Sere Tag cen
CSOs hg
Puasa es
ate mented
SUN TM ayaa
SCAN ca
Rome NCR hm
USING THE SPRAYED CONCRETE
Nea ae)
08 aDVANCE TUNNELS FOR
Geeta \e Relatee
ere iT etm tvd
reten
revit s D
erm
sey cue= SAFETY NEWS SPECIAL EDITION
LAUNCHING OF PRECAST BEAMS IN QUEENSWAY EXTENSION PROJECT
erty
eet
eee
ee
ete
PN eee
Se eee
Cee oad
the flyover across the railway
eee eeant en!
eS ee
Pee ees
een
eect
Risk Assessment and Hazard Identification &
Mitigation of Risks
At the begining ofthe project, the sks associated with the works
art of the callway line below the proposed
s located ina trough. Tere wasa possiblity
anes moved close tothe t09 ofthe slope
were analysed. The
Queensway Extension
of shoe fllure when
0 carry out the
twas made to the embankments along the stretch of the work zone
inching. To prevent slope failure, reinforcemen
As there was the possibilty of debris relling into the railway reserve
and on
o the tracks, debris fences were erected before the
commencement af any ground wrk to prevent loose earth a
from encroaching onto the railway Ine
All possible obstructions to the movement of cranes, suchas telegragh
poles and trees, were either removed or marked out clearly an the
‘ground. The positioning ofthe cranes then had to take into consideration
the obstructions that could nat be removed,
As the wark was across an operational rilway line where the tran
‘operations could nat be disrupted, the launching had to be executed
+ scheduled train services. The
putside the period of the regu
information on scheduled tran services vas obtained fram the operator
x h Melayu Berhad (TMB) and the work was scheduled
accordingly. There was however the possibilty of unscheduled services
during the right for transporation of goods, movement of maintenance
vehicles, ee, This information was only known to KIM, Clase ison
with KTMB was therefore necessary to take into consideration such
In adlition to working closely with KTMB on the unscheduled services,
cuts were stationed
Tanjong Pagar railway station, locate
site an at the Bukit Timah railway tation
five minutes from the w
welve minutes away, to provide early warning. Lookouts were also
stationed 500 metres away on both sides from the worksite to provide
last minute warning,
No erection of machinery platform or scaffolding was allowed within
ne railway reserve. The se itself was ako ver tight and only a arrow
corridor was available for a sas well a5 for
th
manoeuvring. As the delivery of beams could only be effected from
one side of the railway reserve, at some point t
passed over to the
bveams had to
sane on the other side, The transfer would
0 be made in mid-air over the railway line. Suitable cranes had to
ct
radi forthe traverse of the booms and the zane fr the passing of
fen the site constraints, The
ate the manoeuvre g
he beam had to be carefully calculated. The radi and the passing
zone were subsequently marked out on sit so that ground staff could
see itclearhySAFETY NEWS SPECIAL EDITION.
Planning on paper could only offer a two-dimensional overview of a
‘three-dimensiona problem. It was impartant to cheek onthe ground
whether wnat had been planned could be caried out effectively. The
planned positioning and movements were checked on site with the
contractor and thelr crane operators to confirm that it could be
achieved, and adjustments were made where necessary.
Emergency Planning and Exercise
‘An emergency response plan was implemented taking into account
‘the variaus pasible scenarias,e9. topping f eranes and beams into
the ralmay reserve ard the necessary ations to be taken The stenarios
and corrective actions to be taken were discussed in detal with the
contractor, sub-contractors and subsequently with Safety Division
Tre emergency respons plan was rehearsed onsite so all parties were
familiar withthe procedures, Machinery that woul be required to be
Used in the event of an emergeney such as breakers and excavators
vere kept on standby on the site
The emergency response plan was provided to the KTMB and their
Johor staff were briefed accordingly
Consultation with SCDF and MOM.
‘A-channel for communications was established with SCOF whose
services would be called upon in the event ofan emergency. SCDF
‘was briefed about the sensitivity ofthe works, the launching procedures,
the emergency scenarios and the response plan. SCOF officers visited
‘the site to familiarise themselves. As the works progressed and asthe
access routes changes, SCDF was kept updated,
The Ministry of Manpower (MOM) was also briefed on the works.
'MOM's approval was obtained to remove immesiately any fallen beam
or machinery within the ralay eserve without having to wait for
the arrival of MOM personel
Launching Operations
Tree cranes were used for the actual launching. The beams were
delivered to the site via the Queensway side and were picked up by
4 300-ton capacity fixed crane and a 100-ton capacity crawler crane
The function of the 200-ton crane was to bring one end ofthe precast
tbeam into the transfer zane. At this point 4 150-ton crawler crane
fn the other side of the reserve would receive the beam and the
transfer was carted out
To achieve the mid-air transfer without erecting any platform within
the railway reserve, specially fabricated man-cages were fixed onto
the precast beams to allow men to gain access and work on the
shackles necessary to effect the transfer. Several man-cages were
used to allow the men to walk along the beam after having climbed
Up into the man-cage
TMB cooperated by stationing their staff atthe worksite dung the
launching operation. They too kept in contact with ther colleagues
in the Johor and Tanjong Pagar ralway stations for information about
the movement of the trains and approximate remaining travel time
to reach the worksite. After every launching and casting work,
inspections were carried out with the KIMB staff to ensure thatthe
railway line was clear and in time forthe following days scheduled
train service. No launching of beams was carried during daylight
hours. Only preparatory and equipment maintenance work was dane
during this time.
Ini
‘The launching ofall the sisty-five precast beams was carried out
between 4 June and 20 August 2004. With goad planing, good risk
‘management, strict adherence to agreed procedures and with the
cooperation of KIMB, the work was accomplished without any accident
orincdent.
Nedumaran Ramasamy
Road ConstrationCONSTRUCTION OF MRT TUNNEL NEAR HOCK KEE HOUSE
ees)
eee)
Lebar (PYL)cut-and-cover section
Paes
SO ea ar HOCK KEE
Seer HOUSE
CE ee
ieee eg ed
oe nad
House, a five
in 1963 and founded on mostly
Cee a
m thee
Risk Assessment on Buildings
Before the commencement of construction works at the PYL south
cut-ande-cove section, the ground settlement contours
based on the combined effects af
developed
onstructng the retaining walls,
3, bored tunnelling and consolidation settlement
grouting, excavat
Based on this settlement profile, the influence zone {up to Smm
wen’) was determined and all buildings identified tobe within
1 were individually assessed
The affected buildings were assessed for damage based on caleulated
tensile strains. The classification on degree of severity fo
shown in the following table, Most buildings and structures are
considered to be of lot rik ifthe precited degre of damage is within
? iin and Coraing, 1988)
ategory of Oto 2 (8
Limiting fenste | Normal Degree Category of
Strain (06) of Severity Damage
0000 ~ 0980 Nestle °
0050 ~ 0075 Very Slight 1
0075 ~ 0180 Sight 2
0150 ~ 0300 Moderate 3
>0300 | Severe to Very Severe 4105
PYL(CCL)
Risk Management
The hazards asoriated with each construction activity were compiled
into a rik register to manitor the like haod and consequence af each
rise and the residual risks after the mitigation measures were
implemented. The risks assessed to affect Hock Kee House would be
excessive ground movernent due to exe
water tal
9 the b
fation works and lowered
ight cause excessive diferent ent
The method chosen to mitigate the rsks
is in turn
ilding structure
was to construct diaphragm walls to minimise migration of ground
water and preloading struts to minimise defermation of the éaphragn
wall, A comare implemented around
PYL south to measure the performance ofthe tem
10 compare against the design values
instruments would serve as an early indicator so th
measures could be implemented
deviation from the pre-determined values. Some of the contingency
The close monitoring of
quickly in the event of excessive
measures are sted below:
Additional stuts
Increase preload values
ocalse step excavation
Soil improvement
Recharge wells
Repait/propping of building structure
Backtl
Evaevate aeeupants from affected buildings
excavated atea
An effective line of communication was essential to ensure thatthe
ard timely desision could be made to
es. The flanchart be
monitoring data were asses
implemen the contingency mea
munication
3 reparting an temporary works monitoring,SAFETYNES SPECIAL EDITION,
Construction
Contractor
Submission of ly
iestument ings
t
Construction ofthe dlaphragm walls atthe PYL south eut-and-cover section commenced in
May 2003. The monitoring results showed thatthe settlement of Hock Kee House was less
‘than Som and was within the predicted range. However, in July 2003, cracks were observed
‘na column Site investigations proceeded and confirmed thatthe uilding was founded an
Aad ran | | tings ater than on ies sume inthe ial setlemen aah. The eegor af
comngeney Professional damage to Hock Kee House was re-classified to "Moderate", based on the re-analysis, A
a= decision was made toinstallan ado jt rot layer to stengten the temporary wor.
[After the completion of the addtional grouting works, exeavation atthe PYL south ut-and
cover section commenced in February 2004
assessnenof|
insoament readings
t
Petornanee
seceplle
Na
Area f= Yes
Work continues
(On 22 April 2004, a stop-work order was issued to Contract 823 ta re-check all temporary
works design, The stop-work oder was lifted in July 2008 on the basis thatthe temporary
works design would comply with the new requirements
White the re-design took place, the instruments at Hock Kee House showed a trend of
settlement even though excavation works had stopped atthe second strut level as shown
inthe gragh below,
Lines oF Communication for Reporting
‘on Temporary Works Monitoring
Settlement Markers at Hock Kee House (L2406 to L2408)
TTT
PHEPl Gill Habib
Setement Tend at Hock Kee House
To prevent further damage to Hock Kee House, the southern excavated
cul-and-cover section was backfilled in December 2004 as pat of the
Scheme to shorten the eut-and-caver section by 30m. During this
time LA engage two structural consultants to carry aut independent
checks on Hock Kee House, They recommended that the impact to
Hock Kee House could not be reduced to a significant level even with
the implementation of the shortening scheme. In order to ensure the
safety tothe occupants, Hock Kee House was acquired an August 2005
and demolished in November 2008.
erin
‘The impact of construction works to Hock Kee House depended very
‘much an the actual behaviour af the ground asthe works progressed.
‘A comprehensive instrumentation and monitoring regime provided
an early inaiation of ground behaviour to compare against the design.
Hazards to each construction activity identiied enabled contingeney
measures to be implemented in 2 timely manner when necessary.
With the completion of re-design tothe temporary work construction
had re-commenced in October 2005 as soon as Hock Kee House was
‘evacuated, New diaphragm walls had been installed and strutted
excavation works are naw in progress
Tan Ui Chaw
Project Engineer
‘ele Line‘SAFETY IN BUILDING THE FORT CANNING TUNNEL USING SPRAYED CONCRETE LINING METHOD
Introduction SCL Construction Sequence
The tunnel vided into top heading, bench and in
The length ofeach excavation round af top heading was Tm. Each top
heading was immediately closed witha temporary invert just before
‘dumpling, Bench and invert were excavated tagether at 2m per oun.
‘The support system was made up ofthe pe-suppor and primary ning
support. The pre-suoy de up of 40 numbers of grouted fore-
P panese as Al Ground Fastening (AGP.
Excavation tok place under the prtection of this pre-support umbrel
The p
of designs
1 system, known by the
‘of 300mm thik shoterete lining
2 layers of A1O welded
sat Tt longitudinal spacing
ngth 40N Imm rein
The Fort Canning Tunnel is the fi wire Fabric (WWF) with lattice gi
Using the Sprayed Concrete Lining (SCL) method. It is @ 350m long
tunnel built as part of a 500m new road to link the Stamford |e pe Ar sun
Road/Armenian Street junction to Penang Road towards Or
Road,
The three-lane road tunnel runs beneath two roads nal
Rise and Canning Walk The Fort Canning Hil i on one side of the
tunnel, and the Singapore History Museum (SHM) ison the other. The
‘tunnel when completed will provide a more direct nk and uninterupted
flow for taffe along Stamford Road towards Penang Road
180m ofthe Fort Canning Tunnel is constructed using the SCL method
The overburden above the
from dm to 9m. The SCL
rel i relatively shallow, ranging
els about 15m wide and 11m high.
inet
Ibtalaton of a eound fering AGH
. 5a B
Competed bench and nerSafety Cor ns
Thisis the frst oad tunnel in Singapore built using SCL method. is
big tunnel of 15x 115m fabout 135 ~ 145m2) as compared to crass
passage in rail tunnel, In view of issues related to cellanses of SCL
tunnels world-wide, eg, Heathrow Tunnel, the project veam studied
the Health & Safety Executive (HSE) publications "Safety of New
Austrian Tunrelling Method (NATM) Tunnels ~ A Review of Sprayed
Concrete Lined Tunnels and “The Collapse of NATM Tunnel at Heathrow
Airport’, and visited on-gaing and completed SCL. tunnels in Japan
before the commencement of excavation warks. The team identified
the following main rst:
= callapse of excavation, especially the crown
+ failure of tunnel face
= failure of shoterete fining
= settlement above ground and adjacent buildings
= water inflow into tunnel during excavation.
Risk managementinitigation measures were considered and taken at
design and construction stage
Design of the SCL excavation profile was carried out by Contractor's
consultants TYLinall Zeidler, using PHASE 20 software. comprehensive
review and additional analyses was carved out to ensure robustness
and completeness of the design, Contractor conducted adcitionalcheck
by Prof Lee Fook Hou using ABAQUS 30 software for low and high
coverourden eases. For an overall view, Contractor brought in Prot
[Nakagawa for Varaguehi Univesity to conduct review af the desig.
LTA inaukition engaged Prof Andrew White to arty out an independent
check who di the analsis using PLAXIS 30.
Tosuppor the design view, an intensive sol investigation was carried
out. series of boreholes along the tunnel alignment at staggered
tom cfe spacing on both sides was done, which produced
comprenensive sail profile identiying the different layers af residual
sels and locations of boulders
During the construction stage, a comprehensive instrumentation
‘maritaring plan was implemented with daly/wice daily monitoring
acation plan of comprehensive soi ivestiotion
frequency. At the ground surface above the top ofthe tunnel, arrays
of 10 points of ground settlement values at every 10m were monitored.
Within the tunnel, deformation of the crown, sidewalls and footings
at every $m were abo monitored. Coupled with the monitoring of the
instruments, visual observation ofthe excavated soil and the conditions
lof the open face were carried out dally to check the matching of the
soll types with the design parameters and sol profile
Contemotion of ol ioers /aropertes
In the daily excavation work, tit safety rules were implemented anc
safety measures were putin place to safeguard the safety of workers and
Supervisors. Ventilation duet ard fan with capacity of 700m'fmin was
installed asthe excavation face moved ahead, General fluorescent lights
‘wer installed a every Sm interval with emergency lights at every 50m
interval on standby. Emergency phone and alarm were aso installs in
‘he tunnel Designated access into and inside the tunnel was introduces
ta reduce the conflict of workers withthe dill jumbo and shoterete
machine pis lorie, ete working within the ight tunnel space. Fr access
into the tunnel a tunrel lly system was implemented and workers were
‘equipped with standard PPE as well as tight-fitting gas mast, er plugs
and goggles As the warks was carid out within a confined space area
aie quality checks were earied out at hourly interval,
Conclusion
Fort Canning Tunnel
celebrated its breakthrough
en 29 March 2006, The
bench and invert was finally completed on 5 April 2006. It became
the fist road tunnel in Singapore tobe built using the SCL method,
I was also completed without any falureleollapse and no major
construction aesdents. The safe and successful completion of the SCL
tunnel i possible because of careful risk management of all issues
pertaining to the investigation, planning, design, construction and
‘moritoring
Hor Kwai Yeo, Serio Engineer
Chao Eng Grok Poet anager
Road Developmen & ManagementADVANCE TUNNELS FOR PILE REMOVAL IN CIRCLE LINE CONTRACT 852
erty
The
ey
Sry
inthe
eens
ens
Overview of Construction of the Advance Tunnels
ach tunnel was excavated in two stages comprising a heading and an inve typical
advance length of tm. Probe drilling was catied out routinely to verity prevailing ground
conditions in advance of excavation and glass reinforced plastic forepoe arrays
ind conditions, Stel ples encountered within the confines:
tunnel envelope would be partially removed. The remaining section of steel ples would bi
removed by small hand-dug excavations afer completing the advance tunnels
Hazards Encountered
During the construction of the outer tunnel, consierabl inflow of water was encounters
about Bm away from the existing station, It was suspected thatthe ground was having
hydraulic connectivity to the bacefileand between the permanent station wall and the
mperary earth retaining system consisting of solder piles and timber lagging. Some
settlement ofthe NEL structures anc road viaduct was experienced. Tere mas a kelinoo
of further ground settlement ofthe surrounding ac
table if excavation was ta continue, Excavation temporarily halted so that 2
Solution could be worked out
Risk Management
a from LTA, the main contractor,
ask force, comprising represe
rs)
theexsting NEL tunnels At the same
Person (Supervision), Prfessianal Engineer (lemparary
tunnel designer and several specialist consultants of considerable experience, was assembled to evaluate the design of
n ex
ed mining man:
ne, the contactor increased the pool of expertise by appoint
senior tunnelling engineer fram the and grouting subcontractorSAFETY ENS SPECIAL EDITION.
2), Arisk workshop was conducted to identify all the ris associated with potential water ingress due
{o further excavation Subsequently a revised tunnel design and construction method was devised
to mitigate the hazards identified. The features ofthe re-design ae summarised a follows
‘Area of Concern ee as
Buck band sounding | Vere rouing and hozontl | Fst bck bar on the near se was
‘re cxsing sation wall | Gling angatecons ance | EEOE8 with vera jeteoutig whee
Pea sure ces was vale Secon cll
Sanat the frie was ately grating
rough ail ies.
‘il permeate features | Horna ailing and goutinecton | Grout was injected though horizontally
Underneath exiting station eile pes.
Geog genet eature | Block grouting ‘A gouted blk extending up to 12 ahead
(ove) of the tunnel face for seating permeable
features in the ground.
Unstable thinsoilcover | Selig ot hsalatn with rut | Stel ine rotted with non-retunvahes
between the turneteroun | neon pote ‘or grouting to creat a rot prtection for
andthe station tase sab te excavation,
Prleremovalfom TBM as | Enlarging tunnel size to cover full | SCL atvance tunnel e-