Manpower Schedule

Cleaning & Common Structure Backfill with Spreading


Description Grubbing Excavation Excavation & Compaction

Project Engineer 1 1 1 1
Construction Foreman 1 1 1 1
Skilled Labours 2 4 4 4
Laborers 10 10 6 10
Concrete Structure Rubble Furnishing, Cutting, Bending & Grouted Gravel
211 ksc, Class A Masonry Installation of Rein. Steel Bars Riprap Bedding

1 1 1 1 1
1 1 1 1 1
4 4 4 4 4
10 10 10 10 10
Filter Drain with Fabrication and Installation Clearing & Road
Weep Holes of Steel Gate Grubbing Embankment

1 1 1 1
1 1 1 1
8 4 4 4
10 6 10 10
Aggregate Sub-base
Coarse/Graveling

1
1
4
6