4.

Equipment Details :

5. General Inspection : OK

6. Insulation Resistance Test:

Applied Voltage: 5000 V DC Duration: 1 Min.

Condition Measured IR Values in (GΩ)

R-R’ Y-Y’ B-B’


Open
6.47 6.57 5.73

RE YE BE

Close 3.56 3.18 3.52

RY YB BR

5.28 7.68 7.08

5. CAPM Relay Service Settings (For Autorecloser):

PHASE OC E/F OC
Phase Set 20 A Earth Set 10 A

6. Primary Injection Test:

6.1. Phase OC:

Phase Ref. Set Current (A) Operated Current (A)


RY 20 19.7
YB 20 19.7
BR 20 19.7

6.2. Earth Fault OC:

Set Current Injected Operated Current in CAPM


Phase Ref.
(A) Current(A) Relay(A)

Z
Connection 10 3.4 10
(RYB)
7. Functional Check:

1 Manual ON & OFF OK 8.


2 Local ON & OFF through CAPM OK
3 Over Current and Earth Fault Trips through Primary injection Test OK
Checked ON & OFF and Measurements through WSOS Software by USB OK
4
connection with CAPM
Remarks : Test result of Autorecloser is found satisfactory.