Scheduling/Leveling Report - 2019-10-09 10:31:31 - PM.

EXE
=========================================================

Default Project..................................................BUIFDP-7

Projects:
BUIFDP-7.........................................................OMS
ICSS R1

Scheduling/Leveling Settings:
-----------------------------
General
-------
Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................Yes
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retained
Logic
Calculate start-to-start lag from ...............................Early Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish Float
Calculate float based on finish date of .........................Each project
Calendar for scheduling Relationship Lag ........................Predecessor
Activity Calendar

Advanced
--------
Calculate multiple float paths...................................No

Statistics:
-----------
# Projects.......................................................1
# Activities.....................................................154
# Not Started....................................................154
# In Progress....................................................0
# Completed......................................................0
# Relationships..................................................366
# Activities with Constraint.....................................30
Project: BUIFDP-7 Activity: A1110 SmartPlant Instrumentation
(SPI) Data Base level 1 ( I/O Database in Excel with 80% accuracy)
Project: BUIFDP-7 Activity: A1120 TPPS Interface List (With 80%
accuracy)
Project: BUIFDP-7 Activity: A1130 SmartPlant Instrumentation
(SPI) Data Base level 2 ( I/O Database in Excel with 100% accuracy)
Project: BUIFDP-7 Activity: A1140 TPPS Interface List (With
100% accuracy)
Project: BUIFDP-7 Activity: A1150 SmartPlant Instrumentation
(SPI) Data Base level 3 (I/O LIST & MULTICABLE number type(numebr pairs)& ALARMS)
Project: BUIFDP-7 Activity: A1160 Cause and Effects Matrix
(With 60% Accuracy )
Project: BUIFDP-7 Activity: A1170 Control Narratives (With 60%
Accuracy )
Project: BUIFDP-7 Activity: A1180 Safe Guarding Narratives
(With 60% Accuracy )
Project: BUIFDP-7 Activity: A1190 Process & Instrumentation
Diagram (P&IDs) (With 60% Accuracy )
Project: BUIFDP-7 Activity: A1200 Alarm Philosophy
specification (With 60% Accuracy )
Project: BUIFDP-7 Activity: A1210 Cause and Effects Matrix
(With 80% Accuracy )
Project: BUIFDP-7 Activity: A1220 Control Narratives (With 80%
Accuracy )
Project: BUIFDP-7 Activity: A1230 Safe Guarding Narratives
(With 80% Accuracy )
Project: BUIFDP-7 Activity: A1240 Process & Instrumentation
Diagram (P&IDs) (With 80% Accuracy )
Project: BUIFDP-7 Activity: A1250 Plant and Section Level
Graphics (With 80% Accuracy)
Project: BUIFDP-7 Activity: A1260 Marked up P&ID (for Process
Graphic) (With 80% Accuracy )
Project: BUIFDP-7 Activity: A1270 Unit Overview Graphics (With
80% Accuracy )
Project: BUIFDP-7 Activity: A1280 TTPS GRAPHICS (With 80%
Accuracy )
Project: BUIFDP-7 Activity: A1290 Cause and Effects Matrix
(With 100% Accuracy )
Project: BUIFDP-7 Activity: A1300 Control Narratives (With 100%
Accuracy )
Project: BUIFDP-7 Activity: A1310 Safe Guarding Narratives
(With 100% Accuracy )
Project: BUIFDP-7 Activity: A1320 Process & Instrumentation
Diagram (P&IDs) (With 100% Accuracy )
Project: BUIFDP-7 Activity: A1330 SmartPlant Instrumentation
(SPI) Data Base level 4 (I/O LIST&MULTICABLE(termination details)& ALARMS)
Project: BUIFDP-7 Activity: A1340 Plant and Section Level
Graphics (With 100% Accuracy)
Project: BUIFDP-7 Activity: A1350 Marked up P&ID (for Process
Graphic) (With 100% Accuracy )
Project: BUIFDP-7 Activity: A1360 Unit Overview Graphics (With
100% Accuracy )
Project: BUIFDP-7 Activity: A1370 TTPS GRAPHICS (With 100%
Accuracy )
Project: BUIFDP-7 Activity: A1380 Alarm Philosophy
specification (With 100% Accuracy )
Project: BUIFDP-7 Activity: A1390 TTPS MAPPING LIST
Project: BUIFDP-7 Activity: A1400 Alarm Report

Errors:
-------
Warnings:
---------
Activities without predecessors..................................1
Project: BUIFDP-7 Activity: A1000 RECEIPT OF PURCHASE ORDER
FROM TR

Activities without successors....................................3


Project: BUIFDP-7 Activity: A3876 Delivery Milestone :- ICSS
Cabinets DCS/ESD & FGS after Hardware Punch List Clearance
Project: BUIFDP-7 Activity: A3896 Delivery Milestone : Delivery
of Brownfield Raw Material
Project: BUIFDP-7 Activity: A3980 Take Over Certificate By EPC
Contractor to SE
Out-of-sequence activities.......................................0

Activities with Actual Dates > Data Date.........................0

Milestone Activities with invalid relationships..................1


Project: BUIFDP-7 Activity: A3876 Delivery Milestone :- ICSS
Cabinets DCS/ESD & FGS after Hardware Punch List Clearance

Finish milestone and predecessors have different calendars.......0

Scheduling/Leveling Results:
----------------------------
# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................154
# Relationships with other projects..............................0
Data Date........................................................27-Mar-19
Earliest Early Start Date........................................27-Mar-19
Latest Early Finish Date.........................................18-Jun-20
Exceptions:
-----------
Critical Activities..............................................66
Project: BUIFDP-7 Activity: A1030 Issuing PO for TRICONEX /
TRIDENT HARDWARE
Project: BUIFDP-7 Activity: A1040 Issuing PO for DCS Items
(FOXBORO Hardware)
Project: BUIFDP-7 Activity: A1050 Issuing PO for CABINETS
Project: BUIFDP-7 Activity: A1060 Issuing PO for Third Party
Items
Project: BUIFDP-7 Activity: A1070 Delivery of TRICONEX /
TRIDENT HARDWARE
Project: BUIFDP-7 Activity: A1080 Delivery of DCS Items
(FOXBORO Hardware)
Project: BUIFDP-7 Activity: A1090 Delivery of CABINETS
Project: BUIFDP-7 Activity: A1100 Delivery of Third Party Items
Project: BUIFDP-7 Activity: A1110 SmartPlant Instrumentation
(SPI) Data Base level 1 ( I/O Database in Excel with 80% accuracy)
Project: BUIFDP-7 Activity: A1120 TPPS Interface List (With 80%
accuracy)
Project: BUIFDP-7 Activity: A1130 SmartPlant Instrumentation
(SPI) Data Base level 2 ( I/O Database in Excel with 100% accuracy)
Project: BUIFDP-7 Activity: A1140 TPPS Interface List (With
100% accuracy)
Project: BUIFDP-7 Activity: A1150 SmartPlant Instrumentation
(SPI) Data Base level 3 (I/O LIST & MULTICABLE number type(numebr pairs)& ALARMS)
Project: BUIFDP-7 Activity: A1160 Cause and Effects Matrix
(With 60% Accuracy )
Project: BUIFDP-7 Activity: A1170 Control Narratives (With 60%
Accuracy )
Project: BUIFDP-7 Activity: A1180 Safe Guarding Narratives
(With 60% Accuracy )
Project: BUIFDP-7 Activity: A1190 Process & Instrumentation
Diagram (P&IDs) (With 60% Accuracy )
Project: BUIFDP-7 Activity: A1200 Alarm Philosophy
specification (With 60% Accuracy )
Project: BUIFDP-7 Activity: A1210 Cause and Effects Matrix
(With 80% Accuracy )
Project: BUIFDP-7 Activity: A1220 Control Narratives (With 80%
Accuracy )
Project: BUIFDP-7 Activity: A1230 Safe Guarding Narratives
(With 80% Accuracy )
Project: BUIFDP-7 Activity: A1240 Process & Instrumentation
Diagram (P&IDs) (With 80% Accuracy )
Project: BUIFDP-7 Activity: A1250 Plant and Section Level
Graphics (With 80% Accuracy)
Project: BUIFDP-7 Activity: A1260 Marked up P&ID (for Process
Graphic) (With 80% Accuracy )
Project: BUIFDP-7 Activity: A1270 Unit Overview Graphics (With
80% Accuracy )
Project: BUIFDP-7 Activity: A1280 TTPS GRAPHICS (With 80%
Accuracy )
Project: BUIFDP-7 Activity: A1290 Cause and Effects Matrix
(With 100% Accuracy )
Project: BUIFDP-7 Activity: A1300 Control Narratives (With 100%
Accuracy )
Project: BUIFDP-7 Activity: A1310 Safe Guarding Narratives
(With 100% Accuracy )
Project: BUIFDP-7 Activity: A1320 Process & Instrumentation
Diagram (P&IDs) (With 100% Accuracy )
Project: BUIFDP-7 Activity: A1330 SmartPlant Instrumentation
(SPI) Data Base level 4 (I/O LIST&MULTICABLE(termination details)& ALARMS)
Project: BUIFDP-7 Activity: A1340 Plant and Section Level
Graphics (With 100% Accuracy)
Project: BUIFDP-7 Activity: A1350 Marked up P&ID (for Process
Graphic) (With 100% Accuracy )
Project: BUIFDP-7 Activity: A1360 Unit Overview Graphics (With
100% Accuracy )
Project: BUIFDP-7 Activity: A1370 TTPS GRAPHICS (With 100%
Accuracy )
Project: BUIFDP-7 Activity: A1380 Alarm Philosophy
specification (With 100% Accuracy )
Project: BUIFDP-7 Activity: A1390 TTPS MAPPING LIST
Project: BUIFDP-7 Activity: A1400 Alarm Report
Project: BUIFDP-7 Activity: A1450 BILL OF MATERIALS FOR ICSS
Project: BUIFDP-7 Activity: A1710 FAT REPORT FOR CYBER SECURITY
-ICSS
Project: BUIFDP-7 Activity: A1750 FINAL QUALITY DOSSIER
Project: BUIFDP-7 Activity: A1870 INSTALLATION, OPERATION AND
MAINTENANCE MANUAL FOR ICSS
Project: BUIFDP-7 Activity: A1900 LOGIC DIAGRAMS FOR SAFETY
SYSTEMS FOR ICSS
Project: BUIFDP-7 Activity: A2110 SOFTWARE PACKAGE FOR ICSS
Project: BUIFDP-7 Activity: A2520 APPROVAL OF FAT REPORT (CYBER
SECURITY -ICSS)
Project: BUIFDP-7 Activity: A2680 APPROVAL OF INSTALLATION,
OPERATION AND MAINTENANCE MANUAL (ICSS)
Project: BUIFDP-7 Activity: A2710 APPROVAL OF LOGIC DIAGRAMS
FOR SAFETY SYSTEMS (ICSS)
Project: BUIFDP-7 Activity: A2920 APPROVAL OF SOFTWARE PACKAGE
(ICSS)
Project: BUIFDP-7 Activity: A3030 Inspection of TRICONEX /
TRIDENT HARDWARE
Project: BUIFDP-7 Activity: A3040 Inspection of DCS Items
(FOXBORO Hardware)
Project: BUIFDP-7 Activity: A3050 Inspection of CABINETS
Project: BUIFDP-7 Activity: A3060 Inspection of Third Party
Items
Project: BUIFDP-7 Activity: A3070 MANUFACTURING OF TRICONEX /
TRIDENT HARDWARE
Project: BUIFDP-7 Activity: A3080 MANUFACTURING OF DCS Items
(FOXBORO Hardware)
Project: BUIFDP-7 Activity: A3090 MANUFACTURING OF CABINETS
Project: BUIFDP-7 Activity: A3100 MANUFACTURING OF Third Party
Items
Project: BUIFDP-7 Activity: A3110 Assembling of ICSS Cabinets
(DCS/ESD & FGS)
Project: BUIFDP-7 Activity: A3140 Stagging Of ICSS Cabinets
(DCS/ESD & FGS)
Project: BUIFDP-7 Activity: A3170 Hardware Punch Point
Clearance of ICSS Cabinets (DCS/ESD & FGS)
Project: BUIFDP-7 Activity: A3230 Hardware Acceptance Test for
ICSS Cabinets (DCS/ESD & FGS)
Project: BUIFDP-7 Activity: A3260 Integrated Acceptance Test
for ICSS Cabinets (DCS/ESD & FGS)
Project: BUIFDP-7 Activity: A3290 Delivery of ICSS Cabinets
(DCS/ESD & FGS)
Project: BUIFDP-7 Activity: A3876 Delivery Milestone :- ICSS
Cabinets DCS/ESD & FGS after Hardware Punch List Clearance
Project: BUIFDP-7 Activity: A3886 Delivery of BrownField Raw
Material to TR
Project: BUIFDP-7 Activity: A3896 Delivery Milestone : Delivery
of Brownfield Raw Material
Project: BUIFDP-7 Activity: A3980 Take Over Certificate By EPC
Contractor to SE

Activities with unsatisfied constraints..........................30


Project: BUIFDP-7 Activity: A1110 SmartPlant Instrumentation
(SPI) Data Base level 1 ( I/O Database in Excel with 80% accuracy)
Project: BUIFDP-7 Activity: A1120 TPPS Interface List (With 80%
accuracy)
Project: BUIFDP-7 Activity: A1130 SmartPlant Instrumentation
(SPI) Data Base level 2 ( I/O Database in Excel with 100% accuracy)
Project: BUIFDP-7 Activity: A1140 TPPS Interface List (With
100% accuracy)
Project: BUIFDP-7 Activity: A1150 SmartPlant Instrumentation
(SPI) Data Base level 3 (I/O LIST & MULTICABLE number type(numebr pairs)& ALARMS)
Project: BUIFDP-7 Activity: A1160 Cause and Effects Matrix
(With 60% Accuracy )
Project: BUIFDP-7 Activity: A1170 Control Narratives (With 60%
Accuracy )
Project: BUIFDP-7 Activity: A1180 Safe Guarding Narratives
(With 60% Accuracy )
Project: BUIFDP-7 Activity: A1190 Process & Instrumentation
Diagram (P&IDs) (With 60% Accuracy )
Project: BUIFDP-7 Activity: A1200 Alarm Philosophy
specification (With 60% Accuracy )
Project: BUIFDP-7 Activity: A1210 Cause and Effects Matrix
(With 80% Accuracy )
Project: BUIFDP-7 Activity: A1220 Control Narratives (With 80%
Accuracy )
Project: BUIFDP-7 Activity: A1230 Safe Guarding Narratives
(With 80% Accuracy )
Project: BUIFDP-7 Activity: A1240 Process & Instrumentation
Diagram (P&IDs) (With 80% Accuracy )
Project: BUIFDP-7 Activity: A1250 Plant and Section Level
Graphics (With 80% Accuracy)
Project: BUIFDP-7 Activity: A1260 Marked up P&ID (for Process
Graphic) (With 80% Accuracy )
Project: BUIFDP-7 Activity: A1270 Unit Overview Graphics (With
80% Accuracy )
Project: BUIFDP-7 Activity: A1280 TTPS GRAPHICS (With 80%
Accuracy )
Project: BUIFDP-7 Activity: A1290 Cause and Effects Matrix
(With 100% Accuracy )
Project: BUIFDP-7 Activity: A1300 Control Narratives (With 100%
Accuracy )
Project: BUIFDP-7 Activity: A1310 Safe Guarding Narratives
(With 100% Accuracy )
Project: BUIFDP-7 Activity: A1320 Process & Instrumentation
Diagram (P&IDs) (With 100% Accuracy )
Project: BUIFDP-7 Activity: A1330 SmartPlant Instrumentation
(SPI) Data Base level 4 (I/O LIST&MULTICABLE(termination details)& ALARMS)
Project: BUIFDP-7 Activity: A1340 Plant and Section Level
Graphics (With 100% Accuracy)
Project: BUIFDP-7 Activity: A1350 Marked up P&ID (for Process
Graphic) (With 100% Accuracy )
Project: BUIFDP-7 Activity: A1360 Unit Overview Graphics (With
100% Accuracy )
Project: BUIFDP-7 Activity: A1370 TTPS GRAPHICS (With 100%
Accuracy )
Project: BUIFDP-7 Activity: A1380 Alarm Philosophy
specification (With 100% Accuracy )
Project: BUIFDP-7 Activity: A1390 TTPS MAPPING LIST
Project: BUIFDP-7 Activity: A1400 Alarm Report

Activities with unsatisfied relationships........................0

Activities with external dates...................................0