ID Task Task Name Duration Start Finish Qtr 3, 2019 Qtr 4, 2019

Mode Jul Aug Sep Oct Nov


1 START 0 days Mon 6/3/19 Fri 7/19/19 7/19
2 Literature Review 76 days Mon 7/22/19 Mon 11/4/19
3 Collection of Data and Analysis of the Tank10 days Mon 8/19/19 Fri 8/30/19
4 Design and Detailing of Water Tank 45 days Fri 8/30/19 Thu 10/31/19
5 Preparation of Bill of quantities 2 days Fri 11/1/19 Mon 11/4/19
6 Report Writing 56 days Mon 8/19/19 Tue 11/5/19
7 FINAL SUBMISSION 0 days Wed 11/6/19 Wed 11/6/19 11/6

Task Inactive Task Start-only


Split Inactive Milestone Finish-only
Milestone Inactive Summary Deadline
Project: msproj11
Date: Mon 10/14/19 Summary Manual Task Progress
Project Summary Duration-only Manual Progress
External Tasks Manual Summary Rollup
External Milestone Manual Summary