You are on page 1of 34

https://mechzoneblog.files.wordpress.

com/2017/10/180-
top-production-technology-question-and-answers.pdf 6. Material handling in automobile
180 TOP Production Technology - Mechanical Engineering
Multiple choice Questions and Answers Latest Production
industry is done by
Technology (a) overhead crane
1. Work study is concerned with (b) trolley
(a) improving present method and (c) belt conveyor
finding standard time (d) all of the above
(b) motivation of workers (e) none of the above. Ans: a
(c) improving production
capability 7. String diagram is used when
(d) improving production planning (a) team of workers is working at
and control a place
(e) all of the above. (b) material handling is to be done
Ans: a (c) idle time is to be reduced
(d) all of the above
2. Basic tool in work study is (e) none of the above.
(a) graph paper Ans: a
(b) process chart
(c) planning chart 8. Work study is most useful
(d) stop watch (a) where production activities are
(e) analytical mind. involved
Ans: d (b) in judging the rating of
machines
3. What does symbol 'O' imply in (c) in improving industrial
work study relations
(a) operation (d) in judging the output of a man
(b) inspection and improving it
(c) transport (e) where men are biggest
(d) delay/temporary storage contributor to success of a project.
(e) none of the above. Ans: a
Ans: a
9. Micromotion study is
4. What does symbol 'D' imply in (a) enlarged view of motion study
work study (b) analysis of one stage of motion
(a) inspection study
(b) transport (c) minute and detailed motion
(c) delay/temporary storage study
(d) permanent storage (d) subdivision of an operation into
(e) none of the above. therbligs and their analysis
Ans: (e) motion study of small
5. What does symbol 'V' employ in components upto mirco-seconds.
work study Ans: d
(a) operation
(b) inspection
(c) delay/ temporary Storage
(d) permanent storage
(e) none of the above.
Ans: d
10. In micromotion study, therblig 15. Scheduling gives information
is described by about
(a) a symbol (a) when work should start and
(b) an event how much work should be
(c) an activity completed during a certain period
(d) micro motions (b) when work should complete
(e) standard symbol and colour. (c) that how idle time can be
Ans: e minimized
(d) proper utilisation of machines
11. The allowed time for a job (e) none of the above.
equals standard time plus Ans: a
(a) policy allowance
(b) interference allowance 16. Expediting function consists in
(c) process allowance keeping a watch on
(d) learning allowance (a) operator's activity
(e) unforeseen allowance. (b) flow of material and in case of
Ans: a trouble locate source of trouble
(c) minimising the delays
12. Micromotion study involves (d) making efficient despatching
following number of fundamental
hand motions 17. Choose the wrong statement
(a) 8 Time study is used to
(b) 12 (a) determine overhead expenses
(c) 16 (b) provide a basis for setting
(d) 20 piece prices or incentive wages
(e) 24 (c) determine standard costs
Ans: c (d) determine the capability of an
operator to handle the number of
13. The standard time for a job is machines
(a) total work content (e) compare alternative methods.
(b) base time + relaxation time Ans: a
(c) total work content + basic time
(d) total work content + delay 18. Job evaluation is the method-
contingency allowance of determining the
(e) total work content + relaxation (a) relative worth of jobs
time. (b) skills required by a worker
Ans: d (c) contribution of a worker
(d) contribution of a job
14. Work study is done with the (e) effectiveness of various
help of alternatives.
(a) process chart Ans: a
(b) material handling
(c) stop watch 19. Micromotion study is
(d) all of the above (a) analysis of a man-work
(e) none of the above. method by using a motion picture
Ans: c camera with a timing device in the
field of view
(b) motion study* observed on 24. One time measurement unit
enhanced time intervals (TMU) in method time
(c) motion study of a sequence of measurement system equals
operations conducted (a) 0.0001 minute
systematically (b) 0.0006 minute
Ans: a (c) 0.006 minute
20. Per cent idle time for men or (d) 0.001 minute
machines is found by (e) 0.06 minute.
(a) work sampling Ans: b
(b) time study
(c) method study 25. Basic motion time study gives
(d) work study times for basic motions in ten
(e) ABC analysis. thousandths of
Ans: a (a) second
(b) minute
21. TMU in method time (c) hour
measurement stands for (d) day
(a) time motion unit (e) none of the above.
(b) time measurement unit Ans: b
(c) time movement unit
(d) technique measurement unit 26. Choose the wrong statement.
(e) time method unit. Motion study is used for
Ans: b (a) improving a work method
(b) improvising a work method
22. Time study is (c) designing a work method
(a) the appraisal, in terms of time, (d) providing a schematic
of the value of work involving framework
human effort (e) reducing inventory costs.
(b) machine setting time Ans: e
(c) time taken by workers to do a
job 27. Gantt chart provides
(d) method of fixing time for information about the
workers (a) material handling
(e) method of determining the (b) proper utilisation of manpower
personnel Requirement. (c) production schedule
Ans: a (d) efficient working of machine
(e) all of the above.
23. Work sampling observations Ans: c
are taken on the basis of
(a) detailed calculations 28. ABC analysis deals with
(b) convenience (a) analysis of process chart
(c) table of random numbers (b) flow of material
(d) past experience (c) ordering schedule of job
(e) fixed percentage of daily (d) controlling inventory costs
production. money
Ans: c (e) all of the above.
Ans: d
33. The most important objective
29. Process layout is employed for behind plant layout is
(a) batch production (a) overall simplification, safety of
(b) continuous type of product integration
(c) effective utilisation of (b) economy in space
machines (c) maximum travel time in plant
(d) all of the above (d) to provide conveniently located
(e) none of the above. shops
Ans: a (e) to avoid any bottlenecks.
Ans: a
30. For a product layout the
material handling equipment must 34. The process layout is best
(a) have full flexibility suited where
(b) employ conveyor belts, trucks, (a) specialisation exists
tractors etc. (b) machines are arranged
(c) be a general purpose type according to sequence of
(d) be designed as special purpose operation
for a particular application (c) few number of non-
(e) arranging shops according to standardised units are to be
specialization of duties. produced
Ans: d (d) mass production is envisaged
(e) bought out items are more.
31. Travel charts provide Ans: c
(a) an idea of the flow of materials
at various stages 35. A low unit cost can be obtained
(b) a compact estimate of the by following
handling which must be done (a) product layout
between various work sections (b) functional layout
(c) the information for changes (c) automatic material handling
required in rearranging material equipment
handling equipment (d) specialisation of operation
(d) an approximate estimate of (e) minimum travel time plan and
the handling which must be done com¬pact layout.
at a particular station Ans: a
(g) solution to handling techniques
to achieve most optimum^ 36. Military organisation is known
results. as
Ans: b (a) line organisation
(b) line and staff organisation
32. Product layout is employed for (c) functional organisation
(a) batch production (d) all of the above
(b) continuous production (e) none of the above.
(c) effective utilization of machine Ans: a
(d) all of the above
(e) none of the above.
Ans: b
37. The main disadvantage of line 41. The most popular type of
organisation is organisation used for Civil
(a) top level executives have to do Engineering Constructions is
excessive work (a) line organisation
(b) structure is rigid (b) line and staff organisation
(c) communication delays occur (c) functional organisation
(d) all of the above (d) effective organisation
(e) none of the above. (e) none of the above.
Ans: d Ans: a

38. The main advantage of line 42. Templates are used for
organisation is its (a) a planning layout
(a) effective command and control (b) flow of material
(b) defined responsibilities at all (c) advancing a programme in
levels automatic machines
(c) rigid discipline in the (d) copying complicated profiles
organisation (e) none of the above.
(d) ability of quick decision at all Ans: a
levels
(e) all of the above. 43. In steel plant the most
Ans: e important system for materials
handling is
(a) conveyors
39. Frederick W. Taylor introduced (b) cranes and hoists
a system of working known as (c) trucks
(a) line organisation (d) locos
(b) line and staff organisation (e) none of the above.
(c) functional organisation Ans: d
(d) effective organisation
(e) none of the above. 44. Routing prescribes the
Ans: c (a) flow of material in the plant
(b) proper utilization of man power
40. The salient feature of (c) proper utilization of machines
functional organisation is (d) inspection of final product
(a) strict adherence to (e) none of the above.
specification Ans: a
(b) separation of planning and
design part 45. Queuing theory deals with
(c) each individual maintains problems of
functional efficiency (a) material handling
(d) work is properly planned and (b) reducing the waiting time or
distributed idle Jajme
(e) all of the above. (c) better utilization of man
Ans: e services
(d) effective use of machines
(e) none of the above.
Ans: b
46. Standard time is defined as 51. The wastage of material in the
(a) normal time + allowances store is taken into account by the
(b) normal time + idle time + following method in the evaluation
allowances of the material
(c) normal time + idle time issued from the store
(d) only normal time for an (a) inflated system
operation (b) primary cost method
(e) none of the above. (c) current value method
Ans: a (d) fixed price method
(e) variable price method.
47. Father of industrial Ans: a
engineering is
(a) Jeck Gilberth 52. Which of the following is
(b) Gnatt independent of sales forecast
(c) Taylor (a) productivity
(d) Newton (b) inventory control
(e) none of the above. (c) production planning
Ans: b (d) production control
(e) capital budgeting.
48. The grouping of activities into Ans: a
organisational units is called
(a) corporate plans 53. Gantt charts are used for
(b) higher level management (a) forecasting sales
(c) functional authority (b) production schedule
(d) departmentatidn (c) scheduling and routing
Ans: d (d) linear programming
49. Which of the following (e) none of the above.
organisation is preferred in Ans: b
automobile industry
(a) functional organisation 54. Inventory management
(b) line organisation consists of
(c) staff organisation (a) effective running of stores
(d) line and staff organisations (b) state of merchandise methods
(e) scalar organisation. of stroing and maintenance etc.
Ans: d (c) stock control system
(d) all of the above
50. Which of the following (e) none of the above.
organisations is best suited for Ans: d
steel plants 55. Gantt charts provide
(a) functional organisation information about
(b) line organisation (a) break even point analysis
(c) staff organisation (b) production schedule
(d) line, staff and functional (c) material handling layout
organisations (d) determining selling price
(e) scalar organisation. (e) value analysis.
Ans: d Ans: b
56. Inventory control in (b) industries have to train
production, planning and control apprentices ac-cording to their
aims at requirement
(a) achieving optimisation (c) all industries employing more
(b) ensuring against market than 100 workers have to recruit
fluctuations apprentices
(c) acceptable customer service at (d) only industries employing
low capital investment in inventory more than 500 workers have to
(d) discounts allowed in bulk recruit apprentices
purchase (e) all industries other than small
(e) regulate supply and demand. scale industries have to train
Ans: C apprentices.
Ans: d
57. In inventory control, the
economic order quantity is the 61. Standing orders which are
(a) optimum lot size statutory are applicable to
(b) highest level of inventory (a) all industries
(c) lot corresponding to break- (b) all process industries and
even point thermal power plants
(d) capability of a plant to produce (c) only major industries
(e) none of the above. (d) only key industries
Ans: a (e) all industries employing more
than 100 workers.
58. Statistical quality control Ans: e
techniques are based on the
theory of 62. Acceptance sampling is widely
(a) quality used in
(b) statistics (a) batch production
(c) probability (b) job production
(d) all of the above (c) mass production
(e) none of the above. (d) all of the above
Ans: c (e) none of the above.
Ans: c
59. The appellate authority for an 63. The technique of value
industrial dispute is analysis can be applied to
(a) management (a) complicated items only
(b) labour court (b) simple items only
(c) high court/supreme court (c) crash programmer items only
(d) board of directors (d) cost consciousness items only
(e) president. (e) any item.
Ans: c Ans: e

60. Under the Apprenticeship Act 64. The term 'value' in value
(a) all industries have to engineering refers to
necessarily train the apprentices (a) total cost of the product
(b) selling price of the product
(c) utility of the product
(d) manufactured cost of the (b) an individual employee
product (c) a particular division in
(e) depreciation value. workshop
Ans: c (d) machine
(e) overall quality.
65. Value engineering aims at Ans: b
finding out the
(a) depreciation value of a product 69. Material handling and plant
(b) resale value of a product location is analysed by
(c) major function of the item and (a) Gnatt chart
accomplishing the same at least (b) bin chart
cost without change in quality (c) Emerson chart
(d) break even point when (d) travel chart
machine re-quires change (e) activity chart.
(e) selling price of an item. Ans: d
Ans: c
70. Works cost implies
66. In the perpetual inventory (a) primary cost
control, the material is checked (b) factory cost
when it reaches its (c) factory expenses
(a) minimum value (d) primary cost + factory
(b) maximum value expenses
(c) average value (e) none of the above.
(d) alarming value Ans: d
(e) original value.
Ans: a 71. Motion study involves analysis
of
(a) actions of operator
(b) layout of work place
(c) tooling and equipment
Ans: a
67. According to MAPI formula, the
old machine should be replaced by 72. Standard time as compared to
new one when normal time is
(a) CAM < DAM (a) greater
(b) CAM > DAM (b) smaller
(c) CAM = DAM (c) equal
(d) there is no such criterion (d) there is no such correlation
(e) none of the above. (e) none of the above.
(CAM = Challenger's Adverse Ans: a
minimum DAM = Defender's
Adverse minimum) 73. Pick up the incorrect
Ans: a statement about advantages of
work sampling
68. Merit Rating is the method of (a) permits a fine breakdown of
determining worth of activities and delays
(a) a job
(b) simultaneous study of many (c) volunteers
operators may be made by a single (d) the industries notified by
observer Government
(c) calculations are easier, method (e) all major industries.
is economical and less time Ans: d
consuming
(d) no time measuring devices are 78. The amount deducted from the
generally needed salary of workers towards
(e) as operators are not watched employees provident fund is
for long periods, chances of (a) credited into reserves of
obtaining misleading results are company
less. (b) deposited in nationalised bank
Ans: a (c) deposited in post office
(d) deposited in the account of
74. In which of the following worker with employer or Reserve
layouts, the lines need to the Bank of India
balanced (e) deposited in the account of
(a) process layout worker with Provident Fund
(b) product layout Commissioner.
(c) fixed position layout Ans: e
(d) plant layout
(e) functional layout. 79. The deductions for, employees
Ans: b provident fund start
(a) immediately on joining the
75. Which of the following layouts service
is suited for mass production (b) after 60 days of joining the
(a) process layout service
(b) product layout (c) after 100 days of joining the
(c) fixed position layout service
(d) plant layout (d) after 240 days of joining the
(e) functional layout. service
Ans: b Ans: d
80. Father of time study was
76. Which of the following layouts (a) F.W. Taylor
is suited to job production (b) H.L. Gantt
(a) process layout (c) F.B. Gilberfh
(b) product layout (d) R.M. Barnes
(c) fixed position layout (e) H.B. Maynord.
(d) plant layout Ans: a
(e) functional layout.
Ans: a 81. Tick the odd man out
(a) Taylor
77. The employees provident fund (b) Drucker
act is applicable to (c) McGregor
(a) all industries (d) Galileo
(b) all industries other than small (e) Parkinson.
and medium industries Ans: d
Ans: b
82. Current assets include
(a) manufacturing plant 87. Routing is essential in the
(b) manufacturing plant and following type of industry
equipment (a) assembly industry
(c) inventories (b) process industry
(d) common stock held by the firm (c) job order industry
(e) all of the above. (d) mass production industry
Ans: a (e) steel industry.
Ans: a
83. The objective of time study is
to determine the time required to 88. An optimum project schedule
complete a job by implies
(a) fast worker (a) optimum utilization of men,
(b) average worker machines and materials
(c) slow worker (b) lowest possible cost and
(d) new entrant shortest possible time for project
(e) any one of the above. (c) timely execution of project
Ans: b (d) to produce best results under
given constraints
84. Job enrichment technique is (e) realistic execution time,
applied to minimum cost and maximum
(a) reduce labour monotony profits.
(b) overcome boring and Ans: b
demotivating work
(c) make people happy
(d) all of the above
(e) none of the above.
Ans: d 89. Graphical method, simplex
method, and transportation
85. For ship vessel industry the method are concerned with
following layout is best suited (a) break-even analysis
(a) process layout (b) value analysis
(b) product layout (c) linear programming
(c) fixed position layout (d) queing theory
(d) plant layout (e) tnaterial handling.
(e) functional layout. Ans: c
Ans: c
90. Which one of the following
86. In Halsey 50-50 plan, output represents a group incentive plan
standards are established ?
(a) by time study (a) Scanlon Plan
(b) from previous production (b) Rowan Plan
records (c) Bedaux Plan
(c) from one's judgement (d) Taylor Differential Piece Rate
(d) all of the above System
(e) none of the above. (e) Halsey Premium Plan.
Ans: a (e) nil time estimate.
Ans: a
91. In the Halsey 50-50 plan, the
following are rewarded more 96. PERT has following time
(a) past good workers estimate
(b) past poor workers (a) one time estimate
(c) past average workers (b) two time estimate
(d) all of the above (c) three time estimate
(e) none of the above. (d) four time estimate
Ans: b (e) nil time estimate.
Ans: c
92. In the Halsey system of wage
incentive plan, a worker is 97. In Lincoln plan (one type of
(a) paid as per efficiency group incentive plan), the amount
(b) ensured of minimum wages of the profit which an .employee
(c) not paid any bonus till his receives in addition to the
efficiency guaranteed basic pay/wages, is
(d) never a loser based on :
(e) induced to do more work. (a) a standard rating system
Ans: b (b) a merit rating system
Ans: b
93. 'Value' for value engineering 98. Which of the following
and analysis purposes is defined incentive plansrensures a part of
as the swing to the worker and rest
(a) purchase value to the employer
(b) saleable value (a) Emerson efficiency plan
(c) depreciated value (b) Taylor plan
(d) present worth (c) Halsey premium plan
(e) function/cost. (e) Gilberth plan.
Ans: e Ans: c

94. Break-even analysis can be 99. Which of the following is not


used for wage incentive plan
(a) short run analysis (a) differential piece rate system
(b) long run analysis (b) Rowan plan
(c) average of above two run (c) Emerson plan
analysis (d) Taylor plan
(d) there is no such criterion (e) Halsey plan.
(e) none of the above. Ans: d
Ans: a
100. Which of the following plans
95. CPM has following time motivates supervisors by paying a
estimate premium on time saved by
(a) one time estimate workers
(b) two time estimate (a) Halsey plan
(c) three time estimate (b) Rowan plan
(d) four time estimate (c) Haynes plan
(d) Emerson's plan 104. According to Rowan plan, if H
(e) Taylor's plan. = hourly rate, A = actual time and
Ans: c S = standard time, then wages will
be
101. The time required to (a) HA
complete a task is established and (b) HA + (S~A) HA
a bonus is paid to the worker for (c) HA + ^^-H
every hour he saves from the (d) HA + ^^-H
established time required. This (e) HA + ^^-HA.
type of incentive plan is known as Ans: b
(a) Rowan Plan
(b) Bedaux Plan 105. If a worker gets a daily wage
(c) Taylor Differential Piece rate of Rs HA, then according to Rowan
system plan, his maximum daily earnings
(d) Halsey Premium plan can be
(e) Day work plan. (a) 2 HA
Ans: d (b) 1.33 HA
(c) 1.5 HA
(d) 1.15 HA
102. One of the basic essentials of (e) 2.5 HA.
an incentive plan is that Ans: a
(a) a differential piece rate system
should exist 106. In A-B-C control policy,
(b) minimum wages should be maximum attention is given to
guaranteed (a) those items which consume
(c) provide incentive to group money
efficiency performance (b) those items which are not
(d) all standards should be based readily available
on optimum standards of (c) those x items which are in
production more demand
(e) all standards should be based (d) those items which consume
on time studies. more money
Ans: e (e) proper quality assurance
103. In the Emerson efficiency program-mes.
plan, a worker receives only his Ans: d
daily wage and no bonus is paid till
his efficiency reaches 107. Which one of the following
(a) 50% represents a group incentive plan
(b) 661% ?
(c) 75% (a) Halsey Premium Plan
(d) 80% (b) Bedaux Plan
(e) 90%. (c) Lincoln Plan
Ans: b (d) Rowan Plan
(e) Taylor Plan.
Ans: c
108. The mathematical technique (e) none of the above.
for finding the best use of limited Ans: a
resources in an optimum manner
is known as 113. The time required to
(a) operation research complete a job is established and
(b) linear programming a bonus is paid to the worker
(c) network analysis based on the exact % of time
(d) queuing theory saved. This type of incentive plan
(e) break-even analysis. is known as
Ans: b (a) Dry work Plan
(b) Halsey Premium Plan
109. In order that linear (c) Taylor Plan
programming techniques provide (d) Bedaux Plan
valid results (e) Rowan Plan.
(a) relations between factors must Ans: e
be linear (positive) 114. Replacement studies are
(b) relations between factors must made on the fol-lowing basis:
be linear (negative) (a) annual cost method
(c) (a) or (b) (b) rate of return method
(d) only one factor should change (c) total life average method
at a time, others remaining (d) present worth method
constant (e) any one of the above.
Ans: c Ans: e
110. The linear programming 115. String diagram is used
techniques can be applied (a) for checking the relative values
successfully to industries like of various layouts
(a) iron and steel (b) when a group of workers are
(b) food processing working at a place
(c) oil and chemical (c) where processes require the
(d) banking operator to be moved from one
(e) all of the above. place to another
Ans: e (d) all of the above
(e) none of the above.
111. The simplex method is the Ans: d
basic method for
(a) value analysis 116. Which of the following
(b) operation research depreciation system ensures that
(c) linear programming the interest be charged on the cost
(d) model analysis of machine asset every year
(e) none of the above. on the book value, but the rate of
Ans: c depreciation every year remains
112. The two-bin system is constant
concerned with (a) sinking fund method
(a) ordering procedure (b) straight line method
(b) forecasting sales (c) A-B-C charging method
(c) production planning (d) annuity charging method
(d) despatching and expediting Ans: d
117. Bin card is used in 121. CPM is the
(a) administrative wing (a) time oriented technique
(b) workshop (b) event oriented technique
(c) foundry shop (c) activity oriented technique
(d) stores (d) target oriented technique
(e) assembly shop. (e) work oriented technique.
Ans: d Ans: c

118. Slack represents the 122. PMTP (predetermined motion


difference between the time systems) include
(a) latest allowable time and the (a) MTM (method time
normal expected time measurement)
(b) latest allowable time and the (b) WFS (work factor systems)
earliest expected time (c) BNTS (basic motion time
(c) proposed allowable time and study)
the earliest expected time (d) all of the above
(d) normal allowable time and the (e) none of the above
latest expected time Ans: d
(e) project initiation tune and
actual starting time. 123. Work study comprises
Ans: b following main techniques
(a) method study and work
119. PERT and CPM are measurement
(a) techniques to determine (b) method study and time study
project status (c) time study and work
(b) decision making techniques measurement
(c) charts which increase aesthetic (d) method study and job
appearance of rooms evaluation
(d) aids to determine cost (e) value analysis and work
implications of project measurement.
(e) aids to the decision maker. Ans: a
Ans: e
124. Which of the following
120. A big advantage of PERT over equations is not in conformity with
Gantt charts is that in the former others
case (a) organisation performance x
(a) activities and events are motivation = profits
clearly shown (b) knowledge x skill = ability
(b) early start and late finish of an (c) ability x motivation =
activity are clearly marked performance
(c) activity times are clear (d) attitude x situation =
(d) critical path can be easily motivation
determined (e) performance x resources
(e) inter-relationship among Ans: a
activities is clearly shown.
Ans: e
125. PERT is the (a) complete details'of items in,
(a) time oriented technique waiting line are known
(b) event oriented technique (b) arrival and waiting times are
(c) activity oriented technique known and can be grouped to form
(d) target oriented technique a waiting line model
(e) work oriented technique. (c) all variables and constants are
Ans: b known and form a linear equation
(d) the laws governing arrivals,
126. The basic difference between service times, and the order in
PERT and CPM is that which the arriving units are taken
(a) PERT deals with events and into source are known
CPM with activities (e) all of the above.
(b) critical path is determined in Ans: d
PERT only
(c) costs are considered on CPM 130. Queuing theory is associated
only and not in PERT with
(d) guessed times are used in (a) sales
PERT and evaluated times in CPM (b) inspection time
(e) PERT is used in workshops and (c) waiting time
CPM in plants. (d) production time
Ans: d (e) inventory.
Ans: c
127. PERT stands for k (fit) project
evaluation and review technique 131. The reasons which are
(b) project examination and basically responsible for the
review technique formation of a queue should be
(c) project evaluation and that
reporting technique (a) the average service rate Hess
(d) process execution and than the average arrival rate
reporting technology (b) output rate is linearly
(e) project execution and results proportional to input
technique. (c) output rate is constant and the
Ans: a input varies in a random manner
(d) all of the above
128. Queuing theory is used for (e) none of the above.
(a) inventory problems Ans: d
(b) traffic congestion studies
(c) job-shop scheduling 132. Monte Carlo solutions in
(d) all of the above queuing theory are extremely
(e) none of the above. useful in queuing problems
Ans: d (a) that can't be analysed
mathematically
129. In queuing theory, the nature (b) involving multistage queuing
of the waiting situation can be (c) to verify mathematical results
studied and analysed (d) all of the above
mathematically if (e) none of the above.
Ans: a
(c) critical path method is event
133. In perpetual inventory oriented
control, the material is checked as (d) critical.path method is not
it reaches its activity oriented
(a) minimum value (e) none of the above.
(b) maximum value Ans: e
(c) average value
(d) middle value 138. Pick up the correct statement
(e) alarming value. from the following
Ans: a (a) critical path method is an
improvement upon bar chart
134. A milestone chart method
(a) shows the inter dependences (b) critical path method provides a
of various jobs realistic approach to the daily
(b) depicts the delay of jobs, if any problems
(c) points outgoing ahead of (c) critical path method avoids
schedule of jobs, if any delays which are very common in
(d) all of the above bar chart
(e) none of the above. (d) critical path method was
Ans: e invented by Morgan R. Walker of
Dupot and James E. Kelley of
135. Bar charts are suitable for Remington U.S.A in 1957
(a) minor works (e) all of the above.
(b) major works Ans: e
(c) large projects
(d) all of the above 139. Pick up the correct step used
(e) none of the above. for scheduling a project by C.P.M.
Ans: a (a) a project is divided into various
activities
136. The first method invented for (b) required time for each activity
planning projects was is established
(a) bar chart method (c) sequence of various activities is
(b) milestone chart made according to their
(c) critical path method (CPM) importance
(d) programme evaluation and (d) network is drawn by
review technique (PERT) connecting the activities and the
(e) none of the above. events
Ans: a (e) all of the above.
Ans: e
137. Pick up the correct statement
from the following 140. The time of completing a
(a) programmer evaluation and project in network analysis is
review technique is event oriented given by following time of the
(b) programmer evaluation and critical activity meeting at the
review technique is not event finalitiode
oriented (a) early finish
(b) early start
(c) late start (a) an activity of the project is
Ans: a denoted by an arrow on the net
141. The disadvantage of product work
layout is (b) the tail of the arrow indicates
(a) high initial investment for the the start of the activity
specialized facilities (c) the head of the arrow indicates
(b) skilled labour to operate the end of,the activity!
machines (d) the arrows are drawn (to scale
(c) production time is longer, from) left to right
requiring more goods in inventory (e) each activity consumes a given
(d) high cost of inspection time
(e) costly and complex production Ans: d
control.
Ans: a 146. The artificial activity; which
indicates that an activity following
142. Emergency rush order can be it cannot be started unless, the
pushed more effectively in preceding activity is
(a) job production complete, is known as
(b) automatic production (a) event
(c) continuous production (b) free float
(d) intermittent production (c) artificial
(e) none of the above. (d) constraint
Ans: d (e) dummy.
Ans: e
143. Routing assists engineers in
deciding in advance 147. A dummy activity
(a) the flow of material in the plant (a) is artificially introduced
(b) the methods of proper (b) is represented by a dotted line
utilization of manpower (c) does not require any time
(c) the methods of proper (d) all of the above
utilization of machines (e) none of the above.
(d) the layout of factory facilities Ans: d
(e) normal route of workers
through the plant. 148. If E is the duration, ES and EF
Ans: c are die earliest start and finish
times, LS and LF are latest start
144. The performance of a specific and finish times, then the
task in CPM is known as following relation holds good
(a) dummy (a) EF=ES+D
(b) event (b) LS=LF-D
(c) activity (c) LF = LS + D
(d) contract (d) D = EF-ES
(e) none of the above. (e) all of the above.
Ans: c Ans: e

145. Pick up the incorrect


statement from the following
149. The difference between the (c) zero float,
time available to do the job and (d) average float
the time required to do the job, is (e) none of these.
known as Ans: c
(a) event
(b) float 154. The time by which the activity
(c) duration completion time can be delayed
(d) constraint without affecting the start of
(e) none of the above. succeeding activities, is
Ans: b Known as
(a) duration
150. The probability distribution of (b) total float
activity times in PERT follows (c) free float
following distribution (d) interfering float
(a) normal (e) none of the above.
(b) binomial Ans: c
(c) beta
(d) exponential 155. The critical path of a network
(e) Gaussian. represents
Ans: c (a) the minimum time required for
completion of project
151. The probability distribution of (b) the maximum time required for
project completion in PERT follows completion of project
following distribution (c) maximum cost required for
(a) normal completion of project
(b) binomial (d) minimum cost required for
(c) beta completion of project
(d) exponential (e) none of the above.
(e) Gaussian. Ans: a
Ans: e
156. Pick up the correct statement
152. If TL is the largest allowable from the following
event occurrence time, total (a) the float may be positive, zero
activity slack (s) is equal to or negative
(a) latest start time - earliest start (b) if the float is positive and the
time activity is delayed by a period
(b) latest finish time - earliest equal to its total float, the
finish time (EFT) completion of project in not
(c) TL-EFT delayed
(d) all of the above (c) if the float of an activity is
(e) none of the above. negative, delay in its performance
Ans: d is bound to delay the completion of
project
(d) if the float of an activity is zero,
153. The critical activity has the activity is critical and any delay
(a) maximum float in its performance will delay the
(p) minimum float whole project
(e) all of the above. 161. The technique for
Ans: e establishing and maintaining
priorities among the various jobs
157. Critical path moves along the of any project is known as
activities having total float of (a) event flow scheduling
(a) positive value technique
(b) negative value (b) critical ratio scheduling
(c) zero value (c) slotting technique for
(d) same value scheduling
(e) none of the above. (d) short interval scheduling
Ans: c (e) none of the above.
Ans: b
158. Critical Path Net Work helps
an engineer 162. Pick up the incorrect
(a) to concentrate his attention on statement from the following. A
critical activities critical ratio scheduling
(b) to divert the resources from (a) establishes the relative
non-critical advanced activities to priorities among various activities
critical activities on a common basis
(c) to be cautious for avoiding any (b) determines the status of each
delay in the critical activities to activity
avoid delay of the whole project (c) adjusts automatically changes
(d) all of the above in activity progress
(e) none of the above. (d) is a dynamic system
Ans: d (e) none of the above.
Ans: e
159. Pick up the correct statement
about relationship between 163. PERT is
various floats (a) an analytic tool in concept
(a) free float = total float (b) limit up of event oriented
(b) independent float = total float diagrams
(c) independent float > free float (c) used for research and
(d) free float > total float development projects
(e) independent float < free float. (d) based on three time estimates
Ans: e for activities linking up two events
(e) all of the above.
160. The time which results in the Ans: e
least possible direct cost of an
activity is known as 164. CPM is
(a) normal time (a) synthesising in concepts
(b) slow time (b) is built of activities oriented
(c) crash time program-mes
(d) standard time (c) is, based on one time eytimate
(e) none of the above. (d) is used for repetitive works
Ans: b (e) all of the above.
Ans: e
165. A CPM family includes
(a) CPA (Critical Path Analysis) 170. Pick up the correct
(b) CPP (Critical Path Plotted) statement. Dummy activity on a
(c) MCE (Minimum Cost PERT/CPM chart means, it
Expenditure) (a) consumes time, but no
(d) CPS (Critical Path Scheduling) resources
(e) all of the above. (b) consumes resources but no
Ans: e time
(c) consumes neither time nor
166. PERT/CPM, techniques can be resources
used for following applications (d) is a dangling event
(a) once through project (e) consumes both resources and
(b) maintenance jobs time.
(c) research and development Ans: c
(d) all non-technical jobs
(e) all of the above. 171. Criticalpath on PERT/CPM
Ans: e chart is obtained by joining the
events having
167. PERT analysis is based on (a) maximum slack
(a) optimistic time (b) minimum slack
(b) pessimistic time (c) average slack
(c) most likely time (d) no slack
(d) all of the above (e) judgement and experience.
(e) none of the above. Ans: b
Ans: d
172. Slack of various events on
168. Descripancies of bar chart the critical path in PERT/CPM chart
techniques are (a) increases continuously
(a) consequential effects of lack in (b) decreases continuously
one activity on omer (c) remains constant
(b) consequential effects of lack in (d) may increase or decrease
one activity on the finish date depending on various factors
(c) free time available for an (e) unpredictable.
activity can't be predicted Ans: c
(d) effective
monitoring/controlling can't be 173. The assumption in PERT is
done (a) a project will always be behind
(e) all of the above. schedule, if left uncorrected
Ans: e (b) cost of project will always be
more than the estimated cost, if no
169. O on a PERT/CPM chart timely corrections are taken
represents (c) a project can be subdivided
(a) an ordinary event into a set of predictable,
(b) a significant event independent activities
representing some mile-stone (d) activities are fixed and can't be
(d) dangling event changed ,
Ans: a
(e) commissioning time can be 177. In a PERT chart
changed, if activities are behind (a) all activities should be
schedule. numbered
Ans: c (b) only important activities
should be numbered
174. Activity s,lack or float of any (c) only critical activities are
event on a PERT/CPM chart is numbered
represented by (d) only selected activities are
(a) latest start time of succeeding numbered
event -earliest finish time of (e) no activity is numbered.
preceding event activity time Ans: a
(b) latest start time of the event -
earliest start time of the event 178. Positive slack on a PERT
(c) latest finish time of event - indicates that project is
earliest finish time of the event (a) ahead of schedule
(d) anyone of the above (b) beyond schedule
(e) none of the above. (c) as per schedule
Ans: d (d) on critical path
(e) none of the above.
175. The important file in making Ans: a
a PERT is
(a) an event can't be accomplished 179. Pessimistic time is
until activities leading to it are (a) the maximum time which an
completed activity might require
(b) no activity from any event can (b) the average time required for
be started from preceding event a job
till it is completed (c) the most probable time
(c) length of arrow has nothing to considering all conditions
do with time (d) the minimum time in which an
(d) every activity must be activity can possibly be
completed before end point is accomplished
reached (e) the earliest finish.
(e) all of the above. Ans: a
Ans: e
180. In PERT analysis, critical path
176. An event is indicated on the is obtained by joining events
network by having
(a) a straight line (a) +ve slack
(b) a number enclosed in a circle (b) -ve slack
or a square (c) zero sldck
(c) a straight line with circles at (d) dummy activities
the ends (e) critical activities.
(d) a dotted line Ans: c
(e) an arrow.
Ans: b
https://wps.prenhall.com/chet_arnold_materials_6/74/18
954/4852376.cw/-/4852389/index.html ASSEMBLE-TO-ORDER
Introduction to Materials Management
In the _____________
environment, several product
A good planning system must options exist (e.g., automobiles)
consider: and the customer is not willing to
• What are we going to make wait until the product is made.
• What does it take to make it Therefore manufacturers produce
• What do we have and need and stock standard component
parts.
CAPACITY
is the capability of manufacturing PRODUCTION PLANNING
to produce goods and services. is the first step in a manufacturing
planning and control system.
MARKETING
is responsible for analyzing the THE COST OF BACKLOG
marketplace and deciding the that is too large equals the cost of
firm's response, the markets to be turning away business.
served, the products supplied, and
desired levels of customer service.

PRODUCTION
must satisfy the demands of the
marketplace. It does so by using
plants, machinery, equipment,
labor, and materials as efficiently
as possible.

THE MPS
is a plan for the production of
individual end items.

Purchasing and PRODUCTION


ACTIVITY CONTROL (PAC)
represent the implementation and
control phase of the production
planning and control system

A CHASE STRATEGY
means producing the amounts
demanded at any given time.
4. In break-even analysis,
PRODUCTION MANAGEMENT MCQ SET 3
https://www.objectivebooks.com/2015/08/production- total cost consists of
management-mcq.html?m=1 (A) Fixed cost
1. Critical path method (B) Variable cost
(C) Fixed cost + variable cost
(A) Helps in ascertaining time (D) Fixed cost + variable cost +
schedules overheads
(B) Makes better and detailed
planning possible
(C) Provides a standard method
for communicating project plans
schedules and to time and cost 5. Which one of the following
performance techniques is used for
(D) All of the above determining allowances in
time study?

(A) Acceptance sampling


(B) Linear regression
2. Critical Path Net Work helps (C) Performance rating
an engineer (D) Work sampling
(A) To concentrate his attention
on critical activities
(B) To divert the resources from
noncritical advanced activities to
critical activities 6. Expediting function consists
(C) To be cautious for avoiding in keeping a watch on
any delay in the critical activities (A) Operator's activity
to avoid delay of the whole (B) Flow of material and in case
project of trouble locate source of trouble
(D) All of the above (C) Minimizing the delays
(D) Making efficient dispatching

3. Both Rowan plan and 50-50


Halsey plan will provide the 7. The most popular type of
same earning when the actual organisation used for Civil
time is _________ the Engineering Constructions is
standard time. (A) Line organization
(B) Line and staff organization
(A) One-fourth (C) Functional organization
(B) One-half (D) Effective organization
(C) Equal to
(D) Twice
8. Which one of the following 12. Which of the following
chart gives simultaneously wage incentive plan
information about the guarantees minimum wage to
progress of work and machine a worker and bonus is paid for
loading? the fixed percentage of time
saved?
(A) Process chart
(B) Machine load chart (A) Halsey plan
(C) Man-machine chart (B) Gantt plan
(D) Gantt chart (C) Rowan plan
(D) Emerson's efficiency plan

9. Merit Rating is the method


of determining worth of 13. Bin card is used in
(A) A job (A) Administrative wing
(B) An individual employee (B) Workshop
(C) A particular division in (C) Foundry shop
workshop (D) Stores
(D) Machine

14. The production scheduling


10. Routing is essential in the is simpler and high volume of
following type of industry output and high labour
(A) Assembly industry efficiency are achieved in the
(B) Process industry case of
(C) Job order industry
(D) Mass production industry (A) Product layout
(B) Process layout
(C) Fixed position layout
(D) A combination of line and
process layout
11. The time required to
complete a task is established
and a bonus is paid to the
worker for every hour he
saves from the established 15. The disadvantage of
time required. This type of product layout is
incentive plan is known as (A) High initial investment for the
(A) Rowan Plan specialized facilities
(B) Taylor Differential Piece rate (B) Skilled labour to operate
system machines
(C) Halsey Premium plan (C) Production time is longer,
(D) Day work plan requiring more goods in inventory
(D) High cost of inspection
1. Answer: Option D Answer: a
2. Answer: Option D
3. Answer: Option B
Explanation: Oil release sulfur
4. Answer: Option C dioxide gas when they burn. This
5. Answer: Option D sulfur dioxide gas causes
6. Answer: Option B breathing problems for living
7. Answer: Option A
8. Answer: Option C creatures. Along with the health
9. Answer: Option B issue this sulfur dioxide which is
10. Answer: Option A emitted from oil also causes acid
11. Answer: Option C rain.
12. Answer: Option A
13. Answer: Option D 3. The most nuclear fuel used in
14. Answer: Option A
15. Answer: Option A
the world is________________
a) Thorium – 232
b) Uranium – 238
https://www.sanfoundry.com/energy-management- c) Uranium – 235
questions-answers-energy-resources/
d) Plutonium – 239
View Answer
Energy Management Questions and Answers – Energy

Resources
Answer: c
Explanation: The most used
1. Energy is released from fossil nuclear fuel is Uranium – 235. It is
a radioactive metal. Nuclear fuels
fuels when they
like Uranium do not burnt to
are___________________ release energy. Instead, the fuels
a) Pumped are involved in nuclear reaction in
b) Cooled nuclear reaction in the nuclear
c) Burned reactor.
d) Pressurized 4. The blades in wind turbines are
View Answer connected to________________
a) Nacelle
Answer: c
b) Tower
Explanation: Fossil fuels are fuels
because they release heat energy c) Foundations
when they are burned. They are d) String
fossil fuels because they were View Answer
formed from the remains of living
organisms billions of years ago. Answer: a
Some of the examples of fossil Explanation: A nacelle is a cover
fuels are coal, oil and natural gas. housing that houses all of the
generating components in a wind
2. Oil release sulfur dioxide gas
turbine. Wind turbines have huge
when they burn. blades mounted on a tall tower.
a) True The blades are connected to a
b) False nacelle. Thus the nacelle in wind
View Answer turbines helps to work the wind
turbines.
5. In the production of wave wind energy
energy which form of energy is d) Wind energy is transferred to
used? solar energy
a) Potential energy View Answer
b) Kinetic energy Answer: b
c) Solar energy Explanation: Hydroelectricity
d) Wind energy power stations use the kinetic
energy in moving water. But the
View Answer
water comes from behind a dam
Answer: b built across a river valley. The
Explanation: The water in the sea water high up behind the dam
rises and falls because of waves on contains potential energy.
the surface. Wave machines use 8. Solar panels generate
the Kinetic energy in this
electricity.
movement to drive electricity
generators. Wave energy also a) True
known as ocean energy. Wave b) False
energy is essentially power drawn View Answer
from waves.
Answer: b
6. A tidal barrage is a barrier built
Explanation: Solar panels do not
over a___________________ generate electricity. They just heat
a) River bed up water by the external electricity
b) River estuary connection given to them. This
solar panels are often located on
c) River end
the roofs of the building where
d) River starting they can receive heat energy
View Answer directly from the sun.
Answer: b 9. In order to produce solar energy
Explanation: A tidal barrage is a during sunlight, where the energy
barrier built over a river estuary to is stored in the batteries?
make use of the kinetic energy in
a) Nickel Sulfur
the moving water. Huge amounts
of water move in and out of river b) Zinc Cadmium
mouths each day because of the c) Nickel Cadmium
tides. The barrage contains d) Nickel Zinc
electricity generators.
View Answer
7. In hydroelectricity
Answer: c
power_________________
Explanation: Nickel Cadmium cells
a) Kinetic energy is transferred to offers along service life thereby
potential ensuring a high degree of the
b) Potential energy is transferred economy. In the PV industry,
Nickel Cadmium battery cells are
to kinetic
majorly used for the energy
c) Solar energy is transferred to storage technology from
manufacturers and users of PV of of energy. The Sun’s energy
grid systems. warms the planet’s surface,
10. How many forms of fossil fuels powering titanic transfers of heat
and pressure in weather patterns
are there________________
and ocean currents.
a) One advertisement
b) Two 13. SI unit for energy
c) Three is_____________
d) Four a) Watt
View Answer b) Kilogram
Answer: c c) Newton
Explanation: There are three d) Joule
major forms of fossil fuels they are
View Answer
coal, oil and natural gas. They
formed from organic remains of Answer: d
plants and animals that were Explanation: SI unit for energy is
converted into coal, oil and natural joule. Metric unit of measurement
gas by exposure to heat and the for energy or work equal to a force
pressure of the earth’s crust over of one Newton applied through a
millions of years. distance of one meter. One joule is
11. According to WHO, how many equivalent to 0.737324 ft-lbs.
Joule is a SI unit of work, energy
premature deaths annually linked
and heat.
to air pollution causing by the
14. Trapped heat inside the earth
burning of fossil fuels?
is known as_______________
a) One million
a) Heat energy
b) Three million
b) Kinetic energy
c) Five million
c) Geothermal energy
d) Seven million
d) Thermal energy
View Answer
View Answer
12. Energy in the form of heat and Answer: c
light is obtained Explanation: Geothermal energy is
by________________ the heat from the earth. It’s clean
a) Biomass and sustainable. Resources of
geothermal energy range from the
b) Fossil fuels ground to water and hot rock. The
c) Sun term geothermal originates from
d) Wind the Greek words.
View Answer
Answer: c
Explanation: Energy in the form of
heat and light is obtained by sun.
Sunlight contains a large amount
1) Cloud base energy management system provides the ability to

a. Remotely control HVAC


b. Collect real time data
c. Generate intelligent, specific and real time guidance
d. Only b and c
e. All of these
ANSWER: All of these

2) The monitor and control of energy management system is done


by using

a. MATLAB
b. SCADA
c. AUTO - CAED
d. All of these
e. None of these
ANSWER: SCADA

3) The energy strategies of companies have the principle of

a. restoring and preserving the environment


b. reducing wastes and pollutants
c. educating the people about energy conservation
d. all of these
e. none of these
ANSWER: all of these

4) In passive potential energy strategies,

a. There is no systematic planning


b. Measures with low profitability is not considered
c. One should have high knowledge of the energy price
d. All of these
ANSWER: There is no systematic planning
5) In Germany, the maximum energy consumption of a low energy
house is

a. 50 kWh / m2a
b. 60 kWh / m2a
c. 70 kWh / m2a
d. 80 kWh / m2a
ANSWER: 70 kWh / m2a

6) IFMA stands for

a. International Facility Management Association


b. Indian Facility Management Association
c. International Facility Management Academy
d. Indian Facility Management Academy
ANSWER: International Facility Management Association

7) Maximum demand charges are given in

a. kWh
b. kVA
c. kVAr
d. All of these
e. None of these
ANSWER: kVA

8) Which among the following fuel is not available for thermal


energy supply?

a. LSHS
b. LDO
c. LPG
d. All of these
e. None of these
ANSWER: None of these
9) Energy management is a key component of

a. Environmental management
b. Carbon management
c. Nitrogen management
d. Water management
ANSWER: Carbon management

10) The main objective of energy management is to

a. Minimize energy cost


b. Minimum environmental effects
c. Maintain optimum energy procurement and utilization
d. Only A and B
e. All of these
ANSWER: All of these

https://www.careerride.com/mcq-tag-
wise.aspx?Key=Energy%20management&I
d=19

Energy management -
Electrical Engineering
(MCQ)
20 Multiple Choice Questions (MCQs) with Answers 7. Which among the following
on Energy is not an adverse
environmental impact of tidal
http://www.shareyouressays.com/knowledge/20-
power generation?
multiple-choice-questions-mcqs-with-answers-on-

energy/114074
(a) Interference with spawing and
migration of fish
1. Which of the following is a (b) Pollution and health hazard in
non-renewable resource? the estuary due to blockage of
(a) Coal flow of polluted water into the sea
(b) Forests (c) Navigational hazard
(c) Water (d) None of the above
(d) Wildlife 8. Steam reforming is
2. Which among the following currently the least expensive
is not a renewable source of method of producing:
energy? (a) Coal
ADVERTISEMENTS: (b) Biogas
(a) Solar energy (c) Hydrogen
(b) Biomass energy (d) Natural gas
(c) Hydro-power 9. A fuel cell, in order to
(d) Geothermal energy produce electricity, burns:
3. Identify the non-renewable (a) Helium
energy resource from the (b) Nitrogen
following: (c) Hydrogen
(a) Coal (d) None of the above
(b) Fuel cells 10. Fuel cells are:
(c) Wind power (a) Carbon cell
(d) Wave power (b) Hydrogen battery
4. Which of the following is a (c) Nuclear cell
disadvantage of most of the (d) Chromium cell
renewable energy sources? 11. Both power and manure is
(a) Highly polluting provided by:
(b) High waste disposal cost (a) Nuclear plants
(c) Unreliable supply (b) Thermal plants
(d) High running cost (c) Biogas plants
5. Photovoltaic energy is the (d) Hydroelectric plant
conversion of sunlight into: 12. The outermost layer of the
(a) Chemical energy earth is:
(b) Biogas (a) Magma
(c) Electricity (b) Mantle
(d) Geothermal energy (c) Crust
6. Horizontal axis and vertical (d) Solid iron core
axis are the types of: 13. Common energy source in
(a) Nuclear reactor Indian villages is:
(b) Wind mills (a) Electricity
(c) Biogas reactor (b) Coal
(d) Solar cell (c) Sun
(d) Wood and animal dung
14. The one thing that is 20. Boiling water reactor and
common to all fossil fuels is pressurised water reactors
that they: are:
(a) Were originally formed in (a) Nuclear reactor
marine environment
(b) Solar reactor
(b) Contain carbon
(c) Have undergone the same set (c) OTEC
of geological processes during (d) Biogas reactor
their formation
(d) Represent the remains of one ANSWERS
living organisms 1. (a); 2. (b); 3. (a); 4. (c); 5. (a); 6. (b);
15. The process that converts 7. (d); 8. (c); 9. (c); 10. (b); 11. (c); 12.
solid coal into liquid (c); 13. (d); 14. (b); 15. (a); 16. (b); 17.
hydrocarbon fuel is called: (c); 18. (c); 19. (d); 20. (a)
(a) Liquefaction
(b) Carbonation
(c) Catalytic conversion
(d) Cracking
16. Lignite, bituminous and
anthracite are different ranks
of:
(a) Nuclear fuel
(b) Coal
(c) Natural gas
(d) Biogas
17. Cruid oil is:
(a) Colourless
(b) Odourless
(c) Smelly yellow to black liquid
(d) Odourless yellow to black
liquid
18. BTU is measurement of:
(a) Volume
(b) Area
(c) Heat content
(d) Temperature
19. The first controlled fission
of an atom was carried out in
Germany in:
(a) 1920
(b) 1928
(c) 1925
(d) 1938

http://matse1.matse.illinois.edu/energy/qui
z.html
Multiple Choice: A. transportation. B.
1. Energy efficiency is defined electricity generation. C.
as: home heating. D. industrial
A. Energy that escapes in an uses.
unusable form.
B. (Energy in bonds broken) 8. Effects of acid rain include:
- (energy in bonds formed). A. Deterioration of
C. The content of energy in monuments. C. Damage to
a fossil fuel. lakes and their wildlife.
D. The amount of energy B. Damage to vegetation. D.
extracted from a system All of the above.
divided by the total energy
you put into the system. 9. Ways we utilize energy from
the sun include:
2. "Fossil fuels" refers to: A. passive solar heating. C.
A. coal. B. oil. C. natural gas. wind power
D. All of the above. B. photovoltaics. D. All of
the above.
3. The best type of coal in
terms of purity is: 10. Types of spontaneous
A. lignite. B. anthracite. C. radioactive decay include:
bituminous. D. A. gamma emission. C.
subbituminous. alpha bombardment.
B. transmutation. D. nuclear
4. Coal liquefaction refers to fission.
the process of: True/False
A. Washing coal to remove 1. T F Potential energy is really
impurities. C. Turning coal a type of mechanical energy.
into syncrude. 2. T F A BTU is smaller than a
B. Turning coal into natural Joule.
gas. D. None of the above. 3. T F Scientists worry that coal
reserves may run out in the
5. The main method of natural next 100 years.
gas transportation is: 4. T F There is only one way to
A. tankers. B. truck. C. recover oil--drilling.
pipeline. D. none of the 5. T F OPEC is an organization
above. which regulates the solar
power industry.
6. Crude oil is called "sweet" if: 6. T F The greenhouse effect
A. It smells good. C. It refers to global warming due
removed from oil shale. the burning of fossil fuels
B. It is easy to recover. D. It and the subsequent trapping
has <= 1% sulfur. of the waste heat by the
atmosphere.
7. T F Solar ponds are a neat
7. We use most of our oil idea, but they can't make
products for: the water very hot.
8. T F The use and production B. damage to vegetation. D.
of biomass is such that all of the above.
eventually, we'll be able to 8. Ways we utilize energy from
use it for all of our energy the sun include:
needs. A. passive solar heating. C.
9. T F An accident like the one wind power
at Chernobyl could not B. photovoltaics. D. All of
happen in the United States. the above.
10. T F Ordinary objects 9. Types of spontaneous
are radioactive, and you are radioactive decay include:
bombarded with radiation A. gamma emission
every day. True/False
Multiple Choice: 1. T Potential energy is really a
1. Energy efficiency is defined type of mechanical energy.
as: 2. T A BTU is smaller than a
D. the amount of energy Joule.
extracted from a system 3. F Scientists worry that coal
divided by the total reserves may run out in the
energy you put into the next 100 years.
system. 4. F There is only one way to
recover oil--drilling.
2. "Fossil fuels" refers to: 5. F OPEC is an organization
A. coal.B. oil. C. natural which regulates the solar
gas. D. All of the above. power industry.
6. T The greenhouse effect
3. The best type of coal in refers to global warming due
terms of purity is: the burning of fossil fuels
B. anthracite. and the subsequent trapping
of the waste heat by the
4. Coal liquefaction refers to atmosphere.
the process of: 7. F Solar ponds are a neat
C. turning coal into idea, but they can't make
syncrude. the water very hot.
5. The main method of natural 8. F The use and production of
gas transportation is: biomass is such that
C. pipeline eventually, we'll be able to
use it for all of our energy
Crude oil is called "sweet" if: needs.
D. it has <= 1% sulfur. 9. T An accident like the one at
6. We use most of our oil Chernobyl could not happen
products for: in the United States.
A. transportation. 10. T Ordinary objects are
radioactive, and you are
7. Effects of acid rain include: bombarded with radiation
A. deterioration of every day.
monuments. C. damage to
lakes and their wildlife.

You might also like