You are on page 1of 11

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/227753569

Measuring Portfolio Strategic Performance Using Key Performance Indicators

Article  in  Project Management Journal · December 2010


DOI: 10.1002/pmj.20165

CITATIONS READS
36 2,489

2 authors, including:

Hynuk Sanchez
Polytechnique Montréal
6 PUBLICATIONS   136 CITATIONS   

SEE PROFILE

All content following this page was uploaded by Hynuk Sanchez on 09 January 2018.

The user has requested enhancement of the downloaded file.


PAPERS Measuring Portfolio Strategic
Performance Using Key Performance
Indicators
Hynuk Sanchez, École Polytechnique de Montréal, Montréal, Canada
Benoît Robert, Centre Risque & Performance, Montréal, Canada

ABSTRACT ■ INTRODUCTION ■
rom a project portfolio perspective, it is not enough to track the per-
It is difficult to find indicators for measuring the
achievement of objectives during the progress of
project portfolios. This article presents an
approach for developing key strategic perfor-
mance indicators considering this limitation. The
indicators proposed help measure the achieve-
F formance of projects in an isolated way. Portfolio managers need to
have tools that allow the understanding of the meaning of a project’s
performance when it is interconnected with the performance of
other projects and linked with strategic objectives. Tools need to be used in
a timely and effective fashion, with the intention of perceiving trends and
reacting as quickly as possible, giving priority to the most urgent and impor-
ment of a portfolio’s strategic objectives taking
tant problems. This article proposes the development of key strategic per-
into account the realization of key benefits. This
formance indicators for project portfolios, which are the foundation for
approach helps identify strategic interdepen-
developing tools to accomplish the issues already exposed. The indicators
dences between projects that the portfolio is com-
introduced in this article consider a strategic viewpoint and they are split in
posed of, facilitating the understanding of how
two levels: measuring the realization of key benefits of the portfolio and
the performance of a single project affects the
measuring the achievement of the objectives of the portfolio. In this way, the
overall performance of a portfolio. The key perfor-
resulting strategic performance from the aggregation of several projects can
mance indicators can also be used for monitoring
be tracked regarding the achievement of objectives, which is not possible if
the materialization of risks and opportunities influ-
projects are considered in isolation.
encing the strategic performance of a portfolio.
Our proposal is based on the critical success factor method, which aims
at identifying critical benefits that are absolutely necessary for achieving
KEYWORDS: key performance indicators;
strategic goals. The management and realization of benefits is a major
critical success factors; benefits management;
subject in program management. A benefits realization plan is developed
portfolio management; risk management;
during the management of a program and it is tracked in order to realize pro-
program management
gram benefits in a predictable and coordinated manner (Project
Management Institute, 2008a). Key benefits extracted from this plan using
the Critical Success Factor method are used for setting the portfolio key
strategic performance indicators. The result of interconnecting all key bene-
fits from programs is a network of strategic interdependences, which can be
used for identifying the influence of project performance variations on a
portfolio’s strategic goals.
The objective of this article is to introduce a set of key strategic perfor-
mance indicators developed in such a way that they measure the overall
strategic performance of the portfolio, considering the collection of perform-
ances of individual projects and their strategic interdependences. Most indi-
cators used in project portfolios are financial or schedule based. The benefit
of having strategic indicators is the early detection of performance variances
that hinder or facilitate the achievement of a portfolio’s strategic objectives. It per-
Project Management Journal, Vol. 41, No. 5, 64–73 mits the implementation of action plans for treating considerable variances
© 2010 by the Project Management Institute in order to adapt or reestablish the portfolio. The set of indicators can also be
Published online in Wiley Online Library used to detect the materialization of risks and opportunities influencing
(wileyonlinelibrary.com). DOI: 10.1002/pmj.20165 project, program, and portfolio strategic performance. The methodology

64 December 2010 ■ Project Management Journal ■ DOI: 10.1002/pmj


followed for achieving the objective of information (Rockart, 1979). A KPI has the contribution of projects are the
this article has been divided in three a lifetime and requires continuous internal CSFs in a project portfolio.
steps. First, a theoretical frame has updating. Sometimes, its replacement
Benefits
been elaborated for identifying the is also needed (Ghalayini & Noble,
Benefits are measurable improvements
needed concepts to support the devel- 1996). KPIs use a metric for quantita-
perceived to be a value by one or more
opment of key strategic performance tively assessing performance regarding
of the stakeholders (Rajegopal, McGuin,
indicators for project portfolios. The the needs and expectations of stake-
& Waller, 2007, p. 209; Venning, 2007).
theoretical frame is synthesized and holders, the achievement of goals, and
They can be tangible or intangible
presented in the Literature Review. reflecting the critical success factors
depending on the ease with which they
Then, the selected concepts have been (Sinclair & Zairi, 1995). The measure-
can be quantified (Project Management
integrated to construct the visual repre- ment can be performed in two man-
Institute, 2008a; Williams & Parr, 2004).
sentations of strategic interdependen- ners: directly assessing the change
Additionally, tangible benefits can also
cies and to develop the key strategic delivered or specifically assessing the
be classified as financial or nonfinancial
performance indicators are introduced performance of the process (Morris &
(Williams & Parr, 2006). Strategic bene-
and explained. This is followed by a Pinto, 2004, p. 25). In addition, a KPI
fits are usually intangible, and they
discussion of the value and usability of should be complemented by a target
provide a competitive advantage or
these indicators. representing the predetermined desired
contribute to the survival of an organi-
level of performance (Sinclair & Zairi,
zation. Consequently, they cannot be
Literature Review 1995). KPIs can be nonfinancial and
expressed in an adequate way using
Some solutions have already been pro- they must be frequently measured
financial terms (Lefley, 2004). Research-
posed for tracking project performance (Parmenter, 2007).
ers have studied the reasons why
across a portfolio of projects. For
Critical Success Factors strategic or intangible benefits are diffi-
instance, Cable, Ordonez, Chintalapani,
In 1979, John Rockart introduced a cult to appraise. Among those reasons,
and Plaisant (2004) present a visualiza-
method for defining critical success we highlight the following (Giaglis,
tion technique called Treemaps for
factors (CSFs). Using his words, critical Mylonopoulos, & Doukidis, 1999; Lin &
exhibiting the metrics of project per-
success factors are “the limited number Pervan, 2003):
formance in a portfolio; they use Earned
of areas in which results, if they are 1. They are not realized immediately.
Value Management to construct the per-
satisfactory, will ensure successful com- 2. They are difficult to quantify.
formance metrics. However, a control
petitive performance for the organiza- 3. Other factors may confound them,
system must also consider the critical
tion” (Rockart, 1979, p. 85). There are rendering the benefits indistinguish-
success factors for tracking performance
other definitions depending on the able.
and must be adapted to the strategy of
domain they are applied to (Kerzner, 4. Existing techniques are not appropri-
the organization (Anthony, Dearden, &
2006; Pinto & Rouhiainen, 2001; ate for perceiving their value.
Vancil, 1972). Consequently, there is a
Richman, 2006). The use of a CSF 5. It is difficult to plan when they may
clear link between strategic objectives,
approach helps identify the factors that be realized.
critical success factors, and the develop-
should receive careful attention. It can
ment of key performance indicators.
be applied as a top-down methodology It has been proven that most proj-
The following paragraphs explain these
for planning the strategy of an organi- ects deliver different types of benefits,
concepts in more detail.
zation and for developing pertinent including strategic ones (Giaglis et al.,
Key Performance Indicators measures during the monitoring of per- 1999; Lefley, 2004). Postproject evalua-
The origins of key performance indica- formance (Chen, 1999; Quesada & tions help confirm which of the expect-
tors (KPIs) can be traced to 1976 in an Gazo, 2007; Rockart, 1979). Transposing ed benefits have been effectively
article published by BusinessWeek this approach into a project portfolio accomplished in practice (Lin & Pervan,
(“Corporate ‘War Rooms’ Plug Into the context, CSFs are the necessary factors 2003). However, those benefits must be
Computer,” 1976). It described a key to meet the strategic objectives of the planned in advance and aligned to the
indicator system based on three con- portfolio. The projects of a portfolio strategy of the organization. Benefits
cepts: (1) the selection of key indicators deliver key benefits such as new com- management is the domain of knowl-
to represent the health of the organiza- petences or improvements, permitting edge that defines and maximizes them.
tion; (2) exception reporting or, in other the organization to meet strategic goals It is described as the process of organiz-
words, the ability to present only those (Sanchez, Robert, & Pellerin, 2008). ing and managing such that expected
indicators where performance was Successfully achieving these benefits benefits are in fact achieved (Seddon,
considerably different from expected facilitates the achievement of strategic Graeser, & Willcocks, 2001). Following
results; and (3) the visual display of that goals. So, key benefits obtained through the Project Management Institute

December 2010 ■ Project Management Journal ■ DOI: 10.1002/pmj 65


PAPERS
Measuring Portfolio Strategic Performance Using Key Performance Indicators

(2008a), the life cycle of benefits statement. A portfolio is a way to imple- The Contribution of Projects to the
management has four processes: the ment the strategic plan and achieve Achievement of a Portfolio’s Strategic
benefits identification process (where strategic objectives (Sanchez et al., 2008). Objectives
business benefits are identified and As expressed by the Project Manage- Following Ronald Daniel, a system
qualified); the benefits analysis & plan- ment Institute, a portfolio is “a true reporting internal data must be dis-
ning process (where projects are measure of an organization’s intent, direc- criminating and selective (Daniel,
derived and prioritized, benefits met- tion, and progress” (Project Manage- 1961). Managers need to monitor only
rics are derived, the benefits realization ment Institute, 2008b, p. 5). In order to those factors that have gone remark-
plan is established, and benefits are define the key performance indicators ably well to ensure the success of the
mapped into the program plan); the for measuring the achievement of portfolio. Key strategic benefits are
benefits realization process (where strategic objectives, it is necessary to do the success factors inside the portfolio
projects are monitored, the benefits an analysis starting from the mission whose realization facilitates the achieve-
register is maintained, and benefits statement of the organization and then ment of strategic goals. Each project
realization is reported); and the benefits going through the vision, the objectives, contributes to one or to several bene-
transition process (where benefits are and their critical success factors (De Feo fits; otherwise, there would not be a
consolidated and the ongoing responsi- & Janssen, 2001; Lefley, 2004). By defini- reason to consider them in the portfo-
bility is transferred). Additionally, there tion, a performance measure is the lio. Indeed, if a project in progress is not
are other approaches suggested by “numerical or quantitative indicator contributing to the realization of bene-
researchers for realizing and managing that shows how well each objective is fits as intended, the termination of this
benefits. Some examples are the being met” (Pritchard, Roth, Jones, & project should be evaluated, taking into
Cranfield Process Model by Ward, Roth, referred by Sinclair & Zairi, 1995, consideration any interdependency
Taylor, and Bond (1996); the Active p. 50). However, in spite of the impor- with other projects. Project contribu-
Benefits Realization approach by tance of performance indicators to tions to the realization of key benefits
Remenyi, Sherwood-Smith, and White measure the achievement of strategic build a network linking the objectives
(1997); the benefits realization model objectives of a portfolio, most key per- of the portfolio, the key benefits, and
developed by DMR Consulting (Lin & formance indicators used in portfolios the collection of projects. This network
Pervan, 2003); or the benefits realization are based on financial terms or based is composed of several streams that are
approach developed by Thorp (1998). only on the isolated performance of extended along a time frame. The real-
As explained before, a portfolio projects, taking into consideration cost, ization of benefits and objectives, such
brings together all benefits delivered by schedule, and quality (Alarcon & as in projects, must be clearly defined
programs and projects. It has a critical Serpell, 1996; Haponava & Al-Jibouri, within a period because they are
function in assuring that all benefits are 2009; Pillai, Joshi, & Rao, 2002). processes of change, and that change is
aligned to the portfolio’s strategic Limitations of traditional performance only desirable in a specific interval of
objectives. As Venning (2007) wrote, the measures based on costs have already time. Conditions are dynamic, and the
role of a portfolio of projects is verifying been exposed before by many research- change provided by projects may no
that expected benefits are planned, ers; some such limitations are: the longer be pertinent after or before that
realistic, and in fact delivered by pro- exclusion of a strategic perspective, period. This definition is made during
grams and projects. the lack of focus on success factors, and the the Benefits Analysis and Planning
poor consideration of stakeholders’ process of the Benefits Management
Developing Key Performance needs and expectations (Daniel, 1961; life cycle. Figure 1 exhibits the “project-
Indicators for Project Portfolios Ghalayini & Noble, 1996; Pillai et al., benefit-objective” streams inside a
Considering a Strategic 2002; Tangen, 2004). Considering this portfolio.
Perspective approach, it is difficult to find a trend to A portfolio is composed of projects,
The objectives of a portfolio are born forecast where the portfolio is going programs, and other related work
from the mission, the vision, and the with respect to the attainment of the (Project Management Institute, 2008c).
strategy of an organization. The mission strategic goals. The key strategic per- We consider projects as the fundamen-
expresses the reason for the existence of formance indicators we propose help go tal elements for elaborating key strate-
an organization. On the other hand, the beyond these limitations. They are gic performance indicators because
vision is the description of its desired based on two components: (1) the con- they are the constituent parts of pro-
future state. Strategic objectives are set tribution of projects to the achievement grams and portfolios. Programs are
and a strategic plan is designed for of a portfolio’s strategic objectives and implicitly considered in the visual rep-
realizing the vision and accomplishing (2) the level of performance of each resentation such as exhibited in Figure 1.
the purposes expressed in the mission project at a given point in time. As can also be noted in the model,

66 December 2010 ■ Project Management Journal ■ DOI: 10.1002/pmj


Stream element 2009 Qtr 1 2009 Qtr 2 2009 Qtr 3 2009 Qtr 4 2010 Qtr 1 2010 Qtr 2 2010 Qtr 3 2010 Qtr 4 2011 Qtr 1 2011 Qtr 2

Project 1
Project 2
Key Benefit A
Project 3
Objective I
Project 4
Project 5
Key Benefit B
Project 6
Project 7
Key Benefit C
Project 8
Objective II
Project 9
Project 10
Key Benefit D
Project 11
Objective
Objective III
Project 12 Key benefit
Key Benefit E Project
Program
Project 13
Contribution

Figure 1: A model of a portfolio representing the “project-benefit-objective” streams on a time frame.

one project may be related to one or objective pursuing the entrance into written. This step also sets the period
more objectives. The link is established the new market. The model in Figure 1 of monitoring objectives. In other
through the key benefits; for example, is just a simple representation of a port- words, the period from when the
Project 11 contributes to the realization folio; in real life, one project may be change starts to happen until the
of key benefit D, which contributes to related to several objectives. Then, this change occurs at the desired level. It
the achievement of objectives II and III. model helps distinguish the network of is important to remember that a
It brings about the result that any varia- relationships inside the portfolio in portfolio of projects is a means for
tion on performance in this project order to evaluate the consequences organizational change, and portfolio
may become critical because of its that a single variation in a project per- objectives are essential for setting the
impact on the achievement of more formance may produce on the achieve- level and the orientation for this
than one objective. The level of impact ment of several objectives. change.
depends on the level of the project con- Its construction follows the ap- 2. Setting or Validation of Key Benefits.
tribution to key benefit D and its level proach of the CSF. However, we specify In this step, a portfolio management
of contribution to each objective. For the following steps for adapting it to a team performs the critical success
instance, a key benefit is the compli- project portfolio management context: factor method introduced by
ance of environmental regulations on 1. Setting or Validation of Portfolio Rockart. It is applied as follows:
vehicles, which is linked to two objec- Objectives. Following the strategic Considering the benefits realization
tives: (1) entering into a new market plan of the organization and consid- plans of programs, the team starts
demanding those regulations and ering the needs identified by stake- identifying key benefits that are criti-
(2) improving the strategic position in the holders or by the portfolio manager, cal for achieving the objectives of the
current market thanks to an enhanced a nonextensive list of objectives portfolio. An additional analysis is
vehicle. The failure of a project that having the SMART characteristics also performed, aiming at identifying
reduces emissions impacts both objec- (specific, measurable, attainable, rel- more key benefits not included in
tives, but it is more severe on the evant, and time-based objectives) is those plans. The team clarifies the

December 2010 ■ Project Management Journal ■ DOI: 10.1002/pmj 67


PAPERS
Measuring Portfolio Strategic Performance Using Key Performance Indicators

interrelationships between key bene- However, if one of these projects is attainment of portfolio objectives or
fits in order to find which of them can more important for realizing the ben- projects whose contribution is so low
be combined, eliminated, or restated. efit, proportions may be distributed that it is not convenient to assign them
Initial measures for each benefit are as follows: 20% assigned to the three a high budget when they are consider-
also set for further monitoring. Then, regular projects and 40% assigned to ably uncertain. This procedure also
findings are reviewed, aiming to the most important project. We helps to establish a priority to projects
improve them. Measures and reports determine first the relative contribu- from a strategic standpoint, which is
are also discussed in depth. Finally, tion of each key benefit, B, to achieve useful for the Prioritize Components
the team arrives at a final agreement each objective, O, giving it a value CBO. process during the management of the
on key benefits, measures, and After that, the relative contribution of portfolio. Doing a further analysis, if
reports. These benefits must appear each project, P, for the realization key benefits are not supported enough
in the benefits delivery schedule of each key benefit, B, is determined, by authorized projects, new projects
elaborated during the time of portfo- setting the value CPB. A structured may be created or authorized, reinforc-
lio planning. Once again, a period of technique of multiattribute decision ing the realization of those key benefits
monitoring benefits must be estab- making can be used for finding the and helping to align new projects
lished in order to supervise their importance level and establishing toward the strategic goals.
achievement. contributions, such as the analytic
3. Linking Projects, Key Benefits, and hierarchy process (Saaty, 1980). The Level of Performance of Each
Objectives. Based on step 2, each key Scoring models can also be used if Project at a Given Time
benefit is analyzed to find the rela- managers prefer qualitative meth- There is already specialized software
tionship with each objective, and ods. The assessment of the project that automatically takes the data from
each project is analyzed to find the contribution, P, to the achievement the monitoring of budgets, earned
relationship with each key benefit. of a portfolio objective, O, is expres- value, or status of the schedule, and
Steps 1, 2, and 3 are iterative to arrive sed as follows: concentrates that information in a
at a congruent description of streams dashboard. The idea of a dashboard is
a (C
n

showing the links between projects, CPO ⫽ PB · CBO ) based on the concept of exception
B=1
key benefits, and objectives. This reporting as explained before, and its
where
step helps to verify whether all key origins can also be traced back to 1976
benefits are supported by project CPO ⫽ contribution of project P to objec-
when Gould, Inc. combined a visual
contributions. It is possible that tive O, display board with a computer infor-
other key benefits are needed for CPB ⫽ relative contribution of project P to mation system (“Corporate ‘War
achieving portfolio objectives and key benefit B, Rooms’ Plug Into the Computer,” 1976).
any project contributes to its realiza- CBO ⫽ relative contribution of key benefit B At present, a dashboard usually repre-
tion. On the other hand, this step also to objective O, sents the status of a project using key
helps validate and correct benefits P ⫽ project in the stream project-benefit- performance indicators and employing
realization plans of programs detect- objective, three colors: green to represent healthy
ing benefits unrelated to the achieve- O ⫽ objective in the stream project-benefit- performance of the project, yellow to
objective,
ment of strategic objectives. represent the project in alert, and red
B ⫽ key benefit in the stream project-
4. Visualizing the Streams. Consolidating to represent the project in failure—that
benefit-objective, and
the information obtained during steps n ⫽ total number of key benefits.
is, measuring the performance of the
1, 2, and 3i, a model is built to repre- project regarding a specific parameter,
sent the project-benefit-objective Applying the following restrictions: comparing the measurement to a pre-
streams on a time frame (Figure 1). set target, and establishing the status
aC
m
5. Determining the Project Contribution ⫽ 1 for all O depending on the acceptable or unac-
PO
to the Achievement of Portfolio P ⫽1 ceptable deviation between the target

aC
Objectives. Contributions are not n and the parameter measured. To differ-
represented in units; they are only BO ⫽ 1 for all O entiate each status, it is necessary to
B⫽1
represented as proportional values establish thresholds for knowing the
aC
m
with respect to the importance level PB ⫽ 1 for all B acceptable or unacceptable values of a
of the project or benefit. For instance, P ⫽1 key performance indicator. The settle-
if four projects have the same impor- An additional advantage of per- ment of thresholds is an important task
tance for realizing a key benefit, each forming this procedure is the recogni- because decisions will depend on them
of them will contribute 25%. tion of projects not contributing to the for implementing action plans and for

68 December 2010 ■ Project Management Journal ■ DOI: 10.1002/pmj


evaluating in a qualitative manner the
criticality of a performance status. That
is the reason why it is recommended to KPI
Parameter
establish thresholds by consensus
between the people who will be impli- Opportunity zone

cated in the decision-making process Target


Healthy state Green
during the monitoring of the portfolio, Threshold a
such as the people forming the portfo- Alert state Yellow
Threshold b
lio review board. Despite the fact that Risk zone
Failure state Red
thresholds are established by consen-
sus, one member of the portfolio review
t1 t2 t3 t4 ... time
board is empowered to make the final
decision. From a risk management per-
spective, the thresholds and the target Figure 2: Components of a key performance indicator.
define two zones: a zone of opportunity
and a zone of risk. The zone of opportu-
nity is placed above the target. This
means the project performance whose
measure is above this target may be the value of “1” is assigned to repre- The Combination of Components to
profited by to ensure or facilitate the sent the target. All measurements of Obtain the KPIs for Project Portfolios
achievement of portfolio objectives. In performance below the target are rep- Once the components of the KPIs for
opposition, the zone of risk is placed resented as the proportional value project portfolios are discussed, it is
under the first threshold where the sta- between 0 and 1. Measurements of necessary to integrate them. As stated,
tuses in alert and in failure belong. In performance above the target are also the KPIs proposed aim at measuring
other words, the performance meas- represented with their proportional the performance of a project portfolio
urement in this zone threatens the value in regard to the target. Another from a strategic standpoint. It is
achievement of portfolio objectives by requirement is that performance indi- intended to show the level of accom-
making the achievement more difficult cators must reveal the strategic value plishment of the portfolio’s strategic
to reach or rendering it uncertain. of the project with respect to the objectives based on two components:
Figure 2 synthesizes these concepts. objectives of the portfolio. For exam- (1) the performance level of projects
The representation of a KPI using a ple, it could be the weekly rate of deliv- and (2) their level of contribution to
graph is more useful than representing it ery of a new capability or the rate of key benefits, which are the internal
only as a number or with a color. The progress of a new technology develop- critical success factors of the portfolio.
graph allows the status of the project to ment. It could also be the schedule The first KPI for a project portfolio is
be seen immediately, the zone in which performance index if a reduced time to the measurement of the realization of
the project is located, and the trend to market is the benefit expected. A proj- key benefit, B, and it is expressed as
forecast where the project is going with ect may have different indicators follows:
respect to the target. Having all of this depending on which key benefit it is
a (KPI
m
information together at the same time, contributing to. In this case, the KPI KPIB ⫽ PB · CPB)
P ⫽1
managers may anticipate unacceptable must be distinguished regarding the
consequences by analyzing the causes of benefit. The second KPI is the measurement
this behavior and implementing action For example, of the achievement of an objective O,
plans for changing the trend of the and it is expressed as follows:
graph. A KPI has a definition in time, KPIPB ⫽ 0.85, means that the measurement
a (KPI
n
which depends on the period when the is at 85% of the target, and KPIO ⫽ B · CBO)
project is implemented. Then, it is KPIPB ⫽ 1.15, means that the measurement B=1

important to constantly validate the is surpassing the target by 15%. where


metric used by the KPI in order to remain where KPIPB ⫽ the performance metric of project P
flexible with changes and not become an contributing to key benefit B,
inhibitor when changes in the environ- KPIPB ⫽ the performance metric of project P KPIB ⫽ key performance indicator of key
ment or in the portfolio occur. contributing to key benefit B, and benefit B,
The KPIs proposed in this article P ⫽ the project in the stream project- KPIO ⫽ key performance indicator of objec-
are expressed by a rate. In other words, benefit-objective. tive O,

December 2010 ■ Project Management Journal ■ DOI: 10.1002/pmj 69


PAPERS
Measuring Portfolio Strategic Performance Using Key Performance Indicators

CPB ⫽ relative contribution of project P to respect to their contribution to the ben- Standard for Portfolio Management
key benefit B, efit realization or objective achieve- (Project Management Institute, 2008b)
CBO ⫽ relative contribution of key benefit B ment. It would be difficult to find a exhibits the value of using performance
to objective O, common unit to represent all contribu- data for analyzing variance and trends
P ⫽ project in the stream project-benefit- tions from different kinds of projects during the process of control and mon-
objective,
and benefits. Then, representing the itoring risks. On the other hand, the
O ⫽ objective in the stream project-bene-
contribution as a level of importance is Management of Risks: Guidance for
fit-objective,
B ⫽ key benefit in the stream project-ben-
easier and can be used for all kinds of Practitioners (Office of Government
efit-objective, projects and benefits. A pitfall of assess- Commerce, 2007) identifies key per-
n ⫽ total number of key benefits, and ing contributions in this manner is the formance indicators during the process
m ⫽ total number of projects in the port- use of subjectivity. However, subjectivi- of risk identification for monitoring
folio. ty is necessary for exploring fields that risks and opportunities in later stages.
can be very difficult to evaluate if a Performance monitoring allows for
The KPIO shows the level of
quantitative approach is used. The detecting materialized risks and oppor-
achievement of a portfolio objective,
employment of a relative importance tunities that were not identified before;
and using the scheme of Figure 2, it can
for assessing contributions facilitates their consequences influence the port-
be related to a status such as healthy, in
the process of distinguishing which folio performance in regard to the
alert, or in failure. Additionally, it
projects are more important for realiz- achievement of objectives. For instance,
shows if the current status of a portfo-
ing a key benefit and which key benefits materialized risks in a portfolio can be a
lio objective belongs to a risk or oppor-
are more important for achieving an shortage of specialized resources shared
tunity zone. If the portfolio objective
objective. The goal is not finding between projects or the passage of new
does not have a healthy status, it is
an exact value that represents a contri- legislation requiring the postponement
necessary to evaluate the urgency level
bution, but recognizing the most of projects and the addition of project
for reaction in order to enhance or mit-
important projects and benefits and work. These events delay benefits real-
igate the impact, depending on the
prioritizing them with respect to the ization or reduce the delivery of bene-
zone in which it stays. For instance, a
achievement of portfolio objectives. fits. The same negative influence hap-
critical maneuver margin may be
The model used in Figure 1 is a sim- pens with other kinds of risks such as
assessed for this purpose. KPIB and
ple representation of a portfolio. technical (changes in requirements,
KPIPB follow the same reasoning. Then,
Portfolios may be much more complex, problems developing a technology),
the execution of action plans is priori-
having several projects, benefits, and external (changes in the market,
tized based on the project status, the
objectives. The equations introduced in changes in customer needs), organiza-
project contribution to objectives, and
this article are generic and can be easi- tional (lack of funding, increase of proj-
the urgency level.
ly adapted. The authors are developing ect dependencies), or management
Discussion a tool based on these equations and (wrong estimations, lack of communi-
It is important to note that the KPIs concepts to monitor portfolios of proj- cation). All of these materialized events
proposed in this article are just an esti- ects. This tool allows for monitoring affect benefits realization having a sub-
mation of the impact that current proj- portfolios not only having several bene- sequent effect on the accomplishment
ect performances may produce on the fits and objectives, but also different of portfolio objectives. However, there
future realization of key benefits and levels; this tool will be introduced in an is a chance to mitigate the final nega-
objectives; they are not the current upcoming article. tive consequences on the achievement
measurement of that realization. This of objectives if first consequences on
characteristic allows an anticipated Monitoring Project Performance: benefits realization are detected and
reaction before undesirable perfor- Detecting the Materialization responses are quickly implemented.
mances of projects influence the final of Risks and Opportunities for The same approach may be used to
achievement of objectives. If managers Reducing or Enhancing Its enhance the positive consequences on
wait to measure at the time when bene- Influence on the Achievement the accomplishment of objectives by
fits and objectives are supposed to of Portfolio Objectives implementing responses aimed at the
occur, it would be too late to react in As expressed by Ritchie and Brindley profit of an outstanding performance.
order to correct any undesirable mea- (2007), risks are not only those that An abundance of specialized resources
surements. may yield a crisis or a failure, but also or funding may accelerate the benefits
The contribution of projects and those that may influence the ongoing realization or increase the delivery of
benefits is not measured in units. It is performance in terms of effectiveness benefits. As soon as the first conse-
based on the relative importance with and efficiency. Chapter 5 of the quences of the delivery of benefits are

70 December 2010 ■ Project Management Journal ■ DOI: 10.1002/pmj


detected by performance indicators, it and programs with the organization’s the base for developing the KPIs. We are
is possible to analyze which risks or strategy is validated. conscious that a project portfolio has
opportunities were materialized in 5. This approach also helps determine the characteristics of a complex system,
order to implement the most pertinent the contribution of each project, and it is not our intention to construct a
action plans for reducing or enhancing which is useful for certain portfolio deterministic view of the portfolio by
the influence on the final achievement management processes, such as the building this model. Contrary to this,
of objectives. selection and prioritization processes. the model symbolizes in a specific
point in time the dynamic strategic
Advantages and Disadvantages of On the other hand, some disadvan- dependences inside the portfolio and
Using the Approach Proposed tages can be detected. not a static cause-and-effect relation-
The advantages of using the approach 1. Benefits and objectives are frequent- ship expressed on a time frame.
proposed are the following: ly set in the long term; additionally,
1. It not only considers the current per- strategic benefits are often uncertain Conclusion
formance of projects. but also looks and intangible. This situation makes This article presents an approach for
ahead to forecast the achievement of it more difficult to accurately esti- developing key performance indicators
portfolio objectives. This fact allows mate when benefits and objectives (KPIs) for project portfolios, taking into
the implementation of action plans will be realized. account a strategic perspective. This
to improve performance, diminish- 2. Projects and benefits contribution development is made at two levels:
ing risks and enhancing opportuni- must be estimated in a qualitative measuring the realization of key benefits
ties to arrive at the final objectives. way. This fact adds uncertainty to the and measuring the achievement of port-
2. In spite of being difficult to plan values obtained with the KPIs. folio objectives. We have based our
when benefits may be realized, they 3. Some problems may arise when approach on the critical success factor
still need to be detailed, elaborating a implementing the approach pro- method in order to set the metrics
schedule and including it as part of posed to measure the strategic per- focused on objectives and consider the
the benefits realization plan. The formance of the project portfolio. An essential benefits in attaining them. This
approach presented in this article example of this is the lack of commit- article remarks on the importance of
helps to specify when benefits and ment from the people directly considering project performance moni-
objectives must be realized. It estab- involved in the portfolio’s develop- toring to detect the materialization of
lishes a specific time horizon in ment, because of the lack of appreci- risks and opportunities that influence
which the realization has an added ation of its advantages or because of the strategic performance of the portfo-
value, whether profiting from an the fear of punishment when the per- lio. Thanks to continuous monitoring
opportunity window or avoiding a formance of a project is in the risk and visualization of KPIs, anticipation is
risk window such as an economic zone. possible before a project performance
crisis. impacts the achievement of its objec-
3. It is difficult to find KPIs for project A solution to overcoming the first tives. The KPI visualization is built with
portfolios that measure the level of two disadvantages is by performing a the following concepts: opportunity and
achievement of portfolio strategic continuous validation of the values risk zones; healthy, in alert, and in failure
objectives. Most indicators found in assumed. On the other hand, intangible statuses; thresholds of acceptation; and
literature are based on costs, sched- benefits can be transferred to tangible a target. Managers may implement
ule, and deliverables, having the lim- using pertinent conversions. It is action plans for enhancing the positive
itations already discussed. Our con- important to compare the values consequences of good performance or
tribution proposes a strategic vision assumed with real data once these data for mitigating the negative conse-
that complements those indicators are available. It allows the rectification quences of bad performance. The
to have a more holistic view. of bad assumptions and the rendering approach presented in this article helps
4. Key performance indicators and the of resultant KPIs to be more effective. managers to consider portfolio monitor-
model of “project-benefit-portfolio” The model representing the “project- ing from a strategic standpoint.
streams can be used during the gate benefit-objective” streams must be Further research of this approach
reviews of programs and portfolios. continually verified in order to adapt it needs to be oriented toward its practi-
During a gate review, project and to the portfolio’s dynamic behavior cal validation. We also recommend the
program evaluations are performed and its environment. Objectives may development of a tool using the con-
to verify if expected benefits are met change, and projects may become cepts explored here in order to collect
as planned, lessons learned are with- annulated or postponed, all of which all the information in a single frame-
drawn, and the alignment of projects must be reflected in the model that is work, permitting easier monitoring of

December 2010 ■ Project Management Journal ■ DOI: 10.1002/pmj 71


PAPERS
Measuring Portfolio Strategic Performance Using Key Performance Indicators

the portfolio using key strategic per- Kerzner, H. (2006). Project manage- Rajegopal, S., McGuin, P., & Waller, J.
formance indicators. ■ ment best practices: Achieving global (2007). Project portfolio management:
excellence. Hoboken, NJ: Wiley. Leading the corporate vision. New York:
References Lefley, F. (2004). An assessment of vari- Palgrave Macmillan.
Alarcon, L. F., & Serpell, A. (1996). ous approaches for evaluating project Remenyi, D., Sherwood-Smith, M., &
Performance measuring, benchmark- strategic benefits: Recommending the White, T. (1997). Achieving maximum
ing and modeling of project perfor- strategic index. Management Decision, value from information systems: A
mance. Proceedings of the 5th 42, 850–862. process approach. Chichester, UK:
International Conference of the Lin, C., & Pervan, G. (2003). The prac- Wiley.
International Group for Lean tice of IS/IT benefits management in Richman, L. (2006). Improving your
Construction. large Australian organizations. project management skills. New York:
Anthony, N., Dearden, J., & Vancil, R. Information & Management, 41(1), AMACOM.
(1972). Management control systems. 13–24. Ritchie, B., & Brindley, C. (2007).
Homewood, IL: Richard D. Irwin. Morris, P. W. G., & Pinto, J. K. (2004). Supply chain risk management and
Cable, J. H., Ordonez, J. F., Wiley guide to managing projects. performance: A guiding framework for
Chintalapani, G., & Plaisant, C. (2004). Hoboken, NJ: Wiley. future development. International
Portfolio earned value management Office of Government Commerce. Journal of Operations & Production
using Treemaps. In Proceedings of the (2007). Management of risk: Guidance Management, 27, 303–322.
Project Management Institute Research for practitioners. London: The Rockart, J. F. (1979). Chief executives
Conference. Stationary Office. define their own data needs. Harvard
Chen, T. (1999). Critical success factors Parmenter, D. (2007). Key performance Business Review, 57(2), 81–93.
for various strategies in the banking indicators (KPI): Developing, imple- Saaty, T. L. (1980). The analytic hierar-
industry. International Journal of Bank menting, and using winning KPIs. chy process: Planning, priority setting,
Marketing, 17(2), 83–91. Hoboken, NJ: Wiley. resource allocation. New York and
Corporate “war rooms” plug into the Pillai, S. A., Joshi, A., & Rao, K. S. London: McGraw-Hill.
computer. (1976, August 23). Business (2002). Performance measurement of Sanchez, H., Robert, B., & Pellerin, R.
Week, pp. 65–67. R&D projects in a multi-project, con- (2008). A project portfolio risk-
Daniel, D. R. (1961). Management current engineering environment. opportunity identification framework.
information crisis. Harvard Business International Journal of Project Project Management Journal, 39(3),
Review, 39(5), 111–121. Management, 20, 165–177. 97–109.
De Feo, J. A., & Janssen, A. (2001). Pinto, J. K., & Rouhiainen, P. K. (2001). Seddon, P., Graeser, V., & Willcocks, L.
Implementing a strategy successfully. Building customer-based project orga- (2001). IT evaluation revisited: Plus ça
Measuring Business Excellence, 5(4), nizations. Hoboken, NJ: Wiley. change. Proceedings of the Eighth
4–6. Project Management Institute. European Conference on Information
Ghalayini, A. M., & Noble, J. S. (1996). (2008a). The standard for program Technology Evaluation, Oriel College,
The changing basis of performance management (2nd ed.). Newtown Oxford, UK (pp. 1–18).
measurement. International Journal of Square, PA: Author. Sinclair, D., & Zairi, M. (1995).
Operations & Production Management, Project Management Institute. Effective process management through
16(8), 63–80. (2008b). The standard for portfolio performance measurement, part III:
Giaglis, G. M., Mylonopoulos, N., & management (2nd ed.). Newtown An integrated model of total quality-
Doukidis, G. I. (1999). The ISSUE Square, PA: Author. based performance measurement.
methodology for quantifying benefits Project Management Institute. Business Process Re-engineering &
from information systems. Logistics (2008c). A guide to the project manage- Management Journal, 1(3), 50–65.
Information Management, 12(1/2), ment body of knowledge (PMBOK ® Tangen, S. (2004). Performance mea-
50–62. Guide)—Fourth edition. Newtown surement: From philosophy to prac-
Haponava, T., & Al-Jibouri, S. (2009). Square, PA: Author. tice. International Journal of
Identifying key performance indicators Quesada, H., & Gazo, R. (2007). Productivity and Performance
for use in control of pre-project stage Methodology for determining key Management, 53, 726–737.
process in construction. International internal business processes based on Thorp, J. (1998). The information para-
Journal of Productivity and critical success factors: A case study in dox: Realizing the business benefits of
Performance Management, 58, furniture industry. Business Process information technology. New York:
160–173. Management Journal, 13(1), 5–20. McGraw-Hill.

72 December 2010 ■ Project Management Journal ■ DOI: 10.1002/pmj


Venning, C. (2007). Managing portfo-
lios of change with MSP for pro- Hynuk Sanchez, Eng, has been involved in the Benoît Robert, Eng, holds a PhD degree in civil
grammes and PRINCE2 for projects. project management domain for the last 10 engineering. For 15 years, he worked as an engi-
London: The Stationary Office. years. He holds a PhD in industrial engineering, neer consulting in hydraulic and computer sci-
with a specialty in project management. His ence as well as an assistant professor for gradu-
Ward, J., Taylor, P., & Bond, P. (1996).
experience as a project manager in the automo- ate courses at the École Polytechnique de
Evaluation and realization of IS/IT
bile industry was focused on technological proj- Montréal. In 2004, he was named associate pro-
benefits: An empirical study of current
ects, including prototype testing and product fessor of the Department of Mathematics and
practice, European Journal of
development. His current research is oriented to Industrial Engineering at the École Polytechnique
Information Systems, 4, 214–225.
develop a risk management approach specifical- de Montréal. He is pursuing research activities
Williams, D., & Parr, T. (2004). ly written for the project portfolio management as director of Le Centre Risque & Performance
Enterprise programme management: domain. It includes the study of current risk (CRP), a research center he created in 2000 that
Delivering value. New York: Palgrave management approaches integrating strategic specializes in the study of interdependencies
Macmillan. management and complexity science. He is also and domino effects between several lifeline net-
Williams, D., & Parr, T. (2006). Enterprise a member of the Project Management Institute works. He teaches the management of techno-
programme management: Delivering and an active reviewer for the Project Management logical projects and the analysis of technological
value. New York: Palgrave Macmillan. Journal. risks in bachelor and graduate courses.

December 2010 ■ Project Management Journal ■ DOI: 10.1002/pmj 73

View publication stats

You might also like