ALLPILE 6
VERTICAL ANALYSIS SUMMARY OUTPUT
Copyright by CivilTech Software 2005
www.civiltech.com
(425) 453-6488 Fax (425) 453-5848
*****************************************************************
Licensed to
Date: 9/13/2019 File: E:\1. Data Proyek\04. Data Proyek 2019\04. DED MALARKO\DED
MALARKO.alp

Title 1: Trestel DED MLRK


Title 2:

TOTAL LOADS:
Vertical Load, Q: 1000.0 -kN
Load Factor for Vertical Loads: 1.0
Loads Supported by Pile Cap: 0 %

PILE PROFILE:
Pile Length, L= 42.0 -m
Top Height, H= 6.5 -m
Slope Angle, As= 0.0
Batter Angle, Ab= 0.00 Batter Factor, Kbat= 1.00

SINGLE PILE:
Deduction factor due to Group Effect, R= 1.00
Vertical Load= 1000.00 -kN

Single Pile Vertical Analysis:


Results:
Total Ultimate Capacity (Down)= 7993.04-kN, Total Ultimate Capacity (Up)=
2802.28-kN
Total Allowable Capacity (Down)= 2664.35-kN, Total Allowable Capacity (Up)=
934.09-kN
At Work Load= 1000.00-kN, Settlement= 0.38318-cm
At Work Load= 1000.00-kN, Secant Stiffness Kqx= 2609.75-kN/-cm
At Allowable Settlement= 2.500-cm, Capacity= 4513.46-kN
Work Load, 1000.00-kN, OK with the Capacity at Allowable Settlement= 2.50-cm,
Capacity= 4513.46-kN
Work Load, 1000.00-kN, OK with the Allowable Capacity (Down)= 2664.35-kN

____________________________________________
FACTOR OF SAFETY:
FSside FStip FSuplif FSweight
3.0 3.0 3.0 3.0

Note: If program can't find result or the result exceeds the up limits. The result
shows 9999.