SCHEDULE DAN MONTORING PENYELESAIAN ABD DAN FQ. MAIN ROAD TANAH BAKTER 1 DAN 2
PELAKSANAAN PEKERJAAN PEMBANGUNAN BAGIAN PEKERJAAN II JALAN TOL
RUAS BAKAUHENI - TERBANGGI BESAR
PAKET 2 SIDOMULYO - KOTABARU
(STA. 39+400 - 80+000)
ADIT/TONI 2 39+400 sd 45+000 5,600 Revisi Gbr. (Input Tabel, Disposal) 1125 1975 1,500 700 100 200 5600 100%
NIKO
TONY/NIKO 3 45+000 sd 51+000 6,000 Revisi Gbr. (Input Tabel, Disposal) 575 3425 1,000 700 100 - 5800 97%
YOVAN/RICKY 4 51+000 sd 57+000 6,000 Revisi Gbr. (Input Tabel, Disposal) 1550 1450 1,000 500 1,000 325 5825 97%
RICKY/BOY 5 57+000 sd 63+000 6,000 Revisi Gbr. (Input Tabel, Disposal) 1000 2000 2,000 1,000 - - 6000 100%
YOVAN
NANA/FERDY 6 63+000 sd 69+000 6,000 Revisi Gbr. (Input Tabel, Disposal) 2000 2000 700 1,300 - - 6000 100%
FERDI/WAHYU 7 69+000 sd 74+350 5,350 Revisi Gbr. (Input Tabel, Disposal) 1000 2350 2,000 - - - 5350 100%
NANA, FERDY, DAN TEAM 2 BOX UNDERPASS 10 Revisi Gbr. (Input Tabel, Disposal) 0 0%
RENCANA
CLOSE
PROSES