You are on page 1of 45

Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

Document Product Name DBS3900 TDLTE


Number

Intended Client/Engineer/Cooperation Product LTE V100R002C00


Users Partner Version
LTE V100R003C00
Issued by Wireless Product Service Dept, Document 1.1
TSD Version

Guide to Customer’s Preparation for DBS3900


TDLTE Installation

Prepared by Xu chong Date 2010-7-15

Reviewed by Date

Reviewed by Date

Approved by: Date

2019-09-22 HUAWEI Confidential Page 1, Total 46


HUAWEI TECHNOLOGIES CO., LTD.
2010-7-15
Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

Revision Record
Date Version Description Author

2010-7-15 V1.0 First issue Xu chong


2010-12-10 V1.1 Second issue Chen Fei

2019-09-22 HUAWEI Confidential Page 3, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

Contents

1 About This Document..................................................................................................................9

2 Introduction to Huawei Installation Process.........................................................................10

3 System Installation Requirements of the DBS3900 TDLTE...............................................12


3.1 Introduction to the DBS3900 TDLTE..............................................................................................................12

3.2 Site Requirements of the DBS3900 TDLTE....................................................................................................14

3.2.1 Site Selection Requirements of the eNodeB...........................................................................................14

3.2.2 Space Requirements of the DBS3900 TDLTE.......................................................................................15

3.2.3 Requirements for the Tower Where the RRU is Installed......................................................................17

3.2.4 Operating Environment Requirements of the DBS3900 TDLTE...........................................................18

3.3 Power Supply Requirements of the DBS3900 TDLTE...................................................................................19

3.4 Grounding Requirements of the DBS3900 TDLTE.........................................................................................19

3.4.1 Grounding Requirements of the BBU3900............................................................................................19

3.4.2 Grounding Requirements of the RRU....................................................................................................19


3.4.3 Grounding Network Pavement...............................................................................................................20

3.5 Transmission Requirements for the eNodeB Site............................................................................................20

4 Construction Preparations of the DBS3900 TDLTE..............................................................22


4.1 Auxiliary Facilities Preparations for the DBS3900 TDLTE Site.....................................................................22

4.1.1 Preparing the Cable Racks......................................................................................................................22

4.1.2 Preparing the Grounding System............................................................................................................22

4.1.3 Preparing the Metal Pole........................................................................................................................26

4.2 Preparing Auxiliary Facilities for the DBS3900 Antenna System...................................................................28

4.2.1 Requirements for the Tower...................................................................................................................28

4.2.2 Preparing the Antenna Support on the Tower.........................................................................................29

4.2.3 Preparing the Antenna Support on the Rooftop......................................................................................31

4.3 Cable Requirements of the eNodeB.................................................................................................................36

2019-09-22 HUAWEI Confidential Page 5, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

4.3.1 Requirements for Materials of the Indoor eNodeB Cables....................................................................36

4.3.2 Cabling Requirements for the eNodeB...................................................................................................37

4.4 Preparation of Personnel for the Installation...................................................................................................39

5 Appendix 1 Checklist for the Installation Preparations......................................................40


5.1 Acceptance Items for the Environment of the Equipment Room....................................................................40

5.2 Acceptance Items for Power Supply................................................................................................................41

5.3 Acceptance Items for Surge Protection Grounding.........................................................................................42

5.4 Acceptance Items for the eNodeB Antenna System........................................................................................43

6 Appendix 2 Specifications of the DBS3900 TDLTE.............................................................44


6.1 Engineering specifications...............................................................................................................................44

6.2 Environment Specifications.............................................................................................................................45

2019-09-22 HUAWEI Confidential Page 6, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

Tables

Figure 3-1 The BBU and RRU are connected through the CPRI optical port.......................................................12

Figure 3-2 Main equipment appearance of the DBS3900 TDLTE........................................................................12

Figure 3-3 space requirements of the BBU3900 in a 19-inch cabinet (unit: mm).................................................15

Figure 3-4 Space requirements of one RRU3211/RRU3233and combined RRU3211/RRU3233s......................16

Figure 4-1 Grounding grid of the eNodeB.............................................................................................................22

Figure 4-2 Grounding system of the eNodeB equipment room (with dedicated rectifier)....................................23

Figure 4-3 Grounding of metal tower and buildings.............................................................................................24

Figure 4-4 Grounding bar of the eNodeB..............................................................................................................25

Figure 4-5 Installing the metal pole on the concrete floor.....................................................................................26

Figure 4-6 Two stay poles with a metal pole.........................................................................................................27

Figure 4-7 Two metal poles with a stay pole.........................................................................................................27

Figure 4-8 Tower for telecommunication purpose.................................................................................................28

Figure 4-9 Directional antenna support on a tower...............................................................................................30

Figure 4-10 Support for the omni-directional antenna on a tower........................................................................30

Figure 4-11 Installing the antenna support on the rooftop.....................................................................................32

Figure 4-12 Structure of the pole on the rooftop...................................................................................................32

Figure 4-13 Fixing the directional antenna on the rooftop (1)..............................................................................33

Figure 4-14 Fixing the directional antenna on the rooftop (2)..............................................................................34

Figure 4-15 Installing an omni-directional antenna...............................................................................................35

2019-09-22 HUAWEI Confidential Page 7, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

Figure 4-16 Installing an omni-directional antenna support..................................................................................35

2019-09-22 HUAWEI Confidential Page 8, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

1 About This Document

Thank you for choosing Huawei eNodeB (DBS3900 TDLTE).To ensure the smooth completion of
installation, read the HUAWEI TDLTE DBS3900 Installation Preparation Guide, which will guide
you through the preparations that need to be made before the installation. You are expected to
make all the preparations described in this guide before Huawei technical staffs arrive on site, so
that the equipment can be put into operation as soon as possible. This can ensure that you reap
social benefits and economic interests at the earliest.

Before making the installation preparations, read the following contents carefully:

 After you complete all the installation preparations, please contact the Huawei local
representative office on time, so that Huawei can arrange technical staff to start the
installation.
If the installation is implemented before the installation preparations are fully completed
owing to some reason, you should arrange related staff to finish the uncompleted part as early
as possible to ensure the smooth implementation of the project.
If the installation is started before the preparations are fully completed owing to some reason,
and later installation cannot go on because of insufficient preparations, Huawei has the right
to stop the installation. After all the preparations are made, both parties can discuss and
arrange to restart the installation.
 When you are making these preparations, you are welcome to consult Huawei representative
office in the local area (local province or local region) at any time for any doubts.
Address of the Local Huawei Representative Office:_______________________________
Phone/Fax:_______________________________
Contact Person and Phone Number:______________________________

2019-09-22 HUAWEI Confidential Page 9, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

2 Introduction to Huawei Installation


Process

To strengthen understanding and for better cooperation between two parties, this section provides a
brief overview of the Huawei equipment installation process. Huawei equipment installation
process starts when the contract is signed and validated and ends when the equipment passes the
final acceptance test and enters the maintenance period. The process is as follows:

2019-09-22 HUAWEI Confidential Page 10, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

This process shows that smooth completion of an installation project requires close cooperation
between you and Huawei. We sincerely hope for smooth completion of the project.

2019-09-22 HUAWEI Confidential Page 11, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

3 System Installation Requirements of the


DBS3900 TDLTE

3.1 Introduction to the DBS3900 TDLTE


The DBS3900 is the Huawei-developed distributed eNodeB and it is applicable to the scenario of
separated installation of baseband and RF modules. The main equipment of the DBS3900 TDLTE
includes the BBU and RRU, as shown in .

Figure System Installation Requirements of the DBS3900 TDLTE-1 The BBU and RRU are
connected through the CPRI optical port.

2019-09-22 HUAWEI Confidential Page 12, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

Figure System Installation Requirements of the DBS3900 TDLTE-2 Main equipment


appearance of the DBS3900 TDLTE

1. Appearance of the BBU3900: 88.9 mm x 482.6 mm x 310 mm(H×W×D)

2. Appearance of the RRU3211: 480×356×120 (without housing)


484×377×157.6 (with housing) (H×W×D)

3. Appearance of the RRU3233: 550×320×135 (without housing) (H×W×D)


484×377×157.6 (with housing)

2019-09-22 HUAWEI Confidential Page 13, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

The DBS3900 TDLTE equipment configuration is flexible. It can be installed on the wall ,in
the APM30H or TMC or any 19-inch cabinet(indoor and outdoor).The RRU can be installed
close to the antenna, such as on a pole or tower, thus decreasing feeder loss and enhancing
base station performance.

3.2 Site Requirements of the DBS3900 TDLTE


The proper installation, commissioning, and operation of the eNodeB are ensured only when
the installation space is planned and prepared in compliance with the site requirements. The
site requirements of the DBS3900 TDLTE involve the site selection, installation space,
construction of the BBU3900 equipment room and the tower where the RRU is installed, and
the operating environment requirements.

3.2.1 Site Selection Requirements of the eNodeB


To ensure the stable running of the eNodeB over a long term, the site for the eNodeB must
meet the requirements for telecommunication network planning, communications technology,
hydrology, geology, and traffic.

The specific requirements for site selection are as follows:

 The site should not be exposed to excessive heat, dust, harmful gases, flammable or
explosive materials, or unstable voltage.
 The site should be located at a place where earthquakes or strong noise are unlikely to
occur.
 The site should be located far away from power substations, industrial boilers, and
heating boilers.
 The site should be far away from high-power radio transmitters, radar stations, or other
interference sources. The interference field intensity should not be higher than the
shielding specifications of the eNodeB for useless radiation.
 The equipment room for the indoor eNodeB should be constructed at least 3.7 km away
from the seaside or a salt lake. If this is not possible, the equipment room should be
closed and air conditioned. In addition, avoid using salt soil as the building material for
the room. Otherwise, the equipment that can be operated in extreme and unfavorable
environment must be used.
 The outdoor eNodeB should be located more than 500 m away from the sea side.
 The site should be far away from pollution sources. If this requirement cannot be met,
select a site that is in the perennial upwind direction of the pollution source.
− The site should be constructed at least 5 km from heavy pollution sources such as a
smelting plant or a coal mine.
− The site should be constructed at least 3.7 km from medium pollution sources such as
a chemical plant, a rubber plant, or an electric plating plant.
− The site should be constructed at least 2 km from light pollution sources such as a
food product factory or a leather product factory.

2019-09-22 HUAWEI Confidential Page 14, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

 The air inlets of the communication equipment should be far away from the sewer pipe,
septic tank, and sewage disposal pool. The air pressure inside the equipment room
should be higher than the air pressure outside the equipment room. Otherwise, corrosive
gases may enter the equipment room and corrode the components and circuit boards.
 Livestock rooms or fertilizer warehouses cannot be used as the equipment room for the
indoor eNodeB. If this is not possible, it should be located at a place that is in the upwind
direction of the livestock room or fertilizer warehouse.
 It is recommended that the equipment room for the indoor base station be located on the
second floor or above. If this requirement cannot be met, the ground for the equipment
room should be at least 600 mm higher than the maximum flood level recorded in the
area.

3.2.2 Space Requirements of the DBS3900 TDLTE


This describes the space requirements of the BBU3900, RRU3211/RRU3233.

Space Requirements of the BBU3900


When installed in a 19-inch cabinet or on the wall, the BBU3900 has the space requirements for
easy cabling and OM. Huawei offers the recommended space requirements.

1. Space Requirements of the BBU3900 in a 19-Inch Cabinet

Figure System Installation Requirements of the DBS3900 TDLTE-3 space requirements


of the BBU3900 in a 19-inch cabinet (unit: mm)

The minimum space requirements around the BBU3900 in a 19-inch cabinet are as follows:

 A minimum of 25 mm on the left of the BBU for ventilation

 A minimum of 25 mm on the right of the BBU for ventilation

 A minimum of 70 mm in front of the panel for cabling

2019-09-22 HUAWEI Confidential Page 15, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

 A minimum of 800 mm in the front of the panel for maintenance

Space Requirements of the RRU


The RRU3211/RRU3233 has the minimal space requirements for easy cabling and OM in different
installation modes. Based on the engineering practice, Huawei offers the recommended installation
space.

Figure System Installation Requirements of the DBS3900 TDLTE-4 Space requirements of


one RRU3211/RRU3233and combined RRU3211/RRU3233s

(1) Recommended space requirements of a single (2) Minimum space requirements of a single RRU3211/RRU3233
RRU3211/RRU3233 (unit: mm)
(unit: mm)

(3) Recommended Clearance for Multiple Centralized (4) Minimum space requirements of multiple
RRU3211/RRU32331s (unit: mm) RRU3211/RRU3233s (unit: mm)

2019-09-22 HUAWEI Confidential Page 16, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

(5) Recommended Horizontal Clearance for (6) Minimum Horizontal Clearance for
RRU3211/RRU3233s(unit:mm) RRU3211/RRU3233s(unit:mm)

(7) Recommended Vertical Clearance for (8) Minimum Vertical Clearance for
RRU3211/RRU3233s(unit:mm) RRU3211/RRU3233s(unit:mm)

3.2.3 Requirements for the Tower Where the RRU is Installed


To ensure the safety of installers and equipment, the towers must meet the related construction
requirements. The requirements for the tower where the RRU is installed are as follows:

1. Engineering specifications of the tower should comply with the requirements for
communication equipment installation.
2. A maintenance channel with safety design should be provided on the tower. The channel
should be spacious enough that the maintenance personnel can pass through it.
3. Sufficient space should be provided for the RRU installation and future maintenance.
4. The grounding system should meet the grounding requirements of the site.
5. A grounding bar for connecting the PGND cable of the RRU should be installed. If the
grounding bar is not installed, sufficient space should be left for installing the grounding
bar.

2019-09-22 HUAWEI Confidential Page 17, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

6. A cable rack should be installed for the routing the RRU cables such as the power cables
and optical cables. If the cable rack is not installed, sufficient space should be left for
installing the rack.

3.2.4 Operating Environment Requirements of the DBS3900


TDLTE
The operating environment of the DBS3900 TDLTE consists of requirements related to climatic
conditions, biological environment, and air purity specifications.

Climatic Requirements

lists the climatic requirements for the working environment of the DBS3900.

Table System Installation Requirements of the DBS3900 TDLTE-1 Climatic requirements

Item Specification

Altitude ≤ 4,000 m; normal work within the range of -60 m to +3000 m, in


degraded use within the range of 3,000 m to 4,000 m (the ambient
temperature decreases 1℃ when the height increases by 100 m
from 3,000 m)
Air pressure 70 kPa to 106 kPa
Temperature BBU: –20°C to +50°C
RRU: –40°C to +50°C (without solar radiation)
Relative humidity BBU: 5% RH to 95% RH
RRU: 5% RH to 100% RH

Biological Environment Requirements

The operating environment of the DBS3900 must meet the following biological requirements: No
fungus or mildew should grow in the operating environment.

Air Purity Requirements

The air purity requirements related to the running environment are as follows:

There should not be any explosive, conductive, magnetic conductive, or corrosive dust in the air.

2019-09-22 HUAWEI Confidential Page 18, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

3.3 Power Supply Requirements of the DBS3900 TDLTE


To ensure the proper operation of the power system of the DBS3900 TDLTE, the power supply of
all the functional modules must comply with the related specifications. Table lists the power supply
requirements of the DBS3900 TDLTE.

Table System Installation Requirements of the DBS3900 TDLTE-2 Input power


requirements of the DBS3900 TDLTE

Functional Modules of Rated Operating Voltage Operating Voltage


the DBS3900 TDLTE Range

BBU3900 -48 V DC -38 V DC to -57 V DC


+24 V DC +19 V DC to +29 V DC
RRU -48 V DC -36 V DC to -57 V DC

Specifications of the DBS3900 TDLTE (BBU3900+RRU3211/RRU3233) is shown in 6.1


Engineering specifications

If the customer cannot provide the –48 V DC power supply, (for example, the customer can only provide the
220 V AC power supply), Huawei offers the power conversion unit to provide different power supply
solutions.

3.4 Grounding Requirements of the DBS3900


Grounding requirements for the BBU3900 and RRU in the DBS3900 system must be satisfied.

3.4.1 Grounding Requirements of the BBU3900


 The PGND cable of the BBU3900 should be copper-based and insulated with the green and
yellow plastic jacket, and the cross-sectional area of the cable should be at least 6 mm2.
The grounding resistance of the BBU3900 should be smaller than 10 ohms.
When the BBU3900 is installed in the equipment room, the PGND cable should be connected
to the protection grounding bar of the equipment room.
 When the BBU3900 is installed in outdoor cabinets such as the APM30H, the PGND cable of
the BBU3900 should be connected to the grounding bar in the cabinet.
 When the BBU3900 is connected to the RRU, do not use optical cables that have
strengthening ribs.

3.4.2 Grounding Requirements of the RRU


 The PGND cable of the RRU is copper-based and insulated with the green and yellow plastic
jacket, and the cross-sectional area of the cable should be at least 16 mm2.

2019-09-22 HUAWEI Confidential Page 19, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

 The grounding resistance of the RRU should be less than 10 ohms.

3.4.3 Grounding Network Pavement


To ensure safe and reliable operation of the equipment, a good grounding system is essential. The
basic grounding facilities should be paved before the installation of the eNodeB to ensure the
smooth implementation of the project.

7. According to the mobile base station lightning protection specifications of Ministry of


Information Industry (MII), the preferred shape of the grounding network is the mesh shape.
The size of a grid should be equal to or larger than 3 m X 3 m. The intersection point of grids
should be connected with the vertical grounding body. The horizontal connection line
(horizontal grounding body) of the grids should be soldered with the vertical grounding body.
The soldering length should be twice of the overlapping length. The soldering point is at the
place 200 mm away from the top of the vertical grounding body.
8. The vertical grounding body should be buried to the depth equal to or larger than 800 mm.
(The depth is the distance between the bottom of the vertical grounding body to the ground.)
The spacing between grounding bodies should be equal to or larger than 1.5 times of the
length of the grounding body.
9. The grounding lead-in cables are soldered to the grounding network and two cables should be
led out symmetrically. The length of each cable should be equal to or less than 30 m. The
distance between the two points where the cables are led out should be equal to or larger than
5 m.
10. Anti-corrosive measures should be taken for each soldering point.
11. The grounding resistance should be equal to or less than 5 ohm. The chemical resistivity
reduction mixture can be used to reduce the grounding resistance. The salt, however, is not
recommended.
12. If the landform does not allow the use of the mesh-shape grounding network, other shape is
also acceptable. At places where activities of human beings or livestock are frequent, voltage-
sharing measures must be taken.
13. Requirements of grounding components:
− Vertical grounding body:Ф50 mm hot galvanized steel pipe (length: 2000 mm)
− or 50X50X5 mm hot galvanized steel angle (length: 2000 mm)
− Vertical grounding body: 40 X 4 mm hot galvanized flat steel. The length is determined by
the requirement.
− Grounding lead-in:40 X 4 mm hot galvanized flat steel. The length is determined by the
requirement.

3.5 Transmission Requirements for the eNodeB Site


Before the site construction, the transmission devices and auxiliary devices should be prepared
based on the practical application. Transmission requirements of the eNodeB site involve the ODF,
and transmission mode.

2019-09-22 HUAWEI Confidential Page 20, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

Requirements for ODF

If optical transmission is applied, and the optical cables on the eNodeB side are connected to the
transmission device through the ODF. The requirements for the ODF are listed as follows:

 The delivered transmission cables and connectors match the connectors on the ODF on the
transmission device side.
 Before you install the eNodeB, the ODF is installed and external optical cables are connected
to the ODF.
 It is recommended that the copper wires be used to connect the ODF and the grounding bar of
the equipment room.

Requirements for the Transmission Mode

 When the BBU3900 uses GE electric transmission, a 10 m long Ethernet cable is configured
for each site by default. When the required GE Ethernet cable for BBU3900 is longer than 10
m, provide the required length.
 Transmission resources should meet the upcoming requirements of the eNodeB site and extra
resources are reserved for capacity expansion.
 If the eNodeB is within the Line of Sight (LOS) of microwave transmission, and the
microwave transmission is used. The indoor units of the microwave transmission devices
should be installed in the space for the transmission devices in the cabinet.
 If the eNodeB is not within the Line of Sight (LOS) of microwave transmission, and the
xDSL transmission is used. It is recommended that the devices for xDSL transmission be
installed in the space reserved in the cabinet.

2019-09-22 HUAWEI Confidential Page 21, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

4 Construction Preparations of the DBS3900


TDLTE

4.1 Auxiliary Facilities Preparations for the DBS3900


TDLTE Site

4.1.1 Preparing the Cable Racks


14. Cable racks are classified into indoor cable racks and outdoor cable racks. The cable
racks should be installed before the installation of the eNodeB.
15. The recommended specifications of the indoor cable rack are as follows: width: 400 mm;
height: 2.4 m. The cable rack should be installed according to the engineering design.
16. Generally, the indoor cable rack is installed against a suspending lever. If the indoor
cable rack is installed against a wall, a tripod or ground support can be used.
17. The outdoor cable rack consists of the horizontal cable rack and the vertical cable rack.
The outdoor cable rack should be installed according to the engineering design.
18. The indoor cable rack is connected to the indoor grounding bar through cables. The
outdoor cable rack is welded to the lightning rod of the building through the reinforcing
steel bar, thus connecting to the antenna support. If required, wires should be added to
improve electric connectivity between the cable racks.

4.1.2 Preparing the Grounding System


The grounding system of the eNodeB consists of the indoor grounding system and the outdoor
grounding system.

shows the grounding grid of the eNodeB (the outdoor grounding system).

Figure Construction Preparations of the DBS3900 TDLTE-5 Grounding grid of the eNodeB

2019-09-22 HUAWEI Confidential Page 22, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

The grounding grids of the power transformer, tower, and equipment room constitute an integrated grounding
grid. (The grounding grid should be connected to the building and reinforced concrete bars of the tower.
Generally, the grounding grid should be connected to at least two reinforced concrete bars.)
The outdoor grounding ring can be laid out in L-shaped or C-shaped according to the field situation of the
equipment room. If the soil conductibility is poor or there is little soil in the rocky area, it is recommended that
the grounding extension style and concrete bridge be used. The cable embedded concrete bridge radiates
outwardly through the grounding ring and the four corners of the tower grounding ring. The concrete bridge
has strong hygroscopy. The recommended length of the concrete is 10 m to 30 m.

It is recommended that the grounding stake be coated with hot galvanized steel. The specifications
are as follows:

 steel pipe (Ф 50 mm, wall depth greater than 3.5 mm)


 angle steel (at least 50 mm X 50 mm X 5 mm)
 flat steel (at least 40 mm X 4 mm)

The proper length of the grounding stake is from 1.5 m to 2.5 m, and the interval is 1.5 to 2 times
the length of the grounding stake. The space between the top of the grounding stake and the ground
is at least 0.7 m. For cold districts, bury the grounding stake under the frozen soil.

The depth of the grounding ring must be 0.7 m under the concrete base.

You should determine whether to add resistivity reduction mixture based on the equipment room
location and soil conditions.

Figure Construction Preparations of the DBS3900 TDLTE-6 Grounding system of the eNodeB
equipment room (with dedicated rectifier)

2019-09-22 HUAWEI Confidential Page 23, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

The equipment room is configured with a primary grounding bar that is connected to the grounding grid
of all the equipment and the DC power inside the equipment room.
It is recommends that you use the galvanized flat steel of 40 mm x 4 mm or 50 mm x 5 mm as the
grounding cable. The part of the grounding cable outside the earth should be protected against
mechanical damage.

The outdoor grounding system consists of the tower grounding, feeder grounding, grounding grid,
rooftop surge protection grounding bar, cable rack grounding, and outdoor grounding copper
busbar.

Figure Construction Preparations of the DBS3900 TDLTE-7 Grounding of metal tower and
buildings

2019-09-22 HUAWEI Confidential Page 24, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

Ground the feeder pipe when it is on the tower, and before it is connected to the cable rack and routed
through the feeder window. If the tower is higher than 60 m, ground the feeder pipe in the middle of the
tower. The outdoor grounding copper bar should be installed under the outdoor feeder window and be
connected to the outdoor grounding ring. The feeders and indoor surge protector should be connected to
the outdoor grounding copper bar.

Figure Construction Preparations of the DBS3900 TDLTE-8 Grounding bar of the


eNodeB

1 M8 bolt

2019-09-22 HUAWEI Confidential Page 25, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

4.1.3 Preparing the Metal Pole


This section describes how to prepare the metal pole on which you can secure the RRU and
APM30H when launching a site on the rooftop.

The requirements for the metal pole at the DBS3900 TDLTE site are as follows:

 The metal pole is at least 1800 mm and the diameter of the metal pole ranges from 60 mm to
114 mm.
 The base is made of steel frame and concrete block. The dimensions of the base are 630 mm x
430 mm x 120 mm.
 The entire jointing surface is coated with antirust paint.
 The jointing is firm and there is no dry or open weld.
 If the metal pole for the RRU is within the surge protection coverage of the antenna, no
lightning rod is required on the top of the metal pole.
 If the metal pole for the RRU is not within the surge protection coverage of the antenna, a
lightning rod is required on the top of the metal pole. The metal pole should be connected
properly with the grounding grid.

Figure Construction Preparations of the DBS3900 TDLTE-9 Installing the metal pole on the
concrete floor

2019-09-22 HUAWEI Confidential Page 26, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

Figure Construction Preparations of the DBS3900 TDLTE-10 Two stay poles with a metal pole

shows two metal poles with a stay pole. The two metal poles are in I-shaped mode with a one-
meter-long beam in between. The stay pole helps to form a triangle support.

Figure Construction Preparations of the DBS3900 TDLTE-11 Two metal poles with a stay pole

2019-09-22 HUAWEI Confidential Page 27, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

4.2 Preparing Auxiliary Facilities for the DBS3900 Antenna


System

4.2.1 Requirements for the Tower


A tower for telecommunication purpose is required when the eNodeB in a network covers a wide
area and the antennas are installed at a height. Figure shows the tower for communication purpose.

Figure Construction Preparations of the DBS3900 TDLTE-12 Tower for telecommunication


purpose

2019-09-22 HUAWEI Confidential Page 28, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

The requirements for the tower are as follows:

 The height of the tower depends on the field requirements of the eNodeB.
 Typically, the tower has an operating platform of one to three layers with a round or hexagon
structure. The minimum diameter of the circle should be 4 m and the spacing between two
platforms should be 6 m. One-meter-high guard rails are required on the platforms. The
minimum weight-bearing capacity of the platforms should be 150 kg/m2.
 The tower must be able to carry 27 directional antennas and 27 7/8-inch feeders. Each antenna
should weigh 30 kg with the front face area of 0.5 mm2. Each feeder should be 0.49 kg/m
with the diameter 28 mm.
 A ladder for maintenance should be installed on the tower. The reinforcing angle steel should
be installed every 1 m on both sides of the ladder, and the angle steel should extend 0.5 m out
of the ladder on either side.
 A lightning rod should be installed 8 m above the upper platform to ensure that all the feeders
on the tower are within the coverage of the lightning rod.
 Even in the face of the strongest wind that blow once every 30 years, the maximum axial
wobble and torsion of the tower body must be within ±1°.
 The tower should be designed to resist one degree of seismic intensity over the limit
stipulated in local regulations. When earthquake occurs, the tower can withstand the
earthquake and devoid of any distortion that affects the quality of communication.
 A cable rack that can bear the weight of a person should be installed on the tower.

Surge protection and lightning induction devices should be installed on the tower.

 Solar energy lamps should be used for the tower.


 Power cables with metal jackets should be used for the aeronautical lights that use AC power.
Ensure that the metal jackets are grounded at the top of the tower and at positions where the
cables are led into the equipment room.
 Surge protection devices should be installed on the control cables of the tower lamps and on
the phase lines of the power cables at the positions where the cables are led into the
equipment room. The neutral lines are directly grounded.

The wind speed and earthquake intensity level comply with local stipulations.

4.2.2 Preparing the Antenna Support on the Tower


There are many types of antenna support. You need to select a suitable type according to the
antenna type and installation scenario.

When installing the antenna support on the tower, adhere to the following principles:

19. The installation plane of the antenna support is perpendicular to the horizontal plane.
20. The pole for the lightning rod should be installed separately on the tower. The lightning rod
should be placed high enough to bring the protection areas of all the antennas below 45°.

2019-09-22 HUAWEI Confidential Page 29, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

21. The antenna support should be installed in the direction that does not affect the
transmit/receive performance and direction adjustment regulation of the antenna.
22. A stiffener should be used to fasten the rotating lever. The expansion lever and the rotating
lever should be cut into proper length. The cross-section should be welded with a waterproof
cover.
23. The antenna support must not have any dry and open welds. It is recommended that the
support be made of galvanized steel. The surface of the support should be coated with antirust
paint.
24. For the directional antenna, the length of the pole depends on that of the antenna. In wide
coverage application, high gain antennas are generally used. Such antennas are long, so it is
recommended that the length of the pole be greater than 3 m and that the diameter range from
60 mm to 114 mm (generally 75 mm).For the uni-polarization antenna, the distance between
the two diversities of the two antennas serving one sector should be at least 2 m.
shows the recommended directional antenna support on a tower.

Figure Construction Preparations of the DBS3900 TDLTE-13 Directional antenna support


on a tower

25. Generally, an omni-directional antenna is a uni-polarization antenna. The distance


between diversities should be at least 2 m. The length of the support lever of pole should
be greater than 1.5 m. The pole must be made of 75 mm round steel and it should have a
length of 1 m and a diameter of 60–114 mm. During installation, the pole should be flush
with the fixing hoop of the antenna. The pole should not be installed at a very high
position because the omni-directional antenna is long. The top of the antenna should be
within the protection angle of the lightning rod.
shows the recommended support for the omni-directional antenna on a tower.

Figure Construction Preparations of the DBS3900 TDLTE-14 Support for the omni-
directional antenna on a tower

2019-09-22 HUAWEI Confidential Page 30, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

4.2.3 Preparing the Antenna Support on the Rooftop


There are many types of antenna support. You need to select a suitable type according to the
antenna type and installation scenario.

When installing the antenna support on the rooftop, adhere to the following principles:

26. The strength of the materials for the antenna support and pole should meet the requirements
of antenna load capacity and wind load.
27. The connecting pieces for the stiffener should be installed in the positions where the
regulation of the antenna orientation and tilt is not affected.
28. The antenna support should be perpendicular to the horizontal plane.
29. The base of the antenna support, the anchor of the stiffener, and their expansion bolts should
be covered with concrete.

When a directional antenna is installed on the rooftop, a lightning rod should be installed on the
antenna support, and the antenna support should be connected to the grounding grid of the
building. When an omni-directional antenna is installed on the rooftop, a lightning rod should be
installed onto a separate support. If a lightning rod is installed onto the support of the omni-
directional antenna, the omni-directional antenna should be extended from the support for 1 to 1.5
m. If there are enclosing walls on the rooftop, the antenna support can be installed on an enclosing
wall. Ensure that the main supporting post is vertical to the surface of the rooftop. In addition,
ensure that the antenna support is equipped with a surge protector and connected to the grounding
grid of the building.

Specifications of the directional antenna support and pole on a rooftop

(1) For the uni-polarization directional antenna, because of the requirements for diversity spacing,
the distance between the two poles supporting the two antennas should be at least.

2019-09-22 HUAWEI Confidential Page 31, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

(2) The length of the pole depends on that of the antenna. It is recommended that the length of the
pole be greater than 2.5 mm and that the diameter range from 60 mm to 114 mm.

The main supporting post of antenna support should be longer than the antenna. The relation
between h and d should meet the specifications illustrated in and listed in Table, where h indicates
the valid vertical distance between the lower edge of the antenna and the rooftop in the direction
that the antenna faces, and d indicates the distance between the edge of the rooftop in the direction
that the antenna faces and the antenna support.

Figure Construction Preparations of the DBS3900 TDLTE-15 Installing the antenna support on
the rooftop

Height Diameter

0.5 m 0 m to 2 m
1m 2 m to 10 m
2m More than 10 m

The Height and Diameter in the table above is shown in .

Figure Construction Preparations of the DBS3900 TDLTE-16

2019-09-22 HUAWEI Confidential Page 32, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

Figure 29.1 Structure of the pole on the rooftop

(1) Lightning rod for (2) Main support (3) Stiffener (4) Base of the
the antenna antenna support
(5) Use concrete to (6) Solder the (7) Fix the (8) Ladder
cover and fix. stiffener to the main stiffener to the
supporting post. ground.

and show how to fix the directional antenna on the rooftop.

Figure Construction Preparations of the DBS3900 TDLTE-17 Fixing the directional


antenna on the rooftop (1)

2019-09-22 HUAWEI Confidential Page 33, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

Figure Construction Preparations of the DBS3900 TDLTE-18 Fixing the directional


antenna on the rooftop (2)

2019-09-22 HUAWEI Confidential Page 34, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

Specifications of the omni-directional antenna support and pole on a rooftop

(1) Generally, an omni-directional antenna is a uni-polarization antenna. To meet the


requirements of diversity spacing, ensure that the distance between two antenna poles is
greater than 2 m.

(2) After installation, the top of the pole should be flush with the fixing hoop in the lower part
of the antenna. Therefore, the omni-directional antenna pole does not need to be long. The
length of the pole only needs to meet the specifications.

(3) Generally, the omni-directional antenna pole should have a diameter of 60 mm to110 mm
and should be made of 75 mm round steel.

(4) The omni-directional antenna is long and therefore the antenna top is much higher than the
pole top. In this case, the surge protector should not be welded directly to the pole but should
be installed separately in the middle of the two antenna poles. Ensure that the top of omni-
directional antenna is within the protection angle of the surge protector, as shown in .In some
cases, the surge protector may not be prepared independently due to limited conditions.
Instead, you can use the following method shown in .

and show the installation of omni-directional antenna.

Figure Construction Preparations of the DBS3900 TDLTE-19 Installing an omni-


directional antenna

2019-09-22 HUAWEI Confidential Page 35, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

Figure Construction Preparations of the DBS3900 TDLTE-20 Installing an omni-


directional antenna support

2019-09-22 HUAWEI Confidential Page 36, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

4.3 Cable Requirements of the eNodeB

4.3.1 Requirements for Materials of the Indoor eNodeB Cables


Generally, the power cables, grounding cables, and transmission cables are delivered with the
equipment. If you prepare these cables yourself, the cables should comply with related
requirements.

Table Construction Preparations of the DBS3900 TDLTE-3 Requirements for materials of the
indoor eNodeB cables

Cable Type Specification

Power cable The power cables without jackets should be insulated with PVC
materials. If the power cables are required to be weatherproof or
high/low-temperature resistant, materials such as silicone rubber, FEP,
or PFA can be used for insulation.
The power cables with PVC jackets should be insulated through PVC
or XLPE materials. If there are fire-resistant requirements such as
halogen-free and low smoke, use power cables with LSZH jackets.
The high/low-temperature resistant power cables should be coated with
FEP jackets.
Symmetric cable The symmetric cables should be insulated through PE, PP, or PVC
materials and coated with PVC or PE jackets. If there are fire-resistant
requirements such as halogen-free and low smoke, use power cables
with LSZH jackets.
Coaxial cable The coaxial cables should be insulated through PE, PTFE, or FEP
materials and coated with PVC or FEP jackets.
PGND cable The PGND cables should be copper-based and insulated with green
and yellow plastic jackets.

When selecting the indoor cables, you should consider the fire-resistant requirements. Weather proofing
requirements for the indoor cables are not high. Thus, use cables coated with PVC jackets as indoor cables.
If fire-resistant requirements for the cables are high, use cables that are insulated with fire-resistant materials
such as PE or PVC and coated with fire-resistant PVC jackets.
If there are strict requirements for smoke density, and transmittance of the halogen gas released after the
cables caught fire, use cables coated with comparatively expensive LSZH jackets.
Insulating materials and protection jackets of the cables must comply with the Restriction of Hazardous
Substance (RoHS) requirements.
The cable materials can either be customized or comply with local regulations.

2019-09-22 HUAWEI Confidential Page 37, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

4.3.2 Cabling Requirements for the eNodeB


The power cables and signal cables should be routed in compliance with the cabling specifications
to avoid electromagnetic interference to the signals.

Table Construction Preparations of the DBS3900 TDLTE-4 Requirements for Bending


Radius of the Cables

Cable Type Requirements for the


Bending Radius

Feeder 1/2" feeder ≥ 127 mm


7/8" feeder ≥ 250 mm
5/4" feeder ≥ 380 mm
13/8" feeder ≥ 510 mm
Jumper 1/4" jumper ≥ 35 mm
1/2" jumper ≥ 50 mm
Single-jacket cable 2.5 mm ≤ D ≤ 4.5 mm R≥2D
D ≥ 4.5 mm R≥3D
Two-wire or multi-wire 6.5 mm ≤ D ≤ 12.5 mm R≥2D
cables with or without
shielding layers D ≥ 12.5 mm R≥3D

Optical cable R ≥ 20 D

In the preceding table, D refers to the diameter of the cable jacket and R refers to the bending radius of the
cable.

Requirements for Binding Cables

 Cables of different types should be routed separately and cannot be kinked.


 The cables should be bound tightly and neatly without damage to cable jackets.
 The cable ties should be at an interval of 200 mm and face the same direction. The cable ties
at the same position should be placed at the same level. The cut surface of the cable ties
should be smooth without sharp projections.
 Labels should be attached to the cables after installation.

General Cabling Specifications

 Cables of different types should be routed separately.


 Cables of different types cannot be crossed.

2019-09-22 HUAWEI Confidential Page 38, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

 The spacing between cables of different types should be greater than 30 mm when the cables
are routed parallel in the cabinet. The spacing between cables of different types should be
greater than 100 mm when the cables are routed parallel outside the cabinet. If such
requirements cannot be met, the cables should be separated with specific objects.

Cabling Requirements for Power Cables and PGND Cables

 The power cables and PGND cables should be routed in compliance with the engineering
design and general cabling specifications. If the cable is not long enough, replace the cable.
Do not add connectors or solder joints to lengthen the cable.
 The cables should be insulated if they are bound and routed on the metal cable rack.
 Fuses or switches are not allowed on the cables.
 The -48 V power cable and the GND cable should be bound together.
 Both ends of the grounding cables should be anti-corrosive and anti-rust. Connections of the
grounding cables should be secure.
The low-voltage AC power cable for the base station should be led through a metallic conduit
and buried in the ground for at least 50 m before it is led into the equipment room. If the AC
power cable is shorter than 50 m, it should be completely routed under the ground. If such
cables are routed overhead and led into the room, surge protection for the connectors of the
AC power cables are seriously affected. The PGND cable should be buried in the ground or
routed indoors. The PGND cable cannot be routed overhead outdoors before it is led into the
equipment room.

Cabling Requirements for Optical Cables

 The optical cables should be routed in compliance with the engineering design and general
cabling specifications.
 Proper cable surpluses should be left at the turning of the optical cables.
 Do not stretch, step over, or place heavy objects on the optical cables. Keep the cables away
from sharp objects to avoid damage. The optical cable that is curved or pressed or the optical
connector that is damaged cannot be used.
 Extra optical cables should be coiled on the specified device such as the fiber coiler. Use
moderate force to coil the optical cables. Do not bend the cables forcibly lest they be
damaged.
 If unprotected bare fibers are used, the protection tubes can be adopted as required.
 The idle connectors of the optical cables should be covered with dustproof caps.
 If one end of the optical cable is connected to an optical device, do not look directly at the
optical connector to prevent your eyes from being damaged by the infrared laser emitted by
the optical port.
 Fill soft materials such as fireproof cottons in the optical cable inlets at the top of the cabinet
to protect the optical cables.
 You need to check whether the optical connectors are clean before installation. If the optical
connectors are dirty, clean them by using the dust free cloth or fiber cleaner.

2019-09-22 HUAWEI Confidential Page 39, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

4.4 Preparation of Personnel for the Installation


The equipment installation process is also a process of on site training. It is recommended that the
maintenance personnel participate in the training. In this way, the maintenance personnel can get
familiar with the equipment as soon as possible.

2019-09-22 HUAWEI Confidential Page 40, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

5 Appendix 1 Checklist for the Installation


Preparations

5.1 Acceptance Items for the Environment of the


Equipment Room
Acceptance Item Methods and Specification Result Remarks
Requirements

Height of the Minimal distance 3 m to 3.5 m


equipment room between the girder and
the floor
Load bearing capacity Load bearing capacity Greater than 450kg/m2
of the floor
Wall surface . The mat vanish does
not chalk off easily.
Floor The floor should be ESD floor
made from
semiconductor and be
dustproof.
Temperature Long-term –20℃ to +50℃
Humidity Long-term 5% RH to 100% RH
Electromagnetic Electric field Within 300 mV/m
interference proof
Magnetic field Less than 11 Gs
Antistatic Measures ESD floor
ESD ground
Dust proof The diameter of the dust granule should be

2019-09-22 HUAWEI Confidential Page 41, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

Acceptance Item Methods and Specification Result Remarks


Requirements

greater than 5 μm.


The density of the dust granule should be less
than 3 x 104 granule/m.3
Quake proof Design the degree of Raise one degree
seismic intensity for
the equipment room
according to the local
capital construction.
Lighting Avoid direct radiation Average intensity of
of sunlight. illumination: 150–200
LX
Air conditioner Type and power The refrigerating
output should meet the
requirements for the
temperature control of
the equipment room.
Fire fighting Firefighting equipment Meet the local fire
and label fighting standard
Label the sockets of
different voltages.

5.2 Acceptance Items for Power Supply


Item Test Result Specification Result Remarks

DC power supply –48 V DC power supply -38 V DC to -57 V DC


AC power supply Single-phase AC power 176 V AC to 290 V AC.
Three-phase AC power 176 /304 V AC to
290/500 V AC.
Standby diesel Recommended Good
Power cables Route the –48 V power Good
cables into the PDF or the
junction box.
Power alarms Alarms related to power cut Good
and power supply faults can
be reported.
Fuse (APM30H) RRU 20A

2019-09-22 HUAWEI Confidential Page 42, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

BBU 12A
Main Switch (for Three-phase 220v/380v AC 20A~32A
APM30H)
Dual-live-wire 110V AC/ 40A~50A
Single-phase 220V AC/
Dual-live-wire 120V AC

5.3 Acceptance Items for Surge Protection Grounding


Test Item Methods and Specification Result Remarks
Requirements

Main grounding bar The distance between The installation is


and sub-grounding the copper bar and the complete and the
bars copper cable should be contact is proper.
short and the PGND
cable should be thick.
The PGND cables of The installation is
all devices are complete and the
connected to the same contact is proper.
grounding busbar.
Cross-sectional area of BBU3900 Not less than 6 mm2
the PGND cable
RRU3211/RRU3233 Not less than 16 mm2
Grounding resistance Combined grounding eNodeB grounding:
less than 10 
PGND cable Route the grounding Good
cable into the DC PDF
or the junction box.
Feeder grounding Grounding clips are The installation is
installed at an interval complete and the
of 20 m on the feeder. contact is proper.
The feeder is
respectively grounded
0.5 m to 1 m away
from the tower and the
outdoor cable rack.

2019-09-22 HUAWEI Confidential Page 43, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

5.4 Acceptance Items for the eNodeB Antenna System


Serial No. Item Specific Requirements Result Remarks

1 Tower The tower is ready for use.

2 Antenna They should meet the requirements for azimuth


support and of the antenna.
pole
The pole should meet the requirements for the
length of the antenna.
The pole should meet the requirements for the
load capacity and wind load.
3 Outdoor cable The outdoor cable ladder is ready for use.
ladder
The cable ladder on the tower should be
suitable for routing cables.
The cable rack (bridge) should meet the
requirements.
4 Pole The pole is installed.

The position of the pole should meet the


requirements.
The pole should meet the requirements for the
length of the antenna.
The pole should meet the requirements for the
load capacity and wind load.
The concrete base for the GPS antenna is ready
for use.
5 Outdoor cable The outdoor cable rack is ready for use.
rack
Material of the cable rack should meet the
requirements.
The cable rack should be properly grounded.

Fill in the grey part in the table above when the antenna is installed on the tower platform.

2019-09-22 HUAWEI Confidential Page 44, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation Use for Internal

6 Appendix 2 Specifications of the DBS3900

6.1 Engineering specifications


Item Specification Weight Voltage Power Consumption

BBU3900 86mm×442mm× ≤12kg(fullc -48V DC (- 150W (1LBBP + 1LMPT)


310mm onfiguratio 38.4V DC ~
n) -57V DC) 225W(2LBBP + 1LMPT)

+24V DC 300W(3LBBP + 1LMPT)


(+21.6V
DC ~ +29V
DC)
RRU3211 480mm×356mm ≤ 19kg -48V DC(- 180W (2x20W, 100% load)
×120mm (without 36V DC ~
(without housing) -57V DC)
housing)
≤20kg (with
485mm×377mm housing)
×157.6mm (with
housing)
RRU3233 550mm×320mm×1 ≤ 25kg -48V DC(- 370W (8x10W, 100% load)
35mm (without (without 36V DC ~
housing) housing) -57V DC)

2019-09-22 HUAWEI Confidential Page 45, Total 46


Guide to Customer’s Preparation for DBS3900 TDLTE Installation INTERNAL

6.2 Environment Specifications


Item Temperature Relative Protection Air pressure
humidity degree

BBU3900 –20°C to +55°C 5% RH ~ 95% IP20 70 kPa ~ 106


RH kPa
RRU3211 -40℃~+50℃(1120 5% RH~100% IP65
W/m² solar RH
radiation)
RRU3233
-40℃~+55℃
(without solar
radiation)

2019-09-22 HUAWEI Confidential Page 46, Total 46

You might also like