You are on page 1of 12

Technical claims brief

Monthly update – August 2010


Contents

Monthly update August 2010

News 1
Court of Appeal to rule on scope of
pure economic loss 1

Limiting recoverable defence costs in


criminal cases ruled unlawful 1

Ministry of Justice to investigate claims


management companies’ use of text
and e-mail 2

Costs 3
Costs penalties for lack of meaningful
negotiation: Alrahi v Ellis –
Runcorn County Court (2009) 3

Part 36 Rules clarified: Gibbon v


Manchester City Council; L.G. Blower
Specialist Bricklayer Ltd v Reeves
– Court of Appeal (2010) 4

Fraud 6
Amending a defence to allege fraud:
Hussain and Another v Sarkar and
Another – Court of Appeal (2010) 6

Liability 7
Highway Authority liable for creating
pedestrian hazard: Yetkin v London
Borough of Newham – Court of Appeal
(2010) 7

Quantum 8
Periodical payments, allowance for State
Funding: MS (A Protected Party ....)
v X and Y – High Court (2010) 8
News
Court of Appeal to rule on
scope of pure economic loss
The Court of Appeal is due to rule later this
month on whether losses suffered by the
users or owners of a defective product or
building should still be considered as pure
economic loss (not recoverable in tort)
rather than physical damage.

In the case of Linklater Business Services


v Sir Robert McAlpine and Others, ten
years after a major refurbishment of the
claimant’s offices metal pipe work which
was supposed to have been sealed to
protect it from water vapour was found
to have corroded. Linklater brought
proceedings against the main contractors
Sir Robert McAlpine who then brought in
their sub-contractors How Engineering Limiting recoverable defence himself from what might in some cases
who in turn brought in their sub-contractors costs in criminal cases ruled be wholly false accusations. It was most
Southern Insulation who had actually fitted unlawful unlikely that it had been the intention of
the insulation. Parliament when the 1985 Act was passed
In 2009 the Lord Chancellor implemented to allow the Lord Chancellor to make such a
Southern applied to have the claim against new regulations limiting the amount of costs change without Parliamentary scrutiny.
them struck out on the basis that Linklaters that a successful defendant in a criminal
loss was purely economic and could not case could recover from central funds. Comment: Pending the introduction of a
succeed. The application was heard in the Recoverable costs were limited to legal aid new scheme (subjected to Parliamentary
Technology and Construction Court by Mr rates leading to significant shortfalls in the scrutiny) defendant’s costs will presumably
Justice Akenhead who refused it on the costs recovered. be assessed under the old 1986 regulations.
grounds that the case raised important The removal of the 2009 regulations should
points of law which could be decided either The law society sought a judicial review assist insurers who have funded successful
way and because he was not convinced of the new regulations which they argued criminal defences for policyholders and who
that corrosion was “damage” for litigation breached the principle set out in the are seeking to recover their outlay.
purposes. The Court of Appeal will now rule Prosecution of Offenders Act 1985 section
on these issues. 16 (6) that a sum of money should be
provided which was reasonably sufficient to
Comment: Guidance from the Court compensate a successful defendant.
of Appeal will hopefully bring clarity to
a sometimes complex area of law but The Administrative Court has now ruled
their decision may not be welcomed by that the new regulations are unlawful.
defendants or their insurers if claimants are The regulations made a constitutionally
enabled to pursue claims for losses which important change by doing away with the
were previously unrecoverable. idea that a defendant ought not to have to
bear the (reasonable) costs of defending

1
Technical claims brief, monthly update – August 2010
Ministry of Justice at least made enquiries or purchased a
to investigate claims product from them in the past) is regarded
management companies’ use as a breach of regulation and is arguably
of text and e-mail in contravention of the Compensation Act
2006.
Post Magazine has reported that the
Ministry of Justice is understood to be Comment: Lord Young is to lead an
investigating the growing use of unsolicited investigation into the UK’s “compensation
text messages and e-mails by claims culture” and has promised to clamp down
management companies offering their on the advertising of claims recovery
services to recover damages for personal services. The appropriateness of his
injuries. A Royal Bank of Scotland insurance selection has been questioned however due
division study is reported as finding that to his major shareholding in the credit hire
around 15% of claims arose after claimants company Accident Exchange, an illustration
were contacted in this way. Contacting perhaps of how widespread the claims
personal mobile telephone accounts whose management industry has become and how
holders have not opted to use the services difficult it may be to reduce its influence.
of an accident management company (or

2
Technical claims brief, monthly update – August 2010
Costs
Costs penalties for lack of
meaningful negotiation: Alrahi
v Ellis – Runcorn County Court
(2009)
The claimant suffered moderate whiplash
type injuries after her car was struck
in the rear by the defendant’s car. The
defendant’s insurers conceded liability
and made a pre-issue Part 36 offer. The
claimant countered with two Part 36 offers
but these were rejected and the case went
to a hearing.

At trial the claimant was awarded £6,050


failing to beat the defendant’s Part 36 offer
of £6,750. The defendant argued that
the claimant should not even be awarded
predictive costs on the grounds that their
two Part 36 offers of £7,880 and £7,500
were both unrealistic and did not amount to
“negotiation” as required by the pre-action
protocol. They had also failed to disclose
any evidence in support of some items of
special damages claimed.

The judge agreed and penalised the


claimant’s behaviour by awarding only
two thirds of predictive costs (with
disbursements in full) to them and 8 per
cent interest on the defendant’s costs.

Comment: This case is an encouraging


example of the court applying sanctions
against a claimant who would not enter into
meaningful negotiations to settle their claim
short of a hearing.

Our thanks go to Berrymans Lace Mawer


who represented the defendant for giving us
details of this case. Leech and Co acted for
the claimant.

3
Technical claims brief, monthly update – August 2010
Part 36 Rules clarified: on a Part 36 basis of £2,500. The defendant a settlement cheque for £2,500 which
Gibbon v Manchester City did not initially accept the £2,500 offer but the claimant returned prior to issuing
Council; L.G. Blower Specialist made an offer slightly improved on their proceedings.
Bricklayer Ltd v Reeves – original one. The claimant refused this
Court of Appeal (2010) offer and the defendant eventually decided At first instance the judge held that the
to offer the claimant the £2,500 that she defendant was entitled to accept the
In these joined appeals the Court of Appeal had sought, again on a Part 36 basis. The claimant’s offer which had not been
considered a number of issues around claimant by this time however had decided withdrawn and awarded their costs from
the interpretation of Part 36 of the Civil that she would not accept £2,500 and the date of the offer. The claimant appealed
Procedure Rules (CPR) and issued useful rejected the defendant’s offer for this sum. arguing that the offer was no longer
guidance on the application of the rules. The defendant tried to formally accept the capable of acceptance under the common
claimant’s £2,500 offer in writing whereupon law principle that a rejected offer cannot
In Gibbon the claimant had injured herself the claimant’s solicitor advised them that it subsequently be accepted.
when she fell in the defendant’s school had been withdrawn. The defendant cited
playground. The defendant admitted liability CPR 36.9 (2) i.e. that a Part 36 offer may
and made a Part 36 offer. The claimant be accepted at any time unless a notice
rejected the offer and made a counter offer of withdrawal has been served and sent

4
Technical claims brief, monthly update – August 2010
The Court of Appeal held that Part 36.9(2) The Court of Appeal held that the award
was clear and that the court should only was materially more advantageous and
resort to common law principles in situations upheld the trial’s judge’s order on costs
where there was some ambiguity. The as being within his reasonable discretion.
rules clearly stated the manner in which an Whilst accepting that Carver was binding
offer should be withdrawn and this had not the Court of Appeal endorsed Lord
been done, there was no room in the rules Jackson’s criticisms of it in his review of civil
for the concept of implied withdrawal. The litigation for bringing uncertainty into the
acceptance of the offer was valid and the operation of Part 36. They commented that
costs order appropriate. cases where claimants beat Part 36 offers
by a small amount but were ruled to be
materially less advantageous should be rare.
“In a case where the offer has been
beaten by a very small amount Comment: In both these cases the Court
and there is clear evidence that the of Appeal confirmed that common law
successful party has suffered serious principles do not apply to Part 36 offers
adverse consequences as a result and that more than one offer may be open
of pursuing the case to judgement for acceptance at any given time. Parties
those (non financial) factors may be to litigation should be careful to formally
sufficient to outweigh success in withdraw offers if they do not wish to leave
pure financial terms but in my view these open for acceptance. Litigants should
such cases are likely to be rare.” also bear in mind that in judging the success
of the parties the courts will focus on the
Lord Justice Moore-Bick size of the award relative to the Part 36
offers in the majority of cases.

In Blower the claimant was a builder who


sued his customers for the cost of home
improvements which they had refused to
pay for. The defendants made three Part 36
offers at different times but later withdrew
all but the first. At trial the claimant beat the
defendants’ Part 36 offer although not by
a large amount. The judge at first instance
ordered the defendants to pay half the
claimant’s costs from the date that the later
two Part 36 offers were withdrawn. The
defendants appealed arguing in line with the
Court of Appeal decision in Carver v BAA
that although the settlement awarded was a
larger one than their Part 36 offer it was not
all things considered (stress, unrecoverable
costs etc) materially more advantageous.
The judge’s costs order was therefore too
generous to the claimant.

5
Technical claims brief, monthly update – August 2010
Fraud
Amending a defence to allege
fraud: Hussain and Another v
Sarkar and Another – Court of
Appeal (2010)
The two claimants alleged that they had
been injured when the car in which they
were passengers was struck in the rear by
a van. The insurers of the van suspected
that the accident was contrived but had
insufficient evidence to plead fraud. They
applied to the court for extra time to
investigate but were refused.

A week before trial the insurers (the second


defendants) having received additional
information believed that they had enough
circumstantial evidence to specifically plead
fraud and applied to the court to amend the
defence. The recorder again refused their fraud was not permitted. They should
application, found for the claimants at the not be penalised for the lateness of the
hearing and awarded damages for injury. application because they had not had
sufficient evidence to make it earlier and had
The insurers successfully appealed to explained their position to the court.
the Court of Appeal who set aside the
judgments and ordered a retrial. The Comment: Evidence of fraud often only
insurers had information that the driver of emerges close to trial and although each
the van worked for a company with which case must be decided on its facts, this
the three occupants of the car were all judgment should be helpful to insurers.
connected. The accident had also occurred The Court of Appeal has confirmed that a
in a place where it was unusual for the defendant should be allowed to make a late
claimants and defendants to be. Together application to amend provided that it is in
with the inconsistent financial information the interests of justice and they can give a
supplied by the claimants and their satisfactory explanation for the delay.
concealment of their relationship with the
van driver the circumstantial facts amounted
to a reasonable cause for believing that
the accident was staged. The recorder
had been wrong in his assessment that
the defendant’s application was essentially
no more than a “fishing expedition”. The
fundamental objective of the Civil Procedure
Rules was to do justice and the recorder
should have concluded that there was a
substantial risk that the insurers would
suffer injustice if their application to plead

6
Technical claims brief, monthly update – August 2010
Liability The Court of Appeal agreed that the judge
had misunderstood Gorringe which was
Highway Authority liable for not concerned with local authority acts so
creating pedestrian hazard: much as omissions. There was nothing
Yetkin v London Borough of said in Gorringe which undermined the
Newham – Court of Appeal well-established position that a person
(2010) who affected the safety of the highway
The claimant was run over by a car whilst would generally owe a duty of care to road
attempting to cross the second half of a users. Lord Brown’s comments in Gorringe
six lane dual carriageway from the central about highway authorities “enticing” a
reservation. She was using a traffic light motorist into an accident were merely an
controlled pedestrian crossing and her example of colourful language; there was
primary allegation was that the lights were no requirement for a created danger to
green in her favour and red against the amount to enticement. The local authority
motorist’s car. Her alternative submission did owe the claimant a duty of care. The
was that the local authority had created 75% contributory negligence finding was
a hazard by planting shrubs on the appropriate as a pedestrian who chose
central reservation which had grown to a to cross a three lane highway without
considerable height and blocked her view waiting for the lights to change in her favour
to the left. accepted a high degree of responsibility to
ensure that it was safe to do so.
At first instance the judge rejected the
claimant’s allegations against the motorist Comment: Local authorities who plant
finding that he had been proceeding shrubs near crossings should be careful
properly through a green light. The judge “...I entirely accept that the judge that they do not obstruct pedestrians’
went on to find that the shrubs did indeed took these passages from Gorringe views of the highway as on the basis of this
interfere with the claimant’s view of the road out of context and consequently judgment they are likely to be found partially
and had significantly contributed to the misunderstood them. He thought liable if this contributes to a subsequent
accident but having considered the House that they imposed additional accident.
of Lords ruling in Gorringe v Calderdale requirements on a claimant bringing
MBC he ruled that there were additional a conventional common law claim
requirements on a claimant bringing a against a highway authority for
common law claims against a highway creating a hazard on the highway.
authority and the authority did not therefore There are no such additional
owe the claimant a duty of care. The judge requirements.”
said that had the local authority been liable
he would have found 75% contributory Lady Justice Smith
negligence on the part of the claimant.

The claimant appealed arguing that the


judge had taken passages from Gorringe
out of context and had misunderstood
them. She also argued that the finding of
75% contributory negligence should be
reduced to 50%.

7
Technical claims brief, monthly update – August 2010
Quantum
Periodical payments,
allowance for State Funding:
MS (A Protected Party ....) v X
and Y – High Court (2010)
The claimant in this case suffered
catastrophic injuries in a road traffic accident
and was a protected party no longer having
mental capacity to manage the litigation.

He was awarded a lump sum of £350,343


(including general damages of £200,000)
plus Periodical Payments of £92,720 per
annum indexed to the 75th percentile of
the Annual Survey of Hours and Earnings
index number 6115. The claimant’s care
and accommodation were at the time of
the hearing being entirely met by the state.
The Consent Order approved by Master
Fontaine recognised this and stated that the
claimant would not receive any money by
way of Periodical Payments unless and until
he was required to pay for any part of his
care and /or accommodation himself.

Comment: Following the Court of Appeal


ruling in Peters v East Midlands S.H.A. (see
April 2009 brief) that claimants were not
obliged to apply to the state to fund care
and accommodation needs, defendants
found it increasingly difficult to obtain
any discount on lump sum settlements
in respect of state funding. Insurers have
however enjoyed more success with
settlements involving periodical payments
where claimants have proved more willing if
not to offset state funding in advance then
to at least agree to refund the amount of
any state payments received to insurers.
If state funding for the claimant continues
the insurers in this case will achieve a huge
saving.

8
Technical claims brief, monthly update – August 2010
Completed 23 July 2010 – Written by QIEL and the QBE Group have no
(and copy judgments and source material obligation to update this report or any
available from) John Tutton (contact no: information contained within it.
01245 272756, e-mail: john.tutton@uk.qbe.
com). To the fullest extent permitted by law,
QIEL and the QBE Group disclaim any
Disclaimer responsibility or liability for any loss or
damage suffered or cost incurred by you
This publication has been produced by
or by any other person arising out of or in
QBE Insurance (Europe) Ltd (“QIEL”).
connection with you or any other person’s
QIEL is a company member of the QBE
reliance on this publication or on the
Insurance Group.
information contained within it and for any
omissions or inaccuracies.
Readership of this publication does not
create an insurer-client, or other business
QBE Insurance (Europe) Limited and
or legal relationship.
QBE Underwriting Limited are authorised
and regulated by the Financial Services
This publication provides information about
Authority. QBE Management Services (UK)
the law to help you to understand and
Limited and QBE Underwriting Services (UK)
manage risk within your organisation. Legal
Limited are both Appointed Representatives
information is not the same as legal advice.
of QBE Insurance (Europe) Limited and QBE
This publication does not purport to provide
Underwriting Limited.
a definitive statement of the law and is not
intended to replace, nor may it be relied
upon as a substitute for, specific legal or
other professional advice.

QIEL has acted in good faith to provide an


accurate publication. However, QIEL and
the QBE Group do not make any warranties
or representations of any kind about the
contents of this publication, the accuracy or
timeliness of its contents, or the information
or explanations given.

QIEL and the QBE Group do not have


any duty to you, whether in contract, tort,
under statute or otherwise with respect to
or in connection with this publication or the
information contained within it.

9
Technical claims brief, monthly update – August 2010
QBE European Operations
Plantation Place
30 Fenchurch Street
London
EC3M 3BD
tel +44 (0)20 7105 4000
fax +44 (0)20 7105 4019
enquiries@uk.qbe.com
www.QBEeurope.com

2260/technicalclaimsbrief/august2010

QBE European Operations is a trading name of QBE Insurance (Europe) Limited and QBE Underwriting Limited. QBE Insurance (Europe) Limited and QBE Underwriting Limited
are authorised and regulated by the Financial Services Authority. QBE Management Services (UK) Limited and QBE Underwriting Services (UK) Limited are both Appointed Representatives
of QBE Insurance (Europe) Limited and QBE Underwriting Limited.

You might also like