Littlefield Technologies Processing Times Data

Below are the start and finish times associated with processing batches of 60 kits. (The times are only for processing; "queueing time" is not included.)
At each step, the times are given for a single machine.

Station 1, Step 1 Station 2, Step 2 Station 3, Step 3 Station 2, Step 4


Start Time Finish Time Start Time Finish Time Start Time Finish Time Start Time Finish Time
8:03:00 AM 1:22:08 PM 8:03:00 AM 8:33:31 AM 8:00:00 AM 8:29:45 AM 8:04:00 AM 9:29:20 AM
1:22:08 PM 6:40:35 PM 8:33:31 AM 9:06:27 AM 8:29:45 AM 8:41:30 AM 9:29:20 AM 10:55:35 AM
6:40:35 PM 12:00:27 AM 9:06:27 AM 9:37:13 AM 8:41:30 AM 9:20:15 AM 10:55:35 AM 12:22:20 PM
12:00:27 AM 5:19:08 AM 9:37:13 AM 10:09:32 AM 9:20:15 AM 9:31:39 AM 12:22:20 PM 1:46:39 PM
5:19:08 AM 10:41:04 AM 10:09:32 AM 10:40:54 AM 9:31:39 AM 3:29:28 PM 1:46:39 PM 3:13:07 PM
10:41:04 AM 4:04:08 PM 10:40:54 AM 11:12:35 AM 3:29:28 PM 4:02:36 PM 3:13:07 PM 4:37:45 PM
4:04:08 PM 9:24:41 PM 11:12:35 AM 11:43:22 AM 4:02:36 PM 8:29:18 PM 4:37:45 PM 6:04:22 PM
9:24:41 PM 2:46:50 AM 11:43:22 AM 12:13:57 PM 8:29:18 PM 10:59:55 PM 6:04:22 PM 7:29:15 PM