Jumlah Machine Produksi dan penunjang Produksi ( PT.

CENTEX )
DEPT Jumlah
SPINNING Set Unit
1 Blowing 3
2 Carding 19
3 Combing Preparation 3
4 Carding 10
5 PRE-DRAWING 4
6 DRAWING 15
7 ROVING 7
8 RING SPINNING FRAME ( RSF ) 60
9 WINDER 14
WEAVING Set Unit
1 WINDER 3
2 WARPER 2
3 SIZING 2
4 DRAWING-IN 1
5 AIR JET LOOM ( AJL ) 147
6 INSPECTION 4
DYEING Set Unit
1 PRE-TREATMENT 1
2 MERCERISING 1
3 HEAT SET 1
4 ROLL DRYER ( RD ) 2
5 BAKING SOME 1
6 STEAMER 2
7 RESIN FINISH 1
8 SANFORISING 2
9 CALENDER 1
10 INSPECTION 7
11 HEAT CUT 1
12 FORKLIFT 7
UTILITY Set Unit
1 BOILER 11
2 COMPRESSOR 6
3 IPAL ( WWT ) 1