ANALISA BIAYA KONSTRUKSI PEKERJAAN BESI DAN ALUMINIUM


1.) Memasang 1Kg Besi Profil
Bahan : 1.150 Kg Besi Profil @ Rp. 52,300.00 = Rp. 60,145.00
= Rp. 60,145.00
Upah : 0.060 Oh Pekerja @ Rp. 96,000.00 = Rp. 5,760.00
0.060 Oh Tukang Las @ Rp. 120,000.00 = Rp. 7,200.00
0.006 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 780.00
0.0030 Oh Mandor @ Rp. 150,000.00 = Rp. 450.00
= Rp. 14,190.00
Jumlah = Rp. 74,335.00

2.) Memasang 1Kg Rangka Kuda-Kuda Baja IWF


Memasasng 1Kg Besi
1.150
Profil
Kg Besi Baja IWF @ Rp. 52,300.00 = Rp. 60,145.00
= Rp. 60,145.00
Upah : 0.060 Oh Pekerja @ Rp. 96,000.00 = Rp. 5,760.00
0.060 Oh Tukang Las @ Rp. 120,000.00 = Rp. 7,200.00
0.006 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 780.00
0.0030 Oh Mandor @ Rp. 150,000.00 = Rp. 450.00
= Rp. 14,190.00
Jumlah = Rp. 74,335.00

2.) Memasang 1Kg Rangka Plafond Hollow


Memasasng 1Kg Besi
1.150
Profil
Kg Hollow 40x20x2 @ Rp. 34,200.00 = Rp. 39,330.00
= Rp. 39,330.00
Upah : 0.060 Oh Pekerja @ Rp. 96,000.00 = Rp. 5,760.00
0.060 Oh Tukang Las @ Rp. 120,000.00 = Rp. 7,200.00
0.006 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 780.00
0.0030 Oh Mandor @ Rp. 150,000.00 = Rp. 450.00
= Rp. 14,190.00
Jumlah = Rp. 53,520.00

3.) Mengerjakan 100 Kg Pekerjaan Perakitan


Bahan : 1.000 Litter Solar @ Rp. 7,100.00 = Rp. 7,100.00
0.100 Litter Minyak Pelumas @ Rp. 44,800.00 = Rp. 4,480.00
= Rp. 11,580.00
Upah : 0.100 Oh Pekerja @ Rp. 96,000.00 = Rp. 9,600.00
0.100 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 12,000.00
0.001 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 130.00
0.0050 Oh Mandor @ Rp. 150,000.00 = Rp. 750.00
= Rp. 22,480.00
Alat : 0.008 Jam Sewa Alat @ Rp. 150,000.00 = Rp. 1,200.00
= Rp. 1,200.00
Jumlah = Rp. 35,260.00

4.) Membuat 1M2 Pintu Besi Plat Baja Tebal 2mm Rangkap, Rangka Baja Siku
Bahan : 15.000 Kg Besi Siku L : 40.40.4 @ Rp. 4,715.00 = Rp. 70,725.00
32.800 Kg Besi Plat Baja @ Rp. 3,985.11 = Rp. 130,711.49
0.050 Kg Kawat Las @ Rp. 25,650.00 = Rp. 1,282.50
= Rp. 202,718.99
Upah : 1.050 Oh Pekerja @ Rp. 96,000.00 = Rp. 100,800.00
1.050 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 126,000.00
0.1050 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 13,650.00
0.0520 Oh Mandor @ Rp. 150,000.00 = Rp. 7,800.00
= Rp. 248,250.00
Jumlah = Rp. 450,968.99

5.) Mengerjakan 1 cm Pengelasan dengan Las Listrik


Bahan : 0.040 Kg Kawat Las Listrik @ Rp. 25,650.00 = Rp. 1,026.00
0.030 Liter Solar @ Rp. 7,100.00 = Rp. 213.00
0.004 Liter Minyak Pelumas @ Rp. 44,800.00 = Rp. 179.20
= Rp. 1,418.20
Upah : 0.004 Oh Pekerja @ Rp. 96,000.00 = Rp. 384.00
0.002 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 240.00
0.0002 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 26.00
0.0002 Oh Mandor @ Rp. 150,000.00 = Rp. 30.00
= Rp. 680.00
Alat : 0.017 Jam Sewa Alat @ Rp. 150,000.00 = Rp. 2,550.00
= Rp. 2,550.00
Jumlah = Rp. 4,648.20

Bahan : 2.767 Kg Besi Holo 4x4 t=2.3mm @ Rp. 7,033.33 = Rp. 19,458.89

11.110 Cm Pengelasan @ Rp. 4,648.20 = Rp. 51,641.50


Rp. 71,100.39
Upah : 1.000 Oh Pekerja @ Rp. 96,000.00 = Rp. 96,000.00
1.000 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 120,000.00
0.0002 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 26.00
0.0002 Oh Mandor @ Rp. 150,000.00 = Rp. 30.00
216,056.00
Rp. 287,156.39

6.) Membuat 1 m pengaman jendela


Bahan : 0.900 M Besi Nako @ Rp. 12,000.00 = Rp. 10,800.00
9.870 Cm Pengelasan @ Rp. 4,648.20 = Rp. 45,877.73
= Rp. 56,677.73
Upah : 0.043 Oh Pekerja @ Rp. 96,000.00 = Rp. 4,128.00
0.043 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 5,160.00
0.0043 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 559.00
0.0021 Oh Mandor @ Rp. 150,000.00 = Rp. 315.00
= Rp. 10,162.00
Jumlah = Rp. 66,839.73
6.) Membuat 1 m Kusen Pintu Aliminium
Bahan : 1.100 M Prifil Aluminium @ Rp. 51,866.67 = Rp. 57,053.33
2.000 Buah Skrup Fixer @ Rp. 700.00 = Rp. 1,400.00
0.060 Tube Sealant @ Rp. 15,000.00 = Rp. 900.00
= Rp. 59,353.33
Upah : 0.043 Oh Pekerja @ Rp. 96,000.00 = Rp. 4,128.00
0.043 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 5,160.00
0.0043 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 559.00
0.0021 Oh Mandor @ Rp. 150,000.00 = Rp. 315.00
= Rp. 10,162.00
Jumlah = Rp. 69,515.33

7.) Memasang 1 m2 Pintu Aliminium Strip Lebar 8 Cm


Bahan : 4.400 M Prifil Aluminium @ Rp. 51,866.67 = Rp. 228,213.33
14.600 M Aluminium Strip @ Rp. 51,866.67 = Rp. 757,253.33
= Rp. 985,466.67
Upah : 0.085 Oh Pekerja @ Rp. 96,000.00 = Rp. 8,160.00
0.085 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 10,200.00
0.0085 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 1,105.00
0.0042 Oh Mandor @ Rp. 150,000.00 = Rp. 630.00
= Rp. 20,095.00
Jumlah = Rp. 1,005,561.67

8.) Memasang 1 m2 Pintu Kaca Rangka Aluminium


Bahan : 4.400 M Prifil Aluminium @ Rp. 51,866.67 = Rp. 228,213.33
4.500 M Profil Kaca @ Rp. 135,850.00 = Rp. 611,325.00
0.270 Tube Sealant @ Rp. 15,000.00 = Rp. 4,050.00
= Rp. 843,588.33
Upah : 0.085 Oh Pekerja @ Rp. 96,000.00 = Rp. 8,160.00
0.085 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 10,200.00
0.0085 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 1,105.00
0.0042 Oh Mandor @ Rp. 150,000.00 = Rp. 630.00
= Rp. 20,095.00
Jumlah = Rp. 863,683.33

9.) Memasang 1 m2 Terali Besi Strip (2x3)mm


Bahan : 6.177 Kg Besi Strip @ Rp. 67,500.00 = Rp. 416,947.50
27.080 Cm Pengelasan @ Rp. 4,648.20 = Rp. 125,873.26
= Rp. 542,820.76
Upah : 1.670 Oh Pekerja @ Rp. 96,000.00 = Rp. 160,320.00
1.670 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 200,400.00
0.1670 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 21,710.00
0.0830 Oh Mandor @ Rp. 150,000.00 = Rp. 12,450.00
= Rp. 394,880.00
Jumlah = Rp. 937,700.76

10.) Memasang 1 m2 Kawat Nyamuk


Bahan : 1.100 M2 Kawat Nyamuk @ Rp. 26,200.00 = Rp. 28,820.00
11.110 cm Pengelasan @ Rp. 4,648.20 = Rp. 51,641.50
1.716 Kg Baja Strip 0.2x2 cm @ Rp. 57,250.00 = Rp. 98,241.00
= Rp. 178,702.50
Upah : 0.100 Oh Pekerja @ Rp. 96,000.00 = Rp. 9,600.00
0.100 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 12,000.00
0.0100 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 1,300.00
0.0050 Oh Mandor @ Rp. 150,000.00 = Rp. 750.00
= Rp. 23,650.00
Jumlah = Rp. 202,352.50

11.) Memasang 1 m' Talang Datar/Jurai Seng BJLS 0.28 Lebar 90


Bahan : 1.050 M' Seng Plat @ Rp. 18,300.00 = Rp. 19,215.00
0.015 Kg Paku 1cm-2,5cm @ Rp. 15,700.00 = Rp. 235.50
0.019 M3 Papan Kayu Klas II @ Rp. 3,657,500.00 = Rp. 69,492.50
= Rp. 88,943.00
Upah : 0.200 Oh Pekerja @ Rp. 96,000.00 = Rp. 19,200.00
0.400 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 48,000.00
0.0250 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 3,250.00
0.0010 Oh Mandor @ Rp. 150,000.00 = Rp. 150.00
= Rp. 70,600.00
Jumlah = Rp. 159,543.00

12.) Memasang 1 m' Talang 1/2 Lingkaran D-15 cm, Seng BJLS 0.30 Lebar 45
Bahan : 1.050 M' Seng Plat @ Rp. 18,300.00 = Rp. 19,215.00
0.010 Kg Paku 1cm-2,5cm @ Rp. 15,700.00 = Rp. 157.00
0.500 Kg Besi Strip @ Rp. 57,250.00 = Rp. 28,625.00
= Rp. 47,997.00
Upah : 0.150 Oh Pekerja @ Rp. 96,000.00 = Rp. 14,400.00
0.300 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 36,000.00
0.030 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 3,900.00
0.007 Oh Mandor @ Rp. 150,000.00 = Rp. 1,050.00
= Rp. 55,350.00
Jumlah = Rp. 103,347.00

12.) Memasang 1 m' Talang 1/2 Lingkaran D-15 cm, Seng BJLS 0.30 Lebar 45
Bahan : 1.050 M' Seng Plat @ Rp. 18,300.00 = Rp. 19,215.00
0.010 Kg Paku 1cm-2,5cm @ Rp. 15,700.00 = Rp. 157.00
0.500 Kg Besi Strip @ Rp. 11,775.00 = Rp. 5,887.50
= Rp. 25,259.50
Upah : 0.150 Oh Pekerja @ Rp. 96,000.00 = Rp. 14,400.00
0.300 Oh Tukang Besi @ Rp. 120,000.00 = Rp. 36,000.00
0.030 Oh Kepala Tukang @ Rp. 130,000.00 = Rp. 3,900.00
0.007 Oh Mandor @ Rp. 150,000.00 = Rp. 1,050.00
= Rp. 55,350.00
Jumlah = Rp. 80,609.50