A PEKERJAAN TANAH
1 1 M3 Galian Tanah Biasa sedalam 1 m - SNI - 2007
0.4000 Oh Pekerja 70,000.00 28,000.00
0.0400 Oh Mandor 131,000.00 5,240.00
33,240.00 - 33,240.00
B PEKERJAAN PEMANCANGAN
1 Memancang tiang manual
0.2500 Oh pekerja 70,000.00 17,500.00
0.1000 Oh tukang 101,000.00 10,100.00
0.0100 Oh kep tukang 108,000.00 1,080.00
0.0250 Oh mandor 131,000.00 3,275.00
31,955.00 31,955.00
C PEKERJAAN PASANGAN
1 1 M3 Pasangan batu gunung 1 : 5 - SNI-03-2836-2007
1.1000 m³ Batu Gunung 517,500.00 569,250.00
136.0000 Kg Semen portland 1,725.00 234,600.00
0.5440 m³ Pasir Pasang 160,000.00 87,040.00
0.6000 Oh Tukang batu 101,000.00 60,600.00
0.0600 Oh Kepala Tukang Batu 108,000.00 6,480.00
1.5000 Oh Pekerja 70,000.00 105,000.00
0.0750 Oh Mandor 131,000.00 9,825.00
181,905.00 890,890.00 1,072,795.00
D PEKERJAAN BETON
1 1 M3 Beton K-225 (Ready Mix)
1.0000 m3 Beton K-225 (Ready Mix) 1,345,000.00 1,345,000.00
1.0000 Ls Concrete Pump 30,000.00 30,000.00
1.6500 Oh Pekerja 70,000.00 115,500.00
0.2500 Oh Tukang 101,000.00 25,250.00
0.0250 Oh Kepala Tukang 108,000.00 2,700.00
0.0800 Oh Mandor 131,000.00 10,480.00
153,930.00 1,375,000.00 1,528,930.00
10 1 M3 Sloof 15x20
1.00 m3 Beton 1,457,813.50 1,457,813.50
130.70 kg Besi 22,686.90 2,965,177.83
13.33 m2 Beksiting 79,158.00 1,055,440.00
5,478,431.33 5,478,431.33
11 1 M3 Kolom praktis
1.00 m3 Beton 1,457,813.50 1,457,813.50
156.80 kg Besi 22,686.90 3,557,305.92
20.00 m2 Beksiting 149,376.67 2,987,533.33
8,002,652.75 8,002,652.75
12 1 M3 Ring balk
1.00 m3 Beton 1,457,813.50 1,457,813.50
156.80 kg Besi 22,686.90 3,557,305.92
13.33 m2 Beksiting 149,243.33 1,989,911.11
7,005,030.53 7,005,030.53
6 1 M2 Pek daun jendela kaca bening 5 mm kayu bengkirai - SNI 03 - 3432 - 2007
0.0350 m³ kayu bengkirai 4,600,000.00 161,000.00
0.7500 m2 Kaca bening 5 mm 380,951.00 285,713.25
0.8000 Oh pekerja 70,000.00 56,000.00
2.0000 Oh tk.Kayu 101,000.00 202,000.00
0.2000 Oh kepala Tukang 108,000.00 21,600.00
0.0400 Oh mandor 131,000.00 5,240.00
284,840.00 446,713.25 731,553.25
8 1 M2 Kaca Bening 5 mm
1.1000 m2 Kaca Bening 5 mm 330,000.00 363,000.00
0.0150 Oh Pekerja 70,000.00 1,050.00
0.1500 Oh Tukang 101,000.00 15,150.00
0.0150 Oh Kepala Tukang 108,000.00 1,620.00
0.0010 Oh Mandor 131,000.00 131.00
17,951.00 363,000.00 380,951.00
9 1 Bh Pintu Double P1
0.0310 m3 Kusen ky bengkirai 7,205,300.00 223,364.30
3.5200 m2 Daun pintu panel ky bengkirai 540,050.00 1,900,976.00
6.0000 bh Engsel pintu 82,918.25 497,509.50
1.0000 bh Kunci tanam 502,935.00 502,935.00
1.2400 m2 Pengecatan kusen dgn cat Melamic 80,000.00 99,200.00
7.0400 m2 Pengecatan daun pintu dgn cat Melamic 80,000.00 563,200.00
3,787,184.80 3,787,184.80
10 1 Bh Pintu Ruang P2
0.0270 m3 Kusen ky bengkirai 7,205,300.00 194,543.10
1.7600 m2 Daun pintu panel ky bengkirai 540,050.00 950,488.00
3.0000 bh Engsel pintu 82,918.25 248,754.75
1.0000 bh Kunci tanam 502,935.00 502,935.00
1.0800 m2 Pengecatan kusen dgn Melamic 80,000.00 86,400.00
3.5200 m2 Pengecatan daun pintu dgn Melamic 80,000.00 281,600.00
2,264,720.85 2,264,720.85
11 1 Bh Pintu km/wc P3
0.0260 m3 Kusen ky ulin 7,205,300.00 187,337.80
1.5400 m2 Daun pintu PVC 576,405.00 887,663.70
3.0000 bh Engsel pintu 82,918.25 248,754.75
1.0000 bh Kunci tanam 502,935.00 502,935.00
1.0400 m2 Pengecatan kusen dgn Melamic 80,000.00 83,200.00
1,909,891.25 1,909,891.25
12 1 Bh Jendela J1
0.0456 m3 Kusen ky bengkirai 7,205,300.00 328,291.48
0.5400 m2 Daun jendela 731,553.25 395,038.76
0.9000 m2 Kaca mati 5 mm 380,951.00 342,855.90
0.0024 m3 Sekat kayu bengkirai 4,100,000.00 9,840.00
2.0000 bh Engsel jendela 60,918.25 121,836.50
2.0000 bh grendel jendela 43,000.00 86,000.00
2.0000 bh Hak angin jendela 68,802.50 137,605.00
1.0000 bh Handle jendela 43,000.00 43,000.00
1.8225 m2 Pengecatan kusen dgn cat Melamic 80,000.00 145,800.00
0.3240 m2 Pengecatan daun jendela dgn cat Melamic 80,000.00 25,920.00
1,636,187.64 1,636,187.64
13 1 Bh Jendela J2
0.0205 m3 Kusen ky bengkirai 7,205,300.00 147,708.65
0.7500 m2 Kaca mati 5 mm 380,951.00 285,713.25
0.0024 m3 Sekat kayu bengkirai 4,100,000.00 9,840.00
0.8200 m2 Pengecatan kusen dgn cat Melamic 80,000.00 65,600.00
508,861.90 508,861.90
14 1 Bh Jendela J3
0.0225 m3 Kusen ky bengkirai 7,205,300.00 162,119.25
0.6600 m2 Kaca mati 5 mm 380,951.00 251,427.66
0.9000 m2 Pengecatan kusen dgn Melamic 80,000.00 72,000.00
485,546.91 485,546.91
15 1 Bh Jendela J4
0.0140 m3 Kusen ky bengkirai 7,205,300.00 100,874.20
0.3200 m2 Jalusi kayu bengkirai 226,274.00 72,407.68
0.5600 m2 Pengecatan kusen dg Melamic 80,000.00 44,800.00
1.6320 m2 Pengecatan Jalusi dg Melamic 80,000.00 130,560.00
348,641.88 348,641.88
16 1 Bh Bouven BV
0.0120 m3 Kusen ky bengkirai 7,205,300.00 86,463.60
0.3600 m2 Kaca bening 5 mm 380,951.00 137,142.36
0.4800 m2 Pengecatan kusen dg Melamic 80,000.00 38,400.00
262,005.96 - 262,005.96
18 1 Bh Jendela atap
0.0335 m3 Kusen ky bengkirai 7,205,300.00 241,377.55
1.6006 m2 Jalusi kayu bengkirai 226,274.00 362,174.16
1.3400 m2 Pengecatan kusen dg Melamic 80,000.00 107,200.00
1.6006 m2 Pengecatan Jalusi dg Melamic 80,000.00 128,048.00
838,799.71 838,799.71
F PEKERJAAN ATAP
1 1 M3 kuda-kuda kayu Bengkirai - SNI-03-2836-2007
1.1000 m³ Kayu Bengkirai #REF! #REF!
2.0000 kg Baut #REF! #REF!
15.0000 Kg Besi strip / begel #REF! #REF!
4.0000 Oh pekerja #REF! #REF!
12.0000 Oh tukang #REF! #REF!
1.2000 Oh kep tukang #REF! #REF!
0.2000 Oh mandor #REF! #REF!
#REF! #REF! #REF!
G PEK. CAT-CATAN/LABURAN
1 1 M2 mengecat bidang kayu baru dg cat kilap
1 lapis plamir, 1 lapis cat dasar, 3 lapis penutup - SNI - 2007
0.2000 Kg Cat meni #REF! #REF!
0.1500 Kg Plamir #REF! #REF!
0.1700 Kg Cat dasar #REF! #REF!
0.3500 Kg Cat penutup #REF! #REF!
0.0700 Oh Pekerja #REF! #REF!
0.1050 Oh Tukang cat #REF! #REF!
0.0040 Oh Kepala Tukang #REF! #REF!
0.0025 Oh Mandor #REF! #REF!
#REF! #REF! #REF!
I PEKERJAAN SANITAIR
1 Memasang 1 bh klosed jongkok
1.0000 bh Klosed jongkok #REF! #REF!
14.0000 bh Bata merah #REF! #REF!
12.0000 kg Semen portland #REF! #REF!
0.0100 m³ pasir pasang #REF! #REF!
1.0000 Oh Pekerja #REF! #REF!
1.5000 Oh Tukang #REF! #REF!
0.3000 Oh Kepala Tukang #REF! #REF!
0.1100 Oh Mandor #REF! #REF!
#REF! #REF! #REF!
J PEKERJAAN LAIN-LAIN
1 1 m' Pekerjaan Saluran Keliling Bangunan
0.2025 m3 Galian tanah 33,240.00 6,731.10
0.0200 m3 Urugan pasir bawah lantai 166,520.00 3,330.40
1.0500 m2 Pasangan bata 114,762.50 120,500.63
1.1000 m2 Plesteran 44,250.00 48,675.00
179,237.13 179,237.13