BOQ SUMMARY

Project Name: A

Element :  Ground Beam

No. Material Unit Quantity Rate $ Cost $


1 Concrete C28 (cum) 5.57 80.00 446
Sub Total 5.57 445

2 Rebar Ø6 (Fe250) (kg) 111.16 0.80 5558


3 Rebar DB14 (Fe390) (kg) 564.74 0.70 565
4 Rebar DB16 (Fe390) (kg) 76.56 0.70 77
Sub Total 752.46 6,199

5 Shuttering (sq.M) 50.21 10.00 502


Sub Total 502

Grand Total 7,147

Design Metrics
1 Consumption : Reinforcement/Concrete ratio = 135.02 kg/cum
2 Concrete % C28 = 100.00 % 
3 Shuttering  = 9.01 sqm/cum