You are on page 1of 36

Contract Management Guide

Contract Management Guide

Introduction and scope 3


Definition 3
Importance of contract management 3
Activities 4
Upstream or pre-award activities 4
Downstream or post award activities 26
Acknowledgements 36
Bibliography 36

2
Introduction and scope Importance of contract management
This guide is intended to cover all those Organisations in both the public and
activities associated with contract private sectors are facing increasing
management from the establishment of pressure to reduce costs and improve
the business case and the confirmation financial and operational performance.
of need, through contract administration New regulatory requirements,
and relationship management to the globalisation, increases in contract
review of contract performance. The volumes and complexity have resulted in
activities themselves are divided into two an increasing recognition of the
distinct but interdependent phases, importance and benefits of effective
upstream and downstream of the award contract management.2
of the contract.
The growing recognition of the need to
The guide is generic in that its principles automate and improve contractual
are intended to be applicable to all processes and satisfy increasing
contracts from a simple order, through compliance and analytical needs has also
framework contracts to complex led to an increase in the adoption of
construction or service contracts, and it more formal and structured contract
should be seen as equally applicable to management procedures and an increase
contracts in the private as well as the in the availability of software
public sector. applications designed to address these
needs.
Definition
Contract life cycle management “is the It is worthwhile noting that contract
process of systematically and efficiently management is successful if:
managing contract creation, execution • the arrangements for service delivery
and analysis for maximising operational continue to be satisfactory to both
and financial performance and parties, and the expected business
minimising risk”.1 benefits and value for money are
being realised
There are a number of other definitions • the expected business benefits and
of contract management, the majority of value for money are being achieved
which refer to post-award activities. • the supplier is co-operative and
Successful contract management, responsive
however, is most effective if upstream or • the organisation understands its
pre-award activities are properly carried obligations under the contract
out. • there are no disputes
• there are no surprises
• a professional and objective debate
over changes and issues arising can be
had
1
(Aberdeen Group)
• efficiencies are being realised.
2
(Aberdeen Group)

3
Activities Upstream or pre-award activities
The foundations for effective and a) Preparing the business case and
successful post-award contract securing management approval
management rely upon careful,
comprehensive and thorough All contracts are predicated on the need
implementation of the upstream or pre- to obtain management commitment and
award activities. During the pre-award approval at the appropriate level. This
stages, the emphasis should be focused involves the formulation of a sound
on why the contract is being established business case aligned to the organisation’s
and on whether the supplier will be able corporate and functional strategies.
to deliver in service and technical terms.
However, careful consideration must be The business case sets out the policy,
given to how the contract will work once business and contract objectives and the
it has been awarded. The organisation’s issues that affect the decision and the
high-level requirements should be investment. It should seek to establish
carefully researched so that there is that the proposed contract will meet the
clarity of purpose from the outset. This need, that it is achievable and affordable,
will help to ensure clarity in all aspects and it should address the following
of the procurement process. issues:
• the outcome(s) of the contract
Management of contracts, particularly • critical success factors
partnerships, requires flexibility on both • the possible alternatives, including
sides and a willingness to adapt the existing contracts
terms of the contract to reflect changing • the risks including the extent and
circumstances. It is important to where they may fall
recognise that problems are bound to • identification of any contingent needs
arise which could not be foreseen when and ramifications of proceeding
the contract was awarded. • timescale.

Finally, it may not be necessary to follow The business case should be prepared
every activity for every contract - with the involvement of the
particularly in the case of small, simple stakeholders, including where and if
orders - but it is advisable to read the possible, the end users.
whole guide and to apply the advice
provided under each stage as It should be signed off by the sponsor or
appropriate to the particular contractual patron.
circumstances.
The business case is a working
document and should form the basis of
the post-implementation review and
used as a management tool to ensure
that the original outcomes and benefits 3
(OGC Contract
have been achieved. 3 Management)

4
If the project is large, complex and in supplier organisations such as design,
particular, innovative in nature, the production, production planners and
market should be approached logistics.
concurrently with the preparation of the
business case, firstly to alert them to the Clearly, these individuals and groups will
potential need and secondly to take not need to meet all the time but,
soundings on such issues as feasibility, depending on the size and complexity of
capacity, capability, approach and level the project, there may well be a core
of interest.4 group that meets regularly and this will
be the project team. Others will then be
b) Assembling the project team called on as and when required.

The need to assemble a team to manage In addition to the need to identify the
a contractual procurement programme necessary technical skills, knowledge
will be determined not only by the scale, and experience with the appropriate
nature, complexity and significance of level of authority required of the
the procurement and the necessary skills members of the team, the importance of
and experience but also by the extent to the ability of team members to work
which it is considered appropriate, together effectively and the significance
beneficial or a requirement to comply of the role of the project leader should
with organisational policy to involve be recognised.
stakeholders in the project.
These aspects are beyond the scope of
Factors to be considered when this guide, but it is considered advisable
assembling the team are: to devote time to studying the many
• the nature of the project books available on the topics of
• the nature of the work environment motivation, leadership, power, influence
and the management style of the team and group working, particularly if the
• communication internally and size, timescale and complexity of the
externally. procurement project are significant.5

In addition to procurement, the project c) Developing contract strategy


team may be drawn from any and all
disciplines within the organisation as The strategy relating to a particular
appropriate and relevant. The following contract should accord with the
are examples; design, research and organisation’s overall procurement
development, production, quality control, strategy.
logistics, marketing and sales, legal,
4
(OGC Contract
finance and human resources. The The development of a contract strategy is
Management) project team may also advantageously designed to establish the form of the
5
(For example include representatives of the end users, procurement and provide assistance in
see Handy
Understanding whether internal or external, and determining the formulation and award
Organisations) representatives of disciplines within of the contract and the style and type of

5
management to be adopted for the conducted and the form of the supplier
subsequent service delivery, relationship relationship following the award of
management and contract contract. Possible supplier relationship
administration. types range from the spot buy through
call-off contracts, fixed contracts and
There are many references these days to strategic alliances, to long term
‘partner’ rather than suppliers – should partnerships. Issues of relationship style
this be captured here? such as adversarial, partnership, hands-
The latter aims can be characterised by on or pro-active should also be
the need to address understanding, considered.6
measurement and communication post-
contract award. A successful contract Concurrently with determining the
management strategy should achieve contract strategy, consideration should
benefits by: be given to the evaluation strategy which
• managing the organisation’s own sets the direction for the overall
responsibilities during the contract evaluation of suppliers and the
• ensuring the supplier meets the associated tender process. It covers such
minimum performance criteria, such as considerations as:
compliance • business aims
• allowing the achievement of both • critical success factors
short and long term supplier • relative priorities of the requirement
performance improvement through • communication plans
developing effective supplier • criteria for determining quantifiable
relationships. and non-quantifiable items
• overall evaluation procedures
In developing the contract strategy, the including assessment methodology
following issues need to be addressed: • personnel involved in the evaluation
• nature, scale and significance of the • supplier selection criteria including
need to the organisation guidance on interpretation and
• value of need marking of replies.
• type of specification - input or output
• complexity of the need including Another important consideration in
innovation level establishing contract strategy is whether
• attractiveness to the market to utilise Service Level Agreements (SLA).
• market capacity SLAs are negotiated agreements
• timescale and phasing designed to create a common
• level of understanding of the need by understanding about services, priorities
stakeholders and potential suppliers. and responsibilities and are applicable in
two situations. Firstly, internally used
The use of supplier positioning matrices and provided specialist support services
6
will also assist in determining the and secondly when outsourcing. (CIPS study
guide Legal &
contract strategy, the nature of any Procurement
negotiations that may need to be Processes)

6
Internal SLAs are not intended to have • customers have a greater awareness of
legal consequences since the customer the services received and the
and the supplier are part of the same additional services that can be
legal entity which cannot sue itself, and provided
normally there will be no direct financial • customers’ real needs are identified
compensation. External SLAs such as and the associated costs are made
those for bought-in or outsourced clear
services may have contractual • services and service levels adding
implications. They are generally a value can be more easily identified
schedule or part of a schedule to the and distinguished
buy-in or outsource agreement. It should • greater awareness of costs/benefits of
also be remembered that EC services and levels
Procurement Directives may apply to • service level monitoring is facilitated
organisations using SLAs. • failure reports enable improvements to
be readily introduced
The purpose of SLAs and setting service • understanding and trust is created
levels is to enable the customer to between customer and supplier.
monitor and control the performance of
the service received from the supplier Disadvantages include:
against agreed standards. It should be • joint drafting of SLAs, negotiation and
understood that service levels should be measurement processes can be costly
agreed and benchmarked for both • potential increase in bureaucracy
customers and suppliers and should be: • internal providers are seen as
• established at a reasonable level; if suppliers and not colleagues
they are set too they will attract • time wasted if clear goals and
additional charges from the supplier objectives are not set out initially, this
• prioritised by the customer in order of leads to unrealistic expectations and
importance and on an agreed scale for acrimonious relationships, as well as
example critical, major, urgent, giving the setting up of SLAs a bad
important, minor, easily monitored, reputation
such as objective, tangible and • training needed to overcome
quantifiable resistance to the introduction of SLAs.7
• unambiguous and understandable by
all parties d) Risk assessment
• open to re-negotiation at any time.
Risk can be defined as “the probability of
7
(For more There are advantages and disadvantages an unwanted outcome happening”.
information on in using SLAs. Among the advantages are:
SLAs and their
successful
• the service providers and the Risk assessment should be viewed in the
implementation customers are clearly identified overall context of risk management and
see Service Level • attention is focused on what a service seen as one of the three key activities –
Agreements in
the CIPS How to actually does as opposed to a belief risk analysis, risk assessment and risk
series) about the service mitigation - which facilitate the taking of

7
decisions and actions to control risk may have low impact and it is possibly
appropriately. not worth taking action to control or
avoid such risks. Conversely, low
Risk analysis is the process of identifying probability risks may have a significant
all the potential issues that can go wrong impact demanding action to be taken to
with an activity and then estimating the avoid or mitigate the risk.
probability of each happening. It should
form part of any significant contract Other issues for consideration in risk
management process and is a assessment:
fundamental part of determining the • the costs of identifying, controlling or
contract strategy. The process can range avoiding the risk
from a simple listing of risks on an • the need for insurance for risk not
informal, intuitive basis to a formal readily managed or avoided
process involving set procedures and • the need for “sensitivity analysis” on
working with other professional risks of an unknown level or
disciplines in brainstorming and magnitude
technically and financially evaluating • identifying compensating behaviour
potential risks. A more formal process practices
may involve the establishment of a risk • the impact of time, external factors
register for each tenderer and, following and project actions on risk and the
contract award, the transfer of the need for assessment to be iterative
register of the successful tenderer to the • the impact of product life cycle
contract management team for use in including disposal and obsolescence.
risk assessment; see section s).
Having assessed the risks and identified
In addressing the fundamentally those requiring action, responsibility for
important issue of risk in contract managing and mitigating them should be
management, the purchasing allocated. This allocation should be
professional should adopt a continuous dependent on the assessment of the
“what if” mentality throughout the likelihood and consequence of the risk.
procurement of products and services.
Risk management requires a professional Other issues to be considered in risk
who possesses knowledge of techniques, mitigation:
an analytical mind set, objectivity and a • identifying the most appropriate body
knowledge and thorough understanding to manage or control the risk in terms
of their organisation’s business and the of expertise, time and/or resource
market. It is advisable to seek to mitigate • establishing a fair and reasonable
and remove risk whenever possible reimbursement mechanism
before contract award. • insurance
• risk transfer to suppliers including
Risk assessment is the process of issues of appropriate level, “trade off”
8
(CIPS POP Risk
assessing the likely impact of a risk on and supplier contingency.8 management in
the organisation. Highly predictable risks P & SM)

8
A further issue, usefully classified under • major default by your organisation;
a consideration of risk in contract this may include contractual breaches
management is fraud. The need to or changed circumstances - market,
address potential areas for fraud in political ,economic, funding resulting
buyer/supplier relationships and in major procurement need changes,
measures to mitigate their impact should financial resulting in non-payment of
be considered at this early stage in supplier’s invoices
upstream activities, particularly contract • major default by the supplier; this may
formulation. include breaches, technical inability,
capacity, and so on
The adoption of a continuous “what if” • frustration of the contract.
mentality – a similar approach to that
used when assessing risk - is advisable Whilst many of these sets of
when considering areas for potential circumstances are generally predictable,
fraud. The CIPS Knowledge paper on and “standard” terms and conditions are
Fraud provides useful guidance on areas widely included in contracts today, it
of weakness and counter measures and does not detract from the need to carry
gives answers answers to some out this aspect of risk assessment and to
frequently asked questions. ensure that clear and comprehensive
terms and conditions are drawn up
e) Developing contract exit strategy which address the identified
circumstances and the rights and
A contract will conclude when both responsibilities of the parties and the
parties have satisfactorily fulfilled their means by which any damages or costs
responsibilities under the terms of the may be mitigated are set out. This latter
contract. This, for example, will occur should include the method by which the
when the goods or services have been goods or services may continue to be
supplied and payment made and/or at provided and, if possible, seamlessly
the end of a pre-agreed period of time. transferred to another supplier or
This situation, however, does not remove contractor to ensure business continuity.
the need to develop a contract exit It is also important to clarify any notice
strategy as part of the process of risk period to be given and any timescale
identification and reduction, and constraints associated with the exit
reinforces the importance of establishing process itself.
the foundations of sound contract
management. f) Developing a contract management
plan
It is important to identify the
circumstances under which early During pre-contract award stages, it is
9
(Project contract exit may be required or indeed normal for time to be devoted to the
Management- desired. The following is merely a list of preparation of the business case, drafting
Dennis Lock.
OGC Contract
examples and is certainly not an specifications and tender documents
Management) exhaustive list: selecting potential suppliers, and so on.

9
However, time and effort must also be • the need for the buying organisation
spent on determining how the contract to have clear business objectives,
will work once it has been awarded. The coupled with a clear understanding of
importance of contract management has why the contract will contribute to
already been mentioned and it is vital them
that a contract management plan is • the need to understand the provider's
drawn up in advance of contract award. business objectives and drivers
This should set out how the obligations • the ability to recognise and obtain
of all the parties should be carried out senior management agreement to the
effectively and efficiently. need for the service provider to
achieve their objectives and to make a
Contract management success factors, reasonable margin
the conditions that should be met if a • the need for people with the right
contract is to be managed successfully, commercial, interpersonal and
are: management skills to manage these
• the arrangements for service delivery relationships on a peer-to-peer basis
continue to be satisfactory to both and at multiple levels in the
customer and provider organisation.
• expected business benefits and value • to recognise that all parties need
for money are being realised managers who can manage upwards
• the provider is co-operative and in their organisation and persuade
responsive their boards to make decisions for the
• the customer knows its obligations benefit of the relationship.
under the contract
• there are no disputes Other issues to be addressed and
• there are no surprises appropriate processes and procedures
• satisfactory delivery progress is set out in the contract management plan
demonstrable. include:
• the processes for managing the
In addition to these success conditions, it contract which provide the level of
is worthwhile noting the foundations of control you need, such as contract
successful contract management and the governance
need for preparing a management plan: • the retention of sufficient expertise to
• the need for flexibility by the understand the technical direction in
contracting parties, particularly in which the provider is taking your
partnership agreements organisation and to retain the ability to
• a willingness to adapt the terms of the enter into effective dialogue with the
contract to reflect change and supplier
unforeseen problems. Although the risk • to ensure as far as is possible that the
assessment process mentioned earlier supplier is able to provide sufficient
may be carried out thoroughly and skilled resources, given the risk that
professionally, problems are still likely another customer's account might take
to arise during the contract period priority

10
• the possibility of the supplier team • benefits realised
changing after award of contract, • relationship strength and
leading to a lack of continuity responsiveness
• to set down how the members of any • It is important that the performance
supplier consortium handle a variety measures selected and set out in the
of different types of issues so as to contract offer clear and demonstrable
ensure that problems are resolved evidence of the success (or otherwise)
quickly and constructively of the relationship. Once chosen, the
• to set down how members of a requirements underpinning the
supplier consortium should share performance measures should be the
common quality management systems primary focus for contract
and escalation procedures management. They should provide the
• to set down the timescale and framework around which provider
methods by which the provider’s level information requirements and flows,
of knowledge and understanding of contract management teams, skills,
your business can be gained and processes and activities are
transferred to the supplier’s successive developed.10
team members
• roles and responsibilities of g) Drafting specifications and
individuals of the parties to the requirements
contract; this includes issues such as:
• adopting the principles of good A specification is a statement of needs
communication, awareness of new and its purpose is to present to potential
demands in partnership suppliers a clear, accurate and
arrangements, leadership, comprehensive statement of the
appropriateness and capability of organisation’s needs in order that they
existing management structures, can propose solutions to those needs. At
understanding the responsibilities of the same time, the specification should
the various parties, clear enable the organisation to readily
understanding of what is expected evaluate offers, provide the basis for
and effective ways of reporting performance measurement and be a
progress, having a framework record of evidence in any dispute.
defining responsibilities, reporting
arrangements and policies A specification is also known as an
• establishing the performance operational requirement or a statement
measures to cover all aspects of the of requirement. It can take the form of a
service such as: conformance specification – where the
• cost and value obtained organisation sets out how the supplier
• performance and customer should meet its needs - or a performance
satisfaction or output-based specification where the
• delivery improvement and added supplier is given scope to propose
10
(OGC Contract value solutions to an expected and known end
Management) • delivery capability result?

11
Although the drawing up of • decide the type of specification to be
specifications in the majority of large used and then prepare draft. In large,
organisations is not the responsibility complex contracts to be performed
solely of the buyer, nevertheless it over a long period of time, the
should be emphasised that the successful document could include the following:
drafting of specifications is one of the • introduction
most important responsibilities of a • scope of the requirement
professional purchasing officer. • background to the requirement
• detailed description of the
The starting point for the preparation of functional requirements, classified
the specification, particularly in the case as essential, optional and desirable
of large and complex projects, is the • description of the performance
business case. The drafting process is requirements including input and
concerned with breaking down the output details
overall scope set out in the business case • timescale/timetable
into more detail and then, progressively • performance measurement
and iteratively, refining into schedules of requirements, for example volume,
detailed requirements. accuracy, availability, including
damages and incentives/ service
All contracts are different and the credit details
following process is not intended to be • other requirements, for example
prescriptive but to act as a checklist for security, access, standards, training,
issues that should usefully be considered personnel, disaster recovery, data
when preparing the specification: archiving, data protection
• define in detail the scope of the need • constraints, for example, time,
including the essential or core interface with other parties, IT
requirement, optional and “desirable” issues
needs • contract management requirements,
• establish sources of information about for example management
the need from: information, project management
• business owners and risk management methodology,
• customers and users and processes
• other stakeholders • contractual requirements, for
• technicians examples terms and conditions,
• the supply market roles and responsibilities of
• gather information on: personnel, opportunities for
• background to the need submitting alternative proposals
• future developments
• detailed requirements
• metrics required for performance
measurement

12
• procurement procedures including The specification document should be
timetable, evaluation and acceptance reviewed and signed off by a person
criteria and process, contact with the necessary knowledge,
information, format and content of experience and authority. The review
responses. Public sector should ensure that the specification:
organisations subject to the EU • is complete and accurate
Procurement Directives must ensure • meets stakeholders’ needs
that this information is also included • addresses future requirements
in the notice placed in the OJ • addresses identified risks
• appendices providing background • complies with and addresses the
data, statistics, organisational issues identified by the original
information. business case
• is capable of being met by the market
The process of preparing the • complies with EU Procurement
specification should also include the Directives (Public sector organisations
drafting of the evaluation model and only).11
criteria. It is important to ensure that:
• all the information needed for h)Establishing the form of contract
evaluation has been requested from
potential suppliers Contracts can range from a single, ad
• the evaluation covers all the hoc agreement for the provision of a
organisation’s needs product or service of relatively low
• the responses are in a format that monetary value, requiring little more
enables an effective, clear and fair than a short term, formal relationship, or
evaluation of offers to be carried out. an overarching framework agreement,
through contracts for long term product
A successful specification should: or service contracts, to a series of
• set out the requirement fully, clearly, contracts for large, complex construction
logically and unambiguously or leading edge research and
• focus on the outputs and how they are development contracts with multi-million
to be met pound values requiring the
• contain sufficient information for establishment of strategic partnerships
potential suppliers to submit credible and alliances.
and realistic offers
• ensure that all information needed for Commercial or mercantile law includes
11
effective evaluation is requested agency agreements contracts for the sale
(OGC Contract
Management, • permit offers to be evaluated against of goods and services, insurance,
CIPS Study guide the declared criteria negotiable instruments, carriage by air,
Legal &
Procurement
• set out the acceptance criteria sea and land and electronic trading, and
Processes, Lysons • provide a fair opportunity for all there are extensive examples of forms of
CIPS EU potential suppliers to submit offers contract in all these areas.
Procurement
Directive • not discriminate against or be biased
Guides) towards any supplier.

13
Clearly, however, a “one size fits all” determine firstly, whether or not the
approach to the form of contract is organisation will adopt a pre-
unsatisfactory and will be ineffective. It qualification system, determine the
is therefore extremely important that the qualifications or criteria and concurrently
appropriate form of contract is drawn up decide the tendering procedures.
that not only reflects the size, nature,
value and complexity of the need but Public sector organisations must comply
also the relationship required with the (if the procurement itself is applicable)
potential supplier(s). with the requirements of the EU
Procurement Directives. These cover all
Post-award management of longer term, aspects of the procurement of works,
high value and complex contracts can be goods and service requirements and
categorised as service delivery govern consideration of the tendering
management, relationship management procedures to be adopted by the buying
and administration. The form and organisation. The Directives also set out
content of the contract document should the rules covering the procurement
therefore also be determined by the procedure to be followed and the
balance and significance required by permitted criteria for selecting (or
each of these aspects of the post-award excluding) suppliers invited to tender
management. under the restricted and negotiated
procedures and the contract award
It is worth reiterating that the criteria. The Competitive Dialogue
foundations for successful contract process has now been introduced –
management post-contract award are laid should this also be referred to here.
down in these stages and thus the
aspects of clarity and comprehensiveness “The EU Procurement Directives also set
are extremely important in determining out rules covering particularly complex
the form and content of the contract contracts in which a Competitive
document. Dialogue process can be employed. Thus
consideration of the tendering procedure
i) Establishing the pre-qualification, to be followed should also have regard to
qualification & tendering procedures the contract’s complexity.”

Evaluating the suitability of potential The regulations limit the scope of the
suppliers to meet the commercial Selection Stage to three key areas of
requirements of the organisation is questioning relevant to the subject areas
normally undertaken via a pre- of the contract:
qualification system. This is the most • eligibility in terms of insolvency, grave
efficient method of assessing suitability misconduct, and so on.
to meet the required criteria and is • economic and financial standing
carried out prior to inviting them to • capability and capacity for the project
tender. In large, complex contracts of and track record in providing similar
long duration it is important to services.

14
Buying organisations not subject to the The PQQ should seek the following
EU Procurement Directives should also, general information:
however, give full consideration to the • organisation, including ultimate parent
procedures by which they seek potential details, identity and ownership,
suppliers, evaluate and award contracts. background
• principal activities (past and present)
The pre-qualification or selection of • organisational chart
potential suppliers is a critical stage in • contractor/sub-contracting approach
the overall evaluation and award • professional/commercial affiliations
process. It should be seen as distinct • legal
from the contract award but as a process • financial
which informs and assists the contract • capability
award decision. • quality management systems
• experience and track record.
The pre-qualification requirements
should accord with the overall evaluation The PQQ should also make it clear that
strategy drawn up concurrently with the references may be sought from selected
procurement and contract strategy current customers.
referred to in section C.
It is important that PQQ questions ‘make
The key to success at the pre- sense’ to the supplier, that they deal with
qualification or selection stage is to topics, processes and services that they
strike a balance between the creation of can readily understand, that the PQQ
a shorter list of potential suppliers from does not ask for inappropriate
the list of suppliers indicating an interest, information (or the right information in
which can be the subject of in-depth an inappropriate way) and the suppliers
evaluation, and a list sufficiently large to have scope to question, suggest and
ensure that suitable suppliers are possibly adapt your needs.
actually selected and proceed to the
tender invitation or ITT stage. The dividing line between the
information needed for selection and
Information on supplier capability and that which is obtained later (at
capacity can be sought through a evaluation or during negotiations) is not
number of routes, formally and always clear-cut. In some areas, it may
informally. In the case of complex differ in degree of detail rather than in
requirements, it is advisable to indicate nature. Some areas may require
in any advert (including for Public sector expansion or clarification later on,
organisations, any notice placed in the possibly through site visits. It is
OJ) that a Pre-qualification questionnaire important to avoid putting suppliers to
(PQQ) will be issued to those expressing extra work that adds no value. Therefore,
interest. only ask for information which will
actually be used in assessment, avoid
scoring systems based on questions

15
requiring only "yes" or "no" answers, responding, tenderers are entitled to
consider, where appropriate, using expect that their offers will receive fair
standardised formats and word limits to and full consideration and that their bids
level the playing field and reduce bid will remain confidential. It is important
costs and evaluation timescales, and seek therefore that tenderers have confidence
information from participating suppliers in the tendering procedures laid down
on likely bid costs and ways to reduce by the buying organisation to ensure
them. impartiality and confidentiality. In
tendering to the public sector,
A variety of pre-qualification confidence in impartial treatment is
questionnaires are available from CIPS secured by adherence to the strict
which can be tailored to your own tendering rules set out in the EU
particular requirements. Construction Procurement Directives. The need for
line provides a PQQ database covering transparency in the public sector,
most of the construction industry. however, limits confidentiality since the
Consideration should be given to Directives require subsequent
allowing suppliers to refer to this as their publication of price details.
response to the PQQ.
The underlying principle is that the
Supplier appraisal starts formally with an parties to the tendering process should
assessment of those suppliers who have retain confidence by strict and
completed the PQQ. The objectives of transparent adherence to a procedure
this stage are to establish whether any which formalises the manner in which
suppliers should be excluded from tenders are received, evaluated and
further consideration because they fail to awarded. The maxim that the system “is
meet the criteria and reject them, and to and seen to be” impartial is an important
create the manageable shortlist of one. Attention should be given to such
realistic candidates mentioned above procedural issues as:
who qualify by meeting the criteria and • the closing date and time for receipt of
who will be asked to proceed to the next tenders
stage (tendering, entering into • late tenders are returned unopened
negotiations, for example) to identify any • tender documentation is securely held
points that need to be clarified with until the opening process
selected suppliers through meetings, • the tender opening procedure is
supplier visits and/or reference site visits independently witnessed and tender
at a later stage. (See section j) Appraising price details recorded
suppliers.) • electronically submitted tenders are
password controlled and possibly
In the same way that the PQQ should encoded
pose meaningful, relevant questions • evaluation and award criteria
12
designed to inform the selection decision • the format and content of responses (OGC Contract
Management.
without placing unnecessary and costly including the manner in which they CIPS ethical
burdens on potential suppliers in are submitted. code)

16
The procedural matters should be management and the achievement of
communicated to potential tenderers competitive advantage in securing goods
both in the tender documentation and or services.
any advertisements.
The process should commence when the
Other issues to be considered when requirement is known and, because it is
determining the tender procedures are: not necessary to carry out the process
• any post-tender negotiations (PTN) for all needs, the requirement should be
conducted do not undermine categorised according to whether it is
confidence or trust in the competitive standard or non-standard, of strategic or
system through unethical means, the non-strategic importance and of high or
use of buying or political power or the low value. Assistance in assessing these
adoption of “Dutch auction” or “horse latter two categories can be gained from
trading” techniques the application of Kraljic’s matrix to
• adherence to the buying assess the strategic importance of a
organisation and/or the CIPS ethical requirement and the use of Pareto and
code12. ABC analysis techniques to assess value.

j) Appraising suppliers When to appraise?


The process is time consuming and
Supplier appraisal establishes (or costly and, as already mentioned,
otherwise) a potential supplier’s selectively carried out. There are,
capability and capacity to deliver goods however, certain situations in which it is
and services to your organisation now strongly advised to conduct appraisal
and in the future. The assessment and the following provides an indication
process should establish the supplier’s of these situations but is not exhaustive:
capability to control quality, delivery, • strategic, high profit, high risk, non-
quantity, price and all the other factors standard requirements
contained in the contract. Following a • capital requirements, construction and
successful appraisal, the supplier is similar projects
placed on an approved list of suppliers. • supplier development
• JIT arrangements
CIPS produces guidance on Supplier • use of supplier associations
Appraisal in its “How To” series, and it is • global sourcing
not intended to replicate the booklet • e-procurement arrangements with
here but to summarise the issues long-term strategic suppliers
surrounding supplier appraisal under the • negotiating TQM and quality in respect
headings provided in that guidance of of high profit/risk items
why, when, what, who and how. • outsourcing contracts
• before agreeing sub-contracting by a
Why appraise? main supplier
Supplier appraisal is an essential aspect • service level agreements.
of strategic sourcing, successful supplier

17
What should be appraised? innovations introduced, references
There will be a range of factors to be • Corporate Social Responsibility (CSR)
appraised which are directly related to issues, including determining the
the particular requirement, but the policies on environment, human
following should act as a checklist of rights, equality and diversity,
aspects to be assessed for the majority of sustainability, ethics and ethical
contracts; the significance of each and trading, biodiversity, corporate
thus the time devoted to the assessment governance and impact on society13
will again vary according to the • information technology, including the
particular requirement: extent and the use made of current IT
• finance, including turnover, profit, to support and report on business
assets, ROC, borrowings, debts, credit activities.
status takeover/merger possibilities,
market positioning. The appraisal Who should appraise
should employ the service of credit Apart from the procurement of standard
agencies such as Dunn and Bradstreet or MRO products, appraisal should be
to provide supplier evaluation reports carried out on a team basis and include
• production capacity, including the following:
available productive capacity, scope • buyer
for expansion, capacity utilisation • users
percentage with and without your • technical staff
organisation’s requirements • decision makers
• production facilities related to the • other stakeholders.14
particular requirements including
range, type, age and sophistication of • Third Party Appraisal
plant and machinery, maintenance This can be carried out by agencies
levels, housekeeping including:
• human resources, including staff • BSI
numbers and employment, skills and • certification of major companies
qualifications, training policies, • supplier consortia
management/worker relationships, • independent management
worker representation, industrial consultants
dispute record, attitudes and • UK Accreditation Service
motivation, staff turnover • UKSA accredits third party
• quality, including the implementation independent certification bodies,
of quality systems, for example ISO testing and calibration laboratory.
9001:2000, ISO 14000, policies on
TQM, inspection and testing How to appraise
procedures, statistical controls, quality Appraisal methods can be roughly 13
(CIPS
control procedures for sub-contractors, classified under three categories desk: Corporate Social
guarantees field or site visits and third party. Responsibility)
14
(CIPS Supplier
• performance, including information on • Desk appraisal. This utilises published Appraisal. See
past and current projects, features and and unpublished information and is also Lysons)

18
particularly appropriate for product above. It should be borne in mind that
and financial appraisals. Typical while some of the evidence gathered
sources of information are catalogues, may be more subjective, some matters
product data sheets, test reports, can be objectively assessed.
websites and trade journals. Desk • The following are areas which warrant
research should precede field research particular attention by staff involved in
since it will indicate what matters need the appraisal visit:
to be investigated and help to assess • personal attitudes of supplier’s
the accuracy and veracity of the employees, providing an indication
answers provided by potential of likely service quality and
suppliers. Questionnaires are the most dependability
economical method of obtaining • adequacy and care of plant and
information as a basis for supplier machinery
appraisals. They can be used either • technical knowledge of supervisory
prior to visits to suppliers or as basis staff
for supplier certification. They should • quality control methods
provide assurances to the supplier of • housekeeping
confidentiality, and the questions • competence of design, research and
themselves should be as clear and laboratory staff including
concise as possible and designed to knowledge of latest materials, tools
elicit the information required by and processes and industry
avoiding “closed” questions. Assistance developments
on the design of questionnaires can be • competence of management
found in the “How to” guide. including commitment.
• Field appraisal. This involves visits to
potential suppliers and other sites and k)Drafting ITT documents
should follow desk research and
supplement the information gained As with drafting specifications, great
from that process. It is particularly attention should be paid to ensuring that
important to carry out this form of the contract document as a whole sets
appraisal when evaluating suppliers of out clearly, comprehensively and
high risk/high value products and unambiguously, the obligations of the
when long-term, collaborative parties to the agreement.
relationships are under consideration
and vital operational services are to be As already mentioned, all contracts are
supplied from site. A checklist of different, both in requirement as well as
matters to be investigated should be complexity and supplier relationship
carefully prepared prior to the visit to needs. The following schedule should
ensure that no important questions are therefore be seen as a checklist and not
overlooked and to provide the a prescribed list of matters to be
evidence for decisions reached. The considered for inclusion in every
checklist will largely be based on the contract:
matters set out under what to appraise

19
• form of agreement or form of tender • dispute resolution procedures
setting out the contract period and including escalation process
spaces for signatures • sub-contractor information
• specification of requirements including • contract change procedures arising
the levels of output to be achieved and from both internal or external sources
the performance measurement and the consequential need for
methodology, relevant information to flexibility in contractual terms
enable bids to be submitted • contract management arrangements to
• conditions of contract or articles of ensure successful service delivery and
agreement. These should comprise the level of control your organisation
definitions, general terms including requires during contract performance
changes, alterations and variations • communications including frequency,
clause, notice clause, commercial level, detail, content
terms setting out the rights and • exit/termination strategy and
obligations of the parties, conditions, procedures
warranties, confidentiality, intellectual • drawings
property, indemnity, exit management, • free issue materials schedule.
data protection, dispute
resolution/escalation and termination This list of matters which are not
clauses and “standard “ clauses which exhaustive should be categorised and
should appear in all contracts covering arranged clearly and logically into the
such matters as liability, severability, tender document. Typically this may
waiver, force majeure and jurisdiction comprise the following sections:
• pricing schedules - particular attention • form of tender
should be given to ensuring that • conditions of contract
potential suppliers are bidding on the • scope of work or technical
same basis of output required specification
• price variation mechanisms applicable • administrative and tender submission
to products, services and time-based instructions
requirements • schedule of prices
• invoicing and payment terms and • drawings
methods, for example BACS, CHAPS • schedule of free issue materials.
cheque, and so on,, invoice content
requirements An extremely useful model form of
• pricing basis including milestone, Contract for the Provision of Services
incentivisation, payment reductions for together with guidance notes is available
non-compliance, retention, advance, from CIPS and can be used or adapted
interim as the basis of part of contract
• implementation and transition plans documentation.
including knowledge transfer
• testing methodology Contract documentation issued by public
• acceptance strategy and procedures sector organisations will, in addition,
• award criteria need to comply with the tendering

20
procedures of the EU Procurement simple straightforward process to one
Directives, and it would be necessary for which is complex, involving many
the purchasing officer to be familiar with professional disciplines formed into an
those directives. evaluation team and carried out over a
period of time.
It is common practice for the enquiry
inviting tenders to consist of: Tenders should be initially evaluated
• a covering letter explaining the under the twin considerations of
invitation and re-iterating the date and commercial and technical, the latter
time by which tenders must be possibly carried out without price
returned information, to ensure that the bids are
• re-iterating the instructions to brought to a comparable basis for more
tenderers about the manner in which a thorough evaluation and study, without
the tender should be submitted the influence of commercial
• the name and contact details of the considerations.
responsible procurement person
• the procedure for raising queries and The criteria for tender evaluation should
receiving clarification follow the award criteria set out in the
• the tender document tender documents and communicated to
• pre-printed labels for tender return.15 the potential suppliers. Public sector
organisations are required under EU
l) Evaluating tenders Procurement Directives to award tenders
using only the criteria set out by the
All tenders received by the appointed buying organisation in the OJEU
day and time should be recorded. This advertisement. This can be either Lowest
process can range from maintaining a Price only or a range of criteria, linked to
simple clerical record of valid tenders the subject matter of the contract,
received by the appointed time to the collectively known as contributing to the
appointment of a tender opening board “most economically advantageous
who record such issues as: tender”. The relative weighting of each
• who tendered criteria, or their listing in descending
• the price quoted if a lump sum or bill order of importance, must be set out in
of quantities bid the contract document and/or in the
• the organisations which declined to OJEU contract notice.
submit
• rejected bids In principle, the evaluation process
• deviations or qualifications to offers should include not only the analysis of
• programmes quoted the potential supplier’s response to the
• the integrity of the tender procedure. main subject matter of the requirement
set out in the ITT, such as price, delivery,
The formal opening procedure is quality, methodology, for example but
15
(CIPS Buying
Goods and
followed by the tender evaluation also, most importantly, the quality of the
Services) process which, again, may range from a bidder’s offer.

21
delivery or content, in circumstances
The evaluation process includes a which do not put other tenderers at a
clarification process whereby the buying disadvantage or affect adversely their
organisation can seek further confidence or trust in the competitive
information in order to inform the system”. PTN does not apply, for
decision making process. Clarification example, where
should not be seen as an opportunity to • there is no formal tendering process
negotiate or change the basis of the • there is only one supplier
decision, as this will only serve in the • there are discussions to clarify bids
longer term to undermine the credibility, • there is a need to correct problems
trustworthiness and standing of the arising from poor pre-contract
buyer and the buying organisation. preparation, or there are normal price
Additionally, public sector organisations adjustment requests or contract
must comply with EU Procurement variations during the life of the
Directive rules governing the clarification contract by either party.
process.
It is worth reiterating that any PTN
m) Negotiation should not undermine confidence or
trust in the competitive system through
It is not the intention of this guide to unethical means, the use of buying or
provide guidance on negotiation political power or the adoption of “Dutch
techniques. Information and further auction” or “horse trading” techniques
assistance can be found in the and should adhere to the buying
bibliography section of the guide and on organisation and/or the CIPS ethical
the CIPS website. Negotiation is covered code, as well as any tendering rules
here in the context of the formal stages established.
of contract management covered by this
guide. When the buying organisation has
decided that PTN will be conducted, the
It is the aim of every purchasing following matters should be considered:
professional to conclude the best deal • the criteria for conducting PTN
for the organisation he or she represents. • contract value
This is often achieved by post-tender • the balance between potential savings,
negotiation (PTN) and is an activity to be the cost of carrying out PTN and the
considered and planned for in the likely benefits
formulation of the contract strategy. • time
• effect on the market
CIPS defines PTN as “negotiation after • the rules contained in the EU
receipt of formal tenders and before the Procurement Directives for public
letting of contracts with sector organisations
suppliers/contractors submitting the • ethical issues.
lowest acceptable tender with a view to
obtaining an improvement in price,

22
roles and responsibilities
The methodology and conduct in • identifying the buyer’s and the
undertaking PTN is, in principle, the supplier’s respective negotiation
same as that for any negotiations outside situations, strengths and weaknesses
the context of a formal tendering • time and degree of urgency of the
process, although the activity may purchase. “Necessity never made a
possibly be less complex or drawn out. good buyer” – urgency is never a good
The following matters, however, should negotiating position and time may in
be considered in determining the fact determine the negotiating tactics
negotiation strategy: that have to be adopted.
• the approach, such as adversarial or
partnership (respectively a “win-lose” Consideration must also be given to the
or “win-win” situation). There is no negotiating process itself and issues such
right or wrong approach - either may as:
be appropriate. For example, an Pre-negotiation stage:
adversarial tactic may be the right • deciding upon a team or individual
course where no on-going relationship approach – if the former, allocating
is contemplated and the purchase is a roles and ensuring the appropriate
one-off or a simple resolution of a level of expertise will be present; the
problem is sought. A partnership venue, information gathering including
negotiation tactic may be appropriate SWOT analysis and data presentation,
where a long-term, stable relationship determining the objectives, deciding
is contemplated and/or the approach the strategy and tactics at the actual
is the only one likely to succeed in negotiation stage including negotiation
resolving complex, intricate problems order, opening speakers, recesses,
• identification of the implicit and issues of concessions to be made, if
explicit objectives of both parties any, linked issues, for examples price
• the fall-back or Best Alternative to a and quality, likely reactions to tactics
Negotiated Agreement (BATNA) of both parties, role plays and dummy
positions of both parties (as far as runs
possible) Actual negotiation stage:
• the negotiation goals. Both the • establishing the stages and procedural
substance goals and the relationship rules, agreeing the agenda,
goals are effectively concluded when determining the issues to be resolved,
the former have been resolved and agreeing common goals, removing
when the latter have led to the barriers to achieving goals and final
preservation or enhancement of the agreement and closure, adopting the
working relationship appropriate behavioural tactics
• the results of undertaking “what if” necessary, determining the ploys (if
and sensitivity calculations on the any) to be used
tendered prices Post negotiation stage:
• the negotiators – personalities needed, • drafting agreement statements,
authority levels of the negotiator(s), communicating the agreement to

23
stakeholders, implementing the
agreement and monitoring the n) Awarding the contract
implementation
Following tender evaluation and, where
This is not intended to form an appropriate, negotiation, the project
exhaustive check-list of the issues to be team will satisfy itself that an offer has
borne in mind when it is proposed to been made which meets its requirements
conduct post-tender negotiations, but in all respects, including budgetary, and
will act as a prompt to the type and consider that it is in a position to accept
nature of the matters to be addressed. an offer and award the contract to the
tenderer who has made the most
Finally, it is worthwhile bearing in mind economically advantageous offer to the
a number of general principles when organisation. It may then move directly
considering negotiations, particularly in to the award stage or make a
relation to large, high value contracts: recommendation to higher authority
• avoid treating each negotiation as a levels within the organisation for
separate event. This can be acceptance.
counterproductive when viewed from
a strategic level through the agreement The contract award stage comprises of a
of advantageous terms on a particular number of important aspects;
contract at the expense of the long- communicating the award to the
term relationship with the supplier successful tenderer, notifying the
• avoid negotiating each component of a unsuccessful tenderers, debriefing
single negotiation in isolation - a unsuccessful tenderers and, in the case
composite approach can often secure of contracts awarded under EC
a better overall commercial solution Procurement Directives by public sector
• broaden the evaluation of negotiator’s organisations, publishing a contract
performance beyond price and quality award in the OJEC. As will be seen, it is
to measuring innovation and creative also useful for the procurement
alternative solutions organisation to conduct a debriefing of
• recognise the difference between deals the successful tenderer.
and relationships. Concessions granted
during deals can lead to an adversarial This stage should also include activities
climate and mistrust and damage long- such as:
term relationships • ensuring that all relevant parties are
• understand when to “walk away from aware of their roles and
a negotiation”. Negotiators should be responsibilities in the immediate
encouraged to make good choices, not implementation and transition process
merely to produce agreements which • checking that the agreed processes for
are mutually unsatisfactory.16 contract management are in place by
all the parties
• that knowledge transfer from the
procurement or project team (which 16
(Lysons)

24
may not have included members of a variety of reasons, for example to
the contracts management team) to smooth service transition, to speed up
the contracts management team takes the start of a project or to secure more
place to ensure successful time to finalise contractual terms. A wide
management of the contract range of potentially serious problems
• that, where necessary, the continuity can arise from the indiscriminate use of
plans for the seamless transition of the Letters of Intent and consequentially
service from one contractor to the new CIPS discourages their use and advocates
contractor will be carried out as establishing a separate contractual
agreed. arrangement for the small amount of
work that otherwise would be the
The method of informing the successful subject of the Letter of Intent. If there is
tenderer should follow the method set no alternative, great care should be given
down in the tender documents (see to the wording of the Letter of Intent to
section k). Whatever method of minimise the risk to the organisation and
communication is adopted, it is essential to ensure that the Letter is not binding
that the notification is clear, on the organisation for anything other
unambiguous and sufficiently than the specific work set out in it.
comprehensive to ensure that there is no Equally, care should also be taken to
possibility of doubt by either party about avoid giving inadvertent instructions to
what has been accepted. Normally this supplier(s) to carry out work or indeed
should take the form of a counter-signed verbal comments which may be
copy of the tender document interpreted as instructions.17
incorporating all the agreed amendments
made during the negotiation and As already mentioned, it is beneficial for
clarifying stages. Notification should be the buying organisation to debrief the
made by the appropriate authority level successful tenderer to gain their view of
within the organisation. the procurement process recently
undertaken, to gain better understanding
Concurrently, the unsuccessful tenderers of that market, to improve
should be advised of the non-acceptance communications, to maintain good
of their offers and, in the case of practice processes and to establish a
contracts awarded under EC good working relationship with the new
Procurement Directives, a contract award supplier at the earliest opportunity.
notice should be placed in the OJEC
within the proscribed timescale and in It is equally beneficial to debrief
accordance with the regulations relating unsuccessful tenderers. It assists
to the content of the notice. suppliers to improve their competitive
performance, not only with the buying
17
(For more Some organisations from time to time organisation in the future but in markets
information and make use of Letters of Intent to elsewhere. In addition to the benefits
a suggested Letter
see CIPS POP
communicate instructions or requests to gained from debriefing the successful
Letters of Intent) the potential supplier. These are used for tenderer, the organisation benefits by

25
developing a potentially wider range of turns to post-award activities. These can
suppliers, thus increasing the potential be grouped into three general areas: the
for improved value for money, by management of service delivery, the
receiving better quality bids in future management of the relationship with the
and gaining useful market intelligence. supplier and contract administration. The
first is concerned with ensuring that the
Debriefing should be constructive and as service is being delivered in accordance
open as possible, not defensive and with the agreed performance and quality
secretive. In general, it should be seen as levels set out in the contract; the second
helping to demonstrate procurement is concerned with maintaining and
professionalism and establishing the developing an open and constructive
organisation’s reputation as a fair and relationship with the supplier and the
ethical buyer with whom suppliers last with the formal management of the
would want to do business. contract.18

Following selection and award, the o) Changes within the contract


communication advising tenderers of
their success or otherwise should thank Changes are almost inevitable during the
them for their participation in the period of a contract, particularly in the
tendering exercise and offer them a case of large, complex construction and
debriefing opportunity. If unsuccessful service contracts. They should not
tenderers respond, requesting debriefing necessarily be seen as causes for concern
sessions, these should take place as soon but, effectively managed, as
as is conveniently and practically opportunities to improve the contract
possible after award and, in the case of outputs.
public sector organisations, in
accordance with EU Procurement It is important to understand the
Directive regulations. implication of change for both parties.
Changes of any significance will affect
It is important that the debrief the scope and potentially the viability of
parameters are made clear, ideally the contract for either party. If a change
confined to such topics as tenderer results in a reduction in the value or
selection, tender award and tenderer scope of the contract, the organisation
withdrawal issues (where appropriate); it could be faced with claims for increases
will not provide an opportunity to in charges and/or legal claims that there
change any decisions and it will be was, for example, misrepresentation in
confined to their own offer. relation to the likely volumes required
over the period of the contract. If the
Downstream or post-award activities. change results in a substantial increase
in the value or scope, it is important that
Having carried out the pre-award the organisation continues to ensure that
activities associated with contract value for money is secured. Public sector 18
(OGC Contract
formulation and award, the process now organisations should be additionally Management

26
aware of the requirements of the EC p) Service delivery management
Procurement Directives needing
substantial changes during the contract This activity is concerned with the
period. fundamental aspect of contract
management, that of ensuring that the
Change can be driven by a number of actual service provided by the supplier is
factors; amongst the more common are in accordance with the agreed standards
amendments to the strategies and and prices. The ability to measure the
objectives of the parties, the changing performance of the supplier - sometimes
business needs of the organisation, called vendor rating - and to provide
market changes, developments in feedback is critical to successful contract
technology, economic trends which management and supplier development.
affect the viability of the contract and
legislative change. These in turn can lead Performance measures to cover all
to changes in the service required, the aspects of a contract should be designed
metrics needed, service infrastructure to suit the requirements of a particular
and workload. contract and should be set out in the
contract documentation to ensure
Changes are easier to manage when suppliers are fully aware of both the
planned. Even the effects of an measures and the measurement
unexpected, externally driven change methodology before any contract is
can often be mitigated through, for awarded. It is important that the
example, on-going effective risk performance measures selected provide
assessment and the phasing-in of any clear and demonstrable evidence of the
implementation. Changes will require success (or otherwise) of the relationship
negotiation with the provider(s) and the and, in principle, issues such as the
introduction of amendments carefully following should be covered:
scheduled to avoid workload peaks and • cost and value obtained
year-end activities where possible. The • performance and customer satisfaction
implementation of the change should be • delivery improvement and added value
effectively managed using change • delivery capability
control procedures (see section r). • benefits realised
• relationship strength and
Particular care should be taken when responsiveness.
making changes to construction, building
and IT contracts. What are apparently It is important to ensure that the actual
quite small changes can have metrics selected are not over-specified,
unexpected knock-on effects on other that they are, as far as possible, readily
costs, particularly, for example, if a obtained from the direct performance of
construction sequence is affected. the contract and that they are focused on
Wherever possible, the outcome should issues such as those outlined above which
be agreed with the supplier before impact most heavily on the organisation.
instructing such a change. It should be remembered that there are

27
costs attached to the production and There are three aspects to performance
maintenance of metrics by the supplier measurement;
who will seek to pass them on in the • gathering of factual, objective
form of higher prices or charges. information from the supplier - usually
obtained from IT systems
Once chosen, the requirements • gathering feedback from users about
underpinning the performance measures the service received – typically
should be the primary focus for contract through questionnaires, surveys,
management. They should form the telephone or face-to-face enquiry
framework on which information needs • understanding the supplier’s own
and flows and contract management experience of dealing with the
teams, skills, processes and activities are organisation.
developed and improved in conjunction
with the supplier. Performance measurement can be an
expensive and time-consuming activity,
They should not be seen as a method of and as such should be carried out on a
control, but as a proactive means of selective and prioritised basis,
improving the performance of a supplier. proportionate to the value and
Suppliers should always be requested to importance of the contract to the
improve their performance, and organisation. This is particularly
incentives, used appropriately, should important when time and resources are
encourage improvement. Performance very limited. Suppliers of high value,
measurement results can be used to high risk goods and services should be
inform decisions on the type and extent closely monitored, possibly involving
of incentives. frequent regular meetings at the
supplier’s premises or on site. Security or
There are a number of themes which bottleneck type goods and services of
could be used to measure supplier low value but of significant importance
performance: to the organisation may require less
• product quality - Mean Time Between frequent but regular monitoring. High
Failure (MTBF), Mean Time to Repair value or volume and low risk items may
(MTTR), percentage of delivery rejects, need only quarterly meetings to ensure
warranty claims satisfactory performance monitoring.
• service quality using Service Level
Agreements (SLA) – call-out time, q) Relationship management
customer service response time,
performance against agreed delivery, Contractual arrangements may commit
lead times the organisation to its supplier(s) for
• relationship Management (see section some time and to varying degrees of
q) – accessibility and responsiveness dependency. It is therefore important to
of supplier management make the relationship work effectively
• commercial – costs are maintained or by developing mutual trust and
reduced, service improved. understanding, creating an open and

28
constructive environment and problems of management capability,
contributing to the joint management of resources or financial capitalisation
the contract delivery. • too frequent demands for submission
of competitive bids – reduces trust in
It is primarily through the development the relationship.
of mutual trust and confidence that the
other elements for success are created. It should be remembered, however, that
As the supplier gains greater such issues should have been identified
understanding of the organisation’s and resolved at the pre-award appraisal
business needs and style and develops a stage.
level of confidence and trust, it will be
more willing to be proactive and In addition to the elements mentioned
innovative in bringing forward above, other factors that encourage the
improvements and savings to mutual development of a successful relationship
benefit, more willing to share problems, include:
plans and concerns, more willing to • securing senior level support in both
negotiate and more confident in organisations
investing for the longer term. The • recognising that actions and attitudes
organisation benefits by gaining a affect the tone of the relationship
greater understanding of the strengths • ensuring that the governance
and weaknesses of the supplier, enabling arrangements are fair
it to concentrate its management and • ensuring that relationships between
development support in those areas. the parties are peer-to-peer as far as
possible
Factors that can inhibit the development • ensuring that roles and responsibilities
of a successful relationship include: are clearly understood by both parties
• frequent and rapid recourse to the and that the necessary authority levels
formal contract to overcome problems have been ascribed
• clashes in cultures which are so • ensuring that escalation routes are
disparate as to prevent the creation of clear and understood but that
the level of trust and confidence problems are resolved as early as
required possible and as low down the
• reluctance by the supplier to co- management tree as possible
operate in value for money or • separating strategic matters from the
benchmarking tests conducted by the day-to-day service delivery issues
organisation • ensuring that appropriate attitudes and
• commercial issues, for example lack of behaviour are practised and displayed
real competition resulting in to assist the promotion of a positive
uncompetitive, poor value for money and constructive relationship
terms from the supplier, or conversely • communicating and sharing
that the organisation is critically information at the appropriate level
dependent on one supplier leading to between the organisation and the
price rise vulnerability and/or supplier, for example strategic,

29
business and operational levels and as important activity. As already mentioned,
openly as possible. formal change control procedures should
be designed and set out in the original
Performance monitoring of suppliers was contract documentation to avoid
covered in section p) in relation to the misunderstanding and ambiguity about
management of service delivery. It roles, responsibilities and the actions to
should be re-iterated, however, that it is be taken in any given situation. These
equally important that the exercise change control procedures should be
should also cover the relationship initiated at the earliest opportunity, post-
between the organisation and the contract award. They should include
supplier, albeit that the measurements procedures to keep all contract
themselves may be somewhat more documentation up to date and consistent
subjective. Such issues as the quality of so that all parties have a common view
the supplier’s R & D department, their of the agreed changes. For particularly
project management performance, the large contracts or where there are a
level of management responsiveness, number of Service Level Agreements
flexibility and effort can be assessed as (SLA) in place, a formal document
well as benchmarked. management system should be set up.
The procedures need to be
r) Contract administration comprehensive but also flexible and
straightforward and should cover such
This activity is concerned with the issues as:
practicalities of the relationship between • how to request changes including
the organisation and the supplier and additional demands placed on the
the operation of the routine supplier
administrative and clerical functions. The • assessing the impact including
importance to the smooth running of contractual implications
post-award contract management should • prioritisation and authorisation levels
not be underestimated and it should be • agreement methodology
resourced appropriately. This is one of • controlling implementation
the primary responsibilities of a contract • documenting changes.
manager.
Normal price variations in the contract
Whilst the level of significance and often fall outside change control
extent of the activity will vary according procedures and have their own method
to the particular contract, one of the of proposal, assessment, evaluation and
main areas critical to successful contract agreement.
administration is contract maintenance
and change control. A formal framework, defining
responsibilities and reporting
Changes will almost inevitably occur arrangements should have been
during the period of a contract and designed and set out clearly in the
managing these changes is a particularly contract documentation. The information

30
called for may range from a complete Whilst the issue of change during the
suite of performance measurement contract should prompt a risk analysis
reports to exception reporting. The activity, the need continually to assess
design of reports should reflect the need risk in large, complex long-term
for flexibility in the type and detail of the contracts cannot be overemphasised. The
information required during the contract techniques for conducting such analysis
period and the recipients’ possible need and assessment are set out in section d).
for access to greater detail. In addition,
regular reporting – monthly or quarterly Risk management during the contract
– may also be required. period comprises those activities
associated with identifying and
Under the contract administration activity, controlling the risks that may potentially
and if the nature of the contract concerns affect the successful fulfilment of the
the use of the organisation’s assets, there contract. Risks to the contract include
will be a responsibility to ensure that the such issues as:
organisation’s asset register is kept up to • lack of capacity of the supplier,
date, the use of assets by a third party is particularly if there are significant
recorded and upgrades and replacements increases in demand
are planned and budgeted. The contract • reduction in demand leading to higher
manager will be responsible for liaison unit costs borne by the supplier
with the provider on administration and • an event which causes an increase in
maintenance of assets. the total of the price to the purchaser
• an event which causes a programme
Other areas covered by contract delay
administration and forming part of the • supplier staff changes
responsibility of the contract manager • changes to the supplier’s business
are charges and cost monitoring, objectives
ordering and payment procedures, • deterioration in the supplier’s financial
budget procedures, resource standing
management and planning.19 • demand changes that cannot be met
by the supplier
s) Assessment of risk • deterioration of quality
• force majeure issues
The importance of risk assessment to • market fluctuations for commodities.
successful contract management has
already been mentioned (see section d) When a risk is anticipated or perceived,
and the likelihood of changes arising its management involves the parties
during long term contracts has also been working together to identify where the
highlighted. It can be seen therefore that responsibility for it lies, methods of
there is a need to conduct continuous minimising it and how the risk will be
risk analysis and assessment throughout managed. Issues to consider for effective
19
(OGC Contract
the period of the contract in order management to succeed include:
Management effectively to manage the risks that arise.

31
• establishing a binding process to the organisation for any failure in
encourage early warning of issues fulfilment of the contract.
such as those mentioned above, as
soon as either a supplier or the t) Purchasing organisation’s
purchaser becomes aware of them performance and effectiveness review
• identifying the party best able to
control the situation leading to the risk Reference has been made to the
occurring necessity to measure the supplier’s
• identifying the party best able to performance throughout the period of
control the risk itself - this may the contract. Equally important, and
include the organisation another downstream activity, is the
• identifying who should be responsible measurement of the purchasing
if the risk cannot be controlled organisation’s performance effectiveness
• establishing whether, if the risk is and efficiency.
transferred to the supplier, the cost to
the organisation will fall, whether new It is not the intention of this guide to
risks will arise and transfer to the cover the wider issue of performance
organisation, and the legal position of appraisal, which should be conducted in
any transfer. an organisation as part of its normal
management practice, but to focus on
It should be remembered that risks the review of purchasing in relation to
transferred to the supplier still require the upstream and downstream activities
managing by the organisation and that of a particular procurement. Both
suppliers will seek to obtain payment for practices will contribute to the
any transferred risk not identified and development and training of professional
incorporated into the original contract. purchasing staff.
Care should also be taken to ensure, in
any long-term partnership based on Briefly, effectiveness is concerned with
openness and trust where the supplier is the ability to accomplish a given goal or
responsible for risk management, that purpose, and efficiency is concerned
the supplier fulfils its obligations with the ability to maximise productivity
effectively and comprehensively. with the least amount of effort, money or
Furthermore, the organisation should resources. In other words, effectiveness
ensure that risk is not transferred back means “doing the right thing” whereas
to the organisation as a result of a level efficiency means “doing things right”.
of co-operation exceeding the scope of
the contractual requirements by the The aims of performance measurement
organisation’s own representatives. of the purchasing department are to:
• ensure consensus between individual,
Finally, it should be remembered that functional and corporate aims
business risk cannot be transferred to • compare actual results with planned
the supplier and that the ultimate performance
responsibility will always remain with • identify reasons for substandard 20
(Lysons)

32
performance and the basis for that may be gathered but they should
improvement include such broad issues as:
• improve decision making • documentation – clarity, understanding
• identify the contribution purchasing and comprehensiveness
can make to the organisation • pre-award contract processes,
• motivate and encourage staff.20 understanding and timetables
• change control procedures – ease,
A range of traditional purchasing understanding, comprehensiveness
performance measurements can be • communication - suppliers, customers
gathered from the on-going management and other stakeholders
of a contract, including metrics such as: • risk - identification and management
• savings on the purchase price • contractual relationships - smoothness,
• reduced inventory levels conflicts
• incoming defects • customer satisfaction
• on-time deliveries • business continuity and transition
• procurement cycle time issues.
• cost of change
• cost of placing orders. Each topic will suggest a range of
questions related to the particular
These can be considered as quantitative procurement as the measurement drills
questions which are readily monitored down to obtain data which will make a
and measured. They are often considered meaningful contribution to the
to be basic, minimum performance assessment of performance. Responses
standards today; nevertheless, they are may be measured in terms of extent, for
extremely important. example “not at all”, “partially”, “largely”
or “fully”.
At a higher level, effective measurement
of purchasing will be concerned with In addition to conducting an internal
establishing the need, managing internal review of the project and documenting
and external relationships, managing the findings, valuable information on the
contracts and performance, managing performance of the purchasing
change, customer support, infrastructure department can be gathered from
issues, business continuity and transition. suppliers during performance review
meetings.
In relation to a particular contract, these
issues can be addressed by raising It should be recognised that some
questions, although more qualitative and information can only be properly and
subjective in nature than those set out usefully gathered following completion
above, that are concerned with the or closure of the contract, whilst it may
upstream and downstream management be critical that other information is
processes and relationship issues. gathered before closure in order to
Mention has already been made in implement process improvement
earlier stages of a number of the metrics changes for future procurement

33
contracts, including the possible re- final inspection carried out
letting of the current contract. • record the date of release of retention
and/or bank guarantees
u) Contract closure • to agree a statement of specific limits
on continuing contractual obligations
This stage concerns the activities after completion of work and any on-
associated with closing the project down, going obligations following the end of
whether in accordance with the contract guarantees or maintenance periods
or as a result of early termination. • record any materials reconciliation
Different activities of course are • transfer any assets, including data and
associated with the different forms that intellectual property, and any loan
contract termination can take. items
• transfer operational systems to the
In the case of more complex, long-term successful supplier
or construction contracts ending in • record the process of final contract
accordance with the original contract payments and a summary of the
plan, best practice requires the need for financial payments and received
evidence that the contract has been • summarise claims made against or
completed to the satisfaction of all received from the supplier
parties. This is normally carried out in • ensure the retention of records
two stages; firstly, to ascertain internally relating to the contract to counter any
that there are no outstanding matters subsequent claims that may be
and, secondly, to secure agreement from brought. The Limitation Act 1980 sets
supplier(s) that, apart from agreed on- out the general periods – six years or
going liabilities, the contract(s) has twelve years according to the type of
ended. contract - within which an action
maybe brought.
The aim of the closure procedure is to
provide a mechanism for managing the On completion of this activity, agreement
closure of the contract following the end should have been reached on all
of any retention or guarantee periods technical and commercial aspects of the
and the resolution of all other contract. The agreement should require
outstanding matters. The procedure is the signature of the parties to a
designed (where and if applicable) to: document which records the acceptance
• ensure completion of all administrative of the work or service, the obligations
matters fulfilled and the price paid or to be paid.
• record that all technical issues have
been completed Another issue relating to the “normal”
• determine the extent of any liquidated end of a contract, which should have
damages to be deducted from the been considered during the pre-contract
contract price award stages, but worthwhile repeating
• record the end of the retention and here, is the renewal or extension of the
guarantee periods and the date of the contract (if appropriate). The terms and

34
procedures for such eventualities should value contracts, the overriding
be incorporated into the original contract consideration is the need to ensure
documentation and should include the business continuity and the maintenance
period for negotiation of terms in order of a service.
to ensure business continuity, together
with a deadline for agreement. This Remedies for breach will include
deadline should allow for risk of failure recourse to adjudication, mediation,
to agree and a period of time for the conciliation, and arbitration and if these
contract to be re-let in order to ensure methods fail – litigation. Resolution can
the smooth transition of the work or take long periods of time extending to
service from the old contract to the new years in the case of serious disputes.
contract. This period could be extensive Focus should therefore be on activating
and organisations in the public sector plans for securing the smooth transition
are reminded that they are required to of the work or service from alternative
adhere to the EC Procurement Directives sources.
and that it is unlikely that an accelerated
contract award process for a new Another important activity conducted at
contract will be acceptable if the this stage, particularly in the case of high
justification is the failure to agree terms value, large contracts, is the preparation
in accordance with the deadline set out of a post-contract project report. This
in the old contract. may follow a formal post-contract review,
undertaken to assess the business
There are many reasons why a contract benefits – or losses - from carrying out
may not be satisfactorily fulfilled in the procurement, how those benefits
accordance with the contract, and it is may be furthered enhanced and/or costs
not the intention of this stage to describe and risks reduced and how the losses
all the circumstances that may arise and can be recouped and turned to benefits.
the associated activities that may be The review should also gather the
pursued and remedies sought for breach lessons that can be learnt from the
in each case. The important factor to management processes and procedures
remember, as already mentioned in stage followed during the contract and
d), is the need to conduct risk implemented in the future. The review
assessment pre-contract award. As part should include the views of all
of that activity, the possibilities for stakeholders and the report should relate
performance failure and consequential to the costs and benefits set out in the
early termination should have been original business case.21
made and appropriate counter-measures
considered and set out in the contract R D Elsey October 2007
documentation. With complex, high

21
(OGC Contract
Management

35
Acknowledgements Bibliography

The author would like to thank the Best Practices in Contract Management –
officers of the Chartered Institute of Strategies for Optimizing Business
Purchasing and Supply, in particular Relationships (2004), Aberdeen Group
Darren Ford, and the members of the Buying Goods and Services - A
Contracts Group, formerly the Legal and professional guide to contracting
Contracts Management Committees, for including model conditions, A D
their support, encouragement and Allwright & R W Oliver. Revised by E S
assistance in the preparation of this Singleton & K R Burnett (1997), CIPS
guide. Contract Management - Positions on
Practice, CIPS
Contract Management. A range of
practical guides and toolkits – Office of
Government Commerce
Corporate Social Responsibility – 2005,
CIPS
European Community Supplies
Directives - A guide for the Public Sector
Fraud – 2007, CIPS knowledge paper
F Harvey (Revised Edition 1998), CIPS
Law of Contract, Paul Richards (Fourth
Edition 1999), Pearson Education
Legal and Procurement Processes - Study
Guide, Eoin Lonegan & Bernadette King
(Revised edition 2003), CIPS
Letters of Intent – Position on Practice,
CIPS
Model Contract for Provision of Services
– 2007 CIPS
Project Management Dennis Lock
(Eighth Edition 2003), Gower
Purchasing & Supply Chain
Management, Kenneth Lysons & Michael
Gillingham (Sixth Edition 2003) Pearson
Education
Service Level Agreements, K Lysons,
CIPS “How to” series
Understanding Organisations, Charles
Handy (Fourth Edition 1993), Penguin
Risk Management in Purchasing &
Supply Management - Positions on
Practice, CIPS

36

You might also like