ITEMIZED QUANTITIES FOR BOX CULVERTS

EXCAVATION EXCAVATION PE SHEET PE SHEET LEAN LEAN REBARS REBARS CONCRETE CONCRETE BITUMEN BITUMEN BACKFILL BACKFILL
NUMBER
ACTUAL COMPLETED ACTUAL COMPLETED ACTUAL COMPLETED ACTUAL COMPLETED ACTUAL COMPLETED ACTUAL COMPLETED ACTUAL COMPLETED

CWCS 006 842.00 76 18 cu.m. 11,370 147 336 464 cu.m.

CWCS 007 290.70 on going 50.22 6.0 4,583 45 106 131.33

CWCS 008 290.70 50.22 6.0 4,583 45 106 131.33

CWCS 009 290.70 50.22 6.0 4,583 45 106 131.33

CWCS 010 290.70 on going 50.22 6.0 4,583 45 106 131.33

CWCS 011 464.96 464.96 96.50 96.50 10 10 6,874 69 156 174.13

CWCS 012 194.83 194.83 73.60 73.60 8.0 8.0 6,162 61 144 160.00

CWCS 014 181.90 181.90 98 98 14 14 9,363 4,142 83 180 129.00

CWCS 015 181.90 181.90 98 98 14 14 9,363 4,142 83 180 129.00

CWCS 016 181.90 181.90 98 98 14 14 9,363 4,142 83 180 129.00

CWCS 017 181.90 181.90 98 98 14 14 9,363 4,142 83 180 129.00

CWCS 019 244.30 on going 86 11 7,712 56 138 212.00