Professional Documents
Culture Documents
0243-Methodology (Repair of Pot Hole)
0243-Methodology (Repair of Pot Hole)
1 Scope : This work shall include repair of Pot Holes of all types of
bituminous/concrete surface with Semi Dense Bituminous Concrete as
per MOST specification. The mix will either be produced at plant site
or at the site itself with manual method of mixing and placed at site in
the Pot Holes after trimming the Pot Hole to proper shape and depth,
side painting with tack coat and compacting the layer to the levels
specified in the drawing.
2 Materials : The materials used for the Pot Holes should be as per
the contract.
3 Binder
4 Coarse Aggregate
5 Fine Aggregate
6 Filler
7 Aggregate grading
All The minerals aggregates including filler shall be combined as
to confirm to the grading as per MOST specification
*****
Page 2 of 2