You are on page 1of 21

2019/6/1 Assignment 2 -Due Friday May 24 at 23:59

Home ► My courses ► ENGR-301-2191-AA ► Topic 2 ► Assignment 2 -Due Friday May 24 at 23:59

Started on Friday, 24 May 2019, 5:16 PM


State Finished
Completed on Friday, 24 May 2019, 5:43 PM
Time taken 26 mins 48 secs
Grade 7.00 out of 10.00 (70%)

Question 1 Make sure you review the Faculty of Engineering and Computer Science Expectations
Complete of Originality and standards of academic integrity, available at
http://www.concordia.ca/content/dam/encs/docs/Expectations-of-Originality-Feb14-
Not graded
2012.pdf.
I certify that I have conformed to the Faculty’s Expectations of Originality and standards
of academic integrity.

Note: By answering this question, you effectively sign the form and submit it
electronically. There is thus no need to submit a printed copy.

Select one:
Yes

No

The correct answer is: Yes

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 1/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
Question 2
Given a project with the following set of activities:
Correct
Activity
Mark 1.00 out of
Number Description Duration Predecessors
1.00
1 Activity A 6 --
2 Activity B 2 --
3 Activity C 3 A
4 Activity D 2 B
5 Activity E 4 B
6 Activity F 1 C
7 Activity G 3 C,D
8 Activity H 6 D,E
9 Activity I 3 F,G
10 Activity J 3 G,H
11 Activity K 1 H
12 Activity L 2 I,J
13 Activity M 3 K
14 Activity N 4 L,M

The Activity on the Node network diagram for this project is

Find ES, EF, LS, LF and F for all the activities in the diagram and answer the following
question:
What is EF of activity G?

Select one:
5

9
https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 2/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
11

13

other

The completed AON is

The correct answer is: other

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 3/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
Question 3
Given a project with the following set of activities:
Correct
Activity
Mark 1.00 out of
Number Description Duration Predecessors
1.00
1 Activity A 6 --
2 Activity B 2 --
3 Activity C 3 A
4 Activity D 2 B
5 Activity E 4 B
6 Activity F 1 C
7 Activity G 3 C,D
8 Activity H 6 D,E
9 Activity I 3 F,G
10 Activity J 3 G,H
11 Activity K 1 H
12 Activity L 2 I,J
13 Activity M 3 K
14 Activity N 4 L,M

The Activity on the Node network diagram for this project is

Find ES, EF, LS, LF and F for all the activities in the diagram and answer the following
question:
What is ES of activity H?

Select one:
2
4

6
https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 4/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
8

10

other

The completed AON is

The correct answer is: 6

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 5/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
Question 4
Given a project with the following set of activities:
Correct
Activity
Mark 1.00 out of
Number Description Duration Predecessors
1.00
1 Activity A 6 --
2 Activity B 2 --
3 Activity C 3 A
4 Activity D 2 B
5 Activity E 4 B
6 Activity F 1 C
7 Activity G 3 C,D
8 Activity H 6 D,E
9 Activity I 3 F,G
10 Activity J 3 G,H
11 Activity K 1 H
12 Activity L 2 I,J
13 Activity M 3 K
14 Activity N 4 L,M

The Activity on the Node network diagram for this project is

Find ES, EF, LS, LF and F for all the activities in the diagram and answer the following
question:
What is the total project duration?

Select one:
17

19

21
https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 6/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
31

43

other

The completed AON is

The correct answer is: 21

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 7/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
Question 5
Given a project with the following set of activities:
Correct
Activity
Mark 1.00 out of
Number Description Duration Predecessors
1.00
1 Activity A 6 --
2 Activity B 2 --
3 Activity C 3 A
4 Activity D 2 B
5 Activity E 4 B
6 Activity F 1 C
7 Activity G 3 C,D
8 Activity H 6 D,E
9 Activity I 3 F,G
10 Activity J 3 G,H
11 Activity K 1 H
12 Activity L 2 I,J
13 Activity M 3 K
14 Activity N 4 L,M

The Activity on the Node network diagram for this project is

Find ES, EF, LS, LF and F for all the activities in the diagram and answer the following
question:
What is LF of activity J?

Select one:
12

13

14
https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 8/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
15

16

other

The completed AON is

The correct answer is: 15

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 9/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
Question 6
Given a project with the following set of activities:
Incorrect
Activity
Mark 0.00 out of
Number Description Duration Predecessors
1.00
1 Activity A 6 --
2 Activity B 2 --
3 Activity C 3 A
4 Activity D 2 B
5 Activity E 4 B
6 Activity F 1 C
7 Activity G 3 C,D
8 Activity H 6 D,E
9 Activity I 3 F,G
10 Activity J 3 G,H
11 Activity K 1 H
12 Activity L 2 I,J
13 Activity M 3 K
14 Activity N 4 L,M

The Activity on the Node network diagram for this project is

Find ES, EF, LS, LF and F for all the activities in the diagram and answer the following
question:
What is LS of activity D?

Select one:
5

3
https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 10/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
2

other

The completed AON is

The correct answer is: 4

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 11/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
Question 7
Given a project with the following set of activities:
Correct
Activity
Mark 1.00 out of
Number Description Duration Predecessors
1.00
1 Activity A 6 --
2 Activity B 2 --
3 Activity C 3 A
4 Activity D 2 B
5 Activity E 4 B
6 Activity F 1 C
7 Activity G 3 C,D
8 Activity H 6 D,E
9 Activity I 3 F,G
10 Activity J 3 G,H
11 Activity K 1 H
12 Activity L 2 I,J
13 Activity M 3 K
14 Activity N 4 L,M

The Activity on the Node network diagram for this project is

Find ES, EF, LS, LF and F for all the activities in the diagram and answer the following
question:
What is Float of activity J?

Select one:
0
1

2
https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 12/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
3

4
other

The completed AON is

The correct answer is: 0

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 13/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
Question 8
Given a project with the following set of activities:
Correct
Activity
Mark 1.00 out of
Number Description Duration Predecessors
1.00
1 Activity A 6 --
2 Activity B 2 --
3 Activity C 3 A
4 Activity D 2 B
5 Activity E 4 B
6 Activity F 1 C
7 Activity G 3 C,D
8 Activity H 6 D,E
9 Activity I 3 F,G
10 Activity J 3 G,H
11 Activity K 1 H
12 Activity L 2 I,J
13 Activity M 3 K
14 Activity N 4 L,M

The Activity on the Node network diagram for this project is

Find ES, EF, LS, LF and F for all the activities in the diagram and answer the following
question:
What is Float of activity F?

Select one:
0
1

2
https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 14/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
3

4
other

The completed AON is

The correct answer is: 2

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 15/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
Question 9
Given a project with the following set of activities:
Correct
Activity
Mark 1.00 out of
Number Description Duration Predecessors
1.00
1 Activity A 6 --
2 Activity B 2 --
3 Activity C 3 A
4 Activity D 2 B
5 Activity E 4 B
6 Activity F 1 C
7 Activity G 3 C,D
8 Activity H 6 D,E
9 Activity I 3 F,G
10 Activity J 3 G,H
11 Activity K 1 H
12 Activity L 2 I,J
13 Activity M 3 K
14 Activity N 4 L,M

The Activity on the Node network diagram for this project is

Find ES, EF, LS, LF and F for all the activities in the diagram and answer the following
question:
What is ES of activity N?

Select one:
15
17

19
https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 16/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
25

36
other

The completed AON is

The correct answer is: 17

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 17/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
Question 10
Given a project with the following set of activities:
Incorrect
Activity
Mark 0.00 out of
Number Description Duration Predecessors
1.00
1 Activity A 6 --
2 Activity B 2 --
3 Activity C 3 A
4 Activity D 2 B
5 Activity E 4 B
6 Activity F 1 C
7 Activity G 3 C,D
8 Activity H 6 D,E
9 Activity I 3 F,G
10 Activity J 3 G,H
11 Activity K 1 H
12 Activity L 2 I,J
13 Activity M 3 K
14 Activity N 4 L,M

The Activity on the Node network diagram for this project is

Find ES, EF, LS, LF and F for all the activities in the diagram and answer the following
question:
How many critical activities are there?

Select one:
6
7

9
https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 18/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
10

12
other

The completed AON is

The correct answer is: 10

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 19/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
Question 11
Given a project with the following set of activities:
Incorrect
Activity
Mark 0.00 out of
Number Description Duration Predecessors
1.00
1 Activity A 6 --
2 Activity B 2 --
3 Activity C 3 A
4 Activity D 2 B
5 Activity E 4 B
6 Activity F 1 C
7 Activity G 3 C,D
8 Activity H 6 D,E
9 Activity I 3 F,G
10 Activity J 3 G,H
11 Activity K 1 H
12 Activity L 2 I,J
13 Activity M 3 K
14 Activity N 4 L,M

The Activity on the Node network diagram for this project is

Find ES, EF, LS, LF and F for all the activities in the diagram and answer the following
question:
How many critical paths are there?

Select one:
0
1

2
https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 20/21
2019/6/1 Assignment 2 -Due Friday May 24 at 23:59
3

4
other

The completed AON is

The correct answer is: 3

https://moodle.concordia.ca/moodle/mod/quiz/review.php?attempt=1114933 21/21