Professional Documents
Culture Documents
Reviewed by Date
Reviewed by Date
Revision Record
Date Version Description Author
Contents
Tables
Figure 3-1 The BBU and RRU are connected through the CPRI optical port.......................................................12
Figure 3-3 space requirements of the BBU3900 in a 19-inch cabinet (unit: mm).................................................15
Figure 4-2 Grounding system of the eNodeB equipment room (with dedicated rectifier)....................................23
Thank you for choosing Huawei eNodeB (DBS3900 TDLTE).To ensure the smooth completion of
installation, read the HUAWEI TDLTE DBS3900 Installation Preparation Guide, which will guide
you through the preparations that need to be made before the installation. You are expected to
make all the preparations described in this guide before Huawei technical staffs arrive on site, so
that the equipment can be put into operation as soon as possible. This can ensure that you reap
social benefits and economic interests at the earliest.
Before making the installation preparations, read the following contents carefully:
After you complete all the installation preparations, please contact the Huawei local
representative office on time, so that Huawei can arrange technical staff to start the
installation.
If the installation is implemented before the installation preparations are fully completed
owing to some reason, you should arrange related staff to finish the uncompleted part as early
as possible to ensure the smooth implementation of the project.
If the installation is started before the preparations are fully completed owing to some reason,
and later installation cannot go on because of insufficient preparations, Huawei has the right
to stop the installation. After all the preparations are made, both parties can discuss and
arrange to restart the installation.
When you are making these preparations, you are welcome to consult Huawei representative
office in the local area (local province or local region) at any time for any doubts.
Address of the Local Huawei Representative Office:_______________________________
Phone/Fax:_______________________________
Contact Person and Phone Number:______________________________
To strengthen understanding and for better cooperation between two parties, this section provides a
brief overview of the Huawei equipment installation process. Huawei equipment installation
process starts when the contract is signed and validated and ends when the equipment passes the
final acceptance test and enters the maintenance period. The process is as follows:
This process shows that smooth completion of an installation project requires close cooperation
between you and Huawei. We sincerely hope for smooth completion of the project.
Figure System Installation Requirements of the DBS3900 TDLTE-1 The BBU and RRU are
connected through the CPRI optical port.
The DBS3900 TDLTE equipment configuration is flexible. It can be installed on the wall ,in
the APM30H or TMC or any 19-inch cabinet(indoor and outdoor).The RRU can be installed
close to the antenna, such as on a pole or tower, thus decreasing feeder loss and enhancing
base station performance.
The site should not be exposed to excessive heat, dust, harmful gases, flammable or
explosive materials, or unstable voltage.
The site should be located at a place where earthquakes or strong noise are unlikely to
occur.
The site should be located far away from power substations, industrial boilers, and
heating boilers.
The site should be far away from high-power radio transmitters, radar stations, or other
interference sources. The interference field intensity should not be higher than the
shielding specifications of the eNodeB for useless radiation.
The equipment room for the indoor eNodeB should be constructed at least 3.7 km away
from the seaside or a salt lake. If this is not possible, the equipment room should be
closed and air conditioned. In addition, avoid using salt soil as the building material for
the room. Otherwise, the equipment that can be operated in extreme and unfavorable
environment must be used.
The outdoor eNodeB should be located more than 500 m away from the sea side.
The site should be far away from pollution sources. If this requirement cannot be met,
select a site that is in the perennial upwind direction of the pollution source.
− The site should be constructed at least 5 km from heavy pollution sources such as a
smelting plant or a coal mine.
− The site should be constructed at least 3.7 km from medium pollution sources such as
a chemical plant, a rubber plant, or an electric plating plant.
− The site should be constructed at least 2 km from light pollution sources such as a
food product factory or a leather product factory.
The air inlets of the communication equipment should be far away from the sewer pipe,
septic tank, and sewage disposal pool. The air pressure inside the equipment room
should be higher than the air pressure outside the equipment room. Otherwise, corrosive
gases may enter the equipment room and corrode the components and circuit boards.
Livestock rooms or fertilizer warehouses cannot be used as the equipment room for the
indoor eNodeB. If this is not possible, it should be located at a place that is in the upwind
direction of the livestock room or fertilizer warehouse.
It is recommended that the equipment room for the indoor base station be located on the
second floor or above. If this requirement cannot be met, the ground for the equipment
room should be at least 600 mm higher than the maximum flood level recorded in the
area.
The minimum space requirements around the BBU3900 in a 19-inch cabinet are as follows:
(1) Recommended space requirements of a single (2) Minimum space requirements of a single RRU3211/RRU3233
RRU3211/RRU3233 (unit: mm)
(unit: mm)
(3) Recommended Clearance for Multiple Centralized (4) Minimum space requirements of multiple
RRU3211/RRU32331s (unit: mm) RRU3211/RRU3233s (unit: mm)
(5) Recommended Horizontal Clearance for (6) Minimum Horizontal Clearance for
RRU3211/RRU3233s(unit:mm) RRU3211/RRU3233s(unit:mm)
(7) Recommended Vertical Clearance for (8) Minimum Vertical Clearance for
RRU3211/RRU3233s(unit:mm) RRU3211/RRU3233s(unit:mm)
1. Engineering specifications of the tower should comply with the requirements for
communication equipment installation.
2. A maintenance channel with safety design should be provided on the tower. The channel
should be spacious enough that the maintenance personnel can pass through it.
3. Sufficient space should be provided for the RRU installation and future maintenance.
4. The grounding system should meet the grounding requirements of the site.
5. A grounding bar for connecting the PGND cable of the RRU should be installed. If the
grounding bar is not installed, sufficient space should be left for installing the grounding
bar.
6. A cable rack should be installed for the routing the RRU cables such as the power cables
and optical cables. If the cable rack is not installed, sufficient space should be left for
installing the rack.
Climatic Requirements
lists the climatic requirements for the working environment of the DBS3900.
Item Specification
The operating environment of the DBS3900 must meet the following biological requirements: No
fungus or mildew should grow in the operating environment.
The air purity requirements related to the running environment are as follows:
There should not be any explosive, conductive, magnetic conductive, or corrosive dust in the air.
If the customer cannot provide the –48 V DC power supply, (for example, the customer can only provide the
220 V AC power supply), Huawei offers the power conversion unit to provide different power supply
solutions.
If optical transmission is applied, and the optical cables on the eNodeB side are connected to the
transmission device through the ODF. The requirements for the ODF are listed as follows:
The delivered transmission cables and connectors match the connectors on the ODF on the
transmission device side.
Before you install the eNodeB, the ODF is installed and external optical cables are connected
to the ODF.
It is recommended that the copper wires be used to connect the ODF and the grounding bar of
the equipment room.
When the BBU3900 uses GE electric transmission, a 10 m long Ethernet cable is configured
for each site by default. When the required GE Ethernet cable for BBU3900 is longer than 10
m, provide the required length.
Transmission resources should meet the upcoming requirements of the eNodeB site and extra
resources are reserved for capacity expansion.
If the eNodeB is within the Line of Sight (LOS) of microwave transmission, and the
microwave transmission is used. The indoor units of the microwave transmission devices
should be installed in the space for the transmission devices in the cabinet.
If the eNodeB is not within the Line of Sight (LOS) of microwave transmission, and the
xDSL transmission is used. It is recommended that the devices for xDSL transmission be
installed in the space reserved in the cabinet.
shows the grounding grid of the eNodeB (the outdoor grounding system).
Figure Construction Preparations of the DBS3900 TDLTE-5 Grounding grid of the eNodeB
The grounding grids of the power transformer, tower, and equipment room constitute an integrated grounding
grid. (The grounding grid should be connected to the building and reinforced concrete bars of the tower.
Generally, the grounding grid should be connected to at least two reinforced concrete bars.)
The outdoor grounding ring can be laid out in L-shaped or C-shaped according to the field situation of the
equipment room. If the soil conductibility is poor or there is little soil in the rocky area, it is recommended that
the grounding extension style and concrete bridge be used. The cable embedded concrete bridge radiates
outwardly through the grounding ring and the four corners of the tower grounding ring. The concrete bridge
has strong hygroscopy. The recommended length of the concrete is 10 m to 30 m.
It is recommended that the grounding stake be coated with hot galvanized steel. The specifications
are as follows:
The proper length of the grounding stake is from 1.5 m to 2.5 m, and the interval is 1.5 to 2 times
the length of the grounding stake. The space between the top of the grounding stake and the ground
is at least 0.7 m. For cold districts, bury the grounding stake under the frozen soil.
The depth of the grounding ring must be 0.7 m under the concrete base.
You should determine whether to add resistivity reduction mixture based on the equipment room
location and soil conditions.
Figure Construction Preparations of the DBS3900 TDLTE-6 Grounding system of the eNodeB
equipment room (with dedicated rectifier)
The equipment room is configured with a primary grounding bar that is connected to the grounding grid
of all the equipment and the DC power inside the equipment room.
It is recommends that you use the galvanized flat steel of 40 mm x 4 mm or 50 mm x 5 mm as the
grounding cable. The part of the grounding cable outside the earth should be protected against
mechanical damage.
The outdoor grounding system consists of the tower grounding, feeder grounding, grounding grid,
rooftop surge protection grounding bar, cable rack grounding, and outdoor grounding copper
busbar.
Figure Construction Preparations of the DBS3900 TDLTE-7 Grounding of metal tower and
buildings
Ground the feeder pipe when it is on the tower, and before it is connected to the cable rack and routed
through the feeder window. If the tower is higher than 60 m, ground the feeder pipe in the middle of the
tower. The outdoor grounding copper bar should be installed under the outdoor feeder window and be
connected to the outdoor grounding ring. The feeders and indoor surge protector should be connected to
the outdoor grounding copper bar.
1 M8 bolt
The requirements for the metal pole at the DBS3900 TDLTE site are as follows:
The metal pole is at least 1800 mm and the diameter of the metal pole ranges from 60 mm to
114 mm.
The base is made of steel frame and concrete block. The dimensions of the base are 630 mm x
430 mm x 120 mm.
The entire jointing surface is coated with antirust paint.
The jointing is firm and there is no dry or open weld.
If the metal pole for the RRU is within the surge protection coverage of the antenna, no
lightning rod is required on the top of the metal pole.
If the metal pole for the RRU is not within the surge protection coverage of the antenna, a
lightning rod is required on the top of the metal pole. The metal pole should be connected
properly with the grounding grid.
Figure Construction Preparations of the DBS3900 TDLTE-9 Installing the metal pole on the
concrete floor
Figure Construction Preparations of the DBS3900 TDLTE-10 Two stay poles with a metal pole
shows two metal poles with a stay pole. The two metal poles are in I-shaped mode with a one-
meter-long beam in between. The stay pole helps to form a triangle support.
Figure Construction Preparations of the DBS3900 TDLTE-11 Two metal poles with a stay pole
The height of the tower depends on the field requirements of the eNodeB.
Typically, the tower has an operating platform of one to three layers with a round or hexagon
structure. The minimum diameter of the circle should be 4 m and the spacing between two
platforms should be 6 m. One-meter-high guard rails are required on the platforms. The
minimum weight-bearing capacity of the platforms should be 150 kg/m2.
The tower must be able to carry 27 directional antennas and 27 7/8-inch feeders. Each antenna
should weigh 30 kg with the front face area of 0.5 mm2. Each feeder should be 0.49 kg/m
with the diameter 28 mm.
A ladder for maintenance should be installed on the tower. The reinforcing angle steel should
be installed every 1 m on both sides of the ladder, and the angle steel should extend 0.5 m out
of the ladder on either side.
A lightning rod should be installed 8 m above the upper platform to ensure that all the feeders
on the tower are within the coverage of the lightning rod.
Even in the face of the strongest wind that blow once every 30 years, the maximum axial
wobble and torsion of the tower body must be within ±1°.
The tower should be designed to resist one degree of seismic intensity over the limit
stipulated in local regulations. When earthquake occurs, the tower can withstand the
earthquake and devoid of any distortion that affects the quality of communication.
A cable rack that can bear the weight of a person should be installed on the tower.
Surge protection and lightning induction devices should be installed on the tower.
The wind speed and earthquake intensity level comply with local stipulations.
When installing the antenna support on the tower, adhere to the following principles:
19. The installation plane of the antenna support is perpendicular to the horizontal plane.
20. The pole for the lightning rod should be installed separately on the tower. The lightning rod
should be placed high enough to bring the protection areas of all the antennas below 45°.
21. The antenna support should be installed in the direction that does not affect the
transmit/receive performance and direction adjustment regulation of the antenna.
22. A stiffener should be used to fasten the rotating lever. The expansion lever and the rotating
lever should be cut into proper length. The cross-section should be welded with a waterproof
cover.
23. The antenna support must not have any dry and open welds. It is recommended that the
support be made of galvanized steel. The surface of the support should be coated with antirust
paint.
24. For the directional antenna, the length of the pole depends on that of the antenna. In wide
coverage application, high gain antennas are generally used. Such antennas are long, so it is
recommended that the length of the pole be greater than 3 m and that the diameter range from
60 mm to 114 mm (generally 75 mm).For the uni-polarization antenna, the distance between
the two diversities of the two antennas serving one sector should be at least 2 m.
shows the recommended directional antenna support on a tower.
Figure Construction Preparations of the DBS3900 TDLTE-14 Support for the omni-
directional antenna on a tower
When installing the antenna support on the rooftop, adhere to the following principles:
26. The strength of the materials for the antenna support and pole should meet the requirements
of antenna load capacity and wind load.
27. The connecting pieces for the stiffener should be installed in the positions where the
regulation of the antenna orientation and tilt is not affected.
28. The antenna support should be perpendicular to the horizontal plane.
29. The base of the antenna support, the anchor of the stiffener, and their expansion bolts should
be covered with concrete.
When a directional antenna is installed on the rooftop, a lightning rod should be installed on the
antenna support, and the antenna support should be connected to the grounding grid of the
building. When an omni-directional antenna is installed on the rooftop, a lightning rod should be
installed onto a separate support. If a lightning rod is installed onto the support of the omni-
directional antenna, the omni-directional antenna should be extended from the support for 1 to 1.5
m. If there are enclosing walls on the rooftop, the antenna support can be installed on an enclosing
wall. Ensure that the main supporting post is vertical to the surface of the rooftop. In addition,
ensure that the antenna support is equipped with a surge protector and connected to the grounding
grid of the building.
(1) For the uni-polarization directional antenna, because of the requirements for diversity spacing,
the distance between the two poles supporting the two antennas should be at least.
(2) The length of the pole depends on that of the antenna. It is recommended that the length of the
pole be greater than 2.5 mm and that the diameter range from 60 mm to 114 mm.
The main supporting post of antenna support should be longer than the antenna. The relation
between h and d should meet the specifications illustrated in and listed in Table, where h indicates
the valid vertical distance between the lower edge of the antenna and the rooftop in the direction
that the antenna faces, and d indicates the distance between the edge of the rooftop in the direction
that the antenna faces and the antenna support.
Figure Construction Preparations of the DBS3900 TDLTE-15 Installing the antenna support on
the rooftop
Height Diameter
0.5 m 0 m to 2 m
1m 2 m to 10 m
2m More than 10 m
(1) Lightning rod for (2) Main support (3) Stiffener (4) Base of the
the antenna antenna support
(5) Use concrete to (6) Solder the (7) Fix the (8) Ladder
cover and fix. stiffener to the main stiffener to the
supporting post. ground.
(2) After installation, the top of the pole should be flush with the fixing hoop in the lower part
of the antenna. Therefore, the omni-directional antenna pole does not need to be long. The
length of the pole only needs to meet the specifications.
(3) Generally, the omni-directional antenna pole should have a diameter of 60 mm to110 mm
and should be made of 75 mm round steel.
(4) The omni-directional antenna is long and therefore the antenna top is much higher than the
pole top. In this case, the surge protector should not be welded directly to the pole but should
be installed separately in the middle of the two antenna poles. Ensure that the top of omni-
directional antenna is within the protection angle of the surge protector, as shown in .In some
cases, the surge protector may not be prepared independently due to limited conditions.
Instead, you can use the following method shown in .
Table Construction Preparations of the DBS3900 TDLTE-3 Requirements for materials of the
indoor eNodeB cables
Power cable The power cables without jackets should be insulated with PVC
materials. If the power cables are required to be weatherproof or
high/low-temperature resistant, materials such as silicone rubber, FEP,
or PFA can be used for insulation.
The power cables with PVC jackets should be insulated through PVC
or XLPE materials. If there are fire-resistant requirements such as
halogen-free and low smoke, use power cables with LSZH jackets.
The high/low-temperature resistant power cables should be coated with
FEP jackets.
Symmetric cable The symmetric cables should be insulated through PE, PP, or PVC
materials and coated with PVC or PE jackets. If there are fire-resistant
requirements such as halogen-free and low smoke, use power cables
with LSZH jackets.
Coaxial cable The coaxial cables should be insulated through PE, PTFE, or FEP
materials and coated with PVC or FEP jackets.
PGND cable The PGND cables should be copper-based and insulated with green
and yellow plastic jackets.
When selecting the indoor cables, you should consider the fire-resistant requirements. Weather proofing
requirements for the indoor cables are not high. Thus, use cables coated with PVC jackets as indoor cables.
If fire-resistant requirements for the cables are high, use cables that are insulated with fire-resistant materials
such as PE or PVC and coated with fire-resistant PVC jackets.
If there are strict requirements for smoke density, and transmittance of the halogen gas released after the
cables caught fire, use cables coated with comparatively expensive LSZH jackets.
Insulating materials and protection jackets of the cables must comply with the Restriction of Hazardous
Substance (RoHS) requirements.
The cable materials can either be customized or comply with local regulations.
Optical cable R ≥ 20 D
In the preceding table, D refers to the diameter of the cable jacket and R refers to the bending radius of the
cable.
The spacing between cables of different types should be greater than 30 mm when the cables
are routed parallel in the cabinet. The spacing between cables of different types should be
greater than 100 mm when the cables are routed parallel outside the cabinet. If such
requirements cannot be met, the cables should be separated with specific objects.
The power cables and PGND cables should be routed in compliance with the engineering
design and general cabling specifications. If the cable is not long enough, replace the cable.
Do not add connectors or solder joints to lengthen the cable.
The cables should be insulated if they are bound and routed on the metal cable rack.
Fuses or switches are not allowed on the cables.
The -48 V power cable and the GND cable should be bound together.
Both ends of the grounding cables should be anti-corrosive and anti-rust. Connections of the
grounding cables should be secure.
The low-voltage AC power cable for the base station should be led through a metallic conduit
and buried in the ground for at least 50 m before it is led into the equipment room. If the AC
power cable is shorter than 50 m, it should be completely routed under the ground. If such
cables are routed overhead and led into the room, surge protection for the connectors of the
AC power cables are seriously affected. The PGND cable should be buried in the ground or
routed indoors. The PGND cable cannot be routed overhead outdoors before it is led into the
equipment room.
The optical cables should be routed in compliance with the engineering design and general
cabling specifications.
Proper cable surpluses should be left at the turning of the optical cables.
Do not stretch, step over, or place heavy objects on the optical cables. Keep the cables away
from sharp objects to avoid damage. The optical cable that is curved or pressed or the optical
connector that is damaged cannot be used.
Extra optical cables should be coiled on the specified device such as the fiber coiler. Use
moderate force to coil the optical cables. Do not bend the cables forcibly lest they be
damaged.
If unprotected bare fibers are used, the protection tubes can be adopted as required.
The idle connectors of the optical cables should be covered with dustproof caps.
If one end of the optical cable is connected to an optical device, do not look directly at the
optical connector to prevent your eyes from being damaged by the infrared laser emitted by
the optical port.
Fill soft materials such as fireproof cottons in the optical cable inlets at the top of the cabinet
to protect the optical cables.
You need to check whether the optical connectors are clean before installation. If the optical
connectors are dirty, clean them by using the dust free cloth or fiber cleaner.
BBU 12A
Main Switch (for Three-phase 220v/380v AC 20A~32A
APM30H)
Dual-live-wire 110V AC/ 40A~50A
Single-phase 220V AC/
Dual-live-wire 120V AC
Fill in the grey part in the table above when the antenna is installed on the tower platform.