You are on page 1of 3

REKAPITULASI TOTAL RENCANA ANGGARAN BIAYA

KEGIATAN : RENOVASI PEMBANGUNAN MASJID


PEKERJAAN : PEMBANGUNAN Plt LANTAI 1
LOKASI : PERUM KERSANEGARA KOTA TASIKMALAYA
TAHUN : 2019

NO. URAIAN PEKERJAAN JUMLAH HARGA ( RP )

A PEKERJAAN PERSIAPAN 1,300,000.00

B PEKERJAAN KONSTRUKSI
I PEK. TANAH DAN PONDASI 913,275.00
II PEK. DINDING DAN PLESTERAN 17,416,869.62
III PEK. BETON BERTULANG 184,365,981.26
IV PEK. KUSEN, PINTU DAN JENDELA DAN BESI 21,278,623.33
V PEK. Lt 1 4,654,896.00
VI PEK. PELAPIS LANTAI 21,718,075.00
VII PEK. PENGECATAN 3,754,874.75
VIII PEK. LISTRIK 2,614,000.00
C UPAH PEKERJAAN HARIAN 74,250,000.00
JUMLAH TOTAL ( A+B+C ) 332,266,594.96
DIBULATKAN 332,300,000.00
TERBILANG : TIGA RATUS TIGA PULUH DUA JUTA TIGA RATUS RIBU RUPIAH

Diperiksa, Dibuat,
Pengelola Teknis Kegiatan Konsultan Perencana
( PTK ) CV. ARCITEK SEMBILAN

GATOT RUDI ROMDONI


Koordinator Pembangunan Direktur

Mengetahui/Menyetujui, Mengetahui,
Pejabat Pelaksana Teknis kegiatan
( PPK ) ( PPTK )

BENI
no Ketua Pelaksana
RINCIAN RENCANA ANGGARAN BIAYA
KEGIATAN : RENOVASI PEMBANGUNAN MASJID
PEKERJAAN : PEMBANGUNAN Plt LANTAI 1
LOKASI : PERUM KERSANEGARA KOTA TASIKMALAYA
TAHUN : 2019

KODE HARGA SATUAN


NO. URAIAN PEKERJAAN VOLUME SAT. JUMLAH HARGA (RP)
(RP)
ANALISA
1 2 3 4 5 6 7

A PEKERJAAN PERSIAPAN
1 Pas. Papan Nama Kegiatan ex baneer DIHITUNG 1.00 unit 300,000.00 300,000.00
2 Pengukuran/uitzet lokasi pekerjaan DIHITUNG 1.00 Ls 500,000.00 500,000.00
3 Perancah/steger bambu DIHITUNG 1.00 Ls 500,000.00 500,000.00
JUMLAH 1,300,000.00

B PEKERJAAN KONSTRUKSI
I PEK. TANAH DAN PONDASI

1 Pek. Galian tanah u/ pondasi 12.00 M3 64,487.50 773,850.00

2 Pek. Urugan kembali dipadatkan A.2.3.1.9 3.00 M3 46,475.00 139,425.00

JUMLAH 913,275.00
II PEK. DINDING DAN PLESTERAN
1 Pas. Dinding bata adk. 1pc : 5ps A.4.4.1.10 63.00 M2 108,656.68 6,845,370.84
2 Pas. Plesteran dinding adk 1pc : 5ps A.4.4.2.5 126.00 M2 51,813.78 6,528,536.78
3 Pas. Acian Plesteran A.4.4.2.27 126.00 M2 32,087.00 4,042,962.00
JUMLAH 17,416,869.62
III PEK. BETON BERTULANG
1 Pas. Pondasi felkep 1m x 1.5 m adk. 1pc : 2ps : 3krl
* Beton k250 A.4.1.1.2 12.00 M3 900,000.00 10,800,000.00
* Besi beton polos/urill A.4.1.1.5 420.00 Kg 13,779.70 5,787,474.00
* Bekisting A.4.1.1.2 32.00 M2 111,969.00 3,583,008.00
Sub Jumlah 20,170,482.00
2 Pas. Kolom Utama 40x40cm adk. 1pc : 2ps : 3krl
* Beton adk. 1pc : 2ps : 3krl A.4.1.1.2 5.78 M3 900,000.00 5,202,000.00
* Besi beton polos/urill A.4.1.1.5 537.00 Kg 13,779.70 7,399,698.90
* Bekisting A.4.1.1.3 52.00 M2 163,922.00 8,523,944.00
Sub Jumlah 21,125,642.90
3 Pas. Kolom 15/15 cm adk. 1pc : 2ps : 3krl
* Beton k 250 A.4.1.1.2 1.00 M3 900,000.00 900,000.00
* Besi beton polos/urill A.4.1.1.5 228.00 Kg 13,779.70 3,141,771.60
* Bekisting A.4.1.1.3 2.00 M2 163,922.00 327,844.00
Sub Jumlah 4,369,615.60
4 Pas. Balok Slop 20 x 40 adk. 1pc : 2ps : 3krl
* Beton adk. 1pc : 2 ps : 3 krl A.4.1.1.2 3.13 M3 900,000.00 2,821,250.00
* Besi beton polos/urill A.4.1.1.5 428.00 kg 13,779.70 5,897,711.60
* Bekisting A.4.1.1.4 382.00 m 166,397.00 63,563,654.00
Sub Jumlah 72,282,615.60
5 Pas. Ring Balk 12/20 cm adk. 1pc : 2ps : 3krl
* Beton k 250 A.4.1.1.2 900,000.00 -
* Besi beton polos/urill A.4.1.1.5 361.00 Kg 13,779.70 4,974,454.15
* Bekisting A.4.1.1.4 31.28 M2 166,397.00 5,204,898.16
Sub Jumlah 10,179,352.31
6 Pas. Plat Lt 1 tbl 12 cm adk. 1pc : 2ps : 3krl
* Beton k 250 A.4.1.1.2 13.00 M3 900,000.00 11,700,000.00
* Besi beton polos/urill A.4.1.1.5 1,274.00 Kg 13,779.70 17,555,337.80
* Bekisting A.4.1.1.4 110.00 M2 166,397.00 18,303,670.00
Sub Jumlah 47,559,007.80
7 Pas. Plat Tangga adk. 1pc : 2ps : 3krl
* Beton k250 A.4.1.1.2 2.00 M3 900,000.00 1,800,000.00
* Besi beton polos/urill A.4.1.1.5 239.00 Kg 13,779.70 3,293,348.30
* Bekisting A.4.1.1.4 11.00 M2 245,322.00 2,698,542.00
Sub Jumlah 7,791,890.30
8 Pas. Plat Bordes Tangga adk. 1pc : 2ps : 3krl
* Beton k 250 A.4.1.1.2 0.17 M3 900,000.00 155,520.00
* Besi beton polos/urill A.4.1.1.5 25.73 Kg 13,779.70 354,514.27
* Bekisting A.4.1.1.4 1.44 M2 262,042.00 377,340.48
Sub Jumlah 887,374.75
JUMLAH 184,365,981.26
IV PEK. KUSEN, PINTU DAN JENDELA DAN BESI
1 Pas. Pintu alumunium Type P1 Dihitung (P1) 2.00 Unit 3,025,531.73 6,051,063.47
2 Pas. Pintu alumunium Type P2 Dihitung (P2) 1.00 Unit 1,980,286.30 1,980,286.30
3 Pas. Jendela alumunium Type J1 Dihitung (J1) 4.00 Unit 2,824,640.64 11,298,562.55
4 Pas. Bouvenlight alumunium Type BV1 Dihitung (BV) 2.00 Unit 974,355.51 1,948,711.01
JUMLAH 21,278,623.33
V PEK. Lt 1
1 pas.plester lantai 1 lt 1.80 M2 350,000.00 630,000.00
2 Pas. pipa A.4.5.2.1 60.00 M 25,000.00 1,500,000.00
3 Pas. bata merah 1m A.4.5.2.2 36.00 M' 70,136.00 2,524,896.00
JUMLAH 4,654,896.00
VI PEK. PELAPIS LANTAI
1 Pas. Urugan pasir bawah lantai A.2.3.1.11 9.00 M3 139,975.00 1,259,775.00
2 Pas. Lantai keramik 60 x 60 cm luar A.4.4.3.3 25.00 M2 168,700.00 4,217,500.00
3 Pas. Lantai keramik 60 x 60 cm dalam A.4.4.3.3 90.00 M2 168,700.00 15,183,000.00
4 Pas. Lantai keramik 30 x 30 cm warna tangga ( anti selip ) A.4.4.3.2 6.00 M2 176,300.00 1,057,800.00
JUMLAH 21,718,075.00
VII PEK. PENGECATAN
1 Cat dinding baru A.4.7.1.3. 65.00 M2 17,997.10 1,169,811.50
2 Cat Lisplak A.4.7.1.1. 19.00 M2 37,298.25 708,666.75
3 Cat plafond A.4.7.1.5. 90.00 M2 20,848.85 1,876,396.50
JUMLAH 3,754,874.75
VIII PEK. LISTRIK
1 Pas. Penyambungan Instalasi dari sumber terdekat upah bahan 1.00 Ls 150,000.00 150,000.00
2 Pas. Instalasi cahaya sek. kabel prima NYM 2 x 2.5 mm upah bahan 12.00 Ttk 100,000.00 1,200,000.00
3 Pas. Instalasi stop kontak sek. kabel prima NYM 3 x 2.5 mm upah bahan 4.00 Ttk 115,000.00 460,000.00
4 Pas. Lampu fiting upah bahan 12.00 Bh 57,000.00 684,000.00
5 Pas. Saklar ganda upah bahan 4.00 Bh 15,000.00 60,000.00
6 Pas. Stop kontak upah bahan 4.00 Bh 15,000.00 60,000.00
JUMLAH 2,614,000.00