You are on page 1of 343

Dalam bahasa Indonesia

Masukan Angka di sini Ü 85,820,000.00


0 0
1 Satu 0 0
2 Dua 85 85
3 Tiga 85,820 820
4 Empat 85,820,000 0
5 Lima 0
6 Enam 0
7 Tujuh 0
8 Delapan 8 Delapan Ratus
9 Sembilan 0
10 Sepuluh 0
11 Sebelas 0
12 Dua belas 8 Delapan Puluh
13 Tiga Belas 2 Dua Puluh
14 Empat Bel 0
15 Lima Bela 0
16 Enam Bel 0
17 Tujuh Bel 5 Lima
18 Delapan b 0
19 Sembilan 0
Puluh 0
Ratus

Delapan Puluh Lima Juta


Juta Delapan Ratus Dua Puluh Ribu
Ribu
Rupiah
Terbilang :
Delapan Puluh Lima Juta Delapan Ratus Dua Puluh Ribu Rupiah

In English

Enter number here Ü 85,820,000.00


0 0
1 One 0 0
2 Two 85 85
3 Three 85,820 820
4 Four 85,820,000 0
5 Five 0
6 Six 0
7 Seven 0
8 Eight 8 Eight Hundred
9 Nine 0
10 Ten 0
11 Eleven 0
12 Twelve 85 Eighty Five
13 Thirteen 20 Twenty
14 Forteen 0
15 Fifteen 0
16 Sixteen
17 Seventeen
18 Eighteen
19 Nineteen
20 Twenty
21 Twenty One
22 Twenty Two
23 Twenty Three
24 Twenty Four
25 Twenty Five
26 Twenty Six
27 Twenty Seven
28 Twenty Eight
29 Twenty Nine
30 Thirty
31 Thirty One
32 Thirty Two
33 Thirty Three
34 Thirty Four
35 Thirty Five
36 Thirty Six
37 Thirty Seven
38 Thirty Eight
39 Thirty Nine
40 Forty
41 Forty One
42 Forty Two
43 Forty Three
44 Forty Four
45 Forty Five
46 Forty Six
47 Forty Seven
48 Forty Eight
49 Forty Nine
50 Fifty
51 Fifty One
52 Fifty Two
53 Fifty Three
54 Fifty Four
55 Fifty Five
56 Fifty Six
57 Fifty Seven
58 Fifty Eight
59 Fifty Nine
60 Sixty
61 Sixty One
62 Sixty Two
63 Sixty Three
64 Sixty Four
65 Sixty Five
66 Sixty Six
67 Sixty Seven
68 Sixty Eight
69 Sixty Nine
70 Seventy
71 Seventy One
72 Seventy Two
73 Seventy Three
74 Seventy Four
75 Seventy Five
76 Seventy Six
77 Seventy Seven
78 Seventy Eight
79 Seventy Nine
80 Eighty
81 Eighty One
82 Eighty Two
83 Eighty Three
84 Eighty Four
85 Eighty Five
86 Eighty Six
87 Eighty Seven
88 Eighty Eight
89 Eighty Nine
90 Ninety
91 Ninety One
92 Ninety Two
93 Ninety Three
94 Ninety Four
95 Ninety Five
96 Ninety Six
97 Ninety Seven
98 Ninety Eight
99 Ninety Nine
Hundred

Eighty Five Million


Million Eight Hundred Twenty Thousand
Thousand
Rupiah
in Words :
Eighty Five Million Eight Hundred Twenty Thousand Rupiah
REKAPITULASI BIAYA
PEKERJAAN
LOKASI
TAHUN

NO URAIAN

I PEKERJAAN PERSIAPAN

II PEKERJAAN PERBAIKAN DRAENASE DAERAH I

III PEKERJAAN LAIN-LAIN

Sub Total Rp.


PPn (10%) Rp.
Total Rp.

Pembulatan

Terbilang : Delapan Puluh Lima Juta Delapan Ratus Dua Puluh Ribu Rupiah

Belawan,

Dibuat Ole
STAF FASILI

RIZALDY HASIAN H
EKAPITULASI BIAYA

JUMLAH HARGA (Rp)

2,200,000.00

73,821,376.27

2,000,000.00

78,021,376.27
7,802,137.63
85,823,513.90

85,820,000.00

pan Ratus Dua Puluh Ribu Rupiah

Belawan, 2012

Dibuat Oleh :
STAF FASILITAS

RIZALDY HASIAN HARAHAP


OWNERS ESTIMATE (OE)
PEKERJAAN
LOKASI
TAHUN

Harga satuan (Rp) Jumlah ha


No. Uraian Satuan Volume
Upah Bahan Upah + Bahan Upah
2 3 4 5 6 7 8

I PEKERJAAN PERSIAPAN
1 Survey lokasi 1.00 ls 200,000.00 0.00 200,000.00 200,000.00
2 Mobilisasi dan Demobilisasi Alat 1.00 ls 2,000,000.00 0.00 2,000,000.00 2,000,000.00

JUM
II PEKERJAAN PERBAIKAN DRAENASE DAERAH I
1 Pekerjaan perbaikan beton dudukan grill 1.00 ls 200,000.00 300,000.00 500,000.00 200,000.00
2 Pekerjaan bongkar beton 3.13 m³ 464,000.00 0.00 464,000.00 1,453,248.00
3 Pekerjaan bongkar pasangan bata 6.28 m² 165,500.00 0.00 165,500.00 1,039,298.63
4 Pekerjaan beton bertulang dinding drainase 13.46 m³ 508,679.60 2,866,161.24 3,374,840.84 6,849,040.17
5 Pekerjaan besi siku pinggir 40.40.4 309.33 kg 8,880.00 13,915.00 22,795.00 2,746,880.00
6 Pekerjaan besi pelat strip 5.30 128.00 kg 8,880.00 13,915.00 22,795.00 1,136,640.00
7 Pekerjaan besi kotak 40x40 t 1,2 676.45 kg 8,880.00 13,915.00 22,795.00 6,006,915.07

JUM
III PEKERJAAN LAIN-LAIN
1 Pembersihan akhir 1.00 ls 1,000,000.00 0.00 1,000,000.00 1,000,000.00
2 Dokumentasi dan laporan 1.00 ls 1,000,000.00 0.00 1,000,000.00 1,000,000.00

JUM

Belawan,

Dibua
STAF FA
Harga satuan (Rp) Jumlah ha
No. Uraian Satuan Volume Belawan,
Upah Bahan Upah + Bahan Upah
2 3 4 5 6 7 8 Dibua
STAF FA

RIZALDY HAS
OWNERS ESTIMATE (OE)

Jumlah harga (Rp)


Bahan Upah + Bahan
9 10

0.00 200,000.00
0.00 2,000,000.00

JUMLAH 2,200,000.00

300,000.00 500,000.00
0.00 1,453,248.00
0.00 1,039,298.63
38,590,998.09 45,440,038.26
4,304,373.33 7,051,253.33
1,781,120.00 2,917,760.00
9,412,862.98 15,419,778.05

JUMLAH 73,821,376.27

0.00 1,000,000.00
0.00 1,000,000.00

JUMLAH 2,000,000.00

Belawan, 2012

Dibuat Oleh :
STAF FASILITAS
Jumlah harga (Rp)
Belawan, 2012
Bahan Upah + Bahan
Dibuat
9 Oleh : 10
STAF FASILITAS

RIZALDY HASIAN HARAHAP


DAFTAR UPAH DAN BAHAN

PEKERJAAN
LOKASI
TAHUN

KODE NO. NAMA BARANG / BAHAN / TENAGA

UPH UPAH
UPH UPH1 Tukang kayu
UPH UPH2 Tukang batu
UPH UPH3 Tukang alumunium
UPH UPH4 Tukang besi
UPH UPH5 Tukang las
UPH UPH6 Tukang cat
UPH UPH7 Tukang plitur
UPH UPH8 Tukang bor
UPH UPH9 Tukang listrik
UPH UPH10 Tukang pipa ledeng
UPH UPH11 Tukang Pancang
UPH UPH12 Kepala tukang
UPH UPH13 Tukan gali/timbun
UPH UPH14 Pekerja
UPH UPH15 Mandor
UPH UPH16 Pengawas
UPH UPH17 Ahli ukur
UPH UPH18 Asisten ahli ukur
UPH UPH19 Sopir
UPH UPH20 Masinis
UPH UPH21 Kernet / pembantu sopir
UPH UPH22 Mekanik terlatih
UPH UPH23 Operator tak terlatih
UPH UPH24 Operator terlatih
UPH UPH25 Pembantu Operator
UPH UPH26 Operator semi terlatih
UPH UPH27 Penjaga
UPH UPH28 Penyelam
UPH UPH29 Tukang Grouting
UPH UPH30 Operator mesin sondir
UPH UPH31 Analis test sondir

ASB ASBES
ASB ASB1 Asbes plat ( 100 x 100 x 0,3 )
ASB ASB2 Asbes gelombang besar ( 225 x 92 x 0,5 )
KODE NO. NAMA BARANG / BAHAN / TENAGA
ASB ASB3 Asbes gelombang besar ( 200 x 92 x 0,5 )
ASB ASB4 Asbes gelombang besar ( 180 x 92 x 0,5 )
ASB ASB5 Asbes gelombang besar ( 240 x 108 x 0,6 )
ASB ASB6 Asbes gelombang besar ( 210 x 108 x 0,6 )
ASB ASB7 Asbes gelombang besar ( 180 x 108 x 0,6 )
ASB ASB8 Asbes gelombang kecil ( 210 x 105 x 0,4 )
ASB ASB9 Asbes gelombang kecil ( 180 x 105 x 0,4 )
ASB ASB10 Asbes gelombang kecil ( 150 x 105 x 0,4 )
ASB ASB11 Asbes gelombang kecil ( 240 x 105 x 0,4 )
ASB ASB12 Asbes nok gelombang besar
ASB ASB13 Asbes nok gelombang kecil
ASB ASB14 Nok paten (Rabung)
ASB ASB15 Nok stel rata

ASP ASPAL
ASP ASP1 Aspal cair
ASP ASP2 Aspal curah
ASP ASP3 Aspal drum
ASP ASP4 Aspal modifer / asphalt joint
ASP ASP5 Drum aspal bekas
ASP ASP6 Rubber Filler
ASP ASP7 Filler
ASP ASP8 Karosene

ATP GENTENG
ATP ATP1 Genteng beton besar natural 1m 9 biji
ATP ATP2 Genteng beton besar warna 1m 9 biji
ATP ATP3 Genteng beton kecil natural 1m 11 biji
ATP ATP4 Genteng beton kecil warna 1m 11 biji
ATP ATP5 Genteng beton kecil natural 1m 20 biji
ATP ATP6 Genteng beton kecil warna 1m 20 biji
ATP ATP7 Genteng metal
ATP ATP8 Genteng bubungan beton
ATP ATP9 Bubung stel gelombang
ATP ATP10 Genteng bubungan warna
ATP ATP11 GENTENG & RABUNG
ATP ATP12 Genteng keramik lengkung cekung / vlaams
ATP ATP13 Genteng keramik lengkung rata
ATP ATP14 Genteng keramik rata / kodok
ATP ATP15 Genteng keramik berglasir KIA, Kanmuri Natural
ATP ATP16 Nok metal
ATP ATP17 ATAP GENTENG METAL
ATP ATP18 Atap metal gelombang t 0,35 mm
KODE NO. NAMA BARANG / BAHAN / TENAGA
ATP ATP19 Nok standar 40 cm 18 SWG 22
ATP ATP20 Paku anti karat
ATP ATP21 Atap alumunium gelombang tebal 0,55
ATP ATP22 Atap polykarbonat
ATP ATP23 Paku skrup anti karat atap metal/polykarbonat
ATP ATP24 Rabung Atap spandek
ATP ATP25 Atap spandek
ATP ATP26 Baut + Hak Spandek
ATP ATP27 SENG BJLS
ATP ATP28 Seng BJLS 0,20 gelombang P = 180 cm
ATP ATP29 Seng BJLS 0,20 gelombang P = 240 cm
ATP ATP30 Seng plat 3" x 6" BJLS 28
ATP ATP31 Seng gelombang 2" - 5" BJLS 24
ATP ATP32 Alumunium gelombang tebal 0,55
ATP ATP33 Alumunium foil
ATP ATP34 Rabung alumunium standar 40 cm 18 SWG 22

BBM BAHAN PELARUT, PELUMAS


BBM BBM1 Oli SAE 30
BBM BBM2 Minyak bakar / kerosene
BBM BBM3 Minyak bekisting
BBM BBM4 Bensin premium
BBM BBM5 Solar
BBM BBM6 Minyak pelumas
BBM BBM7 Vet
BBM BBM8 Gas Elpiji
BBM BBM9 Minyak bekisting

BKM BAHAN KIMIA PEMBANTU UNTUK BETON


BKM BKM1 Bahan kimia B (kuat ikat cepat )
BKM BKM2 Bahan kimia E (kuat ikat cepat )
BKM BKM3
BKM BKM4 BAHAN PENGAWET DAN BITUMEN
BKM BKM5 Teer kayu
BKM BKM6 Residu
BKM BKM7 Flincoat

BSI BESI BETON


BSI BSI1 Besi beton polos
BSI BSI2 Besi beton ulir
BSI BSI3 Besi baja profil
BSI BSI4 Besi tuang / cor
KODE NO. NAMA BARANG / BAHAN / TENAGA
BSI BSI5 Besi plat lembaran
BSI BSI6 Besi scuare tube
BSI BSI7 Besi lis kaca (1 x 1) cm
BSI BSI8 Besi gording canal
BSI BSI9 Baja profil IWF
BSI BSI10 Besi strip
BSI BSI11 Besi profil
BSI BSI12 Besi siku rata-rata
BSI BSI13 Besi angkur dia. 8mm
BSI BSI14 Plat baja t = 3 mm
BSI BSI15 Formite/penjaga jarak bekisting/spacer
BSI BSI16 Scafolding
BSI BSI17 Profil alumunium
BSI BSI18 Skrup fixer
BSI BSI19 Sealent
BSI BSI20 Alumunium strip
BSI BSI21 Besi pelat/baja tulangan dia 19 mm
BSI BSI22 Al. Composite Panel (Alucopan)
BSI23
BSI BSI24 KAWAT
BSI BSI25 Kawat beton / bindrat
BSI BSI26 Kawat bronjong
BSI BSI27 Kawat nyamuk
BSI BSI28 Kawat jaring
BSI BSI29 Kawat las
BSI BSI30 Kawat galvanis
BSI BSI31 Kawat duri
BSI BSI32 Besi jaring kawat baja
BSI BSI33 Kawat harmonika
BSI BSI34 Kawat penggantung rangka hollow
BSI BSI35 Profil Alumunium "T"
BSI BSI36 Baja ringan
BSI BSI37 Pipa hollow
BSI BSI38 Kusen alumunium uk 2"x4" tebal 1.2 mm sekualitas YKK putih
BSI BSI39 Jendela nako
BSI BSI40 Pintu besi baja
BSI BSI41 Jendela besi baja
BSI BSI42 Jendela besi tahan api
BSI BSI43 Pintu gulung besi
BSI BSI44 Pintu lipat besi
BSI BSI45 Sunscreen alumunium
KODE NO. NAMA BARANG / BAHAN / TENAGA

BSI BSI46 Roll door


BSI BSI47 Pintu alumunium
BSI BSI48 Vertikal blind
BSI BSI49 Wall paper
BSI50
BSI BSI51 Scafolding
BSI BSI52 Main Frame (MF-1219/h = 190 cm)
BSI BSI53 Ladder Frame (LF-1209/h =90)
BSI BSI54 Join Pin (JP-42)
BSI BSI55 Cross Brase (CB-1218/I = 220 cm)-MF
BSI BSI56 Cross Brase (CB-0618/I = 193)-LF
BSI BSI57 Head Jack (HJ-60)
BSI BSI58 Base Jack (BJ-60)
BSI BSI59 Balok 8/12 (10x pakai)
BSI BSI60 Papan Alas 3/20 (3x pakai)
BSI BSI61 Kawat Pengikat

BTN BUIS BETON / KERB


BTN BTN1 Buis beton bulat dia. 80 cm P=0,5 m
BTN BTN2 BETON DAN BARANG DARI BETON (BATAKO)
BTN BTN3 Panel beton pracetak
BTN BTN4 Kolom beton pracetak
BTN BTN5 Tiang Pancang Beton dia … cm (bottom)
BTN BTN6 Tiang Pancang Beton dia … cm (upper)

BTU BATU ALAM / AGREGAT / BAHAN TUMBUHAN


BTU BATU ALAM
BTU BTU1 Batu kali
BTU BTU2 Batu apung
BTU BTU3 Batu Granit
BTU BTU4 Batu hias tempel
BTU BTU5 Batu hias bulat putih
BTU BTU6 Ubin granit uk. 40/40
BTU BTU7 Ubin granit uk. 30/30
BTU BTU8 Ubin keramik artistik
BTU BTU9 Ubin marmer ( 40 x 40 x 2 ) Baitik/Citatah
BTU BTU10 Ubin marmer ( 40 x 60 x 2 ) Baitik
BTU BTU11 Ubin marmer ( 15 x 30 x 2 ) Baitik
BTU BTU12 Vinyl
BTU BTU13 Riol 20 cm
BTU BTU14 Floor hardener
KODE NO. NAMA BARANG / BAHAN / TENAGA

BTU BTU15 Agregat hakus/pasir klas A ( Uk. butir 5 mm )


BTU BTU16 Agregat kasar/krikil/pasir klas B ( Uk. 20 - 40 )
BTU BTU17 Agregat kasar/krikil/pasir klas C ( Uk. 4½ - 19 )
BTU BTU18 Batu tempel
BTU BTU19 Bata pelapis dinding
BTU BTU20 Batu Bata 5 x 11 x 22
BTU BTU21 Batu pecah 2/3 ( split )
BTU BTU22 Batu pecah 3/4
BTU BTU23 Batu pecah 4/6
BTU BTU24 Batu pecah 5/7
BTU BTU25 Batu pecah 1/2
BTU BTU26 Batu belah hitam
BTU BTU27 Batu belah putih
BTU BTU28 Sirtu Klas A lewat ayakan 1"
BTU BTU29 Sirtu klas B lewat ayakan 2½"
BTU BTU30 Pasir urug darat
BTU BTU31 Pasir beton
BTU BTU32 Pasir pasang ( progo )
BTU BTU33 Pasir pasang ( krasak )
BTU BTU34 Krikil beton
BTU BTU35 Kerikil tidak tersaring
BTU BTU36 Split D 30 - 40 mm
BTU BTU37 Split D 10 - 20 mm
BTU BTU38 Split D 1 - 2 cm
BTU BTU39 Batu merah ( 5x11x23 )
BTU BTU40 Batu merah ( 4x9x19 )
BTU BTU41 Tanah liat
BTU BTU42 Tanah urug
BTU BTU43 Tanah timbun
BTU BTU44 Sirtu
BTU BTU45 Batako
BTU BTU46 Bata expose 5 x 11 x 24 cm
BTU BTU47 Terawang / roster 12x11x24 cm
BTU BTU48 Roster 25/25

CAT CAT
CAT CAT1 Cat dasar meni
CAT CAT2 Cat tembok melamin
KODE NO. NAMA BARANG / BAHAN / TENAGA
CAT CAT3 Cat dasar meni kayu
CAT CAT4 Cat alkali resisting primer
CAT CAT5 Cat ICI Weathershield
CAT CAT6 Cat penutup
CAT CAT7 Cat kayu
CAT CAT8 Cat Epoxy/Tar
CAT CAT9 Dempul kayu typa A (putih) Jago
CAT CAT10 Plamur Fuji
CAT CAT11 Kalkarium
CAT CAT12 Politur jadi
CAT CAT13 Teak oil Fuji
CAT CAT14 Pernis
CAT CAT15 Minyak cat
CAT CAT16 Thinner
CAT CAT17 Kuas roll
CAT CAT18 Kuas ukuran 3,5"
CAT CAT19 Kuas ukuran 2,5"
CAT CAT20 Kuas ukuran kecil 1"
CAT CAT21 Soda api
CAT CAT22 Sabun deterjen
CAT CAT23 Amplas
CAT CAT24 Perekat

CBK BATA HALAMAN / PAVING BLOCK


CBK WARNA NATURAL / ABU-ABU
CBK CBK1 Tipe segi empat, uni, segi 6 tebal = 8 cm K 400
CBK CBK2 Tipe uni dan segi empat tebal = 8 cm K 300
CBK CBK3 Tipe segi empat tebal = 6 cm K 200
CBK CBK4 Tipe segi empat tebal = 8 cm K 200
CBK CBK5 Tipe segi enam tebal = 6 cm K 200
CBK CBK6 Tipe segi enam tebal = 8 cm K 200
CBK CBK7 Conblock t=10 cm
CBK CBK8 HB 10
CBK CBK9 HB 15
CBK CBK10 HB 20
CBK CBK11 Conblock tipe segi-empat, abu-abu 10 cm, K-450
CBK CBK12
CBK CBK13 WARNA MERAH / HITAM
CBK CBK14 Tipe grass blok bulat tebal = 10 cm
CBK CBK15 Tipe grass blok tebal = 10 cm

LAIN-LAIN
KODE NO. NAMA BARANG / BAHAN / TENAGA
DLL DLL1 Tiang bendera
DLL DLL2 -Pondasi umpak
DLL DLL3 -Ompak ornamen
DLL DLL4 -Tiang galvanis 3"
DLL DLL5 -Bendera 120 x 180
DLL DLL6 Rambu lalu lintas (terpasang)
DLL DLL7 Papan nama jalan (terpasang)
DLL DLL8 Sumur peresapan 5 m
DLL DLL9 Air minum, instalasi dalam dengan pipa pralon 1" medium, acesories dihitung sendir
DLL DLL10 Air minum, instalasi luar dengan pipa pralon 1" medium, acesoris dihitung sendiri
DLL DLL11 Asbuton
DLL DLL12 Tumpuan konstruksi
DLL DLL13 Geotextile Polyfelt. TS 70
DLL DLL14 Pelapisan kedap air lantai dengan coating ( terpasang )
DLL DLL15 Pelapisan kedap air lantai dengan membran ( terpasang )

KCA BAHAN KACA


KCA KCA1 Kaca polos
KCA KCA2 Kaca patri
KCA KCA3 Fiber glass
KCA KCA4 Profil kaca

KCI PENGGANTUNG / PENGUNCI


KCI KCI1 Engsel pintu
KCI KCI2 Engsel jendela
KCI KCI3 Grendel
KCI KCI4 Hak angin
KCI KCI5 Engsel angin
KCI KCI6 Kait angin
KCI KCI7 Door holder
KCI KCI8 Door stop
KCI KCI9 Penggantung + rel pintu dorong
KCI KCI10 Kunci tanam
KCI KCI11 Kunci tanam antik
KCI KCI12 Kunci tanam biasa
KCI KCI13 Kunci kamar mandi
KCI KCI14 Kunci gembok
KCI KCI15 Kunci selot
KCI KCI16 Kunci silinder
KCI KCI17 Kunci lemari
KCI KCI18 Spring knip
KCI KCI19 Door closer
KODE NO. NAMA BARANG / BAHAN / TENAGA
KCI KCI20 Ramset / dina bolt

KPG KAPUR & GIPS


KPG KPG1 Kapur pasang
KPG KPG2 Kapur sirih
KPG KPG3 Tepung Gypsum
KPG KPG4 Gypsum board
KPG KPG5 Kasa gypsum
KPG KPG6 List profil gypsum lebar sampai 5 cm
KPG KPG7 List profil gypsum lebar sampai 6 - 10 cm
KPG KPG8 List profil gypsum lebar lebih 10 cm
KPG KPG9 Kalsiboard ( 122 x 244 x 0,35 ) cm
KPG KPG10 Kalsiboard ( 122 x 244 x 0,60 ) cm

KYU KAYU
KYU KYU1 Kayu Kelas III
KYU KYU2 Damar Laut (Kelas I)
KYU KYU3 Kayu meranti balok
KYU KYU4 Kayu meranti papan
KYU KYU5 Papan kayu damar laut
KYU KYU6 Papan cetakan / bekesting
KYU KYU7 Kayu dolken
KYU KYU8 Kayu dolken Ø 8 - 10/400 cm
KYU KYU9 Perancah kayu
KYU KYU10
KYU KYU11 LIST KAYU PROFIL
KYU KYU12 List kayu profil
KYU KYU13 Kayu plepet eternit 1/5 cm
KYU KYU14
KYU KYU15 KAYU LAPIS
KYU KYU16 Akustik soft board 60 x 120
KYU KYU17 Akustik soft board 40 x 60
KYU KYU18 Akustik soft board 30 x 60
KYU KYU19 Melamin wood 90 x 120 cm
KYU KYU20 Melamin wood 120 x 240 cm
KYU KYU21 Formika 4" x 8" x 0,3 cm
KYU KYU22 Triplek
KYU KYU23 Teak wood ( 90 x 240 )
KYU KYU24 Plywood 4 mm
KYU KYU25 Multiplek
KODE NO. NAMA BARANG / BAHAN / TENAGA
LNT TEGEL / KERAMIK
LNT LNT1 Plint tegel abu-abu 15/20
LNT LNT2 Plint tegel abu-abu 10/20
LNT LNT3 Plint tegel abu-abu 10/30
LNT LNT4 Plint tegel abu-abu 10/40
LNT LNT5 Plint tegel warna 10/20
LNT LNT6 Plint tegel warna 10/30
LNT LNT7 Plint tegel warna 10/40
LNT LNT8 Plint ubin teraso 10/30
LNT LNT9 Plint ubin teraso 10/40
LNT LNT10 Plint ubin granit 10/30
LNT LNT11 Plint ubin granit 10/40
LNT LNT12 Plint ubin teralux marmer 10/60
LNT LNT13 Plint ubin teralux marmer 10/40
LNT LNT14 Plint ubin teralux marmer 10/30
LNT LNT15 Tegel keramik 5/20 berglasir
LNT LNT16 Tegel keramik 10/20 berglasir
LNT LNT17 Tegel keramik 10/30 berglasir
LNT LNT18 Tegel keramik 20/20 berglasir
LNT LNT19 Tegel keramik 30/30 berglasir
LNT LNT20 Tegel keramik 40/40 berglasir
LNT LNT21 Tegel keramik mosaik
LNT LNT22 Marmer
LNT LNT23 Tegel porselin
LNT LNT24 Stepnosing granito
LNT LNT25 List keramik dinding motif 5/20
LNT LNT26 Plint keramik artistik
LNT LNT27 Keramik dinding 20/25
LNT LNT28 Internal cove
LNT LNT29 Bahan teraso cor

LST LISTRIK
LST LST1 Pasang instalasi / titik
LST LST2 Penyambungan beban
LST LST3 Kabel Snoor 2 x 0,23 "Supreme"
LST LST4 Kabel NYA 2,5 sqmm "Supreme"
LST LST5 Kabel NYA 1,5 sqmm "Supreme"
LST LST6 Kabel NYA 2,5 sqmm "Supreme"
LST LST7 Kabel NYA 1,5 sqmm "Supreme"
LST LST8 Kabel NYM 2 x 1,5 sqmm "Supreme"
LST LST9 Kabel NYM 2 x 2,5 sqmm "Supreme"
LST LST10 Kabel NYM 2 x 4 sqmm "Supreme"
KODE NO. NAMA BARANG / BAHAN / TENAGA

LST LST11 Kabel NYM 3 x 1,5 sqmm "Supreme"


LST LST12 Kabel NYM 3 x 2,5 sqmm "Supreme"
LST LST13 Kabel NYM 3 x 4 sqmm "Supreme"
LST LST14 Kabel NYY 3 x 6 sqmm "Supreme"
LST LST15 Kabel NYY 3 x 1,5 sqmm "Supreme"
LST LST16 Kabel NYY 3 x 2,5 sqmm "Supreme"
LST LST17 Kabel NYY 3 x 4 sqmm "Supreme"
LST LST18 Kabel NYY 3 x 6 sqmm "Supreme"
LST LST19 Kabel NYY 3 x 10 sqmm "Supreme"
LST LST20 Kabel NYY 4 x 10 sqmm "Supreme"
LST LST21 Kabel NYFGBY 3 x 10 sqmm "Supreme"
LST LST22 Kabel DX 2 x 10 sqmm "Supreme"
LST LST23 Kabel DX 2 x 16 sqmm "Supreme"
LST LST24 Kabel DX 2 x 25 sqmm "Supreme"
LST LST25 Kapasitor 12,5 uF
LST LST26 MCB 10 Ampere + box "MG"
LST LST27 MCB 6 Ampere "MG"
LST LST28 Tutup panel 30x30
LST LST29 Pipa pralon 3"
LST LST30 Pasang panel kontrol
LST LST31 Penyetelan dan penyalaan
LST LST32 Alat bantu
LST LST33 Retur material existing
LST LST34 Angkutan

PKB PERALATAN KEBERSIHAN


PKB PKB1 Sapu lidi
PKB PKB2 Tangkai Sapu
PKB PKB3 Seragam
PKB PKB4 Sarung tangan
PKB PKB5 Masker
PKB PKB6 Gerobak (alat baru)
PKB PKB7 Gerobak (sewa)
PKB PKB8 Serok
PKB PKB9 Gunting pangkas
PKB PKB10 Mesin potong rumput
PKB PKB11 Garpu tanah
PKB PKB12 Arit
PKB PKB13 Sepatu
PKB PKB14 Ember
PKB PKB15 Pacul
KODE NO. NAMA BARANG / BAHAN / TENAGA
PKB PKB16 Sewa kendaraan untuk membuang lumpur
PKB PKB17 Gas oksigen 5 kg
PKB PKB18 Pipa dia. 3/8" - 15 cm
PKB PKB19 Nitobond EC
PKB PKB20 Conbextra EP

PKU PAKU
PKU PKU1 Paku gording 125 x 5,1 mm
PKU PKU2 Paku usuk 80 x 3,8 mm
PKU PKU3 Paku reng 55 x 3,1 mm
PKU PKU4 Paku eternit 20 x 1,5 mm
PKU PKU5 Water mur
PKU PKU6 Angkur / baut
PKU PKU7 Paku biasa
PKU PKU8 Paku asbes
PKU PKU9 Paku sumbat
PKU PKU10 Paku sekrup 3.5"
PKU PKU11 Paku skrup
PKU PKU12 Paku triplek
PKU PKU13 Paku gypsum
PKU PKU14 Paku hak panjang 15 cm
PKU PKU15 Paku biasa 1/2" - 1"

PIPA
PPA PPA1 Pipa beton 20 x 30 Panjang 1 m
PPA PPA2 Pipa beton 15 x 30 Panjang 1 m
PPA PPA3 Pipa tanah dia. 15 cm
PPA PPA4 Pipa tanah dia. 20 cm
PPA PPA5 Pipa galvanis dia. 1/2"
PPA PPA6 Pipa galvanis dia. 3/4"
PPA PPA7 Pipa galvanis dia. 1"
PPA PPA8 Pipa galvanis dia. 1 1/2"
PPA PPA9 Pipa galvanis dia. 3"
PPA PPA10 Pipa galvanis dia. 4"
PPA PPA11 Riol 20 cm
PPA PPA12 Riol RCP Ø 60 t 10 cm
PPA PPA13 BAHAN PLASTIK
PPA PPA14 Pipa PVC abu-abu dia. 1/2" Wavin
PPA PPA15 Pipa PVC abu-abu dia. 3/4" Wavin
PPA PPA16 Pipa PVC abu-abu dia. 1" Wavin
PPA PPA17 Pipa PVC abu-abu dia. 1 1/2" Wavin
PPA PPA18 Pipa PVC abu-abu dia. 2" Wavin
KODE NO. NAMA BARANG / BAHAN / TENAGA
PPA PPA19 Pipa PVC abu-abu dia. 2 1/2" Wavin
PPA PPA20 Pipa PVC abu-abu dia. 3" Wavin
PPA PPA21 Pipa PVC abu-abu dia. 4" Wavin

PRK BAHAN PEREKAT HIDROLIS & ORGANIK


PRK PRK1 Portland Cement (PC)
PRK PRK2 Semen putih
PRK PRK3 Semen warna
PRK PRK4 Lem kayu (putih) Fox
PRK PRK5 Lem plastik Acrylic
PRK PRK6 Lem plastik Vinyl
PRK PRK7 Lem Aica Aibon
PRK PRK8 Semen batu bata

SNT BAK MANDI


SNT SNT1 Bak mandi fiber glass 1,00 m3
SNT SNT2 Bak mandi fiber glass 0,30 m3
SNT SNT3 KLOSET
SNT SNT4 Kloset jongkok porselin type CE8 standar
SNT SNT5 Kloset duduk standar / porselin ( dengan tangki KIA standart) "Toto"
SNT SNT6 Kloset duduk putih dengan tangki "Toto"
SNT SNT7 Kloset jongkok teraso
SNT SNT8 WASTAFEL
SNT SNT9 Wastafel putih (KIA)
SNT SNT10 Badkip
SNT SNT11 Bak cuci teraso
SNT SNT12 Bak cuci stainless steel
SNT SNT13 Water drain + asesories
SNT SNT14 Shower dinding
SNT SNT15 URINOIR
SNT SNT16 Urinoir putih
SNT SNT17 Kran air diameter 3/4" atau 1/2" exs. Toto
SNT SNT18 Seal tape
SNT SNT19 Floordrain
SNT SNT20 Kran air angsa
SNT SNT21 Perlengkapan
SNT SNT22 Tempat sabun

TNM BAHAN TUMBUHAN


TNM TNM1 Bambu petung
TNM TNM2 Gedek bambu kulit
TNM TNM3 Gedek bambu daging
TNM TNM4 Ijuk
KODE NO. NAMA BARANG / BAHAN / TENAGA
TNM TNM5 Tali ijuk
TNM TNM6 Gebalan rumput

ALT ALAT
ALT ALT1 Crane Kap. 35 ton
ALT ALT2 Crane Kap. 10-15 Ton
ALT ALT3 Hammer + Pile driver
ALT ALT4 Crawler Crane Kap. 35 ton
ALT ALT5 Alat Pancang Pile Compactor
ALT ALT6 Generator 150 kVA
ALT ALT7 Piling Barge Driving
ALT ALT8 Ponton Kap. 1000 ton
ALT ALT9 Work Boat
ALT ALT10 Kotrek 2,5 ton
ALT ALT11 Kunci
ALT ALT12 Perancah
ALT ALT13 Waterpass
ALT ALT14 Theodolite
ALT ALT15 Genset
ALT ALT16 Bor beton
ALT ALT17 Sewa alat las
ALT ALT18 Sewa alat sondir
ALT ALT19 Sewa alat perakitan tulangan
ALT ALT20 Sewa Scaffolding
ALT ALT21 Biaya tes beton per benda uji
ALT ALT22 Vienetions dan vertikal blinds (tirai)
ALT ALT23 Karpet
ALT ALT24 Biaya analisis tes beton perbeda uji
ALT ALT25 Sewa Compressor untuk pekerjaan grouting
ALT ALT26 Sewa Mesin Grouting
ALT ALT27 Sewa mesin gerinda untuk pekerjaan grouting
ALT ALT28 Sewa mixer ubtuk pekerjaan grouting
ALT ALT29 Sewa alar bor
ALT ALT30 Sewa Alat Ukur
ALT ALT31 Sewa Motor Walls
ALT ALT32 Alat bantu pekerjaan grouting
ALT ALT33 Alat bantu pekerjaan pekerjaan marka
ALT ALT34 Alat bantu pekerjaan pekerjaan expantion joint
ALT ALT35 Waterstop lebar 230 mm - 320 mm
ALT ALT36 Waterstop lebar 200 mm
ALT ALT37 Waterstop lebar 150 mm
ALT37
HARGA SATUAN
SATUAN
(Rp.)

OH 80,000
OH 80,000
OH 80,000
OH 80,000
OH 80,000
OH 80,000
OH 80,000
OH
OH
OH
OH
OH 90,000
OH
OH 55,000
OH 80,000
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH
OH

lbr
lbr
HARGA SATUAN
SATUAN
(Rp.)
lbr
lbr
lbr
lbr
lbr
lbr
lbr
lbr
lbr
lbr
lbr
lbr
lbr

kg 9,400
kg
kg
kg
bh
m1
kg
ltr

bh
bh
bh
bh
bh
bh
m2
bh
lbr
bh

bh
bh
bh
bh
bh

m2
HARGA SATUAN
SATUAN
(Rp.)
m'
kg
m2
m2
bh
m'
m2
bh

lbr 51,000.00
lbr
lbr
lbr
m2
m2
m1

ltr
ltr 18,900.00
ltr 6,000
ltr
ltr
ltr
kg
kg
ltr

kg
kg

box
ltr
ltr

kg 11,600
kg 12,300
kg
kg
HARGA SATUAN
SATUAN
(Rp.)
kg 12,500.00
ml
ml
kg 12,100
kg
kg 13,300
kg 12,100
kg 13,300
kg
Kg
bh
unit
m1
bh
tube 7,500.00
ml
kg
m2 239,400.00

kg 20,000
kg
m2
m2
kg
kg
kg
kg
m2 20,000
m1
m1
m2
m1
m1
bh
m2
m2
m2
m2
m2
m2
HARGA SATUAN
SATUAN
(Rp.)
m2
m2
m2
m2

bh
bh
bh
bh
bh
bh
bh
m3
m3
kg

m1

lbr
btg
m'
m'

m3 195,300.00
Kg
m3
m2
m3
m2 72,000
m2 66,000
m2
m2
m2
m2
bh
bh
kg
HARGA SATUAN
SATUAN
(Rp.)
m3 288,000
m3 276,000
m 3

m2
m2
bh 600
m 3
214,200
m3 214,200
m3 214,200
m 3
214,200
m3 214,200
m3
m3
m3
m3
m3 94,500
m3 120,000
m3 120,000
m3
m3 170,100
m3
m3
m3 214,200
m3 214,200
bj
bj
m3
m3 100,800
m3 100,800
m3 110,900.00
bh
bh
bh
bh

kg 35,300
kg 24,000
HARGA SATUAN
SATUAN
(Rp.)
kg 35,300
kg
kg
kg 51,800
kg 59,200
kg
kg 22,700.00
kg
kg
ltr
ltr
ltr 44,100.00
ltr 12,000
ltr 12,000
bh
bh
bh 7,800
bh 4,800
kg
kg
lbr
kg

m2
m2
m2
m2
m2
m2
m2
bh
bh
bh
m2 193,600.00

m2
m2
HARGA SATUAN
SATUAN
(Rp.)

buah
buah
m'
buah
buah
buah
buah
m1
m1
kg
m
m2
m2
m2

m2 60,900.00
m2
lbr
ml

bh 31,500.00
bh 22,100.00
bh 16,800.00
bh 12,600.00
bh
bh
bh
bh
bh
bh 69,300.00
bh 157,500.00
bh 69,300.00
bh 69,300.00
bh 8,200.00
bh
bh
bh
bh
bh
HARGA SATUAN
SATUAN
(Rp.)
bh

m3
m3
kg
lbr 68,000.00
roll
m1
m1
m1
lbr 63,000.00
lbr 78,800.00

m3 5,937,500
m 3
15,625,000
m3 9,200,000
m3 9,200,000
m 3

m3 5,937,500
btg 15,800
btg
m3

m1
m1

lbr
lbr
lbr
lbr
lbr
lbr 56,100.00
lbr 62,400.00
lbr
lbr
lbr 79,200
HARGA SATUAN
SATUAN
(Rp.)

bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
bh
m2
bh
m2
bh
bh
bh
m2
bh
m3

titik
ls
roll
roll 498,800.00
roll 354,400.00
m' 498,800.00
m' 354,400.00
m1
m1
m1
HARGA SATUAN
SATUAN
(Rp.)
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
m1
buah
buah
buah
buah
m'
unit / ls
titik
set
unit
jam

bh
bh
bh
bh 3,900.00
bh 17,100.00
bh
bh
bh
bh
bh
bh
bh
ps
bh
bh
HARGA SATUAN
SATUAN
(Rp.)
hr
tb
bh
kg
kg

kg
kg
kg
kg
kg
bh
kg 16,300
bh
bh
bh
kg
kg
kg
kg
kg 16,300.00

m
m
bh
bh
m1
m1
m1
m1
m1
m1
bh
bh 820,000.00

btg 13,700.00
btg 18,900.00
btg 25,900.00
btg 44,500.00
btg 56,900.00
HARGA SATUAN
SATUAN
(Rp.)
btg 83,100.00
btg 112,100.00
btg 185,800.00

kg 1,375
kg 1,875
kg
kg
kg
kg
kg
m3

bh 459,400.00
bh 360,900.00

bh
bh
set 1,890,000.00
bh 113,400.00

set 535,500.00
bh
bh
bh
set
set

set
bh 19,700.00
bh
bh 78,100.00
bh 206,700.00
set
bh 52,500.00

btg
m2
m2
m3
HARGA SATUAN
SATUAN
(Rp.)
kg
m2

hari 3,900,000.00
hari 2,800,000.00
hari 1,850,000.00
hari
hari
hari
hari
hari 4,000,000.00
hari 1,000,000.00
bh 200,000.00
set 125,000.00
hari 350,000.00
unit
unit
hari 275,000.00
hari
hr
hr
hr
unit
bh
m2
m2
bh
hr
hr
hr
hr
hr
hr
hr
ls
ls
ls
m'
m'
m'

Medan, Maret 2012


HARGA SATUAN
SATUAN
(Rp.)
ANALISA HARGA SATUAN

PEKERJAAN
LOKASI
TAHUN

KODE Macam Pekerjaan Upah Bahan Jumlah


(1) (2) (3) (4) (5)

PEKERJAAN PERSIAPAN

PPS1 100 M² Pekerjaan Pengukuran Gedung


Pekerja 8.0000 OH X Rp. 55,000.00 440,000.00
Mandor 2.0000 OH X Rp. 80,000.00 160,000.00
Pengawas 0.5000 OH X Rp. - 0.00
Asisten Ahli Ukur 2.0000 OH X Rp. - 0.00
Sewa Alat Ukur 1.0000 hr X Rp. - 0.00
JUMLAH 600,000.00 0.00 600,000.00

Pekerjaan Pengukuran 0.0100 m2 x 600,000.00 6,000.00 0.00 6,000.00

PPS2 1 M' Pengukuran dan pemasangan bouwplank untuk gedung dan saluran
Kayu meranti balok 0.0120 m3 X Rp. 9,200,000.00 110,400.00
Paku reng 55 x 3,1 mm 0.0200 kg X Rp. - 0.00
Kayu meranti papan 0.0070 m3 X Rp. 9,200,000.00 64,400.00
Tukang kayu 0.1000 OH X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 OH X Rp. 90,000.00 900.00
Pekerja 0.1000 OH X Rp. 55,000.00 5,500.00
Mandor 0.0050 OH X Rp. 80,000.00 400.00
JUMLAH 14,800.00 174,800.00 189,600.00

PPS3 1 M² Membersihkan lapangan dan perataan


Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0500 org X Rp. 80,000.00 4,000.00
JUMLAH 9,500.00 0.00 9,500.00

PPS4 1 bh Membuat Papan Nama Proyek 80x120 cm


Kayu meranti balok 0.0350 m3 X Rp. 9,200,000.00 322,000.00
Seng BJLS 0,20 gelombang P = 180 cm 1.4000 lbr X Rp. 51,000.00 71,400.00
Paku biasa 1/2" - 1" 0.6000 kg X Rp. 16,300.00 9,780.00
Cat kayu 1.5000 kg X Rp. 59,200.00 88,800.00
Portland Cement (PC) 16.8000 kg X Rp. 1,375.00 23,100.00
Pasir beton 0.0270 m3 X Rp. 120,000.00 3,240.00
Krikil beton 0.0405 m3 X Rp. 170,100.00 6,889.05
Tukang batu 0.0175 OH X Rp. 80,000.00 1,400.00
Tukang kayu 1.0000 OH X Rp. 80,000.00 80,000.00
Tukang cat 1.0000 OH X Rp. 80,000.00 80,000.00
Pekerja 2.1000 OH X Rp. 55,000.00 115,500.00
Mandor 1.0050 OH X Rp. 80,000.00 80,400.00
JUMLAH 357,300.00 525,209.05 882,509.05

PPS5 1,00 m2 Pembuatan jalan sementara, tebal 25 cm


Batu belah hitam 0.2750 m3 X Rp. - 0.00
Krikil beton 0.0300 m3 X Rp. 170,100.00 5,103.00
Pasir beton 0.0500 m3 X Rp. 120,000.00 6,000.00
Pekerja 1.0000 OH X Rp. 55,000.00 55,000.00
Mandor 0.1000 OH X Rp. 80,000.00 8,000.00
JUMLAH 63,000.00 11,103.00 74,103.00

PPS6 1,00 m2 Pembuatan kantor sementara, dengan lantai plesteran


Kayu dolken Ø 8 - 10 /4 00 cm 1.2500 btg - 0.00
Kayu meranti balok 0.1800 m3 X Rp. 9,200,000.00 1,656,000.00
Paku biasa 0.8500 kg X Rp. 16,300.00 13,855.00
Besi strip 1.1000 kg X Rp. 13,300.00 14,630.00
Portland Cement (PC) 35.0000 kg X Rp. 1,375.00 1,203.13
Pasir pasang ( progo ) 0.1500 m3 X Rp. 120,000.00 18,000.00
Pasir beton 0.1000 m3 X Rp. 120,000.00 12,000.00
Krikil beton 0.1500 m3 X Rp. 170,100.00 25,515.00
Batu merah ( 5x11x23 ) 30.0000 bj X Rp. - 0.00
Seng plat 3" x 6" BJLS 28 0.2500 lbr X Rp. - 0.00
Jendela nako 2.0000 bh X Rp. - 0.00
Kaca polos 0.0800 m2 X Rp. 60,900.00 4,872.00
Kunci tanam 0.1500 bh X Rp. 69,300.00 10,395.00
Plywood 4 mm 0.0600 lbr X Rp. - 0.00
Tukang kayu 2.0000 OH X Rp. 80,000.00 160,000.00
Tukang batu 1.0000 OH X Rp. 80,000.00 80,000.00
Kepala tukang 0.3000 OH X Rp. 90,000.00 27,000.00
Pekerja 2.0000 OH X Rp. 55,000.00 110,000.00
Mandor 0.0500 OH X Rp. 80,000.00 4,000.00
JUMLAH 381,000.00 1,756,470.13 2,137,470.13

PPS7 1 M' Pembuatan pagar sementara dari seng gelombang tinggi 2 meter
Kayu dolken Ø 8 - 10 /4 00 cm 1.2500 btg X Rp. - 0.00
Portland Cement (PC) 2.5000 kg X Rp. 1,375.00 3,437.50
Seng gelombang 2" - 5" BJLS 24 1.2000 lbr X Rp. - 0.00
Pasir beton 0.0050 m3 X Rp. 120,000.00 600.00
Krikil beton 0.0090 m3 X Rp. 170,100.00 1,530.90
Kayu meranti balok 0.0250 m3 X Rp. 9,200,000.00 230,000.00
Paku biasa 0.0600 kg X Rp. 16,300.00 978.00
Cat dasar meni 0.4000 kg X Rp. 35,300.00 14,120.00
Tukang kayu 0.2000 OH X Rp. 80,000.00 16,000.00 16,000.00
Kepala tukang 0.0200 OH X Rp. 90,000.00 1,800.00 1,800.00
Pekerja 0.4000 OH X Rp. 55,000.00 22,000.00 22,000.00
Mandor 0.0200 OH X Rp. 80,000.00 1,600.00 1,600.00
JUMLAH 41,400.00 292,066.40 333,466.40

PPS8 1 M' Pembuatan pagar sementara dari kawat duri tinggi 1,80 meter
Kayu dolken Ø 8 - 10 /4 00 cm 1.0000 btg X Rp. - 0.00
Portland Cement (PC) 2.0000 kg X Rp. 1,375.00 2,750.00
Kawat duri 25.0000 kg X Rp. - 0.00
Pasir beton 0.0050 m3 X Rp. 120,000.00 600.00
Krikil beton 0.0090 m3 X Rp. 170,100.00 1,530.90
Paku biasa 0.0600 kg X Rp. 16,300.00 978.00
Tukang kayu 0.2000 OH X Rp. 80,000.00 16,000.00
Kepala tukang 0.0200 OH X Rp. 90,000.00 1,800.00
Pekerja 0.3000 OH X Rp. 55,000.00 16,500.00
Mandor 0.0200 OH X Rp. 80,000.00 1,600.00
JUMLAH 35,900.00 5,858.90 41,758.90

PPS9 1 m2 Pembuatan gudang semen dan alat-alat


Kayu dolken Ø 8 - 10 /4 00 cm 1.7000 btg X Rp. - 0.00
Kayu Kelas III 0.2100 m3 X Rp. 5,937,500.00 1,246,875.00
Paku biasa 0.3000 kg X Rp. 16,300.00 4,890.00
Portland Cement (PC) 10.5000 kg X Rp. 1,375.00 14,437.50
Pasir beton 0.0300 m3 X Rp. 120,000.00 3,600.00
Krikil beton 0.0500 m3 X Rp. 170,100.00 8,505.00
Seng gelombang 2" - 5" BJLS 24 1.5000 lbr X Rp. - 0.00
Tukang kayu 2.0000 OH X Rp. 80,000.00 160,000.00
Kepala tukang 0.2000 OH X Rp. 90,000.00 18,000.00
Pekerja 1.0000 OH X Rp. 55,000.00 55,000.00
Mandor 0.0500 OH X Rp. 80,000.00 4,000.00
JUMLAH 237,000.00 1,278,307.50 1,515,307.50

PPS10 1 m2 Pembuatan rumah jaga/konstruksi kayu


Kayu dolken Ø 8 - 10 /4 00 cm 3.0000 btg X Rp. - 0.00
Kayu Kelas III 0.2760 m3 X Rp. 5,937,500.00 1,638,750.00
Paku biasa 0.7000 kg X Rp. 16,300.00 11,410.00
Seng gelombang 2" - 5" BJLS 24 1.5000 lbr X Rp. - 0.00
Tukang kayu 1.5000 org X Rp. 80,000.00 120,000.00
Kepala tukang 0.1500 org X Rp. 90,000.00 13,500.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.0500 org X Rp. 80,000.00 4,000.00
JUMLAH 192,500.00 1,650,160.00 1,842,660.00

PPS11 1 m2 Pembuatan bedeng buruh


Kayu dolken Ø 8 - 10 /4 00 cm 1.2500 btg X Rp. - 0.00
Kayu Kelas III 0.1860 m3 X Rp. 5,937,500.00 1,104,375.00
Paku biasa 0.3000 kg X Rp. 16,300.00 4,890.00
Portland Cement (PC) 18.0000 kg X Rp. 1,375.00 24,750.00
Pasir beton 0.0300 m3 X Rp. 120,000.00 3,600.00
Krikil beton 0.0500 m3 X Rp. 170,100.00 8,505.00
Seng gelombang 2" - 5" BJLS 24 1.5000 lbr X Rp. - 0.00
Plywood 4 mm 4.3500 lbr X Rp. - 0.00
Tukang kayu 2.0000 org X Rp. 80,000.00 160,000.00
Kepala tukang 0.2000 org X Rp. 90,000.00 18,000.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.0500 org X Rp. 80,000.00 4,000.00
JUMLAH 237,000.00 1,146,120.00 1,383,120.00

PPS12 1 M' Pasang pagar kawat jaring galvanis, tinggi 1,00 m


Kawat jaring 0.4340 lbr X Rp. - 0.00
Tukang besi 0.0420 org X Rp. 80,000.00 3,360.00
Kepala tukang 0.0040 org X Rp. 90,000.00 360.00
Pekerja 0.0420 org X Rp. 55,000.00 2,310.00
Mandor 0.0020 org X Rp. 80,000.00 160.00
JUMLAH 6,190.00 0.00 6,190.00

PPS13 1 M' Pasang pagar beton pracetak ( 5 x 50 x 213 ) cm


Panel beton pracetak 0.9860 lbr X Rp. - 0.00
Kolom beton pracetak 0.5250 btg X Rp. - 0.00
Pasir beton 0.0740 m3 X Rp. 120,000.00 8,880.00
Batu pecah 2/3 ( split ) 0.1460 m3 X Rp. 214,200.00 31,273.20
Portland Cement (PC) 45.0000 kg X Rp. 1,375.00 61,875.00
Tukang batu 0.1250 org X Rp. 80,000.00 10,000.00
Kepala tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.3750 org X Rp. 55,000.00 20,625.00
Mandor 0.0190 org X Rp. 80,000.00 1,520.00
JUMLAH 33,225.00 102,028.20 135,253.20

PEKERJAAN TANAH

PTN1 1 m3 Galian tanah biasa sedalam sampai 1 meter


Pekerja 0.7500 org X Rp. 55,000.00 41,250.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 43,250.00 0.00 43,250.00

PTN2 1 M³ Galian tanah biasa sedalam 1 - 2 meter


Pekerja 0.9000 org X Rp. 55,000.00 49,500.00
Mandor 0.0450 org X Rp. 80,000.00 3,600.00
JUMLAH 53,100.00 0.00 53,100.00

PTN3 1 M3 Galian tanah biasa sedalam 2 - 3 meter


Pekerja 1.0500 org X Rp. 55,000.00 57,750.00
Mandor 0.0670 org X Rp. 80,000.00 5,360.00
JUMLAH 63,110.00 0.00 63,110.00

PTN4 1 m3 Galian tanah keras sedalam sampai 1 meter


Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.0320 org X Rp. 80,000.00 2,560.00
JUMLAH 57,560.00 0.00 57,560.00

PTN5 1 m3 Galian tanah cadas sedalam sampai 1 meter


Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0600 org X Rp. 80,000.00 4,800.00
JUMLAH 87,300.00 0.00 87,300.00

PTN6 1 M3 Galian tanah lumpur sedalam 1 meter


Pekerja 1.2000 org X Rp. 55,000.00 66,000.00
Mandor 0.0450 org X Rp. 80,000.00 3,600.00
JUMLAH 69,600.00 0.00 69,600.00

PTN7 1 M3 Stripping tebing setinggi 1 meter


Pekerja 0.0500 org X Rp. 55,000.00 2,750.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 3,150.00 0.00 3,150.00

PTN8 1 m3 Pengangkutan tanah sejauh 15 meter


Pekerja 0.3300 org X Rp. 55,000.00 18,150.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 18,950.00 18,950.00

PTN9 1 m3 Pemadatkan tanah per 20 cm


Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0500 org X Rp. 80,000.00 4,000.00
JUMLAH 31,500.00 31,500.00

PTN10 1 m3 Urug kembali bekas galian (dihitung 1/3 kali galian tanah)
Pekerja 0.2500 org X Rp. 55,000.00 13,750.00
Mandor 0.0083 org X Rp. 80,000.00 664.00
JUMLAH 14,414.00 14,414.00

PTN11 1 M3 Urugan pasir


Pasir urug darat 1.2000 m3 X Rp. 94,500.00 113,400.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 17,300.00 113,400.00 130,700.00

PTN12 1 m3 Urugan sirtu padat untuk peninggian lantai bangunan


Sirtu 1.2000 m3 X Rp. 110,900.00 133,080.00
Pekerja 0.2500 org X Rp. 55,000.00 13,750.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 15,750.00 133,080.00 148,830.00

PTN13 1 M3 Urug tanah mendatangkan


Tanah urug 1.2000 m3 X Rp. 100,800.00 120,960.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 17,300.00 120,960.00 138,260.00

PTN14 1 M3 Memasang Lapisan pudel campuran 1 KP : 5 TL untuk stabilisasi


Kapur pasang 0.2480 m3 X Rp. - 0.00
Tanah liat 1.2400 m3 X Rp. - 0.00
Tukang Batu 0.4000 org X Rp. 80,000.00 32,000.00
Kepala Tukang 0.0400 org X Rp. 90,000.00 3,600.00
Pekerja 0.8000 org X Rp. 55,000.00 44,000.00
Mandor 0.0800 org X Rp. 80,000.00 6,400.00
JUMLAH 86,000.00 0.00 86,000.00

PTN15 1 M2 Gebalan rumput


Bambu petung 0.2000 btg X Rp. - 0.00
Gebalan rumput 1.0000 m2 X Rp. - 0.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 29,500.00 0.00 29,500.00

PTN16 1 M3 Pemasangan lapisan ijuk tebal 10cm untuk peresapan


Ijuk 6.0000 kg X Rp. - 0.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 9,450.00 0.00 9,450.00

PTN17 1 m3 Pembuangan Tanah sampai dengan sejauh 150 meter


Pekerja 0.5160 org X Rp. 55,000.00 28,380.00
Mandor 0.0500 org X Rp. 80,000.00 4,000.00
JUMLAH 32,380.00 0.00 32,380.00

PTN18 1 ttk Mengerjakan Sondir Tanah


Sewa alat sondir 0.50 hr X Rp. - 0.00
Operator mesin sondir 1.00 org X Rp. - 0.00
Analis test sondir 0.50 org X Rp. - 0.00
Pekerja 2.00 org X Rp. 55,000.00 110,000.00
Mandor 0.10 org X Rp. 80,000.00 8,000.00
JUMLAH 118,000.00 0.00 118,000.00

PTN19 1 m3 Membuang lumpur SAL sejauh 15 km


Pekerja 0.50 org X Rp. 55,000.00 27,500.00
Mandor 0.02 org X Rp. 80,000.00 1,600.00
Sewa kendaraan untuk membuang lumpur 0.41 hr X Rp. - 0.00
JUMLAH 29,100.00 0.00 29,100.00

PTN20 1 m3 Mengangkut lumpur SAL sejauh 30 m


Pekerja 0.40 org X Rp. 55,000.00 22,000.00
Mandor 0.02 org X Rp. 80,000.00 1,200.00
Gerobak (sewa) 0.50 hr X Rp. - 0.00
JUMLAH 23,200.00 0.00 23,200.00

PEKERJAAN PASANGAN

Pasangan pondasi

PPO1 1 M3 Pasangan pondasi batu kosong (anstamping)


Batu belah hitam 1.2000 m3 X Rp. - 0.00
Pasir urug darat 0.4320 m3 X Rp. 94,500.00 40,824.00
Tukang Batu 0.3900 org X Rp. 80,000.00 31,200.00
Kepala Tukang 0.0390 org X Rp. 90,000.00 3,510.00
Pekerja 0.7800 org X Rp. 55,000.00 42,900.00
Mandor 0.0390 org X Rp. 80,000.00 3,120.00
JUMLAH 80,730.00 40,824.00 121,554.00

PPO2 1 M3 Pasangan pondasi 1 Kp : 1 Sm : 1 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Kapur pasang 0.2290 m3 X Rp. - 0.00
Semen warna 0.2290 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.5440 m3 X Rp. 120,000.00 65,280.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 65,280.00 220,530.00

PPO3 1 M3 Pasangan pondasi 1 Kp : 1 Sm : 2 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Kapur pasang 0.1700 m3 X Rp. - 0.00
Semen warna 0.1700 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.3400 m3 X Rp. 120,000.00 40,800.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 40,800.00 196,050.00

PPO4 1 M3 Pasangan pondasi 1 Pc : 3 Kp : 5 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Portland Cement (PC) 95.4200 kg X Rp. 1,375.00 131,202.50
Kapur pasang 0.2290 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.3820 m3 X Rp. 120,000.00 45,840.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 177,042.50 332,292.50

PPO5 1 M3 Pasangan pondasi 1 Pc : 3 Kp : 10 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Portland Cement (PC) 61.0000 kg X Rp. 1,375.00 83,875.00
Kapur pasang 0.1470 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.4920 m3 X Rp. 120,000.00 59,040.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 142,915.00 298,165.00

PPO6 1 M3 Pasangan pondasi 1/4 Pc : 1 Kp : 4 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Portland Cement (PC) 41.0000 kg X Rp. 1,375.00 56,375.00
Kapur pasang 0.1310 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.5230 m3 X Rp. 120,000.00 62,760.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 119,135.00 274,385.00

PPO7 1 M3 Pasangan pondasi 1 Pc : 4 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Portland Cement (PC) 163.0000 kg X Rp. 1,375.00 224,125.00
Pasir pasang ( progo ) 0.5200 m3 X Rp. 120,000.00 62,400.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 286,525.00 441,775.00

PPO8 1 M3 Pasangan pondasi 1 Pc : 3 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Portland Cement (PC) 202.0000 kg X Rp. 1,375.00 277,750.00
Pasir pasang ( progo ) 0.4850 m3 X Rp. 120,000.00 58,200.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 335,950.00 491,200.00

PPO9 1 M3 Pasangan pondasi 1 Pc : 1 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Portland Cement (PC) 392.0000 kg X Rp. 1,375.00 539,000.00
Pasir pasang ( progo ) 0.3140 m3 X Rp. 120,000.00 37,680.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 576,680.00 731,930.00

PPO10 1 M3 Pasangan pondasi 1 Pc : 2 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Portland Cement (PC) 267.0000 kg X Rp. 1,375.00 367,125.00
Pasir pasang ( progo ) 0.4270 m3 X Rp. 120,000.00 51,240.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 418,365.00 573,615.00

PPO11 1 M3 Pasangan pondasi 1 Pc : 5 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Portland Cement (PC) 136.0000 kg X Rp. 1,375.00 187,000.00
Pasir pasang ( progo ) 0.5440 m3 X Rp. 120,000.00 65,280.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 252,280.00 407,530.00

PPO12 1 M3 Pasangan pondasi 1 Pc : 6 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Portland Cement (PC) 117.0000 kg X Rp. 1,375.00 160,875.00
Pasir pasang ( progo ) 0.5610 m3 X Rp. 120,000.00 67,320.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 228,195.00 383,445.00

PPO13 1 M3 Pasangan pondasi 1 Pc : 8 Ps


Batu belah putih 1.2000 m3 X Rp. - 0.00
Portland Cement (PC) 91.0000 kg X Rp. 1,375.00 125,125.00
Pasir pasang ( progo ) 0.5840 m3 X Rp. 120,000.00 70,080.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 1.5000 org X Rp. 55,000.00 82,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 155,250.00 195,205.00 350,455.00

PPO14 1 M3 Beton cyclope 60% beton camp. 1pc:2ps:3kr, 40% batu belah
Batu belah putih 0.4800 m3 X Rp. - 0.00
Portland Cement (PC) 194.0000 kg X Rp. 1,375.00 266,750.00
Pasir beton 0.3120 m3 X Rp. 120,000.00 37,440.00
Krikil beton 0.4680 m3 X Rp. 170,100.00 79,606.80
Besi beton polos 126.0000 kg X Rp. 11,600.00 1,461,600.00
Kawat beton / bindrat 1.8000 kg X Rp. 20,000.00 36,000.00
Tukang batu 0.8500 org X Rp. 80,000.00 68,000.00
Kepala Tukang 0.0850 org X Rp. 90,000.00 7,650.00
Pekerja 3.4000 org X Rp. 55,000.00 187,000.00
Mandor 0.1700 org X Rp. 80,000.00 13,600.00
JUMLAH 276,250.00 1,881,396.80 2,157,646.80

PPO15 1 M3 Pasangan pondasi sumuran dia. 100 cm


Batu belah putih 0.4500 m3 X Rp. - 0.00
Portland Cement (PC) 194.0000 kg X Rp. 1,375.00 266,750.00
Pasir beton 312.0000 m3 X Rp. 120,000.00 37,440,000.00
Krikil beton 0.4680 m3 X Rp. 170,100.00 79,606.80
Tukang Batu 0.8000 org X Rp. 80,000.00 64,000.00
Kepala Tukang 0.0800 org X Rp. 90,000.00 7,200.00
Pekerja 2.4000 org X Rp. 55,000.00 132,000.00
Mandor 0.1190 org X Rp. 80,000.00 9,520.00
JUMLAH 212,720.00 37,786,356.80 37,999,076.80

PASANGAN DINDING

PPD1 1 m2 Pasangan dinding HB/CB 10, camp. 1pc : 4ps


HB 10 12.5000 bh X Rp. - 0.00
Portland Cement (PC) 12.1300 kg X Rp. 1,375.00 16,678.75
Pasir pasang ( progo ) 0.3880 m3 X Rp. 120,000.00 46,560.00
Besi angkur dia. 8mm 0.2800 kg X Rp. - 0.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 63,238.75 89,838.75

PPD2 1 m2 Pasangan dinding HB/CB 10, camp. 1pc : 3ps


HB 10 12.5000 bh X Rp. - 0.00
Portland Cement (PC) 15.1600 kg X Rp. 1,375.00 20,845.00
Pasir pasang ( progo ) 0.3640 m3 X Rp. 120,000.00 43,680.00
Besi angkur dia. 8mm 0.2800 kg X Rp. - 0.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 64,525.00 91,125.00

PPD3 1 M2 Pasangan dinding HB/CB 15, camp. 1pc : 4ps


HB 15 12.5000 bh X Rp. - 0.00
Portland Cement (PC) 18.2000 kg X Rp. 1,375.00 25,025.00
Pasir pasang ( progo ) 0.5820 m3 X Rp. 120,000.00 69,840.00
Besi angkur dia. 8mm 0.2800 kg X Rp. - 0.00
Tukang Batu 0.1200 org X Rp. 80,000.00 9,600.00
Kepala Tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.3200 org X Rp. 55,000.00 17,600.00
Mandor 0.0160 org X Rp. 80,000.00 1,280.00
JUMLAH 29,560.00 94,865.00 124,425.00

PPD4 1 m2 Pasangan dinding HB/CB 15, camp. 1pc : 3ps


HB 15 12.5000 bh X Rp. - 0.00
Portland Cement (PC) 22.7400 kg X Rp. 1,375.00 31,267.50
Pasir pasang ( progo ) 0.5500 m3 X Rp. 120,000.00 66,000.00
Besi angkur dia. 8mm 0.2800 kg X Rp. - 0.00
Tukang Batu 0.1200 org X Rp. 80,000.00 9,600.00
Kepala Tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.3200 org X Rp. 55,000.00 17,600.00
Mandor 0.0160 org X Rp. 80,000.00 1,280.00
JUMLAH 29,560.00 97,267.50 126,827.50

PPD5 1 m2 Pasangan dinding HB/CB 20, camp. 1pc : 4ps


HB 20 12.5000 bh X Rp. - 0.00
Portland Cement (PC) 24.2600 kg X Rp. 1,375.00 33,357.50
Pasir pasang ( progo ) 0.7720 m3 X Rp. 120,000.00 92,640.00
Besi angkur dia. 8mm 0.2800 kg X Rp. - 0.00
Tukang Batu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala Tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.3500 org X Rp. 55,000.00 19,250.00
Mandor 0.0175 org X Rp. 80,000.00 1,400.00
JUMLAH 34,000.00 125,997.50 159,997.50

PPD6 1 m2 Pasangan dinding HB/CB 20, camp. 1pc : 3ps


HB 20 12.5000 bh X Rp. - 0.00
Portland Cement (PC) 30.3200 kg X Rp. 1,375.00 41,690.00
Pasir pasang ( progo ) 0.7280 m3 X Rp. 120,000.00 87,360.00
Besi angkur dia. 8mm 0.2800 kg X Rp. - 0.00
Tukang Batu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala Tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.3500 org X Rp. 55,000.00 19,250.00
Mandor 0.0175 org X Rp. 80,000.00 1,400.00
JUMLAH 34,000.00 129,050.00 163,050.00

PPD7 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 2Ps


Batu Bata 5 x 11 x 22 70.0000 bh X Rp. 600.00 42,000.00
Kapur pasang 0.0140 m3 X Rp. - 0.00
Semen warna 0.0140 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.0280 m3 X Rp. 120,000.00 3,360.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 45,360.00 71,960.00

PPD8 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 1Ps


Batu Bata 5 x 11 x 22 70.0000 bh X Rp. 600.00 42,000.00
Kapur pasang 0.0180 m3 X Rp. - 0.00
Semen warna 0.0180 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.0180 m3 X Rp. 120,000.00 2,160.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 44,160.00 70,760.00

PPD9 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps


Batu Bata 5 x 11 x 22 70.0000 bh X Rp. 600.00 42,000.00
Portland Cement (PC) 4.5000 kg X Rp. 1,375.00 6,187.50
Kapur pasang 0.0150 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.0500 m3 X Rp. 120,000.00 6,000.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 54,187.50 80,787.50

PPD10 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 8 Ps


Batu Bata 5 x 11 x 22 70.0000 bh X Rp. 600.00 42,000.00
Portland Cement (PC) 6.5000 kg X Rp. 1,375.00 8,937.50
Pasir pasang ( progo ) 0.0500 m3 X Rp. 120,000.00 6,000.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 56,937.50 83,537.50

PPD11 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps


Batu Bata 5 x 11 x 22 70.0000 bh X Rp. 600.00 42,000.00
Portland Cement (PC) 8.3200 kg X Rp. 1,375.00 11,440.00
Pasir pasang ( progo ) 0.0490 m3 X Rp. 120,000.00 5,880.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 59,320.00 85,920.00

PPD12 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps


Batu Bata 5 x 11 x 22 70.0000 bh X Rp. 600.00 42,000.00
Portland Cement (PC) 9.6800 kg X Rp. 1,375.00 13,310.00
Pasir pasang ( progo ) 0.0450 m3 X Rp. 120,000.00 5,400.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 60,710.00 87,310.00

PPD13 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps


Batu Bata 5 x 11 x 22 70.0000 bh X Rp. 600.00 42,000.00
Portland Cement (PC) 11.5000 kg X Rp. 1,375.00 15,812.50
Pasir pasang ( progo ) 0.0430 m3 X Rp. 120,000.00 5,160.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 62,972.50 89,572.50

PPD14 1 m2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps


Batu Bata 5 x 11 x 22 70.0000 bh X Rp. 600.00 42,000.00
Portland Cement (PC) 14.3700 kg X Rp. 1,375.00 19,758.75
Pasir pasang ( progo ) 0.0400 m3 X Rp. 120,000.00 4,800.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 66,558.75 93,158.75

PPD15 1 M2 Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps


Batu Bata 5 x 11 x 22 70.0000 bh X Rp. 600.00 42,000.00
Portland Cement (PC) 18.9500 kg X Rp. 1,375.00 26,056.25
Pasir pasang ( progo ) 0.0380 m3 X Rp. 120,000.00 4,560.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 72,616.25 99,216.25

PPD16 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps


Batu Bata 5 x 11 x 22 140.0000 bh X Rp. 600.00 84,000.00
Portland Cement (PC) 10.0800 kg X Rp. 1,375.00 13,860.00
Kapur pasang 0.0275 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.0925 m3 X Rp. 120,000.00 11,100.00
Tukang Batu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.6000 org X Rp. 55,000.00 33,000.00
Mandor 0.0300 org X Rp. 80,000.00 2,400.00
JUMLAH 53,200.00 108,960.00 162,160.00

PPD17 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 6 Ps


Batu Bata 5 x 11 x 22 140.0000 bh X Rp. 600.00 84,000.00
Portland Cement (PC) 18.5000 kg X Rp. 1,375.00 25,437.50
Pasir pasang ( progo ) 0.1220 m3 X Rp. 120,000.00 14,640.00
Tukang Batu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.6000 org X Rp. 55,000.00 33,000.00
Mandor 0.0300 org X Rp. 80,000.00 2,400.00
JUMLAH 53,200.00 124,077.50 177,277.50

PPD18 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 5 Ps


Batu Bata 5 x 11 x 22 140.0000 bh X Rp. 600.00 84,000.00
Portland Cement (PC) 22.2000 kg X Rp. 1,375.00 30,525.00
Pasir pasang ( progo ) 0.1020 m3 X Rp. 120,000.00 12,240.00
Tukang Batu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.6000 org X Rp. 55,000.00 33,000.00
Mandor 0.0300 org X Rp. 80,000.00 2,400.00
JUMLAH 53,200.00 126,765.00 179,965.00

PPD19 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps


Batu Bata 5 x 11 x 22 140.0000 bh X Rp. 600.00 84,000.00
Portland Cement (PC) 26.5500 kg X Rp. 1,375.00 36,506.25
Pasir pasang ( progo ) 0.0930 m3 X Rp. 120,000.00 11,160.00
Tukang Batu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.6000 org X Rp. 55,000.00 33,000.00
Mandor 0.0300 org X Rp. 80,000.00 2,400.00
JUMLAH 53,200.00 131,666.25 184,866.25

PPD20 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps


Batu Bata 5 x 11 x 22 140.0000 bh X Rp. 600.00 84,000.00
Portland Cement (PC) 32.9500 kg X Rp. 1,375.00 45,306.25
Pasir pasang ( progo ) 0.0910 m3 X Rp. 120,000.00 10,920.00
Tukang Batu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.6000 org X Rp. 55,000.00 33,000.00
Mandor 0.0300 org X Rp. 80,000.00 2,400.00
JUMLAH 53,200.00 140,226.25 193,426.25

PPD21 1 M2 Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps


Batu Bata 5 x 11 x 22 140.0000 bh X Rp. 600.00 84,000.00
Portland Cement (PC) 43.5000 kg X Rp. 1,375.00 59,812.50
Pasir pasang ( progo ) 0.0800 m3 X Rp. 120,000.00 9,600.00
Tukang Batu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.6000 org X Rp. 55,000.00 33,000.00
Mandor 0.0300 org X Rp. 80,000.00 2,400.00
JUMLAH 53,200.00 153,412.50 206,612.50

PPD22 1 M2 Pasangan roster 12 x 11 x 24 cm, camp. 1pc : 4ps


Terawang / roster 12x11x24 cm 30.0000 bh X Rp. - 0.00
Portland Cement (PC) 11.0000 kg X Rp. 1,375.00 15,125.00
Pasir pasang ( progo ) 0.0350 m3 X Rp. 120,000.00 4,200.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 19,325.00 45,925.00

PPD23 1 M2 Pasangan roster 12 x 11 x 24 cm, camp. 1pc : 3ps


Terawang / roster 12x11x24 cm 30.0000 bh X Rp. - 0.00
Portland Cement (PC) 14.0000 kg X Rp. 1,375.00 19,250.00
Pasir pasang ( progo ) 0.0320 m3 X Rp. 120,000.00 3,840.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 23,090.00 49,690.00

PPD24 1 m2 Pasangan bata merah expose (5 x 11 x 24 cm), camp. 1 Pc : 3 Ps


Bata expose 5 x 11 x 24 cm 70.0000 bh X Rp. - 0.00
Portland Cement (PC) 14.0000 kg X Rp. 1,375.00 19,250.00
Pasir pasang ( progo ) 0.0320 m3 X Rp. 120,000.00 3,840.00
Tukang Batu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala Tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 31,050.00 23,090.00 54,140.00

PPD25 1 m2 Pasangan dinding bataco


Batako 12.5000 bh X Rp. - 0.00
Portland Cement (PC) 12.5000 kg X Rp. 1,375.00 17,187.50
Pasir pasang ( progo ) 0.0400 m3 X Rp. 120,000.00 4,800.00
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 38,400.00 21,987.50 60,387.50

PPD26 1 M2 Pasangan roster 25/25 cm


Roster 25/25 16.0000 bh X Rp. - 0.00
Portland Cement (PC) 12.5000 kg X Rp. 1,375.00 17,187.50
Pasir pasang ( progo ) 0.0400 m3 X Rp. 120,000.00 4,800.00
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 0.00 21,987.50 21,987.50

PEKERJAAN BETON

PBT1 1 M3 Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr


Portland Cement (PC) 336.0000 kg X Rp. 1,375.00 462,000.00
Pasir beton 0.5400 m3 X Rp. 120,000.00 64,800.00
Krikil beton 0.8100 m3 X Rp. 170,100.00 137,781.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 1.6500 org X Rp. 55,000.00 90,750.00
Mandor 0.0800 org X Rp. 80,000.00 6,400.00
JUMLAH 119,400.00 664,581.00 783,981.00

PBT2 1 M3 Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr


Portland Cement (PC) 218.0000 kg X Rp. 1,375.00 299,750.00
Pasir beton 0.5200 m3 X Rp. 120,000.00 62,400.00
Krikil beton 0.8700 m3 X Rp. 170,100.00 147,987.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 1.6500 org X Rp. 55,000.00 90,750.00
Mandor 0.0800 org X Rp. 80,000.00 6,400.00
JUMLAH 119,400.00 510,137.00 629,537.00

PBT3 1 M3 Beton mutu f’'c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Portland Cement (PC) 247.000 kg X Rp. 1,375.00 339,625.00
Pasir beton 0.621 m3 X Rp. 120,000.00 74,485.71
Split D 1 - 2 cm 0.740 m3 X Rp. 214,200.00 158,508.00
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 572,618.71 694,443.71

PBT4 1 M3 Beton mutu f’ = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
Portland Cement (PC) 276.000 kg X Rp. 1,375.00 379,500.00
Pasir beton 0.591 m3 X Rp. 120,000.00 70,971.43
Split D 1 - 2 cm 0.750 m3 X Rp. 214,200.00 160,570.67
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 611,042.10 732,867.10

PBT5 1 M3 Beton mutu f’'c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
Portland Cement (PC) 299.000 kg X Rp. 1,375.00 411,125.00
Pasir beton 0.571 m3 X Rp. 120,000.00 68,485.71
Split D 1 - 2 cm 0.753 m3 X Rp. 214,200.00 161,364.00
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 640,974.71 762,799.71

PBT6 1 M3 Lantai kerja Beton mutu f’'c = 7,4 MPa (K 100), slump (3-6) cm w/c = 0,87
Portland Cement (PC) 230.000 kg X Rp. 1,375.00 316,250.00
Pasir beton 0.638 m3 X Rp. 120,000.00 76,542.86
Split D 1 - 2 cm 0.761 m3 X Rp. 214,200.00 162,950.67
Pekerja 1.200 OH X Rp. 55,000.00 66,000.00
Tukang Batu 0.200 OH X Rp. 80,000.00 16,000.00
Kepala Tukang 0.020 OH X Rp. 90,000.00 1,800.00
Mandor 0.060 OH X Rp. 80,000.00 4,800.00
JUMLAH 88,600.00 555,743.52 644,343.52

PBT7 1 M3 Beton mutu f’'c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Portland Cement (PC) 326.000 kg X Rp. 1,375.00 448,250.00
Pasir beton 0.543 m3 X Rp. 120,000.00 65,142.86
Split D 1 - 2 cm 0.762 m3 X Rp. 214,200.00 163,268.00
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 676,660.86 798,485.86

PBT8 1 M3 Beton mutu f’'c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
Portland Cement (PC) 352.000 kg X Rp. 1,375.00 484,000.00
Pasir beton 0.522 m3 X Rp. 120,000.00 62,657.14
Split D 1 - 2 cm 0.764 m3 X Rp. 214,200.00 163,585.33
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 710,242.48 832,067.48

PBT9 1 M3 Beton mutu f’'c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
Portland Cement (PC) 371.000 kg X Rp. 1,375.00 510,125.00
Pasir beton 0.499 m3 X Rp. 120,000.00 59,828.57
Split D 1 - 2 cm 0.776 m3 X Rp. 214,200.00 166,124.00
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 736,077.57 857,902.57

PBT10 1 M3 Beton mutu f’'c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Portland Cement (PC) 384.000 kg X Rp. 1,375.00 528,000.00
Pasir beton 0.494 m3 X Rp. 120,000.00 59,314.29
Split D 1 - 2 cm 0.770 m3 X Rp. 214,200.00 164,854.67
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 752,168.95 873,993.95

PBT11 1 M3 Beton mutu f’'c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
Portland Cement (PC) 406.000 kg X Rp. 1,375.00 558,250.00
Pasir beton 0.489 m3 X Rp. 120,000.00 58,628.57
Split D 1 - 2 cm 0.760 m3 X Rp. 214,200.00 162,792.00
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 779,670.57 901,495.57

PBT12 1 M3 Beton mutu f’'c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
Portland Cement (PC) 413.000 kg X Rp. 1,375.00 567,875.00
Pasir beton 0.486 m3 X Rp. 120,000.00 58,371.43
Split D 1 - 2 cm 0.756 m3 X Rp. 214,200.00 161,998.67
Pekerja 1.650 OH X Rp. 55,000.00 90,750.00
Tukang Batu 0.275 OH X Rp. 80,000.00 22,000.00
Kepala Tukang 0.028 OH X Rp. 90,000.00 2,475.00
Mandor 0.083 OH X Rp. 80,000.00 6,600.00
JUMLAH 121,825.00 788,245.10 910,070.10

PBT13 1 M3 Beton mutu f’'c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49
Portland Cement (PC) 439.000 kg X Rp. 1,375.00 603,625.00
Pasir beton 0.479 m3 X Rp. 120,000.00 57,428.57
Split D 1 - 2 cm 0.745 m3 X Rp. 214,200.00 159,618.67
Pekerja 2.100 OH X Rp. 55,000.00 115,500.00
Tukang Batu 0.350 OH X Rp. 80,000.00 28,000.00
Kepala Tukang 0.035 OH X Rp. 90,000.00 3,150.00
Mandor 0.105 OH X Rp. 80,000.00 8,400.00
JUMLAH 155,050.00 820,672.24 975,722.24

PBT14 1 M3 Beton mutu f’'c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
Portland Cement (PC) 448.000 kg X Rp. 1,375.00 616,000.00
Pasir beton 0.476 m3 X Rp. 120,000.00 57,171.43
Split D 1 - 2 cm 0.741 m3 X Rp. 214,200.00 158,666.67
Pekerja 2.100 OH X Rp. 55,000.00 115,500.00
Tukang Batu 0.350 OH X Rp. 80,000.00 28,000.00
Kepala Tukang 0.035 OH X Rp. 90,000.00 3,150.00
Mandor 0.105 OH X Rp. 80,000.00 8,400.00
JUMLAH 155,050.00 831,838.10 986,888.10

PBT15 1 M3 Membongkar cetakan


Pekerja 4.0000 org X Rp. 55,000.00 220,000.00
JUMLAH 220,000.00 0.00 220,000.00

PBT16 St utwerk unt uk 1 m3 beton, t inggi 3 - 4 m ( m emakai dolken )


Kayu dolken Ø 8 - 10/400 cm 0.7000 m3 X Rp. - 0.00
Tukang kayu 10.5000 org X Rp. 80,000.00 840,000.00
Kepala Tukang 1.0500 org X Rp. 90,000.00 94,500.00
Pekerja 3.5000 org X Rp. 55,000.00 192,500.00
Mandor 0.1750 org X Rp. 80,000.00 14,000.00
JUMLAH 1,141,000.00 0.00 1,141,000.00

PBT17 St utwerk unt uk 1 m3 beton, t inggi 3 - 4 m ( m emakai scaf olding )


Scafolding 32.0000 unit X Rp. - 0.00
Tukang kayu 3.5000 org X Rp. 80,000.00 280,000.00
Kepala Tukang 0.3500 org X Rp. 90,000.00 31,500.00
Pekerja 2.2000 org X Rp. 55,000.00 121,000.00
Mandor 0.1200 org X Rp. 80,000.00 9,600.00
JUMLAH 442,100.00 0.00 442,100.00

PBT18 1 m' PVC Waterstop lebar 150 mm


Waterstop lebar 150 mm 1.050 m' X Rp. - 0.00
Pekerja 0.060 OH X Rp. 55,000.00 3,300.00
Tukang Batu 0.030 OH X Rp. 80,000.00 2,400.00
Kepala Tukang 0.003 OH X Rp. 90,000.00 270.00
Mandor 0.003 OH X Rp. 80,000.00 240.00
JUMLAH 6,210.00 0.00 6,210.00

PBT19 1 m' PVC Waterstop lebar 200 mm


Waterstop lebar 200 mm 1.050 m' X Rp. - 0.00
Pekerja 0.070 OH X Rp. 55,000.00 3,850.00
Tukang Batu 0.035 OH X Rp. 80,000.00 2,800.00
Kepala Tukang 0.004 OH X Rp. 90,000.00 315.00
Mandor 0.007 OH X Rp. 80,000.00 560.00
JUMLAH 7,525.00 0.00 7,525.00

PBT20 1 m' PVC Waterstop lebar 230 mm - 320 mm


Waterstop lebar 230 mm - 320 mm 1.050 m' X Rp. - 0.00
Pekerja 0.080 OH X Rp. 55,000.00 4,400.00
Tukang Batu 0.040 OH X Rp. 80,000.00 3,200.00
Kepala Tukang 0.004 OH X Rp. 90,000.00 360.00
Mandor 0.004 OH X Rp. 80,000.00 320.00
JUMLAH 8,280.00 0.00 8,280.00

PBT21 1 Kg Pembesian dengan besi polos


Besi beton polos 1.0500 kg X Rp. 11,600.00 12,180.00
Kawat beton / bindrat 0.0150 kg X Rp. 20,000.00 300.00
Tukang Besi 0.0070 org X Rp. 80,000.00 560.00
Kepala Tukang 0.0007 org X Rp. 90,000.00 63.00
Pekerja 0.0070 org X Rp. 55,000.00 385.00
Mandor 0.0004 org X Rp. 80,000.00 28.00
JUMLAH 1,036.00 12,480.00 13,516.00

PBT22 1 Kg Pembesian dengan besi ulir


Besi beton ulir 1.0500 kg X Rp. 12,300.00 12,915.00
Kawat beton / bindrat 0.0150 kg X Rp. 20,000.00 300.00
Tukang Besi 0.0070 org X Rp. 80,000.00 560.00
Kepala Tukang 0.0007 org X Rp. 90,000.00 63.00
Pekerja 0.0070 org X Rp. 55,000.00 385.00
Mandor 0.0004 org X Rp. 80,000.00 28.00
JUMLAH 1,036.00 13,215.00 14,251.00

PBT23 1 Kg Memasang kabel presstressed polos/strands


Besi beton polos 1.0500 kg X Rp. 11,600.00 12,180.00
Kawat beton / bindrat 0.0100 kg X Rp. 20,000.00 200.00
Tukang Besi 0.0050 org X Rp. 80,000.00 400.00
Kepala Tukang 0.0005 org X Rp. 90,000.00 45.00
Pekerja 0.0050 org X Rp. 55,000.00 275.00
Mandor 0.0003 org X Rp. 80,000.00 20.00
JUMLAH 740.00 12,380.00 13,120.00

PBT24 1 Kg Memasang jaring kawat baja/wire mesh


Besi beton polos 1.0200 kg X Rp. 11,600.00 11,832.00
Kawat beton / bindrat 0.0050 kg X Rp. 20,000.00 100.00
Tukang Besi 0.0025 org X Rp. 80,000.00 200.00
Kepala Tukang 0.0025 org X Rp. 90,000.00 225.00
Pekerja 0.0025 org X Rp. 55,000.00 137.50
Mandor 0.0001 org X Rp. 80,000.00 10.00
JUMLAH 572.50 11,932.00 12,504.50

PBT25 1 M2 Cetakan beton / begisting memakai papan


Kayu meranti balok 0.0170 m3 X Rp. 9,200,000.00 156,400.00
Kayu meranti papan 0.0240 m3 X Rp. 9,200,000.00 220,800.00
Paku biasa 1/2" - 1" 0.4000 kg X Rp. 16,300.00 6,520.00
Tukang kayu 0.5000 org X Rp. 80,000.00 40,000.00
Kepala Tukang 0.0500 org X Rp. 90,000.00 4,500.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 56,300.00 383,720.00 440,020.00
2 kali pemakaian 28,150.00 191,860.00 220,010.00

PBT26 1 M2 Cetakan beton / begisting memakai multiplek


Kayu meranti balok 0.0170 m3 X Rp. 9,200,000.00 156,400.00
Multiplek 0.3470 lbr X Rp. 79,200.00 27,482.40
Paku biasa 1/2" - 1" 0.4000 kg X Rp. 16,300.00 6,520.00
Tukang kayu 0.5000 org X Rp. 80,000.00 40,000.00
Kepala Tukang 0.0500 org X Rp. 90,000.00 4,500.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 56,300.00 190,402.40 246,702.40
2 kali pemakaian 28,150.00 95,201.20 123,351.20

PBT27 1 M2 Begesting untuk pondasi


Papan cetakan / bekesting 0.0400 m3 X Rp. 5,937,500.00 237,500.00
Paku biasa 1/2" - 1" 0.3000 kg X Rp. 16,300.00 4,890.00
Minyak bekisting 0.1000 ltr X Rp. 6,000.00 600.00
Pekerja 0.5200 org X Rp. 55,000.00 28,600.00
Tukang Kayu 0.2600 org X Rp. 80,000.00 20,800.00
Kepala Tukang 0.0260 org X Rp. 90,000.00 2,340.00
Mandor 0.0260 org X Rp. 80,000.00 2,080.00
JUMLAH 53,820.00 242,990.00 296,810.00
2 kali pemakaian 26,910.00 121,495.00 148,405.00

PBT28 1 M2 Begesting untuk sloof


Papan cetakan / bekesting 0.0450 m3 X Rp. 5,937,500.00 267,187.50
Paku biasa 1/2" - 1" 0.3000 kg X Rp. 16,300.00 4,890.00
Minyak bekisting 0.1000 ltr X Rp. 6,000.00 600.00
Pekerja 0.5200 org X Rp. 55,000.00 28,600.00
Tukang Kayu 0.2600 org X Rp. 80,000.00 20,800.00
Kepala Tukang 0.0260 org X Rp. 90,000.00 2,340.00
Mandor 0.0260 org X Rp. 80,000.00 2,080.00
JUMLAH 53,820.00 272,677.50 326,497.50
2 kali pemakaian 26,910.00 136,338.75 163,248.75

PBT29 1 M2 Begesting untuk kolom


Papan cetakan / bekesting 0.0400 m3 X Rp. 5,937,500.00 237,500.00
Paku biasa 1/2" - 1" 0.4000 kg X Rp. 16,300.00 6,520.00
Minyak bekisting 0.2000 ltr X Rp. 6,000.00 1,200.00
Kayu meranti balok 0.0150 m3 X Rp. 9,200,000.00 138,000.00
Multiplek 0.3500 lbr X Rp. 79,200.00 27,720.00
Kayu dolken 2.0000 btg X Rp. 15,800.00 31,600.00
Pekerja 0.6600 org X Rp. 55,000.00 36,300.00
Tukang Kayu 0.3300 org X Rp. 80,000.00 26,400.00
Kepala Tukang 0.0330 org X Rp. 90,000.00 2,970.00
Mandor 0.0330 org X Rp. 80,000.00 2,640.00
JUMLAH 68,310.00 442,540.00 510,850.00
2 kali pemakaian 34,155.00 221,270.00 255,425.00

PBT30 1 M2 Begesting untuk balok


Papan cetakan / bekesting 0.0400 m3 X Rp. 5,937,500.00 237,500.00
Paku biasa 1/2" - 1" 0.4000 kg X Rp. 16,300.00 6,520.00
Minyak bekisting 0.2000 ltr X Rp. 6,000.00 1,200.00
Kayu meranti balok 0.0180 m3 X Rp. 9,200,000.00 165,600.00
Multiplek 0.3500 lbr X Rp. 79,200.00 27,720.00
Kayu dolken 2.0000 btg X Rp. 15,800.00 31,600.00
Pekerja 0.6600 org X Rp. 55,000.00 36,300.00
Tukang Kayu 0.3300 org X Rp. 80,000.00 26,400.00
Kepala Tukang 0.0330 org X Rp. 90,000.00 2,970.00
Mandor 0.0330 org X Rp. 80,000.00 2,640.00
JUMLAH 68,310.00 470,140.00 538,450.00
2 kali pemakaian 34,155.00 235,070.00 269,225.00

PBT31 1 M2 Begesting untuk lantai


Papan cetakan / bekesting 0.0400 m3 X Rp. 5,937,500.00 237,500.00
Paku biasa 1/2" - 1" 0.4000 kg X Rp. 16,300.00 6,520.00
Minyak bekisting 0.2000 ltr X Rp. 6,000.00 1,200.00
Kayu meranti balok 0.0150 m3 X Rp. 9,200,000.00 138,000.00
Multiplek 0.3500 lbr X Rp. 79,200.00 27,720.00
Kayu dolken 6.0000 btg X Rp. 15,800.00 94,800.00
Pekerja 0.6600 org X Rp. 55,000.00 36,300.00
Tukang Kayu 0.3300 org X Rp. 80,000.00 26,400.00
Kepala Tukang 0.0330 org X Rp. 90,000.00 2,970.00
Mandor 0.0330 org X Rp. 80,000.00 2,640.00
JUMLAH 68,310.00 505,740.00 574,050.00
2 kali pemakaian 34,155.00 252,870.00 287,025.00

PBT32 1 M2 Begesting untuk dinding


Papan cetakan / bekesting 0.0300 m3 X Rp. 5,937,500.00 178,125.00
Paku biasa 1/2" - 1" 0.4000 kg X Rp. 16,300.00 6,520.00
Minyak bekisting 0.2000 ltr X Rp. 6,000.00 1,200.00
Kayu meranti balok 0.0200 m3 X Rp. 9,200,000.00 184,000.00
Multiplek 0.3500 lbr X Rp. 79,200.00 27,720.00
Kayu dolken 3.0000 btg X Rp. 15,800.00 47,400.00
Formite/penjaga jarak bekisting/spacer 4.0000 bh X Rp. - 0.00
Pekerja 0.6600 org X Rp. 55,000.00 36,300.00
Tukang Kayu 0.3300 org X Rp. 80,000.00 26,400.00
Kepala Tukang 0.0330 org X Rp. 90,000.00 2,970.00
Mandor 0.0330 org X Rp. 80,000.00 2,640.00
JUMLAH 68,310.00 444,965.00 513,275.00
2 kali pemakaian 34,155.00 222,482.50 256,637.50

PBT33 1 M2 Begesting untuk tangga


Papan cetakan / bekesting 0.0300 m3 X Rp. 5,937,500.00 178,125.00
Paku biasa 1/2" - 1" 0.4000 kg X Rp. 16,300.00 6,520.00
Minyak bekisting 0.1500 ltr X Rp. 6,000.00 900.00
Kayu meranti balok 0.0150 m3 X Rp. 9,200,000.00 138,000.00
Multiplek 0.3500 lbr X Rp. 79,200.00 27,720.00
Kayu dolken 2.0000 btg X Rp. 15,800.00 31,600.00
Pekerja 0.6600 org X Rp. 55,000.00 36,300.00
Tukang Kayu 0.3300 org X Rp. 80,000.00 26,400.00
Kepala Tukang 0.0330 org X Rp. 90,000.00 2,970.00
Mandor 0.0330 org X Rp. 80,000.00 2,640.00
JUMLAH 68,310.00 382,865.00 451,175.00
2 kali pemakaian 34,155.00 191,432.50 225,587.50

PBT34 Jembatan untuk pengecoran beton


Papan cetakan / bekesting 0.0264 m3 X Rp. 5,937,500.00 156,750.00
Paku biasa 1/2" - 1" 0.6000 kg X Rp. 16,300.00 9,780.00
Kayu dolken 0.5000 btg X Rp. 15,800.00 7,900.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Tukang Kayu 0.0500 org X Rp. 80,000.00 4,000.00
Kepala Tukang 0.0500 org X Rp. 90,000.00 4,500.00
Mandor 0.0075 org X Rp. 80,000.00 600.00
JUMLAH 17,350.00 174,430.00 191,780.00
JASA 10 % 19,178.00

PBT35 1 m' Kolom praktis beton bertulang (11 x 11) cm


Papan cetakan / bekesting 0.0020 m3 X Rp. 5,937,500.00 11,875.00
Paku biasa 1/2" - 1" 0.0100 kg X Rp. 16,300.00 163.00
Besi beton polos 3.0000 kg X Rp. 11,600.00 34,800.00
Kawat beton / bindrat 0.4500 kg X Rp. 20,000.00 9,000.00
Portland Cement (PC) 4.0000 kg X Rp. 1,375.00 5,500.00
Pasir beton 0.0060 m3 X Rp. 120,000.00 720.00
Split D 1 - 2 cm 0.0090 m3 X Rp. 214,200.00 1,927.80
Pekerja 0.1800 OH X Rp. 55,000.00 9,900.00
Tukang Batu 0.0200 OH X Rp. 80,000.00 1,600.00
Tukang Kayu 0.0200 OH X Rp. 80,000.00 1,600.00
Tukang Besi 0.0200 OH X Rp. 80,000.00 1,600.00
Kepala Tukang 0.0060 OH X Rp. 90,000.00 540.00
Mandor 0.0090 OH X Rp. 80,000.00 720.00
JUMLAH 15,960.00 63,985.80 79,945.80

PBT36 1 m' Ring balok beton bertulang (10 x 15) cm


Papan cetakan / bekesting 0.0030 m3 X Rp. 5,937,500.00 17,812.50
Paku biasa 1/2" - 1" 0.0200 kg X Rp. 16,300.00 326.00
Besi beton polos 3.6000 kg X Rp. 11,600.00 41,760.00
Kawat beton / bindrat 0.0500 kg X Rp. 20,000.00 1,000.00
Portland Cement (PC) 5.5000 kg X Rp. 1,375.00 7,562.50
Pasir beton 0.0090 m3 X Rp. 120,000.00 1,080.00
Split D 1 - 2 cm 0.0150 m3 X Rp. 214,200.00 3,213.00
Pekerja 0.2970 OH X Rp. 55,000.00 16,335.00
Tukang Batu 0.0330 OH X Rp. 80,000.00 2,640.00
Tukang Kayu 0.0330 OH X Rp. 80,000.00 2,640.00
Tukang Besi 0.0330 OH X Rp. 80,000.00 2,640.00
Kepala Tukang 0.0100 OH X Rp. 90,000.00 900.00
Mandor 0.0150 OH X Rp. 80,000.00 1,200.00
JUMLAH 26,355.00 72,754.00 99,109.00

PBT37 1 m' Pembuatan tiang pancang (40 x 40) cm, beton bertulang
Pasir urug darat 0.0190 m3 X Rp. 94,500.00 1,795.50
Pasir beton 0.0940 m3 X Rp. 120,000.00 11,280.00
Batu pecah 2/3 ( split ) 0.1500 m3 X Rp. 214,200.00 32,130.00
Portland Cement (PC) 60.5000 kg X Rp. 1,375.00 83,187.50
Besi beton polos 45.0000 kg X Rp. 11,600.00 522,000.00
Kawat beton / bindrat 0.9000 kg X Rp. 20,000.00 18,000.00
Kayu meranti balok 0.0320 m3 X Rp. 9,200,000.00 294,400.00
Paku reng 55 x 3,1 mm 0.1200 kg X Rp. - 0.00
Minyak bekisting 0.0900 ltr X Rp. - 0.00
Plamur Fuji 0.2400 kg X Rp. - 0.00
Tukang batu 0.6700 org X Rp. 80,000.00 53,600.00
Kepala tukang 0.0670 org X Rp. 90,000.00 6,030.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.0500 org X Rp. 80,000.00 4,000.00
JUMLAH 118,630.00 962,793.00 1,081,423.00

PBT38 1 m' Pembuatan tiang pancang (35 x 35) cm, beton bertulang
Pasir urug darat 0.0160 m3 X Rp. 94,500.00 1,512.00
Pasir beton 0.0800 m3 X Rp. 120,000.00 9,600.00
Batu pecah 2/3 ( split ) 0.1250 m3 X Rp. 214,200.00 26,775.00
Portland Cement (PC) 49.0000 kg X Rp. 1,375.00 67,375.00
Besi beton polos 34.5000 kg X Rp. 11,600.00 400,200.00
Kawat beton / bindrat 0.7000 kg X Rp. 20,000.00 14,000.00
Kayu meranti balok 0.0270 m3 X Rp. 9,200,000.00 248,400.00
Paku reng 55 x 3,1 mm 0.1200 kg X Rp. - 0.00
Minyak bekisting 0.0900 ltr X Rp. - 0.00
Plamur Fuji 0.2000 kg X Rp. - 0.00
Tukang batu 0.5000 org X Rp. 80,000.00 40,000.00
Kepala tukang 0.0500 org X Rp. 90,000.00 4,500.00
Pekerja 0.8000 org X Rp. 55,000.00 44,000.00
Mandor 0.0400 org X Rp. 80,000.00 3,200.00
JUMLAH 91,700.00 767,862.00 859,562.00

PEKERJAAN PELESTERAN

PPT1 1 M2 Plesteran 1 Sm : 1 Kp : 1 Ps, tebal 15 mm


Semen warna 0.0090 m3 X Rp. - 0.00
Kapur pasang 0.0090 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.0090 m3 X Rp. 120,000.00 1,080.00
Tukang Batu 0.1200 org X Rp. 80,000.00 9,600.00
Kepala Tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.3600 org X Rp. 55,000.00 19,800.00
Mandor 0.0180 org X Rp. 80,000.00 1,440.00
JUMLAH 31,920.00 1,080.00 33,000.00

PPT2 1 M2 Plesteran 1 Sm : 1 Kp : 2 Ps, tebal 15 mm


Semen warna 0.0070 m3 X Rp. - 0.00
Kapur pasang 0.0070 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.0150 m3 X Rp. 120,000.00 1,800.00
Tukang Batu 0.1200 org X Rp. 80,000.00 9,600.00
Kepala Tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.3600 org X Rp. 55,000.00 19,800.00
Mandor 0.0180 org X Rp. 80,000.00 1,440.00
JUMLAH 31,920.00 1,800.00 33,720.00

PPT3 1 m2 Plesteran 1 Pc : 1/2 Kp : 3 Ps, tebal 15 mm


Portland Cement (PC) 5.7600 kg X Rp. 1,375.00 7,920.00
Kapur pasang 0.0030 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.0130 m3 X Rp. 120,000.00 1,560.00
Tukang Batu 0.1200 org X Rp. 80,000.00 9,600.00
Kepala Tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.3600 org X Rp. 55,000.00 19,800.00
Mandor 0.0180 org X Rp. 80,000.00 1,440.00
JUMLAH 31,920.00 9,480.00 41,400.00

PPT4 1 m2 Plesteran 1 Pc : 2 Kp : 8 Ps, tebal 15 mm


Portland Cement (PC) 3.0000 kg X Rp. 1,375.00 4,125.00
Kapur pasang 0.0050 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.0200 m3 X Rp. 120,000.00 2,400.00
Tukang Batu 0.1200 org X Rp. 80,000.00 9,600.00
Kepala Tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.3600 org X Rp. 55,000.00 19,800.00
Mandor 0.0180 org X Rp. 80,000.00 1,440.00
JUMLAH 31,920.00 6,525.00 38,445.00

PPT5 1 m2 Plesteran 1 Pc : 1 Ps, tebal 15 mm


Portland Cement (PC) 15.5040 kg X Rp. 1,375.00 21,318.00
Kapur pasang 0.0160 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.1500 org X Rp. 120,000.00 18,000.00
Kepala Tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 37,050.00 21,318.00 58,368.00

PPT6 1 m2 Plesteran 1 Pc : 2 Ps, tebal 15 mm


Portland Cement (PC) 10.2240 kg X Rp. 1,375.00 14,058.00
Kapur pasang 0.0200 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.1500 org X Rp. 120,000.00 18,000.00
Kepala Tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 37,050.00 14,058.00 51,108.00

PPT7 1 m2 Plesteran 1 Pc : 3 Ps, tebal 15 mm


Portland Cement (PC) 7.7760 kg X Rp. 1,375.00 10,692.00
Pasir pasang ( progo ) 0.0230 m3 X Rp. 120,000.00 2,760.00
Tukang Batu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala Tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 31,050.00 13,452.00 44,502.00

PPT8 1 m2 Plesteran 1 Pc : 4 Ps, tebal 15 mm


Portland Cement (PC) 6.2400 kg X Rp. 1,375.00 8,580.00
Pasir pasang ( progo ) 0.0240 m3 X Rp. 120,000.00 2,880.00
Tukang Batu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala Tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 31,050.00 11,460.00 42,510.00

PPT9 1 m2 Plesteran 1 Pc : 5 Ps, tebal 15 mm


Portland Cement (PC) 5.1840 kg X Rp. 1,375.00 7,128.00
Pasir pasang ( progo ) 0.0260 m3 X Rp. 120,000.00 3,120.00
Tukang Batu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala Tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 31,050.00 10,248.00 41,298.00

PPT10 1 m2 Plesteran 1 Pc : 6 Ps, tebal 15 mm


Portland Cement (PC) 4.4160 kg X Rp. 1,375.00 6,072.00
Pasir pasang ( progo ) 0.0270 m3 X Rp. 120,000.00 3,240.00
Tukang Batu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala Tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 31,050.00 9,312.00 40,362.00

PPT11 1 m2 Plesteran granit 1 Pc : 2 Batu granit, tebal 10 mm


Portland Cement (PC) 10.0000 kg X Rp. 1,375.00 13,750.00
Batu granit 15.0000 kg X Rp. - 0.00
Tukang Batu 0.2250 org X Rp. 80,000.00 18,000.00
Kepala Tukang 0.0225 org X Rp. 90,000.00 2,025.00
Pekerja 0.4500 org X Rp. 55,000.00 24,750.00
Mandor 0.0225 org X Rp. 80,000.00 1,800.00
JUMLAH 46,575.00 13,750.00 60,325.00

PPT12 1 m2 Plesteran traso 1 Pc : 2 Batu traso, tebal 10 mm


Portland Cement (PC) 10.0000 kg X Rp. 1,375.00 13,750.00
Batu granit 15.0000 kg X Rp. - 0.00
Tukang Batu 0.2250 org X Rp. 80,000.00 18,000.00
Kepala Tukang 0.0225 org X Rp. 90,000.00 2,025.00
Pekerja 0.4500 org X Rp. 55,000.00 24,750.00
Mandor 0.0225 org X Rp. 80,000.00 1,800.00
JUMLAH 46,575.00 13,750.00 60,325.00

PPT13 1 m2 Finishing siar pas. Bata merah (=20m')


Portland Cement (PC) 3.1080 kg X Rp. 1,375.00 4,273.50
Tukang Batu 0.0750 org X Rp. 80,000.00 6,000.00
Kepala Tukang 0.0075 org X Rp. 90,000.00 675.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0075 org X Rp. 80,000.00 600.00
JUMLAH 15,525.00 4,273.50 19,798.50

PPT14 1 m2 Finishing siar pas. Batu kali 1 pc : 2 ps


Portland Cement (PC) 6.3400 kg X Rp. 1,375.00 8,717.50
Pasir pasang ( progo ) 0.0120 m3 X Rp. 120,000.00 1,440.00
Tukang Batu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala Tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 31,050.00 10,157.50 41,207.50

PPT15 1 m2 Plesteran Ciprat, 1 Pc : 2 Ps


Portland Cement (PC) 4.3200 kg X Rp. 1,375.00 5,940.00
Pasir pasang ( progo ) 0.0060 m3 X Rp. 120,000.00 720.00
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 6,660.00 33,260.00

PPT16 1 m2 Acian
Portland Cement (PC) 3.2500 kg X Rp. 1,375.00 4,468.75
Tukang Batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 20,700.00 4,468.75 25,168.75

PPT17 1 m2 Plesteran batu kali 1pc:1/2kp:5ps tebal 10 mm


Portland Cement (PC) 5.1000 kg X Rp. 1,375.00 7,012.50
Kapur pasang 0.0014 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.0136 m3 X Rp. 120,000.00 1,632.00
Tukang batu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.4000 org X Rp. 55,000.00 22,000.00
Mandor 0.0200 org X Rp. 80,000.00 1,600.00
JUMLAH 41,400.00 8,644.50 50,044.50

PPT18 1 m2 Plesteran batu kali 1pc:3ps


Portland Cement (PC) 8.1600 kg X Rp. 1,375.00 11,220.00
Pasir pasang ( progo ) 0.0194 m3 X Rp. 120,000.00 2,328.00
Tukang batu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.4000 org X Rp. 55,000.00 22,000.00
Mandor 0.0200 org X Rp. 80,000.00 1,600.00
JUMLAH 41,400.00 13,548.00 54,948.00

PPT19 1 m2 Plesteran batu kali 1pc:4ps


Portland Cement (PC) 6.5110 kg X Rp. 1,375.00 8,952.63
Pasir pasang ( progo ) 0.0209 m3 X Rp. 120,000.00 2,508.00
Tukang batu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.4000 org X Rp. 55,000.00 22,000.00
Mandor 0.0200 org X Rp. 80,000.00 1,600.00
JUMLAH 41,400.00 11,460.63 52,860.63

PEKERJAAN PASANG LANTAI


Pasang ubin granit, teralux dan marmer

PPL1 1 M2 Pasang lantai ubin granit 40/40


Ubin granit uk. 40/40 6.6300 bh X Rp. 72,000.00 477,360.00
Portland Cement (PC) 9.8000 kg X Rp. 1,375.00 13,475.00
Pasir pasang ( progo ) 0.0450 m3 X Rp. 120,000.00 5,400.00
Semen warna 1.3000 kg X Rp. - 0.00
Tukang Batu 0.1250 org X Rp. 80,000.00 10,000.00
Kepala Tukang 0.0125 org X Rp. 90,000.00 1,125.00
Pekerja 0.2500 org X Rp. 55,000.00 13,750.00
Mandor 0.0125 org X Rp. 80,000.00 1,000.00
JUMLAH 25,875.00 496,235.00 522,110.00

PPL2 1 M2 Pasang lantai ubin granit 30/30


Ubin granit uk. 30/30 11.8700 bh X Rp. 66,000.00 783,420.00
Portland Cement (PC) 10.0000 kg X Rp. 1,375.00 13,750.00
Pasir pasang ( progo ) 0.0450 m3 X Rp. 120,000.00 5,400.00
Semen warna 1.5000 kg X Rp. - 0.00
Tukang Batu 0.1300 org X Rp. 80,000.00 10,400.00
Kepala Tukang 0.0130 org X Rp. 90,000.00 1,170.00
Pekerja 0.2600 org X Rp. 55,000.00 14,300.00
Mandor 0.0130 org X Rp. 80,000.00 1,040.00
JUMLAH 26,910.00 802,570.00 829,480.00

Pasang plint tegel dan teraso

PPL3 1 M' Pasang plint ubin PC abu-abu ukuran 15 x 20 cm


Plint tegel abu-abu 15/20 5.3000 bh X Rp. - 0.00
Portland Cement (PC) 1.6500 kg X Rp. 1,375.00 2,268.75
Pasir pasang ( progo ) 0.0040 m3 X Rp. 120,000.00 480.00
Tukang Batu 0.0900 org X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0900 org X Rp. 55,000.00 4,950.00
Mandor 0.0045 org X Rp. 80,000.00 360.00
JUMLAH 13,320.00 2,748.75 16,068.75

PPL4 1 M' Pasang plint ubin PC abu-abu ukuran 10 x 30 cm


Plint tegel abu-abu 10/30 3.5300 bh X Rp. - 0.00
Portland Cement (PC) 1.2400 kg X Rp. 1,375.00 1,705.00
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Tukang Batu 0.0900 org X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0900 org X Rp. 55,000.00 4,950.00
Mandor 0.0045 org X Rp. 80,000.00 360.00
JUMLAH 13,320.00 2,065.00 15,385.00

PPL5 1 M' Pasang plint ubin PC abu-abu ukuran 10 x 40 cm


Plint tegel abu-abu 10/40 2.6500 bh X Rp. - 0.00
Portland Cement (PC) 1.2400 kg X Rp. 1,375.00 1,705.00
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Tukang Batu 0.0900 org X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0900 org X Rp. 55,000.00 4,950.00
Mandor 0.0045 org X Rp. 80,000.00 360.00
JUMLAH 13,320.00 2,065.00 15,385.00

PPL6 1 M' Pasang plint ubin PC warna ukuran 10 x 20 cm


Plint tegel warna 10/20 5.3000 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.1000 kg X Rp. - 0.00
Tukang Batu 0.0900 org X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0900 org X Rp. 55,000.00 4,950.00
Mandor 0.0045 org X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

PPL7 1 M' Pasang plint ubin PC warna ukuran 10 x 30 cm


Plint tegel warna 10/30 3.5300 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.1000 kg X Rp. - 0.00
Tukang Batu 0.0900 oh X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 oh X Rp. 90,000.00 810.00
Pekerja 0.0900 oh X Rp. 55,000.00 4,950.00
Mandor 0.0045 oh X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

PPL8 1 M' Pasang plint ubin PC warna ukuran 10 x 40 cm


Plint tegel warna 10/40 2.6500 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.1000 kg X Rp. - 0.00
Tukang Batu 0.0900 oh X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 oh X Rp. 90,000.00 810.00
Pekerja 0.0900 oh X Rp. 55,000.00 4,950.00
Mandor 0.0045 oh X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

PPL9 1 M' Pasang plint ubin traso ukuran 10 x 30 cm


Plint ubin teraso 10/30 3.5300 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.1000 kg X Rp. - 0.00
Tukang Batu 0.0900 oh X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 oh X Rp. 90,000.00 810.00
Pekerja 0.0900 oh X Rp. 55,000.00 4,950.00
Mandor 0.0045 oh X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

PPL10 1 M' Pasang plint ubin traso ukuran 10 x 40 cm


Plint ubin teraso 10/40 2.6500 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.1000 kg X Rp. - 0.00
Tukang Batu 0.0900 oh X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 oh X Rp. 90,000.00 810.00
Pekerja 0.0900 oh X Rp. 55,000.00 4,950.00
Mandor 0.0045 oh X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

Pasang plint ubin dan marmer

PPL11 1 M' Pasang plint ubin granit ukuran 10 x 30 cm


Plint ubin granit 10/30 3.5300 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.1000 kg X Rp. - 0.00
Tukang Batu 0.0900 oh X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 oh X Rp. 90,000.00 810.00
Pekerja 0.0900 oh X Rp. 55,000.00 4,950.00
Mandor 0.0045 oh X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

PPL12 1 M' Pasang plint ubin granit ukuran 10 x 40 cm


Plint ubin granit 10/40 2.6500 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.1000 kg X Rp. - 0.00
Tukang Batu 0.0900 oh X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 oh X Rp. 90,000.00 810.00
Pekerja 0.0900 oh X Rp. 55,000.00 4,950.00
Mandor 0.0045 oh X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

PPL13 1 m' Pasang plint ubin teralux marmer ukuran 10 x 60 cm


Plint ubin teralux marmer 10/60 1.7000 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.1000 kg X Rp. - 0.00
Tukang Batu 0.0900 oh X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 oh X Rp. 90,000.00 810.00
Pekerja 0.0900 oh X Rp. 55,000.00 4,950.00
Mandor 0.0045 oh X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

PPL14 1 m' Pasang plint ubin teralux marmer ukuran 10 x 40 cm


Plint ubin teralux marmer 10/40 2.6500 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.1000 kg X Rp. - 0.00
Tukang Batu 0.0900 oh X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 oh X Rp. 90,000.00 810.00
Pekerja 0.0900 oh X Rp. 55,000.00 4,950.00
Mandor 0.0045 oh X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

PPL15 1 m' Pasang plint ubin teralux marmer ukuran 10 x 30 cm


Plint ubin teralux marmer 10/30 3.5300 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.1000 kg X Rp. - 0.00
Tukang Batu 0.0900 oh X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 oh X Rp. 90,000.00 810.00
Pekerja 0.0900 oh X Rp. 55,000.00 4,950.00
Mandor 0.0045 oh X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

PPL16 1 m' Pasang lantai teraso cor ditempat tebal 3 cm


Bahan teraso cor 0.0360 m3 X Rp. - 0.00
Tukang Batu 0.1800 oh X Rp. 80,000.00 14,400.00
Kepala Tukang 0.0180 oh X Rp. 90,000.00 1,620.00
Pekerja 0.3600 oh X Rp. 55,000.00 19,800.00
Mandor 0.0180 oh X Rp. 80,000.00 1,440.00
JUMLAH 37,260.00 0.00 37,260.00

PEKERJAAN KERAMIK

PPL17 1 m2 Pasang lantai keramik artistik uk. 10 x 20 cm


Ubin keramik artistik 53.0000 bh X Rp. - 0.00
Portland Cement (PC) 8.1900 kg X Rp. 1,375.00 11,261.25
Pasir pasang ( progo ) 0.0450 m3 X Rp. 120,000.00 5,400.00
Semen warna 2.7500 kg X Rp. - 0.00
Tukang Batu 0.3500 org X Rp. 80,000.00 28,000.00
Kepala Tukang 0.0350 org X Rp. 90,000.00 3,150.00
Pekerja 0.7000 org X Rp. 55,000.00 38,500.00
Mandor 0.0350 org X Rp. 80,000.00 2,800.00
JUMLAH 72,450.00 16,661.25 89,111.25

PPL18 1 m2 Pasang lantai keramik artistik uk. 10 x 10 cm atau 5 x 20 cm


Ubin keramik artistik 106.0000 bh X Rp. - 0.00
Portland Cement (PC) 8.1900 kg X Rp. 1,375.00 11,261.25
Pasir pasang ( progo ) 0.0450 m3 X Rp. 120,000.00 5,400.00
Semen warna 3.2000 kg X Rp. - 0.00
Tukang Batu 0.3500 org X Rp. 80,000.00 28,000.00
Kepala Tukang 0.0350 org X Rp. 90,000.00 3,150.00
Pekerja 0.7000 org X Rp. 55,000.00 38,500.00
Mandor 0.0350 org X Rp. 80,000.00 2,800.00
JUMLAH 72,450.00 16,661.25 89,111.25

PPL19 1 m2 Pasang ubin porselin uk. 11 x 11 cm


Tegel porselin 86.0000 bh X Rp. - 0.00
Portland Cement (PC) 9.3000 kg X Rp. 1,375.00 12,787.50
Pasir pasang ( progo ) 0.0180 m3 X Rp. 120,000.00 2,160.00
Semen warna 1.5000 kg X Rp. - 0.00
Tukang Batu 0.5000 org X Rp. 80,000.00 40,000.00
Kepala Tukang 0.0500 org X Rp. 90,000.00 4,500.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0500 org X Rp. 80,000.00 4,000.00
JUMLAH 54,000.00 14,947.50 68,947.50

PPL20 1 m2 Pasang ubin porselin uk. 10 x 20 cm


Tegel porselin 53.0000 bh X Rp. - 0.00
Portland Cement (PC) 9.3000 kg X Rp. 1,375.00 12,787.50
Pasir pasang ( progo ) 0.0180 m3 X Rp. 120,000.00 2,160.00
Semen warna 2.7500 kg X Rp. - 0.00
Tukang Batu 0.4500 org X Rp. 80,000.00 36,000.00
Kepala Tukang 0.0450 org X Rp. 90,000.00 4,050.00
Pekerja 0.9000 org X Rp. 55,000.00 49,500.00
Mandor 0.0450 org X Rp. 80,000.00 3,600.00
JUMLAH 93,150.00 14,947.50 108,097.50

PPL21 1 m2 Pasang ubin porselin uk. 20 x 20 cm


Tegel porselin 26.5000 bh X Rp. - 0.00
Portland Cement (PC) 9.3000 kg X Rp. 1,375.00 12,787.50
Pasir pasang ( progo ) 0.0180 m3 X Rp. 120,000.00 2,160.00
Pasir pasang ( progo ) 1.9400 kg X Rp. 120,000.00 232,800.00
Tukang Batu 0.4500 org X Rp. 80,000.00 36,000.00
Kepala Tukang 0.0450 org X Rp. 90,000.00 4,050.00
Pekerja 0.9000 org X Rp. 55,000.00 49,500.00
Mandor 0.0450 org X Rp. 80,000.00 3,600.00
JUMLAH 93,150.00 247,747.50 340,897.50

PPL22 1 m2 Pasang tegel keramik uk. 33/33


Tegel keramik 30/30 berglasir 10.0000 bh X Rp. - 0.00
Portland Cement (PC) 8.1900 kg X Rp. 1,375.00 11,261.25
Pasir pasang ( progo ) 0.0450 m3 X Rp. 120,000.00 5,400.00
Semen warna 1.6200 kg X Rp. - 0.00
Tukang Batu 0.3500 org X Rp. 80,000.00 28,000.00
Kepala Tukang 0.0350 org X Rp. 90,000.00 3,150.00
Pekerja 0.7000 org X Rp. 55,000.00 38,500.00
Mandor 0.0350 org X Rp. 80,000.00 2,800.00
JUMLAH 72,450.00 16,661.25 89,111.25

PPL23 1 m2 Pasang tegel keramik uk. 30/30


Tegel keramik 30/30 berglasir 11.8700 bh X Rp. - 0.00
Portland Cement (PC) 10.0000 kg X Rp. 1,375.00 13,750.00
Pasir pasang ( progo ) 0.0450 m3 X Rp. 120,000.00 5,400.00
Semen warna 1.5000 kg X Rp. - 0.00
Tukang Batu 0.3500 org X Rp. 80,000.00 28,000.00
Kepala Tukang 0.0350 org X Rp. 90,000.00 3,150.00
Pekerja 0.7000 org X Rp. 55,000.00 38,500.00
Mandor 0.0350 org X Rp. 80,000.00 2,800.00
JUMLAH 72,450.00 19,150.00 91,600.00

PPL24 1 m2 Pasang tegel keramik uk. 20/20


Tegel keramik 20/20 berglasir 26.5000 bh X Rp. - 0.00
Portland Cement (PC) 10.4000 kg X Rp. 1,375.00 14,300.00
Pasir pasang ( progo ) 0.0450 m3 X Rp. 120,000.00 5,400.00
Semen warna 1.6200 kg X Rp. - 0.00
Tukang Batu 0.3500 org X Rp. 80,000.00 28,000.00
Kepala Tukang 0.0350 org X Rp. 90,000.00 3,150.00
Pekerja 0.7000 org X Rp. 55,000.00 38,500.00
Mandor 0.0350 org X Rp. 80,000.00 2,800.00
JUMLAH 72,450.00 19,700.00 92,150.00

PPL25 1 m2 Pasang tegel keramik uk. 10 x 33 cm (variasi/border)


Tegel keramik 10/30 berglasir 33.0000 bh X Rp. - 0.00
Portland Cement (PC) 9.8000 kg X Rp. 1,375.00 13,475.00
Pasir pasang ( progo ) 0.0450 m3 X Rp. 120,000.00 5,400.00
Semen warna 4.3700 kg X Rp. - 0.00
Tukang Batu 0.5250 org X Rp. 80,000.00 42,000.00
Kepala Tukang 0.0525 org X Rp. 90,000.00 4,725.00
Pekerja 1.0500 org X Rp. 55,000.00 57,750.00
Mandor 0.0525 org X Rp. 80,000.00 4,200.00
JUMLAH 108,675.00 18,875.00 127,550.00

PPL26 Pasang lantai mozaik uk. 30 x 30 cm, camp. 1pc : 3ps


Tegel keramik 30/30 berglasir 11.8700 bh X Rp. - 0.00
Portland Cement (PC) 14.1500 kg X Rp. 1,375.00 19,456.25
Pasir pasang ( progo ) 0.0390 m3 X Rp. 120,000.00 4,680.00
Semen warna 2.0000 kg X Rp. - 0.00
Tukang Batu 0.3500 org X Rp. 80,000.00 28,000.00
Kepala Tukang 0.0350 org X Rp. 90,000.00 3,150.00
Pekerja 0.7000 org X Rp. 55,000.00 38,500.00
Mandor 0.0350 org X Rp. 80,000.00 2,800.00
JUMLAH 72,450.00 24,136.25 96,586.25

PPL27 1 m' Pasang plint keramik ukuran 10 x 30 cm


Plint keramik artistik 5.3000 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.0250 kg X Rp. - 0.00
Tukang Batu 0.0900 org X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0900 org X Rp. 55,000.00 4,950.00
Mandor 0.0045 org X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

PPL28 1 m' Pasang plint keramik ukuran 10 x 40 cm


Plint keramik artistik 10.6000 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.0500 kg X Rp. - 0.00
Tukang Batu 0.0900 org X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0900 org X Rp. 55,000.00 4,950.00
Mandor 0.0045 org X Rp. 80,000.00 360.00
JUMLAH 13,320.00 1,927.50 15,247.50

PPL29 1 m' Pasang plint keramik 5 x 20 cm


Plint keramik artistik 5.3000 bh X Rp. - 0.00
Portland Cement (PC) 0.5700 kg X Rp. 1,375.00 783.75
Pasir pasang ( progo ) 0.0015 m3 X Rp. 120,000.00 180.00
Semen warna 0.0130 kg X Rp. - 0.00
Tukang Batu 0.0900 org X Rp. 80,000.00 7,200.00
Kepala Tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0900 org X Rp. 55,000.00 4,950.00
Mandor 0.0045 org X Rp. 80,000.00 360.00
JUMLAH 13,320.00 963.75 14,283.75

PPL30 1 m' Pasang plint internal cove artistik 5 x 5 x 20 cm


Internal cove 5.3000 bh X Rp. - 0.00
Portland Cement (PC) 1.1400 kg X Rp. 1,375.00 1,567.50
Pasir pasang ( progo ) 0.0030 m3 X Rp. 120,000.00 360.00
Semen warna 0.1000 kg X Rp. - 0.00
Tukang Batu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala Tukang 0.0750 org X Rp. 90,000.00 6,750.00
Pekerja 0.7500 org X Rp. 55,000.00 41,250.00
Mandor 0.0375 org X Rp. 80,000.00 3,000.00
JUMLAH 111,000.00 1,927.50 112,927.50

PPL31 1 m' Pasang lantai marmer uk. 100 x 100 cm


Marmer 1.0600 bh X Rp. - 0.00
Portland Cement (PC) 8.1900 kg X Rp. 1,375.00 11,261.25
Pasir pasang ( progo ) 0.0450 m3 X Rp. 120,000.00 5,400.00
Semen warna 0.6500 kg X Rp. - 0.00
Tukang Batu 0.3500 org X Rp. 80,000.00 28,000.00
Kepala Tukang 0.0350 org X Rp. 90,000.00 3,150.00
Pekerja 0.7000 org X Rp. 55,000.00 38,500.00
Mandor 0.0350 org X Rp. 80,000.00 2,800.00
JUMLAH 72,450.00 16,661.25 89,111.25

PPL32 1 m2 Pasang lantai karpet


Karpet 1.0500 m2 X Rp. - 0.00
Lem Aica Aibon 0.3500 kg X Rp. - 0.00
Tukang Kayu 0.1700 org X Rp. 80,000.00 13,600.00
Kepala Tukang 0.0170 org X Rp. 90,000.00 1,530.00
Pekerja 0.1700 org X Rp. 55,000.00 9,350.00
Mandor 0.0085 org X Rp. 80,000.00 680.00
JUMLAH 25,160.00 0.00 25,160.00

PPL33 1 m2 Pasang keramik dinding artistik 10 x 20 cm


Tegel keramik 20/20 berglasir 53.0000 bh X Rp. - 0.00
Portland Cement (PC) 9.3000 kg X Rp. 1,375.00 12,787.50
Pasir pasang ( progo ) 0.0180 m3 X Rp. 120,000.00 2,160.00
Semen warna 2.7500 kg X Rp. - 0.00
Tukang Batu 0.4500 org X Rp. 80,000.00 36,000.00
Kepala Tukang 0.0450 org X Rp. 90,000.00 4,050.00
Pekerja 0.9000 org X Rp. 55,000.00 49,500.00
Mandor 0.0450 org X Rp. 80,000.00 3,600.00
JUMLAH 93,150.00 14,947.50 108,097.50

PPL34 1 m2 Pasang keramik dinding artistik 5 x 20 cm


Tegel keramik 5/20 berglasir 106.0000 bh X Rp. - 0.00
Portland Cement (PC) 9.3000 kg X Rp. 1,375.00 12,787.50
Pasir pasang ( progo ) 0.0180 m3 X Rp. 120,000.00 2,160.00
Semen warna 2.7500 kg X Rp. - 0.00
Tukang Batu 0.4500 org X Rp. 80,000.00 36,000.00
Kepala Tukang 0.0450 org X Rp. 90,000.00 4,050.00
Pekerja 0.9000 org X Rp. 55,000.00 49,500.00
Mandor 0.0450 org X Rp. 80,000.00 3,600.00
JUMLAH 93,150.00 14,947.50 108,097.50

PPL35 1 m2 Pasang keramik dinding 10 x 20 cm


Tegel keramik 10/20 berglasir 53.0000 bh X Rp. - 0.00
Portland Cement (PC) 9.3000 kg X Rp. 1,375.00 12,787.50
Pasir pasang ( progo ) 0.0180 m3 X Rp. 120,000.00 2,160.00
Semen warna 2.7500 kg X Rp. - 0.00
Tukang Batu 0.4500 org X Rp. 80,000.00 36,000.00
Kepala Tukang 0.0450 org X Rp. 90,000.00 4,050.00
Pekerja 0.9000 org X Rp. 55,000.00 49,500.00
Mandor 0.0450 org X Rp. 80,000.00 3,600.00
JUMLAH 93,150.00 14,947.50 108,097.50

PPL36 1 m2 Pasang keramik dinding 20 x 20 cm


Tegel keramik 20/20 berglasir 26.5000 bh X Rp. - 0.00
Portland Cement (PC) 9.3000 kg X Rp. 1,375.00 12,787.50
Pasir pasang ( progo ) 0.0180 m3 X Rp. 120,000.00 2,160.00
Semen warna 1.9400 kg X Rp. - 0.00
Tukang Batu 0.4500 org X Rp. 80,000.00 36,000.00
Kepala Tukang 0.0450 org X Rp. 90,000.00 4,050.00
Pekerja 0.9000 org X Rp. 55,000.00 49,500.00
Mandor 0.0450 org X Rp. 80,000.00 3,600.00
JUMLAH 93,150.00 14,947.50 108,097.50

PPL37 1 m2 Pasang keramik dinding 20/25


Tegel keramik 20/20 berglasir 1.0000 m2 X Rp. - 0.00
Portland Cement (PC) 9.3000 kg X Rp. 1,375.00 12,787.50
Pasir pasang ( progo ) 0.0180 m3 X Rp. 120,000.00 2,160.00
Semen putih 1.5000 kg X Rp. 1,875.00 2,812.50
Tukang batu 0.6500 org X Rp. 80,000.00 52,000.00
Kepala Tukang 0.0650 org X Rp. 90,000.00 5,850.00
Pekerja 0.3200 org X Rp. 55,000.00 17,600.00
Mandor 0.0160 org X Rp. 80,000.00 1,280.00
JUMLAH 76,730.00 17,760.00 94,490.00

PPL38 1 m' Pasang keramik stepnosing granito 5/30


Stepnosing granito 3.6000 bh X Rp. - 0.00
Portland Cement (PC) 0.4080 kg X Rp. 1,375.00 561.00
Pasir pasang ( progo ) 0.0009 m3 X Rp. 120,000.00 108.00
Semen warna 0.0600 kg X Rp. - 0.00
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.0500 org X Rp. 55,000.00 2,750.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 11,850.00 669.00 12,519.00

PPL39 1 m2 Pasang dinding marmer uk. 100 x 100 cm


Marmer 1.0600 m2 X Rp. - 0.00
Paku biasa 3.0030 kg X Rp. 16,300.00 48,948.90
Portland Cement (PC) 12.4400 kg X Rp. 1,375.00 17,105.00
Pasir pasang ( progo ) 0.0250 m3 X Rp. 120,000.00 3,000.00
Semen warna 0.6500 kg X Rp. - 0.00
Tukang Batu 0.6500 org X Rp. 80,000.00 52,000.00
Kepala Tukang 0.0650 org X Rp. 90,000.00 5,850.00
Pekerja 1.3000 org X Rp. 55,000.00 71,500.00
Mandor 0.0650 org X Rp. 80,000.00 5,200.00
JUMLAH 134,550.00 69,053.90 203,603.90

PPL40 1 m2 Pasang lantai vinyl uk. 30 x 30 cm kls 1


Vinyl 11.8700 bh X Rp. - 0.00
Lem plastik Vinyl 0.3500 kg X Rp. - 0.00
Tukang Kayu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala Tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0075 org X Rp. 80,000.00 600.00
JUMLAH 22,200.00 0.00 22,200.00

PPL41 1 m2 Pasang wallpaper lebar 50 cm


Wall paper 2.2000 m2 X Rp. - 0.00
Lem Aica Aibon 0.2500 kg X Rp. - 0.00
Tukang Kayu 0.1750 org X Rp. 80,000.00 14,000.00
Kepala Tukang 0.0170 org X Rp. 90,000.00 1,530.00
Pekerja 0.3500 org X Rp. 55,000.00 19,250.00
Mandor 0.0018 org X Rp. 80,000.00 140.00
JUMLAH 34,920.00 0.00 34,920.00

PPL42 1 m2 Pasang floor hardener


Floor hardener 5.0000 kg X Rp. - 0.00
Tukang Kayu 0.1200 org X Rp. 80,000.00 9,600.00
Kepala Tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.1200 org X Rp. 55,000.00 6,600.00
Mandor 0.0060 org X Rp. 80,000.00 480.00
JUMLAH 17,760.00 0.00 17,760.00

PPL43 1 m' Pasang plint vinyl karet uk. 15 x 30 cm dengan perekat


Vinyl 1.7600 bh X Rp. - 0.00
Lem plastik Vinyl 0.0800 kg X Rp. - 0.00
Tukang Kayu 0.0800 org X Rp. 80,000.00 6,400.00
Kepala Tukang 0.0080 org X Rp. 90,000.00 720.00
Pekerja 0.0800 org X Rp. 55,000.00 4,400.00
Mandor 0.0040 org X Rp. 80,000.00 320.00
JUMLAH 11,840.00 0.00 11,840.00

PPL44 1 m' Pasang plint kayu klas II tebal 2cm, lebar 10cm
Papan kayu damar laut 0.0030 m3 X Rp. - 0.00
Paku skrup 0.0500 kg X Rp. - 0.00
Tukang Kayu 0.1200 org X Rp. 80,000.00 9,600.00
Kepala Tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.1200 org X Rp. 55,000.00 6,600.00
Mandor 0.0060 org X Rp. 80,000.00 480.00
JUMLAH 17,760.00 0.00 17,760.00

PEKERJAAN CONBLOCK/PAVING BLOCK

PCB1 1 m2 Pasang conblock tipe segi-empat, uni, segi-enam abu-abu 8 cm, K-400
Tipe segi empat, uni, segi 6 tebal = 8 cm K 400 1.0000 m2 X Rp. - 0.00
Pasir urug darat 0.0500 m3 X Rp. 94,500.00 4,725.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala Tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 51,750.00 4,725.00 56,475.00

PCB2 1 m2 Pasang conblock tipe segi-empat abu-abu 8 cm, K-200


Tipe segi empat tebal = 8 cm K 200 1.0000 m2 X Rp. - 0.00
Pasir urug darat 0.0500 m3 X Rp. 94,500.00 4,725.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala Tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 51,750.00 4,725.00 56,475.00

PCB3 1 m2 Pasang conblock tipe segi-empat, uni, segi-enam warna 8 cm, K-400
Tipe segi empat, uni, segi 6 tebal = 8 cm K 400 1.0000 m2 X Rp. - 0.00
Pasir urug darat 0.0500 m3 X Rp. 94,500.00 4,725.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala Tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 51,750.00 4,725.00 56,475.00

PCB4 1 m2 Pasang conblock tipe segi-empat warna 8 cm, K-200


Tipe segi enam tebal = 8 cm K 200 1.0000 m2 X Rp. - 0.00
Pasir urug darat 0.0500 m3 X Rp. 94,500.00 4,725.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala Tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 51,750.00 4,725.00 56,475.00

PCB5 1 m2 Pasang grassblock bulat tebal 10 cm


Tipe grass blok bulat tebal = 10 cm 1.0000 m2 X Rp. - 0.00
Pasir urug darat 0.0500 m3 X Rp. 94,500.00 4,725.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala Tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 51,750.00 4,725.00 56,475.00

PCB6 1 m2 Pasang grassblock tebal 10 cm


Tipe grass blok bulat tebal = 10 cm 1.0000 m2 X Rp. - 0.00
Pasir urug darat 0.0500 m3 X Rp. 94,500.00 4,725.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala Tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 51,750.00 4,725.00 56,475.00

PCB7 3 m3 Bronjong kawat galvanis


Penganyaman A
Kawat galvanis 70.0000 kg X Rp. - 0.00
Pekerja 2.0000 org X Rp. 55,000.00 110,000.00
Mandor 0.0800 org X Rp. 80,000.00 6,400.00
Pengisian B
Batu kali 3.0000 m3
Pekerja 4.5000 org X Rp. 55,000.00 247,500.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 369,900.00 0.00 369,900.00

PCB8 1 bh Pasang buis beton dia. 80 cm


Buis beton bulat dia. 80 cm P=0,5 m 1.0000 bh X Rp. - 0.00
Tukang batu 0.1250 org X Rp. 80,000.00 10,000.00
Kepala Tukang 0.0125 org X Rp. 90,000.00 1,125.00
Pekerja 0.2500 org X Rp. 55,000.00 13,750.00
JUMLAH 24,875.00 0.00 24,875.00

PCB9 1 m3 Langsiran batu kali


Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0200 org X Rp. 80,000.00 1,600.00
Gerobak (sewa) 1.0000 hr X Rp. - 0.00
JUMLAH 12,600.00 0.00 12,600.00

PCB10 1 m3 Langsiran kerikil


Pekerja 0.1200 org X Rp. 55,000.00 6,600.00
Mandor 0.0120 org X Rp. 80,000.00 960.00
Gerobak (sewa) 1.0000 hr X Rp. - 0.00
JUMLAH 7,560.00 0.00 7,560.00

PCB11 1 m3 Langsiran pasir


Pekerja 0.0500 org X Rp. 55,000.00 2,750.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
Gerobak (sewa) 1.0000 hr X Rp. - 0.00
JUMLAH 3,150.00 0.00 3,150.00

PEKERJAAN KAYU

Pasang kuda-kuda konvensional

PKY1 1 m3 Pasang konstruksi kuda-kuda konvensional


Kayu meranti balok 1.1000 m3 X Rp. 9,200,000.00 10,120,000.00
Besi strip 15.0000 kg X Rp. 13,300.00 199,500.00
Paku biasa 5.6000 kg X Rp. 16,300.00 91,280.00
Tukang Kayu 12.0000 org X Rp. 80,000.00 960,000.00
Kepala Tukang 1.2000 org X Rp. 90,000.00 108,000.00
Pekerja 4.0000 org X Rp. 55,000.00 220,000.00
Mandor 0.2000 org X Rp. 80,000.00 16,000.00
JUMLAH 1,304,000.00 10,410,780.00 11,714,780.00

Pasang gording

PKY2 1 m3 Pasang gording Kayu meranti


Kayu meranti balok 1.1000 m3 X Rp. 9,200,000.00 10,120,000.00
Besi strip 15.0000 kg X Rp. 13,300.00 199,500.00
Paku biasa 3.0000 kg X Rp. 16,300.00 48,900.00
Tukang Kayu 7.2000 org X Rp. 80,000.00 576,000.00
Kepala Tukang 0.7200 org X Rp. 90,000.00 64,800.00
Pekerja 2.4000 org X Rp. 55,000.00 132,000.00
Mandor 0.1200 org X Rp. 80,000.00 9,600.00
JUMLAH 782,400.00 10,368,400.00 11,150,800.00

Pasang usuk dan reng untuk genteng keramik

PKY3 1 m2 Pasang usuk 5/7 Kayu meranti, reng 2/3 Kayu damar laut
Kayu meranti balok 0.0140 m3 X Rp. 9,200,000.00 128,800.00
Damar Laut (Kelas I) 0.0036 m3 X Rp. 15,625,000.00 56,250.00
Paku biasa 1/2" - 1" 0.1500 kg X Rp. 16,300.00 2,445.00
Paku reng 55 x 3,1 mm 0.1000 kg X Rp. - 0.00
Tukang Kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 187,495.00 202,295.00

Pasang usuk dan reng untuk genteng beton

PKY4 1 m2 Pasang usuk 5/7 Kayu meranti, reng 2/3 Kayu damar laut
Kayu meranti balok 0.0140 m3 X Rp. 9,200,000.00 128,800.00
Damar Laut (Kelas I) 0.0072 m3 X Rp. 15,625,000.00 112,500.00
Paku usuk 80 x 3,8 mm 0.1500 kg X Rp. - 0.00
Paku reng 55 x 3,1 mm 0.1000 kg X Rp. - 0.00
Tukang Kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 241,300.00 256,100.00

PKY5 1 m2 Pasang rangka atap sirap


Kayu meranti balok 0.1650 m3 X Rp. 9,200,000.00 1,518,000.00
Paku usuk 80 x 3,8 mm 0.2000 kg X Rp. - 0.00
Tukang Kayu 0.1200 org X Rp. 80,000.00 9,600.00
Kepala Tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.1200 org X Rp. 55,000.00 6,600.00
Mandor 0.0060 org X Rp. 80,000.00 480.00
JUMLAH 17,760.00 1,518,000.00 1,535,760.00

Rangka langit-langit

PKY6 1 m2 Pasang rangka langit-langit (50 x 100) cm, Kayu jati


Kayu meranti balok 0.0154 m3 X Rp. 9,200,000.00 141,680.00
Paku usuk 80 x 3,8 mm 0.2000 kg X Rp. - 0.00
Tukang Kayu 0.3000 org X Rp. 80,000.00 24,000.00
Kepala Tukang 0.0300 org X Rp. 90,000.00 2,700.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0750 org X Rp. 80,000.00 6,000.00
JUMLAH 40,950.00 141,680.00 182,630.00

Pasang Listplank

PKY7 1 m' Pasang lisplank ukuran (3 x 20) cm


Kayu meranti papan 0.0108 m3 X Rp. 9,200,000.00 99,360.00
Paku biasa 0.1000 kg X Rp. 16,300.00 1,630.00
Tukang Kayu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 23,700.00 100,990.00 124,690.00

PKY8 1 m' Pasang lisplank ukuran (3 x 30) cm


Kayu meranti papan 0.0110 m3 X Rp. 9,200,000.00 101,200.00
Paku biasa 0.0500 kg X Rp. 16,300.00 815.00
Tukang Kayu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 23,700.00 102,015.00 125,715.00

PKY9 1 m' Pasang lisplank ukuran (2 x 20) cm


Kayu meranti papan 0.0048 m3 X Rp. 9,200,000.00 44,160.00
Paku biasa 0.0600 kg X Rp. 16,300.00 978.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 45,138.00 59,938.00

PKY10 1 m' Pasang lisplank ukuran (2 x 25) cm


Kayu meranti papan 0.0060 m3 X Rp. 9,200,000.00 55,200.00
Paku biasa 0.0600 kg X Rp. 16,300.00 978.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 56,178.00 70,978.00

PKY11 1 m' Pasang lisplank ukuran 2 x (3 x 20) cm


Kayu meranti papan 0.0145 m3 X Rp. 9,200,000.00 133,400.00
Paku biasa 0.0600 kg X Rp. 16,300.00 978.00
Tukang kayu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0075 org X Rp. 80,000.00 600.00
JUMLAH 31,100.00 134,378.00 165,478.00

PKY12 1 m' Pasang lisplank ukuran 2 x (2 x 20) cm


Kayu meranti papan 0.0086 m3 X Rp. 9,200,000.00 79,120.00
Paku biasa 0.0600 kg X Rp. 16,300.00 978.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 80,098.00 94,898.00

Pasang papan ruiter

1 m' Mengerjakan papan ruiter


PKY13 Kayu meranti papan 0.0040 m3 X Rp. 9,200,000.00 36,800.00
Paku biasa 0.0200 kg X Rp. 16,300.00 326.00
Tukang kayu 0.0800 org X Rp. 80,000.00 6,400.00
Kepala tukang 0.0080 org X Rp. 90,000.00 720.00
Pekerja 0.0280 org X Rp. 55,000.00 1,540.00
Mandor 0.0014 org X Rp. 80,000.00 112.00
JUMLAH 8,772.00 37,126.00 45,898.00

PKY14 1 m2 Pasang rangka dinding pemisah ukuran (60 x 120) cm


Kayu meranti balok 0.0280 m3 X Rp. 9,200,000.00 257,600.00
Paku biasa 0.1500 kg X Rp. 16,300.00 2,445.00
Tukang Kayu 0.4500 org X Rp. 80,000.00 36,000.00
Kepala Tukang 0.0450 org X Rp. 90,000.00 4,050.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0075 org X Rp. 80,000.00 600.00
JUMLAH 48,900.00 260,045.00 308,945.00

PKY15 1 m2 Pasang dinding pemisah teakwood rangkap


Kayu meranti balok 0.0280 m3 X Rp. 9,200,000.00 257,600.00
Teak wood ( 90 x 240 ) 0.8600 lbr X Rp. - 0.00
Lem kayu (putih) Fox 0.5600 kg X Rp. - 0.00
Paku biasa 0.1500 kg X Rp. 16,300.00 2,445.00
Tukang Kayu 0.4500 org X Rp. 80,000.00 36,000.00
Kepala Tukang 0.0450 org X Rp. 90,000.00 4,050.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0075 org X Rp. 80,000.00 600.00
JUMLAH 48,900.00 260,045.00 308,945.00

PKY16 1 m2 Pasang dinding pemisah plywood rangkap


Kayu meranti balok 0.0280 m3 X Rp. 0.00
Plywood 4 mm 0.8600 lbr X Rp. - 0.00
Lem kayu (putih) Fox 0.5600 kg X Rp. - 0.00
Paku biasa 0.1500 kg X Rp. 16,300.00 2,445.00
Tukang Kayu 0.6000 org X Rp. 80,000.00 48,000.00
Kepala Tukang 0.0600 org X Rp. 90,000.00 5,400.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 65,200.00 2,445.00 67,645.00

PKY17 1 m2 Pasang dinding lambiziring


Kayu meranti papan 0.0070 m3 X Rp. 9,200,000.00 64,400.00
Paku biasa 0.1000 kg X Rp. 16,300.00 1,630.00
Paku sekrup 3.5" 0.1500 kg X Rp. - 0.00
Tukang Kayu 1.8000 org X Rp. 80,000.00 144,000.00
Kepala Tukang 0.1800 org X Rp. 90,000.00 16,200.00
Pekerja 0.6000 org X Rp. 55,000.00 33,000.00
Mandor 0.0300 org X Rp. 80,000.00 2,400.00
JUMLAH 195,600.00 66,030.00 261,630.00

PKY18 1 m2 Pasang dinding bilik bambu, rangka kayu klas III, IV


Bambu petung 1.5000 m2 X Rp. - 0.00
Damar Laut (Kelas I) 0.0140 m3 X Rp. 15,625,000.00 218,750.00
List kayu profil 0.0120 kg X Rp. - 0.00
Paku biasa 0.0030 m3 X Rp. 16,300.00 48.90
Tukang Kayu 0.0500 org X Rp. 80,000.00 4,000.00
Kepala Tukang 0.0050 org X Rp. 90,000.00 450.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 10,350.00 218,798.90 229,148.90

PKY19 1 m3 Membuat dan memasang kusen pintu / jendela


Kayu meranti balok 1.1000 m3 X Rp. 9,200,000.00 10,120,000.00
Paku usuk 80 x 3,8 mm 1.2500 kg X Rp. - 0.00
Tukang Kayu 21.0000 org X Rp. 80,000.00 1,680,000.00
Kepala Tukang 2.1000 org X Rp. 90,000.00 189,000.00
Pekerja 7.0000 org X Rp. 55,000.00 385,000.00
Mandor 0.3500 org X Rp. 80,000.00 28,000.00
JUMLAH 2,282,000.00 10,120,000.00 12,402,000.00
PKY20 1 m3 Membuat dan memasang kusen pintu / jendela
Damar Laut (Kelas I) 1.1000 m3 X Rp. 15,625,000.00 17,187,500.00
Paku usuk 80 x 3,8 mm 1.2500 kg X Rp. - 0.00
Tukang Kayu 18.0000 org X Rp. 80,000.00 1,440,000.00
Kepala Tukang 1.8000 org X Rp. 90,000.00 162,000.00
Pekerja 6.0000 org X Rp. 55,000.00 330,000.00
Mandor 0.3000 org X Rp. 80,000.00 24,000.00
JUMLAH 1,956,000.00 17,187,500.00 19,143,500.00

PKY21 1 m2 Membuat dan memasang pintu klamp standar


Damar Laut (Kelas I) 0.0400 m3 X Rp. 15,625,000.00 625,000.00
Paku biasa 0.0500 kg X Rp. 16,300.00 815.00
Tukang Kayu 1.0500 org X Rp. 80,000.00 84,000.00
Kepala Tukang 0.1050 org X Rp. 90,000.00 9,450.00
Pekerja 0.3500 org X Rp. 55,000.00 19,250.00
Mandor 0.0175 org X Rp. 80,000.00 1,400.00
JUMLAH 114,100.00 625,815.00 739,915.00

PKY22 1 m2 Membuat dan memasang daun pintu panil


Kayu meranti papan 0.0400 m3 X Rp. 9,200,000.00 368,000.00
Lem kayu (putih) Fox 0.5000 kg X Rp. - 0.00
Tukang Kayu 3.0000 org X Rp. 80,000.00 240,000.00
Kepala Tukang 0.3000 org X Rp. 90,000.00 27,000.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.0500 org X Rp. 80,000.00 4,000.00
JUMLAH 326,000.00 368,000.00 694,000.00

PKY23 1 m2 Membuat dan memasang daun pintu dan jendela jalusi


Kayu meranti papan 0.0640 m3 X Rp. 9,200,000.00 588,800.00
Lem kayu (putih) Fox 0.5000 kg X Rp. - 0.00
Tukang Kayu 3.0000 org X Rp. 80,000.00 240,000.00
Kepala Tukang 0.3000 org X Rp. 90,000.00 27,000.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.0500 org X Rp. 80,000.00 4,000.00
JUMLAH 326,000.00 588,800.00 914,800.00

PKY24 1 m2 Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu
Kayu meranti papan 0.0250 m3 X Rp. 9,200,000.00 230,000.00
Paku biasa 1/2" - 1" 0.0300 kg X Rp. 16,300.00 489.00
Lem kayu (putih) Fox 0.5000 kg X Rp. - 0.00
Plywood 4 mm 1.0000 lbr X Rp. - 0.00
Tukang kayu 2.1000 org X Rp. 80,000.00 168,000.00
Kepala tukang 0.2100 org X Rp. 90,000.00 18,900.00
Pekerja 0.7000 org X Rp. 55,000.00 38,500.00
Mandor 0.0350 org X Rp. 80,000.00 2,800.00
JUMLAH 228,200.00 230,489.00 458,689.00

PKY25 1 m2 Membuat pintu plywood rangkap, rangka expose


Kayu meranti papan 0.0256 m3 X Rp. 9,200,000.00 235,520.00
Paku biasa 1/2" - 1" 0.0300 kg X Rp. 16,300.00 489.00
Lem kayu (putih) Fox 0.5000 kg X Rp. - 0.00
Plywood 4 mm 1.0000 lbr X Rp. - 0.00
Tukang kayu 2.4000 org X Rp. 80,000.00 192,000.00
Kepala tukang 0.2400 org X Rp. 90,000.00 21,600.00
Pekerja 0.8000 org X Rp. 55,000.00 44,000.00
Mandor 0.0400 org X Rp. 80,000.00 3,200.00
JUMLAH 260,800.00 236,009.00 496,809.00

PKY26 1m2 Memasang jalusi kusen


Kayu meranti papan 0.0600 m3 X Rp. 9,200,000.00 552,000.00
Paku biasa 1/2" - 1" 0.1500 kg X Rp. 16,300.00 2,445.00
Tukang kayu 2.0000 org X Rp. 80,000.00 160,000.00
Kepala tukang 0.2000 org X Rp. 90,000.00 18,000.00
Pekerja 0.6700 org X Rp. 55,000.00 36,850.00
Mandor 0.3350 org X Rp. 80,000.00 26,800.00
JUMLAH 241,650.00 554,445.00 796,095.00

PKY27 1 m2 Memasang teakwood rangkap, rangka expose


Kayu meranti papan 0.0250 m3 X Rp. 9,200,000.00 230,000.00
Paku biasa 1/2" - 1" 0.0300 kg X Rp. 16,300.00 489.00
Lem kayu (putih) Fox 0.3000 kg X Rp. - 0.00
Teak wood ( 90 x 240 ) 1.0000 lbr X Rp. - 0.00
Tukang kayu 2.4000 org X Rp. 80,000.00 192,000.00
Kepala tukang 0.2400 org X Rp. 90,000.00 21,600.00
Pekerja 0.8000 org X Rp. 55,000.00 44,000.00
Mandor 0.0400 org X Rp. 80,000.00 3,200.00
JUMLAH 260,800.00 230,489.00 491,289.00

PKY28 1 m2 Memasang teakwood rangkap lapis formika, rangka expose


Kayu meranti papan 0.0250 m3 X Rp. 9,200,000.00 230,000.00
Paku biasa 1/2" - 1" 0.0300 kg X Rp. 16,300.00 489.00
Lem kayu (putih) Fox 0.8000 kg X Rp. - 0.00
Teak wood ( 90 x 240 ) 1.0000 lbr X Rp. - 0.00
Formika 4" x 8" x 0,3 cm 0.5000 lbr X Rp. 56,100.00 28,050.00
Tukang kayu 2.5500 org X Rp. 80,000.00 204,000.00
Kepala tukang 0.2550 org X Rp. 90,000.00 22,950.00
Pekerja 0.8500 org X Rp. 55,000.00 46,750.00
Mandor 0.0425 org X Rp. 80,000.00 3,400.00
JUMLAH 305,150.00 230,489.00 535,639.00

PEKERJAAN BESI DAN ALUMUNIUM

PBS1 1 kg Pasang besi profil


Besi profil 1.1500 kg X Rp. 12,100.00 13,915.00
Tukang las 0.0600 org X Rp. 80,000.00 4,800.00
Kepala tukang 0.0060 org X Rp. 90,000.00 540.00
Pekerja 0.0600 org X Rp. 55,000.00 3,300.00
Mandor 0.0030 org X Rp. 80,000.00 240.00
JUMLAH 8,880.00 13,915.00 22,795.00

PBS2 1 kg Pasang kuda-kuda baja IWF


Baja profil IWF 1.1500 kg X Rp. - 0.00
Tukang las 0.0600 org X Rp. 80,000.00 4,800.00
Kepala tukang 0.0060 org X Rp. 90,000.00 540.00
Pekerja 0.0600 org X Rp. 55,000.00 3,300.00
Mandor 0.0030 org X Rp. 80,000.00 240.00
JUMLAH 8,880.00 0.00 8,880.00

PBS3 100 kg Kuda-kuda baja siku


Besi siku rata-rata 115.0000 kg X Rp. 13,300.00 1,529,500.00
Pekerja 6.0000 org X Rp. 55,000.00 330,000.00
Tukang besi 6.0000 org X Rp. 80,000.00 480,000.00
Kepala Tukang 0.6000 org X Rp. 90,000.00 54,000.00
Mandor 0.3000 org X Rp. 80,000.00 24,000.00
JUMLAH 888,000.00 1,529,500.00 2,417,500.00
Peralatan 5% 44,400.00 76,475.00 120,875.00
1 Kg 0.01 8,436.00 14,530.25 22,966.25

PBS4 100 kg Plat besi lembaran


Besi plat lembaran 115.0000 kg X Rp. 12,500.00 1,437,500.00
Pekerja 6.0000 org X Rp. 55,000.00 330,000.00
Tukang besi 6.0000 org X Rp. 80,000.00 480,000.00
Kepala Tukang 0.6000 org X Rp. 90,000.00 54,000.00
Mandor 0.3000 org X Rp. 80,000.00 24,000.00
JUMLAH 888,000.00 1,437,500.00 2,325,500.00
Peralatan 5% 44,400.00 71,875.00 116,275.00
1 Kg 0.01 8,436.00 13,656.25 22,092.25

PBS5 100 kg Gording baja


Besi gording canal 115.0000 kg X Rp. 12,100.00 1,391,500.00
Pekerja 6.0000 org X Rp. 55,000.00 330,000.00
Tukang besi 6.0000 org X Rp. 80,000.00 480,000.00
Kepala Tukang 0.6000 org X Rp. 90,000.00 54,000.00
Mandor 0.3000 org X Rp. 80,000.00 24,000.00
JUMLAH 888,000.00 1,391,500.00 2,279,500.00
Peralatan 5% 44,400.00 69,575.00 113,975.00
1 Kg 0.01 8,436.00 13,219.25 21,655.25

PBS6 100 kg Ikatan angin diameter 16 mm dan water mur


Besi beton polos 115.0000 kg X Rp. 11,600.00 1,334,000.00
Water mur 3.0000 kg X Rp. - 0.00
Pekerja 6.0000 org X Rp. 55,000.00 330,000.00
Tukang besi 6.0000 org X Rp. 80,000.00 480,000.00
Kepala Tukang 0.6000 org X Rp. 90,000.00 54,000.00
Mandor 0.3000 org X Rp. 80,000.00 24,000.00
JUMLAH 888,000.00 1,334,000.00 2,222,000.00
Peralatan 5% 44,400.00 66,700.00 111,100.00
1 Kg 0.01 8,436.00 12,673.00 21,109.00

PBS7 100 kg Trekstang diameter 12 mm


Besi beton polos 115.0000 kg X Rp. 11,600.00 1,334,000.00
Pekerja 6.0000 org X Rp. 55,000.00 330,000.00
Tukang besi 6.0000 org X Rp. 80,000.00 480,000.00
Kepala Tukang 0.6000 org X Rp. 90,000.00 54,000.00
Mandor 0.3000 org X Rp. 80,000.00 24,000.00
JUMLAH 888,000.00 1,334,000.00 2,222,000.00
Peralatan 5% 44,400.00 66,700.00 111,100.00
1 Kg 0.01 8,436.00 12,673.00 21,109.00

PBS8 1 unit Manhole uk. 70 x 70 cm


Besi siku rata-rata 6.4000 kg X Rp. 13,300.00 85,120.00
Plat baja t = 3 mm 11.5400 kg X Rp. - 0.00
Besi angkur dia. 8mm 8.0000 bh X Rp. - 0.00
Engsel pintu 2.0000 bh X Rp. 31,500.00 63,000.00
Kunci gembok 1.0000 bh X Rp. 8,200.00 8,200.00
Cat dasar meni 1.1250 m2 X Rp. 35,300.00 39,712.50
Pekerja 1.0000 oh X Rp. 55,000.00 55,000.00
JUMLAH 55,000.00 196,032.50 251,032.50

PBS9 1 unit Grill dari besi beton Ǿ 16mm rangka baja 50.50.5 uk 1 x 1 m
Besi siku rata-rata 24.1280 kg X Rp. 13,300.00 320,902.40
Besi beton polos 31.6000 kg X Rp. 11,600.00 366,560.00
Besi angkur dia. 8mm 2.0000 bh X Rp. - 0.00
Cat dasar meni 1.8850 m2 X Rp. 35,300.00 66,540.50
Tukang Las 0.1000 oh X Rp. 80,000.00 8,000.00
Pekerja 1.0000 oh X Rp. 55,000.00 55,000.00
JUMLAH 63,000.00 754,002.90 817,002.90

PBS10 100 kg Pekerjaan perakitan


Solar 1.0000 ltr X Rp. - 0.00
Minyak pelumas 0.1000 ltr X Rp. - 0.00
Tukang besi 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0010 org X Rp. 90,000.00 90.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
Sewa alat perakitan tulangan 0.8000 jam X Rp. - 0.00 0.00
JUMLAH 13,990.00 0.00 13,990.00
1.00 kg 139.90 0.00 139.90

PBS11 1 m2 Membuat pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Besi siku rata-rata 15.0000 kg X Rp. 13,300.00 199,500.00
Plat baja t = 3 mm 32.8000 kg X Rp. - 0.00
Kawat las 0.0500 kg X Rp. - 0.00
Tukang las 1.0500 org X Rp. 80,000.00 84,000.00
Kepala tukang 0.1050 org X Rp. 90,000.00 9,450.00
Pekerja 1.0500 org X Rp. 55,000.00 57,750.00
Mandor 0.0520 org X Rp. 80,000.00 4,160.00
JUMLAH 155,360.00 199,500.00 354,860.00

PBS12 10 cm Pengelasan dengan las listrik


Kawat las 0.4000 kg X Rp. - 0.00
Solar 0.3000 ltr X Rp. - 0.00
Minyak pelumas 0.0400 ltr X Rp. - 0.00
Tukang besi 0.0200 org X Rp. 80,000.00 1,600.00
Kepala tukang 0.0020 org X Rp. 90,000.00 180.00
Pekerja 0.0400 org X Rp. 55,000.00 2,200.00
Mandor 0.0020 org X Rp. 80,000.00 160.00
Sewa alat las 0.1700 jam X Rp. - 0.00
JUMLAH 4,140.00 0.00 4,140.00
1.00 cm 414.00 0.00 414.00

PBS13 1 m2 Rangka jendela besi square tube (25 x 5) cm


Besi scuare tube 4.7600 m1 X Rp. - 0.00
Besi lis kaca (1 x 1) cm 4.5220 m1 X Rp. - 0.00
Tukang las 0.6500 org X Rp. 80,000.00 52,000.00
Kepala tukang 0.0650 org X Rp. 90,000.00 5,850.00
Pekerja 0.6500 org X Rp. 55,000.00 35,750.00
Mandor 0.0320 org X Rp. 80,000.00 2,560.00
JUMLAH 96,160.00 0.00 96,160.00

PBS14 1 m2 Pasang Rolling door besi


Pintu gulung besi 1.0000 m2 X Rp. - 0.00
Tukang las 1.2000 org X Rp. 80,000.00 96,000.00
Kepala tukang 0.1200 org X Rp. 90,000.00 10,800.00
Pekerja 1.2000 org X Rp. 55,000.00 66,000.00
Mandor 0.0060 org X Rp. 80,000.00 480.00
JUMLAH 173,280.00 0.00 173,280.00

PBS15 1 m2 Pasang pintu lipat (folding door) bahan plastik/PVC


Pintu lipat besi 1.0000 m2 X Rp. - 0.00
Tukang besi 0.4400 org X Rp. 80,000.00 35,200.00
Kepala tukang 0.0440 org X Rp. 90,000.00 3,960.00
Pekerja 0.4400 org X Rp. 55,000.00 24,200.00
Mandor 0.0220 org X Rp. 80,000.00 1,760.00
JUMLAH 65,120.00 0.00 65,120.00

PBS16 1 m2 Pasang pintu Sunscreen alumunium


Sunscreen alumunium 1.0000 m2 X Rp. - 0.00
Tukang besi 0.8000 org X Rp. 80,000.00 64,000.00
Kepala tukang 0.0800 org X Rp. 90,000.00 7,200.00
Pekerja 0.0800 org X Rp. 55,000.00 4,400.00
Mandor 0.0040 org X Rp. 80,000.00 320.00
JUMLAH 75,920.00 0.00 75,920.00

PBS17 1 m2 Pasang Rolling door alumunium


Pintu alumunium 1.0000 m2 X Rp. - 0.00
Tukang alumunium 1.0000 org X Rp. 80,000.00 80,000.00
Kepala tukang 0.1000 org X Rp. 90,000.00 9,000.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.0500 org X Rp. 80,000.00 4,000.00
JUMLAH 148,000.00 0.00 148,000.00

PBS18 1 m' Pasang kusen pintu alumunium


Profil alumunium 1.1000 m1 X Rp. - 0.00
Skrup fixer 2.0000 bh X Rp. - 0.00
Sealent 0.0600 tube X Rp. 7,500.00 450.00
Tukang alumunium 0.0430 org X Rp. 80,000.00 3,440.00
Kepala tukang 0.0043 org X Rp. 90,000.00 387.00
Pekerja 0.0430 org X Rp. 55,000.00 2,365.00
Mandor 0.0021 org X Rp. 80,000.00 168.00
JUMLAH 6,360.00 450.00 6,810.00

PBS19 1 m2 Pasang pintu alumunium strip lebar 8 cm


Profil alumunium 4.4000 m1 X Rp. - 0.00
Alumunium strip 14.6000 m1 X Rp. - 0.00
Tukang alumunium 0.0850 org X Rp. 80,000.00 6,800.00
Kepala tukang 0.0085 org X Rp. 90,000.00 765.00
Pekerja 0.0850 org X Rp. 55,000.00 4,675.00
Mandor 0.0042 org X Rp. 80,000.00 336.00
JUMLAH 12,576.00 0.00 12,576.00

PBS20 1 m2 Pasang pintu kaca rangka alumunium


Pintu alumunium 4.4000 m1 X Rp. - 0.00
Profil kaca 4.5000 m1 X Rp. - 0.00
Sealent 0.2700 tube X Rp. 7,500.00 2,025.00
Tukang alumunium 0.0850 org X Rp. 80,000.00 6,800.00
Kepala tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0850 org X Rp. 55,000.00 4,675.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 12,685.00 2,025.00 14,710.00

PBS21 1 m2 Pasang vienetions dan vertikal blinds


Vienetions dan vertikal blinds (tirai) 1.0000 m2 X Rp. - 0.00
Tukang kayu 0.3500 org X Rp. 80,000.00 28,000.00
Kepala tukang 0.0350 org X Rp. 90,000.00 3,150.00
Pekerja 0.3500 org X Rp. 55,000.00 19,250.00
Mandor 0.0175 org X Rp. 80,000.00 1,400.00
JUMLAH 51,800.00 0.00 51,800.00

PBS22 1 m2 Pasang terali besi strip (2 x 3) mm


Besi strip 6.1770 kg X Rp. 13,300.00 82,154.10
Tukang las 1.6700 org X Rp. 80,000.00 133,600.00
Kepala tukang 0.1670 org X Rp. 90,000.00 15,030.00
Pekerja 1.6700 org X Rp. 55,000.00 91,850.00
Mandor 0.0830 org X Rp. 80,000.00 6,640.00
JUMLAH 247,120.00 82,154.10 329,274.10

PBS23 1 m2 Pasang kawat nyamuk


Kawat nyamuk 1.1000 m2 X Rp. - 0.00
Besi strip 1.7160 kg X Rp. 13,300.00 22,822.80
Tukang las 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 22,822.80 37,622.80

PBS24 1 m2 Pasang jendela nako & tralis


Jendela nako 1.1000 m2 X Rp. - 0.00
Paku skrup 10.0000 bh X Rp. - 0.00
Besi strip 7.0000 m1 X Rp. 13,300.00 93,100.00
Tukang kayu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0010 org X Rp. 80,000.00 80.00
JUMLAH 28,880.00 93,100.00 121,980.00

PBS25 1 m' Pasang talang datar/jurai, seng plat BJLS 28 lebar 90 cm, papan Kayu jati
Seng plat 3" x 6" BJLS 28 1.0500 m1 X Rp. - 0.00
Paku biasa 1/2" - 1" 0.0150 kg X Rp. 16,300.00 244.50
Kayu meranti papan 0.0190 m3 X Rp. 9,200,000.00 174,800.00
Tukang kayu 0.4000 org X Rp. 80,000.00 32,000.00
Kepala tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 46,050.00 175,044.50 221,094.50

PBS26 1 m' Pasang talang ½ lingkaran D - 15 cm, seng plat BJLS 30 lebar 45 cm
Seng plat 3" x 6" BJLS 28 1.0500 lbr X Rp. - 0.00
Paku biasa 1/2" - 1" 0.0100 kg X Rp. 16,300.00 163.00
Besi strip 0.5000 kg X Rp. 13,300.00 6,650.00
Tukang kayu 0.3000 org X Rp. 80,000.00 24,000.00
Kepala tukang 0.0300 org X Rp. 90,000.00 2,700.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0075 org X Rp. 80,000.00 600.00
JUMLAH 35,550.00 6,813.00 42,363.00

PEKERJAAN ATAP

PAT1 1 m2 Langit-langit asbes semen tebal 4, 5 dan 6 mm


Asbes plat ( 100 x 100 x 0,3 ) 1.1000 m2 X Rp. - 0.00
Paku triplek 0.0100 kg X Rp. - 0.00
Tukang kayu 0.0700 org X Rp. 80,000.00 5,600.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.0300 org X Rp. 55,000.00 1,650.00
Mandor 0.0040 org X Rp. 80,000.00 320.00
JUMLAH 8,200.00 0.00 8,200.00

PAT2 1 m2 Langit-langit asbes (1,00 x 1,00) m memakai plepet


Asbes plat ( 100 x 100 x 0,3 ) 1.1000 lbr X Rp. - 0.00
Kayu plepet eternit 1/5 cm 2.6000 m1 X Rp. - 0.00
Paku eternit 20 x 1,5 mm 0.0100 kg X Rp. - 0.00
Tukang kayu 0.0700 org X Rp. 80,000.00 5,600.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.0300 org X Rp. 55,000.00 1,650.00
Mandor 0.0015 org X Rp. 80,000.00 120.00
JUMLAH 8,000.00 0.00 8,000.00

PAT3 1 m2 Langit-langit akustik ukuran (30 x 30) cm


Akustik soft board 60 x 120 12.0000 lbr X Rp. - 0.00
Paku triplek 0.0500 kg X Rp. - 0.00
Tukang kayu 0.1200 org X Rp. 80,000.00 9,600.00
Kepala tukang 0.0120 org X Rp. 90,000.00 1,080.00
Pekerja 0.1200 org X Rp. 55,000.00 6,600.00
Mandor 0.0060 org X Rp. 80,000.00 480.00
JUMLAH 17,760.00 0.00 17,760.00

PAT4 1 m2 Langit-langit akustik ukuran (30 x 60) cm


Akustik soft board 30 x 60 5.8000 lbr X Rp. - 0.00
Paku triplek 0.0500 kg X Rp. - 0.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 0.00 14,800.00

PAT5 1 m2 Langit-langit akustik ukuran (60 x 120) cm


Akustik soft board 60 x 120 1.5000 lbr X Rp. - 0.00
Paku triplek 0.0500 kg X Rp. - 0.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 0.00 14,800.00

PAT6 1 m2 Langit-langit triplek ukuran (120 x 240) cm tebal 3mm, 4mm, dan 6 mm
Triplek 0.3750 lbr X Rp. 62,400.00 23,400.00
Paku triplek 0.0300 kg X Rp. - 0.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 14,800.00 23,400.00 38,200.00

PAT7 1 m2 Langit-langit lambriziring Kayu jati tebal 9 mm


Kayu meranti papan 0.0150 m3 X Rp. 9,200,000.00 138,000.00
Paku triplek 0.0300 kg X Rp. - 0.00
Tukang kayu 0.8000 org X Rp. 80,000.00 64,000.00
Kepala tukang 0.0800 org X Rp. 90,000.00 7,200.00
Pekerja 0.8000 org X Rp. 55,000.00 44,000.00
Mandor 0.0400 org X Rp. 80,000.00 3,200.00
JUMLAH 118,400.00 138,000.00 256,400.00

PAT8 1 m2 Langit-langit gypsum board ukuran (1200 x 2400 x 9) mm


Gypsum board 0.3640 lbr X Rp. 68,000.00 24,752.00
Paku skrup 0.1100 kg X Rp. - 0.00
Tukang kayu 0.0500 org X Rp. 80,000.00 4,000.00
Kepala tukang 0.0050 org X Rp. 90,000.00 450.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 10,350.00 24,752.00 35,102.00

PAT9 1 m' Pasang list plafond gypsum profil


List profil gypsum lebar sampai 5 cm 1.0500 m1 X Rp. - 0.00
Tepung gypsum 0.1500 kg X Rp. - 0.00
Tukang kayu 0.0600 org X Rp. 80,000.00 4,800.00
Kepala tukang 0.0060 org X Rp. 90,000.00 540.00
Pekerja 0.0600 org X Rp. 55,000.00 3,300.00
Mandor 0.0030 org X Rp. 80,000.00 240.00
JUMLAH 8,880.00 0.00 8,880.00

PAT10 1 m2 Langit-langit akustik ukuran 60 x 120 cm + rangka alumunium


Profil alumunium 3.6000 m1 X Rp. - 0.00
Kawat beton / bindrat 0.1500 kg X Rp. 20,000.00 3,000.00
Ramset / dina bolt 1.0500 bh X Rp. - 0.00
Akustik soft board 60 x 120 1.5000 lbr X Rp. - 0.00
Tukang besi 0.5000 org X Rp. 80,000.00 40,000.00
Kepala tukang 0.0500 org X Rp. 90,000.00 4,500.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 74,000.00 3,000.00 77,000.00

PAT11 1 m' List langit-langit kayu profil


List kayu profil 1.0500 m1 X Rp. - 0.00
Paku biasa 1/2" - 1" 0.0100 kg X Rp. 16,300.00 163.00
Tukang kayu 0.0500 org X Rp. 80,000.00 4,000.00
Kepala tukang 0.0050 org X Rp. 90,000.00 450.00
Pekerja 0.0500 org X Rp. 55,000.00 2,750.00
Mandor 0.0030 org X Rp. 80,000.00 240.00
JUMLAH 7,440.00 163.00 7,603.00

PAT12 1 m2 Pasang rangka langit-langit (1,00 x 1,00) m


Kayu meranti balok 0.0120 m3 X Rp. 9,200,000.00 110,400.00
Paku biasa 0.1000 kg X Rp. 16,300.00 1,630.00
Tukang kayu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0075 org X Rp. 80,000.00 600.00
JUMLAH 31,100.00 112,030.00 143,130.00

PAT13 1 m2 Pasang rangka langit-langit (60 x 120) cm


Kayu meranti balok 0.0130 m3 X Rp. 9,200,000.00 119,600.00
Paku biasa 1/2" - 1" 0.1200 kg X Rp. 16,300.00 1,956.00
Tukang kayu 0.2700 org X Rp. 80,000.00 21,600.00
Kepala tukang 0.0270 org X Rp. 90,000.00 2,430.00
Pekerja 0.1700 org X Rp. 55,000.00 9,350.00
Mandor 0.0085 org X Rp. 80,000.00 680.00
JUMLAH 34,060.00 121,556.00 155,616.00

PAT14 1 m2 Langit-langit rangka hollow


Pipa hollow 4.5000 m1 X Rp. - 0.00
Paku skrup 0.0400 kg X Rp. - 0.00
Kawat penggantung rangka hollow 5.0000 m1 X Rp. - 0.00
Tukang kayu 0.3200 org X Rp. 80,000.00 25,600.00
Kepala tukang 0.0320 org X Rp. 90,000.00 2,880.00
Pekerja 0.1400 org X Rp. 55,000.00 7,700.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 36,740.00 0.00 36,740.00

PAT15 1 m 2 P asang gent eng bet on besar Nat ural ( i si 9 / m 2 )


Genteng beton besar natural 1m 9 biji 9.0000 bh X Rp. - 0.00
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 20,700.00 0.00 20,700.00

PAT16 1 m 2 P asang gent eng bet on besar Nat ural ( i si 9 / m 2 ) unt uk rumah ti ngkat
Genteng beton besar natural 1m 9 biji 9.0000 bh X Rp. - 0.00
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 0.00 26,600.00

PAT17 1 m 2 P asang gent eng bet on besar Warna ( i si 9 / m2 )


Genteng beton besar warna 1m 9 biji 9.0000 bh X Rp. - 0.00
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 20,700.00 0.00 20,700.00

PAT18 1 m 2 P asang gent eng bet on besar Warna ( i si 9 / m2 ) untuk rumah ti ngkat
Genteng beton besar warna 1m 9 biji 9.0000 bh X Rp. - 0.00
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 0.00 26,600.00

PAT19 1 m2 Pasang genteng keramik berglasir KIA, Kanmuri Natural


Genteng keramik berglasir KIA, Kanmuri Natural 14.5000 bh X Rp. - 0.00
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 20,700.00 0.00 20,700.00

PAT20 1 m2 Pasang genteng keramik berglasir KIA, Kanmuri Natural untuk rumah tingkat
Genteng beton besar natural 1m 9 biji 14.5000 bh X Rp. - 0.00
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.3000 org X Rp. 55,000.00 16,500.00
Mandor 0.0150 org X Rp. 80,000.00 1,200.00
JUMLAH 26,600.00 0.00 26,600.00

PAT21 1 m' Pasang bubungan genteng paris


Genteng bubungan beton 5.0000 bh X Rp. - 0.00
Kapur pasang 0.0152 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.0152 m3 X Rp. 120,000.00 1,824.00
Portland Cement (PC) 1.5240 kg X Rp. 1,375.00 2,095.50
Tukang batu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.4000 org X Rp. 55,000.00 22,000.00
Mandor 0.0200 org X Rp. 80,000.00 1,600.00
JUMLAH 41,400.00 3,919.50 45,319.50

PAT22 1 m' Pasang bubungan genteng beton Warna


Genteng bubungan warna 4.0000 bh X Rp. - 0.00
Kapur pasang 0.0152 m3 X Rp. - 0.00
Pasir pasang ( progo ) 0.0152 m3 X Rp. 120,000.00 1,824.00
Portland Cement (PC) 1.5240 kg X Rp. 1,375.00 2,095.50
Tukang batu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala Tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.4000 org X Rp. 55,000.00 22,000.00
Mandor 0.0200 org X Rp. 80,000.00 1,600.00
JUMLAH 41,400.00 3,919.50 45,319.50

PAT23 1 m2 Pasang atap asbes gelombang (2,25 x 0,92 m) x 5 mm


Asbes gelombang besar ( 225 x 92 x 0,5 ) 0.6000 lbr X Rp. - 0.00
Paku biasa 1/2" - 1" 0.1200 kg X Rp. 16,300.00 1,956.00
Tukang kayu 0.0750 org X Rp. 80,000.00 6,000.00
Kepala tukang 0.0080 org X Rp. 90,000.00 720.00
Pekerja 0.1400 org X Rp. 55,000.00 7,700.00
Mandor 0.0080 org X Rp. 80,000.00 640.00
JUMLAH 15,060.00 1,956.00 17,016.00

PAT24 1 m2 Pasang atap asbes gelombang (2,00 x 0,92 m) x 5 mm


Asbes gelombang besar ( 200 x 92 x 0,5 ) 0.6000 lbr X Rp. - 0.00
Paku biasa 1/2" - 1" 0.1200 kg X Rp. 16,300.00 1,956.00
Tukang kayu 0.0700 org X Rp. 80,000.00 5,600.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.1400 org X Rp. 55,000.00 7,700.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 14,490.00 1,956.00 16,446.00

PAT25 1 m2 Pasang atap asbes gelombang (1,80 x 0,92 m) x 5 mm


Asbes gelombang besar ( 180 x 92 x 0,5 ) 0.7500 lbr X Rp. - 0.00
Paku biasa 1/2" - 1" 0.1200 kg X Rp. 16,300.00 1,956.00
Tukang kayu 0.0700 org X Rp. 80,000.00 5,600.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.1400 org X Rp. 55,000.00 7,700.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 14,490.00 1,956.00 16,446.00

PAT26 1 m2 Pasang atap asbes gelombang (2,40 x 1,05 m) x 4 mm


Asbes gelombang kecil ( 240 x 105 x 0,4 ) 0.4400 lbr X Rp. - 0.00
Paku biasa 1/2" - 1" 0.1200 kg X Rp. 16,300.00 1,956.00
Tukang kayu 0.0670 org X Rp. 80,000.00 5,360.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.1400 org X Rp. 55,000.00 7,700.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 14,250.00 1,956.00 16,206.00

PAT27 1 m2 Pasang atap asbes gelombang (2,10 x 1,05 m) x 4 mm


Asbes gelombang besar ( 210 x 108 x 0,6 ) 0.5100 lbr X Rp. - 0.00
Paku biasa 1/2" - 1" 0.1200 kg X Rp. 16,300.00 1,956.00
Tukang kayu 0.0670 org X Rp. 80,000.00 5,360.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.1400 org X Rp. 55,000.00 7,700.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 14,250.00 1,956.00 16,206.00

PAT28 1 m2 Pasang atap asbes gelombang (1,50 x 1,05 m) x 4 mm


Asbes gelombang kecil ( 150 x 105 x 0,4 ) 0.8000 lbr X Rp. - 0.00
Paku biasa 1/2" - 1" 0.1200 kg X Rp. 16,300.00 1,956.00
Tukang kayu 0.0670 org X Rp. 80,000.00 5,360.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.1400 org X Rp. 55,000.00 7,700.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 14,250.00 1,956.00 16,206.00

PAT29 1 m2 Pasang atap sbes gelombang (2,40 x 1,08 m) x 6 mm


Asbes gelombang besar ( 240 x 108 x 0,6 ) 0.4600 lbr X Rp. - 0.00
Paku biasa 1/2" - 1" 0.1200 kg X Rp. 16,300.00 1,956.00
Tukang kayu 0.0670 org X Rp. 80,000.00 5,360.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.1400 org X Rp. 55,000.00 7,700.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 14,250.00 1,956.00 16,206.00

PAT30 1 m2 Pasang atap asbes gelombang (2,10 x 1,08 m) x 6 mm


Asbes gelombang besar ( 210 x 108 x 0,6 ) 0.4900 lbr X Rp. - 0.00
Paku biasa 1/2" - 1" 0.1200 kg X Rp. 16,300.00 1,956.00
Tukang kayu 0.0670 org X Rp. 80,000.00 5,360.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.1400 org X Rp. 55,000.00 7,700.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 14,250.00 1,956.00 16,206.00

PAT31 1 m2 Pasang atap asbes gelombang (1,80 x 1,08 m) x 6 mm


Asbes gelombang besar ( 180 x 108 x 0,6 ) 0.5700 lbr X Rp. - 0.00
Paku biasa 1/2" - 1" 0.1200 kg X Rp. 16,300.00 1,956.00
Tukang kayu 0.0670 org X Rp. 80,000.00 5,360.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.1400 org X Rp. 55,000.00 7,700.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 14,250.00 1,956.00 16,206.00

PAT32 1 m' Pasang bubung stel gelombang 0,92 m


Bubung stel gelombang 2.4000 lbr X Rp. - 0.00
Paku skrup 6.0000 bh X Rp. - 0.00
Tukang kayu 0.1250 org X Rp. 80,000.00 10,000.00
Kepala tukang 0.0130 org X Rp. 90,000.00 1,170.00
Pekerja 0.0840 org X Rp. 55,000.00 4,620.00
Mandor 0.0040 org X Rp. 80,000.00 320.00
JUMLAH 16,110.00 0.00 16,110.00

PAT33 1 m' Pasang nok stel rata 0,92 m


Nok stel rata 1.1000 lbr X Rp. - 0.00
Paku skrup 6.0000 bh X Rp. - 0.00
Tukang kayu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala tukang 0.0130 org X Rp. 90,000.00 1,170.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0040 org X Rp. 80,000.00 320.00
JUMLAH 18,990.00 0.00 18,990.00

PAT34 1 m' Pasang nok stel rata 1,09 m


Nok stel rata 1.1000 lbr X Rp. - 0.00
Paku skrup 6.0000 bh X Rp. - 0.00
Tukang kayu 0.1250 org X Rp. 80,000.00 10,000.00
Kepala tukang 0.0130 org X Rp. 90,000.00 1,170.00
Pekerja 0.0840 org X Rp. 55,000.00 4,620.00
Mandor 0.0040 org X Rp. 80,000.00 320.00
JUMLAH 16,110.00 0.00 16,110.00

PAT35 1 m' Pasang nok atap seng


Seng plat 3" x 6" BJLS 28 0.3000 lbr X Rp. - 0.00
Paku biasa 1/2" - 1" 0.0400 kg X Rp. 16,300.00 652.00
Tukang kayu 0.0700 org X Rp. 80,000.00 5,600.00
Kepala tukang 0.0080 org X Rp. 90,000.00 720.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0060 org X Rp. 80,000.00 480.00
JUMLAH 15,050.00 652.00 15,702.00

PAT36 1 m2 Pasang atap genteng metal zinc alume type prima roof
Genteng metal 1.0200 m2 X Rp. - 0.00
Paku anti karat 0.2000 kg X Rp. - 0.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0010 org X Rp. 80,000.00 80.00
JUMLAH 19,980.00 0.00 19,980.00

PAT37 1 m2 Pasang atap metal gelombang


Atap metal gelombang t 0,35 mm 1.0200 m2 X Rp. - 0.00
Paku anti karat 4.0000 bh X Rp. - 0.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0010 org X Rp. 80,000.00 80.00
JUMLAH 19,980.00 0.00 19,980.00

PAT38 1 m' Pasang nok genteng metal U type prima roof


Nok metal 1.1000 bh X Rp. - 0.00
Paku anti karat 0.0500 kg X Rp. - 0.00
Tukang kayu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.2500 org X Rp. 55,000.00 13,750.00
Mandor 0.0130 org X Rp. 80,000.00 1,040.00
JUMLAH 28,140.00 0.00 28,140.00

PAT39 1 m2 Pasang atap alumunium


Atap alumunium gelombang tebal 0,55 1.0500 m2 X Rp. - 0.00
Paku hak panjang 15 cm 0.0200 kg X Rp. - 0.00
Tukang kayu 0.7500 org X Rp. 80,000.00 60,000.00
Kepala tukang 0.0080 org X Rp. 90,000.00 720.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0060 org X Rp. 80,000.00 480.00
JUMLAH 69,450.00 0.00 69,450.00

PAT40 1 m' Pasang nok alumunium


Nok standar 40 cm 18 SWG 22 1.2000 m1 X Rp. - 0.00
Paku hak panjang 15 cm 0.0400 kg X Rp. - 0.00
Tukang kayu 1.0000 org X Rp. 80,000.00 80,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 87,200.00 0.00 87,200.00

PAT41 1 m2 Pasang alumunium foil / sisalation


Alumunium foil 1.0500 m2 X Rp. - 0.00
Tukang kayu 0.0500 org X Rp. 80,000.00 4,000.00
Kepala tukang 0.0050 org X Rp. 90,000.00 450.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0080 org X Rp. 80,000.00 640.00
JUMLAH 13,340.00 0.00 13,340.00

PAT42 1 m2 Pasang atap polikarbonat


Atap polykarbonat 1.0500 m2 X Rp. - 0.00
Besi profil 7.0000 kg X Rp. 12,100.00 84,700.00
Paku skrup 9.0000 bh X Rp. - 0.00
Tukang besi 0.5000 org X Rp. 80,000.00 40,000.00
Kepala tukang 0.0500 org X Rp. 90,000.00 4,500.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 72,200.00 84,700.00 156,900.00

PAT43 1 M2 Rangka atap baja ringan atap genteng metal:


Paku biasa 1/2" - 1" 0.100 Kg X Rp. 16,300.00 1,630.00
Baja ringan 1.000 m2 X Rp. - 0.00
Tukang kayu 0.145 org/hr X Rp. 80,000.00 11,600.00
Kepala Tukang 0.015 org/hr X Rp. 90,000.00 1,305.00
Pekerja 0.218 org/hr X Rp. 55,000.00 11,962.50
Mandor 0.011 org/hr X Rp. 80,000.00 870.00
JUMLAH 25,737.50 1,630.00 27,367.50

PAT44 1 M2 Atap spandek tebal 0,50 mm uk. 0.75X1.33 m2 :


Atap spandek 1.200 M2 X Rp. - 0.00
Baut + Hak Spandek 4.000 Bh X Rp. - 0.00
Kepala tukang 0.030 org/hr X Rp. 90,000.00 2,700.00
Tukang besi 0.300 org/hr X Rp. 80,000.00 24,000.00
Pekerja 0.380 org/hr X Rp. 55,000.00 20,900.00
Mandor 0.019 org/hr X Rp. 80,000.00 1,520.00
Sewa alar bor 1.000 ls X Rp. -
JUMLAH 49,120.00 0.00 49,120.00

PAT45 10 M' Rabung atap spandek :


Rabung Atap spandek 10.000 m' X Rp. - 0.00
Baut + Hak Spandek 20.000 Bh X Rp. - 0.00
Tukang besi 0.250 org/hr X Rp. 80,000.00 20,000.00
Kepala tukang 0.025 org/hr X Rp. 90,000.00 2,250.00
Pekerja 0.250 org/hr X Rp. 55,000.00 13,750.00
JUMLAH 36,000.00 0.00 36,000.00
Per M' 3,600.00 0.00 3,600.00

PEKERJAAN PENGECATAN

PPC1 10 m2 Mengecat kerb 3 kali


Cat dasar meni 4.2500 kg X Rp. 35,300.00 150,025.00
Minyak cat 0.5700 ltr X Rp. 12,000.00 6,840.00
Tukang cat 3.0000 org X Rp. 80,000.00 240,000.00
Kepala Tukang 0.3000 org X Rp. 90,000.00 27,000.00
Pekerja 2.0000 org X Rp. 55,000.00 110,000.00
Mandor 0.1000 org X Rp. 80,000.00 8,000.00
385,000.00 156,865.00 541,865.00
TI AP 1 M2 ( 3 kali ) 38,500.00 15,686.50 54,186.50
TIA P 1 M 2 ( 2 kali ) 25,666.67 10,457.67 36,124.33
TIA P 1 M 2 ( 1 kali ) 12,833.33 5,228.83 18,062.17

PPC2 Mengikis / mengerok permukaan cat tembok lama


Soda api 0.0500 kg X Rp. - 0.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 8,450.00 0.00 8,450.00

PPC3 1 m2 Mengerok karat cat lama permukaan baja dengan cara manual
Sabun deterjen 0.0500 kg X Rp. - 0.00
Pekerja 0.1500 org X Rp. 55,000.00 8,250.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 8,450.00 0.00 8,450.00

PPC4 1 m2 Mendempul dan menggosok kayu


Dempul kayu typa A (putih) Jago 0.0800 kg X Rp. 22,700.00 1,816.00
Minyak cat 0.0200 kg X Rp. 12,000.00 240.00
Batu apung 0.0100 kg X Rp. - 0.00
Tukang cat 0.0400 org X Rp. 80,000.00 3,200.00
Kepala tukang 0.0040 org X Rp. 90,000.00 360.00
Pekerja 0.0400 org X Rp. 55,000.00 2,200.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 5,960.00 2,056.00 8,016.00

PPC5 1 m2 Pengecatan bidang kayu lama


Plamur Fuji 0.1500 kg X Rp. - 0.00
Cat dasar meni kayu 0.1700 kg X Rp. 35,300.00 6,001.00
Cat penutup 0.1700 kg X Rp. 51,800.00 8,806.00
Tukang cat 0.0750 org X Rp. 80,000.00 6,000.00
Kepala tukang 0.0075 org X Rp. 90,000.00 675.00
Pekerja 0.0700 org X Rp. 55,000.00 3,850.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 10,725.00 14,807.00 25,532.00

PPC6 1 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
Cat dasar meni kayu 0.2000 kg X Rp. 35,300.00 7,060.00
Plamur Fuji 0.1500 kg X Rp. - 0.00
Cat dasar meni kayu 0.1700 kg X Rp. 35,300.00 6,001.00
Cat penutup 0.2600 kg X Rp. 51,800.00 13,468.00
Tukang cat 0.0900 org X Rp. 80,000.00 7,200.00
Kepala tukang 0.0060 org X Rp. 90,000.00 540.00
Pekerja 0.0700 org X Rp. 55,000.00 3,850.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 4,590.00 33,729.00 38,319.00

PPC7 1 m2 Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
Cat dasar meni kayu 0.2000 kg X Rp. 35,300.00 7,060.00
Plamur Fuji 0.1500 kg X Rp. - 0.00
Cat kayu 0.1700 kg X Rp. 59,200.00 10,064.00
Cat penutup 0.3500 kg X Rp. 51,800.00 18,130.00
Tukang cat 0.1050 org X Rp. 80,000.00 8,400.00
Kepala tukang 0.0040 org X Rp. 90,000.00 360.00
Pekerja 0.0700 org X Rp. 55,000.00 3,850.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 12,810.00 35,254.00 48,064.00

PPC8 1 m2 Pelaburan bidang kayu dengan teak oil


Teak oil Fuji 0.3600 ltr X Rp. - 0.00
Tukang cat 0.0630 org X Rp. 80,000.00 5,040.00
Kepala tukang 0.0630 org X Rp. 90,000.00 5,670.00
Pekerja 0.0400 org X Rp. 55,000.00 2,200.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 13,110.00 0.00 13,110.00

PPC9 1 m2 Pelaburan bidang kayu dengan politur


Politur jadi 0.1500 ltr X Rp. - 0.00
Politur jadi 0.3720 ltr X Rp. - 0.00
Amplas 2.0000 lbr X Rp. - 0.00
Tukang cat 0.0600 org X Rp. 80,000.00 4,800.00
Kepala tukang 0.0160 org X Rp. 90,000.00 1,440.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 6,440.00 0.00 6,440.00

PPC10 1 m2 Pelaburan bidang kayu dengan cat residu atau ter


Residu 0.3500 ltr X Rp. - 0.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0060 org X Rp. 80,000.00 480.00
JUMLAH 5,980.00 0.00 5,980.00

PPC11 1 m2 Pelaburan bidang kayu dengan vernis


Pernis 0.1500 ltr X Rp. 44,100.00 6,615.00
Dempul kayu typa A (putih) Jago 0.0500 kg X Rp. 22,700.00 1,135.00
Amplas 0.1000 lbr X Rp. - 0.00
Kuas ukuran 3,5" 0.0100 bh X Rp. - 0.00
Tukang cat 0.1600 org X Rp. 80,000.00 12,800.00
Kepala tukang 0.0160 org X Rp. 90,000.00 1,440.00
Pekerja 0.1600 org X Rp. 55,000.00 8,800.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 23,240.00 7,750.00 30,990.00

PPC12 1 m2 Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Plamur Fuji 0.1000 kg X Rp. - 0.00
Cat dasar meni kayu 0.1000 kg X Rp. 35,300.00 3,530.00
Cat penutup 0.2600 kg X Rp. 51,800.00 13,468.00
Tukang cat 0.0630 org X Rp. 80,000.00 5,040.00
Kepala tukang 0.0063 org X Rp. 90,000.00 567.00
Pekerja 0.0200 org X Rp. 55,000.00 1,100.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 6,907.00 16,998.00 23,905.00

PPC13 1 m2 Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
Cat dasar meni kayu 0.1200 kg X Rp. 35,300.00 4,236.00
Cat penutup 0.1800 kg X Rp. 51,800.00 9,324.00
Tukang cat 0.0420 org X Rp. 80,000.00 3,360.00
Kepala tukang 0.0042 org X Rp. 90,000.00 378.00
Pekerja 0.0280 org X Rp. 55,000.00 1,540.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 5,478.00 13,560.00 19,038.00

PPC14 1 m2 Pengecatan tembok tidak terlindung dari panas dan hujan


Cat alkali resisting primer 0.1000 kg X Rp. - 0.00
Cat ICI Weathershield 0.3600 kg X Rp. - 0.00
Tukang cat 0.0630 org X Rp. 80,000.00 5,040.00
Kepala tukang 0.0063 org X Rp. 90,000.00 567.00
Pekerja 0.0200 org X Rp. 55,000.00 1,100.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 6,907.00 0.00 6,907.00

PPC15 1 m2 Melabur tembok dengan kalkarium


Kalkarium 0.1000 kg X Rp. - 0.00
Tukang cat 0.0420 org X Rp. 80,000.00 3,360.00
Kepala tukang 0.0042 org X Rp. 90,000.00 378.00
Pekerja 0.0280 org X Rp. 55,000.00 1,540.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 5,478.00 0.00 5,478.00

PPC16 1 m2 Pengecatan bidang besi ( 3 x )


Cat dasar meni 0.1670 kg X Rp. 35,300.00 5,895.10
Thinner 0.1500 ltr X Rp. 12,000.00 1,800.00
Tukang cat 0.1050 org X Rp. 80,000.00 8,400.00
Kepala tukang 0.0040 org X Rp. 90,000.00 360.00
Pekerja 0.0700 org X Rp. 55,000.00 3,850.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 12,810.00 7,695.10 20,505.10

PPC17 1 m2 Melamin
Cat tembok melamin 0.2000 kg X Rp. 24,000.00 4,800.00
Kuas ukuran 3,5" 0.0150 bh X Rp. - 0.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Tukang cat 0.1000 org X Rp. 80,000.00 8,000.00
Kepala Tukang 0.0050 org X Rp. 90,000.00 450.00
Mandor 0.0005 org X Rp. 80,000.00 40.00
JUMLAH 19,490.00 4,800.00 24,290.00

PPC18 1 m2 Pemasangan wall paper


Wall paper 1.2000 m2 X Rp. - 0.00
Perekat 0.2000 kg X Rp. - 0.00
Tukang cat 0.2000 org X Rp. 80,000.00 16,000.00
Kepala tukang 0.0020 org X Rp. 90,000.00 180.00
Pekerja 0.0200 org X Rp. 55,000.00 1,100.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 17,480.00 0.00 17,480.00

PPC19 1 m2 Pengecacatan permukaan baja dengan meni besi


Cat dasar meni 0.1000 kg X Rp. 35,300.00 3,530.00
Kuas ukuran 3,5" 0.0100 bh X Rp. - 0.00
Tukang cat 0.2000 org X Rp. 80,000.00 16,000.00
Kepala tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.0200 org X Rp. 55,000.00 1,100.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 19,700.00 3,530.00 23,230.00

PPC20 1 m2 Pengecacatan permukaan baja dengan meni besi memakai perancah


Cat dasar meni 0.1000 kg X Rp. 35,300.00 3,530.00
Kuas ukuran 3,5" 0.0100 bh X Rp. - 0.00
0.0020 m
3
Perancah kayu X Rp. - 0.00
Tukang cat 0.2250 org X Rp. 80,000.00 18,000.00
Kepala tukang 0.0225 org X Rp. 90,000.00 2,025.00
Pekerja 0.2250 org X Rp. 55,000.00 12,375.00
Mandor 0.0075 org X Rp. 80,000.00 600.00
JUMLAH 33,000.00 3,530.00 36,530.00

PPC21 1 m2 Pengetiran kayu ( 2 x )


Teer kayu 0.3500 kg X Rp. - 0.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 5,900.00 0.00 5,900.00

PPC22 1 m2 Mengecat genteng


Cat ICI Weathershield 0.3600 kg X Rp. - 0.00
Tukang cat 0.0630 org X Rp. 80,000.00 5,040.00
Kepala Tukang 0.0063 org X Rp. 90,000.00 567.00
Pekerja 0.0200 org X Rp. 55,000.00 1,100.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 6,907.00 0.00 6,907.00

PPC23 1 m2 Mengerjakan Cat Sungging


Mengerjakan cat dasar
Cat dasar meni kayu 0.1200 kg X Rp. 35,300.00 4,236.00
Tukang cat 0.0400 org X Rp. 80,000.00 3,200.00
Kepala Tukang 0.0040 org X Rp. 90,000.00 360.00
Pekerja 0.0667 org X Rp. 55,000.00 3,668.50
Mandor 0.0033 org X Rp. 80,000.00 264.00
JUMLAH ( A ) 7,492.50 4,236.00 11,728.50

Mengecat dan membuat gradasi tutulan berkali-kali


Cat kayu 0.4250 kg X Rp. 59,200.00 25,160.00
Minyak cat 0.1000 ltr X Rp. 12,000.00 1,200.00
Tukang cat 5.0000 org X Rp. 80,000.00 400,000.00
Kepala Tukang 0.5000 org X Rp. 90,000.00 45,000.00
Pekerja 0.2000 org X Rp. 55,000.00 11,000.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH ( B ) 456,800.00 26,360.00 483,160.00
JUMLAH A + B 464,292.50 30,596.00 494,888.50

PEKERJAAN BONGKARAN

PBK1 1 m3 Membongkar pasangan batu kali


Tukang batu 4.0000 org X Rp. 80,000.00 320,000.00
Pekerja 0.4000 org X Rp. 55,000.00 22,000.00
JUMLAH 342,000.00 0.00 342,000.00

PBK2 1 m3 Membongkar pasangan batu merah dan membersihkan


Tukang batu 2.0000 org X Rp. 80,000.00 160,000.00
Pekerja 0.1000 org X Rp. 55,000.00 5,500.00
JUMLAH 165,500.00 0.00 165,500.00

PBK3 1 m3 Membongkar beton bertulang dan membersihkan


Tukang batu 0.2000 org X Rp. 80,000.00 16,000.00
Pekerja 8.0000 org X Rp. 55,000.00 440,000.00
Mandor 0.1000 org X Rp. 80,000.00 8,000.00
JUMLAH 464,000.00 0.00 464,000.00

PBK4 10 m2 Pekerjaan bongkar lantai tegel untuk dipergunakan lagi


Pekerja 2.0000 org X Rp. 55,000.00 110,000.00
Mandor 0.1000 org X Rp. 80,000.00 8,000.00
JUMLAH 118,000.00 0.00 118,000.00
TIAP 1M2 11,800.00 0.00 11,800.00

PBK5 10 m2 Mengupas plesteran lama


Pekerja 1.2500 org X Rp. 55,000.00 68,750.00
Mandor 0.1250 org X Rp. 80,000.00 10,000.00
JUMLAH 78,750.00 0.00 78,750.00
TIAP 1M2 7,875.00 0.00 7,875.00

PBK6 10 m2 Membongkar genteng / sirap untuk dipergunakan lagi


Pekerja 2.0000 org X Rp. 55,000.00 110,000.00
Mandor 0.1000 org X Rp. 80,000.00 8,000.00
JUMLAH 118,000.00 0.00 118,000.00
TIAP 1M2 11,800.00 0.00 11,800.00

PBK7 10 m2 Membongkar atap seng


Tukang besi 0.5000 org X Rp. 80,000.00 40,000.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
JUMLAH 95,000.00 0.00 95,000.00
TIAP 1M2 9,500.00 0.00 9,500.00

PBK8 10 m2 Membongkar usuk / reng dipakai lagi


Tukang kayu 0.6000 org X Rp. 80,000.00 48,000.00
Kepala Tukang 0.0600 org X Rp. 90,000.00 5,400.00
Pekerja 2.0000 org X Rp. 55,000.00 110,000.00
Mandor 0.1000 org X Rp. 80,000.00 8,000.00
JUMLAH 171,400.00 0.00 171,400.00
TIAP 1M2 17,140.00 0.00 17,140.00

PBK9 10 m2 Membongkar usuk / reng tidak dipakai lagi


Pekerja 2.0000 org X Rp. 55,000.00 110,000.00
Mandor 0.1000 org X Rp. 80,000.00 8,000.00
JUMLAH 118,000.00 0.00 118,000.00
TIAP 1M2 11,800.00 0.00 11,800.00

PBK10 1 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi
Tukang kayu 6.0000 org X Rp. 80,000.00 480,000.00
Kepala Tukang 0.6000 org X Rp. 90,000.00 54,000.00
Pekerja 4.0000 org X Rp. 55,000.00 220,000.00
Mandor 0.2000 org X Rp. 80,000.00 16,000.00
JUMLAH 770,000.00 0.00 770,000.00

PBK11 1 m3 Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.2000 org X Rp. 80,000.00 16,000.00
JUMLAH 71,000.00 0.00 71,000.00

PBK12 1 m3 Mengerjakan kembali bangunan kayu yang telah dibongkar


Tukang kayu 12.0000 org X Rp. 80,000.00 960,000.00
Kepala Tukang 1.2000 org X Rp. 90,000.00 108,000.00
Pekerja 4.0000 org X Rp. 55,000.00 220,000.00
Mandor 0.2000 org X Rp. 80,000.00 16,000.00
JUMLAH 1,304,000.00 0.00 1,304,000.00

PEKERJAAN SANITASI

PSI1 1 bh Memasang kloset duduk/monoblock


Kloset duduk putih dengan tangki "Toto" 1.0000 bh X Rp. 1,890,000.00 1,890,000.00
Harga kloset (Perlengkapan) 6% x X Rp. 113,400.00 6,804.00
Tukang batu 1.1000 org X Rp. 80,000.00 88,000.00
Kepala tukang 0.0010 org X Rp. 90,000.00 90.00
Pekerja 3.3000 org X Rp. 55,000.00 181,500.00
Mandor 0.1600 org X Rp. 80,000.00 12,800.00
JUMLAH 282,390.00 1,896,804.00 2,179,194.00

PSI2 1 bh Memasang kloset jongkok porselen


Kloset jongkok porselin type CE8 standar 1.0000 bh X Rp. - 0.00
Portland Cement (PC) 6.0000 kg X Rp. 1,375.00 8,250.00
Pasir pasang ( progo ) 0.0100 m3 X Rp. 120,000.00 1,200.00
Tukang batu 1.5000 org X Rp. 80,000.00 120,000.00
Kepala tukang 1.5000 org X Rp. 90,000.00 135,000.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.1600 org X Rp. 80,000.00 12,800.00
JUMLAH 322,800.00 9,450.00 332,250.00

PSI3 1 bh Memasang kloset jongkok teraso


Kloset jongkok teraso 1.0000 bh X Rp. 113,400.00 113,400.00
Batu merah ( 5x11x23 ) 7.0000 bh X Rp. - 0.00
Portland Cement (PC) 6.0000 kg X Rp. 1,375.00 8,250.00
Pasir pasang ( progo ) 0.0100 m3 X Rp. 120,000.00 1,200.00
Tukang batu 1.5000 org X Rp. 80,000.00 120,000.00
Kepala tukang 0.3000 org X Rp. 90,000.00 27,000.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.1100 org X Rp. 80,000.00 8,800.00
JUMLAH 210,800.00 122,850.00 333,650.00

PSI4 1 bh Memasang urinoir


Urinoir putih 1.0000 bh X Rp. - 0.00
Harga urinoir (Perlengkapan) 30% x X Rp. - 0.00
Portland Cement (PC) 6.0000 kg X Rp. 1,375.00 8,250.00
Pasir pasang ( progo ) 0.0100 m3 X Rp. 120,000.00 1,200.00
Tukang batu 1.0000 org X Rp. 80,000.00 80,000.00
Kepala tukang 0.1000 org X Rp. 90,000.00 9,000.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.1000 org X Rp. 80,000.00 8,000.00
JUMLAH 152,000.00 9,450.00 161,450.00

PSI5 1 bh Memasang wastafel


Wastafel putih (KIA) 1.0000 bh X Rp. 535,500.00 535,500.00
Harga wastafel (Perlengkapan) 12% x X Rp. 64,260.00 7,711.20
Portland Cement (PC) 6.0000 kg X Rp. 1,375.00 8,250.00
Pasir pasang ( progo ) 0.0100 m3 X Rp. 120,000.00 1,200.00
Tukang batu 1.4500 org X Rp. 80,000.00 116,000.00
Kepala tukang 0.1500 org X Rp. 90,000.00 13,500.00
Pekerja 1.2000 org X Rp. 55,000.00 66,000.00
Mandor 0.1000 org X Rp. 80,000.00 8,000.00
JUMLAH 203,500.00 552,661.20 756,161.20

PSI6 1 bh Memasang bak mandi f ibergl ass vol ume 0 ,30 m3


Bak mandi fiber glass 0,30 m3 1.0000 bh X Rp. 360,900.00 360,900.00
Harga bak(Perlengkapan) 18% x X Rp. 64,962.00 11,693.16
Tukang batu 2.7000 org X Rp. 80,000.00 216,000.00
Kepala tukang 0.5400 org X Rp. 90,000.00 48,600.00
Pekerja 1.8000 org X Rp. 55,000.00 99,000.00
Mandor 0.1100 org X Rp. 80,000.00 8,800.00
JUMLAH 372,400.00 372,593.16 744,993.16

PSI7 1 bh Memasang badkip porselen


Badkip 1.0000 bh X Rp. - 0.00
Harga badkip (Perlengkapan) 20% x X Rp. - 0.00
Tukang batu 0.0750 org X Rp. 80,000.00 6,000.00
Kepala tukang 0.7500 org X Rp. 90,000.00 67,500.00
Pekerja org X Rp. 55,000.00 0.00
Mandor 0.2500 org X Rp. 80,000.00 20,000.00
JUMLAH 93,500.00 0.00 93,500.00

PSI8 1 m 2 Me masang bak f ibergl ass vol ume 1 m 3 air


Bak mandi fiber glass 1,00 m3 1.0000 bh X Rp. 459,400.00 459,400.00
Harga bak (Perlengkapan) 12% x X Rp. 55,128.00 6,615.36
Tukang batu 4.5000 org X Rp. 80,000.00 360,000.00
Kepala tukang 0.9000 org X Rp. 90,000.00 81,000.00
Pekerja 3.0000 org X Rp. 55,000.00 165,000.00
Mandor 0.9000 org X Rp. 80,000.00 72,000.00
JUMLAH 678,000.00 466,015.36 1,144,015.36

PSI9 Memasang pipa penyalur air limbah jenis pipa tanah, diameter 15 cm
Pipa tanah dia. 15 cm 1.6000 bh X Rp. - 0.00
Portland Cement (PC) 0.6800 kg X Rp. 1,375.00 935.00
Pasir pasang ( progo ) 0.0130 m3 X Rp. 120,000.00 1,560.00
Pasir urug darat 0.0110 m3 X Rp. 94,500.00 1,039.50
Tukang batu 0.0300 org X Rp. 80,000.00 2,400.00
Kepala tukang 0.0030 org X Rp. 90,000.00 270.00
Pekerja 0.0600 org X Rp. 55,000.00 3,300.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 6,170.00 3,534.50 9,704.50

PSI10 1 m' Memasang pipa penyalur air limbah jenis pipa tanah, diameter 20 cm
Pipa tanah dia. 20 cm 1.6000 bh X Rp. - 0.00
Portland Cement (PC) 0.8700 kg X Rp. 1,375.00 1,196.25
Pasir pasang ( progo ) 0.0140 m3 X Rp. 120,000.00 1,680.00
Pasir urug darat 0.1400 m3 X Rp. 94,500.00 13,230.00
Tukang batu 0.0400 org X Rp. 80,000.00 3,200.00
Kepala tukang 0.0040 org X Rp. 90,000.00 360.00
Pekerja 0.0800 org X Rp. 55,000.00 4,400.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 8,520.00 16,106.25 24,626.25

PSI11 1 m' Memasang pipa beton, diameter 15 cm - 20 cm


Pipa beton 15 x 30 Panjang 1 m 1.1000 bh X Rp. - 0.00
Batu merah ( 5x11x23 ) 16.0000 bh X Rp. - 0.00
Portland Cement (PC) 3.9200 kg X Rp. 1,375.00 5,390.00
0.0560 m
3
Pasir pasang ( progo ) X Rp. 120,000.00 6,720.00
Pasir urug darat 0.0240 m3 X Rp. 94,500.00 2,268.00
Tukang batu 0.0700 org X Rp. 80,000.00 5,600.00
Kepala tukang 0.0070 org X Rp. 90,000.00 630.00
Pekerja 0.1400 org X Rp. 55,000.00 7,700.00
Mandor 0.0070 org X Rp. 80,000.00 560.00
JUMLAH 14,490.00 14,378.00 28,868.00

PSI12 1 m' Memasang pipa beton, diameter 30 cm - 100 cm


Pipa beton 20 x 30 Panjang 1 m 1.1000 bh X Rp. - 0.00
Batu merah ( 5x11x23 ) 330.0000 bh X Rp. - 0.00
Portland Cement (PC) 10.3000 kg X Rp. 1,375.00 14,162.50
Pasir pasang ( progo ) 0.0610 m3 X Rp. 120,000.00 7,320.00
Pasir urug darat 0.0690 m3 X Rp. 94,500.00 6,520.50
Tukang batu 0.1900 org X Rp. 80,000.00 15,200.00
Kepala tukang 0.0190 org X Rp. 90,000.00 1,710.00
Pekerja 0.3800 org X Rp. 55,000.00 20,900.00
Mandor 0.0190 org X Rp. 80,000.00 1,520.00
JUMLAH 39,330.00 28,003.00 67,333.00

PSI13 1 bh Memasang bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm
Batu merah ( 5x11x23 ) 87.0000 bh X Rp. - 0.00
Portland Cement (PC) 44.0000 kg X Rp. 1,375.00 60,500.00
Pasir pasang ( progo ) 0.0700 m3 X Rp. 120,000.00 8,400.00
Krikil beton 0.0700 m3 X Rp. 170,100.00 11,907.00
Besi beton polos 1.6000 kg X Rp. 11,600.00 18,560.00
Pasir beton 0.0600 m3 X Rp. 120,000.00 7,200.00
Tukang batu 1.0150 org X Rp. 80,000.00 81,200.00
Kepala tukang 0.0015 org X Rp. 90,000.00 135.00
Pekerja 3.2000 org X Rp. 55,000.00 176,000.00
Mandor 0.0160 org X Rp. 80,000.00 1,280.00
JUMLAH 258,615.00 106,567.00 365,182.00

PSI14 1 bh Memasang bak kontrol pasangan batu bata ukuran (45 x 45) cm, tinggi 50 cm
Batu merah ( 5x11x23 ) 150.0000 bh X Rp. - 0.00
Portland Cement (PC) 77.0000 kg X Rp. 1,375.00 105,875.00
Pasir pasang ( progo ) 0.1300 m3 X Rp. 120,000.00 15,600.00
Krikil beton 0.0200 m3 X Rp. 170,100.00 3,402.00
Besi beton polos 2.6000 kg X Rp. 11,600.00 30,160.00
Pasir beton 0.0900 m3 X Rp. 120,000.00 10,800.00
Tukang batu 0.4730 org X Rp. 80,000.00 37,840.00
Kepala tukang 0.0470 org X Rp. 90,000.00 4,230.00
Pekerja 1.4200 org X Rp. 55,000.00 78,100.00
Mandor 0.0710 org X Rp. 80,000.00 5,680.00
JUMLAH 125,850.00 165,837.00 291,687.00

PSI15 1 bh Memasang bak kontrol pasangan batu bata ukuran (60 x 60) cm, tingg 65 cm
Batu merah ( 5x11x23 ) 222.0000 bh X Rp. - 0.00
Portland Cement (PC) 114.0000 kg X Rp. 1,375.00 156,750.00
Pasir pasang ( progo ) 0.1840 m3 X Rp. 120,000.00 22,080.00
Krikil beton 0.0330 m3 X Rp. 170,100.00 5,613.30
Besi beton polos 4.8500 kg X Rp. 11,600.00 56,260.00
Pasir beton 0.1200 m3 X Rp. 120,000.00 14,400.00
Tukang batu 0.7200 org X Rp. 80,000.00 57,600.00
Kepala tukang 0.0720 org X Rp. 90,000.00 6,480.00
Pekerja 2.1600 org X Rp. 55,000.00 118,800.00
Mandor 0.1000 org X Rp. 80,000.00 8,000.00
JUMLAH 190,880.00 255,103.30 445,983.30

PSI16 1 m' Memasang pipa galvanis diameter 1/2"


1.2000 m
1
Pipa galvanis dia. 1/2" X Rp. - 0.00
Harga pipa (Perlengkapan) 35% x X Rp. - 0.00
Tukang batu 0.0900 org X Rp. 80,000.00 7,200.00
Kepala tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0540 org X Rp. 55,000.00 2,970.00
Mandor 0.0270 org X Rp. 80,000.00 2,160.00
JUMLAH 13,140.00 0.00 13,140.00

PSI17 1 m' Memasang pipa galvanis diameter 3/4"


Pipa galvanis dia. 3/4" 1.2000 m1 X Rp. - 0.00
Harga pipa (Perlengkapan) 35% x X Rp. - 0.00
Tukang batu 0.0900 org X Rp. 80,000.00 7,200.00
Kepala tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0540 org X Rp. 55,000.00 2,970.00
Mandor 0.0270 org X Rp. 80,000.00 2,160.00
JUMLAH 13,140.00 0.00 13,140.00

PSI18 1 m' Memasang pipa galvanis diameter 1"


Pipa galvanis dia. 1" 1.2000 m1 X Rp. - 0.00
Harga pipa (Perlengkapan) 35% x X Rp. - 0.00
Tukang batu 0.0900 org X Rp. 80,000.00 7,200.00
Kepala tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0540 org X Rp. 55,000.00 2,970.00
Mandor 0.0270 org X Rp. 80,000.00 2,160.00
JUMLAH 13,140.00 0.00 13,140.00

PSI19 1 m' Memasang pipa galvanis diameter 1 1/2"


Pipa galvanis dia. 1 1/2" 1.2000 m1 X Rp. - 0.00
Harga pipa (Perlengkapan) 35% x X Rp. - 0.00
Tukang batu 0.1800 org X Rp. 80,000.00 14,400.00
Kepala tukang 0.0180 org X Rp. 90,000.00 1,620.00
Pekerja 0.1080 org X Rp. 55,000.00 5,940.00
Mandor 0.0054 org X Rp. 80,000.00 432.00
JUMLAH 22,392.00 0.00 22,392.00

PSI20 1 m' Memasang pipa galvanis diameter 3"


Pipa galvanis dia. 3" 1.2000 m1 X Rp. - 0.00
Harga pipa (Perlengkapan) 35% x X Rp. - 0.00
Tukang batu 0.1800 org X Rp. 80,000.00 14,400.00
Kepala tukang 0.0180 org X Rp. 90,000.00 1,620.00
Pekerja 0.1080 org X Rp. 55,000.00 5,940.00
Mandor 0.0054 org X Rp. 80,000.00 432.00
JUMLAH 22,392.00 0.00 22,392.00

PSI21 1 m' Memasang pipa galvanis diameter 4"


Pipa galvanis dia. 4" 1.2000 m1 X Rp. - 0.00
Harga pipa (Perlengkapan) 35% x X Rp. - 0.00
Tukang batu 0.2250 org X Rp. 80,000.00 18,000.00
Kepala tukang 0.0225 org X Rp. 90,000.00 2,025.00
Pekerja 0.1350 org X Rp. 55,000.00 7,425.00
Mandor 0.0068 org X Rp. 80,000.00 544.00
JUMLAH 27,994.00 0.00 27,994.00

PSI22 1 m' Memasang pipa PVC tipe AW diameter 1/2"


Pipa PVC abu-abu dia. 1/2" Wavin 1.2000 m1 X Rp. 13,700.00 16,440.00
Harga pipa (Perlengkapan) 35% x X Rp. 4,795.00 1,678.25
Tukang batu 0.0600 org X Rp. 80,000.00 4,800.00
Kepala tukang 0.0060 org X Rp. 90,000.00 540.00
Pekerja 0.0360 org X Rp. 55,000.00 1,980.00
Mandor 0.0018 org X Rp. 80,000.00 144.00
JUMLAH 7,464.00 18,118.25 25,582.25

PSI23 1 m' Memasang pipa PVC tipe AW diameter 3/4"


Pipa PVC abu-abu dia. 3/4" Wavin 1.2000 m1 X Rp. 18,900.00 22,680.00
Harga pipa (Perlengkapan) 35% x X Rp. 6,615.00 2,315.25
Tukang batu 0.0600 org X Rp. 80,000.00 4,800.00
Kepala tukang 0.0060 org X Rp. 90,000.00 540.00
Pekerja 0.0360 org X Rp. 55,000.00 1,980.00
Mandor 0.0018 org X Rp. 80,000.00 144.00
JUMLAH 7,464.00 24,995.25 32,459.25

PSI24 1 m' Memasang pipa PVC tipe AW diameter 1"


Pipa PVC abu-abu dia. 1" Wavin 1.2000 m1 X Rp. 25,900.00 31,080.00
Harga pipa (Perlengkapan) 35% x X Rp. 9,065.00 3,172.75
Tukang batu 0.0600 org X Rp. 80,000.00 4,800.00
Kepala tukang 0.0060 org X Rp. 90,000.00 540.00
Pekerja 0.0360 org X Rp. 55,000.00 1,980.00
Mandor 0.0018 org X Rp. 80,000.00 144.00
JUMLAH 7,464.00 34,252.75 41,716.75

PSI25 1 m' Memasang pipa PVC tipe AW diameter 1 1/2"


Pipa PVC abu-abu dia. 1 1/2" Wavin 1.2000 m1 X Rp. 44,500.00 53,400.00
Harga pipa (Perlengkapan) 35% x X Rp. 15,575.00 5,451.25
Tukang batu 0.0600 org X Rp. 80,000.00 4,800.00
Kepala tukang 0.0060 org X Rp. 90,000.00 540.00
Pekerja 0.0360 org X Rp. 55,000.00 1,980.00
Mandor 0.0018 org X Rp. 80,000.00 144.00
JUMLAH 7,464.00 58,851.25 66,315.25

PSI26 1 m' Memasang pipa PVC tipe AW diameter 2"


Pipa PVC abu-abu dia. 2" Wavin 1.2000 m1 X Rp. 56,900.00 68,280.00
Harga pipa (Perlengkapan) 35% x X Rp. 19,915.00 6,970.25
Tukang batu 0.0900 org X Rp. 80,000.00 7,200.00
Kepala tukang 0.0090 org X Rp. 90,000.00 810.00
Pekerja 0.0544 org X Rp. 55,000.00 2,992.00
Mandor 0.0027 org X Rp. 80,000.00 216.00
JUMLAH 11,218.00 75,250.25 86,468.25

PSI27 1 m' Memasang pipa PVC tipe AW diameter 2 1/2"


Pipa PVC abu-abu dia. 2 1/2" Wavin 1.2000 m1 X Rp. 83,100.00 99,720.00
Harga pipa (Perlengkapan) 35% x X Rp. 29,085.00 10,179.75
Tukang batu 0.0600 org X Rp. 80,000.00 4,800.00
Kepala tukang 0.0060 org X Rp. 90,000.00 540.00
Pekerja 0.0360 org X Rp. 55,000.00 1,980.00
Mandor 0.0018 org X Rp. 80,000.00 144.00
JUMLAH 7,464.00 109,899.75 117,363.75

PSI28 1 m' Memasang pipa PVC tipe AW diameter 3"


Pipa PVC abu-abu dia. 3" Wavin 1.2000 m1 X Rp. 112,100.00 134,520.00
Harga pipa (Perlengkapan) 35% x X Rp. 39,235.00 13,732.25
Tukang batu 0.1350 org X Rp. 80,000.00 10,800.00
Kepala tukang 0.0135 org X Rp. 90,000.00 1,215.00
Pekerja 0.0810 org X Rp. 55,000.00 4,455.00
Mandor 0.0410 org X Rp. 80,000.00 3,280.00
JUMLAH 19,750.00 148,252.25 168,002.25

PSI29 1 m' Memasang pipa PVC tipe AW diameter 4"


Pipa PVC abu-abu dia. 4" Wavin 1.2000 m1 X Rp. 185,800.00 222,960.00
Harga pipa (Perlengkapan) 35% x X Rp. 65,030.00 22,760.50
Tukang batu 0.1350 org X Rp. 80,000.00 10,800.00
Kepala tukang 0.0135 org X Rp. 90,000.00 1,215.00
Pekerja 0.0810 org X Rp. 55,000.00 4,455.00
Mandor 0.0410 org X Rp. 80,000.00 3,280.00
JUMLAH 19,750.00 245,720.50 265,470.50

PSI30 1 bh Memasang bak cuci piring stainless steel


Bak cuci stainless steel 1.0000 bh X Rp. - 0.00
Water drain + asesories 1.0000 set X Rp. - 0.00
Tukang batu 0.3000 org X Rp. 80,000.00 24,000.00
Kepala tukang 0.0300 org X Rp. 90,000.00 2,700.00
Pekerja 0.0300 org X Rp. 55,000.00 1,650.00
Mandor 0.0015 org X Rp. 80,000.00 120.00
JUMLAH 28,470.00 0.00 28,470.00

PSI31 1 bh Memasang bak cuci piring teraso


Bak cuci teraso 1.0000 bh X Rp. - 0.00
Water drain + asesories 1.0000 set X Rp. - 0.00
Portland Cement (PC) 20.0000 kg X Rp. 1,375.00 27,500.00
Pasir pasang ( progo ) 0.0500 m3 X Rp. 120,000.00 6,000.00
Tukang batu 0.5000 org X Rp. 80,000.00 40,000.00
Kepala tukang 0.0500 org X Rp. 90,000.00 4,500.00
Pekerja 0.0500 org X Rp. 55,000.00 2,750.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 47,450.00 33,500.00 80,950.00

PSI32 1 bh Memasang kran diameter 3/4" atau 1/2"


Kran air diameter 3/4" atau 1/2" exs. Toto 1.0000 bh X Rp. 19,700.00 19,700.00
Seal tape 0.0250 bh X Rp. - 0.00
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.0100 org X Rp. 55,000.00 550.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 9,850.00 19,700.00 29,550.00

PSI33 1 bh Memasang floor drain


Floordrain 1.0000 bh X Rp. 78,100.00 78,100.00
Tukang batu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.0100 org X Rp. 55,000.00 550.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 9,850.00 78,100.00 87,950.00

PSI34 1 bh Memasang shower dinding


Shower dinding 1.000 bh X Rp. - 0.00
Pekerja 0.010 org/hr X Rp. 55,000.00 550.00
Tukang pipa ledeng 0.100 org/hr X Rp. - 0.00
JUMLAH 550.00 0.00 550.00

PSI35 1 bh Memasang kran air angsa


Kran air angsa 1.000 bh X Rp. 206,700.00 206,700.00
Perlengkapan 1.000 set X Rp. - 0.00
Pekerja 0.010 org/hr X Rp. 55,000.00 550.00
Tukang pipa ledeng 0.100 org/hr X Rp. - 0.00
JUMLAH 207,250.00 0.00 207,250.00

PSI36 1 bh Memasang tempat sabun


Tempat sabun 1 bh X Rp. 52,500.00 52,500.00
Pekerja 0.01 org/hr X Rp. 55,000.00 550.00
Tukang pipa ledeng 0.1 org/hr X Rp. - 0.00
550.00 52,500.00 53,050.00

PEKERJAAN KUNCI DAN KACA

PPG1 1 bh Pasang kunci tanam antik


Kunci tanam antik 1.0000 bh X Rp. 157,500.00 157,500.00
Tukang kayu 0.6000 org X Rp. 80,000.00 48,000.00
Kepala tukang 0.0600 org X Rp. 90,000.00 5,400.00
Pekerja 0.0600 org X Rp. 55,000.00 3,300.00
Mandor 0.0030 org X Rp. 80,000.00 240.00
JUMLAH 56,940.00 157,500.00 214,440.00

PPG2 1 bh Pasang kunci tanam biasa


Kunci tanam biasa 1.0000 bh X Rp. 69,300.00 69,300.00
Tukang kayu 0.5000 org X Rp. 80,000.00 40,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.0100 org X Rp. 55,000.00 550.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 41,850.00 69,300.00 111,150.00

PPG3 1 bh Pasang kunci tanam kamar mandi


Kunci tanam 1.0000 bh X Rp. 69,300.00 69,300.00
Tukang kayu 0.5000 org X Rp. 80,000.00 40,000.00
Kepala tukang 0.0050 org X Rp. 90,000.00 450.00
Pekerja 0.0050 org X Rp. 55,000.00 275.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 40,925.00 69,300.00 110,225.00

PPG4 1 bh Pasang kunci tanam silinder


Kunci silinder 1.0000 bh X Rp. - 0.00
Tukang kayu 0.5000 org X Rp. 80,000.00 40,000.00
Kepala tukang 0.0050 org X Rp. 90,000.00 450.00
Pekerja 0.0050 org X Rp. 55,000.00 275.00
Mandor 0.0003 org X Rp. 80,000.00 20.00
JUMLAH 40,745.00 0.00 40,745.00

PPG5 1 bh Pasang engsel pintu


Engsel pintu 1.0000 bh X Rp. 31,500.00 31,500.00
Tukang kayu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.0150 org X Rp. 55,000.00 825.00
Mandor 0.0008 org X Rp. 80,000.00 60.00
JUMLAH 14,235.00 31,500.00 45,735.00

PPG6 1 bh Pasang engsel jendela kupu-kupu


Engsel jendela 1.0000 bh X Rp. 22,100.00 22,100.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.0100 org X Rp. 55,000.00 550.00
Mandor 0.0050 org X Rp. 80,000.00 400.00
JUMLAH 9,850.00 22,100.00 31,950.00

PPG7 1 bh Pasang engsel angin


Engsel angin 1.0000 bh X Rp. - 0.00
Tukang kayu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.0200 org X Rp. 55,000.00 1,100.00
Mandor 0.0100 org X Rp. 80,000.00 800.00
JUMLAH 19,700.00 0.00 19,700.00

PPG8 1 bh Pasang spring knip


Spring knip 1.0000 bh X Rp. - 0.00
Tukang kayu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.0150 org X Rp. 55,000.00 825.00
Mandor 0.0008 org X Rp. 80,000.00 60.00
JUMLAH 14,235.00 0.00 14,235.00

PPG9 1 bh Pasang kait angin


Kait angin 1.0000 bh X Rp. - 0.00
Tukang kayu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.0150 org X Rp. 55,000.00 825.00
Mandor 0.0008 org X Rp. 80,000.00 60.00
JUMLAH 14,235.00 0.00 14,235.00

PPG10 1 m' Pasang door closer


Door closer 1.0000 bh X Rp. - 0.00
Tukang kayu 0.5000 org X Rp. 80,000.00 40,000.00
Kepala tukang 0.0500 org X Rp. 90,000.00 4,500.00
Pekerja 0.0500 org X Rp. 55,000.00 2,750.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 47,450.00 0.00 47,450.00

PPG11 1 bh Pasang kunci selot


Kunci selot 1.0000 bh X Rp. - 0.00
Tukang kayu 0.2000 org X Rp. 80,000.00 16,000.00
Kepala tukang 0.0200 org X Rp. 90,000.00 1,800.00
Pekerja 0.0200 org X Rp. 55,000.00 1,100.00
Mandor 0.0010 org X Rp. 80,000.00 80.00
JUMLAH 18,980.00 0.00 18,980.00

PPG12 1 bh Pasang pegangan pintu / door holder


Door holder 1.0000 bh X Rp. - 0.00
Tukang kayu 0.5000 org X Rp. 80,000.00 40,000.00
Kepala tukang 0.0500 org X Rp. 90,000.00 4,500.00
Pekerja 0.0500 org X Rp. 55,000.00 2,750.00
Mandor 0.0025 org X Rp. 80,000.00 200.00
JUMLAH 47,450.00 0.00 47,450.00

PPG13 1 bh Pasang door stop


Door stop 1.0000 bh X Rp. - 0.00
Tukang kayu 0.1000 org X Rp. 80,000.00 8,000.00
Kepala tukang 0.0100 org X Rp. 90,000.00 900.00
Pekerja 0.0100 org X Rp. 55,000.00 550.00
Mandor 0.0005 org X Rp. 80,000.00 40.00
JUMLAH 9,490.00 0.00 9,490.00

PPG14 1 bh Pasang rel pintu dorong


Penggantung + rel pintu dorong 1.0000 bh X Rp. - 0.00
Tukang kayu 0.6000 org X Rp. 80,000.00 48,000.00
Kepala tukang 0.0600 org X Rp. 90,000.00 5,400.00
Pekerja 0.0600 org X Rp. 55,000.00 3,300.00
Mandor 0.0030 org X Rp. 80,000.00 240.00
JUMLAH 56,940.00 0.00 56,940.00

PPG15 1 bh Pasang kunci lemari


Kunci lemari 1.0000 bh X Rp. - 0.00
Tukang kayu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.0250 org X Rp. 55,000.00 1,375.00
Mandor 0.0013 org X Rp. 80,000.00 100.00
JUMLAH 23,725.00 0.00 23,725.00

PPG16 1 m2 Pasang kaca


Kaca polos 1.1000 m2 X Rp. 60,900.00 66,990.00
Tukang kayu 0.1500 org X Rp. 80,000.00 12,000.00
Kepala tukang 0.0150 org X Rp. 90,000.00 1,350.00
Pekerja 0.0150 org X Rp. 55,000.00 825.00
Mandor 0.0008 org X Rp. 80,000.00 60.00
JUMLAH 14,235.00 66,990.00 81,225.00

PPG17 1 m' Pasang kusen alumunium


Kusen alumunium uk 2"x4" tebal 1.2 mm sekualitas YKK p 1.1000 m1 X Rp. - 0.00
Harga kusen (Perlengkapan) 15% x X Rp. - 0.00
Tukang alumunium 0.1500 oh X Rp. 80,000.00 12,000.00
Kepala tukang 0.0150 oh X Rp. 90,000.00 1,350.00
Pekerja 0.0150 oh X Rp. 55,000.00 825.00
Mandor 0.0008 oh X Rp. 80,000.00 60.00
JUMLAH 14,235.00 0.00 14,235.00

PEKERJAAN TAMAN
PTM1 10 m2 Penyapuan Jalan Dan Trotoar
Sapu lidi 447.00 bh X Rp. - 0.00
Tangkai Sapu 14.00 bh X Rp. - 0.00
Serok 8.0000 bh X Rp. - 0.00
Seragam 16.00 bh X Rp. - 0.00
Sarung tangan 14.00 bh X Rp. 3,900.00 54,600.00
Masker 14.00 bh X Rp. 17,100.00 239,400.00
Gerobak (sewa) 4.00 bh X Rp. - 0.00
Pekerja 2,555.00 org X Rp. 55,000.00 140,525,000.00
Mandor 365.00 org X Rp. 80,000.00 29,200,000.00
JUMLAH 169,725,000.00 294,000.00 170,019,000.00
BIAYA TI AP 1M2 / HA RI :
/ 3,650,000.00 46.50 0.08 46.58

PTM2 1 m2 Pembersihan / Penyapuan halaman


Sapu lidi 0.1506 bh X Rp. - 0.00
Serok 0.0109 bh X Rp. - 0.00
Seragam 0.0082 bh X Rp. - 0.00
Gerobak (sewa) 0.0009 bh X Rp. - 0.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.1428 org X Rp. 80,000.00 11,424.00
JUMLAH 66,424.00 0.00 66,424.00
BIAYA TI AP 1M2 / HA RI :
/ 1,000.00 66.42 0.00 66.42

PTM3 1000 m2 Pemangkasan teh-tehan


Gunting pangkas 0.0280 bh X Rp. - 0.00
Gerobak (sewa) 0.0030 bh X Rp. - 0.00
Pekerja 5.0000 org X Rp. 55,000.00 275,000.00
Mandor 0.5000 org X Rp. 80,000.00 40,000.00
JUMLAH 315,000.00 0.00 315,000.00
DIBULATKAN 315,000.00
BIAYA TI AP 1M2 / HA RI :
/ 30,000.00 10.50 0.00 10.50

PTM4 1 m2 Pangkas bentuk tanaman perdu


Gunting pangkas 0.0890 bh X Rp. - 0.00
Gerobak (sewa) 0.0060 bh X Rp. - 0.00
Pekerja 8.0000 org X Rp. 55,000.00 440,000.00
Mandor 1.0000 org X Rp. 80,000.00 80,000.00
JUMLAH 520,000.00 0.00 520,000.00
DIKERJAKAN 2 KALI ( Dalam 1 bulan ) 1,040,000.00 0.00 1,040,000.00
BIAYA TI AP 1M2 / HA RI :
1,040,000.00 / 30,000.00 34.67 0.00 34.67

PTM5 1 m2 Pangkas rumput


Mesin potong rumput 0.0010 bh X Rp. - 0.00
Sapu lidi 1.0000 bh X Rp. - 0.00
Gerobak (sewa) 0.0030 bh X Rp. - 0.00
Bensin premium 6.0000 ltr X Rp. - 0.00
Pekerja 1.0000 org X Rp. 55,000.00 55,000.00
Mandor 0.5000 org X Rp. 80,000.00 40,000.00
JUMLAH 95,000.00 0.00 95,000.00
DIKERJAKAN 2 KALI ( Dalam 1 bulan ) 190,000.00 0.00 190,000.00
BIAYA TI AP 1M2 / HA RI :
190,000.00 / 30,000.00 6.33 0.00 6.33

PTM6 1 m2 Penyiangan tanaman semak dan penggemburan tanah


Garpu tanah 0.0230 bh X Rp. - 0.00
Arit 0.0230 bh X Rp. - 0.00
Pekerja 4.0000 org X Rp. 55,000.00 220,000.00
Mandor 1.0000 org X Rp. 80,000.00 80,000.00
JUMLAH 300,000.00 0.00 300,000.00
DIKERJAKAN 2 KALI ( Dalam 1 bulan ) 600,000.00 0.00 600,000.00
BIAYA TI AP 1M2 / HA RI :
600,000.00 / 30,000.00 20.00 0.00 20.00

ANALISA TAMBAHAN (SUPLEMEN)

SPL1 1 m2 PASANG STOOT WERK (SCAFOLDING)


Main Frame (MF-1219/h = 190 cm) 4.0000 bh X Rp. - 0.00
Ladder Frame (LF-1209/h =90) 2.0000 bh X Rp. - 0.00
Join Pin (JP-42) 4.0000 bh X Rp. - 0.00
Cross Brase (CB-1218/I = 220 cm)-MF 2.0000 bh X Rp. - 0.00
Cross Brase (CB-0618/I = 193)-LF 2.0000 bh X Rp. - 0.00
Head Jack (HJ-60) 4.0000 bh X Rp. - 0.00
Base Jack (BJ-60) 4.0000 bh X Rp. - 0.00
Balok 8/12 (10x pakai) 0.0500 m3 X Rp. - 0.00
Papan Alas 3/20 (3x pakai) 0.0030 m3 X Rp. - 0.00
Kawat Pengikat 1.5000 kg X Rp. - 0.00
Pekerja 2.0000 org X Rp. 55,000.00 110,000.00
Mandor 0.2000 org X Rp. 80,000.00 16,000.00
JUMLAH 126,000.00 0.00 126,000.00
4 m2 Scafolding 2x Pakai 504,000.00 0.00 504,000.00

SPL2 1 m2 Pemasangan Geotextile


Pekerja 0.1 org/hr X Rp. 55,000.00 5,500.00
Tukan gali/timbun 0.02 org/hr X Rp. - 0.00
Mandor 0.02 org/hr X Rp. 80,000.00 1,600.00
Geotextile Polyfelt. TS 70 1.05 m2 X Rp. - 0.00
Alat bantu 1 ls X Rp. - 0.00
JUMLAH 7,100.00 0.00 7,100.00

SPL3 1 m3 Timbunan tanah merah dipadatkan


Tanah timbun 1.200 m3 X Rp. 100,800.00 120,960.00
Pekerja 0.500 org/hr X Rp. 55,000.00 27,500.00
Mandor 0.250 org/hr X Rp. 80,000.00 20,000.00
Buldozer 100 - 150 HP 0.006 hr X Rp. 369,999.61 2,055.55
Mesin Gilas 3 Roda 8 - 10 ton (Three Wheel Roller) 0.007 hr X Rp. 113,261.36 786.54
Mesin Gilas getar otomatis 5 - 8 T 0.007 hr X Rp. 236,640.05 1,643.33
Truk tangki air 100 HP 4000 L (Water Tank Truck ) 0.007 hr X Rp. 167,998.54 1,166.66
JUMLAH 47,500.00 126,612.08 174,112.08

SPL4 1 m3 Lapisan Base coarse Agregat kelas A dipadatkan


Agregat hakus/pasir klas A ( Uk. butir 5 mm ) 1.100 m3 X Rp. 288,000.00 316,800.00
Pekerja 0.500 org/hr X Rp. 55,000.00 27,500.00
Mandor 0.125 org/hr X Rp. 80,000.00 10,000.00
Motor Grader > 100 HP 0.002 hr X Rp. 384,919.36 751.46
Mesin Gilas getar otomatis 5 - 8 T 0.003 hr X Rp. 236,640.05 703.97
Truk tangki air 100 HP 4000 L (Water Tank Truck ) 0.004 hr X Rp. 167,998.54 590.36
JUMLAH 37,500.00 318,845.79 356,345.79

SPL5 1 m3 Lapisan Sub Base coarse Agregat kelas B dipadatkan


Agregat kasar/krikil/pasir klas B ( Uk. 20 - 40 ) 1.200 m3 X Rp. 276,000.00 331,200.00
Pekerja 0.500 org/hr X Rp. 55,000.00 27,500.00
Mandor 0.125 org/hr X Rp. 80,000.00 10,000.00
Motor Grader > 100 HP 0.002 hr X Rp. 384,919.36 751.46
Mesin Gilas getar otomatis 5 - 8 T 0.003 hr X Rp. 236,640.05 703.97
Truk tangki air 100 HP 4000 L (Water Tank Truck ) 0.004 hr X Rp. 167,998.54 590.36
JUMLAH 37,500.00 333,245.79 370,745.79

SPL6 1 m3 Lapisan Sub Base coarse Agregat Kelas C dipadatkan


Agregat kasar/krikil/pasir klas C ( Uk. 4½ - 19 ) 1.200 m3 X Rp. - 0.00
Pekerja 0.500 org/hr X Rp. 55,000.00 27,500.00
Mandor 0.125 org/hr X Rp. 80,000.00 10,000.00
Motor Grader > 100 HP 0.002 hr X Rp. 384,919.36 751.46
Mesin Gilas getar otomatis 5 - 8 T 0.004 hr X Rp. 236,640.05 844.77
Truk tangki air 100 HP 4000 L (Water Tank Truck ) 0.004 hr X Rp. 167,998.54 590.36
JUMLAH 37,500.00 2,186.58 39,686.58

SPL7 100 Kg memasang gelagar-gelagar besi :


Tukang besi 0.100 org/hr X Rp. 80,000.00 8,000.00
Kepala tukang 0.010 org/hr X Rp. 90,000.00 900.00
Pekerja 0.500 org/hr X Rp. 55,000.00 27,500.00
Mandor 0.025 org/hr X Rp. 80,000.00 2,000.00
38,400.00 0.00 38,400.00
JUMLAH per Kg 384.00 0.00 384.00

SPL8 100 Kg Menurunkan gelagar-gelagar besi jembatan :


Pekerja 1.500 org/hr X Rp. 55,000.00 82,500.00
Mandor 0.025 org/hr X Rp. 80,000.00 2,000.00
84,500.00 0.00 84,500.00
JUMLAH per Kg 845.00 0.00 845.00

SPL9 1 M2 Mengerjakan lantai jembatan (papan yang dipakukan diatas gelagar kayu) :
Paku biasa 1/2" - 1" 0.075 kg X Rp. 16,300.00 1,222.50
Papan kayu damar laut 0.025 X Rp. - 0.00
Tukang kayu 0.500 org/hr X Rp. 80,000.00 40,000.00
Kepala tukang 0.050 org/hr X Rp. 90,000.00 4,500.00
Pekerja 0.200 org/hr X Rp. 55,000.00 11,000.00
Mandor 0.010 org/hr X Rp. 80,000.00 800.00
JUMLAH 56,300.00 1,222.50 57,522.50

SPL10 Memasang 1 Kg jaring kawat baja/wire mesh


Kawat jaring 1.100 Kg X Rp. - 0.00
Kawat beton / bindrat 0.050 Kg X Rp. 20,000.00 1,000.00
Sewa alat Las 1.000 ls X Rp. - 0.00
Pekerja 0.027 Org/hr X Rp. 55,000.00 1,485.00
Tukang besi 0.027 Org/hr X Rp. 80,000.00 2,160.00
Kepala tukang 0.008 Org/hr X Rp. 90,000.00 675.00
Mandor 0.004 Org/hr X Rp. 80,000.00 300.00
JUMLAH 4,620.00 1,000.00 5,620.00

SPL11 1 M2 memasang lantai cone block t.10 cm dipadatkan denganVibratory Roller kapasitas 10-15 ton
Conblock t=10 cm 44.000 Bh X Rp. - 0.00
Pasir pasang ( progo ) 0.050 M3 X Rp. 120,000.00 6,000.00
Pasir pasang ( krasak ) 0.015 M3 X Rp. - 0.00
Tukang batu 0.100 org/hr X Rp. 80,000.00 8,000.00
Pekerja 0.400 org/hr X Rp. 55,000.00 22,000.00
Kepala tukang 0.010 org/hr X Rp. 90,000.00 900.00
Mandor 0.040 org/hr X Rp. 80,000.00 3,200.00
Mesin Gilas getar otomatis 5 - 8 T 0.002 hr X Rp. 236,640.05 473.28
JUMLAH 34,573.28 6,000.00 40,573.28

SPL12 10 M' memasang riol 20 cm :


Riol 20 cm 10.000 Bh X Rp. - 0.00
Portland Cement (PC) 2.660 Zak X Rp. 1,375.00 3,657.50
Pasir pasang ( progo ) 0.760 M3 X Rp. 120,000.00 91,200.00
Tukang batu 1.200 org/hr X Rp. 80,000.00 96,000.00
Kepala tukang 0.120 org/hr X Rp. 90,000.00 10,800.00
Pekerja 2.400 org/hr X Rp. 55,000.00 132,000.00
Mandor 0.120 org/hr X Rp. 80,000.00 9,600.00
JUMLAH 248,400.00 94,857.50 343,257.50
Per M' 24,840.00 9,485.75 34,325.75

SPL13 1 M2 memasang kawat harmonica :


Besi jaring kawat baja 1.050 M2 X Rp. - 0.00
Angkur / baut 6.000 Bh X Rp. - 0.00
Tukang besi 0.125 org/hr X Rp. 80,000.00 10,000.00
Pekerja 0.500 org/hr X Rp. 55,000.00 27,500.00
JUMLAH 37,500.00 0.00 37,500.00

SPL14 1 M2 memasang kawat duri :


Kawat duri 10.5 M' X Rp. - 0.00
Paku biasa 1/2" - 1" 0.025 Kg X Rp. 16,300.00 407.50
Tukang besi 0.125 org/hr X Rp. 80,000.00 10,000.00
Pekerja 0.5 org/hr X Rp. 55,000.00 27,500.00
JUMLAH 37,500.00 407.50 37,907.50

SPL15 1 m2 Pasang Aluminium Composite Panel (Alucopan) : (Jumlah volume besi disesuaikan terhadap rencana design)
Al. Composite Panel (Alucopan) 1.05 m2 X Rp. 239,400.00 251,370.00
Besi Profil 30 Kg X Rp. 12,100.00 363,000.00
Ramset / dina bolt 8 Bh X Rp. - 0.00
Sewa alat las 1 ls X Rp. - 0.00
Tukang alumunium 0.5 org/hr X Rp. 80,000.00 40,000.00
Kepala Tukang 0.05 org/hr X Rp. 90,000.00 4,500.00
Pekerja 1 org/hr X Rp. 55,000.00 55,000.00
Mandor 0.05 org/hr X Rp. 80,000.00 4,000.00
JUMLAH 103,500.00 614,370.00 717,870.00

SPL16 Mobilisasi dan Demobilisasi Peralatan


Crane Kap. 35 ton 1.000 Unit X Rp. 3,900,000.00 3,900,000.00
Hammer + Pile driver 1.000 Unit X Rp. 1,850,000.00 1,850,000.00
Piling Barge Driving 1.000 Unit X Rp. - 0.00
Ponton Kap. 1000 ton 1.000 Unit X Rp. 4,000,000.00 4,000,000.00
Work Boat 1.000 Unit X Rp. 1,000,000.00 1,000,000.00
Alat Pancang Pile Compactor 1.000 Unit X Rp. - 0.00
Generator 150 kVA 1.000 Unit X Rp. - 0.00
JUMLAH 10,750,000.00 0.00 10,750,000.00

SPL17 Pengadaan Tiang Pancang Beton dia …. Cm (Bottom)


Tiang Pancang Beton dia … cm (bottom) 1.000 M X Rp. - 0.00 0.00

SPL18 Pengadaan Tiang Pancang Beton dia …. Cm (Upper/Middle)


Tiang Pancang Beton dia … cm (upper) 1.000 M X Rp. - 0.00 0.00

SPL19 1 bh Handling dan Transport tiang pancang dan penimbunan ke titik pancang
Pekerja 8.400 oh X Rp. 55,000.00 462,000.00
Tukang Pancang 0.800 oh X Rp. - 0.00
Alat Bantu 1.000 ls X Rp. - 0.00
JUMLAH 462,000.00 0.00 462,000.00

SPL20 1 m Pemancangan tiang pancang (Darat)


Asumsi : Pemancangan tiang 120 m/hari
Pekerja 6.000 Org/hr X Rp. 55,000.00 330,000.00
Operator terlatih 4.000 Org/hr X Rp. - 0.00
Pembantu Operator 4.000 Org/hr X Rp. - 0.00
Mandor 1.000 Org/hr X Rp. 80,000.00 80,000.00
Ahli ukur 2.000 Org/hr X Rp. - 0.00
Crane Kap. 35 ton 1.000 hr X Rp. 3,900,000.00 3,900,000.00
Hammer + Pile driver 1.000 hr X Rp. 1,850,000.00 1,850,000.00
Waterpass 1.000 unit X Rp. - 0.00
Alat Bantu 1.000 unit X Rp. - 0.00
JUMLAH 6,160,000.00 0.00 6,160,000.00
per m' 51,333.33 0.00 51,333.33

SPL21 1 m Pemancangan tiang (Laut)


Asumsi : Pemancangan tiang 80 m/hari
Pekerja 5.000 Org/hr X Rp. 55,000.00 275,000.00
Penyelam 3.000 Org/hr X Rp. - 0.00
Operator terlatih 5.000 Org/hr X Rp. - 0.00
Pembantu Operator 5.000 Org/hr X Rp. - 0.00
Mandor 1.000 Org/hr X Rp. 80,000.00 80,000.00
Ahli ukur 2.000 Org/hr X Rp. - 0.00
Crane Kap. 35 ton 1.000 hr X Rp. 3,900,000.00 3,900,000.00
Hammer + Pile driver 1.000 hr X Rp. 1,850,000.00 1,850,000.00
Piling Barge Driving 1.000 hr X Rp. - 0.00
Ponton Kap. 1000 ton 1.000 hr X Rp. 4,000,000.00 4,000,000.00
Work Boat 1.000 hr X Rp. 1,000,000.00 1,000,000.00
Generator 150 kVA 1.000 hr X Rp. - 0.00
Theodolite 1.000 unit X Rp. - 0.00
Alat Bantu 1.000 unit X Rp. - 0.00
JUMLAH 11,105,000.00 0.00 11,105,000.00
per M' 138,812.50 0.00 138,812.50

SPL22 Pengangkatan 1 m Tiang Pancang ke titik pancang (Darat)


Asumsi : Pengangkatan ke titik pancang 200 m Tiang Pancang/hari
Pekerja 2.000 org/hr X Rp. 55,000.00 110,000.00
Operator terlatih 1.000 org/hr X Rp. - 0.00
Pembantu Operator 1.000 org/hr X Rp. - 0.00
Mandor 1.000 org/hr X Rp. 80,000.00 80,000.00
Crane Kap. 10-15 Ton 0.500 hr X Rp. 2,800,000.00 1,400,000.00
Alat Bantu 1.000 unit X Rp. - 0.00
JUMLAH 13,833,812.50 0.00 13,833,812.50
per M' 69,169.06 0.00 69,169.06

SPL23 Pengangkatan 1 m Sheet Pile ke titik pancang (laut)


Asumsi : Pengangkatan ke titik pancang = 300 m sheet pile/hari
Pekerja 4.000 org/hr X Rp. - 0.00
Operator terlatih 2.000 org/hr X Rp. - 0.00
Pembantu Operator 2.000 org/hr X Rp. - 0.00
Mandor 1.000 org/hr X Rp. - 0.00
Crane Kap. 10-15 Ton 0.050 hr X Rp. - 0.00
Alat Bantu 1.000 unit X Rp. - 0.00
JUMLAH 0.00 0.00 0.00
per M' 0.00 0.00 0.00

SPL24 1 m' Pemancangan Sheet Pile


Asumsi : Pemancangan tiang 120 m'/hari
Pekerja 6.000 Org/hr X Rp. 55,000.00 330,000.00
Operator terlatih 2.000 Org/hr X Rp. - 0.00
Pembantu Operator 2.000 Org/hr X Rp. - 0.00
Mandor 1.000 Org/hr X Rp. 80,000.00 80,000.00
Crawler Crane Kap. 35 ton 1.000 hr X Rp. - 0.00
Alat Pancang Pile Compactor 1.000 hr X Rp. - 0.00
Alat Bantu 1.000 unit X Rp. - 0.00
JUMLAH 410,000.00 0.00 410,000.00
per M' 3,416.67 0.00 3,416.67

SPL25 1 bh Sambungan tiang pancang beton/spun pile dia 50 cm


Pengelasan 3x 471 cm X Rp. 414.00 194,994.00
Pengecatan Epoxy/Tar 0.628 m2 X Rp. 52,020.00 32,668.56
JUMLAH 227,662.56 0.00 227,662.56

SPL26 1 bh Sambungan tiang pancang baja dia 50 cm


Besi pelat/baja tulangan dia 19 mm 6.000 kg X Rp. - 0.00
Pengelasan 3x 471.000 cm X Rp. 414.00 194,994.00
Pengecatan Epoxy/Tar 0.628 m2 X Rp. 52,020.00 32,668.56
JUMLAH 227,662.56 0.00 227,662.56

SPL27 1 bh Memotong tiang pancang beton/ spun pile dia 50 cm


Pekerja 1 oh X Rp. 55,000.00 55,000.00
mandor 0.390 oh X Rp. 80,000.00 31,200.00
memotong baja 157.000 cm X Rp. 414.00 64,998.00
Pengecatan Epoxy/Tar 0.100 m2 X Rp. 52,020.00 5,202.00
JUMLAH 156,400.00 0.00 156,400.00

SPL28 1 m' Pembuatan tiang pancang (40 x 40) cm, beton bertulang
Beton mutu f’'c = 26,4 MPa (K 300) 0.1760 m3 X Rp. 910,070.10 160,172.34
Besi beton polos 30.0000 kg X Rp. 13,516.00 405,480.00
Bekisting 1.6000 m2 X Rp. 220,010.00 352,016.00
Minyak bekisting 0.1600 ltr X Rp. - 0.00
Bongkar bekisting 1.0000 ls X Rp. 220,000.00 220,000.00
JUMLAH 0.00 1,137,668.34 1,137,668.34

SPL29 1 m' Pembuatan tiang pancang (35 x 35) cm, beton bertulang
Beton mutu f’'c = 26,4 MPa (K 300) 0.1348 m3 X Rp. 910,070.10 122,631.95
Besi beton polos 20.0000 kg X Rp. 13,516.00 270,320.00
Bekisting 1.4000 m2 X Rp. 220,010.00 308,014.00
Minyak bekisting 0.1400 ltr X Rp. - 0.00
Bongkar bekisting 1.0000 ls X Rp. 220,000.00 220,000.00
JUMLAH 0.00 920,965.95 920,965.95

SPL30 1 m Pemancangan Cerucuk kayu laut dia. 3" - 4" panjang 5 m


Asumsi : 120 m Pemancangan Cerucuk kayu laut dia. 3" - 4" panjang 5 m per hari
Pekerja 3.000 Org/hr X Rp. 55,000.00 165,000.00
Operator terlatih 1.000 Org/hr X Rp. - 0.00
Pembantu Operator 1.000 Org/hr X Rp. - 0.00
Mandor 1.000 Org/hr X Rp. 80,000.00 80,000.00
Alat Pancang Pile Compactor 1.000 hr X Rp. - 0.00
Alat Bantu 1.000 unit X Rp. - 0.00
JUMLAH 245,000.00 0.00 245,000.00
per M' 2,041.67 0.00 2,041.67

SPL31 1 bh Membongkar dan melepas fender


Pekerja 4.000 oh X Rp. 55,000.00 220,000.00
Tukang batu 1.000 oh X Rp. 80,000.00 80,000.00
mandor 0.400 oh X Rp. 80,000.00 32,000.00
Alat Bantu 1.000 ls X Rp. - 0.00
JUMLAH 332,000.00 0.00 332,000.00

SPL32 1 Bh Mengebor beton dermaga untuk lobang baut fender '(dihitung 120 menit).
Tukang besi 0.250 org/hr X Rp. 80,000.00 20,000.00
Kepala tukang 0.025 org/hr X Rp. 90,000.00 2,250.00
Pekerja 0.250 org/hr X Rp. 55,000.00 13,750.00
Mandor 0.025 org/hr X Rp. 80,000.00 2,000.00
Mekanik terlatih 1.000 org/hr X Rp. - 0.00
Genset 0.250 hr X Rp. 275,000.00 68,750.00
Bor beton 0.250 hr X Rp. - 0.00
Perancah 0.250 hr X Rp. 350,000.00 87,500.00
JUMLAH 194,250.00 0.00 194,250.00

SPL33 1 Bh Memasang fender karet :


Kotrek 2,5 ton 2.000 Bh X Rp. 200,000.00 400,000.00
Kunci 1.000 Set X Rp. 125,000.00 125,000.00
Tukang besi 2.000 org/hr X Rp. 80,000.00 160,000.00
Kepala tukang 0.200 org/hr X Rp. 90,000.00 18,000.00
Pekerja 2.000 org/hr X Rp. 55,000.00 110,000.00
Mandor 0.100 org/hr X Rp. 80,000.00 8,000.00
Mekanik terlatih 1.000 org/hr X Rp. - 0.00
Perancah 1.000 hr X Rp. 350,000.00 350,000.00
JUMLAH 1,171,000.00 0.00 1,171,000.00

SPL34 1 m' Pasang pipa beton oval dia. 25/37,5 dalam 0 - 1 m


Pipa beton 20 x 30 Panjang 1 m 1.000 bh X Rp. - 0.00
Pekerja 0.750 org X Rp. 55,000.00 41,250.00
Tukang batu 0.150 org X Rp. 80,000.00 12,000.00
Mandor 0.015 Org X Rp. 80,000.00 1,200.00
JUMLAH 54,450.00 0.00 54,450.00

SPL35 1 m' Pasang pipa beton oval dia. 25/37,5 dalam 1 - 2 m


Pipa beton 20 x 30 Panjang 1 m 1.000 bh X Rp. - 0.00
Pekerja 1.500 org X Rp. 55,000.00 82,500.00
Tukang batu 0.150 org X Rp. 80,000.00 12,000.00
Mandor 0.015 Org X Rp. 80,000.00 1,200.00
JUMLAH 95,700.00 0.00 95,700.00

SPL36 1 bh Membongkar perkerasan lama (serifying) tebal 10 cm


Pekerja 0.008 oh X Rp. 55,000.00 440.00
Tukang besi 0.010 oh X Rp. 80,000.00 800.00
Kepala tukang 0.001 oh X Rp. 90,000.00 90.00
mandor 0.0004 oh X Rp. 80,000.00 32.00
JUMLAH 1,362.00 0.00 1,362.00

SPL37 1 M2 Pelapisan epoxy/tar tiang pancang


Pekerja 0.500 oh X Rp. 55,000.00 27,500.00
Tukang cat 0.250 oh X Rp. 80,000.00 20,000.00
Mandor 0.025 oh X Rp. 80,000.00 2,000.00
Cat Epoxy/Tar 0.460 kg X Rp. - 0.00
Minyak cat 0.140 ltr X Rp. 12,000.00 1,680.00
Thinner 0.070 ltr X Rp. 12,000.00 840.00
Alat Bantu 1.000 ls X Rp. - 0.00 0.00
JUMLAH 49,500.00 2,520.00 52,020.00

SPL38 1 m' Pekerjaan Grouting / Injeksi retakan dinding bata dengan Semen Slurry (Cebex 100)
Pipa PVC abu-abu dia. 1/2" Wavin 3.000 bh X Rp. 13,700.00 41,100.00
Nitobond EC 0.050 kg X Rp. - 0.00
Sewa Mesin Grouting 0.150 hr X Rp. - 0.00
Sewa mesin gerinda untuk pekerjaan grouting 0.075 hr X Rp. - 0.00
Alat bantu 1.000 ls X Rp. - 0.00
Tukang grouting 0.3125 org X Rp. - 0.00
Kepala Tukang 0.0312 org X Rp. 90,000.00 2,808.00
Pekerja 1.2500 org X Rp. 55,000.00 68,750.00
Mandor 0.1562 org X Rp. 80,000.00 12,496.00
JUMLAH 84,054.00 41,100.00 125,154.00

SPL39 1 M2 Pelapisan epoxy/tar tiang pancang


Pekerja 0.500 oh X Rp. 55,000.00 27,500.00
Tukang cat 0.250 oh X Rp. 80,000.00 20,000.00
Mandor 0.025 oh X Rp. 80,000.00 2,000.00
Cat Epoxy/Tar 0.460 kg X Rp. - 0.00
Minyak cat 0.140 ltr X Rp. 12,000.00 1,680.00
Thinner 0.070 ltr X Rp. 12,000.00 840.00
Alat Bantu 1.000 ls X Rp. - 0.00 0.00
JUMLAH 49,500.00 2,520.00 52,020.00

SPL40 1 m' Cor beton kerb ( 15 x 30 ) cm, dengan 1pc:2ps:3kr


Portland Cement (PC) 15.3000 kg X Rp. 1,375.00 21,037.50
Pasir pasang ( progo ) 0.0243 m3 X Rp. 120,000.00 2,916.00
Krikil beton 0.0369 m3 X Rp. 170,100.00 6,276.69
Papan cetakan / bekesting 0.0027 m3 X Rp. 5,937,500.00 16,031.25
Paku biasa 1/2" - 1" 0.0272 kg X Rp. 16,300.00 443.36
Tukang kayu 0.0340 org X Rp. 80,000.00 2,720.00
Tukang batu 0.0158 org X Rp. 80,000.00 1,264.00
Kepala tukang 0.0050 org X Rp. 90,000.00 450.00
Pekerja 0.1374 org X Rp. 55,000.00 7,557.00
Mandor 0.0063 org X Rp. 80,000.00 504.00
JUMLAH 12,495.00 46,704.80 59,199.80

SPL41 1 m' Cor beton Devider ( 30 x 30 ) cm, dengan 1pc:2ps:3kr


Portland Cement (PC) 30.6000 kg X Rp. 1,375.00 42,075.00
Pasir pasang ( progo ) 0.0486 m3 X Rp. 120,000.00 5,832.00
Krikil beton 0.0738 m3 X Rp. 170,100.00 12,553.38
Papan cetakan / bekesting 0.0027 m3 X Rp. 5,937,500.00 16,031.25
Paku biasa 1/2" - 1" 0.0272 kg X Rp. 16,300.00 443.36
Tukang kayu 0.0340 org X Rp. 80,000.00 2,720.00
Tukang batu 0.0315 org X Rp. 80,000.00 2,520.00
Kepala tukang 0.0066 org X Rp. 90,000.00 594.00
Pekerja 0.2499 org X Rp. 55,000.00 13,744.50
Mandor 0.0116 org X Rp. 80,000.00 928.00
JUMLAH 20,506.50 76,934.99 97,441.49

SPL42 1m2 Membongkar Paving Block


Pekerja 0.100 oh X Rp. 55,000.00 5,500.00
mandor 0.010 oh X Rp. 80,000.00 800.00
JUMLAH 6,300.00 0.00 6,300.00

SPL43 10 M' memasang Riol RCP Ø 60 t 10 cm :


Riol RCP Ø 60 t 10 cm 10.000 Bh X Rp. 820,000.00 8,200,000.00
Portland Cement (PC) 106.400 kg X Rp. 1,375.00 146,300.00
Pasir pasang ( progo ) 0.760 M3 X Rp. 120,000.00 91,200.00
Tukang batu 1.200 org/hr X Rp. 80,000.00 96,000.00
Kepala tukang 0.120 org/hr X Rp. 90,000.00 10,800.00
Pekerja 2.400 org/hr X Rp. 55,000.00 132,000.00
Mandor 0.120 org/hr X Rp. 80,000.00 9,600.00
JUMLAH 248,400.00 8,437,500.00 8,685,900.00
Per M' 24,840.00 843,750.00 868,590.00

SPL44 1 m2 Pasang conblock tipe segi-empat, abu-abu 10 cm, K-450


Conblock tipe segi-empat, abu-abu 10 cm, K-450 1.0000 m2 X Rp. 193,600.00 193,600.00
Pasir urug darat 0.0500 m3 X Rp. 94,500.00 4,725.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala Tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 51,750.00 198,325.00 250,075.00

SPL45 1 m2 Pasang kembali conblock bekas


Pasir urug darat 0.0500 m3 X Rp. 94,500.00 4,725.00
Tukang batu 0.2500 org X Rp. 80,000.00 20,000.00
Kepala Tukang 0.0250 org X Rp. 90,000.00 2,250.00
Pekerja 0.5000 org X Rp. 55,000.00 27,500.00
Mandor 0.0250 org X Rp. 80,000.00 2,000.00
JUMLAH 51,750.00 4,725.00 56,475.00

SPL46 1 m3 Beton bertulang K225 pondasi pagar


Beton K-225 1.000 m3 121,825.00 736,077.57
Besi 115.033 kg 119,174.53 1,435,616.00
Bekisting 5.333 m2 143,520.00 647,973.33
JUMLAH 384,519.53 2,819,666.90 3,204,186.44

SPL47 1 m3 Beton bertulang K225 kolom pagar


Beton K-225 1.000 m3 121,825.00 736,077.57
Besi 141.888 kg 146,995.97 1,770,762.24
Bekisting 10.000 m2 341,550.00 2,212,700.00
JUMLAH 610,370.97 4,719,539.81 5,329,910.78

SPL48 1 m3 Beton bertulang K225 balok pagar


Beton K-225 1.000 m3 121,825.00 736,077.57
Besi 180.060 kg 186,541.64 2,247,142.56
Bekisting 13.333 m2 358,800.00 1,817,850.00
JUMLAH 667,166.64 4,801,070.13 5,468,236.77

SPL49 1 m3 Beton tanpa tulangan K225 pondasi menerus


Beton K-225 1.000 m3 121,825.00 736,077.57
Besi 0.000 kg 0.00 0.00
Bekisting 0.000 m2 0.00 0.00
JUMLAH 121,825.00 736,077.57 857,902.57

SPL50 1 m3 Beton bertulang K225 manhole


Beton K-225 1.000 m3 121,825.00 736,077.57
Besi 61.054 kg 63,251.81 761,952.35
Bekisting 3.577 m2 96,264.68 487,722.28
JUMLAH 281,341.50 1,985,752.21 2,267,093.70

SPL51 1 m3 Beton bertulang 1:2:3 dinding drainase


Beton 1:2:3 1.000 m3 119,400.00 664,581.00
Besi 98.600 kg 102,149.60 1,230,528.00
Bekisting 5.100 m2 287,130.00 971,052.24
JUMLAH 508,679.60 2,866,161.24 3,374,840.84

Belawan, 2012

Disetujui Oleh : Diperiksa Oleh : Dibuat Oleh :


MENEJER TEKNIK ASMEN FASILITAS STAF FASILITAS

SADARUDDIN SAMSU RIZAL RIZALDY HASIAN HARAHAP


PT Pelabuhan Indonesia I (Persero)

REKAPITULASI

KODE SATUAN

PP 0
PPS1 1 M2
PPS2 1 M1
PPS3 1 M2
PPS4 1 buah
PPS5 1 M2
PPS6 1 M2
PPS7 1 M1
PPS8 1 M1
PPS9 1 M2
PPS10 1 M2
PPS11 1 M2
PPS12 1 M2
PPS13 1 M1

PTN
PTN1 1 M3
PTN2 1 M3
PTN3 1 M3
PTN4 1 M3
PTN5 1 M3
PTN6 1 M3
PTN7 1 M3
PTN8 1 M3
PTN9 1 M3
PTN10 1 M3
PTN11 1 M3
PTN12 1 M3
PTN13 1 M3
PTN14 1 M2
PTN15 1 M2
PTN16 1 M3
PTN17 1 M3
PTN18 1 Ttk
Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :47
PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PTN19 1 M3
PTN20 1 M3

PPO
PPO1 1 M3
PPO2 1 M3
PPO3 1 M3
PPO4 1 M3
PPO5 1 M3
PPO6 1 M3
PPO7 1 M3
PPO8 1 M3
PPO9 1 M3
PPO10 1 M3
PPO11 1 M2
PPO12 1 M2
PPO13 1 M2
PPO14 1 M2
PPO15 1 M2

PPD
PPD1 1 M2
PPD2 1 M2
PPD3 1 M2
PPD4 1 M2
PPD5 1 M2

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :48


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PPD6 1 M2
PPD7 1 M2
PPD8 1 M2
PPD9 1 M2
PPD10 1 M2
PPD11 1 M2
PPD12 1 M2
PPD13 1 M2
PPD14 1 M2
PPD15 1 M2
PPD16 1 M2
PPD17 1 M2
PPD18 1 M2
PPD19 1 M2
PPD20 1 M2
PPD21 1 M2
PPD22 1 M2
PPD23 1 M2
PPD24 1 M2
PPD25 1 M2
PPD26 1 M2

PBT
PBT1 1 M3
PBT2 1 M3
PBT3 1 M3
PBT4 1 M3
PBT5 1 M3
PBT6 1 M3
PBT7 1 M3
PBT8 1 M3
PBT9 1 M3
PBT10 1 M3
PBT11 1 M3
PBT12 1 M3
PBT13 1 M3

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :49


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PBT14 1 M3
PBT15 1 M3
PBT16 1 M3
PBT17 1 M3
PBT18 1 M1
PBT19 1 M1
PBT20 1 M1
PBT21 1 KG
PBT22 1 KG
PBT23 1 KG
PBT24 1 KG
PBT25 1 M2
PBT26 1 M2
PBT27 1 M2
PBT28 1 M2
PBT29 1 M2
PBT30 1 M2
PBT31 1 M2
PBT32 1 M2
PBT33 1 M2
PBT34 1 M1

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :50


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PBT35 1 M1
PBT36 1 M1
PBT37 1 M1
PBT38 1 M1

PPT
PPT1 1 M2
PPT2 1 M2
PPT3 1 M2
PPT4 1 M2
PPT5 1 M2
PPT6 1 M2
PPT7 1 M2
PPT8 1 M2
PPT9 1 M2
PPT10 1 M2
PPT11 1 M2
PPT12 1 M2
PPT13 1 M2
PPT14 1 M2
PPT15 1 M2
PPT16 1 M2
PPT17 1 M2
PPT18 1 M2
PPT19 1 M2

PPL

PPL1 1 M2
PPL2 1 M2

PPL3 1 M1
PPL4 1 M1
PPL5 1 M1
PPL6 1 M1
PPL7 1 M1
PPL8 1 M1
PPL9 1 M1

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :51


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PPL10 1 M1

PPL11 1 M1
PPL12 1 M1
PPL13 1 M1
PPL14 1 M1
PPL15 1 M1
PPL16 1 M1

PPL17 1 M2
PPL18 1 M2
PPL19 1 M2
PPL20 1 M2
PPL21 1 M2
PPL22 1 M2
PPL23 1 M2
PPL24 1 M2
PPL25 1 M2
PPL26 1 M2
PPL27 1 M1
PPL28 1 M1
PPL29 1 M1
PPL30 1 M1
PPL31 1 M2
PPL32 1 M2
PPL33 1 M2
PPL34 1 M2

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :52


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PPL35 1 M2
PPL36 1 M2
PPL37 1 M2
PPL38 1 M2
PPL39 1 M2
PPL40 1 M2
PPL41 1 M2
PPL42 1 M2
PPL43 1 M1
PPL44 1 M1

PCB
PCB1 1 M2
PCB2 1 M2
PCB3 1 M2
PCB4 1 M2
PCB5 1 M2
PCB6 1 M2
PCB7 1 M3
PCB8 1 bh
PCB9 1 M3
PCB10 1 M3
PCB11 1 M3

PKY
PKY1 1 M3
PKY2 1 M3
PKY3 1 M2
PKY4 1 M2
PKY5 1 M2
PKY6 1 M2
PKY7 1 M'
PKY8 1 M'
PKY9 1 M'
PKY10 1 M'
PKY11 1 M'
PKY12 1 M'
PKY13 1 M'
PKY14 1 M2
PKY15 1 M2
PKY16 1 M2
PKY17 1 M2

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :53


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PKY18 1 M2
PKY19 1 M2
PKY20 1 M2
PKY21 1 M2
PKY22 1 M2
PKY23 1 M2
PKY24 1 M2
PKY25 1 M2
PKY26 1 M2
PKY27 1 M2
PKY28 1 M2

PBS
PBS1 1 Kg
PBS2 1 Kg
PBS3 1 Kg
PBS4 1 Kg
PBS5 1 Kg
PBS6 1 Kg
PBS7 1 Kg
PBS8 1 Unit
PBS9 1 Unit
PBS10 1 Kg
PBS11 1 M2
PBS12 1 Cm
PBS13 1 M2
PBS14 1 M2
PBS15 1 M2
PBS16 1 M2
PBS17 1 M2
PBS18 1 M2
PBS19 1 M2
PBS20 1 M2
PBS21 1 M2
PBS22 1 M2
PBS23 1 M2
PBS24 1 M2
PBS25 1 M'

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :54


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PBS26 1 M'

PAT
PAT1 1 M2
PAT2 1 M2
PAT3 1 M2
PAT4 1 M2
PAT5 1 M2
PAT6 1 M2
PAT7 1 M2
PAT8 1 M2
PAT9 1 M'
PAT10 1 M2
PAT11 1 M'
PAT12 1 M2
PAT13 1 M2
PAT14 1 M2
PAT15 1 M2
PAT16 1 M2
PAT17 1 M2
PAT18 1 M2
PAT19 1 M2
PAT20 1 M2
PAT21 1 M1
PAT22 1 M1
PAT23 1 M2
PAT24 1 M2
PAT25 1 M2
PAT26 1 M2
PAT27 1 M2
PAT28 1 M2
PAT29 1 M2
PAT30 1 M2
PAT31 1 M2
PAT32 1 M1
PAT33 1 M1
PAT34 1 M1

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :55


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PAT35 1 M1
PAT36 1 M1
PAT37 1 M1
PAT38 1 M1
PAT39 1 M1
PAT40 1 M1
PAT41 1 M2
PAT42 1 M2
PAT43 1 M2
PAT44 1 M2
PAT45 1 M'

PPC
PPC1 1 M2

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :56


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PPC2 1 M2
PPC3 1 M2
PPC4 1 M2
PPC5 1 M2
PPC6 1 M2
PPC7 1 M2
PPC8 1 M2
PPC9 1 M2
PPC10 1 M2
PPC11 1 M2
PPC12 1 M2
PPC13 1 M2
PPC14 1 M2
PPC15 1 M2
PPC16 1 M2
PPC17 1 M2
PPC18 1 M2
PPC19 1 M2
PPC20 1 M2
PPC21 1 M2
PPC22 1 M2
PPC23 2 M2

PBK
PBK1 1 M3
PBK2 1 M3
PBK3 1 M3
PBK4 1 M2
PBK5 1 M2
PBK6 1 M2
PBK7 1 M2
PBK8 1 M2
PBK9 1 M2
PBK10 1 M3
PBK11 1 M3
PBK12 1 M3

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :57


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PSN
PSN1 1 bh
PSN2 1 bh
PSN3 1 bh
PSN4 1 bh
PSN5 1 bh
PSN6 1 bh
PSN7 1 bh
PSN8 1 bh
PSN9 1 M1
PSN10 1 M1
PSN11 1 M1
PSN12 1 M1
PSN13 1 bh
PSN14 1 bh
PSN15 1 bh
PSN16 1 M1
PSN17 1 M1
PSN18 1 M1
PSN19 1 M1
PSN20 1 M1
PSN21 1 M1
PSN22 1 M1
PSN23 1 M1
PSN24 1 M1
PSN25 1 M1

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :58


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PSN26 1 M1
PSN27 1 M1
PSN28 1 M1
PSN29 1 M1
PSN30 1 bh
PSN31 1 bh
PSN32 1 bh
PSN33 1 bh
PSN34 1 bh
PSN35 1 bh
PSN36 1 bh

PPG
PPG1 1 bh
PPG2 1 bh
PPG3 1 bh
PPG4 1 bh
PPG5 1 bh
PPG6 1 bh
PPG7 1 bh
PPG8 1 bh
PPG9 1 bh
PPG10 1 bh
PPG11 1 bh
PPG12 1 bh
PPG13 1 bh
PPG14 1 bh
PPG15 1 bh
PPG16 1 M2
PPG17 1 M'

PTM
PTM1 1 M2/Hari
PTM2 1 M2/Hari
PTM3 1 M2/Hari
PTM4 1 M2/Hari
PTM5 1 M2/Hari
PTM6 1 M2/Hari

SPL
SPL1 1 M2
Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :59
PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

SPL2 1 M2
SPL3 1 M3
SPL4 1 M3
SPL5 1 M3
SPL6 1 M3
SPL7 1 KG
SPL8 1 KG
SPL9 1 M2
SPL10 1 KG
SPL11 1 M2
SPL12 1 M'
SPL13 1 M2
SPL14 1 M2
SPL15 1 M2
SPL16 1 M'
SPL17 1 M'
SPL18 1 M'
SPL19 1 M'
SPL20 1 M'
SPL21 1 M'
SPL22 1 M'
SPL23 1 M'
SPL24 1 M'
SPL25 1 Bh
SPL26 1 Bh
SPL27 1 Bh
SPL28 1 M'
SPL29 1M
SPL30 1 M'
SPL31 1 bh

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :60


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

SPL32 1 M'
SPL33 1 BH
SPL34 1 M'
SPL35 1 M'
SPL36 1 M2
SPL37 1 M2
SPL38 1 M'
SPL39 1 M'
SPL40 1 M'
SPL41 1 M'
SPL42 1 M2
SPL43 1 M'
SPL44 1 M2
SPL45 1 M2
SPL46 1 M3
SPL47 1 M3
SPL48 1 M3
SPL49 1 M3
SPL50 1 M3
SPL51 1 M3

PLS
PLS1 1 M1
PLS2 1 M1
PLS3 1 M1
PLS4 1 M1
PLS5 1 M1
PLS6 1 M1
PLS7 1 M1
PLS8 1 M1
PLS9 1 Unit
PLS10 1 Unit
PLS11 1 Unit
PLS12 1 Unit
PLS13 1 Set
PLS14 1 Unit
PLS15 1 Set

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :61


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

PLS16 1 Unit
PLS17 1 Set
PLS18 1 Set
PLS19 1 M1
PLS20 1 M1
PLS21 1 M1
PLS22 1 bh
PLS23 1 bh
PLS24 1 bh
PLS25 1 Set
PLS26 1 Set
PLS27 1 Set
PLS28 1 Set
PLS29 1 Set
PLS30 1 Set
PLS31 1 Set
PLS32 1 Set
PLS33 1 Set
PLS34 1 Set
PLS35 1 Set
PLS36 1 Set

ABS
ABS1 1 M2
ABS2 1 M3
ABS3 1 M2
ABS4 1 M2
ABS5 1 M2
ABS6 1 M2
ABS7 1 M2
ABS8 1 M2
ABS9 1 M2
ABS10 1 M2
ABS11 1 M2
ABS12 1 M2
ABS13 1 M2
ABS14 1 M2
ABS15 1 M1
ABS16 1 M2

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :62


PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

ASP
ASP1 1 M2
ASP2 1 M2
ASP3 1 M3
ASP4 1 liter
ASP5 1 M3
ASP6 1 M3
ASP7 1 liter
ASP8 1 M2

ALT
ALT1 1 Jam
ALT2 1 Jam
ALT3 1 Jam
ALT4 1 Jam
ALT5 1 Jam
ALT6 1 Jam
ALT7 1 Jam
ALT8 1 Jam
ALT9 1 Jam
ALT10 1 Jam
ALT11 1 Jam
ALT12 1 Jam
ALT13 1 Jam
ALT14 1 Jam
ALT15 1 Jam
ALT16 1 Jam
ALT17 1 Jam
ALT18 1 Jam
ALT19 1 Jam
ALT20 1 Jam
ALT21 1 Jam
ALT22 1 Jam
ALT23 1 Jam
ALT24 1 Jam
ALT25 1 Jam
ALT26 1 Jam
ALT27 1 Jam
ALT28 1 Jam
ALT29 1 Jam
ALT30 1 Jam
Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :63
PT Pelabuhan Indonesia I (Persero)

KODE SATUAN

ALT31 1 Jam
ALT32 1 Jam
ALT33 1 Jam
ALT34 1 Jam
ALT35 1 Jam
ALT36 1 Jam
ALT37 1 Jam
ALT38 1 Jam
ALT39 1 Jam
ALT40 1 Jam
ALT41 1 Jam

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :64


PT Pelabuhan Indonesia I (Persero)

REKAPITULASI ANALISA HARGA SATUAN

MACAM PEKERJAAN

PEKERJAAN PERSIAPAN
Pekerjaan Pengukuran Gedung
Pengukuran dan pemasangan bouwplank untuk gedung dan saluran
Membersihkan lapangan dan perataan
Membuat Papan Nama Proyek 80x120 cm
Pembuatan jalan sementara, tebal 25 cm
Pembuatan kantor sementara, dengan lantai plesteran
Pembuatan pagar sementara dari seng gelombang tinggi 2 meter
Pembuatan pagar sementara dari kawat duri tinggi 1,80 meter
Pembuatan gudang semen dan alat-alat
Pembuatan rumah jaga/konstruksi kayu
Pembuatan bedeng buruh
Pasang pagar kawat jaring galvanis, tinggi 1,00 m
Pasang pagar beton pracetak ( 5 x 50 x 213 ) cm

PEKERJAAN TANAH
Galian tanah biasa sedalam sampai 1 meter
Galian tanah biasa sedalam 1 - 2 meter
Galian tanah biasa sedalam 2 - 3 meter
Galian tanah keras sedalam sampai 1 meter
Galian tanah cadas sedalam sampai 1 meter
Galian tanah lumpur sedalam 1 meter
Stripping tebing setinggi 1 meter
Pengangkutan tanah sejauh 15 meter
Pemadatkan tanah per 20 cm
Urug kembali bekas galian (dihitung 1/3 kali galian tanah)
Urugan pasir
Urugan sirtu padat untuk peninggian lantai bangunan
Urug tanah mendatangkan
Memasang Lapisan pudel campuran 1 KP : 5 TL untuk stabilisasi
Gebalan rumput
Pemasangan lapisan ijuk tebal 10cm untuk peresapan
Pembuangan Tanah sampai dengan sejauh 150 meter
Mengerjakan Sondir Tanah
Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :65
PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Membuang lumpur SAL sejauh 15 km


Mengangkut lumpur SAL sejauh 30 m

PEKERJAAN PASANGAN PONDASI


Pasangan pondasi batu kosong (anstamping)
Pasangan pondasi 1 Kp : 1 Sm : 1 Ps
asangan pondasi 1 Kp : 1 Sm : 2 Ps
Pasangan pondasi 1 Pc : 3 Kp : 5 Ps
Pasangan pondasi 1 Pc : 3 Kp : 10 Ps
Pasangan pondasi 1/4 Pc : 1 Kp : 4 Ps
Pasangan pondasi 1 Pc : 4 Ps
Pasangan pondasi 1 Pc : 3 Ps
Pasangan pondasi 1 Pc : 1 Ps
Pasangan pondasi 1 Pc : 2 Ps
Pasangan pondasi 1 Pc : 5 Ps
Pasangan pondasi 1 Pc : 6 Ps
Pasangan pondasi 1 Pc : 8 Ps
Beton cyclope 60% beton camp. 1pc:2ps:3kr, 40% batu belah
Pasangan pondasi sumuran dia. 100 cm

PASANGAN DINDING
Pasangan dinding HB/CB 10, camp. 1pc : 4ps
Pasangan dinding HB/CB 10, camp. 1pc : 3ps
Pasangan dinding HB/CB 15, camp. 1pc : 4ps
Pasangan dinding HB/CB 15, camp. 1pc : 3ps
Pasangan dinding HB/CB 20, camp. 1pc : 4ps

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :66


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Pasangan dinding HB/CB 20, camp. 1pc : 3ps


Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 2Ps
Pasangan bata merah tebal 1/2 bata, 1 Kp : 1 Sm : 1Ps
Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Kp : 10 Ps
Pasangan bata merah tebal 1/2 bata, 1 Pc : 8 Ps
Pasangan bata merah tebal 1/2 bata, 1 Pc : 6 Ps
Pasangan bata merah tebal 1/2 bata, 1 Pc : 5 Ps
Pasangan bata merah tebal 1/2 bata, 1 Pc : 4 Ps
Pasangan bata merah tebal 1/2 bata, 1 Pc : 3 Ps
Pasangan bata merah tebal 1/2 bata, 1 Pc : 2 Ps
Pasangan bata merah tebal 1 bata, 1 Pc : 3 Kp : 10 Ps
Pasangan bata merah tebal 1 bata, 1 Pc : 6 Ps
Pasangan bata merah tebal 1 bata, 1 Pc : 5 Ps
Pasangan bata merah tebal 1 bata, 1 Pc : 4 Ps
Pasangan bata merah tebal 1 bata, 1 Pc : 3 Ps
Pasangan bata merah tebal 1 bata, 1 Pc : 2 Ps
Pasangan roster 12 x 11 x 24 cm, camp. 1pc : 4ps
Pasangan roster 12 x 11 x 24 cm, camp. 1pc : 3ps
Pasangan bata merah expose (5 x 11 x 24 cm), camp. 1 Pc : 3 Ps
Pasangan dinding bataco
Pasangan roster 25/25 cm

PEKERJAAN BETON
Membuat beton bertulang, 1 Pc : 2 Ps : 3 Kr
Membuat beton tumbuk, 1 Pc : 3 Ps : 5 Kr
Beton mutu f’'c = 7,4 MPa (K 100), slump (12 ± 2) cm, w/c = 0,87
Beton mutu f’ = 9,8 MPa (K 125), slump (12 ± 2) cm, w/c = 0,78
Beton mutu f’'c = 12,2 MPa (K 150), slump (12 ± 2) cm, w/c = 0,72
Lantai kerja Beton mutu f’'c = 7,4 MPa (K 100), slump (3-6) cm w/c = 0,87
Beton mutu f’'c = 14,5 MPa (K 175), slump (12 ± 2) cm, w/c = 0,66
Beton mutu f’'c = 16,9 MPa (K 200), slump (12 ± 2) cm, w/c = 0,61
Beton mutu f’'c = 19,3 MPa (K 225), slump (12 ± 2) cm, w/c = 0,58
Beton mutu f’'c = 21,7 MPa (K 250), slump (12 ± 2) cm, w/c = 0,56
Beton mutu f’'c = 24,0 MPa (K 275), slump (12 ± 2) cm, w/c = 0,53
Beton mutu f’'c = 26,4 MPa (K 300), slump (12 ± 2) cm, w/c = 0,52
Beton mutu f’'c = 28,8 MPa (K 325), slump (12 ± 2) cm, w/c = 0,49

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :67


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Beton mutu f’'c = 31,2 MPa (K 350), slump (12 ± 2) cm, w/c = 0,48
Membongkar cetakan
Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai dolken )
Stutwerk untuk 1 m3 beton, tinggi 3 - 4 m ( memakai scafolding )
PVC Waterstop lebar 150 mm
PVC Waterstop lebar 200 mm
PVC Waterstop lebar 230 mm - 320 mm
Pembesian dengan besi polos
Pembesian dengan besi ulir
Memasang kabel presstressed polos/strands
Memasang jaring kawat baja/wire mesh
Cetakan beton / begisting memakai papan
Cetakan beton / begisting memakai multiplek
Begesting untuk pondasi
Begesting untuk sloof
Begesting untuk kolom
Begesting untuk balok
Begesting untuk lantai
Begesting untuk dinding
Begesting untuk tangga
Jembatan untuk pengecoran beton

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :68


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Kolom praktis beton bertulang (11 x 11) cm


Ring balok beton bertulang (10 x 15) cm
Pembuatan tiang pancang (40 x 40) cm, beton bertulang
Pembuatan tiang pancang (35 x 35) cm, beton bertulang

PEKERJAAN PLESTERAN
Plesteran 1 Sm : 1 Kp : 1 Ps, tebal 15 mm
Plesteran 1 Sm : 1 Kp : 2 Ps, tebal 15 mm
Plesteran 1 Pc : 1/2 Kp : 3 Ps, tebal 15 mm
Plesteran 1 Pc : 2 Kp : 8 Ps, tebal 15 mm
Plesteran 1 Pc : 1 Ps, tebal 15 mm
Plesteran 1 Pc : 2 Ps, tebal 15 mm
Plesteran 1 Pc : 3 Ps, tebal 15 mm
Plesteran 1 Pc : 4 Ps, tebal 15 mm
Plesteran 1 Pc : 5 Ps, tebal 15 mm
Plesteran 1 Pc : 6 Ps, tebal 15 mm
Plesteran granit 1 Pc : 2 Batu granit, tebal 10 mm
Plesteran traso 1 Pc : 2 Batu traso, tebal 10 mm
1 m2 Finishing siar pas. Bata merah (=20m')
Finishing siar pas. Batu kali 1 pc : 2 ps
Plesteran Ciprat, 1 Pc : 2 Ps
Acian
Plesteran batu kali 1pc:1/2kp:5ps tebal 10 mm
Plesteran batu kali 1pc:3ps
Plesteran batu kali 1pc:4ps

PEKERJAAN PASANG LANTAI


PASANG UBIN GRANIT
Pasang lantai ubin granit 40/40
Pasang lantai ubin granit 30/30

PASANG PLINT TEGEL DAN TERASO


Pasang plint ubin PC abu-abu ukuran 15 x 20 cm
Pasang plint ubin PC abu-abu ukuran 10 x 30 cm
Pasang plint ubin PC abu-abu ukuran 10 x 40 cm
Pasang plint ubin PC warna ukuran 10 x 20 cm
Pasang plint ubin PC warna ukuran 10 x 30 cm
Pasang plint ubin PC warna ukuran 10 x 40 cm
Pasang plint ubin traso ukuran 10 x 30 cm

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :69


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Pasang plint ubin traso ukuran 10 x 40 cm

PASANG PLINT UBIN DAN MARMER


Pasang plint ubin granit ukuran 10 x 30 cm
Pasang plint ubin granit ukuran 10 x 40 cm
Pasang plint ubin teralux marmer ukuran 10 x 60 cm
Pasang plint ubin teralux marmer ukuran 10 x 40 cm
Pasang plint ubin teralux marmer ukuran 10 x 30 cm
Pasang lantai teraso cor ditempat tebal 3 cm

PEKERJAAN KERAMIK
Pasang lantai keramik artistik uk. 10 x 20 cm
Pasang lantai keramik artistik uk. 10 x 10 cm atau 5 x 20 cm
Pasang ubin porselin uk. 11 x 11 cm
Pasang ubin porselin uk. 10 x 20 cm
Pasang ubin porselin uk. 20 x 20 cm
Pasang tegel keramik uk. 33/33
Pasang tegel keramik uk. 30/30
Pasang tegel keramik uk. 20/20
Pasang tegel keramik uk. 10 x 33 cm (variasi/border)
Pasang lantai mozaik uk. 30 x 30 cm, camp. 1pc : 3ps
Pasang plint keramik ukuran 10 x 30 cm
Pasang plint keramik ukuran 10 x 40 cm
Pasang plint keramik 5 x 20 cm
Pasang plint internal cove artistik 5 x 5 x 20 cm
Pasang lantai marmer uk. 100 x 100 cm
Pasang lantai karpet
Pasang keramik dinding artistik 10 x 20 cm
Pasang keramik dinding artistik 5 x 20 cm

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :70


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Pasang keramik dinding 10 x 20 cm


Pasang keramik dinding 20 x 20 cm
Pasang keramik dinding 20/25
Pasang keramik stepnosing granito 5/30
Pasang dinding marmer uk. 100 x 100 cm
Pasang lantai vinyl uk. 30 x 30 cm kls 1
Pasang wallpaper lebar 50 cm
Pasang floor hardener
Pasang plint vinyl karet uk. 15 x 30 cm dengan perekat
Pasang plint kayu klas II tebal 2cm, lebar 10cm

PEKERJAAN CONE BLOCK / PAVING BLOCK


Pasang conblock tipe segi-empat, uni, segi-enam abu-abu 8 cm, K-400
Pasang conblock tipe segi-empat abu-abu 8 cm, K-200
Pasang conblock tipe segi-empat, uni, segi-enam warna 8 cm, K-400
Pasang conblock tipe segi-empat warna 8 cm, K-200
Pasang grassblock bulat tebal 10 cm
Pasang grassblock tebal 10 cm
Bronjong kawat galvanis
Pasang buis beton dia. 80 cm
Langsiran batu kali
Langsiran kerikil
Langsiran pasir

PEKERJAAN KAYU
Pasang konstruksi kuda-kuda konvensional
Pasang gording Kayu meranti
Pasang usuk 5/7 Kayu meranti, reng 2/3 Kayu damar (laut)
Pasang usuk 5/7 Kayu meranti, reng 3/4 Kayu damar (laut)
Pasang rangka atap sirap
Pasang rangka langit-langit (50 x 100) c
Pasang lisplank ukuran (3 x 20) cm
Pasang lisplank ukuran (3 x 30) cm,
Pasang lisplank ukuran (2 x 20) cm
Pasang lisplank ukuran (2 x 25) cm
Pasang lisplank ukuran 2 x (3 x 20) cm
Pasang lisplank ukuran 2 x (2 x 20) cm
Mengerjakan papan ruiter 2/20
Pasang rangka dinding pemisah ukuran (60 x 120) cm
Pasang dinding pemisah teakwood rangkap
Pasang dinding pemisah plywood rangkap
Pasang dinding lambiziring, dari Kayu jati papan

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :71


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Pasang dinding bilik bambu, rangka kayu klas III, IV


Membuat dan memasang kusen pintu / jendela Kayu Meranti
Membuat dan memasang kusen pintu / jendela kayu Damar Laut
Membuat dan memasang pintu klamp standar
Membuat dan memasang daun pintu panil
Membuat dan memasang daun pintu dan jendela jalusi
Membuat daun pintu kayu lapis plywood rangkap, rangka tertutup kayu
Membuat pintu plywood rangkap, rangka expose
Memasang jalusi kusen
Memasang teakwood rangkap, rangka expose
Memasang teakwood rangkap lapis formika, rangka expose

PEKERJAAN BESI DAN ALUMUNIUM


Pasang besi profil
Pasang kuda-kuda baja IWF
Kuda-kuda baja siku
Plat besi lembaran
Gording baja
Ikatan angin diameter 16 mm dan water mur
Trekstang diameter 12 mm
Manhole uk. 70 x 70 cm
Grill dari besi beton Ǿ 16mm rangka baja 50.50.5 uk 1 x 1 m
Pekerjaan perakitan
Membuat pintu besi plat baja tebal 2 mm rangkap, rangka baja siku
Pengelasan dengan las listrik
Rangka jendela besi square tube (25 x 5) cm
Pasang Rolling door besi
Pasang pintu lipat (folding door) bahan plastik/PVC
Pasang pintu Sunscreen alumunium
Pasang Rolling door alumunium
Pasang kusen pintu alumunium
Pasang pintu alumunium strip lebar 8 cm
Pasang pintu kaca rangka alumunium
Pasang vienetions dan vertikal blinds
Pasang terali besi strip (2 x 3) mm
Pasang kawat nyamuk
Pasang jendela nako & tralis
Pasang talang datar/jurai, seng plat BJLS 28 lebar 90 cm

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :72


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Pasang talang ½ lingkaran D - 15 cm, seng plat BJLS 30 lebar 45 cm

PEKERJAAN ATAP
Langit-langit asbes semen tebal 4, 5 dan 6 mm
Langit-langit asbes (1,00 x 1,00) m memakai plepet
Langit-langit akustik ukuran (30 x 30) cm
Langit-langit akustik ukuran (30 x 60) cm
Langit-langit akustik ukuran (60 x 120) cm
Langit-langit triplek ukuran (120 x 240) cm tebal 3mm, 4mm, dan 6 mm
Langit-langit lambriziring Kayu jati tebal 9 mm
Langit-langit gypsum board ukuran (1200 x 2400 x 9) mm
Pasang list plafond gypsum profil
Langit-langit akustik ukuran 60 x 120 cm + rangka alumunium
List langit-langit kayu profil
Pasang rangka langit-langit (1,00 x 1,00) m, Kayu jati
Pasang rangka langit-langit (60 x 120) cm, Kayu jati
Langit-langit rangka hollow
Pasang genteng beton besar Natural ( isi 9 / m2 )
Pasang genteng beton besar Natural ( isi 9 / m2 ) untuk rumah tingkat
Pasang genteng beton besar Warna ( isi 9 / m2 )
Pasang genteng beton besar Warna ( isi 9 / m2 ) untuk rumah tingkat
Pasang genteng keramik berglasir KIA, Kanmuri Natural
Pasang genteng keramik berglasir KIA, Kanmuri Natural untuk rumah tingkat
Pasang bubungan genteng paris
Pasang bubungan genteng beton Warna
Pasang atap asbes gelombang (2,25 x 0,92 m) x 5 mm
Pasang atap asbes gelombang (2,00 x 0,92 m) x 5 mm
Pasang atap asbes gelombang (1,80 x 0,92 m) x 5 mm
Pasang atap asbes gelombang (2,40 x 1,05 m) x 4 mm
Pasang atap asbes gelombang (2,10 x 1,05 m) x 4 mm
Pasang atap asbes gelombang (1,50 x 1,05 m) x 4 mm
Pasang atap sbes gelombang (2,40 x 1,08 m) x 6 mm
Pasang atap asbes gelombang (2,10 x 1,08 m) x 6 mm
Pasang atap asbes gelombang (1,80 x 1,08 m) x 6 mm
Pasang bubung stel gelombang 0,92 m
Pasang nok stel rata 0,92 m
Pasang nok stel rata 1,09 m

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :73


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Pasang nok atap seng


Pasang atap genteng metal zinc alume type prima roof
Pasang atap metal gelombang
Pasang nok genteng metal U type prima roof
Pasang atap alumunium
Pasang nok alumunium
Pasang alumunium foil / sisalation
Pasang atap polikarbonat
Rangka atap baja ringan atap genteng metal
Atap spandek tebal 0,50 mm uk. 0.75X1.33 m2
Rabung atap spandek

PEKERJAAN PENGECATAN
Mengecat kerb 3 kali TIAP 1 M2 ( 3 kali )
Mengecat kerb 3 kali TIAP 1 M2 ( 2 kali )
Mengecat kerb 3 kali TIAP 1 M2 ( 1 kali )

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :74


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Mengikis / mengerok permukaan cat tembok lama


Mengerok karat cat lama permukaan baja dengan cara manual
Mendempul dan menggosok kayu
Pengecatan bidang kayu lama
Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 2 lapis cat penutup
Pengecatan bidang kayu baru (1 lapis plamir), 1 lapis cat dasar, 3 lapis cat penutup
Pelaburan bidang kayu dengan teak oil
Pelaburan bidang kayu dengan politur
Pelaburan bidang kayu dengan cat residu atau ter
Pelaburan bidang kayu dengan vernis
Pengecatan tembok baru (1 lapis plamir, 1 lapis cat dasar, 2 lapis cat penutup)
Pengecatan tembok lama (1 lapis cat dasar, 2 lapis cat penutup)
Pengecatan tembok tidak terlindung dari panas dan hujan
Melabur tembok dengan kalkarium
Pengecatan bidang besi ( 3 x )
Melamin
Pemasangan wall paper
Pengecacatan permukaan baja dengan meni besi
Pengecacatan permukaan baja dengan meni besi memakai perancah
Pengetiran kayu ( 2 x )
Mengecat genteng
Mengerjakan Cat Sungging

PEKERJAAN BONGKARAN
Membongkar pasangan batu kali
Membongkar pasangan batu merah dan membersihkan
Membongkar beton bertulang dan membersihkan
Pekerjaan bongkar lantai tegel untuk dipergunakan lagi
Mengupas plesteran lama
Membongkar genteng / sirap untuk dipergunakan lagi
Membongkar atap seng
Membongkar usuk / reng dipakai lagi
Membongkar usuk / reng tidak dipakai lagi
Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan untuk digunakan lagi
Membongkar kayu balok loteng, kuda-kuda, dlurung, jembatan tidak digunakan lagi
Mengerjakan kembali bangunan kayu yang telah dibongkar

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :75


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

PEKERJAAN SANITASI
Memasang kloset duduk/monoblock
Memasang kloset jongkok porselen
Memasang kloset jongkok teraso
Memasang urinoir
Memasang wastafel
Memasang bak mandi fiberglass volume 0,30 m3
Memasang badkip porselen
Memasang bak fiberglass volume 1 m3 air
Memasang pipa penyalur air limbah jenis pipa tanah, diameter 15 cm
Memasang pipa penyalur air limbah jenis pipa tanah, diameter 20 cm
Memasang pipa beton, diameter 15 cm - 20 cm
Memasang pipa beton, diameter 30 cm - 100 cm
Memasang bak kontrol pasangan batu bata ukuran (30 x 30) cm, tinggi 35 cm
Memasang bak kontrol pasangan batu bata ukuran (45 x 45) cm, tinggi 50 cm
Memasang bak kontrol pasangan batu bata ukuran (60 x 60) cm, tingg 65 cm
Memasang pipa galvanis diameter 1/2"
Memasang pipa galvanis diameter 3/4"
Memasang pipa galvanis diameter 1"
Memasang pipa galvanis diameter 1 1/2"
Memasang pipa galvanis diameter 3"
Memasang pipa galvanis diameter 4"
Memasang pipa PVC tipe AW diameter 1/2"
Memasang pipa PVC tipe AW diameter 3/4"
Memasang pipa PVC tipe AW diameter 1"
Memasang pipa PVC tipe AW diameter 1 1/2"

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :76


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Memasang pipa PVC tipe AW diameter 2"


Memasang pipa PVC tipe AW diameter 2 1/2"
Memasang pipa PVC tipe AW diameter 3"
Memasang pipa PVC tipe AW diameter 4"
Memasang bak cuci piring stainless steel
Memasang bak cuci piring teraso
Memasang kran diameter 3/4" atau 1/2"
Memasang floor drain
Memasang shower dinding
Memasang kran air angsa
Memasang tempat sabun

PEKERJAAN KUNCI DAN KACA


Pasang kunci tanam antik
Pasang kunci tanam biasa
Pasang kunci tanam kamar mandi
Pasang kunci tanam silinder
Pasang engsel pintu
Pasang engsel jendela kupu-kupu
Pasang engsel angin
Pasang spring knip
Pasang kait angin
Pasang door closer
Pasang kunci selot
Pasang pegangan pintu / door holder
Pasang door stop
Pasang rel pintu dorong
Pasang kunci lemari
Pasang kaca
Pasang kusen alumunium

PEKERJAAN TAMAN /JALAN


Penyapuan Jalan Dan Trotoar
Pembersihan / Penyapuan halaman
Pemangkasan teh-tehan
Pangkas bentuk tanaman perdu
Pangkas rumput
Penyiangan tanaman semak dan penggemburan tanah

ANALISA TAMBAHAN (SUPLEMEN)


PASANG STOOT WERK (SCAFOLDING)
Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :77
PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Pemasangan Geotextile
Timbunan tanah merah dipadatkan
Lapisan Base coarse Agregat kelas A dipadatkan
Lapisan Sub Base coarse Agregat kelas B dipadatkan
Lapisan Sub Base coarse Agregat Kelas C dipadatkan
Memasang gelagar-gelagar besi
Menurunkan gelagar-gelagar besi jembatan
Mengerjakan lantai jembatan (papan yang dipakukan diatas gelagar kayu)
Memasang 1 Kg jaring kawat baja/wire mesh
Memasang lantai cone block t.10 cm dipadatkan denganVibratory Roller kapasitas 10-15 ton
Memasang riol 20 cm
Memasang kawat harmonica
Memasang kawat duri
Pasang Aluminium Composite Panel (Alucopan)
Mobilisasi dan Demobilisasi Peralatan
Pengadaan Tiang Pancang Beton dia …. Cm (Bottom)
Pengadaan Tiang Pancang Beton dia …. Cm (Upper/Middle)
Handling dan Transport tiang pancang dan penimbunan ke titik pancang
Pemancangan tiang pancang (Darat)
Pemancangan tiang (Laut)
Pengangkatan 1 m Tiang Pancang ke titik pancang (Darat)
Pengangkatan 1 m Sheet Pile ke titik pancang (laut)
Pemancangan Sheet Pile
Sambungan tiang pancang beton/spun pile dia 50 cm
Sambungan tiang pancang baja dia 50 cm
Memotong tiang pancang beton/ spun pile dia 50 cm
Pembuatan tiang pancang (40 x 40) cm, beton bertulang
Pembuatan tiang pancang (35 x 35) cm, beton bertulang
Pemancangan Cerucuk kayu laut dia. 3" - 4" panjang 5 m
Membongkar dan melepas fender

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :78


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Mengebor beton dermaga untuk lobang baut fender '(dihitung 120 menit).
Memasang fender karet
Pasang pipa beton oval dia. 25/37,5 dalam 0 - 1 m
Pasang pipa beton oval dia. 25/37,5 dalam 1 - 2 m
Membongkar perkerasan lama (serifying) tebal 10 cm
Pelapisan epoxy/tar tiang pancang
Pekerjaan Grouting / Injeksi retakan dinding bata dengan Semen Slurry (Cebex 100)
Pelapisan epoxy/tar tiang pancang
Cor beton kerb ( 15 x 30 ) cm, dengan 1pc:2ps:3kr
Cor beton Devider ( 30 x 30 ) cm, dengan 1pc:2ps:3kr
Membongkar Paving Block
Memasang Riol RCP Ø 60 t 10 cm :
Pasang conblock tipe segi-empat, abu-abu 10 cm, K-450
Pasang kembali conblock bekas
Beton bertulang K225 pondasi pagar
Beton bertulang K225 kolom pagar
Beton bertulang K225 balok pagar
Beton tanpa tulangan K225 pondasi menerus
Beton bertulang K225 manhole
Beton bertulang 1 :2:3, dinding drainase

ANALISA HARGA SATUAN PEKERJAAN LISTRIK


Pasang Kabel NYY 3 x 6 sqmm
Pasang Kabel NYY 3 x 4 sqmm
Pasang Kabel NYM 2 x 2,5 sqmm
Pasang Kabel NYM 2 x 1,5 sqmm
Pasang Kabel NYA 1 x 2,5 sqmm
Pasang Kabel DX 2x10 sqmm + Accessories (antar tiang / gawang)
Pasang Kabel DX 2x16 sqmm + Accessories (antar tiang / gawang)
Pasang Kabel NYY 3x10 sqmm
Pasang Box Panel dan Panel Kontrol
Pasang Box KWH dan Meter
Pasang tiang lampu antik (b3)
Pasang tiang lampu antik (b3)
Pemasangan armatur komplit
Pemasangan komponen + Box
Bongkar komponen

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :79


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

Bongkar Armatur
Bongkar Tiang Lampu Antik
Bongkar Tiang Lampu Antik
Pasang Kabel NYM 2x2,5 sqmm
Pasang Kabel NYA 2,5 sqmm
Pasang Pralon 3" Kabel NYY 3x6 sqmm
Pasang tutup panel ukuran 30x30
Pasang MCB Ampere + box tutup panel ukuran 30 x 30
Pasang Kapasitor 12,5 uF
1 Set Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son + pengetesan dan penyalaan
1 Set Pasang Stang Ornamen 6 meter + Lampu SRP 822/250 Watt Son
1 Set Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son
Pasang Tiang Octogonal Cabang 1, h= 7 meter+ lampu SRP 822/250 Watt Son
Pasang Tiang Octogonal Cabang 1, h= 9 meter + lampu SRP 822/250 Watt Son
Pasang Tiang Octogonal Cabang 2, h= 9 meter+ lampu SRP 822/250 Watt Son
Pasang Tiang Octogonal Cabang 3, h= 9 m+ lampu SRP 822/250 Watt Son
Pasang Tiang Octogonal Cabang 3, h= 11 m+ lampu SRP 822/250 Watt Son
Bongkar armatur pada stang ornamen existing + pasang lampu SRP 822/150 Watt Son + return
Bongkar armatur pada stang ornamen existing + pasang Lampu SRP 822/250 Watt Son + retur
Bongkar armatur pada tang existing + pasang Lampu SRP 822/250 Watt Son + retur
Bongkar komponen lama existing + pasang komponen Lampu SRP 822/250 Watt Son + retur

ANALISA BASE
Menghampar dan mengisi bahan perkerasan
Menyawur pasir
Menggilas dengan motor walls
Perkerasan lapis pondasi bawah (sub base) tebal 20 cm padat
Pembuatan lapis pondasi bawah (sub base) tebal 15 cm padat
Pembuatan lapis pondasi atas (base) tebal 10 cm padat
Pembuatan lapis pondasi atas (base) tebal 8 cm padat
Pembuatan lapis pondasi atas (base) tebal 7 cm padat
Lapisan Penetrasi 4 cm padat
Pengaspalan sand sheet (latasir), tebal 1 cm jereng
Pengaspalan sand sheet (latasir) tanpa aspal, tebal 1 cm jereng
Mengecat marka jalan dengan Rettar
Mengecat marka jalan dengan Thermoplastic
Pemotongan aspal dengan mesin potong (cutter), 2 sisi
Pembongkaran aspal dengan Jack Hammer
Expantion joint

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :80


PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

ANALISA ASPAL
LATASTON ( HRS )
LASTON ( AC )
ASPHALT TREATED BASE ( ATB )
LAPIS RESAP PENGIKAT (PRIME COAT)
LAPIS PONDASI AGREGAT KLAS A
LAPIS PONDASI AGREGAT KLAS B
LAPIS PEREKAT (TACK COAT)
PENYIAPAN BADAN JALAN (PEMADATAN DAN PERATAAN)

SEWA ALAT :
ASPHALT MIXING PLANT
ASPHALT FINISHER
ASPHALT SPRAYER
BULLDOZER 100 -150 HP
COMPRESSOR 4000 - 6500 L/M
WHEEL LOADER 1,0 - 1,6 M3
TANDEM ROLLER 6 - 8 T
PNEUMATIC TYRE ROLLER 8 - 10 T
DUMP TRUCK
GENERATOR SET
MOTOR GRADER > 100 HP
VIBRATORY ROLLER 5 - 8 T
WATER TANK TRUCK 3000 - 4000 L
JACK HAMMER
TAMPER
STONE CRUSHER
THREE WHEEL ROLLER 6 - 8 T
CONCRETE VIBRATOR
CONCRETE MIXER 0.3 - 0.6 M3
CRANE 10 - 15 TON
DUMP TRUCK 3 - 4 M3
EXCAVATOR 80 - 140 HP
FLAT BED TRUCK 3 - 4 M3
WATER PUMP 70 - 100 mm
FULVI MIXER
TRACK LOADER 75 - 100 HP
MESIN PENYARING 8 HP
CHIP SPREADER
MESIN PENGHAMPAR 1820 MM 30 HP
THRILLER GANDENG 1 TON
Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :81
PT Pelabuhan Indonesia I (Persero)

MACAM PEKERJAAN

DUMP TRUCK 3,5 TON 44 HP


POMPA AIR ( D 5 CM ) 30 M3/JAM
TRAKTOR
THRILLER 1 TON
ALAT BOR
ALAT UKUR
BETON MOLEN
MESIN CUTTER
MOTOR WALLS
PERALATAN LAS
SPRAYER

BATAS RANGE

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :82


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN

HARGA SATUAN
UPAH BAHAN TOTAL

6,000 - 6,000
14,800 174,800 189,600
9,500 - 9,500
357,300 525,209 882,509
63,000 11,103 74,103
381,000 1,756,470 2,137,470
41,400 292,066 333,466
35,900 5,859 41,759
237,000 1,278,308 1,515,308
192,500 1,650,160 1,842,660
237,000 1,146,120 1,383,120
6,190 - 6,190
33,225 102,028 135,253

43,250 - 43,250
53,100 - 53,100
63,110 - 63,110
57,560 - 57,560
87,300 - 87,300
69,600 - 69,600
3,150 - 3,150
18,950 - 18,950
31,500 - 31,500
14,414 - 14,414
17,300 113,400 130,700
15,750 133,080 148,830
17,300 120,960 138,260
86,000 - 86,000
29,500 - 29,500
9,450 - 9,450
32,380 - 32,380
118,000 - 118,000
Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :83
PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
29,100 - 29,100
23,200 - 23,200

80,730 40,824 121,554


155,250 65,280 220,530
155,250 40,800 196,050
155,250 177,043 332,293
155,250 142,915 298,165
155,250 119,135 274,385
155,250 286,525 441,775
155,250 335,950 491,200
155,250 576,680 731,930
155,250 418,365 573,615
155,250 252,280 407,530
155,250 228,195 383,445
155,250 195,205 350,455
276,250 1,881,397 2,157,647
212,720 ### 37,999,077

26,600 63,239 89,839


26,600 64,525 91,125
29,560 94,865 124,425
29,560 97,268 126,828
34,000 125,998 159,998

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :84


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
34,000 129,050 163,050
26,600 45,360 71,960
26,600 44,160 70,760
26,600 54,188 80,788
26,600 56,938 83,538
26,600 59,320 85,920
26,600 60,710 87,310
26,600 62,973 89,573
26,600 66,559 93,159
26,600 72,616 99,216
53,200 108,960 162,160
53,200 124,078 177,278
53,200 126,765 179,965
53,200 131,666 184,866
53,200 140,226 193,426
53,200 153,413 206,613
26,600 19,325 45,925
26,600 23,090 49,690
31,050 23,090 54,140
38,400 21,988 60,388
- 21,988 21,988

119,400 664,581 783,981


119,400 510,137 629,537
121,825 572,619 694,444
121,825 611,042 732,867
121,825 640,975 762,800
88,600 555,744 644,344
121,825 676,661 798,486
121,825 710,242 832,067
121,825 736,078 857,903
121,825 752,169 873,994
121,825 779,671 901,496
121,825 788,245 910,070
155,050 820,672 975,722

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :85


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
155,050 831,838 986,888
220,000 - 220,000
1,141,000 - 1,141,000
442,100 - 442,100
6,210 - 6,210
7,525 - 7,525
8,280 - 8,280
1,036 12,480 13,516
1,036 13,215 14,251
740 12,380 13,120
573 11,932 12,505
28,150 191,860 220,010
28,150 95,201 123,351
26,910 121,495 148,405
26,910 136,339 163,249
34,155 221,270 255,425
34,155 235,070 269,225
34,155 252,870 287,025
34,155 222,483 256,638
34,155 191,433 225,588
17,350 174,430 191,780

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :86


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
15,960 63,986 79,946
26,355 72,754 99,109
118,630 962,793 1,081,423
91,700 767,862 859,562

31,920 1,080 33,000


31,920 1,800 33,720
31,920 9,480 41,400
31,920 6,525 38,445
37,050 21,318 58,368
37,050 14,058 51,108
31,050 13,452 44,502
31,050 11,460 42,510
31,050 10,248 41,298
31,050 9,312 40,362
46,575 13,750 60,325
46,575 13,750 60,325
15,525 4,274 19,799
31,050 10,158 41,208
26,600 6,660 33,260
20,700 4,469 25,169
41,400 8,645 50,045
41,400 13,548 54,948
41,400 11,461 52,861

25,875 496,235 522,110


26,910 802,570 829,480

13,320 2,749 16,069


13,320 2,065 15,385
13,320 2,065 15,385
13,320 1,928 15,248
13,320 1,928 15,248
13,320 1,928 15,248
13,320 1,928 15,248

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :87


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
13,320 1,928 15,248

13,320 1,928 15,248


13,320 1,928 15,248
13,320 1,928 15,248
13,320 1,928 15,248
13,320 1,928 15,248
37,260 - 37,260

72,450 16,661 89,111


72,450 16,661 89,111
54,000 14,948 68,948
93,150 14,948 108,098
93,150 247,748 340,898
72,450 16,661 89,111
72,450 19,150 91,600
72,450 19,700 92,150
108,675 18,875 127,550
72,450 24,136 96,586
13,320 1,928 15,248
13,320 1,928 15,248
13,320 964 14,284
111,000 1,928 112,928
72,450 16,661 89,111
25,160 - 25,160
93,150 14,948 108,098
93,150 14,948 108,098

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :88


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
93,150 14,948 108,098
93,150 14,948 108,098
76,730 17,760 94,490
11,850 669 12,519
134,550 69,054 203,604
22,200 - 22,200
34,920 - 34,920
17,760 - 17,760
11,840 - 11,840
17,760 - 17,760

51,750 4,725 56,475


51,750 4,725 56,475
51,750 4,725 56,475
51,750 4,725 56,475
51,750 4,725 56,475
51,750 4,725 56,475
369,900 - 369,900
24,875 - 24,875
12,600 - 12,600
7,560 - 7,560
3,150 - 3,150

1,304,000 ### 11,714,780


782,400 ### 11,150,800
14,800 187,495 202,295
14,800 241,300 256,100
17,760 1,518,000 1,535,760
40,950 141,680 182,630
23,700 100,990 124,690
23,700 102,015 125,715
14,800 45,138 59,938
14,800 56,178 70,978
31,100 134,378 165,478
14,800 80,098 94,898
8,772 37,126 45,898
48,900 260,045 308,945
48,900 260,045 308,945
65,200 2,445 67,645
195,600 66,030 261,630

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :89


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
10,350 218,799 229,149
2,282,000 ### 12,402,000
1,956,000 ### 19,143,500
114,100 625,815 739,915
326,000 368,000 694,000
326,000 588,800 914,800
228,200 230,489 458,689
260,800 236,009 496,809
241,650 554,445 796,095
260,800 230,489 491,289
305,150 230,489 535,639

8,880 13,915 22,795


8,880 - 8,880
8,436 14,530 22,966
8,436 13,656 22,092
8,436 13,219 21,655
8,436 12,673 21,109
8,436 12,673 21,109
55,000 196,033 251,033
63,000 754,003 817,003
140 - 140
155,360 199,500 354,860
414 - 414
96,160 - 96,160
173,280 - 173,280
65,120 - 65,120
75,920 - 75,920
148,000 - 148,000
6,360 450 6,810
12,576 - 12,576
12,685 2,025 14,710
51,800 - 51,800
247,120 82,154 329,274
14,800 22,823 37,623
28,880 93,100 121,980
46,050 175,045 221,095

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :90


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
35,550 6,813 42,363

8,200 - 8,200
8,000 - 8,000
17,760 - 17,760
14,800 - 14,800
14,800 - 14,800
14,800 23,400 38,200
118,400 138,000 256,400
10,350 24,752 35,102
8,880 - 8,880
74,000 3,000 77,000
7,440 163 7,603
31,100 112,030 143,130
34,060 121,556 155,616
36,740 - 36,740
20,700 - 20,700
26,600 - 26,600
20,700 - 20,700
26,600 - 26,600
20,700 - 20,700
26,600 - 26,600
41,400 3,920 45,320
41,400 3,920 45,320
15,060 1,956 17,016
14,490 1,956 16,446
14,490 1,956 16,446
14,250 1,956 16,206
14,250 1,956 16,206
14,250 1,956 16,206
14,250 1,956 16,206
14,250 1,956 16,206
14,250 1,956 16,206
16,110 - 16,110
18,990 - 18,990
16,110 - 16,110

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :91


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
15,050 652 15,702
19,980 - 19,980
19,980 - 19,980
28,140 - 28,140
69,450 - 69,450
87,200 - 87,200
13,340 - 13,340
72,200 84,700 156,900
25,738 1,630 27,368
49,120 - 49,120
3,600 - 3,600

38,500 15,687 54,187


25,667 10,458 36,124
12,833 5,229 18,062

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :92


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
8,450 - 8,450
8,450 - 8,450
5,960 2,056 8,016
10,725 14,807 25,532
4,590 33,729 38,319
12,810 35,254 48,064
13,110 - 13,110
6,440 - 6,440
5,980 - 5,980
23,240 7,750 30,990
6,907 16,998 23,905
5,478 13,560 19,038
6,907 - 6,907
5,478 - 5,478
12,810 7,695 20,505
19,490 4,800 24,290
17,480 - 17,480
19,700 3,530 23,230
33,000 3,530 36,530
5,900 - 5,900
6,907 - 6,907
464,293 30,596 494,889

342,000 - 342,000
165,500 - 165,500
464,000 - 464,000
11,800 - 11,800
7,875 - 7,875
11,800 - 11,800
9,500 - 9,500
17,140 - 17,140
11,800 - 11,800
770,000 - 770,000
71,000 - 71,000
1,304,000 - 1,304,000

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :93


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL

282,390 1,896,804 2,179,194


322,800 9,450 332,250
210,800 122,850 333,650
152,000 9,450 161,450
203,500 552,661 756,161
372,400 372,593 744,993
93,500 - 93,500
678,000 466,015 1,144,015
6,170 3,535 9,705
8,520 16,106 24,626
14,490 14,378 28,868
39,330 28,003 67,333
258,615 106,567 365,182
125,850 165,837 291,687
190,880 255,103 445,983
13,140 - 13,140
13,140 - 13,140
13,140 - 13,140
22,392 - 22,392
22,392 - 22,392
27,994 - 27,994
7,464 18,118 25,582
7,464 24,995 32,459
7,464 34,253 41,717
7,464 58,851 66,315

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :94


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
11,218 75,250 86,468
7,464 109,900 117,364
19,750 148,252 168,002
19,750 245,721 265,471
28,470 - 28,470
47,450 33,500 80,950
9,850 19,700 29,550
9,850 78,100 87,950
550 - 550
207,250 - 207,250
550 52,500 53,050

56,940 157,500 214,440


41,850 69,300 111,150
40,925 69,300 110,225
40,745 - 40,745
14,235 31,500 45,735
9,850 22,100 31,950
19,700 - 19,700
14,235 - 14,235
14,235 - 14,235
47,450 - 47,450
18,980 - 18,980
47,450 - 47,450
9,490 - 9,490
56,940 - 56,940
23,725 - 23,725
14,235 66,990 81,225
14,235 - 14,235

47 0 47
66 - 66
11 - 11
35 - 35
6 - 6
20 - 20

504,000 - 504,000
Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :95
PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
7,100 - 7,100
47,500 126,612 174,112
37,500 318,846 356,346
37,500 333,246 370,746
37,500 2,187 39,687
384 - 384
845 - 845
56,300 1,223 57,523
4,620 1,000 5,620
34,573 6,000 40,573
24,840 9,486 34,326
37,500 - 37,500
37,500 408 37,908
103,500 614,370 717,870
10,750,000 - 10,750,000
- - -
- - -
462,000 - 462,000
51,333 - 51,333
138,813 - 138,813
69,169 - 69,169
- - -
3,417 - 3,417
227,663 - 227,663
227,663 - 227,663
156,400 - 156,400
- 1,137,668 1,137,668
- 920,966 920,966
2,042 - 2,042
332,000 - 332,000

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :96


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
194,250 - 194,250
1,171,000 - 1,171,000
54,450 - 54,450
95,700 - 95,700
1,362 - 1,362
49,500 2,520 52,020
84,054 41,100 125,154
49,500 2,520 52,020
12,495 46,705 59,200
20,507 76,935 97,441
6,300 - 6,300
24,840 843,750 868,590
51,750 198,325 250,075
51,750 4,725 56,475
384,520 2,819,667 3,204,186
610,371 4,719,540 5,329,911
667,167 4,801,070 5,468,237
121,825 736,078 857,903
281,341 1,985,752 2,267,094
508,680 2,866,161 3,374,841

675 - 675
675 - 675
675 - 675
675 - 675
338 - 338
47,500 - 47,500
47,500 - 47,500
675 - 675
61,250 - 61,250
61,250 - 61,250
399,230 - 399,230
300,000 - 300,000
61,250 - 61,250
81,640 - 81,640
49,000 - 49,000

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :97


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
40,828 - 40,828
300,000 - 300,000
399,395 - 399,395
950 - 950
950 - 950
950 - 950
7,500 - 7,500
7,500 - 7,500
7,500 - 7,500
67,500 - 67,500
107,431 - 107,431
67,500 - 67,500
236,750 206,304 443,054
267,300 206,304 473,604
280,964 206,304 487,268
310,750 206,304 517,054
337,262 206,304 543,566
116,844 - 116,844
102,509 - 102,509
116,844 - 116,844
109,326 - 109,326

772,658 - 772,658
491,200 - 491,200
1,964,800 9,210,000 11,174,800
169,464 230,250 399,714
135,080 203,234 338,314
92,919 141,220 234,139
13,099 125,256 138,355
9,824 109,906 119,730
98,928 2,410,171 2,509,099
1,250,595 104,380 1,354,975
89,890 37,086 126,975
220,058 236,758 456,816
446,992 1,624,644 2,071,636
2,807 13,333 16,139
173,394 972,576 1,145,970
2,750,720 ### 19,016,808

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :98


PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL

19,220
29,149
629,690
2,254
105,095
106,415
2,815
5,081

6,816,302
216,086
54,621
370,000
163,285
344,901
177,077
215,630
227,651
369,422
384,919
236,640
167,999
6,380
9,289
451,227
113,261
21,426
34,275
300,141
178,697
179,333
210,793
11,228
139,372
205,761
50,000
50,000
181,000
184,000
Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :99
PT Pelabuhan Indonesia I (Persero)

HARGA SATUAN
UPAH BAHAN TOTAL
118,000
11,000
15,000
15,000
150,000
75,000
25,000
60,000
20,000
75,000
48,000

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :100


KUBIKASI/CALCULATION SHEET
PERKERASAN LAPANGAN EKS KANTIN DAN PARKIR TRU
BELAWAN INTERNATIONAL CONTAINER TERMINAL

NO. URAIAN PEKERJAAN Luas (m²)

1 2 3

I PEKERJAAN PERSIAPAN
1 Survey lokasi
2 Mobilisasi dan Demobilisasi Alat

Jumlah I

II PEKERJAAN GRILL DRAINASE DAERAH I


panjang grill baru
panjang bongkar psng btn
pekerjaan bongkar bata

1 Pekerjaan perbaikan beton dudukan grill

2 Pekerjaan bongkar beton 0.054

3 Pekerjaan bongkar bata 0.075

4 Pekerjaan beton bertulang 0.095

5 Pekerjaan besi siku pinggir 40.40.4 2

6 Pekerjaan besi pelat strip 5.50

7 Pekerjaan besi kotak 40x40 t 1,2

Jumlah II

IV PEKERJAAN LAIN-LAIN
1 Pembersihan akhir
2 Dokumentasi dan laporan

Jumlah IV
LATION SHEET
KANTIN DAN PARKIR TRUK
L CONTAINER TERMINAL

Panjang/t koefisien Gambar/ Keterangan


ebal (m¹) Jumlah (kg/m¹) Volume Satuan
4 5 6 7= 4 x 5 x 6 6

1 ls
1 ls

8 8 64 m
58 m
83.73 m

1 ls

58 3.132 m3

83.73 6.27975 m³

141.73 13.46435 m3

64 2.416667 309.3333 kg

64 2 128 kg

0.6 768 1.468 676.4544 kg

1 ls
1 ls
PERHITUNGAN VOLUME BESI
PEKERJAAN PERLUASAN WORKSHOP
BELAWAN INTERNATIONAL CONTAINER TERMINAL
Panjang / Panjang Koefisien
Ø Lebar Tinggi
No keliling(m Jumlah Jumlah Jumlah Berat
Besi(mm) (m¹) (m¹)
¹) (m¹) (Kg/m¹)
a b b c=axb d
sloof/ring balok beton bertulang untuk 1m³
1 10 10.526316 10 10 105.26316 0.617
2 8 0.15 0.45 1.2 70.175439 71 85.2 0.395

jumlah

pjng 1 m volume 0.095 m³

Pjng untuk menghasilkan 1m³ beton 10.526316 m¹


Berat Keterang
Besi (Kg) an

e=cxd

64.947 t.utama
33.654 sengkang

98.601 kg
PT Pelabuhan Indonesia I (Persero)

KAMUS KODE ANALISA dan UPAH/BAHAN

KODE URAIAN ANALISA KODE

PPS PEKERJAAN PERSIAPAN UPH


U

PTN PEKERJAAN TANAH ALT

PPO PEKERJAAN PASANGAN PONDASI ASB

PPD PASANGAN DINDING ASP


P

PBT PEKERJAAN BETON ATP

PPT PEKERJAAN PLESTERAN BBM

PPL PEKERJAAN PASANG LANTAI BKM

PCB PEKERJAAN CONE BLOCK / PAVING BLOCK BSI

PKY PEKERJAAN KAYU BTN

PAT PEKERJAAN ATAP BTU

PPC PEKERJAAN PENGECATAN CAT

PBK PEKERJAAN BONGKARAN CBK

SPL ANALISA SUPLEMEN DLL

PSI PEKERJAAN SANITASI KCA

PBS PEKERJAAN BESI DAN ALUMUNIUM KCI

PPG KPG
PEKERJAAN KUNCI DAN KACA

PLS ANALISA HARGA SATUAN PEKERJAAN LISTRIK KYU


PG

ABS ANALISA BASE LNT

ASP ANALISA ASPAL LST

ALT SEWA ALAT PKB

PTM PEKERJAAN PEMBERSIHAN TAMAN, JALAN PKU

PPA

PRK

SNT

TNM

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :107


PT Pelabuhan Indonesia I (Persero)

KODE URAIAN ANALISA KODE


TNM
TNM

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :108


PT Pelabuhan Indonesia I (Persero)

A dan UPAH/BAHAN

URAIAN UPAH DAN BAHAN

UPAH

SEWA ALAT

ASBES

ASPAL

ATAP

BAHAN PELARUT, PELUMAS

BAHAN KIMIA PEMBANTU UNTUK BETON

BAHAN BESI/BAJA TULANGAN/BESI BETON

BAHAN DARI BETON / BUIS / TIANG PANCANG

BATU, AGREGAT, TANAH

BAHAN CAT

CONEBLOCK / PAVING BLOCK

LAIN-LAIN

BAHAN KACA

PENGGANTUNG / PENGUNCI

KAPUR DAN GIPS

BAHAN KAYU

LANTAI KERAMIK / TERASO

INSTALASI LISTRIK

PERLATAN KEBERSIHAN

PAKU / BAUT

PIPA

BAHAN PEREKAT HIDROLIS & ORGANIK

PEATAN SANITASI

PERALATAN TAMAN / JALAN

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :109


PT Pelabuhan Indonesia I (Persero)

FORMULIR STANDAR UNTUK PEREKAMAN ANALISA


MASING MASING HARGA SATUAN

JENIS PEKERJAAN : LATASTON ( HRS )


SATUAN : M2

NO KOMPONEN SATUAN KUANTITAS

A TENAGA
1 Pekerja ( L 01 ) Jam 0.0113
2 Mandor ( L 03 ) Jam 0.0016

JUMLAH HARGA TENAGA

B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.0121
2 Agregat Halus ( M 04 ) M3 0.0232
3 Filler ( M 05 ) Kg 4.8004
4 Aspal ( M 10 ) Kg 5.2962

JUMLAH HARGA BAHAN

C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0011
2 AMP ( E 01 ) Jam 0.0016
3 Genset ( E 12 ) Jam 0.0016
4 Dump Truck ( E 09 ) Jam 0.0143
5 Aspal Finisher ( E 02 ) Jam 0.0020
6 Tandem Roller ( E 17 ) Jam 0.0017
7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0013
8 Alat Bantu Ls 1.0000

JUMLAH HARGA PERALATAN

JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan

Harga Satuan Pekerjaan Tahun 2012 Hal :110


PT Pelabuhan Indonesia I (Persero)

2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembaya
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar da
lainnya

Harga Satuan Pekerjaan Tahun 2012 Hal :111


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA HARGA SATUAN LATASTON ( HRS )


SATUAN : M2

No URAIAN KODE KOEF.

I ASUMSI
1 Menggunakan alat berat ( cara mekanik )
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0
5 Tebal lapisan padat t 0.03
6 Jam kerja efektif 1 hari Tk 7.00
7 Faktor kehilangan material
- Agregat Fh 1 1.10
- Aspal Fh 2 1.05

8 Komposisi campuran HRS ( Spesifikasi )


- Coarse Agregat 20 - 40 % CA 29.50
- Fine Agregat 47 - 67 % FA 56.50
- Fraksi Filler 5 - 9 % FF 6.49
- Aspal minimum 7,3 % As 7.51

9 Berat jenis bahan


- HRS D1 2.24
- Coarse Agregat dan fine agregat D2 1.80
- Fraksi Filler D3 2.00
- Aspal D4 1.03

II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat langsung ke
dalam Dump Truck dan diangkut ke lokasi pekerjaan.
3 Campuran panas HRS dihampar dengan Finisher dan dipadatakan dengan Tandem
dan Peneumatic Tire Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu

III PEMAKAIAN BAHAN ALAT DAN TENAGA


1 BAHAN
a Agregat kasar = {( CA x D1 x t m3 ) x ( Fh 1 )}/ D2 M03 0.0121
b Agregat halus = {( FA x D1 x t m3 ) x ( Fh 1 )}/ D2 M04 0.0232
c Filler = {( FF x D1 x t m3 ) x ( Fh 1 )} M05 4.8004
d Aspal = {( AS x D1 x t m3 ) x ( Fh 2 )}x1000 M10 5.2962

Harga Satuan Pekerjaan Tahun 2012 Hal :112


PT Pelabuhan Indonesia I (Persero)

2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50
Faktor bucket Fb 0.90
Faktor efisiensi alat Fa 0.83
Waktu siklus Ts 1
- Muat T1 1.50
- Lain lain T2 0.50
Ts 1 2.00

Kap Produksi / Jam = D2 x V x Fb x Fa x 60 Q1 900.40


D1 x t x Ts1
Koefisien Alat / m2 = 1 / Q1 ( E 15 ) 0.0011

Harga Satuan Pekerjaan Tahun 2012 Hal :113


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

b Aspalt Mixing Plant ( AMP ) ( E 01 )


Kapasitas produksi V 50.00
faktor Efisiensi alat Fa 0.83

Kapasitas produksi / jam = V x Fa Q2 617.56


D1 x t

Koefisien Alat / m2 = 1 / Q2 ( E 01 ) 0.0016

c Generator Set ( Genset ) ( E 12 )


Kapasitas produksi / jam = sama dengan AMP Q3 617.56

Koefisien Alat / m2 = 1 / Q3 ( E 12 ) 0.0016

d Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 8.00
Faktor efisiensi alat Fa 0.83
Kecepatan rata rata bermuatan v1 40.00
Kecepatan rata rata kosong v2 50.00
Kapasitas AMP batch Q2 b 0.50
Waktu menyiapkan 1 batch HRS Tb 1.00
Waktu Siklus Ts2
- Mengisi bak = ( V : Q2b ) x Tb T1 16.00
- Angkut = ( L : v1 ) x 60 menit T2 30.00
- Tunggu + Dumping + Putar T3 15.00
- Kembali = ( L : v2 ) x 60 menit T4 24.00
Ts2 85.00

Kapasitas Produksi / jam = V x Fa x 60 Q4 69.75


D1 x t x Ts2

Koefisien Alat / m2 = 1 / Q4 ( E 09 ) 0.0143

e Finisher ( E 02 )
Kapasitas produksi V 40.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = V x Fa Q5 494.05


D1 x t

Koefisien Alat / m2 = 1 / Q5 ( E 02 ) 0.0020

Harga Satuan Pekerjaan Tahun 2012 Hal :114


PT Pelabuhan Indonesia I (Persero)

f Tandem Roller ( E 17 )
Kecepatan rata rata alat v 3.50
Lebar efektif pemadatan b 1.20
Jumlah lintasan n 6.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = ( v x 1000 ) x b x Fa Q6 581.00


n

Koefisien Alat / m2 = 1 / Q6 ( E 17 ) 0.0017

Harga Satuan Pekerjaan Tahun 2012 Hal :115


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

g Pneumatic Tire Roller ( E 18 )


Kecepatan rata rata alat v 5.00
Lebar efektif pemadatan b 1.50
Jumlah lintasan n 8.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = ( v x 1000 ) x b x Fa Q7 778.13


n

Koefisien Alat / m2 = 1 / Q7 ( E 18 ) 0.0013

h Alat Bantu
Diperlukan :
- Kereta dorong = 2 bh
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan

3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 617.56
Produksi HRS / hari = Tk x Q2 Qt 4,322.92

Kebutuhan tenaga
- Pekerja P 7.00
- Mandor M 1.00

Koefisien tenaga /m2 :


- Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.0113
- Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0016

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT


( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing
Harga Satuan "
DIDAPAT HARGA SATUAN PEKERJAAN

Rp 19,220.00 / M2

6 WAKTU PELAKSANAAN YANG DIPERLUKAN

Harga Satuan Pekerjaan Tahun 2012 Hal :116


PT Pelabuhan Indonesia I (Persero)

Masa Pelaksanaan = ....... Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN


Volume Pekerjaan = . . . . . . . M2

Harga Satuan Pekerjaan Tahun 2012 Hal :117


PT Pelabuhan Indonesia I (Persero)

FORMULIR STANDAR UNTUK PEREKAMAN ANALISA


MASING MASING HARGA SATUAN

JENIS PEKERJAAN : LASTON ( AC )


SATUAN : M2

NO KOMPONEN SATUAN KUANTITAS

A TENAGA
1 Pekerja ( L 01 ) Jam 0.0217
2 Mandor ( L 03 ) Jam 0.0022

JUMLAH HARGA TENAGA

B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.0336
2 Agregat Halus ( M 04 ) M3 0.0149
3 Filler ( M 05 ) Kg 4.8015
4 Aspal ( M 10 ) Kg 6.6150

JUMLAH HARGA BAHAN

C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0015
2 AMP ( E 01 ) Jam 0.0022
3 Genset ( E 12 ) Jam 0.0022
4 Dump Truck ( E 09 ) Jam 0.0348
5 Aspal Finisher ( E 02 ) Jam 0.0027
6 Tandem Roller ( E 17 ) Jam 0.0016
7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0023
8 Alat Bantu Ls 1.0000

JUMLAH HARGA PERALATAN

JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembaya
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator

Harga Satuan Pekerjaan Tahun 2012 Hal :118


PT Pelabuhan Indonesia I (Persero)

4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar da
lainnya

Harga Satuan Pekerjaan Tahun 2012 Hal :119


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA HARGA SATUAN LASTON ( AC )


SATUAN : M2

No URAIAN KODE KOEF.

I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0
5 Tebal lapisan ( AC ) padat t 0.04
6 Jam kerja efektif 1 hari Tk 7.00
7 Faktor kehilangan material
- Agregat Fh 1 1.10
- Aspal Fh 2 1.05

8 Komposisi campuran AC ( Spesifikasi )


- Coarse Agregat 30 - 50 % CA 61.15
- Fine Agregat 39 - 59 % FA 27.00
- Filler 4,5 - 7,5 % FF 4.85
- Aspal minimum 6,7 % As 7.00

9 Berat jenis bahan


- AC D1 2.25
- Coarse Agregat dan fine agregat D2 1.80
- Filler D3 2.00
- Aspal D4 1.03

II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat langsung ke
dalam Dump Truck dan diangkut ke lapangan
3 Campuran panas AC dihampar dengan Finisher dan dipadatakan dengan Tandem dan
Tire Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu

III PEMAKAIAN BAHAN ALAT DAN TENAGA


1 BAHAN
a Agregat kasar = {( CA x D1 x t m3 ) x ( Fh 1 )}/ D2 M03 0.034
b Agregat halus = {( FA x D1 x t m3 ) x ( Fh 1 )}/ D2 M04 0.015
c Filler = {( FF x D1 x t m3 ) x ( Fh 1 )} M05 4.802
d Aspal = {( AS x D1 x t m3 ) x ( Fh 2 )}x1000 M10 6.615

Harga Satuan Pekerjaan Tahun 2012 Hal :120


PT Pelabuhan Indonesia I (Persero)

2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50
Faktor bucket Fb 0.90
Faktor efisiensi alat Fa 0.83
Waktu siklus Ts 1
- Muat T1 1.50
- Lain lain T2 0.50
Ts 1 2.00

Kap Produksi / Jam = D2 x V x Fb x Fa x 60 Q1 672.30


D1 x t x Ts1
Koefisien Alat / m2 = 1 / Q1 ( E 15 ) 0.0015

Harga Satuan Pekerjaan Tahun 2012 Hal :121


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

b Aspalt Mixing Plant ( AMP ) ( E 01 )


Kapasitas produksi V 50.00
faktor Efisiensi alat Fa 0.83

Kapasitas produksi / jam = V x Fa Q2 461.11


D1 x t

Koefisien Alat / m2 = 1 / Q2 ( E 01 ) 0.0022

c Generator Set ( Genset ) ( E 12 )


Kapasitas produksi / jam = sama dengan AMP Q3 461.11

Koefisien Alat / m2 = 1 / Q3 ( E 12 ) 0.0022

d Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 4.00
Faktor efisiensi alat Fa 0.83
Kecepatan rata rata bermuatan v1 40.00
Kecepatan rata rata kosong v2 50.00
Kapasitas AMP batch Q2 b 0.50
Waktu menyiapkan 1 batch AC Tb 1.00
Waktu Siklus Ts2
- Mengisi bak = ( V : Q2b ) x Tb T1 8.00
- Angkut = ( L : v1 ) x 60 menit T2 29.99
- Tunggu + Dumping + Putar T3 15.00
- Kembali = ( L : v2 ) x 60 menit T4 23.99
Ts2 76.98

Kapasitas Produksi / jam = V x Fa x 60 Q4 28.75


D1 x t x Ts2

Koefisien Alat / m2 = 1 / Q4 ( E 09 ) 0.0348

e Finisher ( E 02 )
Kapasitas produksi V 40.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = V x Fa Q5 368.89


D1 x t

Koefisien Alat / m2 = 1 / Q5 ( E 02 ) 0.0027

Harga Satuan Pekerjaan Tahun 2012 Hal :122


PT Pelabuhan Indonesia I (Persero)

f Tandem Roller ( E 17 )
Kecepatan rata rata alat v 2.50
Lebar efektif pemadatan b 1.20
Jumlah lintasan n 4.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = ( v x 1000 ) x b x Fa Q6 622.50


n

Koefisien Alat / m2 = 1 / Q6 ( E 17 ) 0.0016

Harga Satuan Pekerjaan Tahun 2012 Hal :123


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

g Pneumatic Tire Roller ( E 18 )


Kecepatan rata rata alat v 3.50
Lebar efektif pemadatan b 1.20
Jumlah lintasan n 8.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = ( v x 1000 ) x b x Fa Q7 435.75


n

Koefisien Alat / m2 = 1 / Q7 ( E 18 ) 0.0023

h Alat Bantu
Diperlukan :
- Rambu = 2 bh
- Kereta dorong = 2 bh
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan

3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 461.11
Produksi AC / hari = Tk x Q2 Qt 3,227.78

Kebutuhan tenaga
- Pekerja P 10.00
- Mandor M 1.00

Koefisien tenaga /m2 :


- Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.0217
- Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0022

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT


( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing
Harga Satuan "
DIDAPAT HARGA SATUAN PEKERJAAN

Rp 29,149.00 / M2

Harga Satuan Pekerjaan Tahun 2012 Hal :124


PT Pelabuhan Indonesia I (Persero)

6 WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan = . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN


Volume Pekerjaan = . . . . . . . M2

Harga Satuan Pekerjaan Tahun 2012 Hal :125


PT Pelabuhan Indonesia I (Persero)

FORMULIR STANDAR UNTUK PEREKAMAN ANALISA


MASING MASING HARGA SATUAN

JENIS PEKERJAAN : ASPHALT TREATED BASE ( ATB )


SATUAN : M3

NO KOMPONEN SATUAN KUANTITAS

A TENAGA
1 Pekerja ( L 01 ) Jam 0.3880
2 Mandor ( L 03 ) Jam 0.0554

JUMLAH HARGA TENAGA

B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.7028
2 Agregat Halus ( M 04 ) M3 0.5341
3 Filler ( M 05 ) Kg 139.2
4 Aspal ( M 10 ) Kg 157.0

JUMLAH HARGA BAHAN

C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0380
2 AMP ( E 01 ) Jam 0.0554
3 Genset ( E 12 ) Jam 0.0554
4 Dump Truck ( E 09 ) Jam 0.4906
5 Aspal Finisher ( E 02 ) Jam 0.0767
6 Tandem Roller ( E 17 ) Jam 0.0430
7 Pneumatic Tyre Roller ( E 18 ) Jam 0.0321
8 Alat Bantu Ls 1.0000

JUMLAH HARGA PERALATAN

JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembaya
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator

Harga Satuan Pekerjaan Tahun 2012 Hal :126


PT Pelabuhan Indonesia I (Persero)

4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar da
lainnya

Harga Satuan Pekerjaan Tahun 2012 Hal :127


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA HARGA SATUAN ASPHALT TREATED BASE ( ATB )

SATUAN : M3

No URAIAN KODE KOEF.

I ASUMSI
1 Menggunakan alat berat ( Cara mekanik )
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0
5 Tebal lapisan ( ATB ) padat t 0.04
6 Jam kerja efektif 1 hari Tk 7.00
7 Faktor kehilangan material
- Agregat Fh 1 1.10
- Aspal Fh 2 1.05

8 Komposisi campuran ATB ( Spesifikasi )


- Coarse Agregat 40 - 60 % CA 50.00
- Fine Agregat 26 - 49,5 % FA 38.00
- Fraksi Filler 4,5 - 7,5 % FF 5.50
- Aspal minimum 6 % As 6.50

9 Berat jenis bahan


- ATB D1 2.30
- Coarse Agregat dan fine agregat D2 1.80
- Fraksi Filler D3 2.00
- Aspal D4 1.03

II METODA KERJA
1 WHEEL LOADER memuat agregat dan aspal kedalam Coldbin AMP
2 Agregat dan aspal dicampur dan dipanaskan dengan AMP untuk dimuat langsung ke
dalam Dump truck dan diangkut ke lokasi pekerjaan
3 Campuran panas ATB dihampar dengan Finisher dan dipadatakan dengan Tandem dan
Pneumatic Roller
4 Selama pemadatan sekelompok pekerja merapikan tepi hamparan dengan
menggunakan alat bantu

III PEMAKAIAN BAHAN ALAT DAN TENAGA


1 BAHAN
a Agregat kasar = {( CA x D1 x 1 m3 ) x ( Fh 1 )}/ D2 M03 0.7028
b Agregat halus = {( FA x D1 x 1 m3 ) x ( Fh 1 )}/ D2 M04 0.5341
c Filler = {( FF x D1 x 1 m3 ) x ( Fh 1 )} M05 139.2
d Aspal = {( AS x D1 x 1 m3 ) x ( Fh 2 )} M10 157.0

Harga Satuan Pekerjaan Tahun 2012 Hal :128


PT Pelabuhan Indonesia I (Persero)

2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50
Faktor bucket Fb 0.90
Faktor efisiensi alat Fa 0.83
Waktu siklus Ts 1
- Muat T1 1.50
- Lain lain T2 0.50
Ts 1 2.00

Kap Produksi / Jam = D2 x V x Fb x Fa x 60 Q1 26.31


D1 x Ts1
Koefisien Alat / m2 = 1 / Q1 ( E 15 ) 0.0380

Harga Satuan Pekerjaan Tahun 2012 Hal :129


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

b Aspalt Mixing Plant ( AMP ) ( E 01 )


Kapasitas produksi V 50.00
Faktor Efisiensi alat Fa 0.83

Kapasitas produksi / jam = V x Fa Q2 18.04


D1

Koefisien Alat / m3 = 1 / Q2 ( E 01 ) 0.0554

c Generator Set ( Genset ) ( E 12 )


Kapasitas produksi / jam = sama dengan AMP Q3 18.04

Koefisien Alat / m3 = 1 / Q3 ( E 12 ) 0.0554

d Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 8.00
Faktor efisiensi alat Fa 0.83
Kecepatan rata rata bermuatan v1 40.00
Kecepatan rata rata kosong v2 50.00
Kapasitas AMP batch Q2 b 0.50
Waktu menyiapkan 1 batch ATB Tb 1.00
Waktu Siklus Ts2
- Mengisi bak = ( V : Q2b ) x Tb T1 16.00
- Angkut = ( L : v1 ) x 60 menit T2 29.99
- Tunggu + Dumping + Putar T3 15.00
- Kembali = ( L : v2 ) x 60 menit T4 23.99
Ts2 84.99

Kapasitas Produksi / jam = V x Fa x 60 Q4 2.04


D1 x Ts2

Koefisien Alat / m3 = 1 / Q4 ( E 09 ) 0.4906

e Finisher
Kapasitas produksi V 40.00
Faktor efisiensi alat Fa 0.75

Kapasitas produksi / jam = V x Fa Q5 13.04


D1

Koefisien Alat / m3 = 1 / Q5 ( E 02 ) 0.0767

Harga Satuan Pekerjaan Tahun 2012 Hal :130


PT Pelabuhan Indonesia I (Persero)

f Tandem Roller ( E 17 )
Kecepatan rata rata alat v 3.50
Lebar efektif pemadatan b 1.20
Jumlah lintasan n 6.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q6 23.24


n

Koefisien Alat / m3 = 1 / Q6 ( E 17 ) 0.0430

Harga Satuan Pekerjaan Tahun 2012 Hal :131


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

g Pneumatic Tire Roller ( E 18 )


Kecepatan rata rata alat v 5.00
Lebar efektif pemadatan b 1.50
Jumlah lintasan n 8.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q7 31.13


n

Koefisien Alat / m3 = 1 / Q7 ( E 18 ) 0.0321

h Alat Bantu
Diperlukan :
- Kereta dorong = 2 bh
- Skop = 3 bh
- Garpu = 2 bh
- Tongkat kontrol ketebalan hamparan

3 TENAGA
Produksi menentukan : ASPALT MIXING PLANT ( AMP ) Q2 18.04
Produksi ATB / hari = Tk x Q2 Qt 126.30

Kebutuhan tenaga
- Pekerja P 7.00
- Mandor M 1.00

Koefisien tenaga /m2 :


- Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.3880
- Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0554

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT


( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing
Harga Satuan "
DIDAPAT HARGA SATUAN PEKERJAAN

Rp 629,690.00 / M3

6 WAKTU PELAKSANAAN YANG DIPERLUKAN

Harga Satuan Pekerjaan Tahun 2012 Hal :132


PT Pelabuhan Indonesia I (Persero)

Masa Pelaksanaan = . . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN


Volume Pekerjaan = . . . . . . . . . M2

Harga Satuan Pekerjaan Tahun 2012 Hal :133


PT Pelabuhan Indonesia I (Persero)

FORMULIR STANDAR UNTUK PEREKAMAN ANALISA


MASING MASING HARGA SATUAN

JENIS PEKERJAAN : LAPIS RESAP PENGIKAT (PRIME COAT)


SATUAN : LITER

NO KOMPONEN SATUAN KUANTITAS

A TENAGA
1 Pekerja ( L 01 ) Jam 0.0301
2 Mandor ( L 03 ) Jam 0.0060

JUMLAH HARGA TENAGA

B BAHAN
1 Aspal ( M 10 ) ( M 10 ) Kg 0.6417
2 Karosene ( M 11 ) ( M 11 ) Liter 0.4889

JUMLAH HARGA BAHAN

C PERALATAN
1 Asphalt Sprayer ( E 03 ) Jam 0.0030
2 Compresor ( E 05 ) Jam 0.0031
3 Dump Truck ( E 08 ) Jam 0.0030

JUMLAH HARGA PERALATAN

JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembaya
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar da
lainnya

Harga Satuan Pekerjaan Tahun 2012 Hal :134


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA HARGA SATUAN LAPIS RESAP PENGIKAT

SATUAN : L

No URAIAN KODE KOEF.

I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.00
4 Jam kerja efektif 1 hari Tk 7.00
5 Faktor kehilangan material Fh 1.10
6 Komposisi campuran AC ( Spesifikasi )
- Aspal AC - 10 atau AC - 20 AS 56
- Minyak Flux / pencair K 44

7 Berat jenis bahan


- Aspal AC - 10 atau AC - 20 D1 1.05
- Minyak Flux / pencair D2 0.80

8 Bahan dasar ( aspal dan minyak pencair ) semuanya diterima di Lokasi Pekerjaan

II METODA KERJA
1 Aspal dan minyak Flux dicampur dan dipanaskan sehingga menjadi campuran aspal cair
2 Permukaan yang akan dilapis dibersihkan dari debu dan kotoran dg air kompresor
3 Campuran aspal cair disemprotkan dg aspahalt sprayer ke atas permukaan yg akan dilapis
4 Angkutan aspal dan minyak Flux menggunakan Dump truck

III PEMAKAIAN BAHAN ALAT DAN TENAGA


1 BAHAN
Untuk mendapatkan 1 liter lapis resap pengikat diperlukan
( 1 Liter x Fh ) PC 1.1000
a Aspal = AS x PC x D1 M10 0.6417
b Kerosene = K x PC M11 0.4889

2 ALAT
a Asphalt Sprayer ( E 03 )
Kapasitas alat V 800.00
Faktor efisiensi alat Fa 0.83
Waktu siklus ( termasuk proses pemanasan ) Ts 2.00

Kap Produksi / Jam = V x Fa Q1 332.00


Ts

Harga Satuan Pekerjaan Tahun 2012 Hal :135


PT Pelabuhan Indonesia I (Persero)

Koefisien Alat / Liter = 1 / Q1 ( E 03 ) 0.0030

b Air Compresor ( E 05 )
Kapasitas alat -----------> Diambil V 400.00
Aplikasi Lapis Resap Pengikat Rata rata ( Spesifikasi ) Ap 0.80

Kapasitas produksi / jam = V x Ap Q2 320.00

Koefisien Alat / liter = 1 / Q2 ( E 05 ) 0.0031

Harga Satuan Pekerjaan Tahun 2012 Hal :136


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

c Dump Truk ( DT ) ( E 08 )
Sebagai alat pengangkut bahan di lokasi pekerjaan Dump Truck melayani alat
Asphalt Sprayer

Kapasitas Produksi / jam = V x Fa Q3 332.00


Ts

Koefisien Alat / m2 = 1 / Q3 ( E 08 ) 0.0030

3 TENAGA
Produksi menentukan : ASPALT FINISHER Q4 332.00
Produksi Lapis Resap Pengikat / hari = Tk x Q4 Qt 2,324.00

Kebutuhan tenaga
- Pekerja P 10.00
- Mandor M 2.00

Koefisien tenaga /liter :


- Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.0301
- Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0060

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT


( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing
Harga Satuan "
DIDAPAT HARGA SATUAN PEKERJAAN

Rp 2,254.00 / LITER

6 WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan = . . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN


Volume Pekerjaan = . . . . . . . . . Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :137


PT Pelabuhan Indonesia I (Persero)

FORMULIR STANDAR UNTUK PEREKAMAN ANALISA


MASING MASING HARGA SATUAN

JENIS PEKERJAAN : LAPIS PONDASI AGREGAT KLAS A


SATUAN : M3

NO KOMPONEN SATUAN KUANTITAS

A TENAGA
1 Pekerja ( L 01 ) Jam 0.4373
2 Mandor ( L 03 ) Jam 0.0625

JUMLAH HARGA TENAGA

B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.7680
2 Agregat Halus ( M 04 ) M3 0.4320

JUMLAH HARGA BAHAN

C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0625
2 Dump Truck ( E 09 ) Jam 0.1994
3 Motor Grader ( E 13 ) Jam 0.0117
4 Vibratory Roller ( E 19 ) Jam 0.0178
5 Pneumatic Tyre Roller ( E 18 ) Jam 0.0043
6 Water Tank Truck ( E 23 ) Jam 0.0211
7 Alat Bantu Ls 1.0000

JUMLAH HARGA PERALATAN

JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN

UNTUK 1 M2 TEBAL 20 CM
UNTUK 1 M2 TEBAL 15 CM
UNTUK 1 M2 TEBAL 10 CM

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembaya

Harga Satuan Pekerjaan Tahun 2012 Hal :138


PT Pelabuhan Indonesia I (Persero)

3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar da
lainnya

Harga Satuan Pekerjaan Tahun 2012 Hal :139


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA HARGA SATUAN LAPIS PONDASI AGREGAT KLAS A

SATUAN : M3

No URAIAN KODE KOEF.

I ASUMSI
1 Menggunakan alat berat Cara mekanik
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0
5 Tebal Agregat padat t 0.15
6 Faktor kembang material ( padat - lepas ) Fk 1.20
7 Jam kerja efektif per hari Tk 7.00
8 Proporsi campuran
- Agregat Kasar Ak 64.00
- Agregat halus Ah 36.00

II METODA KERJA
1 WHEEL LOADER mencampur dan memuat agregat ke dalam Dump Truck di Base
camp
2
Dump Truck mengangkut Agregat ke lokasi pekerjaan dan dihampar dg motor Grader
3 Hamparan Agregat di basahi dengan Water Tank Truck sebelum dipadatkan dengan
Tandem Roller & PTR
4 Selama pemadatan sekelompok pekerja akan merapikan tepi hamparan dan level
permukaan dengan menggunakan alat bantu

III PEMAKAIAN BAHAN ALAT DAN TENAGA


1 BAHAN
a Agregat kasar = Ak x 1 m3 x Fk M03 0.7680
b Agregat halus = Ah x 1 m3 x Fk M04 0.4320

2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50
Faktor bucket Fb 0.90
Faktor efisiensi alat Fa 0.83
Waktu siklus Ts 1
- Mencampur T1 2.50
- Memuat dan Lain lain T2 1.00
Ts 1 3.50

Kap Produksi / Jam = V x Fb x Fa x 60 Q1 16.01

Harga Satuan Pekerjaan Tahun 2012 Hal :140


PT Pelabuhan Indonesia I (Persero)

Fk x Ts1
Koefisien Alat / m3 = 1 / Q1 ( E 15 ) 0.0625

b Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 6.00
Faktor efisiensi alat Fa 0.83
Kecepatan rata rata bermuatan v1 45.00
Kecepatan rata rata kosong v2 60.00
Waktu Siklus Ts2
- Waktu tempuh isi = ( L : v1 ) x 60 menit T1 26.65
- Waktu tempuh kosong = ( L : v2 ) x 60 menit T2 19.99
- lain lain termasuk menurunkan Agregat T3 3.00

Ts2 49.65

Harga Satuan Pekerjaan Tahun 2012 Hal :141


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

Kapasitas Produksi / jam = V x Fa x 60 Q2 5.02


Fk x Ts2

Koefisien Alat / m3 = 1 / Q2 ( E 09 ) 0.1994

c Motor Grader ( E 13 )
Panjang hamparan Lh 50.00
Lebar efektif kerja blade b 2.40
Faktor Efisiensi alat Fa 0.83
Kecepatan rata rata alat v 4.00
Jumlah lintasan n 6.00
Waktu siklus Ts 3
- Perataan 1 Lintasan = Lh : ( v x 1000 x 60 menit ) T1 0.75
- Lain lain T2 1.00
Ts 3 1.75

Kapasitas produksi / jam = Lh x b x t x Fa x 60 Q3 85.37


n x Ts 3

Koefisien Alat / m3 = 1 / Q3 ( E 02 ) 0.0117

d Vibratory Roller ( E 19 )
Kecepatan rata rata alat v 3.00
Lebar efektif pemadatan b 1.20
Jumlah lintasan n 8.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q4 56.03


n

Koefisien Alat / m3 = 1 / Q4 ( E 19 ) 0.0178

e Pneumatic Tire Roller ( E 18 )


Kecepatan rata rata alat v 5.00
Lebar efektif pemadatan b 1.50
Jumlah lintasan n 4.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q5 233.44


n

Koefisien Alat / m3 = 1 / Q5 ( E 18 ) 0.0043

Harga Satuan Pekerjaan Tahun 2012 Hal :142


PT Pelabuhan Indonesia I (Persero)

f Water Tank Truck ( E 23 )


Volume tangki air v 4.00
Kebutuhan air / m3 agregat padat Wc 0.07
Pengisian tangki / jam n 1.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = v x n x Fa Q6 47.43


Wc

Koefisien Alat / m3 = 1 / Q6 ( E 23 ) 0.0211

Harga Satuan Pekerjaan Tahun 2012 Hal :143


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

g Alat Bantu
Diperlukan :

- Kereta dorong = 2 bh
- Skop = 3 bh
- Garpu = 2 bh

3 TENAGA
Produksi menentukan : WHEEL LOADER Q1 16.01
Produksi Agregat / hari = Tk x Q1 Qt 112.05

Kebutuhan tenaga
- Pekerja P 7.00
- Mandor M 1.00

Koefisien tenaga /m2 :


- Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.4373
- Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0625

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT


( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing
Harga Satuan "
DIDAPAT HARGA SATUAN PEKERJAAN

Rp 105,095.00 / M2

6 WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan = . . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN


Volume Pekerjaan = . . . . . . . . . M3

Harga Satuan Pekerjaan Tahun 2012 Hal :144


PT Pelabuhan Indonesia I (Persero)

FORMULIR STANDAR UNTUK PEREKAMAN ANALISA


MASING MASING HARGA SATUAN

JENIS PEKERJAAN : LAPIS PONDASI AGREGAT KLAS B


SATUAN : M3

NO KOMPONEN SATUAN KUANTITAS

A TENAGA
1 Pekerja ( L 01 ) Jam 0.4373
2 Mandor ( L 03 ) Jam 0.0625

JUMLAH HARGA TENAGA

B BAHAN
1 Agregat Kasar ( M 03 ) M3 0.7080
2 Agregat Halus ( M 04 ) M3 0.4920

JUMLAH HARGA BAHAN

C PERALATAN
1 Wheel Loader ( E 15 ) Jam 0.0625
2 Dump Truck ( E 09 ) Jam 0.1994
3 Motor Grader ( E 13 ) Jam 0.0117
4 Vibratory Roller ( E 19 ) Jam 0.0178
5 Pneumatic Tyre Roller ( E 18 ) Jam 0.0043
6 Water Tank Truck ( E 23 ) Jam 0.0211
7 Alat Bantu Ls 1.0000

JUMLAH HARGA PERALATAN

JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN

UNTUK 1 M2 TEBAL 20 CM
UNTUK 1 M2 TEBAL 15 CM
UNTUK 1 M2 TEBAL 10 CM

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan

Harga Satuan Pekerjaan Tahun 2012 Hal :145


PT Pelabuhan Indonesia I (Persero)

2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembaya

3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar da
lainnya

Harga Satuan Pekerjaan Tahun 2012 Hal :146


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA HARGA SATUAN LAPIS PONDASI AGREGAT KLAS B

SATUAN : M3

No URAIAN KODE KOEF.

I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Kondisi existing jalan sedang
4 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.0
5 Tebal Agregat padat t 0.15
6 Faktor kembang material ( padat - lepas ) Fk 1.20
7 Jam kerja efektif per hari Tk 7.00
8 Proporsi campuran
- Agregat Kasar Ak 59.00
- Agregat halus Ah 41.00

II METODA KERJA
1 WHEEL LOADER mencampur dan memuat agregat ke dalam Dump Truck di Base
camp
2 Dump Truck mengangkut Agregat ke lokasi pekerjaan dan dihampar dengan motor
Grader
3 Hamparan Agregat di basahi dengan Water Tank Truck sebelum dipadatkan dengan
Tandem Roller & PTR
4 Selama pemadatan sekelompok pekerja akan merapikan tepi hamparan dan level
permukaan dengan menggunakan alat bantu

III PEMAKAIAN BAHAN ALAT DAN TENAGA


1 BAHAN
a Agregat kasar = Ak x 1 m3 x Fk M03 0.7080
b Agregat halus = Ah x 1 m3 x Fk M04 0.4920

2 ALAT
a Wheel Loader ( E 15 )
Kapasitas bucket V 1.50
Faktor bucket Fb 0.90
Faktor efisiensi alat Fa 0.83
Waktu siklus Ts 1
- Mencampur T1 2.50
- Memuat dan Lain lain T2 1.00
Ts 1 3.50

Kap Produksi / Jam = V x Fb x Fa x 60 Q1 16.01

Harga Satuan Pekerjaan Tahun 2012 Hal :147


PT Pelabuhan Indonesia I (Persero)

Fk x Ts1
Koefisien Alat / m2 = 1 / Q1 ( E 15 ) 0.0625

b Dump Truk ( DT ) ( E 09 )
Kapasitas bak V 6.00
Faktor efisiensi alat Fa 0.83
Kecepatan rata rata bermuatan v1 45.00
Kecepatan rata rata kosong v2 60.00
Waktu Siklus Ts2
- Waktu tempuh isi = ( L : v1 ) x 60 menit T1 26.65
- Waktu tempuh kosong = ( L : v2 ) x 60 menit T2 19.99
- lain lain termasuk menurunkan Agregat T3 3.00

Ts2 49.65

Harga Satuan Pekerjaan Tahun 2012 Hal :148


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

Kapasitas Produksi / jam = V x Fa x 60 Q2 5.02


Fk x Ts2

Koefisien Alat / m2 = 1 / Q2 ( E 09 ) 0.1994

c Motor Grader ( E 13 )
Panjang hamparan Lh 50.00
Lebar efektif kerja blade b 2.40
Faktor Efisiensi alat Fa 0.83
Kecepatan rata rata alat v 4.00
Jumlah lintasan n 6.00
Waktu siklus Ts 3
- Perataan 1 Lintasan = ( Lh x 60 ) : ( v x 1000 ) T1 0.75
- Lain lain T2 1.00
Ts 3 1.75

Kapasitas produksi / jam = Lh x b x t x Fa x 60 Q3 85.37


n x Ts 3

Koefisien Alat / m2 = 1 / Q3 ( E 02 ) 0.0117

d Vibratory Roller ( E 17 )
Kecepatan rata rata alat v 3.00
Lebar efektif pemadatan b 1.20
Jumlah lintasan n 8.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q4 56.03


n

Koefisien Alat / m2 = 1 / Q4 ( E 17 ) 0.0178

e Pneumatic Tire Roller ( E 18 )


Kecepatan rata rata alat v 5.00
Lebar efektif pemadatan b 1.50
Jumlah lintasan n 4.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = ( v x 1000 ) x b x t x Fa Q5 233.44


n

Koefisien Alat / m2 = 1 / Q5 ( E 18 ) 0.0043

Harga Satuan Pekerjaan Tahun 2012 Hal :149


PT Pelabuhan Indonesia I (Persero)

f Water Tank Truck ( E 23 )


Volume tangki air v 4.00
Kebutuhan air / m3 agregat padat Wc 0.07
Pengisian tangki / jam n 1.00
Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = v x n x Fa Q6 47.43


Wc

Koefisien Alat / m2 = 1 / Q6 ( E 23 ) 0.0211

Harga Satuan Pekerjaan Tahun 2012 Hal :150


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

g Alat Bantu
Diperlukan :

- Kereta dorong = 2 bh
- Skop = 3 bh
- Garpu = 2 bh

3 TENAGA
Produksi menentukan : WHEEL LOADER Q1 16.01
Produksi Agregat / hari = Tk x Q1 Qt 112.05

Kebutuhan tenaga
- Pekerja P 7.00
- Mandor M 1.00

Koefisien tenaga /m2 :


- Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.4373
- Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0625

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT


( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing
Harga Satuan "
DIDAPAT HARGA SATUAN PEKERJAAN

Rp 106,415.00 / M2

6 WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan = . . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN


Volume Pekerjaa = . . . . . . . . . M2

Harga Satuan Pekerjaan Tahun 2012 Hal :151


PT Pelabuhan Indonesia I (Persero)

FORMULIR STANDAR UNTUK PEREKAMAN ANALISA


MASING MASING HARGA SATUAN

JENIS PEKERJAAN : LAPIS PEREKAT (TACK COAT)


SATUAN : LITER

NO KOMPONEN SATUAN KUANTITAS

A TENAGA
1 Pekerja ( L 01 ) Jam 0.0301
2 Mandor ( L 03 ) Jam 0.0060

JUMLAH HARGA TENAGA

B BAHAN
1 Aspal ( M 10 ) Kg 0.8880
2 Kerosene ( M 11 ) Liter 0.2530

JUMLAH HARGA BAHAN

C PERALATAN
1 Asphalt Sprayer ( E 03 ) Jam 0.0030
2 Compresor ( E 05 ) Jam 0.0063
3 Dump Truck ( E 08 ) Jam 0.0030

JUMLAH HARGA PERALATAN

JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembaya
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar da
lainnya

Harga Satuan Pekerjaan Tahun 2012 Hal :152


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA HARGA SATUAN LAPIS PEREKAT

SATUAN : M3

No URAIAN KODE KOEF.

I ASUMSI
1 Menggunakan alat berat
2 Lokasi pekerjaan sepanjang jalan
3 Jarak rata rata Base Camp ke Lokasi pekerjaan L 20.00
4 Jam kerja efektif 1 hari Tk 7.00
5 Faktor kehilangan material Fh 1.10
6 Komposisi campuran ( Spesifikasi )
- Aspal AC - 10 atau AC - 20 AS 77
- Minyak Flux / pencair K 23

7 Berat jenis bahan


- Aspal AC - 10 atau AC - 20 D1 1.05
- Minyak Flux / pencair D2 0.80

8
Bahan dasar ( aspal dan minyak pencair ) semuanya diterima di Lokasi Pekerjaan

II METODA KERJA
1 Aspal dan minyak Flux dicampur dan dipanaskan sehingga menjadi campuran aspal
cair
2
Permukaan yang akan dilapis dibersihkan dari debu dan kotoran dg air kompresor
3 Campuran aspal cair disemprotkan dg aspahalt sprayer ke atas permukaan yg akan
dilapis
4 Angkutan aspal dan minyak Flux menggunakan Dump truck

III PEMAKAIAN BAHAN ALAT DAN TENAGA


1 BAHAN
Untuk mendapatkan 1 liter lapis resap pengikat diperlukan
( 1 Liter x Fh ) PC 1.1000
a Aspal = AS x PC x D1 M10 0.8880
b Kerosene = K x PC M11 0.2530

2 ALAT
a Asphalt Sprayer ( E 03 )
Kapasitas alat V 800.00
Faktor efisiensi alat Fa 0.83
Waktu siklus ( termasuk proses pemanasan ) Ts 2.00

Harga Satuan Pekerjaan Tahun 2012 Hal :153


PT Pelabuhan Indonesia I (Persero)

Kap Produksi / Jam = V x Fa Q1 332.00


Ts
Koefisien Alat / Liter = 1 / Q1 ( E 03 ) 0.0030

b Air Compresor ( E 05 )
Kapasitas alat . . . . . Diambil V 400.00
Aplikasi Lapis Resap Pengikat Rata rata ( Spesifikasi ) Ap 0.40

Kapasitas produksi / jam = V x Ap Q2 160.00

Koefisien Alat / liter = 1 / Q2 ( E 05 ) 0.0063

Harga Satuan Pekerjaan Tahun 2012 Hal :154


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

c Dump Truk ( DT ) ( E 08 )
Sebagai alat pengangkut bahan di lokasi pekerjaan Dump Truck melayani alat
Asphalt Sprayer

Kapasitas Produksi / jam = V x Fa Q3 332.00


Ts

Koefisien Alat / m2 = 1 / Q3 ( E 08 ) 0.0030

3 TENAGA
Produksi menentukan : ASPALT FINISHER Q4 332.00
Produksi Lapis Perekat / hari = Tk x Q4 Qt 2,324.00

Kebutuhan tenaga
- Pekerja P 10.00
- Mandor M 2.00

Koefisien tenaga /liter :


- Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.0301
- Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0060

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT


( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing
Harga Satuan "
DIDAPAT HARGA SATUAN PEKERJAAN

Rp 2,815.00 / Liter

6 WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan = . . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN


Volume Pekerjaan = . . . . . . . . . Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :155


PT Pelabuhan Indonesia I (Persero)

FORMULIR STANDAR UNTUK PEREKAMAN ANALISA


MASING MASING HARGA SATUAN

JENIS PEKERJAAN : PENYIAPAN BADAN JALAN (PEMADATAN DAN PERATAAN)


SATUAN : M2

NO KOMPONEN SATUAN KUANTITAS

A TENAGA
1 Pekerja ( L 01 ) Jam 0.0161
2 Mandor ( L 02 ) Jam 0.0040

JUMLAH HARGA TENAGA

B BAHAN

JUMLAH HARGA BAHAN

C PERALATAN
1 Motor Grader ( E 13 ) Jam 0.0025
2 Vibratory Roller ( E 19 ) Jam 0.0040
3 Water Tank Truck ( E 23 ) Jam 0.0105
4 Alat Bantu Ls 1.0000

JUMLAH HARGA PERALATAN

JUMLAH
JASA 10 %
JUMLAH ( BELUM TERMASUK PPN )
DIBULATKAN

1 Satuan dapat berdasarkan atas jam operasi untuk tenaga kerja dan peralatan, Volume dan / atau ukuran berat untuk bahan
2 Kuantitas satuan adalah kuantitas setiap komponen untuk menyelesaikan satu satuan pekerjaan dari nomor mata pembaya
3 Biaya satuan untuk peralatan sudah termasuk bahan bakar, bahan habis dipakai dan operator
4 Biaya satuan sudah termasuk pengeluaran untuk seluruh pajak yang berkaitan ( tetapi tidak termasuk PPN yang dibayar da
lainnya

Harga Satuan Pekerjaan Tahun 2012 Hal :156


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA HARGA SATUAN PENYIAPAN BADAN JALAN


( PEMADATAN DAN PERATAAN )

SATUAN : M2

No URAIAN KODE KOEF.

I ASUMSI
1 Pekerjaan dilakukan pada hanya pada tanah galian
2 Pekerjaan dilakukan secara mekanis
3 Lokasi pekerjaan : sepanjang jalan
4 Kondisi jalan : jelek / belum padat
5 Jam kerja efektif per hari Tk 7.00

II URUTAN KERJA
1 Motor Grader meratakan permukaan hasil galian
2 Vibro Roller memadatkan permukaan jalan yang telah diratakan oleh Motor grader
3 Sekelompok pekerja akan membanru meratakan badan jalan dengan alat bantu
permukaan dengan menggunakan alat bantu

III PEMAKAIAN BAHAN ALAT DAN TENAGA


1 BAHAN
Tidak diperlukan bahan / material

2 ALAT
a Motor Grader ( E 13 )
Panjang hamparan Lh 50.00
Lebar efektif kerja blade b 2.40
Faktor Efisiensi alat Fa 0.83
Kecepatan rata rata alat v 2.00
Jumlah lintasan n 6.00
Waktu siklus Ts 1
- Perataan 1 Lintasan = Lh : ( v x 1000 x 60 menit ) T1 1.50
- Lain lain T2 1.00
Ts 1 2.50

Kapasitas produksi / jam = Lh x b x Fa x 60 Q1 398.40


n x Ts 1

Koefisien Alat / m3 = 1 / Q1 ( E 02 ) 0.0025

b Vibratory Roller ( E 19 )
Kecepatan rata rata alat v 2.00
Lebar efektif pemadatan b 1.20

Harga Satuan Pekerjaan Tahun 2012 Hal :157


PT Pelabuhan Indonesia I (Persero)

Jumlah lintasan n 8.00


Faktor efisiensi alat Fa 0.83

Kapasitas produksi / jam = ( v x 1000 ) x b x Fa Q2 249.00


n

Koefisien Alat / m3 = 1 / Q2 ( E 19 ) 0.0040

c Water Tank Truck ( E 23 )


Volume tangki air v 4.00
Kebutuhan air / m3 agregat padat Wc 0.07
Pengisian tangki / jam n 2.00
Faktor efisiensi alat Fa 0.83

Harga Satuan Pekerjaan Tahun 2012 Hal :158


PT Pelabuhan Indonesia I (Persero)

No URAIAN KODE KOEF.

Kapasitas produksi / jam = v x n x Fa Q3 94.86


Wc

Koefisien Alat / m3 = 1 / Q3 ( E 23 ) 0.0105

g Alat Bantu
Diperlukan :

- Skop = 3 bh

3 TENAGA
Produksi menentukan : VIBRATORY ROLLER Q2 249.00
Produksi Pekerjaan / hari = Tk x Q2 Qt 1,743.00

Kebutuhan tenaga
- Pekerja P 4.00
- Mandor M 1.00

Koefisien tenaga /m2 :


- Pekerja = ( Tk x P ) / Qt ( L 01 ) 0.0161
- Mandor = ( Tk x M ) / Qt ( L 03 ) 0.0040

4 HARGA DASAR SATUAN UPAH, BAHAN, DAN ALAT


( Lihat Lampiran )

5 ANALISA HARGA SATUAN PEKERJAAN


Lihat perhitungan dalam " Formulir Standart Untuk Perekaman Analisa Masing - nasing
Harga Satuan "
DIDAPAT HARGA SATUAN PEKERJAAN

Rp 5,081.00 / M2

6 WAKTU PELAKSANAAN YANG DIPERLUKAN


Masa Pelaksanaan = . . . . . . . . . Bulan

7 VOLUME PEKERJAAN YANG DIPERLUKAN


Volume Pekerjaan = . . . . . . . . . M3

Harga Satuan Pekerjaan Tahun 2012 Hal :159


PT Pelabuhan Indonesia I (Persero)

ASP 1

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

6,875.00 77.93
80,000.00 129.54

207.47

- -
20,000.00 464.05
- -
- -

464.05

344,900.53 383.05
6,816,302.41 11,037.48
369,422.18 598.20
227,650.78 3,263.91
216,085.57 437.38
177,076.60 304.78
215,630.16 277.12
500.00 500.00

16,801.91

17,473.44
1,747.34
19,220.78
19,220.00

rat untuk bahan bahan

Harga Satuan Pekerjaan Tahun 2012 Hal :160


PT Pelabuhan Indonesia I (Persero)

r mata pembayaran

yang dibayar dari kontrak ) dan biaya biaya

Harga Satuan Pekerjaan Tahun 2012 Hal :161


PT Pelabuhan Indonesia I (Persero)

ASP 2

SATUAN KET.

Km
m
Jam

-
-

%
%
%
%

t / m3
t / m3
t / m3
t / m3

m3
m3
Kg
Kg

Harga Satuan Pekerjaan Tahun 2012 Hal :162


PT Pelabuhan Indonesia I (Persero)

m3
-
-

menit
menit
menit

m2

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :163


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

ton / jam
-

m2

Jam

m2

Jam

ton
-
km / jam
km / jam
ton
menit

menit
menit
menit
menit
menit

m2

Jam

km / jam
-

m2

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :164


PT Pelabuhan Indonesia I (Persero)

km/jam
m
lintasan
-

m2

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :165


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

km / jam
m
lintasan
-

m2

Jam

Lump sum

m2 / jam
m2

orang
orang

jam
jam

Harga Satuan Pekerjaan Tahun 2012 Hal :166


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :167


PT Pelabuhan Indonesia I (Persero)

ASP 3

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

6,875.00 149.10
80,000.00 173.49

322.59

- -
20,000.00 297.00
- -
- -

297.00

344,900.53 513.02
6,816,302.41 14,782.34
369,422.18 801.16
227,650.78 7,918.11
216,085.57 585.77
177,076.60 284.46
215,630.16 494.85
500.00 500.00

25,879.71

26,499.30
2,649.93
29,149.23
29,149.00

rat untuk bahan bahan


r mata pembayaran

Harga Satuan Pekerjaan Tahun 2012 Hal :168


PT Pelabuhan Indonesia I (Persero)

yang dibayar dari kontrak ) dan biaya biaya

Harga Satuan Pekerjaan Tahun 2012 Hal :169


PT Pelabuhan Indonesia I (Persero)

ASP 4

SATUAN KET.

Km
m
Jam

-
-

%
%
%
%

t / m3
t / m3
t / m3
t / m3

m3
m3
Kg
Kg

Harga Satuan Pekerjaan Tahun 2012 Hal :170


PT Pelabuhan Indonesia I (Persero)

m3
-
-

menit
menit
menit

m3

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :171


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

ton / jam
-

m2

Jam

m2

Jam

m3
-
km / jam
km / jam
ton
menit

menit
menit
menit
menit
menit

m2

Jam

ton / jam
-

m2

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :172


PT Pelabuhan Indonesia I (Persero)

km / jam
m
lintasan
-

m2

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :173


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

km / jam
m
lintasan
-

m2

Jam

Lump sum

m2 / jam
m2

orang
orang

jam
jam

Harga Satuan Pekerjaan Tahun 2012 Hal :174


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :175


PT Pelabuhan Indonesia I (Persero)

ASP 5

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

6,875.00 2,667.17
80,000.00 4,433.73

7,100.90

- -
20,000.00 10,682.22
- -
- -

10,682.22

344,900.53 13,110.40
6,816,302.41 377,770.98
369,422.18 20,474.00
227,650.78 111,693.42
216,085.57 16,566.56
177,076.60 7,619.47
215,630.16 6,927.88
500.00 500.00

554,662.71

572,445.84
57,244.58
629,690.42
629,690.00

rat untuk bahan bahan


r mata pembayaran

Harga Satuan Pekerjaan Tahun 2012 Hal :176


PT Pelabuhan Indonesia I (Persero)

yang dibayar dari kontrak ) dan biaya biaya

Harga Satuan Pekerjaan Tahun 2012 Hal :177


PT Pelabuhan Indonesia I (Persero)

B)

ASP 6

SATUAN KET.

Km
m
Jam

-
-

%
%
%
%

t / m3
t/m3
t/m3
t/m3

m3
m3
Kg
Kg

Harga Satuan Pekerjaan Tahun 2012 Hal :178


PT Pelabuhan Indonesia I (Persero)

m3
-
-

menit
menit
menit

m3

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :179


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

ton / jam
-

m3

Jam

m3

Jam

ton
-
km / jam
km / jam
ton
menit

menit
menit
menit
menit
menit

m3

Jam

ton/jam
-

m3

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :180


PT Pelabuhan Indonesia I (Persero)

km / jam
m
lintasan
-

m3

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :181


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

km / jam
m
lintasan
-

m3

Jam

Lump sum

m3 / jam
m3

orang
orang

jam
jam

Harga Satuan Pekerjaan Tahun 2012 Hal :182


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :183


PT Pelabuhan Indonesia I (Persero)

ASP 7

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

6,875.00 207.08
80,000.00 481.93

689.01

- -
- -

54,620.78 164.52
163,284.90 510.27
227,650.78 685.70

1,360.48

2,049.49
204.95
2,254.44
2,254.00

rat untuk bahan bahan


r mata pembayaran

yang dibayar dari kontrak ) dan biaya biaya

Harga Satuan Pekerjaan Tahun 2012 Hal :184


PT Pelabuhan Indonesia I (Persero)

ASP 8

SATUAN KET.

Km
Jam
-

% 100 Bagian
% 80 Bagian

Kg / Lt
Kg / Lt

liter Campuran
kg
liter

liter
-
jam

liter

Harga Satuan Pekerjaan Tahun 2012 Hal :185


PT Pelabuhan Indonesia I (Persero)

jam

m2 / jam
liter / m2

liter

jam

Harga Satuan Pekerjaan Tahun 2012 Hal :186


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

liter

jam

Liter
Liter

orang
orang

jam
jam

Harga Satuan Pekerjaan Tahun 2012 Hal :187


PT Pelabuhan Indonesia I (Persero)

ASP 9

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

6,875.00 3,006.47
80,000.00 4,997.77

8,004.24

- -
20,000.00 8,640.00

8,640.00

344,900.53 21,546.66
227,650.78 45,389.05
236,640.05 2,771.89
236,640.05 4,223.83
215,630.16 923.72
167,998.54 3,542.14
500.00 500.00

78,897.29

95,541.53
9,554.15
105,095.68
105,095.00

21,019.00
15,764.00
10,509.00

rat untuk bahan bahan


r mata pembayaran

Harga Satuan Pekerjaan Tahun 2012 Hal :188


PT Pelabuhan Indonesia I (Persero)

yang dibayar dari kontrak ) dan biaya biaya

Harga Satuan Pekerjaan Tahun 2012 Hal :189


PT Pelabuhan Indonesia I (Persero)

S A

ASP 10

SATUAN KET.

Km
m

Jam

% Tabel; 5.1.2 (a)


%

m3
m3

m3
-
-

menit
menit
menit

m3

Harga Satuan Pekerjaan Tahun 2012 Hal :190


PT Pelabuhan Indonesia I (Persero)

Jam

m3
-
km / jam
km / jam

menit
menit
menit

menit

Harga Satuan Pekerjaan Tahun 2012 Hal :191


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

m3

Jam

m
m
-
km / jam
Lintas 3 x pp

menit
menit
menit

m3

Jam

km / jam
m
lintasan
-

m3

Jam

km/jam
m
lintasan
-

m3

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :192


PT Pelabuhan Indonesia I (Persero)

m3
m3
kali
-

m3

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :193


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

Lump sum

m3 / jam
m3

orang
orang

jam
jam

Harga Satuan Pekerjaan Tahun 2012 Hal :194


PT Pelabuhan Indonesia I (Persero)

ASP 11

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

6,875.00 3,006.47
80,000.00 4,997.77

8,004.24

- -
20,000.00 9,840.00

9,840.00

344,900.53 21,546.66
227,650.78 45,389.05
236,640.05 2,771.89
236,640.05 4,223.83
215,630.16 923.72
167,998.54 3,542.14
500.00 500.00

78,897.29

96,741.53
9,674.15
106,415.68
106,415.00

21,283.00
15,962.00
10,641.00

rat untuk bahan bahan

Harga Satuan Pekerjaan Tahun 2012 Hal :195


PT Pelabuhan Indonesia I (Persero)

r mata pembayaran

yang dibayar dari kontrak ) dan biaya biaya

Harga Satuan Pekerjaan Tahun 2012 Hal :196


PT Pelabuhan Indonesia I (Persero)

S B

ASP 12

SATUAN KET.

Km
m

Jam

% Tabel; 5.1.2 (a)


%

m3
m3

m3
-
-

menit
menit
menit

m3

Harga Satuan Pekerjaan Tahun 2012 Hal :197


PT Pelabuhan Indonesia I (Persero)

Jam

m3
-
km / jam
km / jam

menit
menit
menit

menit

Harga Satuan Pekerjaan Tahun 2012 Hal :198


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

m3

Jam

m
m
-
km / jam
Lintas 3 x pp

menit
menit
menit

m3

Jam

km / jam
m
lintasan
-

m3

Jam

km / jam
m
lintasan
-

m3

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :199


PT Pelabuhan Indonesia I (Persero)

km / jam
m3
lintasan
-

m3

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :200


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

Lump sum

m3 / jam
m3 / jam

orang
orang

jam
jam

Harga Satuan Pekerjaan Tahun 2012 Hal :201


PT Pelabuhan Indonesia I (Persero)

ASP 13

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

6,875.00 207.08
80,000.00 481.93

689.01

- -
- -

54,620.78 164.52
163,284.90 1,020.53
227,650.78 685.70

1,870.75

2,559.75
255.98
2,815.73
2,815.00

rat untuk bahan bahan


r mata pembayaran

yang dibayar dari kontrak ) dan biaya biaya

Harga Satuan Pekerjaan Tahun 2012 Hal :202


PT Pelabuhan Indonesia I (Persero)

ASP 14

SATUAN KET.

Km
Jam
-

% 100 Bagian
% 30 Bagian

Kg / Lt
Kg / Lt

Liter Campuran
Kg
Liter

Liter
-
Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :203


PT Pelabuhan Indonesia I (Persero)

Liter

Jam

m2 / jam
Liter / m2

Liter

Jam

Harga Satuan Pekerjaan Tahun 2012 Hal :204


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

Liter

Jam

Liter
Liter

orang
orang

jam
jam

Harga Satuan Pekerjaan Tahun 2012 Hal :205


PT Pelabuhan Indonesia I (Persero)

ASP 15

HARGA JUMLAH
SATUAN HARGA
(Rp.) (Rp.)

6,875.00 110.44
80,000.00 321.29

431.73

384,919.36 966.16
236,640.05 950.36
167,998.54 1,771.07
500.00 500.00

4,187.59

4,619.32
461.93
5,081.25
5,081.00

rat untuk bahan bahan


r mata pembayaran

yang dibayar dari kontrak ) dan biaya biaya

Harga Satuan Pekerjaan Tahun 2012 Hal :206


PT Pelabuhan Indonesia I (Persero)

ASP 16

SATUAN KET.

Jam

m
m
-
km / jam
Lintas 3 x pp

menit
menit
menit

m3

Jam

km / jam
m

Harga Satuan Pekerjaan Tahun 2012 Hal :207


PT Pelabuhan Indonesia I (Persero)

lintasan
-

m3

Jam

m3
m3
kali
-

Harga Satuan Pekerjaan Tahun 2012 Hal :208


PT Pelabuhan Indonesia I (Persero)

SATUAN KET.

m3

Jam

Lump sum

m3 / jam
m3

orang
orang

jam
jam

Harga Satuan Pekerjaan Tahun 2012 Hal :209


PT Pelabuhan Indonesia I (Persero)

NO. MACAM ALAT SATUAN HARGA

A.1 Mesin penyampur aspal (AMP) Unit 7,500,000,000.00


2 Aspahlt Finisher Unit 715,000,000.00
3 Mesin penyemprot aspal 800 liter (Asphlt Sprayer) Unit 145,000,000.00
4 Buldozer 100 - 150 HP Unit 700,000,000.00
5 Compressor 4000 - 6500 L/M Unit 175,000,000.00
6 Concrette Mixer 0,3 - 0,6 m3 Unit 45,000,000.00
7 Crane 10 - 15 Ton Unit 300,000,000.00
8 Dump Truck 3 - 4 M3 Unit 100,000,000.00
9 Dump Truck 8 ton 125 HP Unit 145,000,000.00
10 Excavator 80 - 140 HP Unit 250,000,000.00
11 Flat Bed Truck (Truk Bak Terbuka) 3 - 4 m3 Unit 250,000,000.00
12 Genset 125 KVA Unit 440,000,000.00
13 Motor Grader > 100 HP Unit 880,000,000.00
14 Track Loader 75 - 100 HP Unit 300,000,000.00
15 Wheel Loader 105 HP Unit 840,000,000.00
16 Mesin Gilas 3 Roda 8 - 10 ton (Three Wheel Roller) Unit 125,000,000.00
17 Mesin Gilas Tandem 6 - 8 ton (Tandem Roller) Unit 460,000,000.00
18 Mesin Roda Karet 8 - 10 ton (Pneumatic Tyre Roller) Unit 510,000,000.00
19 Mesin Gilas getar otomatis 5 - 8 T Unit 500,000,000.00
20 Alat penggetar beton 4 HP (Concrette Vibrator) Unit 12,000,000.00
21 Pemecah batu 220 HP (Stone Crusher) Unit 491,500,000.00
22 Water Pump / Pompa Air 70 - 100 mm Unit 5,000,000.00
23 Truk tangki air 100 HP 4000 L (Water Tank Truck ) Unit 50,000,000.00
24 Stamper 5 HP Unit 3,000,000.00
25 Jack Hammer Unit 3,500,000.00
26 Fulvi Mixer Unit 100,000,000.00
27 Mesin penyaring 8 HP jam 50,000.00
28 Chip Spreader jam 50,000.00
29 Mesin penghampar 1820 MM 30 HP jam 181,000.00
30 Thriller gandeng 1 ton jam 184,000.00
31 Dump Truck 3,5 ton 44 HP jam 118,000.00
32 Pompa air (D 5 cm) 30 m3 / jam jam 11,000.00
33 Thriller 1ton jam 15,000.00
34 Traktor jam 15,000.00
35 Alat Bor jam 150,000.00
36 Alat Ukur jam 75,000.00
37 Beton Molen jam 25,000.00

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :210


PT Pelabuhan Indonesia I (Persero)

38 Mata Cutter bh 1,000,000.00


39 Mesin Cutter jam 60,000.00
40 Motor Walls jam 20,000.00
41 Peralatan Las jam 75,000.00
42 Sprayer jam 48,000.00
43 Alat bantu untuk pekerjaan analisa - E ls 500.00

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :211


PT Pelabuhan Indonesia I (Persero)

KETERANGAN

Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Alat Baru
Sewa
Sewa
Sewa
Sewa
Sewa
Sewa
Sewa
Sewa
Sewa
Sewa
Sewa

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :212


PT Pelabuhan Indonesia I (Persero)

baru
Sewa
Sewa
Sewa
Sewa

Analisa Harga Satuan Pekerjaan Tahun 2012 Hal :213


PT Pelabuhan Indonesia I (Persero)
ANALISA BASE

No. Macam Pekerjaan


(1) (2)

BS1 1 m2 Menghampar dan mengisi bahan perkerasan


Pekerja 1.5000 org X Rp. 491,200.00
Mandor 0.0730 org X Rp. 491,200.00
JUMLAH

BS2 1 m3 Menyawur pasir


Pekerja 1.0000 org X Rp. 491,200.00
JUMLAH

BS3 1 hari Menggilas dengan motor walls


Masinis 1.0000 org X Rp. 491,200.00
Kenek 1.0000 org X Rp. 491,200.00
Penjaga 1.0000 org X Rp. 491,200.00
Pekerja 1.0000 org X Rp. 491,200.00
Olie 1.0000 ltr X Rp. 491,200.00
Olie SAE 1.0000 ltr X Rp. 491,200.00
Vet 0.7500 ltr X Rp. 491,200.00
Solar 16.0000 ltr X Rp. 491,200.00
JUMLAH

BS4 100 m2 Perkerasan lapis pondasi bawah (sub base) tebal 20 cm padat
Pasair pasang 5.0000 m3 X Rp. 491,200.00
Batu belah 15/20 23.0000 m 3
X Rp. 491,200.00
Batu pecah 5/7 cm 3.0000 m3 X Rp. 491,200.00
Pasir urug 6.5000 m3 X Rp. 491,200.00
Isi batu berkerasan 26.0000 m 3
X Rp. 491,200.00
Menyawur pasir 6.5000 Tng X Rp. 491,200.00
JUMLAH

Tiap m2
1/100 x 15,964,000.00 + 18,420,000.00
Biaya menggilas
1/200 x 1,964,800.00 + 9,210,000.00
Sewa motor walls
1/200 x -
JUMLAH

BS5 100 m2 Pembuatan lapis pondasi bawah (sub base) tebal 15 cm padat
Pasair urug 5.0000 m3 X Rp. 491,200.00
Batu belah 15/20 17.5000 m3 X Rp. 491,200.00
Batu pecah 5/7 cm 3.0000 m 3
X Rp. 491,200.00
Pasir urug (pengisi) 6.5000 m3 X Rp. 491,200.00
Isi batu berkerasan 20.5000 m3 X Rp. 491,200.00
Menyawur pasir 5.0000 Tng X Rp. 491,200.00
JUMLAH ( BELUM TERMASUK PPN )

Tiap m2
1/100 x 12,525,600.00 + 15,718,400.00
Biaya menggilas

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :214


PT Pelabuhan Indonesia I (Persero)
No. Macam Pekerjaan
(1) (2)
1/200 x 1,964,800.00 + 9,210,000.00
Sewa motor walls
1/200 x -
JUMLAH

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :215


PT Pelabuhan Indonesia I (Persero)
No. Macam Pekerjaan
(1) (2)

BS6 100 m2 Pembuatan lapis pondasi atas (base) tebal 10 cm padat


Batu koral 5/7 cm 10.0000 m3 X Rp. 491,200.00
Batu koral 3/4 cm 2.0000 m3 X Rp. 491,200.00
Batu koral 2/3 cm 1.0000 m3 X Rp. 491,200.00
Pasir urug (pengisi) 3.2500 m3 X Rp. 491,200.00
Isi batu berkerasan 13.0000 m3 X Rp. 491,200.00
Menyawur pasir 3.2500 Tng X Rp. 491,200.00
JUMLAH

Tiap m2
1/100 x 7,982,000.00 + 7,982,000.00
Biaya menggilas
1/150 x 1,964,800.00 + 9,210,000.00
Sewa motor walls
1/150 x -
JUMLAH

BS7 1 m2 Pembuatan lapis pondasi atas (base) tebal 8 cm padat


8/10 x 79,820.00 + 79,820.00
Biaya menggilas
1/150 x 1,964,800.00 + 9,210,000.00
Sewa motor walls
1/150 x -
JUMLAH

BS8 Pembuatan lapis pondasi atas (base) tebal 7 cm padat


1/100 x 79,820.00 + 79,820.00
Biaya menggilas
1/200 x 1,964,800.00 + 9,210,000.00
Sewa motor walls
1/200 x -
JUMLAH

BS9 100 m2 Lapisan Penetrasi 4 cm padat


Krokos D 20 - 40 mm 0.2400 m3 X Rp. 491,200.00
Split D 10 mm 0.4800 m3 X Rp. 491,200.00
Split D 30 - 40 mm 3.5000 m 3
X Rp. 491,200.00
Split D 10 - 20 mm 1.2000 m3 X Rp. 491,200.00
Kayu bakar 1.2500 m3 X Rp. 491,200.00
Pekerja 14.0000 org X Rp. 491,200.00
Mandor 1.0000 org X Rp. 491,200.00
Juru godog aspal 1.5000 org X Rp. 491,200.00
Masinis 1.0000 org X Rp. 491,200.00
Kenek 1.0000 org X Rp. 491,200.00
Penyemprot 1.0000 org X Rp. 491,200.00
Aspal 400.0000 kg X Rp. 491,200.00
Aspal lem 80.0000 kg X Rp. 491,200.00
Sprayer (sewa) 1.0000 hr X Rp. 491,200.00
JUMLAH

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :216


PT Pelabuhan Indonesia I (Persero)
No. Macam Pekerjaan
(1) (2)

Tiap m2
1/100 x 9,578,400.00 + 239,543,504.00
Biaya menggilas
4/12,5/200 x 1,964,800.00 + 9,210,000.00
Sewa motor walls
1/200 x -
JUMLAH

BS10 100 m2 Pengaspalan sand sheet (latasir), tebal 1 cm jereng


Aspal 125.0000 kg X Rp. 491,200.00
Pasair pasang 1.0000 m3 X Rp. 491,200.00
Kayu bakar 0.9000 m3 X Rp. 491,200.00
Juru godog aspal 0.2500 org X Rp. 491,200.00
Pekerja 8.1000 org X Rp. 491,200.00
Mandor 0.4000 org X Rp. 491,200.00
JUMLAH

Tiap m2
Aspal sand sheet 2 cm jereng (1 cm padat)
2/100 x 62,333,280.00 + 4,298,000.00
Biaya menggilas
1/500 x 1,964,800.00 + 9,210,000.00
Sewa motor walls
1/500 x -
Aspal untuk lem 0,5 kg
0.5000 x -
JUMLAH

Tiap m1
Aspal sand sheet 3 cm jereng (2 cm padat)
3/100 x 62,333,280.00 + 4,298,000.00
Biaya menggilas
1/500 x 1,964,800.00 + 9,210,000.00
Sewa motor walls
1/500 x -
Aspal untuk lem 0,5 kg
0.5000 x -
JUMLAH

BS11 100 m2 Pengaspalan sand sheet (latasir) tanpa aspal, tebal 1 cm jereng
Aspal - kg X Rp. 491,200.00
Pasair pasang 1.0000 m3 X Rp. 491,200.00
Kayu bakar 0.9000 m3 X Rp. 491,200.00
Juru godog aspal 0.2500 org X Rp. 491,200.00
Pekerja 8.1000 org X Rp. 491,200.00
Mandor 0.4000 org X Rp. 491,200.00
JUMLAH

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :217


PT Pelabuhan Indonesia I (Persero)
No. Macam Pekerjaan
(1) (2)

Tiap m2
Aspal sand sheet 2 cm jereng (1 cm padat) tanpa aspal
2/100 x 4,298,000.00 + 933,280.00
Biaya menggilas
1/500 x 1,964,800.00 + 9,210,000.00
Sewa motor walls
1/500 x -
Aspal untuk lem 0,5 kg
0.5000 x -
JUMLAH

Tiap m2
Aspal sand sheet 2 cm jereng (1 cm padat) tanpa aspal
2/100 x 4,298,000.00 + 933,280.00
Biaya menggilas
1/500 x 1,964,800.00 + 9,210,000.00
Sewa motor walls
1/500 x -
Aspal untuk lem 0,5 kg
0.5000 x -
JUMLAH

BS12 Mengecat marka jalan dengan Rettar


Cat rettar 4.2500 kg X Rp. 491,200.00
Minyak cat 0.5700 ltr X Rp. 491,200.00
Tukang cat 2.2500 org X Rp. 491,200.00
Kepala tukang cat 0.2300 org X Rp. 491,200.00
Pekerja 2.0000 org X Rp. 491,200.00
JUMLAH

Mengecat marka jalan dengan reTiap m2


1/ 10 x 2,200,576.00 + 2,367,584.00
JUMLAH

BS13 1 m2 Mengecat marka jalan dengan Thermoplastic


Cat marka 1.6575 kg X Rp. 491,200.00
Glasbit 0.4500 kg X Rp. 491,200.00
Thinner 1.0500 ltr X Rp. 491,200.00
Sewa Compressor 0.0750 jam X Rp. 491,200.00
Sewa Dumptruck 0.0750 jam X Rp. 491,200.00
Alat bantu 0.0100 ls X Rp. 491,200.00
Tukang cat 0.2250 org X Rp. 491,200.00
Pekerja 0.6000 org X Rp. 491,200.00
Mandor 0.0750 org X Rp. 491,200.00
JUMLAH

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :218


PT Pelabuhan Indonesia I (Persero)
No. Macam Pekerjaan
(1) (2)

BS14 350 m' Pemotongan aspal dengan mesin potong (cutter), 2 sisi
Cutter 2.0000 bh X Rp. 491,200.00
Sewa mesin cutter 2.0000 hr X Rp. 491,200.00
Solar 15.0000 ltr X Rp. 491,200.00
Tk. Cutter / masinis 2.0000 org X Rp. 491,200.00
Pekerja 2.0000 org X Rp. 491,200.00
JUMLAH

Tiap m1
1/350 x 1,964,800.00 + 9,332,800.00

Pemotongan aspal dengan mesinTiap


p m1
1/700 x 1,964,800.00 + 9,332,800.00

BS15 1 m2 Pembongkaran aspal dengan Jack Hammer


Sewa mesin Jack Hammer 0.6600 hari X Rp. 491,200.00
Solar 1.3200 ltr X Rp. 491,200.00
Tk. Jack Hammer / masinis 0.0400 org X Rp. 491,200.00
Pekerja 0.2500 org X Rp. 491,200.00
Mandor 0.0630 org X Rp. 491,200.00
JUMLAH

BS16 Expantion joint 1.0000 m1


Ashpaltic Joint 18.5000 kg X Rp. 491,200.00
Plate baja 5 mm 5.5000 kg X Rp. 491,200.00
Joint Filler 1.0000 m1 X Rp. 491,200.00
Split 1/2 cm 0.0150 m3 X Rp. 491,200.00
Gas Elpiji 6.5000 kg X Rp. 491,200.00
Sewa Jack Hammer 0.1000 hr X Rp. 491,200.00
Sewa Genset 2000 watt 0.1000 hr X Rp. 491,200.00
Sewa Compressor 0.1000 hr X Rp. 491,200.00
Sewa Stamper 0.1000 hr X Rp. 491,200.00
Mata cutter 0.1000 bh X Rp. 491,200.00
Sewa mesin cutter 0.1000 hr X Rp. 491,200.00
Alat bantu 1.0000 ls X Rp. 491,200.00
Mekanik terlatih 1.0000 org X Rp. 491,200.00
Operator terlatih 4.5000 org X Rp. 491,200.00
Mandor 0.1000 org X Rp. 491,200.00
JUMLAH

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :219


PT Pelabuhan Indonesia I (Persero)
SE

Upah Bahan Jumlah


(3) (4) (5)

736,800.00 -
35,857.60 -
772,657.60 - 772,657.60

491,200.00
491,200.00 - 491,200.00

491,200.00
491,200.00
491,200.00
491,200.00
491,200.00
491,200.00
368,400.00
7,859,200.00
1,964,800.00 9,210,000.00 11,174,800.00

2,456,000.00
11,297,600.00
1,473,600.00
3,192,800.00
12,771,200.00
3,192,800.00
15,964,000.00 18,420,000.00 34,384,000.00

159,640.00 184,200.00

9,824.00 46,050.00

-
169,464.00 230,250.00 399,714.00

2,456,000.00
8,596,000.00
1,473,600.00
3,192,800.00
10,069,600.00
2,456,000.00
12,525,600.00 15,718,400.00 28,244,000.00

125,256.00 157,184.00

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :220


PT Pelabuhan Indonesia I (Persero)
Upah Bahan Jumlah
(3) (4) (5)
9,824.00 46,050.00

-
135,080.00 203,234.00 338,314.00

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :221


PT Pelabuhan Indonesia I (Persero)
Upah Bahan Jumlah
(3) (4) (5)

4,912,000.00
982,400.00
491,200.00
1,596,400.00
6,385,600.00
1,596,400.00
7,982,000.00 7,982,000.00 15,964,000.00

79,820.00 79,820.00

13,098.67 61,400.00

-
92,918.67 141,220.00 234,138.67

- 63,856.00

13,098.67 61,400.00

-
13,098.67 125,256.00 138,354.67

- 63,856.00

9,824.00 46,050.00

-
9,824.00 109,906.00 119,730.00

117,888.00
235,776.00
1,719,200.00
589,440.00
614,000.00
6,876,800.00
491,200.00
736,800.00
491,200.00
491,200.00
491,200.00
196,480,000.00
39,296,000.00
491,200.00
9,578,400.00 239,543,504.00 249,121,904.00

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :222


PT Pelabuhan Indonesia I (Persero)
Upah Bahan Jumlah
(3) (4) (5)

95,784.00 2,395,435.04

3,143.68 14,736.00

-
98,927.68 2,410,171.04 2,509,098.72

61,400,000.00
491,200.00
442,080.00
122,800.00
3,978,720.00
196,480.00
62,333,280.00 4,298,000.00 66,631,280.00

1,246,665.60 85,960.00

3,929.60 18,420.00

-
1,250,595.20 104,380.00 1,354,975.20

1,869,998.40 128,940.00

3,929.60 18,420.00

-
1,873,928.00 147,360.00 2,021,288.00

-
491,200.00
442,080.00
122,800.00
3,978,720.00
196,480.00
4,298,000.00 933,280.00 5,231,280.00

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :223


PT Pelabuhan Indonesia I (Persero)
Upah Bahan Jumlah
(3) (4) (5)

85,960.00 18,665.60

3,929.60 18,420.00

-
89,889.60 37,085.60 126,975.20

85,960.00 18,665.60

3,929.60 18,420.00

-
89,889.60 37,085.60 126,975.20

2,087,600.00
279,984.00
1,105,200.00
112,976.00
982,400.00
2,200,576.00 2,367,584.00 4,568,160.00

220,057.60 236,758.40
220,057.60 236,758.40 456,816.00

814,164.00
221,040.00
515,760.00
36,840.00
36,840.00
4,912.00
110,520.00
294,720.00
36,840.00
446,992.00 1,624,644.00 2,071,636.00

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :224


PT Pelabuhan Indonesia I (Persero)
Upah Bahan Jumlah
(3) (4) (5)

982,400.00
982,400.00
7,368,000.00
982,400.00
982,400.00
1,964,800.00 9,332,800.00 11,297,600.00

5,613.71 26,665.14 32,278.86

2,806.86 13,332.57 16,139.43

324,192.00
648,384.00
19,648.00
122,800.00
30,945.60
173,393.60 972,576.00 1,145,969.60

9,087,200.00
2,701,600.00
491,200.00
7,368.00
3,192,800.00
49,120.00
49,120.00
49,120.00
49,120.00
49,120.00
49,120.00
491,200.00
491,200.00
2,210,400.00
49,120.00
2,750,720.00 16,266,088.00 19,016,808.00

Analisa Harga Satuan Pekerjaan KPUT Tahun 2012 Hal :225


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan ASPHALT MIXING PL

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengmbalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1


Bahan bakar pemanasan = 12 x 0,7 Cp x Ms H2
material
2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I
3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 3 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb

Harga Satuan Pekerjaan Tahun 2012 Hal :226


PT Pelabuhan Indonesia I (Persero)

5 Bahan bakar solar Ms


6 Minyak Pelumas Mp
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :227


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan ASPHALT FINISHE

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :228


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :229


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan ASPHALT SPRAYE

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :230


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :231


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan BULLDOZER 100 -15

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :232


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :233


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan COMPRESSOR 4000 - 6

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :234


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :235


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan WHEEL LOADER 1,0 -

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms

Harga Satuan Pekerjaan Tahun 2012 Hal :236


PT Pelabuhan Indonesia I (Persero)

6 Minyak Pelumas Mp
7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :237


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan TANDEM ROLLER 6

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru a Umur Ekonomis A
b Jam Kerja dalam 1 Tahun W
c Harga Alat B
5 Alat yang dipakai a Umur Ekonomis A'
b Jam Kerja dalam 1 Tahun W'
c Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :238


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :239


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan PNEUMATIC TYRE ROLLE

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru a Umur Ekonomis A
b Jam Kerja dalam 1 Tahun W
c Harga Alat B
5 Alat yang dipakai a Umur Ekonomis A'
b Jam Kerja dalam 1 Tahun W'
c Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :240


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :241


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan DUMP TRUCK

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :242


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :243


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan GENERATOR SE

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :244


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :245


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan MOTOR GRADER > 1

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru a Umur Ekonomis A
b Jam Kerja dalam 1 Tahun W
c Harga Alat B
5 Alat yang dipakai a Umur Ekonomis A'
b Jam Kerja dalam 1 Tahun W'
c Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :246


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :247


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan VIBRATORY ROLLER

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru Umur Ekonomis A
Jam Kerja dalam 1 Tahun W
Harga Alat B
5 Alat yang dipakai a Umur Ekonomis A'
b Jam Kerja dalam 1 Tahun W'
c Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :248


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :249


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan WATER TANK TRUCK 300

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a Biaya Pengembalian Modal = ( B-C)xD E
W'
b Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :250


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :251


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan JACK HAMMER

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a Biaya Pengembalian Modal = ( B-C)xD E
W'
b Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :252


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :253


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan TAMPER

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a Biaya Pengembalian Modal = ( B-C)xD E
W'
b Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :254


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :255


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan STONE CRUSHER

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a Biaya Pengembalian Modal = ( B-C)xD E
W'
b Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 2 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :256


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :257


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan THREE WHEEL ROLLER

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a Biaya Pengembalian Modal = ( B-C)xD E
W'
b Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :258


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :259


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan CONCRETE VIBRAT

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a Biaya Pengembalian Modal = ( B-C)xD E
W'
b Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :260


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :261


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan CONCRETE MIXER 0.3 -

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a Biaya Pengembalian Modal = ( B-C)xD E
W'
b Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :262


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :263


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan CRANE 10 - 15 TO

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a Biaya Pengembalian Modal = ( B-C)xD E
W'
b Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :264


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :265


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan DUMP TRUCK 3 - 4

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :266


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :267


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan EXCAVATOR 80 - 140

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :268


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :269


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan FLAT BED TRUCK 3 -

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :270


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :271


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan WATER PUMP 70 - 10

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :272


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :273


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan FULVI MIXER

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :274


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :275


PT Pelabuhan Indonesia I (Persero)

URAIAN ANALISA ALAT

No URAIAN KODE

I URAIAN PERALATAN
1 Jenis Peralatan TRACK LOADER 75 - 1

2 Tenaga Pw
3 Kapasitas Cp
4 Alat Baru : a. Umur Ekonomis A
b. Jam Kerja dalam 1 Tahun W
c. Harga Alat B
5 Alat Yang Dipakai : a. Umur Ekonomis A'
b. Jam Kerja dalam 1 Tahun W'
c. Harga Alat B'

II BIAYA PASTI PER JAM KERJA

1 Nila sisa alat = 10 % x B C


2 Faktor angsuran Modal = i x ( 1 + i ) ^ A' D
( 1 + i )^A'-1
3 Biaya pasti per jam
a. Biaya Pengembalian Modal = ( B-C)xD E
W'
b. Asuransi dll = 0,002 x B ' F
W'
Biaya Pasti Perjam = ( E + F ) G

III BIAYA OPERASI PER JAM KERJA

1 Bahan Bakar = ( 0,125 - 0,175 ltr / HP / Jam ) x Pw x Ms H1

2 Pelumas = ( 0,01 - 0,02 ltr / HP / Jam ) x Pw x Mp I


3 Perawatan dan perbaikan = ( 12,5 % - 17,5 % ) x B ' K
W'
4 Operator = ( 1 org / Jam ) x U1 L
5 Pembantu Operator ( 1 org / Jam ) x U2 M

Biaya Operasi Per jam = ( H1 + H2 + I + K + L + M ) P

IV TOTAL BIAYA SEWA ALAT / JAM ( G + P ) T

V LAIN LAIN
1 Tingkat suku bunga (i)
2 Upah Operator / Sopir U1
3 Upah Pembantu Operator / Pembantu Sopir U2
4 Bahan bakar bensin Mb
5 Bahan bakar solar Ms
6 Minyak Pelumas Mp

Harga Satuan Pekerjaan Tahun 2012 Hal :276


PT Pelabuhan Indonesia I (Persero)

7 PPn diperhitungkan pada lembar Rekapitulasi Biaya Pekerjaan

Harga Satuan Pekerjaan Tahun 2012 Hal :277


PT Pelabuhan Indonesia I (Persero)

AT

KOEF. SATUAN KET.

ASPHALT MIXING PLANT E01

150.00 HP
50.00 Ton/jam
10.00 Tahun
1,500.00 Jam
7,500,000,000.00 Rupiah
10.00 Tahun Alat Baru
1,500.00 Jam Alat Baru
7,500,000,000.00 Rupiah Alat Baru

750,000,000.00 Rupiah
0.23852 -

1,073,352.41 Rupiah

10,000.00 Rupiah

1,083,352.41 Rupiah

217,500.00 Rupiah
4,872,000.00 Rupiah Khusus AMP

18,450.00 Rupiah
625,000.00 Rupiah

- Rupiah
- Rupiah

5,732,950.00 Rp

6,816,302.41 Rp

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :278


PT Pelabuhan Indonesia I (Persero)

11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :279


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

ASPHALT FINISHER E02

47.00 HP
6.00 Ton
6.00 Tahun
2,000 Jam
715,000,000.00 Rupiah
6.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
715,000,000.00 Rupiah Alat Baru

71,500,000.00 Rupiah
0.30071 -

96,752.07 Rupiah

715.00 Rupiah

97,467.07 Rupiah

68,150.00 Rupiah

5,781.00 Rupiah
44,687.50 Rupiah

0.00 Rupiah
0.00 Rupiah

118,618.50 Rupiah

216,085.57 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :280


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :281


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

ASPHALT SPRAYER E03

15.00 HP
800.00 Liter
5.00 Tahun
2,000 Jam
145,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
145,000,000.00 Rupiah Alat Baru

14,500,000.00 Rupiah
0.33438 -

21,818.28 Rupiah

145.00 Rupiah

21,963.28 Rupiah

21,750.00 Rupiah

1,845.00 Rupiah
9,062.50 Rupiah

0.00 Rupiah
0.00 Rupiah

32,657.50 Rupiah

54,620.78 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :282


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :283


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

BULLDOZER 100 -150 HP E04

140.00 HP
Ton
5.00 Tahun
2,000 Jam
700,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
700,000,000.00 Rupiah Alat Baru

70,000,000.00 Rupiah
0.33438 -

105,329.61 Rupiah

700.00 Rupiah

106,029.61 Rupiah

203,000.00 Rupiah

17,220.00 Rupiah
43,750.00 Rupiah

0.00 Rupiah
0.00 Rupiah

263,970.00 Rupiah

369,999.61 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :284


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :285


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

COMPRESSOR 4000 - 6500 L/M E05

80.00 HP
Ton
5.00 Tahun
2,000 Jam
175,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
175,000,000.00 Rupiah Alat Baru

17,500,000.00 Rupiah
0.33438 -

26,332.40 Rupiah

175.00 Rupiah

26,507.40 Rupiah

116,000.00 Rupiah

9,840.00 Rupiah
10,937.50 Rupiah

0.00 Rupiah
0.00 Rupiah

136,777.50 Rupiah

163,284.90 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :286


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :287


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

WHEEL LOADER 1,0 - 1,6 M 3 E15

105.00 HP
1.50 Ton
5.00 Tahun
2,000.00 Jam
840,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
840,000,000.00 Rupiah Alat Baru

84,000,000.00 Rupiah
0.33438 -

126,395.53 Rupiah

840.00 Rupiah

127,235.53 Rupiah

152,250.00 Rupiah

12,915.00 Rupiah
52,500.00 Rupiah

0.00 Rupiah
0.00 Rupiah

217,665.00 Rupiah

344,900.53 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :288


PT Pelabuhan Indonesia I (Persero)

12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :289


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

TANDEM ROLLER 6 - 8 T E17

50.00 HP
8.00 Ton
5.00 Tahun
2,000.00 Jam
460,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
460,000,000.00 Rupiah Alat Baru

46,000,000.00 Rupiah
0.33 -

69,216.60 Rupiah

460.00 Rupiah

69,676.60 Rupiah

72,500.00 Rupiah

6,150.00 Rupiah
28,750.00 Rupiah

0.00 Rupiah
0.00 Rupiah

107,400.00 Rupiah

177,076.60 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :290


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :291


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

PNEUMATIC TYRE ROLLER 8 - 10 T E18

60.00 HP
10.00 Ton
5.00 Tahun
1,800.00 Jam
510,000,000.00 Rupiah
5.00 Tahun Alat Baru
1,800.00 Jam Alat Baru
510,000,000.00 Rupiah Alat Baru

51,000,000.00 Rupiah
0.33438 -

85,266.82 Rupiah

566.67 Rupiah

85,833.49 Rupiah

87,000.00 Rupiah

7,380.00 Rupiah
35,416.67 Rupiah

0.00 Rupiah
0.00 Rupiah

129,796.67 Rupiah

215,630.16 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :292


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :293


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

DUMP TRUCK E09

125.00 HP
8.00 Ton
5.00 Tahun
2,000.00 Jam
145,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
145,000,000.00 Rupiah Alat Baru

14,500,000.00 Rupiah
0.33438 -

21,818.28 Rupiah

145.00 Rupiah

21,963.28 Rupiah

181,250.00 Rupiah

15,375.00 Rupiah
9,062.50 Rupiah

- Rupiah
- Rupiah

205,687.50 Rupiah

227,650.78 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :294


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :295


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

GENERATOR SET E12

175.00 HP
125.00 KVA
5.00 Tahun
2,000.00 Jam
440,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
440,000,000.00 Rupiah Alat Baru

44,000,000.00 Rupiah
0.33438 -

66,207.18 Rupiah

440.00 Rupiah

66,647.18 Rupiah

253,750.00 Rupiah

21,525.00 Rupiah
27,500.00 Rupiah

- Rupiah
- Rupiah

302,775.00 Rupiah

369,422.18 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :296


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :297


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

MOTOR GRADER > 100 HP E12

125.00 HP
- -
5.00 Tahun
2,000.00 Jam
880,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
880,000,000.00 Rupiah Alat Baru

88,000,000.00 Rupiah
0.33438 -

132,414.36 Rupiah

880.00 Rupiah

133,294.36 Rupiah

181,250.00 Rupiah

15,375.00 Rupiah
55,000.00 Rupiah

- Rupiah
- Rupiah

251,625.00 Rupiah

384,919.36 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :298


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :299


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

VIBRATORY ROLLER 5 - 8 T E19

75.00 HP
7.00 Ton
4.00 Tahun
2,000.00 Jam
500,000,000.00 Rupiah
4.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
500,000,000.00 Rupiah Alat Baru

50,000,000.00 Rupiah
0.38629 -

86,915.05 Rupiah

500.00 Rupiah

87,415.05 Rp

108,750.00 Rupiah

9,225.00 Rupiah
31,250.00 Rupiah

- Rupiah
- Rupiah

149,225.00 Rp

236,640.05 Rp

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :300


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :301


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

WATER TANK TRUCK 3000 - 4000 L E23

100.00 HP
4,000.00 Liter
5.00 Tahun
2,000.00 Jam
50,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
50,000,000.00 Rupiah Alat Baru

5,000,000.00 Rupiah
0.33438 -

7,523.54 Rupiah

50.00 Rupiah

7,573.54 Rp

145,000.00 Rupiah

12,300.00 Rupiah
3,125.00 Rupiah

- Rupiah
- Rupiah

160,425.00 Rp

167,998.54 Rp

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :302


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :303


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

JACK HAMMER E26

3.00 HP
- Liter
4.00 Tahun
1,000.00 Jam
3,500,000.00 Rupiah
4.00 Tahun Alat Baru
1,000.00 Jam Alat Baru
3,500,000.00 Rupiah Alat Baru

350,000.00 Rupiah
0.38629 -

1,216.81 Rupiah

7.00 Rupiah

1,223.81 Rp

4,350.00 Rupiah

369.00 Rupiah
437.50 Rupiah

- Rupiah
- Rupiah

5,156.50 Rp

6,380.31 Rp

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :304


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :305


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

TAMPER E25

5.00 HP
0.170 Ton
4.00 Tahun
1,000.00 Jam
3,000,000.00 Rupiah
4.00 Tahun Alat Baru
1,000.00 Jam Alat Baru
3,000,000.00 Rupiah Alat Baru

300,000.00 Rupiah
0.38629 -

1,042.98 Rupiah

6.00 Rupiah

1,048.98 Rp

7,250.00 Rupiah

615.00 Rupiah
375.00 Rupiah

- Rupiah
- Rupiah

8,240.00 Rp

9,288.98 Rp

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :306


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :307


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

STONE CRUSHER E21

220.00 HP
50.00 Ton/Jam
5.00 Tahun
2,000.00 Jam
491,500,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
491,500,000.00 Rupiah Alat Baru

49,150,000.00 Rupiah
0.33438 -

73,956.43 Rupiah

491.50 Rupiah

74,447.93 Rp

319,000.00 Rupiah

27,060.00 Rupiah
30,718.75 Rupiah

- Rupiah
- Rupiah

376,778.75 Rp

451,226.68 Rp

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :308


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :309


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

THREE WHEEL ROLLER 6 - 8 T E16

55.00 HP
8.00 Ton
5.00 Tahun
2,000.00 Jam
125,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
125,000,000.00 Rupiah Alat Baru

12,500,000.00 Rupiah
0.33438 -

18,808.86 Rupiah

125.00 Rupiah

18,933.86 Rp

79,750.00 Rupiah

6,765.00 Rupiah
7,812.50 Rupiah

- Rupiah
- Rupiah

94,327.50 Rp

113,261.36 Rp

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :310


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :311


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

CONCRETE VIBRATOR E20

10.00 HP
- -
4.00 Tahun
1,000.00 Jam
12,000,000.00 Rupiah
4.00 Tahun Alat Baru
1,000.00 Jam Alat Baru
12,000,000.00 Rupiah Alat Baru

1,200,000.00 Rupiah
0.38629 -

4,171.92 Rupiah

24.00 Rupiah

4,195.92 Rp

14,500.00 Rupiah

1,230.00 Rupiah
1,500.00 Rupiah

- Rupiah
- Rupiah

17,230.00 Rp

21,425.92 Rp

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :312


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :313


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

CONCRETE MIXER 0.3 - 0.6 M3 E06

15.00 HP
500.00 Liter
4.00 Tahun
2,000.00 Jam
45,000,000.00 Rupiah
4.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
45,000,000.00 Rupiah Alat Baru

4,500,000.00 Rupiah
0.38629 -

7,822.35 Rupiah

45.00 Rupiah

7,867.35 Rp

21,750.00 Rupiah

1,845.00 Rupiah
2,812.50 Rupiah

- Rupiah
- Rupiah

26,407.50 Rp

34,274.85 Rp

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :314


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :315


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

CRANE 10 - 15 TON E07

150.00 HP
15.00 Ton
5.00 Tahun
2,000.00 Jam
300,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
300,000,000.00 Rupiah Alat Baru

30,000,000.00 Rupiah
0.33438 -

45,141.26 Rupiah

300.00 Rupiah

45,441.26 Rp

217,500.00 Rupiah

18,450.00 Rupiah
18,750.00 Rupiah

- Rupiah
- Rupiah

254,700.00 Rp

300,141.26 Rp

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :316


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :317


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

DUMP TRUCK 3 - 4 M3 E08

100.00 HP
6.00 Ton
5.00 Tahun
2,000.00 Jam
100,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
100,000,000.00 Rupiah Alat Baru

10,000,000.00 Rupiah
0.33438 -

15,047.09 Rupiah

100.00 Rupiah

15,147.09 Rupiah

145,000.00 Rupiah

12,300.00 Rupiah
6,250.00 Rupiah

- Rupiah
- Rupiah

163,550.00 Rupiah

178,697.09 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :318


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :319


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

EXCAVATOR 80 - 140 HP E10

80.00 HP
0.50 M3
5.00 Tahun
2,000.00 Jam
250,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
250,000,000.00 Rupiah Alat Baru

25,000,000.00 Rupiah
0.33438 -

37,617.72 Rupiah

250.00 Rupiah

37,867.72 Rupiah

116,000.00 Rupiah

9,840.00 Rupiah
15,625.00 Rupiah

- Rupiah
- Rupiah

141,465.00 Rupiah

179,332.72 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :320


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :321


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

FLAT BED TRUCK 3 - 4 M3 E11

100.00 HP
4.00 M3
5.00 Tahun
2,000.00 Jam
250,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
250,000,000.00 Rupiah Alat Baru

25,000,000.00 Rupiah
0.33438 -

37,617.72 Rupiah

250.00 Rupiah

37,867.72 Rupiah

145,000.00 Rupiah

12,300.00 Rupiah
15,625.00 Rupiah

- Rupiah
- Rupiah

172,925.00 Rupiah

210,792.72 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :322


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :323


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

WATER PUMP 70 - 100 mm E22

6.00 HP
- -
2.00 Tahun
2,000.00 Jam
5,000,000.00 Rupiah
2.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
5,000,000.00 Rupiah Alat Baru

500,000.00 Rupiah
0.65455 -

1,472.73 Rupiah

5.00 Rupiah

1,477.73 Rupiah

8,700.00 Rupiah

738.00 Rupiah
312.50 Rupiah

- Rupiah
- Rupiah

9,750.50 Rupiah

11,228.23 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :324


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :325


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

FULVI MIXER E27

75.00 HP
- -
5.00 Tahun
2,000.00 Jam
100,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
100,000,000.00 Rupiah Alat Baru

10,000,000.00 Rupiah
0.33438 -

15,047.09 Rupiah

100.00 Rupiah

15,147.09 Rupiah

108,750.00 Rupiah

9,225.00 Rupiah
6,250.00 Rupiah

- Rupiah
- Rupiah

124,225.00 Rupiah

139,372.09 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :326


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :327


PT Pelabuhan Indonesia I (Persero)

KOEF. SATUAN KET.

TRACK LOADER 75 - 100 HP E14

90.00 HP
1.60 M3
5.00 Tahun
2,000.00 Jam
300,000,000.00 Rupiah
5.00 Tahun Alat Baru
2,000.00 Jam Alat Baru
300,000,000.00 Rupiah Alat Baru

30,000,000.00 Rupiah
0.33438 -

45,141.26 Rupiah

300.00 Rupiah

45,441.26 Rupiah

130,500.00 Rupiah

11,070.00 Rupiah
18,750.00 Rupiah

- Rupiah
- Rupiah

160,320.00 Rupiah

205,761.26 Rupiah

20.00 % / Tahun
- Rp / Jam
- Rp / Jam
- Liter
11,600.00 Liter
12,300.00 Liter

Harga Satuan Pekerjaan Tahun 2012 Hal :328


PT Pelabuhan Indonesia I (Persero)

Harga Satuan Pekerjaan Tahun 2012 Hal :329


PT Pelabuhan Indonesia I (Persero)

ANALISA HARGA SATUAN PEKERJAAN LISTRIK

KODE MACAM PEKERJAAN


(1) (2)

PLS1 1 M' Pasang Kabel NYY 3 x 6 sqmm


Tukang Listrik 0.0050 org X Rp. 0
Pekerja 0.0050 org X Rp. 55000
Mandor 0.0050 org X Rp. 80000
JUMLAH

PLS2 1 M' Pasang Kabel NYY 3 x 4 sqmm


Tukang Listrik 0.0050 org X Rp. 0
Pekerja 0.0050 org X Rp. 55000
Mandor 0.0050 org X Rp. 80000
JUMLAH

PLS3 1 M' Pasang Kabel NYM 2 x 2,5 sqmm


Tukang Listrik 0.0050 org X Rp. 0
Pekerja 0.0050 org X Rp. 55000
Mandor 0.0050 org X Rp. 80000
JUMLAH

PLS4 1 M' Pasang Kabel NYM 2 x 1,5 sqmm


Tukang Listrik 0.0050 org X Rp. 0
Pekerja 0.0050 org X Rp. 55000
Mandor 0.0050 org X Rp. 80000
JUMLAH

PLS5 1 M' Pasang Kabel NYA 1 x 2,5 sqmm


Tukang Listrik 0.0025 org X Rp. 0
Pekerja 0.0025 org X Rp. 55000
Mandor 0.0025 org X Rp. 80000
JUMLAH

PLS6 50 M' Pasang Kabel DX 2x10 sqmm + Accessories (antar tiang / gawang)
Kabel DX 2 x 10 sqmm "Supreme" 50.0000 m1 X Rp. 0
Tukang Listrik 0.5000 org X Rp. 0
Pekerja 0.5000 org X Rp. 55000
Mandor 0.2500 org X Rp. 80000
Penyambungan beban 1.0000 ls X Rp. 0
JUMLAH

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :330


PT Pelabuhan Indonesia I (Persero)

(1) (2)

PLS7 50 M' Pasang Kabel DX 2x16 sqmm + Accessories (antar tiang / gawang)
Kabel DX 2 x 16 sqmm "Supreme" 50.0000 m1 X Rp. 0
Tukang Listrik 0.5000 org X Rp. 0
Pekerja 0.5000 org X Rp. 55000
Mandor 0.2500 org X Rp. 80000
Penyambungan beban 1.0000 ls X Rp. 0
JUMLAH

PLS8 1 M' Pasang Kabel NYY 3x10 sqmm


Kabel NYY 3 x 10 sqmm "Supreme" 1.0000 m1 X Rp. 0
Tukang Listrik 0.0050 org X Rp. 0
Pekerja 0.0050 org X Rp. 55000
Mandor 0.0050 org X Rp. 80000
JUMLAH

PLS9 1 Unit Pasang Box Panel dan Panel Kontrol


Tukang Listrik 0.5000 org X Rp. 0
Pekerja 0.7500 org X Rp. 55000
Mandor 0.2500 org X Rp. 80000
Pasang panel kontrol 1.0000 unit X Rp. 0
JUMLAH

PLS10 1 Unit Pasang Box KWH dan Meter (1 Unit)


Tukang Listrik 0.5000 org X Rp. 0
Pekerja 0.7500 org X Rp. 55000
Mandor 0.2500 org X Rp. 80000
Pasang panel kontrol 1.0000 unit X Rp. 0
JUMLAH

PLS11 1 Unit Pasang tiang lampu antik (b3)


Tukang batu 0.6600 org X Rp. 80000
Tukang listrik 0.6600 org X Rp. 0
Pekerja 5.3300 org X Rp. 55000
Mandor 0.6660 org X Rp. 80000
Alat bantu 0.6660 set X Rp. 0
Angkutan 4.6000 jam X Rp. 0
JUMLAH

PLS12 1 Unit Pasang tiang lampu antik (b3)


Tukang batu 0.5000 org X Rp. 80000
Tukang listrik 0.5000 org X Rp. 0
Pekerja 4.0000 org X Rp. 55000
Mandor 0.5000 org X Rp. 80000
Alat bantu 0.5000 set X Rp. 0
Angkutan 3.5000 jam X Rp. 0
JUMLAH

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :331


PT Pelabuhan Indonesia I (Persero)

(1) (2)

PLS13 1 Set Pemasangan armatur komplit


Tukang listrik 0.5000 org X Rp. 0
Pekerja 0.7500 org X Rp. 55000
Mandor 0.2500 org X Rp. 80000
Alat bantu 1.0000 set X Rp. 0
JUMLAH

PLS14 1 Unit Pemasangan komponen + Box


Tukang listrik 0.6660 org X Rp. 0
Pekerja 1.0000 org X Rp. 55000
Mandor 0.3330 org X Rp. 80000
Alat bantu 1.0000 set X Rp. 0
JUMLAH

PLS15 1 Set Bongkar komponen


Tukang listrik 0.4000 org X Rp. 0
Pekerja 0.6000 org X Rp. 55000
Mandor 0.2000 org X Rp. 80000
Alat bantu 1.0000 set X Rp. 0
JUMLAH

PLS16 1 Unit Bongkar Armatur


Tukang Listrik 0.3300 org X Rp. 0
Pekerja 0.5000 org X Rp. 55000
Mandor 0.1666 org X Rp. 80000
Angkutan 1.0000 jam X Rp. 0
JUMLAH

PLS17 1 Set Bongkar Tiang Lampu Antik (b.1)


Tukang batu 0.5000 org X Rp. 80000
Tukang Listrik 0.5000 org X Rp. 0
Pekerja 4.0000 org X Rp. 55000
Mandor 0.5000 org X Rp. 80000
Alat bantu 0.5000 set X Rp. 0
Angkutan 3.5000 jam X Rp. 0
JUMLAH

PLS18 1 Set Bongkar Tiang Lampu Antik (b.1)


Tukang batu 0.6600 org X Rp. 80000
Tukang Listrik 0.6600 org X Rp. 0
Pekerja 5.3330 org X Rp. 55000
Mandor 0.6660 org X Rp. 80000
Alat bantu 0.6660 set X Rp. 0
Angkutan 4.6000 jam X Rp. 0
JUMLAH

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :332


PT Pelabuhan Indonesia I (Persero)

(1) (2)

PLS19 1 m' Pasang Kabel NYM 2x2,5 sqmm


Kabel NYM 2 x 2,5 sqmm "Supreme" 1.0000 m1 X Rp. 0
Tukang Listrik 0.2500 org X Rp. 0
Pekerja 0.0100 org X Rp. 55000
Mandor 0.0050 org X Rp. 80000
JUMLAH

PLS20 1 m' Pasang Kabel NYA 2,5 sqmm


Kabel NYM 2 x 2,5 sqmm "Supreme" 1.0000 m1 X Rp. 0
Tukang Listrik 0.2500 org X Rp. 0
Pekerja 0.0100 org X Rp. 55000
Mandor 0.0050 org X Rp. 80000
JUMLAH

PLS21 1 m' Pasang Pralon 3" Kabel NYY 3x6 sqmm


Pipa pralon 3" 1.0000 m1 X Rp. 0
Pekerja 0.0100 org X Rp. 55000
Mandor 0.0050 org X Rp. 80000
JUMLAH

PLS22 Pasang tutup panel ukuran 30x30


Tutup panel 30x30 1.0000 bh X Rp. 0
Tukang listrik 0.0500 org X Rp. 0
Pekerja 0.1000 org X Rp. 55000
Mandor 0.0250 org X Rp. 80000
JUMLAH

PLS23 Pasang MCB Ampere + box tutup panel ukuran 30 x 30


MCB 10 Ampere + box "MG" 1.0000 bh X Rp. 0
Tukang listrik 0.0500 org X Rp. 0
Pekerja 0.1000 org X Rp. 55000
Mandor 0.0250 org X Rp. 80000
JUMLAH

PLS24 Pasang Kapasitor 12,5 uF 1.0000 bh


Kapasitor 12,5 uF 1.0000 bh X Rp. 0
Tukang listrik 0.0500 org X Rp. 0
Pekerja 0.1000 org X Rp. 55000
Mandor 0.0250 org X Rp. 80000
JUMLAH

PLS25 1 Set Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son + pengetesan dan penyalaan

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :333


PT Pelabuhan Indonesia I (Persero)

(1) (2)
Pekerja 0.5000 org X Rp. 55000
Tukang Listrik 0.5000 org X Rp. 0
Pengawas 1.2500 org X Rp. 0
Mandor 0.5000 org X Rp. 80000
JUMLAH (A)

Pengetesan dan Penyalaan


Pasang instalasi / titik 1.0000 ttk X Rp. 0
JUMLAH (B)

PLS26 1 Set Pasang Stang Ornamen 6 meter + Lampu SRP 822/250 Watt Son
Pekerja 0.8750 org X Rp. 55000
Tukang Listrik 0.8750 org X Rp. 0
Pengawas 1.8033 org X Rp. 0
Mandor 0.7413 org X Rp. 80000
JUMLAH (C)

PLS27 1 Set Pasang Stang Ornamen 2,2 meter + Lampu SRP 822/250 Watt Son
Pekerja 0.5000 org X Rp. 55000
Tukang Listrik 0.5000 org X Rp. 0
Pengawas 1.2500 org X Rp. 0
Mandor 0.5000 org X Rp. 80000
JUMLAH (D)

PLS28 1 Set Pasang Tiang Octogonal Cabang 1, h= 7 meter+ lampu SRP 822/250 Watt Son
Pondasi Tiang Beton bertulang 1:2:3 0.4200 m3 X Rp. 491,200.00
Pekerja 2.8500 org X Rp. 55000
Tukang Listrik 2.8500 org X Rp. 0
Pengawas 2.0075 org X Rp. 0
Mandor 1.0000 org X Rp. 80000
JUMLAH (E)

PLS29 1 Set Pasang Tiang Octogonal Cabang 1, h= 9 meter + lampu SRP 822/250 Watt Son
Pondasi Tiang Beton bertulang 1:2:3 0.4200 m3 X Rp. 491,200.00
Pekerja 3.1000 org X Rp. 55000
Tukang Listrik 3.1000 org X Rp. 0
Pengawas 2.5000 org X Rp. 0
Mandor 1.2100 org X Rp. 80000
JUMLAH (F)

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :334


PT Pelabuhan Indonesia I (Persero)

(1) (2)

PLS30 1 Set Pasang Tiang Octogonal Cabang 2, h= 9 meter+ lampu SRP 822/250 Watt Son
Pondasi Tiang Beton bertulang 1:2:3 0.4200 m3 X Rp. 491,200.00
Pekerja 3.3000 org X Rp. 55000
Tukang Listrik 3.3000 org X Rp. 0
Pengawas 2.5782 org X Rp. 0
Mandor 1.2433 org X Rp. 80000
JUMLAH (G)

PLS31 1 Set Pasang Tiang Octogonal Cabang 3, h= 9 m+ lampu SRP 822/250 Watt Son
Pondasi Tiang Beton bertulang 1:2:3 0.4200 m3 X Rp. 491,200.00
Pekerja 3.8100 org X Rp. 55000
Tukang Listrik 3.8100 org X Rp. 0
Pengawas 2.6626 org X Rp. 0
Mandor 1.2650 org X Rp. 80000
JUMLAH (H)

PLS32 1 Set Pasang Tiang Octogonal Cabang 3, h= 11 m+ lampu SRP 822/250 Watt Son
Pondasi Tiang Beton bertulang 1:2:3 0.4200 m3 X Rp. 491,200.00
Pekerja 4.2500 org X Rp. 55000
Tukang Listrik 4.2500 org X Rp. 0
Pengawas 2.9287 org X Rp. 0
Mandor 1.2939 org X Rp. 80000
JUMLAH (I)

PLS33 1 Set Bongkar armatur pada stang ornamen existing + pasang lampu SRP 822/150 Watt Son + return
Pekerja 0.9000 org X Rp. 55000
Tukang Listrik 0.9000 org X Rp. 0
Pengawas 2.1044 org X Rp. 0
Mandor 0.8418 org X Rp. 80000
Retur material existing 0.0500 unit X Rp. 0
JUMLAH (J)

PLS34 1 Set Bongkar armatur pada stang ornamen existing + pasang Lampu SRP 822/250 Watt Son + retur
Pekerja 0.8750 org X Rp. 55000
Tukang Listrik 0.8750 org X Rp. 0
Pengawas 1.6995 org X Rp. 0
Mandor 0.6798 org X Rp. 80000
Retur material existing 0.0500 unit X Rp. 0
JUMLAH (K)

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :335


PT Pelabuhan Indonesia I (Persero)

(1) (2)

PLS35 1 Set Bongkar armatur pada tang existing + pasang Lampu SRP 822/250 Watt Son + retur
Pekerja 0.9000 org X Rp. 55000
Tukang Listrik 0.9000 org X Rp. 0
Pengawas 2.1044 org X Rp. 0
Mandor 0.8418 org X Rp. 80000
Retur material existing 0.0500 unit X Rp. 0
JUMLAH (L)

PLS36 1 Set Bongkar komponen lama existing + pasang komponen Lampu SRP 822/250 Watt Son + retur
Pekerja 0.8500 org X Rp. 55000
Tukang Listrik 0.8500 org X Rp. 0
Pengawas 1.9554 org X Rp. 0
Mandor 0.7822 org X Rp. 80000
Retur material existing 0.0500 unit X Rp. 0
JUMLAH (M)

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :336


PT Pelabuhan Indonesia I (Persero)

RJAAN LISTRIK

Upah Bahan Jumlah


(3) (4) (5)

-
275.00
400.00
675.00 - 675.00

-
275.00
400.00
675.00 - 675.00

-
275.00
400.00
675.00 - 675.00

-
275.00
400.00
675.00 - 675.00

-
137.50
200.00
337.50 - 337.50

-
-
27,500.00
20,000.00
-
47,500.00 - 47,500.00

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :337


PT Pelabuhan Indonesia I (Persero)

(3) (4) (5)

-
-
27,500.00
20,000.00
-
47,500.00 - 47,500.00

-
-
275.00
400.00
675.00 - 675.00

-
41,250.00
20,000.00
-
61,250.00 - 61,250.00

-
41,250.00
20,000.00
-
61,250.00 - 61,250.00

52,800.00
-
293,150.00
53,280.00
-
-
399,230.00 - 399,230.00

40,000.00
-
220,000.00
40,000.00
-
-
300,000.00 - 300,000.00

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :338


PT Pelabuhan Indonesia I (Persero)

(3) (4) (5)

-
41,250.00
20,000.00
-
61,250.00 - 61,250.00

-
55,000.00
26,640.00
-
81,640.00 - 81,640.00

-
33,000.00
16,000.00
-
49,000.00 - 49,000.00

-
27,500.00
13,328.00
-
40,828.00 - 40,828.00

40,000.00
-
220,000.00
40,000.00
-
-
300,000.00 - 300,000.00

52,800.00
-
293,315.00
53,280.00
-
-
399,395.00 - 399,395.00

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :339


PT Pelabuhan Indonesia I (Persero)

(3) (4) (5)

-
-
550.00
400.00
950.00 - 950.00

-
-
550.00
400.00
950.00 - 950.00

-
550.00
400.00
950.00 - 950.00

-
-
5,500.00
2,000.00
7,500.00 - 7,500.00

-
-
5,500.00
2,000.00
7,500.00 - 7,500.00

-
-
5,500.00
2,000.00
7,500.00 - 7,500.00

+ pengetesan dan penyalaan

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :340


PT Pelabuhan Indonesia I (Persero)

(3) (4) (5)


27,500.00
-
-
40,000.00
67,500.00 - 67,500.00

-
- - -

48,125.00
-
-
59,306.40
107,431.40 - 107,431.40

27,500.00
-
-
40,000.00
67,500.00 - 67,500.00

0 Watt Son
206,304.00
156,750.00
-
-
80,000.00
236,750.00 206,304.00 443,054.00

50 Watt Son
206,304.00
170,500.00
-
-
96,800.00
267,300.00 206,304.00 473,604.00

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :341


PT Pelabuhan Indonesia I (Persero)

(3) (4) (5)

0 Watt Son
206,304.00
181,500.00
-
-
99,464.00
280,964.00 206,304.00 487,268.00

206,304.00
209,550.00
-
-
101,200.00
310,750.00 206,304.00 517,054.00

206,304.00
233,750.00
-
-
103,512.00
337,262.00 206,304.00 543,566.00

P 822/150 Watt Son + return


49,500.00
-
-
67,344.00
-
116,844.00 - 116,844.00

P 822/250 Watt Son + retur


48,125.00
-
-
54,384.00
-
102,509.00 - 102,509.00

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :342


PT Pelabuhan Indonesia I (Persero)

(3) (4) (5)

Watt Son + retur


49,500.00
-
-
67,344.00
-
116,844.00 - 116,844.00

822/250 Watt Son + retur


46,750.00
-
-
62,576.00
-
109,326.00 - 109,326.00

Analisa Harga Satuan Pekerjaan Listrik Tahun 2012 Hal :343

You might also like