MC 013-19 Reiteration of LWUA MC No. 003-13 On Review of Build-Operate-Transfer (BOT) and Similar Public-Private Partnership (PPP) For Bulk Water Supply
MC 013-19 Reiteration of LWUA MC No. 003-13 on Review of Build-Operate-Transfer (BOT) and Similar Public-Private Partnership (PPP) for Bulk Water Supply
MC 013-19 Reiteration of LWUA MC No. 003-13 On Review of Build-Operate-Transfer (BOT) and Similar Public-Private Partnership (PPP) For Bulk Water Supply
LOCAL WATER UTILITIES ADMINISTRATION
P.O. BOX34, UP. Post Office, Kalipunon Avenue, Balora, Quezon City
} Tel No.: 920-5881 to 99; 920-8601 FaxNo.: (632) 922-8434
o ‘Administrator’ Ditect line: (02) 929-61-07
LUNUA Websile: www.nua.gov.ph
MEMORANDUM CIRCULAR No.0 | 3" 1 9
TO + ALLLOCAL WATER DISTRICTS
SUBJECT : Reiteration of LWUA MC No, 00313 dated Feb. 28, 2013 on LWUA Review of BOT
and Similar PPP Proposals for Water Supply Projects of LWDs
DATE —: October 8, 2019
On February 28, 2013, our office issued Memorandum Circular No. 003-13" (MC 003-13)
requiring all local water districts (LWDs) intending to implement Build-Operate-Transfer (BCT)
or Public-Private Partnership (PPP) projects through bulk water supply contracts, joint venture
agreements (JVAs), concession contracts and other similar contractual schemes to comply with
Executive Order No. 68 (EO 68) issued on February 10, 1999 by then President Joseph Ejercito
Estrada. EO 68 was issued to implement Republic Act (RA) No. 6957 (An Act Authorizing The
Financing, Construction, Operation And Maintenance of Infrastructure Projects By the Private
Sector And For Other Purposes), as amended by RA No. 7718. The directive was for the
submission of the unsolicited proposals of private sector to our office for appropriate review
and evaluation.
Under EO 68, LWUA is mandated to conduct preliminary and final reviews of BOT proposals for
water supply projects. Section 3 of EO 68 pertinently provides:
“SEC. 3. UNSOLICITED PROPOSALS. For unsolicited BOT proposals with the water
districts as implementing agencies, the approval process shall be as
follows:
WOK XK HK
e. Submission of Documents and Reports — The WD shall be required to
provide LWUA with copies of all the above documents and reports for
its information in order that its review of the proposal will have
sufficient basis.
f. Before the evaluated proposal is submitted for preliminary review by
NEDA, LWUA shall also make a preliminary review of the project
proposal based on the evaluation made by the PBAC (for BOT) of the
water districts;
* LWUA Review of Build-Operate-Transfer and Similar Public-Private Partnership (PPP) Proposals on Water Supply
Projects of Water Districts
Tubig sa Nayon - Alay sa Pilipinas!013:19
g. LWUA shall make its final review of the project proposal after the WD
Board of Directors shall have approved the same.”
In view of the foregoing and considering that EO 68 has not been repealed or superseded, the
directive in MC 003-13 that all LWDs should submit the proposals they receive from the private
sector for BOT or PPP projects to our office for appropriate review and/or evaluation is hereby
reiterated.
Strict compliance is enjoined.
Téci a. Lapus