Jul-19 Aug

SCOPE OF WORKS
30 31 1 2 3 4 5 6 7 8
Mobilize to site
Attend Required orientation Seminar, if any
Conduct initial evaluation.
Electrical Inspection and Instrumentation testing:
Winding Resistance Test
Insulation Resistance Test
Polarization Index Test
Surge Comparison Test
Check Heaters & RTD's
Dis-assembly, marking provision on all motor parts
Mechanical visual inspection and testing.
Conduct bearing housing & Journal Clearances check
Remove contaminants on the winding.
Wash the winding using chemical wash
Oven Baking, monitor to cure winding, conduct Insulation Testing
Apply class F insulating varnish and bake to cure.
Cool down and remove excess varnish.
Clean all motor parts and accessories.
Install Brand new bearings. Separate proposal
Assemble the motor
Install & Couple to Compressor
Witness testing and commissioning.
Perform quality control test:
Insulation Resistance Test
Winding Resistance Test
Polarization Index Test
Test run without load and monitor
Voltage
Current
Speed
Submit test report.
Demobilize