mahagony 32cmx31cm m2
- Standar 35cmx22cm m2
- Special 35cmx22cm m2
- Premium 35cmx22cm m2
- Knoc Natural 35cmx22cm kpng
Genteng Keramik Glassur sekwalitas KIA bh
Bubungan Genteng Keramik Glassur sekwalitas KIA bh
Nok 3 Arah setara KIA bh
Nok Ujung Jurai KIA bh
4 GENTENG TANAH LIAT bh
Genteng Sokka Kebumen Plentong bulat bh
Plentong papak bh
Mageze bh
Kodok bh
Morando Natural bh
Morando Glasir bh
Krepus Papak bh
Krepus Lancip bh
Vlaam Godean bh
Cat genteng kg
5 GENTENG KACA
Vlaam tebal 2 mm bh
Vlaam tebal 3 mm bh
Kodok tebal 2 mm bh
Kodok tebal 3 mm bh
6 GENTENG METAL
Galvalum 1219 mm x 1000 mm x 0.5 mm lbr
Galvalum 1219 mm x 2438 mm x 0.5 mm lbr
Uk. 80 x 77 cm lbr
Acesories genteng metal
7 ZINCALLUM atap lbr
Bubungan lbr

8 GENTENG MULTIROOF
- Genteng 2 x 5 Multiroof lbr
- Nok Model U Multiroof bh
- Nok Model C Multiroof bh
- Nok Samping Multiroof bh
- Wall Flashing Multiroof bh
- Tutup Nok Multiroof bh
- atap galvallum m2
9 SURYA ROOF
- Genteng 1 x 4 Suryacolor stone lbr
- Nok Model U Suryacolor bh
- Nok Model C Suryacolor bh
- Nok Samping Suryacolor bh
- Wall Flashing Suryacolor lbr
- Wall Flashing Suryacolor lbr
10 ASBES GELOMBANG BESAR
Djabes 6 1/2
. 150 cm X 105 cm X 5 mm lbr
. 180 cm X 105 cm X 5 mm lbr
. 210 cm X 105 cm X 5 mm lbr
. 240 cm X 105 cm X 6 mm lbr
. 270 cm X 105 cm X 6 mm lbr
. 300 cm X 105 cm X 6 mm lbr
Nok Asbes lbr
Nusa 6
. 250 cm X 50 cm X 5 mm lbr
. 300 cm X 80 cm X 5 mm lbr
. 250 cm X 100 cm X 5 mm lbr
. 300 cm X 100 cm X 5 mm lbr
11 ASBES GELOMBANG KECIL
Djabes 14
. 1500 mm X 800 mm X 3,5 mm lbr
. 1800 mm X 800 mm X 3,5 mm lbr
. 2100 mm X 800 mm X 3,5 mm lbr
. 2400 mm X 800 mm X 3,5 mm lbr
. 3000 mm X 800 mm X 3,5 mm lbr

. 1500 mm X 1020 mm X 4,0 mm lbr


. 1800 mm X 1020 mm X 4,0 mm lbr
. 2100 mm X 1020 mm X 4,0 mm lbr
. 2400 mm X 1020 mm X 4,0 mm lbr
. 2700 mm X 1020 mm X 4,0 mm lbr
. 3000 mm X 1020 mm X 4,0 mm lbr

12 ASBES PLAT . 3000 mm X 800 mm X 3,5 mm


Jabes Plat
. 100cm X 100 cm X 3 mm lbr
. 40 cm X 200 cm X 3 mm lbr
. 50 cm X 200 cm X 3 mm lbr
. 60 cm X 200 cm X 3 mm lbr
Jabes nok
. Kerpus Genteng bh
. Stel Besar bh
. Alumunium Foil lbr
Nokstel gelombang harflex
. Stel Besar bh
. Patent Besar bh
. Plat besar bh
13 FIBRE GLASS (JABES)
Flat sheet (rata) m'
Gelombang m'
kotak m'
14 POLYCARBONATE CLEAR (TWINILITE)
tebal 4,5 mm 2,1 m x 11,8 m lbr
tebal 5 mm 2,1 m x 11,8 m lbr
tebal 6 mm 2,1 m x 11,8 m lbr
tebal 10 mm 2,1 m x 11,8 m lbr
15 SENG PLAT
BJLS 0,18 m2
BJLS 0,20 m2
BJLS 0,28 m2
BJLS 0,30 m2
16 SENG GELOMBANG
180 x 80 x 0,2 mm lbr
210 x 80 x 0,2 mm lbr
240 x 80 x 0,2 mm lbr
300 x 80 x 0,2 mm lbr
180 x 80 x 0,3 mm lbr
210 x 80 x 0,3 mm lbr
240 x 80 x 0,3 mm lbr
300 x 80 x 0,3 mm lbr
17 ONDULINE
Atap Onduline 2000 mm x 950 mm x 3 mm lbr
Nok 1000 mm x 500 mm x 3 mm lbr
Paku onduline panjang 65 mm bh
18 RANGKA ATAP BAJA RINGAN
Star/CFS/Tidar Roof Profil C bentang ≤ 8 m' tebal 0.75 mm m2
Star/CFS/Tidar Roof Profil C bentang ≤ 8 m' tebal 1.00 mm m2
Star/CFS/Tidar Roof Profil C bentang > 8 m' m2
Galva bentang ≤ 8 m' m2
bentang > 8 m' m2
Canopy baja ringan m2
19 AKSESORIS
~ Lisplang GRC Urat kayu lbr
~ Nok samping polos lbr
~Nok samping pasir m'
~Talang Air tepi Zincalume m'
~Allumunium Foil Super woven Single m2
~Allumunium Foil Super woven Double m2
~Floordeck 1 m x 4 m m2
G. B A H A N PENUTUP LANTAI
1 KERAMIK LANTAI
KIA, Mulia, Ikad , diamond 20 X 20 cm m2
30 X 30 cm m2
40 x 40 m2
Platinum 30 x 60 m2
58 x 58 m2
60 x 60 m2
m2
2 TEGEL PLINT
PC warna 10 X 20 cm bh
Teraso 10 X 30 cm bh
3 POLIS UBIN Lantai/ badan m'
Plint m'
Trap m'
4 PASANG ALDAS DECORATIVE STONE m2
5 UBIN GRANITO
standar Granito Salsa Uk. 40 cm x 40 cm m2
standar Granito Salsa Uk. 30 cm x 60 cm m2
premium Granito Salsa Uk. 60 cm x 60 cm m2
premium Granito Salsa Uk. 80 cm x 80 cm m2
6 KERAMIK DINDING
Roman putih m2
Roman motif m2
Mulia/Ikad warna muda m2
Mulia/ikad warna tua m2

7 Keramik list 10 X 20 cm biji


10 X 40 cm biji
10 x 60 cm biji
Batu tempel Motif Serit m2
Batu tempel banjar m2
Coating Natural Batu alam kg
Lantai Keramik Steep/stair nosing
6 cm x 30 cm pcs
10 cm x 30 cm pcs
warna 10 cm x 30 cm pcs
ukuran 30 cm x 60 cm pcs
Mozaik m2
Panel Plafond UPVC m2
8 KARPET Classic Bali m2
lbr 4 m Nobel Long Life m2
Classic Hercules m2

H. B A H A N PENUTUP LANGIT-LANGIT

1 AKUSTIK-uk : 30 X 30 cm tebal 9 mm lbr


30 X 60 cm tebal 9 mm lbr
40 X 40 cm tebal 9 mm lbr
60 X 120 tebal 9 mm lbr
Harga terpasang 60 X 60 tebal 9 mm dg holow 20/40 m2
60 X 120 tebal 9 mm dg holow 20/40 m2
List Kayu Profil btg
2 SOFT BOARD-uk: 4'X 8' lbr
Gypsum tebal 9 mm lbr
3 HARD BOARD-uk: 4'X 8' lbr
4 Eternit Standar SNI tebal 3,5 mm lbr
(Langit-langit Asbes) tebal 4 mm lbr
tebal 5 mm lbr
tebal 6 mm lbr
5 Papan Kalsium Silikat Plain 8 mm lbr
Plain 12 mm lbr
Partisi kalsiboard 9 mm + rangka hollow m2

6 GYPSUM
Jayaboard 9 mm (1,2x2,4) lbr
Elephant 9 mm (1,2x2,4) lbr
Knauf 9 mm (1,2x2,4) lbr
Star 9 mm (1,2x2,4) lbr
Aplus 9 mm (1,2x2,4) lbr
Sekrup gypsum Sunray 6 x 1½" isi 1000 biji pak
Sekrup gypsum Sunray 8 x 3" isi 1000 biji pak
Sekrup gypsum Sunray 6 x 1" isi 1000 biji pak
tepung gypsum kg
Alkasit kg
List profil gypsum m'
Kasa Gypsum rol
Aplus Cornice Coumpound Adhesive 20 kg
7 COMPOUND Acimex zak
Aplus zak
MDU zak
Jayaboard 9 mm zak

I. B A H A N CETAKAN
IV. B A H A N CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh
Ø 20 cm - 100 cm bh
Ø 30 cm - 100 cm bh
Ø 50 cm - 100 cm bh
Ø 60 cm - 100 cm bh
Ø 70 cm - 50 cm bh
Ø 80 cm - 50 cm bh
Ø 100 cm - 50 cm bh
U 10 cm - 100 cm bh
U 15 cm - 100 cm bh
U 20 cm - 100 cm bh
U 30 cm - 100 cm bh
U 50 cm - 100 cm bh
2 LUBANG ANGIN (ROSTER) PC + PASIR
Roster Pasir 10 X 20 cm bh
20 X 20 cm bh
Roster Keramik 20 X 20 cm bh
30 X 30 cm bh
Roster Keramik 20 X 20 cm bh
( Warna ) 30 X 30 cm bh
Roster bulat Ø 40 cm bh
3 HEBEL Blok reguler tebal 7,5x20x60 cm m3
Blok Jumbo 10x20x60 cm m3
Anak tangga m3
Panel m3
PAVING ALDAS CONCRETE INDUSTRI
1 Tebal 6 cm K-200 Abu-abu m2
Merah/ hitam m2
Tebal 8 cm K - 200 Abu-abu m2
Merah/ hitam m2
2 Tebal 6 cm K-250 Abu-abu m2
Merah/ hitam m2
Tebal 8 cm K - 250 Abu-abu m2
Merah/ hitam m2
3 Tebal 6 cm K-300 Abu-abu m2
Merah/ hitam m2
Tebal 8 cm K - 300 Abu-abu m2
Merah/ hitam m2
4 Tebal 6 cm K-400 Abu-abu m2
Merah/ hitam m2
Tebal 8 cm K - 400 Abu-abu m2
Merah/ hitam m2
5 Tebal 8 cm K-500 Abu-abu m2
Merah/ hitam m2
Tebal 10 cm K - 500 Abu-abu m2
Merah/ hitam m2
6 UBIN FULL K- 300 Abu-abu m2
tebal 6 cm Merah/ hitam m2
7 TOPI USKUP K-300 Abu-abu m2
tebal 6 cm Merah/ hitam m2
8 TRAPEZ Abu-abu m2
Merah/ hitam m2
9 TRAPEZ GRASS BLOCK
Abu-abu m2
Merah/ hitam m2
10 STANDARD GRASS BLOCK ABU-ABU KUALITAS I
Lubang Kotak tebal 10 mm m2
Lubang Bulat tebal 10 mm m2
11 KANSTIN BETON KUALITAS I ukuran tbl 10cm tgg 20cm, panj 50 cm bh
ukuran tbl 15 cm tgg 25 cm, panj 40 c bh
ukuran tbl 10 cm tgg 30cm, panj 50 cm bh
ukuran tbl 10cm tgg 30 cm, panj 50 cm bh
RAM uk tbl 20cm tgg 30cm, panj 50 c bh
12 BATACO Pejal/Solid bh
lubang bh
Bataco besar m2
13 BATA RINGAN Tebal 7,5 cm bh
Tebal 10 cm bh
14 TALUD Talud H (9/24 x 49 x 57) bh
Talud U (9/24 x 49 x 28.5) bh
15 KERB K-300 Kerb Tali air 21 x 10 x 40) bh
New Dishedchanel (8 x 22 x 33) bh
Kerb Standard 10 x 20 x 50 bh
Kerb Standard 12.5 x 25 x 40 bh
16 KERB TAMAN
Kerb Taman 20 x 30 x 25 bh
Kerb Taman lubang 20 x 30 x 25 bh
Kerb Guci utuh 30 x 55 x 25 bh
Kerb Guci setengah 14 x 55 x 25 bh
17 SALURAN BARU K-300
Saluran 21 x 12 x 40 bh
Saluran 21 x 24 x 60 bh
Saluran 25 x 25 x 60 bh
Kerb lubang 10 x 25 x 50 bh
18 U - DICTH
20 x 30 x 120 tebal 5 cm bh
30 x 30 x 120 tebal 5 cm bh
40 x 40 x 120 tebal 5 cm bh
40 x 60 x 120 tebal 6 cm bh
50 x 50 x 120 tebal 6 cm bh
60 x 60 x 120 tebal 8 cm bh
80 x 80 x 120 tebal 8 cm bh
100 x 100 x 120 tebal 10 cm bh
100 x 120 x 120 tebal 10 cm bh

19 TUTUP U -DICTH 30 x 60 cn tebal 8.5 cm bh


40 x 60 cn tebal 10 cm bh
50 x 60 cn tebal 12.5 cm bh
60 x 60 cn tebal 15 cm bh
80 x 60 cm tebal 15.5 cm bh
100 x 60 cm tebal 18.5 cm bh
120 x 60 cm tebal 15.5 cm bh
20 BOX CULVERT 80x80x120 tbl 10cm bh
100x100x120 tbl 12cm bh
100x100x120 tbl 20cm bh

J. B A H A N CAT
1 KAYU
Menie ltr
Dempul plamur kg
Ambril/ amplas lbr
Batu Apung kg
Cat Vernis ltr
Cat Kayu kg
- Siralax ons
- Spiritus ltr
- Plitur jadi ltr
- Cat Plafond 2,5 lt
Soda Api kg
2 TEMBOK
Kalkarium kg
Kapur sirih kg
Plamur kg
Avitex 5kg
Vinilex 5 kg
Decholite 5 kg
Catylac 25 kg
Catylac 5 kg
Mowilex Mowilex 1 kg
Mowilex 2,5 ltr
Mowilex 20 ltr
Jotun interior 20 ltr
Eksterior 20 ltr
Dulux Pentalite warna standar 2,5 ltr
Wathershield Pro Exterior 2,5 ltr
Pearl GO warna standar 2,5 ltr
Cat Exterior Propan 2,5 liter klg
20 liter klg
Cat Interior Propan 2,5 liter klg
20 liter klg
Cat Dasar Propan 2,5 liter klg
20 liter klg
3 BESI
Menie ltr
Cat mengkilat kg
Cat kg
Minyak cat ltr
Thinner A ltr
Thinner Super ltr
Residu (teer/ aspal) ltr
4 CAT ANTI BOCOR
aAquaproof kg
Damdex kg
No Drop kg
5 CAT GENTENG
Danaroof water based 1 lt
Danaroof standar 4 lt
Danaroof khusus 20 lt
6 FIBER GLASS (TANGKI AIR)
kapasitas 550 liter. bh
kapasitas 1100 liter. bh
Lem Aica Aibon kg

K. B A H A N KAYU CETAKAN
1 GRC
Versaboard 4,0 mm (1,20x2,40) lbr
Versaboard 6,0 mm (1,20x2,40) lbr
Versaboard 9,0 mm (1,20x2,40) lbr
Wood Plank GRC elephant (4050 x 100) tebal 8 mm kpg
Wood Plank GRC elephant (4050 x 200) tebal 8 mm kpg
Wood Plank GRC elephant (4050 x 300) tebal 10 mm
2 PLY WOOD
Teak wood
90 X 210 X 3 mm x 7 TM lbr
. 120 X 240 X 3 mm lbr
. 90 X 210 X 4 mm x 8 TM lbr
. 90 X 210 X 9 mm lbr
. 90 X 210 X 12 mm lbr
. 90 X 210 X 15 mm lbr
. 90 X 210 X 18 mm lbr
3 Tripleks
. 120 X 240 X 3 mm lbr
. 120 X 240 X 4 mm lbr
. 120 X 240 X 6 mm lbr
4 Multipleks
. 120 X 240 X 9 mm lbr
. 120 X 240 X 12 mm lbr
. 120 X 240 X 15 mm lbr
. 120 X 240 X 18 mm lbr
5 Formika ukuran pintu lbr

L. BAHAN ALLUMUNIUM
1 KREI 25 mm m2
2 PINTU ROLLING DOOR
Allumunium tebal 0,8 mm m2
Allumunium tebal 10 mm m2
Rolling door panel tbl 1.4 mm m2
Rolling door panel tbl 1.8 mm m2
3 Naco per Daun bh
4 FOLDING GATE besi tebal 0.3 mm m2
besi tebal 0.4 mm m2
besi tebal 0.5 mm m2
galvalum tebal 0.4 mm m2
galvalum tebal 0.3 mm m2
galvalum tebal 0.5 mm m2
5 Awning Almunium m2

6 PROFIL ALLUMUNIUM
Profil Almunium Warna Coklat Glossy 4" ALEXINDO/ Setara m'
Profil Pintu Almunium Warna Coklat Glossy ALEXINDO/ Setara m'
Profil Jendela/ Boven Almunium Warna Coklat Glossy ALEXINDO m'

7 KUSEN ALLUMUNIUM
Elexindo Kusen 3" Silver/putih/coklat m'
Kusen 3" Hitam (urat kayu) m'
YKK Kusen 3" Silver/putih/coklat m'
Kusen 3" Hitam (urat kayu) m'
Elexindo Kusen 4" Silver/putih/coklat m'
Kusen 4" Hitam (urat kayu) m'
YKK Kusen 4" Silver/putih/coklat m'
Kusen 4" Coklat & Hitam (urat kayu) m'
8 JENDELA ALLUMUNIUM INCLUDE KACA SEKELAS YKK
Jendela Silver/ daun 60x120 cm non casement set
Jendela Casement silver daun 60 x 120 cm set
Jendela sliding Silver/ daun 60x120 cm set
Jendela sliding coklat/ daun 60x120 cm set
Jendela Casement Urat Kayu/ daun set
9 PINTU SLIDING / SWING
Pintu Slaiding/swing Silver / daun 90 x 200 cm daun
Pintu Slaiding/swing Hitam / daun 90 x 200 cm, floor hinge dorma daun
Pintu freamless (tempered 12 mm polos) daun 90 x 200 cm, floor hinge d daun
Pintu fitting (tempered 12 mm polos) daun 90 x 200 cm, floor hinge dorm daun
Pintu expanda + Kawat Nyamuk Unit
Pintu Shower kaca tempered 10 mm unit
Powdwer coating allumunium m'
Karet pintu/Jendela allumunium m'
Sealant tube
Kaca film TAKIKOSSAI/ Setara m2
sunblasing m2
10 HPL ( HIGHT PRESSURE LAMINATE ) motif urat kayu TACO m2
HPL ( HIGHT PRESSURE LAMINATE ) motif Granit TACO/ Setara m2
HPL ( HIGHT PRESSURE LAMINATE ) motif Krom TACO/ Setara m2
Railling kayu pabrikasi (5 x 7) cm R-54 m'

M. BAHAN ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union/dekson : 1 slagh bh
2 slagh bh
Yale : 1 slagh bh
2 slagh bh
Kuda : 1 slagh bh
2 slagh bh
2 ENGSEL DAN GERENDEL
Engsel pintu panel 3" bh
Engsel pintu panel 4" bh
Engsel pintu panel 5" bh
Kupu-kupu jendela kualitas baik bh
Nylon kupu-kupu Pintu bh
Engsel Hinge dekson psg
Engsel Salon dekson psg
Engsel bendera dekson psg
Engsel sendok bh
Engsel chasement jendela 8 " psg
Engsel chasement jendela 10 " psg
Friction Stay dekson psg
Rambuncis bh
casement handel bh
Espagnoled - dalam negeri bh
Espagnoled - luar negeri bh
Grendel Tanam luar negeri bh
Grendel biasa kualitas baik bh
Kunci lemari bh
door closer kualitas dekson bh
Kunci Pelor kualitas dekson bh
Kunci tanam / bodi pelor setara Solid bh
Handle tarik stainles steel bh
Handel + kunci tanam pintu tempered bh
Handel pintu (untuk pintu tempered) bh
Kunci Pintu (untuk pintu tempered) bh
Kait angin Jendela aluumunium Alpha/dekson bh
Gantungan handuk stainless 1" panjang = 53 m' bh

N. B A H A N SANITAIR
1 KLOSET DUDUK Toto tanpa Sprayer bh
Toto + Sprayer bh
Siram INA bh
Monoblok INA bh
American standart IMAGINE bh
American standart + sprayer
2 KLOSET JONGKOK
Merk INA bh
Merk TOTO bh
Merk DUTY bh
American standart bh
Stop kran pendek setara TOTO bh
Jet Spray (kran Cebok) DU - PHON, Wasser bh

3 WASTAFEL BAK CUCI


Merk TOTO bh
4 TEMPAT SABUN GANTUNG
210x110x 45 mm/ Type H-411 bh
110x110x 45 mm/ Type H-412 bh
5 DISPENSER TEMPAT SABUN TANAM
1 Tabung bh
2 Tabung bh
6 SEPTIC TANK (ETERNIT GRESIK)
5 Pemakai 500 liter unit
10 Pemakai 1.000 liter unit
7 URINAL
Urinal putih U. 57 unit
U. 57 M unit
Partisi Urinal A. 100 unit
8 JET WASHER unit
THX20MCRB unit
THX20NBPIV unit
THX403SBPIV
9 FLOOR DRAIN
Toto bh
Bak Cuci Stainlees bh
Km mandi stainlees bh
10 TOWEL BAR panjang 1 m'
11 PINTU KM MANDI
Pintu Fiber set
KW 1 Polos set
KW 1 + gambar + Kaca set

12 Tandon Air 225 liter bh


300 liter bh
550 liter bh
650 liter bh
1050 liter bh
1200 liter bh
1550 liter bh
2000 liter bh
O. BAHAN A L A T PENGIKAT KAYU
1 PAKU - ukuran 1" s/d 4" kg
2 PAKU - payung kg
3 PAKU - sekrup dos
4 PAKU - beton bh
5 PAKU - Seng kg
6 PAKU - Genteng metal kg
7 PAKU - Gypsum kg
8 MUR BAUT (kuda-kuda) kg
9 ANGKUR BAUT bh
10 LEM KAYU kg
11 Tali Ijuk ikat
12 SKRUP Fixer bh
13 Dynabolt bh

P. P O M P A AIR
1 POMPA AIR TANGAN
Dragon buatan Korea bh
Dragon buatan Jepang bh
Dragon buatan Indonesia bh
2 POMPA AIR LISTRIK
Sumur Dangkal 125 watt bh
200 watt bh
Semi Jet Pump . 100 watt bh
.> 100 watt bh
Jet Pump Watt kecil bh
. 250 watt bh
. 375 watt bh
. 500 watt bh
Jet Pump Stainless . 400 watt bh
. 500 watt bh

Q. LISTRIK

1 LAMPU RUMAH TANGGA


Lampu Pijar 110/220 Volt 5 watt bh
Lampu Pijar 110/220 Volt 10 watt bh
Lampu Pijar 110/220 Volt 15 watt bh
Lampu Pijar 110/220 Volt 25 watt bh
Lampu Pijar 110/220 Volt 40 watt bh
Lampu Pijar 110/220 Volt 60 watt bh
Lampu Pijar 110/220 Volt 75 watt bh
Lampu Pijar 110/220 Volt 100 watt bh
Lampu Hallogen 220 Volt 500 watt bh
Lampu Hallogen 220 Volt 1000 watt bh
Lampu LPL 220 Volt 50 watt bh
Lampu LPL 220 Volt 80 watt bh
Lampu LPL 220 Volt 125 watt bh
Lampu TL 10 watt bh
Lampu TL 15 watt bh
Lampu TL 18 watt bh
Lampu TL 20 watt bh
Lampu TL 36 watt bh
Lampu TL 40 watt bh

2 LAMPU PENERANGAN JALAN UMUM


Lampu PJU Multi LED 160 Watt Unit
120 Watt Unit
80 Watt Unit
40 Watt Unit
Lampu PJU Tall LED 120 Watt Unit
80 Watt Unit
50 Watt Unit
40 Watt Unit
30 Watt Unit
Lampu PJU LED 125 Watt Unit
100 Watt Unit
75 Watt Unit
50 Watt Unit
Lampu Sorot LED 80 Watt Unit
40 Watt Unit
Lampu PJU Tenaga Surya 120 Watt Paket
100 Watt Paket
75 Watt Paket
50 Watt Paket
35 Watt Paket
25 Watt Paket
10 Watt Paket
Lampu Jalan LVD 80 Watt Unit
60 Watt Unit
40 Watt Unit
Lampu Traficlight 3 Mata Unit
2 Mata Unit
1 Mata Unit
Trafo TL 10 watt bh
Trafo TL 15 watt bh
Trafo TL 20 watt bh
Trafo TL 40 watt bh
Tiang PJU + Pemasangan bh
3 KABEL LISTRIK per meter panjang
NYA : . 1 X 1 1/2 m'
SPLN LMK 1 X 2 1/2 m'
. 1X4 m'
1X6 m'
1 X 10
NYY :. 2 X 1 1/2 m'
PRIMA 2 X 2 1/2 m'
. 2X4 m'
2X6 m'
3 X 1 1/2 m'
3 X 2 1/2 m'
3X4 m'
4X6 m'
NYM :. 2 X 1 1/2 m'
PRIMA 2 X 2 1/2 m'
. 2X4 m'
3 X 1 1/2 m'
3 X 2 1/2 m'
3X4 m'
4 X 2,5 m'

4 KABEL LISTRIK / ROL (GULUNG)


Eterna NYA 1 x 1.5 100 m'
Eterna NYA 1 x 2.5 100 m'
Eterna NYA 1 x 4 100 m'
Eterna NYA 1 x 6 100 m'
Eterna NYA 1 x 10 100 m'

Eterna NYM 3 x 1.5 50 m'


Eterna NYM 3 x 2.5 50 m'
Eterna NYM 2 x 1.5 50 m'
Eterna NYM 2 x 2.5 50 m'
Eterna NYM 3 x 4 50 m'
Eterna NYM 4 x 2.5 50 m'
Eterna NYM 4 x 4 50 m'
Eterna NYM 4 x 6 50 m'
Eterna NYM 4 x 10 50 m'

Eterna NYY 2 x 1.5 50 m'


Eterna NYY 2 x 2.5 50 m'
Eterna NYY 3 x 1.5 50 m'
Eterna NYY 3 x 2.5 50 m'
Eterna NYY 3 x 4 50 m'
Eterna NYY 3 x 6 50 m'
Eterna NYY 4 x 2.5 50 m'
Eterna NYY 4 x 4 50 m'
Eterna NYY 4 x 6 50 m'
Eterna NYY 4 x 10 50 m'

5 KABEL LISTRIK SUPREME / ROL (GULUNG)


SUPREME (PREMIUM)
Eterna NYA 1 x 1.5 100 m'
Eterna NYA 1 x 2.5 100 m'

Eterna NYM 2 x 1.5 50 m'


2 x 2.5 50 m'
3 x 1.5 50 m'
3 x 2.5 50 m'
4 x 2.5 50 m'

6 SKAKELAR BROCO
Out bauw . Seri bh
. Engkel bh
In bauw . Seri bh
. Engkel bh
7 FUSE BOX (SEKERING KASA)
1 group bh
2 group bh
3 group bh
8 STEKER - BROCO Biasa bh
Arde bh
T Biasa bh
T dengan Arde bh
9 FITING Flapon bh
Gantung bh
Kap bh
Kombinasi bh
10 STOP KONTAK - BROCO bh
Dengan tutup bh
dengan Arde IB bh
Arde Putar bh
MCB 2A 1 Phase Unit

11 HARGA PEMASANGAN LISTRIK + INSTALASI DAN MATERIAL (Material ber-SNI)


Instalasi Lampu titik Unit
Instalasi Lampu Taman Unit
Instalsi Lampu Hotel/Gedung tidak sederhana Unit
Instalasi Stop Kontak Unit
Instalasi Stop Kontak AC Unit
Instalasi Stop Kontak Waterheater Unit
Instalasi Stop Kontak Pompa Air Unit
Instalasi Kabel Antena TV/Telp Unit
Instalasi Panel Box MCB Unit
Instalasi Pembumian Unit

R. JARINGAN LISTRIK
1 TRAVES / CROSS ARM
- Cros Arm UNP. 8 panjang 1.5 btg
- Cros Arm UNP. 8 panjang 1.8 btg
- Cros Arm UNP. 10 panjang 1.5 btg
- Cros Arm UNP. 10 panjang 1.8 btg
- Cros Arm UNP. 10 panjang 2.0 btg
2 ACCESSORIES ARM
- Klemground rod 5/8 " bh
- Klem begel 3 " bh
- Klem begel 4 " bh
- Braco for support cros arm / arm tie bh
- Braco for support cros arm / arm tie+begel bh
- Double klem begel /Klem for stay 3" bh
- Double klem begel /Klem for stay 4" bh
- Mur Baud 16x60 mm bh
- Mur Baud 16x140 mm bh
- Plat baja penahan traves / Plat simpul bh
- Plat strip Vertikal type 1 bh
- Plat strip segitiga lima type 2 bh
- Climber Protection bh
- Warning sign kecil set
- Warning sign besar set

3 ACCESSORIES ISOLATOR TARIK/HANG INSULATOR


- Cros arm Clevis set
- Boult Clevis bh
- Socket Clevis bh
- Strain Clamp AAAC, ACR bh
- Strain Clamp AAAC, ACR bh

4 ACCESSORIES KABEL HUTM


- Joint Slep/Compresion Terminal lug bh
- Joint Slep/Compresion joint Type H 50 bh
- Joint Slep/Compresion joint H type 70 bh
- Paralel group AL/ 25-70 bh
- Paralel group AL/ 70-150 bh
- Paralel group AL/ 150-240 bh

5 STAY SET JTM / TREECK SCHOOR


- Expanding Anchoor with block anchoor 3/4" bh
- Turn buckle bh
- Shackle 14 mm bh
- Thimble tebal 2 mm bh
- Klem for stay 6 " bh
- Klem for stay 8 " bh
- Preform Spiral Grip D.9 bh
- Guy Insulator /Insulator belimbing bh
- Kawat steel Wire 35 mm m'
- Clip Wire bh
- Primary Dead End Clamp LC 35 s/d 35mm2 70 mm2 bh
- Primary Dead End Clamp LC 150 s/d 240mm2 70 mm2
- Load Dead End Clamp LC 35 s/d 35mm2 70 mm2
6 INSULATOR
- Insulator tumpu type Pin bh
- Insulator tumpu type Line Post bh
- Insulator Tarik/Hang Insulator set
7 PENGHANTAR
Kawat AAAC 35 mm2 m'
50 mm 2
m'
70 mm 2
m'
Kawat AAAC/S
150 mm2 m'
240 mm2 m'
Kabel Twisted AL
3 x 25 + 25 mm2 m'
3 x 35 + 25 mm2 m'
3 x 50 + 35 mm 2
m'
3 x 70 + 50 mm 2
m'
2 x 25 + 25 mm 2
m'
2 x 35 + 25 mm 2
m'
2 x 70 + 50 mm 2
m'

2 x 10 mm2 m'
2 x 16 mm2 m'
4 x 10 mm2 m'
4 x 16 mm2 m'
Kabel TM 20 KV NA 2XSY
1 x 35 mm2 m'
1 x 50 mm 2
m'
1 x 70 mm 2
m'
1 x 95 mm 2
m'
Kabel TM 20 KV N2XXSY
1 x 35 mm2 m'
1 x 50 mm 2
m'
1 x 70 mm2 m'
1 x 95 mm2 m'
Kabel TM 20 KV NA2XSEBY
3 x 50 mm2 m'
3 x 70 mm 2
m'
3 x 95 mm2 m'
Kabel TR NYFGBY
4 x 25 mm2 m'
4 x 35 mm2 m'
4 x 50 mm 2
m'
4 x 95 mm 2
m'
8 TRAFO DISTRIBUSI
1 PHASA CSP 20 KV / B2
15.00 bh
25.00 bh
50.00 bh
9 3 PHASA 20 KV / B2
25.00 bh
50.00 bh
100.00 bh
10 KUBIKEL 20 KV 400 A
- LBS Kubikel bh
- Voltage Transformer Kubikel bh
- Transformer protection - 3 (TP-3) Kubikel bh
- Transformer protection - 1 (TP-3) Kubikel bh

11 PENGAMAN
- Line Post Insulator 20 KV bh
- Pin Post Insulator 20 KV bh
- Suspension Post Insulator 20 KV bh
- Fuse Link Type H, 2 A bh
- Fuse Link Type K, 4 A - 10 A bh
- Fuse Link Type K, 12,5 A - 20 A bh
- Fuse Cut Out 20 KV, 100 A bh
- Lightening Arrester 24 KV, 10 A bh
- Load breaker Switch, 20 KV 600 A bh
- Load breaker Switch, 20 KV 630 A bh

12 TIANG BETON / BESI


TIANG BESI 7 M / 100 daN btg
9 M / 90 daN btg
9 M / 100 daN btg
11 M / 156 daN btg
11 M / 200 daN btg
12 M / 200 daN btg
12 M / 350 daN btg
13 TIANG BETON
C-7 M / 100 daN btg
C-9 M / 100 daN btg
C-9 M / 200 daN btg
C-11 M / 200 daN btg
C-11 M / 350 daN btg
C-12 M / 350 daN btg
C-12 M / 350 daN btg

14 GROUND ROD
- Ground rod Lug bh
- Ground rod + clamp bh
- Ground wire / BC 16 m'
- Ground wire / BC 50 m'
- Guy Hook / Attachment bh
- Guy wire 35 m'
- Guy wire 55 m'
- Amour rod AAAC 70 mm2 bh
- Amour rod type 1/4 " m'

S. BIDANG BINA MARGA

I. ASPAL
1 Aspal Penetrasi 60/70 /kg (drum) kg
Aspal Emulsi CMS2/ AE-70.M kg
Aspal Emulsi AE-61.S/css-1 kg
Aspal Emulsi CRS-2/ AE-63.R kg
Aspal Emulsi AE-63.S/CSS-1Polymer kg
Aspal Curah kg
Aspal Emulsi PC kg
Kerosin ltr
Cat Marka kg
Glassbit m2
Harga Solar, Premium dan Minyak Tnah ltr
2 HOT MIX + PEMADATAN (tergelar)
Jenis ATB /ton
Hot Mix AC - BC /ton
Hot Mix AC - WC /ton
Jenis ATWC /ton
Jenis 3-Laston /ton
Jenis Laston Spc /ton
Jenis HRS /ton
Jenis Sandsheet /ton
Jenis Sand sheet spc /ton
Tack Coat / Emulsi liter
Prime Coat liter
Agregat A m3
Agregat B m3

II. BALOK GIRDER


1 PRA TEGANG BALOK BETON SLAB BETON
(TYPE SII-36), 36" X 15" feeth
(TYPE SII-36), 36" X 18" feeth
(TYPE SII-36), 36" X 21" feeth
(TYPE SII-48), 48" X 15" feeth
(TYPE SII-48), 48" X 18" feeth
2 PRETENSION BALOK WONOREJO
Ukuran 45" feeth
Ukuran 54" feeth
Ukuran 63" feeth
Ukuran 72" feeth
Ukuran 1125 mm m'
Ukuran 1575 mm m'
III. UTILITAS BINA MARGA
1 UTILITAS
Marka jalan thermoplastic m2
Guard rail = 2.37 mm x 83 mm x 310 mm (terpasang) m'
Glass bead kg
Paku Marka
Kaca bh
Kotak alumunium tanpa light bh
Kotak alumunium dengan light bh
Bulat acrylic bh
Rambu Jalan terpasang 45 x 45 cm bh
60 x 60 cm bh
75 x 75 cm bh
Minyak Beton ltr
Filler kg
Kerb m'
Expansion Joint Tipe Noma 1 m'
Expansion Joint Tipe Noma 2 m'
Expansion Joint Tipe Rubber m'
Elastomer Bearing 300 x 350 x 36 bh
Elastomer Bearing 300 x 470 x 90 bh
Pipa Galvanis dia 3" m'
Ducting ( Kabel presstess ) m'
Ducting ( Strand presstess ) m'
Strip Bearing bh
Matras Concrette bh
Joint Sealant kg
Geotextile m2
Pemantul Cahaya (Reflector) bh
Cerucuk Kayu m'
Pohon Ayoman bh
Gebalan Rumput m2
Baja Galvanis titik leleh 2500 kg/ m2 kg
Baja Galvanis titik leleh 2800 kg/ m2 kg
2 BALOK GIRDER BAJA
H - Beam SS400 ton
I - Beam ton
3 TIANG PANCANG
Tiang Pancang Beton
Diameter 30 cm /m'
Diameter 35 cm /m'
Tiang Pancang Baja
Diameter 40 cm, t = 12 mm /m'
Diameter 50 cm, t = 12 mm /m'
T. BIDANG PENGAIRAN
1 PINTU AIR
PINTU ANGKAT (BxHxH1xTR)
200 x 250 x 500 x 1050 bh
250 x 300 x 600 x 1150 bh
300 x 300 x 750 x 1300 bh
300 x 400 x 700 x 1250 bh
300 x 400 x 800 x 1350 bh
300 x 400 x 950 x 1500 bh
300 x 500 x 1050 x 1600 bh
350 x 400 x 950 x 1500 bh
350 x 500 x 1050 x 1600 bh
400 x 450 x 1000 x 1550 bh
400 x 500 x 1050 x 1600 bh
500 x 500 x 1000 x 1550 bh
PINTU SORONG BAJA (BxHxH1xTR)
300 x 300 x 600 x 1400 bh
300 x 400 x 800 x 1600 bh
300 x 500 x 1000 x 1800 bh
400 x 400 x 800 x 1600 bh
400 x 500 x 1000 x 1800 bh
400 x 600 x 1200 x 2000 bh
500 x 500 x 1000 x 1800 bh
500 x 600 x 1200 x 2000 bh
500 x 700 x 1400 x 2200 bh
600 x 400 x 800 x 1600 bh
600 x 500 x 1000 x 1800 bh
600 x 600 x 1200 x 2000 bh
600 x 700 x 1400 x 2200 bh
600 x 800 x 1200 x 2000 bh
700 x 600 x 1200 x 2000 bh
700 x 700 x 1400 x 2200 bh
700 x 800 x 1400 x 2200 bh
800 x 600 x 1400 x 2000 bh
800 x 700 x 1200 x 2000 bh
800 x 800 x 1400 x 2200 bh
900 x 600 x 1200 x 2000 bh
900 x 700 x 1200 x 2000 bh
900 x 800 x 1300 x 2100 bh
900 x 900 x 1400 x 2200 bh
PINTU SORONG BAJA STANG TUNGGAL (BxHxH1xTR)
1000 x 800 x 1600 x 2400 bh
1000 x 1000 x 2000 x 2600 bh
1000 x 1200 x 2400 x 2700 bh
1000 x 1500 x 3000 x 2700 bh
1200 x 1200 x 2500 x 3400 bh
1200 x 1200 x 2600 x 3400 bh
PINTU SORONG BAJA STANG GANDA (BxHxH1xTR)
1500 x 1000 x 2000 x 2800 bh
1500 x 1200 x 2400 x 3200 bh
1500 x 1500 x 2600 x 3400 bh
1500 x 1500 x 3000 x 3800 bh
1600 x 1200 x 2400 x 3200 bh
1600 x 1600 x 3200 x 4000 bh
1700 x 1500 x 3000 x 3800 bh
1700 x 1700 x 3400 x 4200 bh
1800 x 1500 x 3000 x 3800 bh
1800 x 1800 x 3600 x 4400 bh
2000 x 1500 x 2600 x 3400 bh
2000 x 1500 x 3000 x 3800 bh
2000 x 2000 x 3700 x 4500 bh
2000 x 2000 x 4000 x 4800 bh
2000 x 2500 x 4400 x 5500 bh
2500 x 2500 x 5000 x 5800 bh
PINTU SORONG KAYU (BxHxH1xTR)
600 x 1000 x 1800 x 2600 bh
800 x 1000 x 1900 x 2700 bh
900 x 1000 x 2000 x 2800 bh
1000 x 1000 x 2100 x 2900 bh
1200 x 1000 x 2000 x 2900 bh
1200 x 1000 x 3000 x 3800 bh
PINTU SORONG KAYU STANG GNADA (BxHxH1xTR)
1500 x 1500 x 3000 x 3800 bh
2000 x 1000 x 2000 x 2800 bh
2000 x 1500 x 3000 x 3800 bh
2000 x 2000 x 3800 x 4600 bh
2500 x 2000 x 4000 x 4800 bh
2500 x 2500 x 5000 x 5800 bh
2 DAUN PINTU
1,20 x 0,75 bh
0,60 x 0,80 bh
0,40 x 0,60 bh
3 KUNINGAN
Kuningan Æ 2,5" bh
Kuningan Æ 3,0" bh
Kuningan Æ 4,0" bh
4 DRAT STANG
Drat Stang Æ 1,0" m'
Drat Stang Æ 1,5" m'
Drat Stang Æ 2,0" m'
5 KUNCI PEMUTAR
Kunci Pemutar panjang 70 cm bh
Kunci Pemutar lingkaran Æ 70 cm bh
6 KANAL
Kanal (panjang 1 mx UNP 20) m'
Kanal (panjang 1,5 mx UNP 20) m'
Canal U 160.65.7.5 berat 18,8 kg/ m' kg
7 KUSEN PINTU
Kusen pintu L.50.50.5 berat 3,77 kg/ kg
Kusen pintu L.70.70.7 berat 7,38 kg/ kg
Kusen pintu L.100.100.10 berat 15,1 k kg
8 WATER STOP rol

U. INDEKS HARGA SATUAN BANGUNAN GEDUNG NEGARA


1 BANGUNAN GEDUNG KANTOR
a Bangunan Tidak Bertingkat
· - Sederhana m2
· - Tidak Sederhana m2
b Bangunan Bertingkat
· Sederhana m2
- Bertingkat 2 m2
- Bertingkat 3 m2
- Bertingkat 4 m2
- Bertingkat 5 m2

· Tidak Sederhana m2
- Bertingkat 2 m2
- Bertingkat 3 m2
- Bertingkat 4 m2
- Bertingkat 5 m2
c Pagar
· Gedung Sederhana
- Depan m2
- Samping m2
- Belakang m2
· Gedung Tidak Sederhana
- Depan m2
- Samping m2

2 BANGUNAN RUMAH DINAS


a Rumah Negara
· Type A unit
Type B unit
Type C unit

b Pagar Rumah Negara


· Type A
- Depan m'
- Samping m'
- Samping m'
· Type B
- Depan m'
- Samping m'
· Type C
- Depan m'
- Samping m'

Catatan:
Survey harga dilakukan pada tanggal 20 s/d 30 Desember 2017
Barang yang tidak terdapat di pasaran lokasi survey, harga ditentukan berdasar pertimbangan harga di daerah sekit
Analisa pekerjaan mengacu pada Peraturan Menteri Dan Perumahan Rakyat Republik Indonesia Nomor : 28/PRT/M
Untuk barang dengan spesifikasi khusus, harga ditentukan kemudian, berdasar sumber yang dapat dipertanggungja

Keterangan untuk IHSBGN:


Perhitungan dilakukan menggunakan Program "Model Perhitungan Harga Satuan Bangunan Gedung Negara"
BANGUNAN GEDUNG KANTOR/RUMAH DINAS
* Harga tertinggi per m2 bangunan gedung/rumah dinas dimaksud merupakan Biaya konstruksi Fisik per m
Tidak termasuk biaya perencanaan, pengawasan dan administrasi proyek dan PPn.
* Harga Satuan tertinggi tersebut telah memperhitungkan aspek kemudahan jangkauan pelayanan transportasi dan se
PAGAR GEDUNG KANTOR/RUMAH DINAS
* Harga tertinggi per m' bangunan pagar rumah dinas dimaksud merupakan Biaya konstruksi Fisik per m',
Tidak termasuk biaya perencanaan, pengawasan dan administrasi proyek dan PPn.
* Harga Satuan tertinggi tersebut telah memperhitungkan aspek kemudahan jangkauan pelayanan transportasi dan se
FAKTOR PENGALI UNTUK GEDUNG BERTINGKAT
- Bertingkat 2 1.09
- Bertingkat 3 1.12
- Bertingkat 4 1.135
- Bertingkat 5 1.162
HARGA HARGA + PPN

4 5

220,000 242,000
225,000 247,500
165,000 181,500
285,000 313,500
300,000 330,000
310,000 341,000
250,000 275,000
220,000 242,000
255,000 280,500
700 770
9,600 10,560
165,000 181,500
235,000 258,500
240,000 264,000
100,000 110,000
100,000 110,000
13,000 14,300
-
50,000 55,000
39,000 42,900
85,000 93,500
11,000 12,100
950 1,045
2,400 2,640
-
-
-
29,000 31,900
43,000 47,300
66,000 72,600
95,000 104,500
140,000 154,000
195,000 214,500
295,000 324,500
405,000 445,500
480,000 528,000
660,000 726,000
9,000 9,900
10,000 11,000
40,000 44,000
55,000 60,500
125,000 137,500
235,000 258,500
335,000 368,500
395,000 434,500
-
365,000 401,500
580,000 638,000
1,750,000 1,925,000
2,200,000 2,420,000
-
185,000 203,500
220,000 242,000
245,000 269,500
334,000 367,400
269,000 295,900
370,000 407,000
365,000 401,500
500,000 550,000
-
-
3,000,000 3,300,000
-
1,300,000 1,430,000
170,000 187,000
2,000,000 2,200,000
2,750,000 3,025,000
3,500,000 3,850,000
6,700,000 7,370,000
6,250,000 6,875,000
8,500,000 9,350,000
10,000,000 11,000,000
-
12,500 13,750
15,500 17,050
-
70,000 77,000
235,000 258,500
37,500 41,250
45,000 49,500
-
20,000 22,000
15,000 16,500
20,000 22,000
20,000 22,000
15,000 16,500
22,000 24,200
20,000 22,000
20,000 22,000
18,250 20,075
84,000 92,400
18,250 20,075
575,000 632,500
350,000 385,000
-
-
22,000 24,200
23,000 25,300
31,000 34,100
34,000 37,400
25,500 28,050
32,000 35,200
36,000 39,600
41,000 45,100
-
122,500 134,750
170,000 187,000
40,000 44,000
-
350,000 385,000
350,000 385,000
400,000 440,000
750,000 825,000
225,000 247,500
350,000 385,000
325,000 357,500
2,850,000 3,135,000
1,000,000 1,100,000
-
-
-
28,500,000 31,350,000
26,005,000 28,605,500
11,550,000 12,705,000
9,750,000 10,725,000
8,000,000 8,800,000
7,500,000 8,250,000
6,500,000 7,150,000
6,000,000 6,600,000
5,500,000 6,050,000
5,000,000 5,500,000
11,000,000 12,100,000
10,000,000 11,000,000
15,500 17,050
17,000 18,700
36,000 39,600
2,750,000 3,025,000
4,500,000 4,950,000
-
25,000 27,500
17,500 19,250
35,000 38,500
1,350,000 1,485,000
250,000 275,000
12,000 13,200
2,900,000 3,190,000
2,050,000 2,255,000
10,000 11,000
-
-
64,000 70,400
82,500 90,750
110,000 121,000
140,000 154,000
190,000 209,000
60,000 66,000
85,000 93,500
130,000 143,000
79,000 86,900
100,000 110,000
120,000 132,000
217,000 238,700
187,500 206,250
-
215,000 236,500
265,000 291,500
390,000 429,000
675,000 742,500
140,000 154,000
-
23,000 25,300
1,500,000 1,650,000
2,000,000 2,200,000
1,250,000 1,375,000
600,000 660,000
750,000 825,000
-
-
-
-
21,000 23,100
26,000 28,600
38,000 41,800
53,000 58,300
57,500 63,250
76,000 83,600
-
37,000 40,700
41,500 45,650
53,000 58,300
72,000 79,200
95,000 104,500
150,000 165,000
235,000 258,500
305,000 335,500
540,000 594,000
875,000 962,500
1,250,000 1,375,000
-
-
165,000 181,500
182,000 200,200
325,000 357,500
435,000 478,500
495,000 544,500
675,000 742,500
870,000 957,000
1,200,000 1,320,000
1,650,000 1,815,000
2,625,000 2,887,500
3,750,000 4,125,000
4,500,000 4,950,000
7,500 8,250
33,000 36,300
-
230,000 253,000
110,000 121,000
-
50,000 55,000
75,000 82,500
145,000 159,500
70,000 77,000
65,000 71,500
95,000 104,500
130,000 143,000
2,500 2,750
3,000 3,300
4,500 4,950
2,500 2,750
3,000 3,300
4,500 4,950
13,500 14,850
27,500 30,250
4,000 4,400
5,500 6,050
18,500 20,350
26,000 28,600
-
-
-
250,000 275,000
-
6,500 7,150
7,000 7,700
7,750 8,525
11,500 12,650
17,500 19,250
22,500 24,750
-
82,500 90,750
96,000 105,600
93,000 102,300
120,000 132,000
164,500 180,950
17,500 19,250
10,000 11,000
22,500 24,750
71,000 78,100
60,000 66,000
-
2,200 2,420
2,200 2,420
2,300 2,530
3,500 3,850
4,000 4,400
4,500 4,950
7,000 7,700
7,000 7,700
1,900 2,090
35,000 38,500
-
7,200 7,920
13,000 14,300
12,500 13,750
13,000 14,300
-
160,000 176,000
350,000 385,000
36,000 39,600
-
78,500 86,350
76,000 83,600
-
-
116,000 127,600
36,500 40,150
26,000 28,600
36,500 40,150
36,500 40,150
28,000 30,800
-
-
33,500 36,850
29,500 32,450
17,750 19,525
32,100 35,310
33,000 36,300
22,500 24,750
-
-
47,500 52,250
52,000 57,200
83,000 91,300
105,000 115,500
116,000 127,600
127,000 139,700
33,000 36,300
-
63,000 69,300
80,000 88,000
97,000 106,700
105,000 115,500
-
-
42,500 46,750
51,000 56,100
59,500 65,450
68,000 74,800
95,000 104,500
-
51,000 56,100
60,000 66,000
66,000 72,600
82,000 90,200
92,500 101,750
105,000 115,500
-
-
-
17,500 19,250
19,000 20,900
26,000 28,600
28,000 30,800
-
34,000 37,400
38,000 41,800
56,000 61,600
-
41,000 45,100
41,500 45,650
48,000 52,800
-
58,000 63,800
71,000 78,100
75,000 82,500
-
2,000,000 2,200,000
2,410,000 2,651,000
2,900,000 3,190,000
3,750,000 4,125,000
-
49,000 53,900
55,000 60,500
67,500 74,250
78,000 85,800
-
50,000 55,000
59,000 64,900
66,000 72,600
79,000 86,900
69,000 75,900
78,500 86,350
87,500 96,250
110,000 121,000
-
145,000 159,500
73,000 80,300
1,000 1,100
-
115,000 126,500
125,000 137,500
135,000 148,500
150,000 165,000
175,000 192,500
175,000 192,500
-
55,000 60,500
48,000 52,800
58,000 63,800
105,000 115,500
36,000 39,600
37,500 41,250
158,000 173,800
-
-
52,000 57,200
49,000 53,900
49,000 53,900
75,000 82,500
110,000 121,000
122,000 134,200
-
-
4,750 5,225
-
10,500 11,550
-
6,500 7,150
-
-
210,000 231,000
260,000 286,000
250,000 275,000
625,000 687,500
-
51,000 56,100
53,000 58,300
50,000 55,000
58,000 63,800
-
4,500 4,950
6,250 6,875
-
90,000 99,000
45,000 49,500
72,500 79,750
-
10,000 11,000
15,000 16,500
17,000 18,700
30,000 33,000
285,000 313,500
220,000 242,000
210,000 231,000
166,000 182,600
195,000 214,500
-
-
-
6,300 6,930
14,750 16,225
27,000 29,700
45,500 50,050
150,000 165,000
140,000 154,000
8,000 8,800
48,000 52,800
56,500 62,150
47,000 51,700
16,500 18,150
18,000 19,800
20,500 22,550
30,000 33,000
32,500 35,750
49,000 53,900
242,500 266,750
-
-
64,500 70,950
65,000 71,500
60,000 66,000
60,000 66,000
60,000 66,000
110,000 121,000
100,000 110,000
130,000 143,000
12,750 14,025
12,500 13,750
13,500 14,850
15,000 16,500
75,000 82,500
68,000 74,800
65,000 71,500
65,000 71,500
70,000 77,000
-
-
-
25,000 27,500
52,000 57,200
68,000 74,800
95,000 104,500
105,000 115,500
73,000 80,300
80,000 88,000
122,000 134,200
32,500 35,750
37,500 41,250
48,000 52,800
52,000 57,200
69,000 75,900
-
4,500 4,950
7,000 7,700
33,000 36,300
50,000 55,000
45,000 49,500
66,500 73,150
50,000 55,000
725,000 797,500
750,000 825,000
2,750,000 3,025,000
1,000,000 1,100,000
-
65,000 71,500
75,000 82,500
90,000 99,000
107,000 117,700
75,000 82,500
85,000 93,500
96,000 105,600
113,000 124,300
75,200 82,720
85,000 93,500
108,000 118,800
125,000 137,500
84,200 92,620
95,000 104,500
115,000 126,500
137,500 151,250
119,200 131,120
130,000 143,000
158,500 174,350
170,000 187,000
110,000 121,000
120,000 132,000
115,000 126,500
125,000 137,500
110,000 121,000
120,000 132,000
-
110,500 121,550
120,000 132,000
-
95,000 104,500
95,000 104,500
-
15,000 16,500
25,000 27,500
36,000 39,600
40,000 44,000
62,000 68,200
3,500 3,850
2,250 2,475
110,000 121,000
7,500 8,250
10,000 11,000
85,000 93,500
43,000 47,300
16,000 17,600
13,500 14,850
15,500 17,050
23,500 25,850
-
33,500 36,850
39,500 43,450
44,500 48,950
23,000 25,300
-
21,000 23,100
47,000 51,700
51,000 56,100
26,500 29,150
-
425,000 467,500
470,000 517,000
550,000 605,000
710,000 781,000
870,000 957,000
1,025,000 1,127,500
1,500,000 1,650,000
2,400,000 2,640,000
2,700,000 2,970,000
-
97,000 106,700
150,000 165,000
200,000 220,000
250,000 275,000
380,000 418,000
425,000 467,500
500,000 550,000
2,800,000 3,080,000
3,900,000 4,290,000
6,360,000 6,996,000
-
-
-
28,000 30,800
26,000 28,600
3,500 3,850
12,600 13,860
29,000 31,900
57,500 63,250
17,500 19,250
16,000 17,600
57,500 63,250
120,000 132,000
26,000 28,600
-
7,500 8,250
8,000 8,800
17,000 18,700
98,000 107,800
115,000 126,500
103,000 113,300
460,000 506,000
108,000 118,800
67,000 73,700
170,000 187,000
1,250,000 1,375,000
460,000 506,000
625,000 687,500
160,000 176,000
260,000 286,000
180,000 198,000
220,000 242,000
1,650,000 1,815,000
160,500 176,550
1,100,000 1,210,000
125,000 137,500
850,000 935,000
-
28,000 30,800
57,500 63,250
55,000 60,500
20,000 22,000
20,000 22,000
27,500 30,250
17,000 18,700
-
51,000 56,100
52,500 57,750
47,500 52,250
-
48,000 52,800
155,000 170,500
745,000 819,500
-
1,000,000 1,100,000
1,700,000 1,870,000
55,000 60,500
-
-
-
58,000 63,800
100,000 110,000
235,000 258,500
55,000 60,500
83,000 91,300
120,000 132,000
-
-
-
85,000 93,500
90,000 99,000
95,000 104,500
190,000 209,000
290,000 319,000
420,000 462,000
-
46,000 50,600
65,000 71,500
75,000 82,500
-
110,000 121,000
210,000 231,000
260,000 286,000
290,000 319,000
275,000 302,500
-
-
325,000 357,500
-
350,000 385,000
400,000 440,000
450,000 495,000
475,000 522,500
-
400,000 440,000
500,000 550,000
510,000 561,000
525,000 577,500
580,000 638,000
600,000 660,000
350,000 385,000
-
-
110,000 121,000
105,000 115,500
107,500 118,250
-
-
75,000 82,500
95,000 104,500
125,000 137,500
150,000 165,000
95,000 104,500
110,000 121,000
150,000 165,000
200,000 220,000
-
650,000 715,000
750,000 825,000
900,000 990,000
950,000 1,045,000
1,000,000 1,100,000
-
1,550,000 1,705,000
2,500,000 2,750,000
4,000,000 4,400,000
4,500,000 4,950,000
2,000,000 2,200,000
3,800,000 4,180,000
7,500 8,250
2,000 2,200
25,000 27,500
54,000 59,400
95,000 104,500
190,000 209,000
190,000 209,000
190,000 209,000
55,000 60,500
-
-
76,000 83,600
105,000 115,500
82,500 90,750
120,000 132,000
72,500 79,750
75,000 82,500
-
21,000 23,100
25,500 28,050
31,000 34,100
17,500 19,250
10,000 11,000
149,000 163,900
38,000 41,800
172,000 189,200
45,000 49,500
35,000 38,500
40,000 44,000
75,000 82,500
25,000 27,500
25,000 27,500
33,000 36,300
79,000 86,900
70,000 77,000
15,000 16,500
17,500 19,250
175,000 192,500
185,000 203,500
125,000 137,500
35,000 38,500
335,000 368,500
250,000 275,000
235,000 258,500
27,500 30,250
275,000 302,500
-
-
4,000,000 4,400,000
5,500,000 6,050,000
350,000 385,000
1,200,000 1,320,000
6,500,000 7,150,000
7,500,000 8,250,000
-
145,000 159,500
215,000 236,500
155,000 170,500
210,000 231,000
75,000 82,500
100,000 110,000
-
-
300,000 330,000
-
50,000 55,000
35,000 38,500
-
75,000 82,500
105,000 115,500
-
275,000 302,500
325,000 357,500
-
2,000,000 2,200,000
2,150,000 2,365,000
1,000,000 1,100,000
-
275,000 302,500
195,000 214,500
325,000 357,500
-
300,000 330,000
180,000 198,000
40,000 44,000
700,000 770,000
-
175,000 192,500
200,000 220,000
275,000 302,500
-
425,000 467,500
640,000 704,000
1,000,000 1,100,000
1,150,000 1,265,000
1,650,000 1,815,000
1,750,000 1,925,000
1,900,000 2,090,000
2,000,000 2,200,000
-
-
16,000 17,600
33,000 36,300
14,000 15,400
900 990
33,000 36,300
27,500 30,250
22,000 24,200
20,000 22,000
20,000 22,000
16,000 17,600
11,000 12,100
900 990
8,000 8,800
-
-
-
190,000 209,000
335,000 368,500
185,000 203,500
-
390,000 429,000
450,000 495,000
850,000 935,000
1,300,000 1,430,000
1,400,000 1,540,000
1,600,000 1,760,000
1,900,000 2,090,000
3,000,000 3,300,000
3,800,000 4,180,000
5,250,000 5,775,000
-
-
-
-
-
5,000 5,500
7,500 8,250
8,000 8,800
9,000 9,900
13,000 14,300
14,500 15,950
17,000 18,700
18,000 19,800
100,000 110,000
140,000 154,000
69,000 75,900
70,000 77,000
75,000 82,500
10,000 11,000
12,000 13,200
12,500 13,750
16,000 17,600
17,500 19,250
23,000 25,300
-
-
3,550,000 3,905,000
2,900,000 3,190,000
2,045,000 2,249,500
1,450,000 1,595,000
2,650,000 2,915,000
1,950,000 2,145,000
1,750,000 1,925,000
1,500,000 1,650,000
1,100,000 1,210,000
3,250,000 3,575,000
2,500,000 2,750,000
2,000,000 2,200,000
1,750,000 1,925,000
1,600,000 1,760,000
1,100,000 1,210,000
17,000,000 18,700,000
15,000,000 16,500,000
12,000,000 13,200,000
9,500,000 10,450,000
7,500,000 8,250,000
6,000,000 6,600,000
5,250,000 5,775,000
2,350,000 2,585,000
2,000,000 2,200,000
1,800,000 1,980,000
3,500,000 3,850,000
2,500,000 2,750,000
1,900,000 2,090,000
35,000 38,500
36,000 39,600
37,000 40,700
40,000 44,000
8,000,000 8,800,000
-
-
3,000 3,300
4,000 4,400
4,250 4,675
4,750 5,225
9,000 9,900
8,000 8,800
8,000 8,800
9,500 10,450
15,000 16,500
10,000 11,000
12,500 13,750
22,000 24,200
28,000 30,800
8,000 8,800
14,000 15,400
13,500 14,850
7,000 7,700
21,000 23,100
17,000 18,700
28,000 30,800
-
-
220,000 242,000
240,000 264,000
375,000 412,500
540,000 594,000
890,000 979,000
-
305,000 335,500
430,000 473,000
240,000 264,000
340,000 374,000
700,000 770,000
550,000 605,000
900,000 990,000
1,260,000 1,386,000
2,050,000 2,255,000
-
335,000 368,500
450,000 495,000
410,000 451,000
550,000 605,000
850,000 935,000
1,100,000 1,210,000
660,000 726,000
1,025,000 1,127,500
1,325,000 1,457,500
2,235,000 2,458,500
-
-
-
205,000 225,500
350,000 385,000
-
280,000 308,000
580,000 638,000
405,000 445,500
525,000 577,500
1,400,000 1,540,000
-
-
17,000 18,700
1,800 1,980
17,000 18,700
19,000 20,900
-
37,000 40,700
51,000 56,100
64,000 70,400
4,500 4,950
11,000 12,100
20,500 22,550
20,000 22,000
12,000 13,200
5,000 5,500
22,000 24,200
7,000 7,700
-
34,000 37,400
13,500 14,850
25,000 27,500
100,000 110,000
-
-
150,000 165,000
200,000 220,000
200,000 220,000
150,000 165,000
210,000 231,000
210,000 231,000
150,000 165,000
200,000 220,000
150,000 165,000
250,000 275,000
-
-
-
185,000 203,500
210,000 231,000
280,000 308,000
245,000 269,500
405,000 445,500
-
13,750 15,125
49,500 54,450
55,000 60,500
38,500 42,350
110,000 121,000
71,500 78,650
77,000 84,700
8,250 9,075
10,450 11,495
55,000 60,500
27,500 30,250
19,250 21,175
137,500 151,250
49,500 54,450
82,500 90,750
-
-
33,000 36,300
27,500 30,250
27,500 30,250
27,500 30,250
36,000 39,600
-
-
19,250 21,175
27,500 30,250
38,500 42,350
12,000 13,200
23,000 25,300
33,000 36,300
-
-
132,000 145,200
25,000 27,500
13,750 15,125
4,400 4,840
71,500 78,650
77,000 84,700
22,000 24,200
55,000 60,500
8,500 9,350
5,500 6,050
49,500 54,450
154,000 169,400
33,000 36,300
-
338,000 371,800
305,000 335,500
407,000 447,700
-
8,500 9,350
9,900 10,890
13,500 14,850
-
36,000 39,600
57,500 63,250
-
22,500 24,750
33,000 36,300
42,500 46,750
64,000 70,400
17,500 19,250
22,000 24,200
42,000 46,200
-
57,750 63,525
8,250 9,075
11,250 12,375
15,800 17,380
-
28,600 31,460
31,900 35,090
36,300 39,930
41,250 45,375
-
36,850 40,535
41,250 45,375
50,800 55,880
64,900 71,390
-
110,000 121,000
126,500 139,150
145,750 160,325
-
49,500 54,450
63,250 69,575
79,750 87,725
141,900 156,090
-
-
22,825,000 25,107,500
25,300,000 27,830,000
34,540,000 37,994,000
-
28,600,000 31,460,000
38,000,000 41,800,000
48,000,000 52,800,000
-
27,500,000 30,250,000
38,500,000 42,350,000
40,150,000 44,165,000
36,300,000 39,930,000
-
-
305,000 335,500
337,000 370,700
407,000 447,700
30,250 33,275
34,650 38,115
37,600 41,360
1,369,500 1,506,450
495,000 544,500
12,100,000 13,310,000
15,400,000 16,940,000
-
-
1,375,000 1,512,500
1,430,000 1,573,000
1,540,000 1,694,000
2,519,000 2,770,900
2,750,000 3,025,000
3,850,000 4,235,000
4,400,000 4,840,000
-
2,134,000 2,347,400
2,310,000 2,541,000
2,662,000 2,928,200
3,938,000 4,331,800
5,280,000 5,808,000
6,875,000 7,562,500
7,370,000 8,107,000
-
-
12,650 13,915
82,500 90,750
137,500 151,250
144,100 158,510
17,600 19,360
15,730 17,303
21,340 23,474
71,500 78,650
7,500 8,250
-
-
-
-
13,600 14,960
14,600 16,060
13,000 14,300
13,200 14,520
12,800 14,080
11,300 12,430
13,100 14,410
13,750 15,125
59,000 64,900
46,000 50,600
-
-
1,370,000 1,507,000
1,660,000 1,826,000
1,735,000 1,908,500
1,265,000 1,391,500
1,620,000 1,782,000
1,725,000 1,897,500
1,510,000 1,661,000
1,850,000 2,035,000
1,950,000 2,145,000
9,000 9,900
17,500 19,250
175,000 192,500
160,000 176,000
-
-
-
1,350,000 1,485,000
1,400,000 1,540,000
1,650,000 1,815,000
1,700,000 1,870,000
1,750,000 1,925,000
-
1,650,000 1,815,000
1,750,000 1,925,000
1,950,000 2,145,000
2,100,000 2,310,000
5,100,000 5,610,000
6,100,000 6,710,000
-
-
75,000 82,500
550,000 605,000
50,400 55,440
-
100,000 110,000
125,000 137,500
250,000 275,000
400,000 440,000
450,000 495,000
600,000 660,000
750,000 825,000
19,000 20,900
-
80,000 88,000
1,700,000 1,870,000
2,200,000 2,420,000
-
6,050,000 6,655,000
4,951,000 5,446,100
115,000 126,500
216,000 237,600
72,000 79,200
330,000 363,000
583,000 641,300
49,000 53,900
50,500 55,550
18,000 19,800
40,800 44,880
12,700 13,970
18,200 20,020
14,100 15,510
14,000 15,400
-
8,750,000 9,625,000
9,500,000 10,450,000
-
-
250,000 275,000
375,000 412,500
-
1,000,000 1,100,000
1,500,000 1,650,000
-
-
-
1,850,000 2,035,000
1,980,000 2,178,000
2,060,000 2,266,000
2,200,000 2,420,000
2,750,000 3,025,000
2,300,000 2,530,000
2,500,000 2,750,000
2,400,000 2,640,000
2,500,000 2,750,000
2,500,000 2,750,000
2,600,000 2,860,000
2,800,000 3,080,000
-
7,200,000 7,920,000
7,700,000 8,470,000
7,750,000 8,525,000
7,800,000 8,580,000
8,500,000 9,350,000
9,000,000 9,900,000
9,100,000 10,010,000
6,700,000 7,370,000
10,243,000 11,267,300
840,000 924,000
8,375,000 9,212,500
8,455,000 9,300,500
10,250,000 11,275,000
12,000,000 13,200,000
12,500,000 13,750,000
12,700,000 13,970,000
13,000,000 14,300,000
13,500,000 14,850,000
13,750,000 15,125,000
14,500,000 15,950,000
14,750,000 16,225,000
14,900,000 16,390,000
15,000,000 16,500,000
15,600,000 17,160,000
-
25,573,000 28,130,300
27,551,000 30,306,100
29,525,000 32,477,500
32,490,000 35,739,000
26,245,000 28,869,500
36,218,000 39,839,800
-
46,197,000 50,816,700
53,920,000 59,312,000
54,017,000 59,418,700
54,291,000 59,720,100
55,055,000 60,560,500
56,853,000 62,538,300
58,646,500 64,511,150
59,127,000 65,039,700
59,843,000 65,827,300
60,442,000 66,486,200
54,291,000 59,720,100
61,041,000 67,145,100
61,284,000 67,412,400
61,879,000 68,066,900
62,010,000 68,211,000
74,205,000 81,625,500
-
57,100,000 62,810,000
69,000,000 75,900,000
78,500,000 86,350,000
85,000,000 93,500,000
105,000,000 115,500,000
142,000,000 156,200,000
-
87,000,000 95,700,000
92,000,000 101,200,000
98,000,000 107,800,000
110,000,000 121,000,000
116,000,000 127,600,000
153,000,000 168,300,000
-
2,300,000 2,530,000
1,500,000 1,650,000
750,000 825,000
-
3,740,000 4,114,000
5,000,000 5,500,000
6,500,000 7,150,000
-
500,000 550,000
650,000 715,000
800,000 880,000
-
275,000 302,500
300,000 330,000
-
550,000 605,000
810,000 891,000
25,000 27,500
-
25,000 27,500
25,000 27,500
25,000 27,500
900,000 990,000
-
-
-
-
3,650,000 4,015,000
5,030,000 5,533,000
-
3,650,000 4,015,000
3,978,500 4,376,350
4,088,000 4,496,800
4,142,750 4,557,025
4,241,300 4,665,430
-
5,030,000 5,533,000
5,482,700 6,030,970
5,633,600 6,196,960
5,709,050 6,279,955
5,844,860 6,429,346
-
-
2,040,000 2,244,000
1,740,000 1,914,000
1,680,000 1,848,000
-
1,495,200 1,644,720
1,423,200 1,565,520
-
-
-
4,730,000 5,203,000
4,310,000 4,741,000
4,050,000 4,455,000
-
-
-
1,870,000 2,057,000
1,140,000 1,254,000
1,070,000 1,177,000

ertimbangan harga di daerah sekitar


publik Indonesia Nomor : 28/PRT/M/2016
umber yang dapat dipertanggungjawabkan.

Bangunan Gedung Negara"

a konstruksi Fisik per m 2,

auan pelayanan transportasi dan sebaran di wilayah

konstruksi Fisik per m',

auan pelayanan transportasi dan sebaran di wilayah


DAFTAR HARGA SATUAN UPAH TENAGA KERJA th. 2018

PEKERJAAN PEMBANGUNAN RUMAH TINGGAL


LUAS BANGUNAN/LUAS TANAH
0

NO URAIAN SATUAN HARGA HARGA + PPN


1 2 3 4 5

1 Pekerja/Pekerja/Penjaga OHK 54,000 59,400


2 Mandor OHK 71,000 78,100
3 Kepala Tukang Kayu OHK 69,000 75,900
4 Tukang Kayu OHK 68,000 74,800
5 Kepala Tukang Batu OHK 69,000 75,900
6 Tukang Batu OHK 66,000 72,600
7 Kepala Tukang Besi OHK 69,000 75,900
8 Tukang Besi OHK 66,000 72,600
9 Kepala Tukang Cat OHK 69,000 75,900
10 Tukang Cat OHK 66,000 72,600
11 Tukang listrik OHK 66,000 72,600
12 Tukang Plitur OHK 66,000 72,600
13 Tukang Leideng OHK 66,000 72,600
14 Tk. Penganyam Bronjong OHK 64,000 70,400
15 Tukang Masak Aspal OHK 64,000 70,400
16 Masinis/operator alat berat OHK 66,000 72,600
17 Pembantu Masinis/operator OHK 64,000 70,400
18 Mekanik OHK 64,000 70,400
19 Sopir OHK 66,000 72,600
ANALISIS HARGA SATUAN PEKERJA

PEKERJAAN PEMBANGUNAN RUMAH TINGGAL

NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A. PEKERJAAN PERSIAPAN

1 A. 2.2. Pembersihan 1 m2 lapangan dan perataan

No Kode Uraian Satuan Koefisien Harga Satuan Jumlah


(Rp) Harga
(Rp)
A TENAGA
L.01 Pekerja OH 0.100 X Rp 54,000.00 = Rp 5,400.00
L.04 Mandor OH 0.050 X Rp 71,000.00 = Rp 3,550.00
JUMLAH TENAGA KERJA = Rp 8,950.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 8,950.00


E Overhead & Profit 10% x D 895.00
F Harga Satuan Pekerjaan (D+E) = Rp 9,845.00

4 A. 2.2. Pengukuran dan pemasangan 1 m’ Bouwplank


A TENAGA
L.01 Pekerja OH 0.100 X Rp 54,000.00 = Rp 5,400.00
L.02 Tukang Kayu OH 0.100 X Rp 68,000.00 = Rp 6,800.00
L.03 Kepala Tukang Kayu OH 0.010 X Rp 69,000.00 = Rp 690.00
L.04 Mandor OH 0.005 X Rp 71,000.00 = Rp 355.00
JUMLAH TENAGA KERJA = Rp 13,245.00
B BAHAN
Kayu 5/7 m3 0.005 X Rp 2,750,000.00 = Rp 13,750.00
PAKU - ukuran 1" s/d 4" Kg 0.020 X Rp #N/A = Rp #N/A
Kayu papan 3/20 m3 0.007 X Rp 2,750,000.00 = Rp 19,250.00
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) #N/A


E Overhead & Profit 10% x D #N/A
F Harga Satuan Pekerjaan (D+E) = Rp #N/A

B. PEKERJAAN TANAH
1 A.2.3.1Penggalian 1 m3 tanah biasa sedalam 1 m
A TENAGA
L.01 Pekerja OH 0.750 X Rp 54,000.00 = Rp 40,500.00
L.04 Mandor OH 0.025 X Rp 71,000.00 = Rp 1,775.00
JUMLAH TENAGA KERJA = Rp 42,275.00
B BAHAN

JUMLAH HARGA BAHAN


C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 42,275.00


E Overhead & Profit 10% x D 4,227.50
F Harga Satuan Pekerjaan = Rp 46,502.50

11 A.2.3.1Pengurugan 1 m3 dengan pasir urug


A TENAGA
L.01 Pekerja OH 0.300 X Rp 54,000.00 = Rp 16,200.00
L.04 Mandor OH 0.010 X Rp 71,000.00 = Rp 710.00
NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

JUMLAH TENAGA KERJA = Rp 16,910.00


B BAHAN
Pasir urug m3 1.200 X Rp 165,000.00 = Rp 198,000.00
JUMLAH HARGA BAHAN = Rp 198,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 214,910.00


E Overhead & Profit 10% x D 21,491.00
F Harga Satuan Pekerjaan = Rp 236,401.00

24 A.3.2.1Pemasangan 1 m3 batu kosong (anstamping)


A TENAGA
L.01 Pekerja OH 0.780 X Rp 54,000.00 = Rp 42,120.00
L.02 Tukang Batu OH 0.390 X Rp 66,000.00 = Rp 25,740.00
L.03 Kepala Tukang OH 0.039 X Rp 69,000.00 = Rp 2,691.00
L.04 Mandor OH 0.039 X Rp 71,000.00 = Rp 2,769.00
JUMLAH TENAGA KERJA = Rp 73,320.00
B BAHAN
Batu belah m3 1.200 X Rp 225,000.00 = Rp 270,000.00
Pasir urug m3 0.432 X Rp 165,000.00 = Rp 71,280.00
JUMLAH HARGA BAHAN = Rp 341,280.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 414,600.00


E Overhead & Profit 10% x D 41,460.00
F Harga Satuan Pekerjaan = Rp 456,060.00

16 A.2.3.1Pengurugan 1 m3 urugan tanah kembali


A TENAGA
L.01 Pekerja OH 0.250 X Rp 54,000.00 = Rp 13,500.00
L.04 Mandor OH 0.025 X Rp 71,000.00 = Rp 1,775.00
JUMLAH TENAGA KERJA = Rp 15,275.00
B BAHAN
JUMLAH HARGA BAHAN
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 15,275.00


E Overhead & Profit 10% x D 1,527.50
F Harga Satuan Pekerjaan = Rp 16,802.50

C. PEKERJAAN PONDASI
18 A.3.2.1Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5Pasir Pasang
A TENAGA
L.01 Pekerja OH 1.500 X Rp 54,000.00 = Rp 81,000.00
L.02 Tukang Batu OH 0.750 X Rp 66,000.00 = Rp 49,500.00
L.03 Kepala Tukang OH 0.075 X Rp 69,000.00 = Rp 5,175.00
L.04 Mandor OH 0.075 X Rp 71,000.00 = Rp 5,325.00
JUMLAH TENAGA KERJA = Rp 141,000.00
B BAHAN
Batu belah m3 1.200 X Rp 225,000.00 = Rp 270,000.00
Semen PC Kg 136.000 X Rp 1,000.00 = Rp 136,000.00
Pasir Pasang m3 0.544 X Rp 235,000.00 = Rp 127,840.00
JUMLAH HARGA BAHAN = Rp 533,840.00
C PERALATAN

JUMLAH HARGA ALAT


D Jumlah (A+B+C) 674,840.00
E Overhead & Profit 10% x D 67,484.00
F Harga Satuan Pekerjaan (D+E) = Rp 742,324.00

D. PEKERJAAN BETON
36 A.4.1.1Membuat 1 m’ Sloof beton bertulang (15 x 20) cm
A TENAGA
L.01 Pekerja OH 0.297 X Rp 54,000.00 = Rp 16,038.00
L.02 Tukang Batu OH 0.033 X Rp 66,000.00 = Rp 2,178.00
NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

L.02 Tukang Kayu OH 0.033 X Rp 68,000.00 = Rp 2,244.00


L.02 Tukang besi OH 0.033 X Rp 66,000.00 = Rp 2,178.00
L.03 Kepala tukang OH 0.010 X Rp 69,000.00 = Rp 690.00
L.04 Mandor OH 0.015 X Rp 71,000.00 = Rp 1,065.00
JUMLAH TENAGA KERJA = Rp 24,393.00
B BAHAN
Kayu kelas III m3 0.005 X Rp 2,750,000.00 = Rp 13,750.00
PAKU - ukuran 1" s/d 4" kg 0.030 X Rp #N/A = Rp #N/A
Minyak bekisting Liter 0.020 X Rp 10,000.00 = Rp 200.00
Besi polos D 12 kg 3.000 X Rp 9,000.00 = Rp 27,000.00
Ikat beton/bendrat kg 0.050 X Rp 20,000.00 = Rp 1,000.00
Semen PC kg 5.500 X Rp 1,000.00 = Rp 5,500.00
Pasir Beton m3 0.009 X Rp 240,000.00 = Rp 2,160.00
Kerikil m3 0.015 X Rp 165,000.00 = Rp 2,475.00
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) #N/A


E Overhead & Profit 10% x D #N/A
F Harga Satuan Pekerjaan = Rp #N/A

35 A.4.1.1Membuat 1 m’ kolom beton bertulang (15 x 25) cm


A TENAGA
L.01 Pekerja OH 0.200 X Rp 54,000.00 = Rp 10,800.00
L.02 Tukang Batu OH 0.020 X Rp 66,000.00 = Rp 1,320.00
L.02 Tukang Kayu OH 0.020 X Rp 68,000.00 = Rp 1,360.00
L.02 Tukang besi OH 0.020 X Rp 66,000.00 = Rp 1,320.00
L.03 Kepala tukang OH 0.006 X Rp 69,000.00 = Rp 414.00
L.04 Mandor OH 0.009 X Rp 71,000.00 = Rp 639.00
JUMLAH TENAGA KERJA = Rp 15,853.00
B BAHAN
Kayu kelas III m3 0.008 X Rp 2,750,000.00 = Rp 22,000.00
PAKU - ukuran 1" s/d 4" kg 0.010 X Rp #N/A = Rp #N/A
Minyak bekisting Liter 0.200 X Rp 10,000.00 = Rp 2,000.00
Besi polos D12 kg 3.500 X Rp 9,000.00 = Rp 31,500.00
Ikat beton/bendrat kg 0.450 X Rp 20,000.00 = Rp 9,000.00
Semen PC kg 4.000 X Rp 1,000.00 = Rp 4,000.00
Pasir Beton m3 0.006 X Rp 240,000.00 = Rp 1,440.00
Kerikil m3 0.009 X Rp 165,000.00 = Rp 1,485.00
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) #N/A


E Overhead & Profit 10% x D #N/A
F Harga Satuan Pekerjaan = Rp #N/A

36 A.4.1.1Membuat 1 m’ Ring Balk beton bertulang (15 x 20) cm


A TENAGA
L.01 Pekerja OH 0.300 X Rp 54,000.00 = Rp 16,200.00
L.02 Tukang Batu OH 0.050 X Rp 66,000.00 = Rp 3,300.00
L.02 Tukang Kayu OH 0.080 X Rp 68,000.00 = Rp 5,440.00
L.02 Tukang besi OH 0.050 X Rp 66,000.00 = Rp 3,300.00
L.03 Kepala tukang OH 0.020 X Rp 69,000.00 = Rp 1,380.00
L.04 Mandor OH 0.015 X Rp 71,000.00 = Rp 1,065.00
JUMLAH TENAGA KERJA = Rp 30,685.00
B BAHAN
Kayu kelas III m3 0.006 X Rp 2,750,000.00 = Rp 16,500.00
PAKU - ukuran 1" s/d 4" kg 0.030 X Rp #N/A = Rp #N/A
Minyak bekisting Liter 0.020 X Rp 10,000.00 = Rp 200.00
Besi polos D 12 kg 3.000 X Rp 9,000.00 = Rp 27,000.00
Ikat beton/bendrat kg 0.050 X Rp 20,000.00 = Rp 1,000.00
Semen PC kg 5.500 X Rp 1,000.00 = Rp 5,500.00
Pasir Beton m3 0.009 X Rp 240,000.00 = Rp 2,160.00
Kerikil m3 0.015 X Rp 165,000.00 = Rp 2,475.00
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN

JUMLAH HARGA ALAT


NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

D Jumlah (A+B+C) #N/A


E Overhead & Profit 10% x D #N/A
F Harga Satuan Pekerjaan = Rp #N/A

36 A.4.1.1Membuat 1 m’ Atap dak (beton)10cm


A TENAGA
L.01 Pekerja OH 0.300 X Rp 54,000.00 = Rp 16,200.00
L.02 Tukang Batu OH 0.050 X Rp 66,000.00 = Rp 3,300.00
L.02 Tukang Kayu OH 0.080 X Rp 68,000.00 = Rp 5,440.00
L.02 Tukang besi OH 0.050 X Rp 66,000.00 = Rp 3,300.00
L.03 Kepala tukang OH 0.020 X Rp 69,000.00 = Rp 1,380.00
L.04 Mandor OH 0.015 X Rp 71,000.00 = Rp 1,065.00
JUMLAH TENAGA KERJA = Rp 30,685.00
B BAHAN
Kayu kelas III m3 0.006 X Rp 2,750,000.00 = Rp 16,500.00
PAKU - ukuran 1" s/d 4" kg 0.020 X Rp #N/A = Rp #N/A
Minyak bekisting Liter 0.020 X Rp 10,000.00 = Rp 200.00
Besi polos D 12 kg 4.000 X Rp 9,000.00 = Rp 36,000.00
Ikat beton/bendrat kg 0.050 X Rp 20,000.00 = Rp 1,000.00
Semen PC kg 5.500 X Rp 50,000.00 = Rp 275,000.00
Pasir Beton m3 0.020 X Rp 240,000.00 = Rp 4,800.00
Kerikil m3 0.020 X Rp 165,000.00 = Rp 3,300.00
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) #N/A


E Overhead & Profit 10% x D #N/A
F Harga Satuan Pekerjaan = Rp #N/A

E. PEKERJAAN DINDING
9 A.4.4.1Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4Pasir Pasang
A TENAGA
L.01 Pekerja OH 0.300 X Rp 54,000.00 = Rp 16,200.00
L.02 Tukang Batu OH 0.100 X Rp 66,000.00 = Rp 6,600.00
L.03 Kepala Tukang OH 0.010 X Rp 69,000.00 = Rp 690.00
L.04 Mandor OH 0.015 X Rp 71,000.00 = Rp 1,065.00
JUMLAH TENAGA KERJA = Rp 24,555.00
B BAHAN
Bata merah Bh 70.000 X Rp 700.00 = Rp 49,000.00
Semen PC Kg 11.500 X Rp 1,000.00 = Rp 11,500.00
Pasir Pasang m3 0.043 X Rp 235,000.00 = Rp 10,105.00
JUMLAH HARGA BAHAN = Rp 70,605.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 95,160.00


E Overhead & Profit 10% x D 9,516.00
F Harga Satuan Pekerjaan (D+E) = Rp 104,676.00

12 A. 4.4. Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP :8Pasir Pasang
A TENAGA
L.01 Pekerja OH 0.300 X Rp 54,000.00 = Rp 16,200.00
L.02 Tukang Batu OH 0.100 X Rp 66,000.00 = Rp 6,600.00
L.03 Kepala Tukang OH 0.010 X Rp 69,000.00 = Rp 690.00
L.04 Mandor OH 0.015 X Rp 71,000.00 = Rp 1,065.00
JUMLAH TENAGA KERJA = Rp 24,555.00
B BAHAN
Bata merah Bh 70.000 X Rp 700.00 = Rp 49,000.00
Semen PC Kg 6.500 X Rp 1,000.00 = Rp 6,500.00
Pasir Pasang m3 0.050 X Rp 235,000.00 = Rp 11,750.00
JUMLAH HARGA BAHAN = Rp 67,250.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 91,805.00


NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

E Overhead & Profit 10% x D 9,180.50


F Harga Satuan Pekerjaan (D+E) = Rp 100,985.50

F. PEKERJAAN PLESTERAN
4 A.4.4.2Pemasangan 1 m2 plesteran 1SP : 4Pasir Pasang tebal 15 mm
A TENAGA
L.01 Pekerja OH 0.300 X Rp 54,000.00 = Rp 16,200.00
L.03 Tukang Batu OH 0.150 X Rp 66,000.00 = Rp 9,900.00
L.03 Kepala Tukang OH 0.015 X Rp 69,000.00 = Rp 1,035.00
L.04 Mandor OH 0.015 X Rp 71,000.00 = Rp 1,065.00
JUMLAH TENAGA KERJA = Rp 28,200.00
B BAHAN
Semen PC Kg 6.240 X Rp 1,000.00 = Rp 6,240.00
Pasir Pasang m3 0.024 X Rp 235,000.00 = Rp 5,640.00
JUMLAH HARGA BAHAN = Rp 11,880.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 40,080.00


E Overhead & Profit 10% x D 4,008.00
F Harga Satuan Pekerjaan = Rp 44,088.00

G. PEKERJAAN KAYU
2 A.4.6.1Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela. kayu kelas II
A TENAGA
L.01 Pekerja OH 6.000 X Rp 54,000.00 = Rp 324,000.00
L.03 Tukang Kayu OH 18.000 X Rp 68,000.00 = Rp 1,224,000.00
L.03 Kepala Tukang Kayu OH 1.800 X Rp 69,000.00 = Rp 124,200.00
L.04 Mandor OH 0.300 X Rp 71,000.00 = Rp 21,300.00
JUMLAH TENAGA KERJA = Rp 1,693,500.00
B BAHAN
Balok kayu Bengkirai m3 1.000 X Rp ### = Rp 11,000,000.00
PAKU - ukuran 1" s/d 4" Kg 1.250 X Rp #N/A = Rp #N/A
Lem kayu Kg 0.100 X Rp - = Rp -
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN
JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp #N/A


E Overhead & Profit 10% x D = Rp #N/A
F Harga Satuan Pekerjaan (D+E) = Rp #N/A

5 A.4.6.1Pembuatan dan pemasangan 1 m2 daun pintu panel. kayu kelas II


A TENAGA
L.01 Pekerja OH 1.000 X Rp 54,000.00 = Rp 54,000.00
L.03 Tukang Kayu OH 3.000 X Rp 68,000.00 = Rp 204,000.00
L.03 Kepala Tukang Kayu OH 0.300 X Rp 69,000.00 = Rp 20,700.00
L.04 Mandor OH 0.050 X Rp 71,000.00 = Rp 3,550.00
JUMLAH TENAGA KERJA = Rp 282,250.00
B BAHAN
Papan kayu Bengkirai m3 0.040 X Rp ### = Rp 440,000.00
Lem kayu Kg 0.500 X Rp - = Rp -
JUMLAH HARGA BAHAN = Rp 440,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 722,250.00


E Overhead & Profit 10% x D = Rp 72,225.00
F Harga Satuan Pekerjaan (D+E) = Rp 794,475.00

6 A.4.6.1Pembuatan dan pemasangan 1 m2 jendela kaca. kayu kelas II


A TENAGA
L.01 Pekerja OH 0.800 X Rp 54,000.00 = Rp 43,200.00
L.03 Tukang Kayu OH 2.400 X Rp 68,000.00 = Rp 163,200.00
L.03 Kepala Tukang Kayu OH 0.240 X Rp 69,000.00 = Rp 16,560.00
L.04 Mandor OH 0.040 X Rp 71,000.00 = Rp 2,840.00
JUMLAH TENAGA KERJA = Rp 225,800.00
B BAHAN
Papan kayu Bengkirai m3 0.024 X Rp ### = Rp 264,000.00
NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

Lem kayu Kg 0.300 X Rp - = Rp -


JUMLAH HARGA BAHAN = Rp 264,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 489,800.00


E Overhead & Profit 10% x D = Rp 48,980.00
F Harga Satuan Pekerjaan (D+E) = Rp 538,780.00

H. PEKERJAAN ATAP
13 A.4.6.1Pemasangan 1 m3 konstruksi kuda-kuda konvensional. kayu kelas II
A TENAGA
L.01 Pekerja OH 4.000 X Rp 54,000.00 = Rp 216,000.00
L.03 Tukang Kayu OH 12.000 X Rp 68,000.00 = Rp 816,000.00
L.03 Kepala Tukang Kayu OH 1.200 X Rp 69,000.00 = Rp 82,800.00
L.04 Mandor OH 0.200 X Rp 71,000.00 = Rp 14,200.00
JUMLAH TENAGA KERJA = Rp 1,129,000.00
B BAHAN
Balok kayu m3 1.000 X Rp ### = Rp 10,000,000.00
Besi strip tebal 5mm kg 15.000 X Rp 3,200.00 = Rp 48,000.00
PAKU - ukuran 1" s/d 4" kg 1.000 X Rp #N/A = Rp #N/A
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp #N/A


E Overhead & Profit 10% x D = Rp #N/A
F Harga Satuan Pekerjaan (D+E) = Rp #N/A

25 A.4.5.2Pemasangan 1 m’ Nok 8/12


A TENAGA
L.01 Pekerja OH 0.084 X Rp 54,000.00 = Rp 4,536.00
L.03 Tukang Kayu OH 0.125 X Rp 68,000.00 = Rp 8,500.00
L.11 Kepala Tukang Kayu OH 0.013 X Rp 69,000.00 = Rp 897.00
L.15 Mandor OH 0.004 X Rp 71,000.00 = Rp 284.00
JUMLAH TENAGA KERJA = Rp 14,217.00
B BAHAN
Nok 8/12 M' 1.000 X Rp 96,153.85 = Rp 96,153.85
Besi strip tebal 5 mm kg 0.200 X Rp 64,000.00 = Rp 12,800.00
Paku sekrup 3.5” Bh 0.500 X Rp 15,000.00 = Rp 7,500.00
JUMLAH HARGA BAHAN = Rp 116,453.85
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 130,670.85


E Overhead & Profit 10% x D = Rp 13,067.08
F Harga Satuan Pekerjaan (D+E) = Rp 143,737.93

25 A.4.5.2Pemasangan 1 m’ Gording 8/12


A TENAGA
L.01 Pekerja OH 0.084 X Rp 54,000.00 = Rp 4,536.00
L.03 Tukang Kayu OH 0.125 X Rp 68,000.00 = Rp 8,500.00
L.11 Kepala Tukang Kayu OH 0.013 X Rp 69,000.00 = Rp 897.00
L.15 Mandor OH 0.004 X Rp 71,000.00 = Rp 284.00
JUMLAH TENAGA KERJA = Rp 14,217.00
B BAHAN
Nok 8/12 M' 1.000 X Rp 96,153.85 = Rp 96,153.85
Besi strip tebal 5 mm kg 0.200 X Rp 64,000.00 = Rp 12,800.00
Paku sekrup 3.5” Bh 0.500 X Rp 15,000.00 = Rp 7,500.00
JUMLAH HARGA BAHAN = Rp 116,453.85
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 130,670.85


E Overhead & Profit 10% x D = Rp 13,067.08
F Harga Satuan Pekerjaan (D+E) = Rp 143,737.93
NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

25 A.4.5.2Pemasangan 1 m’ Balok Tembok 8/12


A TENAGA
L.01 Pekerja OH 0.084 X Rp 54,000.00 = Rp 4,536.00
L.03 Tukang Kayu OH 0.125 X Rp 68,000.00 = Rp 8,500.00
L.11 Kepala Tukang Kayu OH 0.013 X Rp 69,000.00 = Rp 897.00
L.15 Mandor OH 0.004 X Rp 71,000.00 = Rp 284.00
JUMLAH TENAGA KERJA = Rp 14,217.00
B BAHAN
Nok 8/12 M' 1.000 X Rp 96,153.85 = Rp 96,153.85
Besi strip tebal 5 mm kg 0.100 X Rp 64,000.00 = Rp 6,400.00
Paku sekrup 3.5” Bh 0.500 X Rp 15,000.00 = Rp 7,500.00
JUMLAH HARGA BAHAN = Rp 110,053.85
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 124,270.85


E Overhead & Profit 10% x D = Rp 12,427.08
F Harga Satuan Pekerjaan (D+E) = Rp 136,697.93

25 A.4.5.2Pemasangan 1 m’ Usuk 4/7


A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
L.03 Tukang Kayu OH 0.010 X Rp 68,000.00 = Rp 680.00
L.11 Kepala Tukang Kayu OH 0.013 X Rp 69,000.00 = Rp 897.00
L.15 Mandor OH 0.004 X Rp 71,000.00 = Rp 284.00
JUMLAH TENAGA KERJA = Rp 2,941.00
B BAHAN
Usuk 4/7 M' 0.500 X Rp 32,051.28 = Rp 16,025.64
Paku sekrup usuk Bh 0.200 X Rp 15,000.00 = Rp 3,000.00
JUMLAH HARGA BAHAN = Rp 19,025.64
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 21,966.64


E Overhead & Profit 10% x D = Rp 2,196.66
F Harga Satuan Pekerjaan (D+E) = Rp 24,163.31

25 A.4.5.2Pemasangan 1 m’ Reng 2/3


A TENAGA
L.01 Pekerja OH 0.030 X Rp 54,000.00 = Rp 1,620.00
L.03 Tukang Kayu OH 0.020 X Rp 68,000.00 = Rp 1,360.00
L.11 Kepala Tukang Kayu OH 0.013 X Rp 69,000.00 = Rp 897.00
L.15 Mandor OH 0.004 X Rp 71,000.00 = Rp 284.00
JUMLAH TENAGA KERJA = Rp 4,161.00
B BAHAN
Reng 2/3 M' 0.500 X Rp 5,998.80 = Rp 2,999.40
Paku sekrup usuk Bh 0.200 X Rp 15,000.00 = Rp 3,000.00
JUMLAH HARGA BAHAN = Rp 5,999.40
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 10,160.40


E Overhead & Profit 10% x D = Rp 1,016.04
F Harga Satuan Pekerjaan (D+E) = Rp 11,176.44

30 A.4.5.2Pemasangan 1 m2 genteng tanah liat


A TENAGA
L.01 Pekerja OH 0.200 X Rp 54,000.00 = Rp 10,800.00
L.03 Tukang Kayu OH 0.100 X Rp 68,000.00 = Rp 6,800.00
L.11 Kepala Tukang Kayu OH 0.010 X Rp 69,000.00 = Rp 690.00
L.15 Mandor OH 0.010 X Rp 71,000.00 = Rp 710.00
JUMLAH TENAGA KERJA = Rp 19,000.00
B BAHAN
Genteng beton Bh 11.000 X Rp 4,000.00 = Rp 44,000.00
PAKU - ukuran 1" s/d 4" 2”-5” Kg 0.030 X Rp 15,000.00 = Rp 450.00
JUMLAH HARGA BAHAN = Rp 44,450.00
C PERALATAN
NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 63,450.00


E Overhead & Profit 10% x D = Rp 6,345.00
F Harga Satuan Pekerjaan (D+E) = Rp 69,795.00

5 A.4.5.2 Pemasangan 1 m’ Genteng Bubungan


A TENAGA
L.01 Pekerja OH 0.400 X Rp 54,000.00 = Rp 21,600.00
L.03 Tukang Kayu OH 0.200 X Rp 68,000.00 = Rp 13,600.00
L.11 Kepala Tukang Kayu OH 0.020 X Rp 69,000.00 = Rp 1,380.00
L.15 Mandor OH 0.002 X Rp 71,000.00 = Rp 142.00
JUMLAH TENAGA KERJA = Rp 36,722.00
B BAHAN
Genteng bubung Bh 5.000 X Rp 7,000.00 = Rp 35,000.00
Semen PC Kg 8.000 X Rp #N/A = Rp #N/A
Pasir pasang M3 0.032 X Rp 235,000.00 = Rp 7,520.00
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp #N/A


E Overhead & Profit 10% x D = Rp #N/A
F Harga Satuan Pekerjaan (D+E) = Rp #N/A

22a A.4.6.1Pemasangan 1 m’ listplank wood plank rangkap 2x20 cm


A TENAGA
L.01 Pekerja OH 0.100 X Rp 54,000.00 = Rp 5,400.00
L.03 Tukang Kayu OH 0.200 X Rp 68,000.00 = Rp 13,600.00
L.03 Kepala Tukang Kayu OH 0.020 X Rp 69,000.00 = Rp 1,380.00
L.04 Mandor OH 0.005 X Rp 71,000.00 = Rp 355.00
JUMLAH TENAGA KERJA = Rp 20,735.00
B BAHAN
Wood plank lebar 20 cm m' 2.000 X Rp #N/A = Rp #N/A
PAKU - sekrup dos 0.100 X Rp #N/A = Rp #N/A
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp #N/A


E Overhead & Profit 10% x D = Rp #N/A
F Harga Satuan Pekerjaan = Rp #N/A

I. PEKERJAAN PLAFON
7a A.4.5.1Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm. tebal 9 mm + rangka hollow
A TENAGA
L.01 Pekerja OH 0.250 X Rp 54,000.00 = Rp 13,500.00
L.02 Tukang Kayu OH 0.300 X Rp 68,000.00 = Rp 20,400.00
L.03 Kepala tukang OH 0.035 X Rp 69,000.00 = Rp 2,415.00
L.04 Mandor OH 0.080 X Rp 71,000.00 = Rp 5,680.00
JUMLAH TENAGA KERJA = Rp 41,995.00
B BAHAN
Gypsum tebal 9 mm Lembar 0.364 X Rp 18,000.00 = Rp 6,552.00
Hollow 4/4 tebal 0,50 mm m 4.000 X Rp 41,000.00 = Rp 164,000.00
PAKU - sekrup dos 0.110 X Rp #N/A = Rp #N/A
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) #N/A


E Overhead & Profit 10% x D #N/A
F Harga Satuan Pekerjaan = Rp #N/A

J. PENUTUP LANTAI
4 A.4.4.3Pemasangan 1m2 lantai ubin warna ukuran 40cm x40 cm
A TENAGA
L.01 Pekerja OH 0.250 X Rp 54,000.00 = Rp 13,500.00
L.02 Tukang Batu OH 0.125 X Rp 66,000.00 = Rp 8,250.00
NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

L.03 Kepala tukang OH 0.013 X Rp 69,000.00 = Rp 897.00


L.04 Mandor OH 0.013 X Rp 71,000.00 = Rp 923.00
JUMLAH TENAGA KERJA = Rp 23,570.00
B BAHAN
Ubin warna Bh 6.630 X Rp 15,250.00 = Rp 101,107.50
Semen PC kg 9.800 X Rp 1,000.00 = Rp 9,800.00
Semen warna Kg 1.300 X Rp #N/A = Rp #N/A
Pasir pasang M3 0.045 X Rp 235,000.00 = Rp 10,575.00
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) #N/A


E Overhead & Profit 10% x D #N/A
F Harga Satuan Pekerjaan (D+E) = Rp #N/A

21 A.4.4.3Pemasangan 1 m’ plint ubin warna ukuran 10cm x 40cm


A TENAGA
L.01 Pekerja OH 0.090 X Rp 54,000.00 = Rp 4,860.00
L.02 Tukang Batu OH 0.090 X Rp 66,000.00 = Rp 5,940.00
L.03 Kepala tukang OH 0.009 X Rp 69,000.00 = Rp 621.00
L.04 Mandor OH 0.005 X Rp 71,000.00 = Rp 355.00
JUMLAH TENAGA KERJA = Rp 11,776.00
B BAHAN
Plint ubin warna Bh 2.650 X Rp - = Rp -
Semen PC kg 1.140 X Rp 1,000.00 = Rp 1,140.00
Semen warna Kg 0.100 X Rp 11,000.00 = Rp 1,100.00
Pasir pasang M3 0.003 X Rp 235,000.00 = Rp 705.00
JUMLAH HARGA BAHAN = Rp 2,945.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 14,721.00


E Overhead & Profit 10% x D 1,472.10
F Harga Satuan Pekerjaan (D+E) = Rp 16,193.10

58 A.4.4.3Pemasangan 1 m2 dinding batu tempel hitam


A TENAGA
L.01 Pekerja OH 0.500 X Rp 54,000.00 = Rp 27,000.00
L.02 Tukang Batu OH 0.350 X Rp 66,000.00 = Rp 23,100.00
L.03 Kepala tukang OH 0.030 X Rp 69,000.00 = Rp 2,070.00
L.04 Mandor OH 0.035 X Rp 71,000.00 = Rp 2,485.00
JUMLAH TENAGA KERJA = Rp 54,655.00
B BAHAN
Batu temple hitam Bh 1.100 X Rp 10,000.00 = Rp 11,000.00
Semen PC Kg 11.750 X Rp 1,000.00 = Rp 11,750.00
Pasir Pasang M3 0.035 X Rp 235,000.00 = Rp 8,225.00
JUMLAH HARGA BAHAN = Rp 30,975.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) 85,630.00


E Overhead & Profit 10% x D 8,563.00
F Harga Satuan Pekerjaan = Rp 94,193.00

K. PEKERJAAN PENGECATAN
10 A.4.7.1Pengecatan 1 m2 tembok baru ( 1lapis plamuur. 1 lapis cat dasar. 2 lapis cat penutup)
A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
L.02 Tukang Cat OH 0.063 X Rp 66,000.00 = Rp 4,158.00
L.03 Kepala tukang OH 0.006 X Rp 69,000.00 = Rp 434.70
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 5,885.70
B BAHAN
Plamur Kg 0.100 X Rp #N/A = Rp #N/A
Catylac Kg 0.100 X Rp 6,800.00 = Rp 680.00
Catylac Kg 0.260 X Rp 6,800.00 = Rp 1,768.00
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN
NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp #N/A


E Overhead & Profit 10% x D = Rp #N/A
F Harga Satuan Pekerjaan = Rp #N/A

4 A.4.7.11 m2 Pengecatan bidang kayu baru (1 lapis plamuur. 1 lapis cat dasar. 2 lapis cat penutup)
A TENAGA
L.01 Pekerja OH 0.070 X Rp 54,000.00 = Rp 3,780.00
L.02 Tukang Cat OH 0.009 X Rp 66,000.00 = Rp 594.00
L.03 Kepala tukang OH 0.006 X Rp 69,000.00 = Rp 414.00
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 5,001.00
B BAHAN
Meni kayu Kg 0.200 X Rp 12,600.00 = Rp 2,520.00
Dempul plamur Kg 0.150 X Rp 29,000.00 = Rp 4,350.00
Cat dasar (Menni) Kg 0.170 X Rp 12,600.00 = Rp 2,142.00
Cat Kayu Kg 0.260 X Rp 57,500.00 = Rp 14,950.00
Kuas Bh 0.010 X Rp #N/A = Rp #N/A
Thinner Super Kg 0.030 X Rp - = Rp -
Ambril/ amplas Lbr 0.200 X Rp 57,500.00 = Rp 11,500.00
JUMLAH HARGA BAHAN = Rp #N/A
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp #N/A


E Overhead & Profit 10% x D = Rp #N/A
F Harga Satuan Pekerjaan (D+E) = Rp #N/A

L. PEKERJAAN PENGUNCI
10 A.4.7.1Pasang 1bh handel pintu
A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
L.02 Tukang Kayu OH 0.063 X Rp 68,000.00 = Rp 4,284.00
L.03 Kepala tukang OH 0.006 X Rp 69,000.00 = Rp 434.70
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 6,011.70
B BAHAN
handel bh 1.000 X Rp 235,000.00 = Rp 235,000.00
JUMLAH HARGA BAHAN = Rp 235,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 241,011.70


E Overhead & Profit 10% x D = Rp 24,101.17
F Harga Satuan Pekerjaan = Rp 265,112.87

10 A.4.7.1Pasang 1bh pengunci tanam


A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
L.02 Tukang Kayu OH 0.063 X Rp 68,000.00 = Rp 4,284.00
L.03 Kepala tukang OH 0.006 X Rp 69,000.00 = Rp 434.70
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 6,011.70
B BAHAN
pengunci tanam bh 1.000 X Rp 185,000.00 = Rp 185,000.00
JUMLAH HARGA BAHAN = Rp 185,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 191,011.70


E Overhead & Profit 10% x D = Rp 19,101.17
F Harga Satuan Pekerjaan = Rp 210,112.87

10 A.4.7.1Pasang 1bh engsel pintu 5"


A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

L.02 Tukang Kayu OH 0.063 X Rp 68,000.00 = Rp 4,284.00


L.03 Kepala tukang OH 0.006 X Rp 69,000.00 = Rp 434.70
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 6,011.70
B BAHAN
Engsel pintu 5" bh 1.000 X Rp 149,000.00 = Rp 149,000.00
JUMLAH HARGA BAHAN = Rp 149,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 155,011.70


E Overhead & Profit 10% x D = Rp 15,501.17
F Harga Satuan Pekerjaan = Rp 170,512.87

10 A.4.7.1Pasang 1bh engsel jendela 4"


A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
L.02 Tukang Kayu OH 0.063 X Rp 68,000.00 = Rp 4,284.00
L.03 Kepala tukang OH 0.006 X Rp 69,000.00 = Rp 434.70
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 6,011.70
B BAHAN
Engsel jendela 4" bh 1.000 X Rp 5,000.00 = Rp 5,000.00
JUMLAH HARGA BAHAN = Rp 5,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 11,011.70


E Overhead & Profit 10% x D = Rp 1,101.17
F Harga Satuan Pekerjaan = Rp 12,112.87

10 A.4.7.1Pasang 1M2 kaca 5 mm (polos, es kabur, ray band)


A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
L.02 Tukang Kayu OH 0.063 X Rp 68,000.00 = Rp 4,284.00
L.03 Kepala tukang OH 0.006 X Rp 69,000.00 = Rp 434.70
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 6,011.70
B BAHAN
kaca 5mm bh 1.000 X Rp 190,000.00 = Rp 190,000.00
JUMLAH HARGA BAHAN = Rp 190,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 196,011.70


E Overhead & Profit 10% x D = Rp 19,601.17
F Harga Satuan Pekerjaan = Rp 215,612.87

M. PEKERJAAN LISTRIK
10 A.4.7.1Pasang 1M' Pemasangan kabel NYA
A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
L.02 Tukang Listrik OH 0.063 X Rp 66,000.00 = Rp 4,158.00
L.03 Kepala tukang OH 0.006 X Rp 66,000.00 = Rp 415.80
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 5,866.80
B BAHAN
Kabel NYA m' 1.000 X Rp 5,400.00 = Rp 5,400.00
JUMLAH HARGA BAHAN = Rp 5,400.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 11,266.80


E Overhead & Profit 10% x D = Rp 1,126.68
F Harga Satuan Pekerjaan = Rp 12,393.48

10 A.4.7.1Pasang 1bh skakelar


NO / KODE URAIAN PEKERJAAN SATUAN KOEFISIEN HARGA SATUAN (Rp) JUMLAH HARGA (Rp)

A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
L.02 Tukang Listrik OH 0.063 X Rp 66,000.00 = Rp 4,158.00
L.03 Kepala tukang OH 0.006 X Rp 66,000.00 = Rp 415.80
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 5,866.80
B BAHAN
skakelar bh 1.000 X Rp 19,000.00 = Rp 19,000.00
JUMLAH HARGA BAHAN = Rp 19,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 24,866.80


E Overhead & Profit 10% x D = Rp 2,486.68
F Harga Satuan Pekerjaan = Rp 27,353.48

10 A.4.7.1Pasang 1bh titik lampu


A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
L.02 Tukang Listrik OH 0.063 X Rp 66,000.00 = Rp 4,158.00
L.03 Kepala tukang OH 0.006 X Rp 66,000.00 = Rp 415.80
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 5,866.80
B BAHAN
lampu bh 1.000 X Rp 18,000.00 = Rp 18,000.00
JUMLAH HARGA BAHAN = Rp 18,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 23,866.80


E Overhead & Profit 10% x D = Rp 2,386.68
F Harga Satuan Pekerjaan = Rp 26,253.48

10 A.4.7.1Pasang 1bh fiting


A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
L.02 Tukang Listrik OH 0.063 X Rp 66,000.00 = Rp 4,158.00
L.03 Kepala tukang OH 0.006 X Rp 66,000.00 = Rp 415.80
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 5,866.80
B BAHAN
fiting lampu bh 1.000 X Rp 7,000.00 = Rp 7,000.00
JUMLAH HARGA BAHAN = Rp 7,000.00
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 12,866.80


E Overhead & Profit 10% x D = Rp 1,286.68
F Harga Satuan Pekerjaan = Rp 14,153.48

10 A.4.7.1Pasang 1bh stop kontak


A TENAGA
L.01 Pekerja OH 0.020 X Rp 54,000.00 = Rp 1,080.00
L.02 Tukang Listrik OH 0.063 X Rp 66,000.00 = Rp 4,158.00
L.03 Kepala tukang OH 0.006 X Rp 66,000.00 = Rp 415.80
L.04 Mandor OH 0.003 X Rp 71,000.00 = Rp 213.00
JUMLAH TENAGA KERJA = Rp 5,866.80
B BAHAN
stop kontak bh 1.000 X Rp - = Rp -
JUMLAH HARGA BAHAN = Rp -
C PERALATAN

JUMLAH HARGA ALAT

D Jumlah (A+B+C) = Rp 5,866.80


E Overhead & Profit 10% x D = Rp 586.68
F Harga Satuan Pekerjaan = Rp 6,453.48
VOLUME PEKERJAAN
PEKERJAAN : PEMBANGUNAN RUMAH TINGGAL
ALAMAT
PERIODE : 12 NOVEMBER 2018

DIMENSI
VOLUME/
NO JENIS PEKERJAAN SAT
PANJANG LEBAR TEBAL LUAS

1 2 3 4 5 6 7
A. PEKERJAAN PERSIAPAN
1 Pembersihan 1 m2 lapangan dan perataan m² 120.00
2 Pengukuran dan pemasangan 1 m’ Bouwplank m² 120.00

B. PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m M³ 79.80
2 Pengurugan 1 m3 dengan pasir urug M³ 7.98
3 Pemasangan 1 m3 batu kosong (anstamping) M³ 15.96
4 Pengurugan 1 m3 urugan tanah kembali M³ 26.60

C. PEKERJAAN PONDASI
1 Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5Pasir Pasang M³ 28.73

D. PEKERJAAN BETON
1 Membuat 1 m’ Sloof beton bertulang (15 x 20) cm m 2.79
2 Membuat 1 m’ kolom beton bertulang (15 x 25) cm m 1.98
3 Membuat 1 m’ Ring Balk beton bertulang (15 x 20) cm m 1.27
4 Membuat 1 m’ Atap dak (beton)10cm m 16.00

E. PEKERJAAN DINDING
1 Pemasangan 1m2 dinding bata merah (5x11x22) cm tebal ½ batu campuran 1SP :4Pasir Pasang m2 -
2 Pemasangan 1m2 dinding bata merah (5x11x22)cm tebal ½ batu campuran 1SP :8Pasir Pasang m2 339.80

F. PEKERJAAN PLESTERAN
1 Pemasangan 1 m2 plesteran 1SP : 4Pasir Pasang tebal 15 mm m² 679.60
2 Acian m² 679.60
3 Dinding Keramik m² 4.95

G. PEKERJAAN KAYU
1 Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela. kayu kelas II m3 0.40
2 Pembuatan dan pemasangan 1 m2 daun pintu panel. kayu kelas II m2 9.56
3 Pembuatan dan pemasangan 1 m2 jendela kaca. kayu kelas II m² 4.20

H. PEKERJAAN ATAP
1 Pemasangan 1 m3 konstruksi kuda-kuda konvensional. kayu kelas II M³ 0.63
2 Pemasangan 1 m’ Nok 8/12 m' 15.27
3 Pemasangan 1 m’ Gording 8/12 m' 23.56
4 Pemasangan 1 m’ Balok Tembok 8/12 m' 21.00
5 Pemasangan 1 m’ Usuk 4/7 m' 210.00
6 Pemasangan 1 m’ Reng 2/3 m' 400.00
7 Pemasangan 1 m2 genteng tanah liat m2 87.67
8 Pemasangan 1 m’ Genteng Bubungan m' 23.28
9 Pemasangan 1 m’ listplank wood plank rangkap 2x20 cm m' 20.70

I. PEKERJAAN PLAFON
1 Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm. tebal 9 mm + rangka hollow m² 60.12

J. PENUTUP LANTAI
1 Pemasangan 1m2 lantai ubin warna ukuran 40cm x40 cm m² 55.06
2 Pemasangan 1 m’ plint ubin warna ukuran 10cm x 40cm m1 71.74

K. PEKERJAAN PENGECATAN
DIMENSI
VOLUME/
NO JENIS PEKERJAAN SAT
PANJANG LEBAR TEBAL LUAS

1 2 3 4 5 6 7
1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur. 1 lapis cat dasar. 2 lapis cat penutup) m² 674.65
2 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur. 1 lapis cat dasar. 2 lapis cat penutup) m² 11.57

L. PEKERJAAN PENGUNCI
1 Pasang 1bh handel pintu bh 6.00
2 Pasang 1bh pengunci tanam bh 12.00
3 Pasang 1bh engsel pintu 5" bh 18.00
4 Pasang 1bh engsel jendela 4" bh 18.00
5 Pasang 1M2 kaca 5 mm (polos, es kabur, ray band) m² 2.57

M. PEKERJAAN LISTRIK
1 Pasang 1M' Pemasangan kabel NYA m' 5.00
2 Pasang 1bh skakelar bh 10.00
3 Pasang 1bh titik lampu bh 14.00
4 Pasang 1bh fiting bh 14.00
5 Pasang 1bh stop kontak bh 7.00
RENCANA ANGGARAN BIAYA

PEKERJAAN PEMBANGUNAN RUMAH TINGGAL

VOLUM
E SAT. HARGA SATUAN
NO JENIS PEKERJAAN HARGA TOTAL SUB. TOTAL
PEKER PEK. PEKERJA
JAAN
1 2 3 4
A. PEKERJAAN PERSIAPAN #N/A
2 Pembersihan 1 m2 lapangan dan perataan 120.00 m² Rp 9,845.00 Rp 1,181,400.00
3 Pengukuran dan pemasangan 1 m’ Bouwplank 120.00 m² #N/A #N/A

B. PEKERJAAN TANAH Rp 13,323,043.58


1 Penggalian 1 m3 tanah biasa sedalam 1 m 79.80 M³ Rp 46,502.50 Rp 3,710,899.50
2 Pengurugan 1 m3 dengan pasir urug 7.98 M³ Rp 236,401.00 Rp 1,886,479.98
3 Pemasangan 1 m3 batu kosong (anstamping) 15.96 M³ Rp 456,060.00 Rp 7,278,717.60
4 Pengurugan 1 m3 urugan tanah kembali 26.60 M³ Rp 16,802.50 Rp 446,946.50

C. PEKERJAAN PONDASI Rp 21,325,483.87


1 Pemasangan 1 m3 pondasi batu belah campuran 1S 28.728 M³ Rp 742,324.00 Rp 21,325,483.87

D. PEKERJAAN BETON #N/A


1 Membuat 1 m’ Sloof beton bertulang (15 x 20) cm 2.79 m' #N/A #N/A
2 Membuat 1 m’ kolom beton bertulang (15 x 25) cm 1.98 m' #N/A #N/A
3 Membuat 1 m’ Ring Balk beton bertulang (15 x 20) 1.27 m' #N/A #N/A
4 Membuat 1 m’ Atap dak (beton)10cm 16.00 m² #N/A #N/A
E. PEKERJAAN DINDING Rp 34,314,872.90
1 Pemasangan 1m2 dinding bata merah (5x11x22) cm 0.00 m² Rp 104,676.00 Rp -
2 Pemasangan 1m2 dinding bata merah (5x11x22)cm t 339.80 m² Rp 100,985.50 Rp 34,314,872.90

F. PEKERJAAN PLESTERAN Rp 29,962,204.80


1 Pemasangan 1 m2 plesteran 1SP : 4Pasir Pasang t 679.60 m² Rp 44,088.00 Rp 29,962,204.80

G. PEKERJAAN KAYU #N/A


1 Pembuatan dan pemasangan 1 m3 kusen pintu dan ku 0.40 m² #N/A #N/A
2 Pembuatan dan pemasangan 1 m2 daun pintu panel. 9.56 m² Rp 794,475.00 Rp 7,595,181.00
3 Pembuatan dan pemasangan 1 m2 jendela kaca. kayu 4.20 m² Rp 538,780.00 Rp 2,262,876.00

H. PEKERJAAN ATAP #N/A


1 Pemasangan 1 m3 konstruksi kuda-kuda konvensional 0.63 M³ #N/A #N/A
2 Pemasangan 1 m’ Nok 8/12 15.27 m' Rp 143,737.93 Rp 2,194,878.20
3 Pemasangan 1 m’ Gording 8/12 23.56 m' Rp 143,737.93 Rp 3,386,465.65
4 Pemasangan 1 m’ Balok Tembok 8/12 21.00 m' Rp 143,737.93 Rp 3,018,496.55
5 Pemasangan 1 m’ Usuk 4/7 210.00 m' Rp 24,163.31 Rp 5,074,294.08
6 Pemasangan 1 m’ Reng 2/3 400.00 m' Rp 11,176.44 Rp 4,470,576.05
7 Pemasangan 1 m2 genteng tanah liat 87.67 m' Rp 69,795.00 Rp 6,119,067.24
8 Pemasangan 1 m’ Genteng Bubungan 23.28 m' #N/A #N/A
9 Pemasangan 1 m’ listplank wood plank rangkap 2x2 20.70 m' #N/A #N/A

I. PEKERJAAN PLAFON #N/A


1 Pemasangan 1 m2 langit-langit gypsum board ukura 60.12 m² #N/A #N/A

J. PENUTUP LANTAI #N/A


1 Pemasangan 1m2 lantai ubin warna ukuran 40cm x 55.0586 m² #N/A #N/A
2 Pemasangan 1 m’ plint ubin warna ukuran 10cm x 4 71.74 m Rp 16,193.10 Rp 1,161,692.99

K. PEKERJAAN PENGECATAN #N/A


1 Pengecatan 1 m2 tembok baru ( 1lapis plamuur. 1 lapi 674.65 m² #N/A #N/A
2 1 m2 Pengecatan bidang kayu baru (1 lapis plamuur. 111.5664 m² #N/A #N/A

L. PEKERJAAN PENGUNCI Rp 7,954,066.89


1 Pasang 1bh handel pintu 6 bh Rp 265,112.87 Rp 1,590,677.22
2 Pasang 1bh pengunci tanam 12 bh Rp 210,112.87 Rp 2,521,354.44
3 Pasang 1bh engsel pintu 5" 18 bh Rp 170,512.87 Rp 3,069,231.66
4 Pasang 1bh engsel jendela 4" 18 bh Rp 12,112.87 Rp 218,031.66
5 Pasang 1M2 kaca 5 mm (polos, es kabur, ray band) 2.573 m² Rp 215,612.87 Rp 554,771.91

M. PEKERJAAN LISTRIK Rp 946,374.00


1 Pasang 1M' Pemasangan kabel NYA 5 m' Rp 12,393.48 Rp 61,967.40
2 Pasang 1bh skakelar 10 bh Rp 27,353.48 Rp 273,534.80
3 Pasang 1bh titik lampu 14 bh Rp 26,253.48 Rp 367,548.72
4 Pasang 1bh fiting 14 bh Rp 14,153.48 Rp 198,148.72
5 Pasang 1bh stop kontak 7 bh Rp 6,453.48 Rp 45,174.36

TOTAL #N/A
#DIV/0!
#N/A
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#N/A
#N/A
#N/A
#N/A
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#N/A
#N/A
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#N/A
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#N/A
#N/A
#DIV/0!
#DIV/0!
#N/A
#DIV/0!
#DIV/0!
#N/A
#DIV/0!
#DIV/0!
#DIV/0!
#N/A
#N/A
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
#DIV/0!
REKAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN PEMBANGUNAN RUMAH TINGGAL

NO JENIS PEKERJAAN HARGA (Rp)

1 2 3
I A. PEKERJAAN PERSIAPAN #N/A
II B. PEKERJAAN TANAH Rp 13,323,043.58
III C. PEKERJAAN PONDASI Rp 21,325,483.87
IV D. PEKERJAAN BETON #N/A
V E. PEKERJAAN DINDING Rp 34,314,872.90
VI F. PEKERJAAN PLESTERAN Rp 29,962,204.80
VII G. PEKERJAAN KAYU #N/A
VIII H. PEKERJAAN ATAP #N/A
IX I. PEKERJAAN PLAFON #N/A
X J. PENUTUP LANTAI #N/A
XI K. PEKERJAAN PENGECATAN #N/A
XII L. PEKERJAAN PENGUNCI Rp 7,954,066.89
XIII M. PEKERJAAN LISTRIK Rp 946,374.00

Jumlah Biaya Fisik Bangunan


A (Jumlah I s.d XIII) #N/A

B Jumlah biaya Penyediaan Perabot Rp 16,000,000.00


Biaya Oprasional TPPP 2% dari
C Biaya Fisik Bangunan (A) #N/A
Biaya Oprasional Tim Teknis 4% dari
D Biaya Fisik Bangunan (A) #N/A
Total Biaya A+B+C+D #N/A

PEMBULATAN Rp 239,000,000.00

DUA RATUS TIGA PULUH SEMBILAN JUTA RUPIAH

Mengetahui
`Wonogiri, 12
Nopember 2018
Dibuat oleh

Eni Pujiati, SPd.


Eni Pujiati, SPd.
Eni Pujiati, SPd.
KAPITULASI RENCANA ANGGARAN BIAYA
PEKERJAAN PEMBANGUNAN RUMAH TINGGAL

NO JENIS PEKERJAAN HARGA (Rp) MINGGU KE


BOBOT 1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4
I A. PEKERJAAN PERSIAPAN #N/A #N/A 1.8 1.8
II B. PEKERJAAN TANAH Rp 13,323,043.58 #N/A 3.3 3.3
III C. PEKERJAAN PONDASI Rp 21,325,483.87 #N/A 5.15 5.15
IV D. PEKERJAAN BETON #N/A #N/A 1.7 1.7
V E. PEKERJAAN DINDING Rp 34,314,872.90 #N/A 4.175 8.35 4.175
VI F. PEKERJAAN PLESTERAN Rp 29,962,204.80 #N/A 5 5 5
VII G. PEKERJAAN KAYU #N/A #N/A 2.5 2.5 2.5
VIII H. PEKERJAAN ATAP #N/A #N/A 5.73 5.73 5.73
IX I. PEKERJAAN PLAFON #N/A #N/A 3.4 3.4
X J. PENUTUP LANTAI #N/A #N/A 2.6 2.6
XI K. PEKERJAAN PENGECATAN #N/A #N/A 1.75 1.75
XII L. PEKERJAAN PENGUNCI Rp 7,954,066.89 #N/A 1.9 1.9
XIII M. PEKERJAAN LISTRIK Rp 946,374.00 #N/A 0.5
JUMLAH #N/A #N/A
PROGRES MINGGUINI 0 1.8 5.1 8.45 11.025 17.55 17.405 13.23 9.13 6 4.35 3.65 2.4
PROGRES KOMULATIF MINGGU INI 0 1.8 6.9 15.35 26.375 43.925 61.33 74.56 83.69 89.69 94.04 97.69 100.09

Mengetahui Wonogiri, 12 Nopember 2018


Dibuat oleh
Eni Pujiati, SPd.
KURVA 'S' KURVA S

NO JENIS PEKERJAAN HARGA ( Rp) BOBOT (%)

1 2 3 4
I A. PEKERJAAN PERSIAPAN Rp 7,569,870.00 3.6%
II B. PEKERJAAN TANAH Rp 13,915,669.77 6.6%
III C. PEKERJAAN PONDASI Rp 21,656,107.24 10.3%
IV D. PEKERJAAN BETON Rp 7,076,501.59 3.4%
V E. PEKERJAAN DINDING Rp 35,093,269.75 16.7%
VI F. PEKERJAAN PLESTERAN Rp 31,560,114.30 15.0%
VII G. PEKERJAAN KAYU Rp 15,823,318.78 7.5%
VIII H. PEKERJAAN ATAP Rp 36,129,782.74 17.2%
IX I. PEKERJAAN PLAFON Rp 14,387,992.85 6.8%
X J. PEKERJAAN LANTAI Rp 10,936,091.97 5.2%
XI K. PEKERJAAN PENGECATAN Rp 7,333,157.76 3.5%
XII L. PEKERJAAN PENGUNCI Rp 7,980,471.21 3.8%
XII M. PEKERJAAN LISTRIK Rp 955,677.25 0.5%
JUMLAH Rp 210,418,025.21 100%
PROGRES MINGGU INI 0
PROGRES KOMULATIF MINGGU INI 0
MINGGU KE

1 2 3 4 5 6 7 8 9

1.8 1.8
3.3 3.3
5.15 5.15
1.7 1.7
4.175 8.35 4.175
5 5 5
2.5 2.5 2.5
5.73 5.73 5.73
3.4 3.4
2.6

1.8 5.1 8.45 11.025 17.55 17.405 13.23 9.13 6


1.8 6.9 15.35 26.375 43.925 61.33 74.56 83.69 89.69
10 11 12

2.6
1.75 1.75
1.9 1.9
0.5

4.35 3.65 2.4


94.04 97.69 100.09

You might also like