You are on page 1of 95

DAFTAR SEWA P E R A L A T AN

SUMBER DATA : PASARAN B E BAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI NOPEMBER 2015

HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM
(Rp) (Rp)

1 Dump Truck 3 ton Jam 80,000 115,000

2 Dump Truck 9 ton Jam 145,000 160,000

3 Truk Bak Terbuka Engkel Jam 160,000 165,000

4 Truk Tanki Air Jam 250,000 265,000

5 Bulldozer 100 - 150 hp Jam 600,000 650,000

6 Motor Grader Jam 575,000 585,000

7 Wheel Loader Jam 225,000 250,000

8 Excavator Jam 590,000 610,000

9 Crane 35 ton Jam 525,000 550,000

10 Flat Bed Truck jam 380,000 400,000

11 Baby Roller / Pedestrian Jam 100,000 110,000

12 P.Tire Roller 8 - 10 ton Jam 430,000 460,000

13 Baby Roller jam 50,000 60,000

14 Vibrator Roller self 7 ton Jam 460,000 500,000

15 Pile Driver / Hammer jam 140,000 150,000

16 Water Pump Jam 35,000 40,000

17 Asphalt Sprayer Jam 125,000 135,000


18 Pick Up single cabin Jam 55,000 60,000

19 A M P Jam 5,000,000 5,150,000

20 Asphalt Finisher Jam 320,000 330,000

21 Concrete Vibrator Jam 50,000 55,000

22 Compressor Jam 280,000 290,000


23 Concrete Mixer 0,125m3 Jam 70,000 75,000

24 Concrete Cutter jam 32,500 40,000

25 Stamper Jam 35,000 40,000

26 Genset 5-25kva+bbm Jam 160,000 40,000

27 Alat Pengecat Marka Jam 300,000 320,000

28 Mesin Las jam 180,000 200,000

29 Stone Crusher jam 800,000 800,000


DAFTAR SEWA P E R A L A T AN

EDISI NOPEMBER 2015

KET.
DAFTAR U PAH PE K E R JA

SUMBER DATA : PASARAN B E BAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI NOPEMBER 2015

HARGA
NO. URAIAN PEKERJA SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 55,000 65,000

2 Mandor Hr 75,000 90,000

3 Tukang listrik Hr 75,000 85,000

4 Tukang kayu Hr 75,000 85,000

5 Kep. tk. kayu Hr 85,000 95,000

6 Tukang batu Hr 75,000 85,000

7 Kep. tk. batu Hr 85,000 95,000

8 Tukang besi Hr 75,000 85,000

9 Kep. tk. besi Hr 85,000 95,000

10 T u k a n g c a t Hr 75,000 85,000

11 K e p . t k . c a t Hr 85,000 95,000

12 T u k a n g p l i t u r Hr 75,000 85,000

13 T u k a n g j a l a n Hr 60,000 65,000

14 T u k a n g g a l i Hr 60,000 65,000

15 Tukang masak aspal Hr 60,000 65,000

16 T k . l e i d e n g Hr 75,000 85,000

17 M a s i n i s Hr 150,000 175,000

18 P e m b . M a s i n i s Hr 100,000 110,000

19 P e n j a g a a p i Hr 50,000 65,000

20 P e n j a g a m a l a m Hr 60,000 65,000

21 Sopir Hr 150,000 165,000

22 Pembantu Sopir Hr 100,000 110,000

443255086.xls 95 daftar upah tenaga kerja


DAFTAR HARGA SATUAN BAHAN BANGUNAN

SUMBER DATA : PASARAN BEBAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI NOPEMBER 2015

HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)

I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 160,000 170,000
Bulat Belah m3 180,000 190,000
Pecah 10/15 m3 200,000 210,000
Pecah 5/7 m3 210,000 230,000
Pecah 3/5 m3 230,000 250,000
2 KERIKIL Timbun m3 120,000 130,000
Sawur / Koral m3 240,000 260,000
Beton 0,5/1 m3 260,000 300,000
Beton ,1/2 m3 280,000 310,000
Beton ,2/3 m3 280,000 325,000
Biasa m3 125,000 140,000
Tras Giling m3 215,000 290,000
3 BATU BATA ex lokal bh 450 500

4 PASIR Urug m3 120,000 150,000


Pasang m3 225,000 270,000
Beton m3 320,000 350,000
5 TANAH Padas m3 100,000 125,000
Liat m3 110,000 120,000
6 KAPUR Pasang m3 250,000 310,000
Semen Merah m3 175,000 185,000
7 PORTLAND CEMENT
Merk I 40 kg zak 50,000 52,000
Merk I 50 kg zak 64,000 66,000
Merk II 40 kg zak 51,000 54,000
Merk II 50 kg zak 65,000 67,000
Semen Putih 40 kg zak 62,000 65,000
Semen Putih 50 kg zak 85,000 90,000
Semen warna kg 15,000 18,000

II BAHAN PENUTUP ATAP

1 SIRAP (100 lbr) pak 185,000 190,000

2 GENTENG BETON Genteng Beton Warna standard bh 6,000 7,000


Genteng Beton Warna Special bh 9,500 10,500
Genteng Beton Warna Khusus bh 14,000 15,200
Kerpus Beton Warna Standard bh 8,500 10,000
Kerpus Beton Warna Special bh 11,500 12,000
Kerpus Beton Warna Khusus bh 13,000 13,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
3 GENTENG TANAH LIAT
Vlaam/Plentong bh 2,200 2,400
Kodok bh 2,900 3,200
Kodok Glasur bh 4,000 4,250
Nok kerpus Kodok bh 6,500 6,800
Nok kerpus Kodok Glasur bh 8,000 8,500
Plentong super besar 18 bh/m2 bh 5,100 5,350
Nok kerpus plentong super bh 9,000 9,200
4 GENTENG KACA
Vlaam tebal 2 mm bh 10,000 12,500
Vlaam tebal 3 mm bh 12,000 15,000
Kodok tebal 2 mm bh 10,000 12,500
Kodok tebal 3 mm bh 13,000 17,500

5 ASBES GELOMBANG BESAR


. 200 cm X 102 cm X 5 mm bh 80,000 90,000
. 225 cm X 102 cm X 5 mm bh 93,000 98,000
. 250 cm X 102 cm X 5 mm bh 103,000 108,000
. 200 cm X 102 cm X 6 mm bh 92,000 95,000
. 225 cm X 102 cm X 6 mm bh 95,000 100,000
. 250 cm X 102 cm X 6 mm bh 105,000 110,000
Asbes Gelombang Kecil
. 150 cm X 105 cm X 4 mm bh 42,500 50,000
. 180 cm X 105 cm X 4 mm bh 51,000 57,000
. 210 cm X 105 cm X 4 mm bh 60,000 65,000
. 240 cm X 105 cm X 4 mm bh 68,000 75,000
. 270 cm X 105 cm X 4 mm bh 77,000 85,000
. 300 cm X 105 cm X 4 mm bh 85,000 95,000
ONDULINE : 95 cm x 200cm x 0.3mm lbr 140,000 150,000
ONDUVILLA : 40cm x 106 cm x 0,3mm lbr 75,000 85,000
NOK Jabes nok
. Kerpus Genteng bh 29,000 35,000
. Stel Besar bh 45,000 50,000
. Paten Besar bh 43,000 47,000
Nokstel gelombang harflex
. Stel Besar bh 44,000 48,000
. Patent Besar bh 27,000 30,500
. Plat besar bh 51,000 55,000
NOK UNT ONDULINE & ONDUVILLA
Ukuran 50cm x 50 cm x 0,3mm lbr 100,000 110,000
6 ASBES PLAT
. 100cm X 100 cm X 3 mm bh 16,000 17,000
. 100cm X 100 cm X 4 mm bh 18,000 20,000
. 50 cm X 200 cm X 3 mm bh 14,000 15,000
. 40 cm X 200 cm X 3 mm bh 13,000 14,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
FIBER PLAT uk. 100cm x 100cm x 4mm lbr 25,000 27,000
unt Plafond uk. 120cm x 240cm x 4mm lbr 66,000 70,000
uk. 122cm x 244cm x 4mm lbr 68,000 72,000
GRC BOARD uk.122cm x 244cm x 5mm lbr 100,000 108,000
uk.122cm x 244cm x 6mm lbr 125,000 132,000
uk.122cm x 244cm x 8mm lbr 185,000 192,000
uk.122cm x 244cm x 10mm lbr 245,000 260,000
7 FIBRE GLASS (JABES)
180 X 92 cm bh 48,000 75,000
200 X 92 cm bh 56,000 85,000
250 X 92 cm bh 64,000 75,000
180 X 105 cm bh 70,000 90,500
210 X 105 cm bh 70,000 105,000
250 X 105 cm bh 95,000 120,000
8 SENG PLAT
BJLS 0,18 lebar 55 cm m' 14,000 25,000
BJLS 0,20 lebar 55 cm m' 25,000 28,000
BJLS 0,28 lebar 55 cm m' 26,000 28,000
BJLS 0,30 lebar 55 cm m' 27,500 31,000
9 SENG GELOMBANG
BJLS 0,18 panjang 180 cm lbr 45,000 55,000
BJLS 0,20 panjang 180 cm lbr 48,000 57,000
BJLS 0,30 panjang 180 cm lbr 54,000 67,000
BJLS 0,40 panjang 180 cm lbr 72,000 75,000
III . B A H A N K A Y U
1 JATI Papan m3 22,000,000 23,000,000
Balok/pesagen m3 20,000,000 20,500,000
2 KAMPER Papan m3 7,600,000 7,800,000
Balok/pesagen m3 6,900,000 7,500,000
3 KRUING Papan m3 5,200,000 6,500,000
Balok/pesagen m3 4,800,000 5,550,000
4 MERANTI Papan m3 4,800,000 5,100,000
Balok/pesagen m3 4,500,000 4,600,000
5 LANAN Papan m3 2,050,000 3,290,000
Balok/pesagen m3 2,000,000 2,100,000
6 BENGKIRAI Papan m3 9,800,000 10,000,000
Balok/pesagen m3 9,375,000 9,600,000
7 DOLKEN Sedang 8 x 10 x 400 cm bt 18,000 20,000
Kecil 6 x 7 x 400 cm bt 16,000 18,000
Besar 10 x 12 x 400 cm bt 28,000 32,000
Kayu cetakan m3 1,850,000 2,200,000
Kayu bakar m3 150,000 170,000
Bambu bt 10,000 11,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
IV . BAHAN PENUTUP DINDING / LANTAI
1 UBIN (TEGEL BIASA)
PC polos 30 X 30 cm m2 34,000 36,000
20 X 20 cm m2 32,000 34,000
PC warna 30 X 30 cm m2 45,000 46,000
20 X 20 cm m2 40,000 42,000
Teraso 30 X 30 cm m2 52,000 56,000
2 TEGEL PLINT
PC warna 10 X 20 cm bh 5,200 5,500
PC abu-abu 15 x 20 bh 5,100 6,000

3 POLIS UBIN Lantai/badan m'


Plint m'
Trap m'

4 UBIN PORSELIN
Lokal 11 X 11 putih dos 42,000 43,000
11 X 11 warna dos 45,000 46,000
Lokal 15 X 15 putih dos 45,000 47,500
15 X 15 warna dos 46,000 49,000
5 MOZAIK PORSELIN
10 X 20 cm m2 48,000 52,000
15 X 15 cm m2 48,000 52,000
20 X 20 cm m2 48,000 55,000
20 X 25 cm m2 49,000 56,000

6 Keramik 30 X 30 cm m2 52,000 57,000


20 X 20 cm m2 54,000 56,000
33 x 33 cm m2 52,000 58,000
25 x 25 cm m2 51,000 55,000
15 x 20 cm m2 52,000 57,000
2,250 2,500
7 Parquet Jati m2 195,000 210,000
8 Batu Paros m2 95,000 102,000
9 Batu Tempel Hitam m2 98,000 102,000
10 GRANITO 40 x 40 cm m2 220,000 410,000
30 x 30 cm m2 250,000 450,000
11 Marmer m2 475,000 480,000
V.BAHAN CETAK
1 BUIS BETON Ø 10 cm - 100 cm bh 31,000 35,000
Ø 20 cm - 100 cm bh 36,000 45,000
Ø 30 cm - 100 cm bh 58,000 70,000
Ø 50 cm - 100 cm bh 102,000 130,000
Ø 60 cm - 100 cm bh 165,000 190,000
Ø 70 cm - 100 cm bh 185,000 225,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
U 10 cm - 100 cm bh 22,000 23,000
U 15 cm - 100 cm bh 30,500 35,000
U 20 cm - 100 cm bh 35,000 45,000
U 30 cm - 100 cm bh 42,000 55,000
U 50 cm - 100 cm bh - -
2 LUBANG ANGIN (ROSTER) PC + PASIR
10 X 20 cm bh 5,600 7,500
20 X 20 cm bh 6,300 8,000
25 X 25 cm bh 6,800 8,500
30 X 30 cm bh 7,200 9,000
15 X 25 cm bh 7,500 8,200
15 X 30 cm bh 7,500 8,500
VI . B A H A N B E S I
1 BESI BETON besi beton polos kg 9,500 10,500
besi beton prestress kg 16,500 17,000
besi beton ulir kg 12,500 13,000

2 BESI PLAT Besi Strip kg 12,500 13,500

3 BESI PROFIL Besi Profil kg 12,800 13,600


a BAJA RINGAN
GALVALUME lebar : 7,5cm tebal : 1mm btg 125,000 panj : 6 m
type CT 75 lebar : 7,5cm tebal : 0.75mm btg 85,000 panj : 6 m
lebar : 7,5cm tebal : 0,65mm btg 80,000 panj : 6 m
b type RT 12 tinggi : 3,5 cm, tebal : 0,45mm btg 45,000 panj : 6 m
type RT 10 tinggi : 3,0 cm, tebal : 0,45mm btg 40,000 panj : 6 m
c HOLLOW GALVANIS LIPAT
tinggi 2 cm; tebal : 0,4mm btg 22,000 25,000 panj : 4 m
tinggi 4 cm; tebal : 0,4 mm btg 28,000 30,000 panj : 4 m
4 JARING - JARING BAJA
Diameter 4 - 15 kg 15,000 15,500
Diameter 6 - 15 kg 15,000 15,750
Kawat Bronjong kg 9,500 10,000
5 BESI SIKU L 40 X 40 X 4 btg 134,000 140,000
L 50 X 50 X 5 btg 205,000 220,000
L 60 X 60 X 6 btg 300,000 310,000

6 KAWAT - Ikat beton/bendrat kg 14,500 16,500


- Harmonika 12 X 45 mm m2 20,000 25,000
- Harmonika 12 X 24 mm m2 21,000 27,000
- Harmonika 14 X 30 mm m2 20,000 26,000
- Harmonika 14 X 35 mm m2 19,000 26,000
- Kawat Nyamuk Nylon m2 9,000 10,000
- Kawat Kasa m2 13,000 17,000
- Saringan pasir m2 13,500 17,500
- Kawat loket m2 14,000 17,500
- Kawat duri rol 110,000 135,000
- Kawat bronjong kg 20,000 21,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)

VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 26,000 35,000 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 32,000 40,000 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 44,000 50,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 60,000 69,000 panjang 6 m
Pipa PVC DN 63 ( 2" ) btg 95,000 112,000 panjang 6 m
Pipa PVC DN 90 ( 3" ) btg 210,000 260,000 panjang 6 m
Pipa PVC DN 110 ( 4" ) btg 300,000 325,000 panjang 6 m
Pipa PVC DN 160 ( 6" ) btg 625,000 650,000 panjang 6 m
Pipa PVC DN 200 ( 8" ) btg 950,000 1,100,000 panjang 6 m
Pipa PVC DN 250 ( 10" ) btg 1,400,000 1,500,000 panjang 6 m
Pipa PVC DN 315 ( 12" ) btg 2,050,000 2,100,000 panjang 6 m

2 Pipa Medium B Galvanis - SII


Pipa Medium B Galvanis DN ½" btg 65,000 110,000 panjang 6 m
Pipa Medium B Galvanis DN 25 ( ¾" ) btg 75,000 150,000 panjang 6 m
Pipa Medium B Galvanis DN 32 ( 1" ) btg 95,000 190,000 panjang 6 m
Pipa Medium B Galvanis DN 50 ( 1½" ) btg 130,000 260,000 panjang 6 m
Pipa Medium B Galvanis DN 63 ( 2" ) btg 160,000 310,000 panjang 6 m
Pipa Medium B Galvanis DN 2½" btg 245,000 380,000 panjang 6 m
Pipa Medium B Galvanis DN 90 ( 3" ) btg 460,000 490,000 panjang 6 m
Pipa Medium B Galvanis DN 110 ( 4" ) btg 560,000 580,000 panjang 6 m
Pipa Medium B Galvanis DN 160 ( 6" ) btg 960,000 1,050,000 panjang 6 m
Pipa Medium B Galvanis DN 200 ( 8" ) btg 1,850,000 2,100,000 panjang 6 m
Pipa Medium B Galvanis DN 250 ( 10") btg - - panjang 6 m

VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,500 5,800
30 X 60 lbr 13,000 13,200
60 X 120 lbr 41,000 42,000
List Kayu Profil m' 4,800 5,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 62,000 68,000
3 HARD BOARD-uk: 4'X 8' lbr 68,000 72,000
GYPROC uk.120cmx240cmx9mm lbr 57,500
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 50,000 65,000
. 120 X 240 X 3 mm lbr 90,000 95,000
. 90 X 210 X 4 mm lbr 65,000 70,000
. 90 X 210 X 9 mm lbr 115,000 125,000
. 90 X 210 X 12 mm lbr 160,000 180,000
. 90 X 210 X 15 mm lbr 225,000 240,000
. 90 X 210 X 18 mm lbr 295,000 310,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
Tripleks
. 120 X 240 X 3 mm lbr 50,000 55,000
. 120 X 240 X 4 mm lbr 62,000 70,000
. 120 X 240 X 6 mm lbr 75,000 80,000
Multipleks
. 120 X 240 X 9 mm lbr 125,000 160,000
. 120 X 240 X 12 mm lbr 145,000 180,000
. 120 X 240 X 15 mm lbr 185,000 280,000
. 120 X 240 X 18 mm lbr 210,000 310,000
Formika ukuran pintu lbr 68,000 75,000

IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 25,000 30,000
Dempul plamur kg 25,000 30,000
Ambril/amplas lbr 3,800 4,100
Batu Apung kg 29,000 31,000
Cat dasar kg 34,000 36,500
. Emco kg 51,000 55,000
. Yunior 66 (nippon paint) kg 50,000 58,000
- Koas bh 7,500 8,000
. Deculux kg 55,000 58,000
. Siralax ons 10,000 18,000
. Spiritus ltr 11,000 13,500
. Plitur jadi ltr 35,000 42,000

2 TEMBOK
Kalkarium kg 4,200 5,000
Kapur sirih kg 4,250 4,750
Plamur kg 20,000 32,000
Cat Tembok kg 20,000 21,000
Sintex 5 kg 100,000 105,000
Danabride 5 kg 100,000 110,000
Catylac 5 kg 105,000 120,000
Mowilex 5 kg 275,000 300,000

3 BESI
Menie kg 20,000 30,000
Cat mengkilat kg 35,000 58,000
Cat kg 36,000 42,500
Thinner A ltr 15,000 16,000
Minyak cat ltr 13,000 20,000
Thinner Super ltr 12,000 25,000
Residu (teer/aspal) drum 55,000 60,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 875,000 1,250,000
kapasitas 1100 liter. bh 1,650,000 1,700,000
Lem Aica Aibon kg 37,500 60,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 60,000 65,000
5 mm m2 70,000 76,000
2 ES KABUR 3 mm m2 70,000 75,000
5 mm m2 80,000 88,000
3 RAY BAND 3 mm m2 70,000 75,000
5 mm m2 80,000 85,000

XI . BAHAN INSTALASI LISTRIK

1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 3,100 3,300
SPLN LMK 1 X 2 1/2 mm2 m' 3,700 3,900
. 1X4 mm2 m' 5,700 6,000
1X6 mm2 m' 8,500 8,900
NYY :. 2 X 1 1/2 mm2 m' 9,000 9,450
PRIMA 2 X 2 1/2 mm2 m' 15,000 15,500
. 2X4 mm2 m' 27,000 28,000
2X6 mm2 m' 35,000 37,000
3 X 1 1/2 mm2 m' 13,200 14,000
3 X 2 1/2 mm2 m' 20,000 21,000
3X4 mm2 m' 34,500 36,500
3X6 mm2 m' 50,000 53,000
NYM :. 2 X 1 1/2 mm2 m' 7,000 8,000
PRIMA 2 X 2 1/2 mm2 m' 10,900 11,500
. 2X4 mm2 m' 21,000 23,000
3 X 1 1/2 mm2 m' 12,500 14,000
3 X 2 1/2 mm2 m' 19,000 22,000
3X4 mm2 m' 30,000 35,000
3X6 mm2 m' 43,000 48,000

2 SKAKELAR
Out bauw . Seri bh 15,000 21,000
. Engkel bh 12,000 15,000
In bauw . Seri bh 11,500 16,500
. Engkel bh 9,500 12,000

3 FUSE BOX (SEKERING KASA)


1 group bh 115,000 135,000
2 group bh 220,000 245,000
3 group bh 325,000 360,000

4 STEKER - Biasa bh 10,000 12,000


Arde bh 15,000 16,000
T Biasa bh 12,500 13,000
T dengan Arde bh 17,000 17,500
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
5 FITING Flaon bh 7,500 11,000
Gantung bh 10,000 20,000
Kap bh 5,000 17,500
Kombinasi bh 275,000 350,000

6 STOP KONTAK - Arde Outbow putih bh 12,500 15,000


Arde Outbow hitam bh 5,000 6,000
Arde IB bh 10,000 15,000
Arde Putar bh 31,000 42,000

XII . ALAT - ALAT PENGUNCI & PENGGANTUNG


1 KUNCI TANAM Union : 1 X slag bh 55,000 60,000
2 X slag bh 65,000 70,000
Yale : 1 X slag bh 85,000 95,000
2 X slag bh 140,000 155,000
Kuda : 1 X slag bh 55,000 60,000
2 X slag bh 70,000 75,000

2 ENGSEL DAN GERENDEL


Engsel Angin bh 15,000 16,000
Kupu-kupu biasa bh 4,000 4,500
Nylon kupu-kupu bh 6,000 9,000
Espagnoled - dalam negeri bh 30,000 50,000
Grendel Tanam luar negeri bh 7,500 11,000
Grendel biasa bh 10,000 20,000
Kait Angin bh 5,000 17,500
Door Stop bh 275,000 350,000

XIII . BAHAN SANITAIR


1 KLOSET DUDUK bh 1,450,000 1,500,000
2 KLOSET JONGKOK bh 140,000 155,000
3 WASTAFEL PEDESTAL bh 850,000 1,250,000
4 WASTAFEL MEJA OVAL bh 700,000 950,000
5 WASTAFEL GANTUNG BULAT bh 275,000 450,000
6 WASTAFEL GANTUNG SUDUT bh 240,000 310,000
7 WASTAFEL GANTUNG SUDUT KECIL bh 230,000 275,000
8 WASTAFEL BAK CUCI bh 145,000 170,000
9 TEMPAT SABUN GANTUNG bh 30,000 35,000
10 TEMPAT SABUN TANAM bh 20,000 25,000

11 SEPTIC TANK (ETERNIT GRESIK)


5 Pemakai 500 liter unit
10 Pemakai 1.000 liter unit - -
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
12 LAIN - LAIN
Kran Air bh 15,000 35,000
Seal tape bh 3,900 4,100
Floor drain bh 15,000 20,000

XIV . ALAT PENGIKAT KAYU


1 PAKU - ukuran 1" s/d 4" kg 13,000 15,000
2 PAKU - payung kg 20,000 30,000
3 PAKU - sekrup kg 6,000 8,000
4 PAKU - beton kg 25,000 30,000
5 MUR BAUT (kuda-kuda) kg 13,000 14,000
6 ANGKUR BAUT bh 13,000 13,500
7 LEM KAYU bh 18,000 20,000
8 Tali Ijuk kg 7,000 10,000

XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 275,000 310,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 975,000 1,050,000
Fuji 250 watt bh 1,450,000 1,500,000
Shimizu . 100 watt bh 450,000 510,000
. 90 watt bh 350,000 380,000
Dab . 125 watt bh 350,000 400,000
. 175 watt bh 425,000 450,000

X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 50,000 65,000
Merah/hitam m2 52,500 70,000
2 HOLLAND Abu-abu m2 50,000 65,000
Merah/hitam m2 52,500 70,000
3 UNIDECOR Abu-abu m2 42,000 55,000
Merah/hitam m2 52,500 70,000
4 UNI Abu-abu m2 50,000 65,000
Merah/hitam m2 52,500 70,000
5 TRIHEX Abu-abu m2 50,000 65,000
Merah/hitam m2 52,500 70,000
6 OLYMPIA HEXA Abu-abu m2 50,000 65,000
7 HEXAGONAL Abu-abu m2 52,500 70,000
Merah/hitam m2 50,000 65,000
8 CASTLE Abu-abu m2 52,500 70,000
9 TRAPEZ Abu-abu m2 50,000 65,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 50,000 65,000
11 STANDARD GRASS BLOCK ABU-ABU BH 7,500 8,500
12 BATACO BH 3,500 4,250
13 KANSTEEN m' 15,000 27,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
XVII. L A I N - L A I N
1 KREI 25 MM m2 45,000 50,000
2 Sliding Pintu J4 bh 180,000 235,000
3 Naco per Daun bh 12,000 12,500
4 Rolling door Besi m2 300,000 325,000
Rolling door Almunium m2 230,000 275,000
5 Awning Almunium m2 210,000 225,000
6 Kusen Almunium 4" Putih m' 80,000 85,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,500,000 1,550,000

8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 1,650,000 1,700,000

Hotmix Tebal = 4 Cm m2 65,000 70,000


Hotmix Tebal = 5 Cm m2 80,000 85,000
Hotmix Tebal = 6 Cm m2 95,000 100,000
Hotmix Tebal = 7 Cm m2 110,000 120,000
Binder Course ton 1,300,000 1,350,000
Wearing Course ton 1,300,000 1,450,000
Hot Roller Sheet ton 1,150,000 1,300,000
Sand Sheet ton 1,100,000 1,250,000
Sand Sheet Emulsi ton 1,450,000 1,600,000
Cold Mix ton 1,750,000 1,850,000
Prime / Tack Coard RC liter 8,200 8,700
Prime Coat MC liter 8,200 8,700
Prime / Tack Coat Emulsi liter 8,200 8,700
10 K A C A
Cermin tebal 5 mm m2 225,000 275,000

11 PAGAR BRC. Pagar BRC 90 A2 /lb 175,000 200,000


Pagar BRC 120 A2 /lb 225,000 250,000
12 LAIN-LAIN
Minyak Beton & bekisting ltr 9,000 10,000
Pintu Lipat Besi m2 380,000 425,000
Sunscreen Allumunim m2 310,000 350,000
Allumunium Foil m2 7,500 8,000
Soda api kg 12,000 13,000
Sabun kg 11,000 13,000
Air m3 12,500 15,000
Koas Alang-alang ikat 1,250 2,000
Solar (Industri) ltr 11,250 11,300
Premium (Industri) ltr 10,000 11,000
Pelumas ltr 37,500 45,000
Vynil 30x30 cm bh 6,200 6,500
DAFTAR HAR GA S AT UAN P E K E R J AAN

SUMBER DATA PASARAN BEBAS


D A E R A H KOTA SEMARANG & SEKITAR
EDISI NOPEMBER 2015

HARGA SATUAN PEKERJAAN


NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
(Rp) (Rp)

I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN

1 A.2.2.1.2 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m m' 535,617.50 622,627.50

2 A.2.2.1.4 Pengukuran dan Pemasangan Bouwplank m' 119,333.50 141,680.00

3 A.2.2.1.5 Pembuatan Kantor Sementara dg Lantai Plesteran m2 1,636,272.00 1,877,535.00

4 A.2.2.1.7 Pembuatan Gudang Semen dan Peralatan m2 1,514,672.50 1,747,240.00

5 A.2.2.1.9 Membersihkan Lapangan dan Perataan m2 10,175.00 12,100.00

6 A.2.2.1.10 Pembuatan Steger/Perancah dari Bambu m2 263,507.20 301,521.00

7 A.2.2.1.11 Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm bh 424,699.00 509,685.00

8 A.2.2.1.13 Bongkaran Beton Bertulang m3 861,652.00 1,019,315.00

9 A.2.2.1.14 Bongkaran Dinding Tembok Bata Merah m3 406,076.00 479,957.50

II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 Menggali Tanah Biasa Sedalam 1 m m3 47,437.50 56,100.00

2 A.2.3.1.2 Menggali Tanah Biasa Sedalam 2 m m3 58,162.50 68,805.00

3 A.2.3.1.3 Menggali Tanah Biasa Sedalam 3 m m3 69,052.50 81,708.00

4 A.2.3.1.4 Menggali Tanah Keras Sedalam 1 m m3 63,140.00 74,668.00

5 A.2.3.1.5 Menggali Tanah Cadas Sedalam 1 m m3 95,700.00 113,190.00

6 A.2.3.1.6 Menggali Tanah Lumpur Sedalam 1 m m3 76,312.50 90,255.00

7 A.2.3.1.7 Mengerjakan Striping Tebing Setinggi 1 m m2 3,437.50 4,070.00

8 A.2.3.1.8 MembuangTanah sejauh 30 m' m3 20,790.00 24,585.00

9 A.2.3.1.9 Pengurugan Kembali m3 1/3 x Gal.tanah

10 A.2.3.1.10 Pemadatan Tanah (per 20 cm) m3 34,375.00 40,700.00

11 A.2.3.1.11 Urugan Pasir m3 177,375.00 220,440.00

12 A.2.3.1.12 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL m3 244,832.50 293,755.00

13 A.2.3.1.13 Pemasangan Lapisan Ijuk tebal 10 cm unt Bidang Resapan m2 56,512.50 78,210.00

14 A.2.3.1.14 Mengurug Sirtu Padat m3 175,587.50 191,950.00

III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI

1 A.3.2.1.1 Pemasangan Pondasi Batu Belah 1SP : 3 PP m3 827,612.50 902,742.50

2 A.3.2.1.2 Pemasangan Pondasi Batu Belah 1SP : 4 PP m3 782,650.00 857,367.50

3 A.3.2.1.3 Pemasangan Pondasi Batu Belah 1SP : 5 PP m3 751,465.00 825,885.50

4 A.3.2.1.4 Pemasangan Pondasi Batu Belah 1SP : 6 PP m3 729,547.50 803,764.50

5 A.3.2.1.5 Pemasangan Pondasi Batu Belah 1SP : 8 PP m3 699,490.00 773,415.50

6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 593,450.00 663,382.50

7 A.3.2.1.7 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP m3 675,895.00 753,318.50

8 A.3.2.1.8 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP m3 643,995.00 719,262.50

9 A.3.2.1.9 Pemasang Batu Kosong/Anstamping m3 407,253.00 448,651.50

10 A.3.2.1.10 Pasang Pondasi Siklop, 60% Beton Camp. 1PC : 2PB : 3KR & 40% Batu Belah m3 2,188,081.50 2,414,769.50

11 A.3.2.1.11 Pasang Pondasi Sumuran diameter 100 cm m3 768,421.50 840,103.00

IV A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING

1 A.4.4.1.1 Pemasangan Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 bata Camp. 1SP: 2PP m2 206,057.50 229,625.00

2 A.4.4.1.2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP m2 194,273.75 217,805.50

3 A.4.4.1.3 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP m2 185,968.75 209,247.50

4 A.4.4.1.4 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP m2 182,215.00 205,700.00

5 A.4.4.1.5 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP m2 182,077.50 206,349.00

file:///conversion/tmp/scratch/443255086.xls 15/95 sat.pekerjaan


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
(Rp) (Rp)
6 A.4.4.1.6 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP m2 170,761.25 194,924.40

7 A.4.4.1.7 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP m2 98,683.75 110,214.50

8 A.4.4.1.8 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP m2 92,881.25 104,259.10

9 A.4.4.1.9 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP m2 89,677.50 101,046.00

10 A.4.4.1.10 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP m2 87,670.00 99,037.40

11 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m2 86,790.00 98,280.60

12 A.4.4.1.12 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP m2 84,535.00 95,975.00

13 A.4.4.1.13 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP m2 85,910.00 98,230.00

14 A.4.4.1.14 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1SM : 1PP m2 76,092.50 86,977.00

15 A.4.4.1.15 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1KP : 1SM : 2PP m2 87,769.00 87,769.00

16 A.4.4.1.20 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP m2 190,558.50 224,788.30

17 A.4.4.1.21 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP m2 192,332.25 227,583.40

18 A.4.4.1.22 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 2PP m2 240,542.50 310,354.00

19 A.4.4.1.23 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP m2 237,160.00 306,955.00

V A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN

1 A,4,4,2.1 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm m2 58,443.00 65,450.22

2 A,4,4,2.2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm m2 52,173.00 59,087.82

3 A,4,4,2.3 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm m2 49,549.50 56,478.18

4 A,4,4,2.4 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm m2 47,685.00 54,578.70

5 A,4,4,2.5 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm m2 46,728.00 53,662.62

6 A,4,4,2.6 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm m2 45,919.50 52,861.38

7 A,4,4,2.7 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm m2 45,507.00 52,471.98

8 A,4,4,2.8 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm m2 45,094.50 52,082.58

9 A.4.4.2.9 Pemasangan Plesteran 1 Pc : 1/2 Kp : 3 Pp Tebal 15 mm m2 46,249.50 53,116.80

10 A,4,4,2.10 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm m2 44,737.00 51,931.00

11 A,4,4,2.11 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm m2 40,722.00 47,569.50

12 A,4,4,2.12 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm m2 41,272.00 48,262.50

13 A,4,4,2.13 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm m2 69,811.50 79,080.76

14 A,4,4,2.14 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm m2 51,910.00 58,818.40

15 A,4,4,2.15 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm m2 63,745.00 72,969.60

16 A,4,4,2.16 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm m2 62,551.50 71,847.16

17 A,4,4,2.17 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm m2 61,391.00 70,679.84

18 A,4,4,2.18 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm m2 57,304.50 66,753.50

19 A,4,4,2.19 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm m2 30,233.50 34,500.62

20 A,4,4,2.20 Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm m' 45,815.00 52,272.00

21 A,4,4,2.23 Pemasangan Plesteran Ciprat 1Pc : 2 Pp m2 35,997.50 41,289.60

22 A,4,4,2.24 Pemasangan Finishing Siar Pasangan Dinding Bata Merah (=20 m') m2 20,944.00 23,809.94

23 A,4,4,2.25 Pemasangan Finishing Siar Pasangan Dinding Conblock ekspose (=8 m') m2 10,026.50 11,379.50

24 A,4,4,2.26 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp m2 44,852.50 51,157.70

25 A,4,4,2.27 Pemasangan Acian m2 26,578.75 30,332.50

VI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U

1 A.4.6.1.1 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I m3 26,618,900.00 27,565,725.00

2 A.4.6.1.2 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas II atau III m3 11,186,725.00 12,272,425.00

3 A.4.6.1.3 Pembuatan & Pemasangan Pintu KlampStandard Kayu Klas II (Kayu Kamfer) m2 454,217.50 479,979.50

4 A.4.6.1.4 Pembuatan & Pemasangan Daun Pintu Klamp Sederhana Kayu Klas III m2 454,217.50 479,979.50

5 A.4.6.1.5 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II m2 675,565.00 732,600.00

6 A.4.6.1.6 Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Klas I atau II m2 478,720.00 523,160.00

7 A.4.6.1.7 Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu Klas I atau II (jati) m2 1,898,875.00 2,018,500.00

file:///conversion/tmp/scratch/443255086.xls 16/95 sat.pekerjaan


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
(Rp) (Rp)
8 A.4.6.1.8 Pembuatan&Pemasangan Pintu kayu lapis (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 cm) m2 528,951.50 574,805.00

9 A.4.6.1.9 Pembuatan&Pemasangan Pintu Plywood rangkap, rangka expose kayu klas I atau II m2 567,985.00 618,783.00

10 A.4.6.1.10 Pembuatan & Pemasangan Jalusi mati Kosen Kayu Klas I atau II m2 1,706,017.50 1,809,445.00

11 A.4.6.1.11 Pembuatan & Pemasangan Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I m2 955,009.00 1,027,235.00

12 A.4.6.1.12 Pembuatan&Pemasangan Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II m2 609,103.00 665,109.50

13 A.4.6.1.13 Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 meter m3 9,996,030.00 10,943,350.00

14 A.4.6.1.14 Pembuatan&Pemasangan Konstruksi Kuda-kuda Expose, Kayu Klas I m3 28,965,502.50 29,976,760.00

15 A.4.6.1.15 Pemasangan konstruksi Gording, Kayu Klas II m3 9,414,570.00 10,279,170.00

16 A.4.6.1.16 Pemasangan Rangka Atap Genteng Keramik, Kayu Klas II m2 152,806.50 167,365.00

17 A.4.6.1.17 Pemasangan Rangka Atap Genteng Beton, Kayu Klas II m2 180,130.50 197,065.00

18 A.4.6.1.18 Pemasangan Rangka Atap Sirap, Kayu Klas II m2 127,897.00 140,448.00

19 A.4.6.1.19 Pemasangan Rangka Langit-langit (50x1,00) m, kayu Klas II atau III m2 162,563.50 179,685.00

20 A.4.6.1.20 Pemasangan Rangka Langit-langit (60x60) cm, kayu Klas II atau III m2 167,772.00 185,075.00

21 A.4.6.1.21 Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau II m' 287,622.50 303,325.00

22 A.4.6.1.22 Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau klas II m' 117,507.50 123,640.00

23 A.4.6.1.23 Pemasangan Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III m2 265,732.50 291,769.50

24 A.4.6.1.24 Pemasangan Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II m2 338,310.50 370,309.50

25 A.4.6.1.25 Pemasangan Dinding Pemisah Plywood Rangkap Rangka Kayu Klas II m2 344,388.00 376,805.00

26 A.4.6.1.26 Pemasangan Dinding Lambriziring dari Papan klas I m2 375,925.00 413,050.00

27 A.4.6.1.27 Pemasangan Dinding Lambriziring dari Plywood ukuran (120x240) cm m2 36,525.50 41,360.00

28 A.4.6.1.28 Pemasangan Dinding Bilik, Rangka Kayu Klas III atau IV m2 118,162.44 128,722.00

VII A.4.1.1 HARGA SATUAN PEKERJAAN BETON

1 A.4.1.1.1 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87 m3 920,970.68 1,015,113.00

2 A.4.1.1.2 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 m3 953,503.03 1,048,750.59

3 A.4.1.1.3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72 m3 978,977.35 1,074,989.67

4 A.4.1.1.4 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 m3 869,298.86 956,923.81

5 A.4.1.1.5 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 m3 1,009,034.41 1,106,052.44

6 A.4.1.1.6 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61 m3 1,037,949.28 1,135,787.07

7 A.4.1.1.7 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 m3 1,059,427.50 1,158,119.11

8 A.4.1.1.8 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 1,073,968.75 1,172,940.59

9 A.4.1.1.9 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53 m3 1,099,241.39 1,198,758.00

10 A.4.1.1.10 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 m3 1,106,971.37 1,206,618.93

11 A.4.1.1.11 Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm, w/c = 0,49 m3 1,172,415.43 1,278,898.70

12 A.4.1.1.12 Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm, w/c = 0,48 m3 1,182,667.26 1,289,354.81

13 A.4.1.1.17 Pembesian dg Besi Polos atau Besi Ulir 10 kg 157,762.00 165,550.00

14 A.4.1.1.18 Kabel Presstresed Polos/strand 10 kg 119,185.00 132,159.50

15 A.4.1.1.19 Jaring Kawat baja/Wire Mesh 10 kg 229,042.00 240,960.50

16 A.4.1.1.20 Memasang Bekisting untuk Pondasi m2 150,766.00 165,231.00

17 A.4.1.1.21 Memasang Bekisting untuk Sloof m2 161,766.00 176,781.00

18 A.4.1.1.22 Memasang Bekisting untuk Kolom m2 335,588.00 383,135.50

19 A.4.1.1.23 Memasang Bekisting untuk Balok m2 351,428.00 401,450.50

20 A.4.1.1.24 Memasang Bekisting untuk Lantai m2 414,788.00 471,135.50

21 A.4.1.1.25 Memasang Bekisting untuk Dinding m2 381,788.00 436,760.50

22 A.4.1.1.26 Memasang Bekisting untuk Tangga m2 313,093.00 359,485.50

23 A.4.1.1.27 Memasang Jembatan Cor m2 90,887.50 98,598.50

24 A.4.1.1.28 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) m3 3,632,304.50 4,007,069.00

25 A.4.1.1.29 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) m3 4,434,710.50 4,889,423.00

26 A.4.1.1.30 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) m3 7,716,725.50 8,639,103.00

file:///conversion/tmp/scratch/443255086.xls 17/95 sat.pekerjaan


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
(Rp) (Rp)
27 A.4.1.1.31 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) m3 6,066,368.00 6,798,198.00

28 A.4.1.1.32 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting) m3 5,584,975.00 6,255,232.50

29 A.4.1.1.33 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting) m3 5,461,494.50 6,138,319.00

30 A.4.1.1.34 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) m3 5,586,300.50 6,255,348.00

31 A.4.1.1.35 Membuat Kolom Penguat Beton Bertulang (11 x 11) cm m' 64,138.25 71,497.25

32 A.4.1.1.36 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 88,962.50 99,462.00

VIII A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP

1 A.4.5.2.1 Pemasangan Atap Genteng Plentong Kecil m2 77,123.75 85,313.25

2 A.4.5.2.2 Pemasangan Atap Genteng Kodok / Glasur m2 126,670.50 136,240.50

3 A.4.5.2.3 Pemasangan Atap Genteng Plentong Super / Besar m2 117,650.50 125,295.50

4 A.4.5.2.4 Pemasangan Genteng Bubung Plentong m' 111,155.00 121,132.00

5 A.4.5.2.5 Pemasangan Genteng Bubung Kodok / Glasur m' 97,405.00 107,932.00

6 A.4.5.2.6 Pemasangan Genteng Bubung Plentong Besar m' 101,255.00 111,012.00

7 A.4.5.2.9 Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5 mm m2 65,301.50 74,420.50

8 A.4.5.2.10 Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5 mm m2 59,433.00 67,809.50

9 A.4.5.2.12 Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4 mm m2 50,248.00 56,732.50

10 A.4.5.2.15 Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4 mm m2 51,183.00 56,622.50

11 A.4.5.2.30 Pemasangan Atap Genteng Beton m2 95,139.00 110,880.00

12 A.4.5.2.32 Pemasangan Atap Genteng Metal m2 81,070.00 96,305.00

13 A.4.5.2.33 Pemasangan Atap Sirap m2 97,575.50 104,648.50

14 A.4.5.2.34 Pemasangan Nok Genteng Beton m' 100,430.00 115,643.00

15 A.4.5.2.36 Pemasangan Nok Genteng Metal m' 54,890.00 62,804.50

16 A.4.5.2.37 Pemasangan Nok Sirap m' 44,033.00 49,654.00

17 A.4.5.2.38 Pemasangan Atap Seng Gelombang m2 33,572.00 37,301.00

18 A.4.5.2.39 Pemasangan Atap Nok Seng m' 25,151.50 28,495.50

19 A.4.5.2.42 Pasang Allumunium Foil / Sisalation m2 22,990.00 25,954.50

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT

1 A.4.5.1.1 Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm m2 28,077.50 30,552.50

2 A.4.5.1.2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm m2 92,092.00 99,033.00

3 A.4.5.1.3 Pemasangan Langit-langit Akustik Ukuran (30x60) cm m2 99,302.50 103,081.00

4 A.4.5.1.4 Pemasangan Langit-langit Akustik Ukuran (60x120) cm m2 84,012.50 88,165.00


5 A.4.5.1.5 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 4 mm & 6 mm m2 41,651.50 47,410.00

6 A.4.5.1.6 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm m2 488,323.00 523,985.00

7 A.4.5.1.7 Memasang Langit-langit Gypsu Board, Uk (120x240) tebal 9 mm m2 37,694.80 41,945.20

8 A.4.5.1.9 Memasang Langit-langit Akuatik Uk (60x120) cm & Rangka Allumunium m2 185,652.50 201,905.00

9 A.4.5.1.10 List Langit-Langit Kayu Profil m1 13,552.00 15,009.50

X A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG

1 A.5.1.1.1 Memasang Closet Duduk / Mono Blok Unit 1,994,393.50 2,103,744.50

2 A.5.1.1.2 Memasang Closet Jongkok Porselen Unit 502,425.00 566,390.00

3 A.5.1.1.4 Memasang Urinoir Unit 671,825.00 733,150.00

4 A.5.1.1.5 Memasang Wastafel Unit 510,812.50 779,982.50

5 A.5.1.1.6 Pemasangan Bathcuip porselen Unit 1,063,672.50 1,139,622.00

6 A.5.1.1.7 Pemasangan Bak Fibreglass vol.1 m3 Unit 970,475.00 1,099,175.00

7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,256,354.27 1,413,478.54

8 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 333,107.50 375,815.00

9 A.5.1.1.14 Pemasangan Floor Drain buah 26,702.50 33,605.00

10 A.5.1.1.15 Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi 35 cm bh 342,809.50 388,443.00

file:///conversion/tmp/scratch/443255086.xls 18/95 sat.pekerjaan


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
(Rp) (Rp)
11 A.5.1.1.16 Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm bh 514,673.50 582,488.50

12 A.5.1.1.17 Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm bh 621,181.00 698,874.00

13 A.5.1.1.18 Pemasangan Pipa Galvanis Ø ½" m' 32,231.83 47,147.83

14 A.5.1.1.19 Pemasangan Kran Ø ½" atau Ø ¾" bh 54,268.23 81,301.28

15 A.5.1.1.20 Pemasangan Pipa Galvanis Ø ¾" m' 35,073.50 58,514.50

16 A.5.1.1.21 Pemasangan Pipa Galvanis Ø 1" m' 40,756.83 69,881.17

17 A.5.1.1.22 Pemasangan Pipa Galvanis Ø 1½ " m' 60,421.17 100,811.33

18 A.5.1.1.23 Pemasangan Pipa Galvanis Ø 3" m' 160,174.67 173,028.17

19 A.5.1.1.24 Pemasangan Pipa Galvanis Ø 4" m' 268,158.00 281,011.50

20 A.5.1.1.25 Pemasangan Pipa PVC tipe AW Ø ½" m' 18,936.50 23,927.75

21 A.5.1.1.26 Pemasangan Pipa PVC tipe AW Ø ¾" m' 21,494.00 26,059.00

22 A.5.1.1.27 Pemasangan Pipa PVC tipe AW Ø 1" m' 26,609.00 30,321.50

23 A.5.1.1.28 Pemasangan Pipa PVC tipe AW Ø 1½" m' 28,831.00 33,121.00

24 A.5.1.1.29 Pemasangan Pipa PVC tipe AW Ø 2" m' 38,776.83 45,340.17

25 A.5.1.1.31 Pemasangan Pipa PVC tipe AW Ø 3" m' 77,305.25 94,104.08

26 A.5.1.1.32 Pemasangan Pipa PVC tipe AW Ø 4" m' 93,104.00 101,363.17

27 A.5.1.1.33 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm m' 79,882.00 87,912.00

28 A.5.1.1.34 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm m' 34,732.50 39,825.50

29 A.5.1.1.35 Pemasangan Pipa Beton Ø 20 cm m' 91,478.75 109,764.60

30 A.5.1.1.36 Pemasangan Pipa Beton Ø 100 cm m' 493,256.50 538,422.50

XI A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM

1 A.4.2.1.1 Pemasangan Besi Profil Kg 26,900.50 30,008.00

2 A.4.2.1.2 Pemasangan Rangka Kuda-kuda Baja IWF kg 25,580.50 28,028.00

3 A.4.2.1.3 Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) kg 75,306.00 87,279.50

4 A.4.2.1.4 Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku m2 829,317.50 903,875.50

5 A.4.2.1.5 Pengerjaan Pengelasan dengan Las Listrik cm 16,596.25 19,347.90

6 A.4.2.1.7 Pemasangan Pintu Rolling Door Besi m2 513,315.00 568,634.00

7 A.4.2.1.8 Pemasangan Pintu Lipat (Folding Door) m2 486,849.00 546,876.00

8 A.4.2.1.9 Pemasangan Sunscreen Allumunium m2 419,650.00 474,276.00

9 A.4.2.1.10 Pemasangan Rolling Door Allumunium m2 409,475.00 482,900.00

10 A.4.2.1.11 Pemasangan Kusen Pintu Allumunium m' 108,474.30 116,322.25

11 A.4.2.1.12 Pemasangan Pintu Allumunium Strip Lebar 8 cm m2 472,766.25 507,029.05

12 A.4.2.1.13 Pemasangan Pintu Kaca Rangka Allumunium m2 440,209.00 474,380.50

13 A.4.2.1.14 Pemasangan Venetions Blinds & Vertical Blinds m2 159,307.50 173,189.50

14 A.4.2.1.15 Pemasangan Terali Besi Strip (2x3) cm m2 319,202.28 368,024.87

15 A.4.2.1.16 Pemasangan Kawat Nyamuk m2 49,179.28 56,333.33

16 A.4.2.1.17 Pemasangan Jendela Nako & Tralis m2 61,132.50 68,464.00

17 A.4.2.1.18 Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm m' 164,967.00 191,015.00

18 A.4.2.1.19 Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm m' 60,478.00 79,167.00

19 A.4.2.1.20 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 60x120 cm dinding partisi m2 154,660.00 179,899.50

20 A.4.2.1.21 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 60x60 cm dinding plafond m2 186,807.50 217,189.50

XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA

1 A.4.6.2.2 Pemasangan Kunci Tanam Biasa Buah 197,202.50 219,505.00

2 A.4.6.2.3 Pemasangan Kunci Kamar Mandi Buah 135,726.25 152,377.50

3 A.4.6.2.4 Pemasangan Kunci Selinder Buah 196,226.25 218,377.50

4 A.4.6.2.5 Pemasangan Engsel Pintu Buah 21,903.75 27,307.50

5 A.4.6.2.6 Pemasangan Engsel Jendela Kupu-kupu Buah 14,602.50 16,555.00

file:///conversion/tmp/scratch/443255086.xls 19/95 sat.pekerjaan


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
(Rp) (Rp)
6 A.4.6.2.7 Pemasangan Engsel Angin Buah 40,961.25 45,589.50

7 A.4.6.2.9 Pemasangan Kait Angin Buah 20,845.00 36,707.00

8 A.4.6.2.10 Pasang Door Closer Buah 351,656.25 440,797.50

9 A.4.6.2.11 Pemasangan Kunci Selot Buah 30,662.50 44,319.00

10 A.4.6.2.13 Pemasangan Door Stop Buah 312,331.25 396,159.50

11 A.4.6.2.14 Pemasangan Rel Pintu Dorong Buah 256,987.50 325,457.00

12 A.4.6.2.15 Pemasangan Kunci Lemari Buah 30,082.25 36,153.70

13 A.4.6.2.16 Pemasangan Kaca tebal 3 mm m2 87,346.88 95,389.25

14 A.4.6.2.17 Pemasangan Kaca tebal 5 mm m2 99,446.88 108,699.25

15 A.4.6.2.18 Pemasangan Kaca Cermin tebal 5 mm m2 286,996.88 349,489.25

XIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING

1 A.4.4.3.2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm m2 92,971.00 102,605.00

2 A.4.4.3.3 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm m2 92,686.00 102,657.50

3 A.4.4.3.5 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm m2 131,795.50 145,357.50

4 A.4.4.3.6 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm m2 128,744.00 144,061.50

5 A.4.4.3.9 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm m2 341,198.00 583,682.00

6 A.4.4.3.16 Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm m' 56,699.50 66,403.70

7 A.4.4.3.19 Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm m' 33,242.00 36,819.20

8 A.4.4.3.32 Pemasangan Lantai Keramik 10x 20 cm m2 201,126.75 230,056.20

9 A.4.4.3.33 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm m2 208,551.75 238,966.20

10 A.4.4.3.34 Pemasangan Lantai Keramik 33 x 33 cm m2 190,069.31 217,939.09

11 A.4.4.3.35 Pemasangan Lantai Keramik 30 x 30 cm m2 188,746.50 214,921.50

12 A.4.4.3.36 Pemasangan Lantai Keramik 20 x 20 cm m2 192,516.50 215,506.50

13 A.4.4.3.37 Pemasangan Lantai Keramik uk.10 x 33 cm, untuk variasi / border m2 392,898.00 435,831.00

14 A.4.4.3.39 Pemasangan Plint Keramik Ukuran 10x20 cm m' 31,421.50 36,791.70

15 A.4.4.3.40 Pemasangan Plint Keramik Ukuran 10x10 cm m' 77,891.00 83,926.70

16 A.4.4.3.41 Pemasangan Plint Keramik Ukuran 5x20 cm m' 75,559.00 82,760.70

17 A.4.4.3.43 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm m2 664,358.75 687,524.20

18 A.4.4.3.44 Pemasangan Lantai Karpet m2 185,454.50 203,967.50

19 A.4.4.3.46 Pemasangan Lantai Parquet Jati m2 327,360.00 372,047.50

20 A.4.4.3.48 Pemasangan Dinding Porselen 11 x 11 cm m2 221,621.16 251,127.32

21 A.4.4.3.49 Pemasangan Dinding Keramik 10x20 cm, m2 218,080.50 249,309.50

22 A.4.4.3.50 Pemasangan Dinding Keramik 20x20 cm, m2 203,659.50 235,559.50

23 A.4.4.3.53 Pemasangan Dinding Keramik 10x20 cm, m2 218,080.50 249,309.50

24 A.4.4.3.55 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm m2 731,698.12 764,832.32

25 A.4.4.3.58 Pemasangan Dinding Batu Paros / Batu Tempel Hitam m2 217,153.75 240,515.00

26 A.4.4.3.59 Pemasangan Lantai Vynil uk.30 x 30 cm m2 128,632.90 144,732.50

27 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 36,762.00 43,978.00

XIV A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

1 A.4.7.1.1 Pengikisan / pengerokan Permukaan Cat Tembok Lama m2 9,982.50 11,737.00

2 A.4.7.1.2 Pencucian Bidang Permukaan Tembok yang Pernah dicat m2 9,927.50 11,737.00

3 A.4.7.1.3 Pengerokan Karat Cat Lama permukaan Baja dg cara manual m2 10,340.00 12,232.00

4 A.4.7.1.4 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) m2 37,416.50 43,384.00

5 A.4.7.1.5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penutup) m2 50,099.50 57,893.00

6 A.4.7.1.6 Pelaburan Bidang Kayu dg Teak Oil m2 29,991.50 32,263.00

7 A.4.7.1.7 Pelaburan Bidang Kayu dg Politur m2 37,570.50 43,575.40

file:///conversion/tmp/scratch/443255086.xls 20/95 sat.pekerjaan


HARGA SATUAN PEKERJAAN
NO. KODE URAIAN PEKERJAAN SAT MINIMUM MAKSIMUM
(Rp) (Rp)
8 A.4.7.1.8 Pelaburan Bidang Kayu dg Cat Residu & Ter m2 7,603.75 8,899.00

9 A.4.7.1.9 Pelaburan Bidang Kayu dg Vernis m2 30,541.50 34,595.00

10 A.4.7.1.10 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar m2 16,484.05 19,451.85

11 A.4.7.1.11 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup) m2 11,343.20 12,802.90

12 A.4.7.1.12 Pengecatan Tembok dengan Kalkarium m2 6,261.20 7,214.90

13 A.4.7.1.13 Pelaburan Tembok dengan Kapur Sirih m2 11,372.35 13,397.45

14 A.4.7.1.14 Pelaburan Tembok lama dengan Kapur Sirih (pemeliharaan) m2 5,667.75 6,646.75

15 A.4.7.1.15 Pemasangan Wallpaper m2 74,236.25 88,467.50

16 A.4.7.1.16 Pengecatan Permukaan Baja dg Meni Besi m2 20,715.75 24,546.50

17 A.4.7.1.17 Pengecatan Permukaan Baja dg Meni Besi & Perancah m2 43,422.50 50,586.25

file:///conversion/tmp/scratch/443255086.xls 21/95 sat.pekerjaan


DAFTAR ANALISA PE K E R JAAN

SUMBER DATA : PASARAN B E BAS


D A E R A H : KOTA SEMARANG & SEKITAR
EDISI NOPEMBER 2015

HARGA BAHAN/UPAH JUMLAH


No. SNI KODE KOEF SAT. URAIAN PAKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
I A. 2.2.1 HARGA SATUAN PEKERJAAN PERSIAPAN
1 A.2.2.1.2 1 m' Pagar Sementara dari Seng Gelombang Tinggi 2,00 m 535,617.50 622,627.50
A TENAGA 44,200.00 50,700.00
L.01 0.2 OH Pekerja 55,000.00 65,000.00 11,000.00 13,000.00
L.02 0.4 OH Tukang Kayu 75,000.00 85,000.00 30,000.00 34,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.02 OH Mandor 75,000.00 90,000.00 1,500.00 1,800.00
B BAHAN 442,725.00 515,325.00
1.25 Btg Kayu Dolken diameter 8 - 10 / 400 cm 18,000.00 20,000.00 22,500.00 25,000.00
2.5 Kg Portalnd Semen 1,250.00 1,300.00 3,125.00 3,250.00
1.2 Lbr Seng Gelombang 3" - 5" 48,000.00 57,000.00 57,600.00 68,400.00
0.005 m3 Pasir Beton 320,000.00 350,000.00 1,600.00 1,750.00
0.009 m3 Koral Beton 280,000.00 325,000.00 2,520.00 2,925.00
0.072 m3 Kayu 5/7X4m Kayu Kruing 4,800,000.00 5,550,000.00 345,600.00 399,600.00
0.06 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 780.00 900.00
0.45 Kg Meni Besi 20,000.00 30,000.00 9,000.00 13,500.00
C PERALATAN
D Jumlah A + B + C 486,925.00 566,025.00
E Overhead & Profit (contah 10%) 10% 48,692.50 56,602.50
F Harga Satuan Pekerjaan (D+E) 535,617.50 622,627.50
Overhead & Profit (contah 10%)
2 A.2.2.1.4 1 m' Pengukuran dan Pemasangan Bouwplank 119,333.50 141,680.00
A Tenaga 14,225.00 16,400.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.1 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 94,260.00 112,400.00
0.012 m3 Kayu 5/7x 4m Kayu Kruing 4,800,000.00 5,550,000.00 57,600.00 66,600.00
0.02 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 260.00 300.00
0.007 m3 Kayu Papan 3/20 Kruing 5,200,000.00 6,500,000.00 36,400.00 45,500.00
C PERALATAN
D Jumlah A + B + C 108,485.00 128,800.00
E Overhead & Profit (contah 10%) 10% 10,848.50 12,880.00
F Harga Satuan Pekerjaan (D+E) 119,333.50 141,680.00

3 A.2.2.1.5 1 m2 Pembuatan Kantor Sementara dg Lantai Plesteran 1,636,272.00 1,877,535.00


A Tenaga 364,250.00 418,000.00
L.01 2 OH Pekerja 55,000.00 65,000.00 110,000.00 130,000.00
L.02 2 OH Tukang Kayu 75,000.00 85,000.00 150,000.00 170,000.00
L.02 1 OH Tukang Batu 75,000.00 85,000.00 75,000.00 85,000.00
L.03 0.3 OH Kepala Tukang 85,000.00 95,000.00 25,500.00 28,500.00
L.04 0.05 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00
B Bahan 1,123,270.00 1,288,850.00
1.25 Btg Kayu Dolken Ø 8 - 10 / 4 m 18,000.00 20,000.00 22,500.00 25,000.00
0.18 m3 Kayu 4,800,000.00 5,550,000.00 864,000.00 999,000.00
0.85 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 11,050.00 12,750.00
1.1 Kg Besi Strip 12,500.00 13,500.00 13,750.00 14,850.00
35 Kg Portland Sement 1,250.00 1,300.00 43,750.00 45,500.00
0.15 m3 Pasir pasang 225,000.00 270,000.00 33,750.00 40,500.00
0.1 m3 Pasir Beton 320,000.00 350,000.00 32,000.00 35,000.00
0.15 m3 Koral Beton 280,000.00 325,000.00 42,000.00 48,750.00
30 buah Batu bata Merah 450.00 500.00 13,500.00 15,000.00
0.25 Lbr Seng Plat 14,000.00 25,000.00 3,500.00 6,250.00
2 buah Jendela Naco 12,000.00 12,500.00 24,000.00 25,000.00
0.08 m2 Kaca Polos 60,000.00 65,000.00 4,800.00 5,200.00
0.15 buah Kunci Tanam 65,000.00 70,000.00 9,750.00 10,500.00
0.3 buah Engsel 4,000.00 4,500.00 1,200.00 1,350.00
0.06 Lbr Plywood 4 mm 62,000.00 70,000.00 3,720.00 4,200.00
C PERALATAN
D Jumlah A + B + C 1,487,520.00 1,706,850.00
E Overhead & Profit (contah 10%) 10% 148,752.00 170,685.00
F Harga Satuan Pekerjaan (D+E) 1,636,272.00 1,877,535.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

4 A.2.2.1.7 1 m2 Pembuatan Gudang Semen dan Peralatan 1,514,672.50 1,747,240.00


A Tenaga 225,750.00 258,500.00
L.01 1 OH Pekerja 55,000.00 65,000.00 55,000.00 65,000.00
L.02 2 OH Tukang Kayu 75,000.00 85,000.00 150,000.00 170,000.00
L.03 0.2 OH Kepala Tukang 85,000.00 95,000.00 17,000.00 19,000.00
L.04 0.05 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00
B Bahan 1,151,225.00 1,329,900.00
1.7 Btg Kayu Dolken diameter 8 - 10 / 400 cm 18,000.00 20,000.00 30,600.00 34,000.00
0.21 m3 Kayu 4,800,000.00 5,550,000.00 1,008,000.00 1,165,500.00
0.3 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 3,900.00 4,500.00
10.5 Kg Portland Semen 1,250.00 1,300.00 13,125.00 13,650.00
0.03 m3 Pasir Beton 320,000.00 350,000.00 9,600.00 10,500.00
0.05 m3 Koral Beton 280,000.00 325,000.00 14,000.00 16,250.00
1.5 Lbr Seng Gelombang BJLS 32 48,000.00 57,000.00 72,000.00 85,500.00
C PERALATAN
D Jumlah A + B + C 1,376,975.00 1,588,400.00
E Overhead & Profit (contah 10%) 10% 137,697.50 158,840.00
F Harga Satuan Pekerjaan (D+E) 1,514,672.50 1,747,240.00

5 A.2.2.1.9 1 m2 Membersihkan Lapangan dan Perataan 10,175.00 12,100.00


A Tenaga 9,250.00 11,000.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.04 0.05 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00
B Bahan
C PERALATAN
D Jumlah A + B + C 9,250.00 11,000.00
E Overhead & Profit (contah 10%) 10% 925.00 1,100.00
F Harga Satuan Pekerjaan (D+E) 10,175.00 12,100.00

6 A.2.2.1.10 1 m2 Pembuatan Steger/Perancah dari Bambu 263,507.20 301,521.00


A Tenaga 225,750.00 258,500.00
L.01 1.00 OH Pekerja 55,000.00 65,000.00 55,000.00 65,000.00
L.02 2.00 OH Tukang Kayu 75,000.00 85,000.00 150,000.00 170,000.00
L.03 0.200 OH Kepala Tukang 85,000.00 95,000.00 17,000.00 19,000.00
L.04 0.0500 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00
B Bahan 13,802.00 15,610.00
1.250 Btg Bambu diameter 6 - 8 / 600 cm 10,000.00 11,000.00 12,500.00 13,750.00
0.186 Kg Tali Ijuk 7,000.00 10,000.00 1,302.00 1,860.00
C PERALATAN
D Jumlah A + B + C 239,552.00 274,110.00
E Overhead & Profit (contah 10%) 10% 23,955.20 27,411.00
F Harga Satuan Pekerjaan (D+E) 263,507.20 301,521.00

7 A.2.2.1.11 1 bh Pembuatan Kotak Adukan ukuran 40cmx50cmx25cm 424,699.00 509,685.00


A Tenaga 25,050.00 28,350.00
L.02 0.300 OH Tukang Kayu 75,000.00 85,000.00 22,500.00 25,500.00
L.03 0.030 OH Kepala Tukang 85,000.00 95,000.00 2,550.00 2,850.00
B Bahan 361,040.00 435,000.00
0.036 m3 Kayu Papan Kelas III 5,200,000.00 6,500,000.00 187,200.00 234,000.00
0.036 m3 Kayu Balok Kelas III 4,800,000.00 5,550,000.00 172,800.00 199,800.00
0.080 kg Paku Biasa 13,000.00 15,000.00 1,040.00 1,200.00
C PERALATAN
D Jumlah A + B + C 386,090.00 463,350.00
E Overhead & Profit (contah 10%) 10% 38,609.00 46,335.00
F Harga Satuan Pekerjaan (D+E) 424,699.00 509,685.00

8 A.2.2.1.13 1 m3 Bongkaran Beton Bertulang 861,652.00 1,019,315.00


A Tenaga 783,320.00 926,650.00
L.02 13.334 OH Pekerja 55,000.00 65,000.00 733,370.00 866,710.00
L.04 0.666 OH Mandor 75,000.00 90,000.00 49,950.00 59,940.00
B Bahan
C PERALATAN
D Jumlah A + B + C 783,320.00 926,650.00
E Overhead & Profit (contah 10%) 10% 78,332.00 92,665.00
F Harga Satuan Pekerjaan (D+E) 861,652.00 1,019,315.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PAKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.2.2.1.14 1 m3 Bongkaran Dinding Tembok Bata Merah 406,076.00 479,957.50
B Tenaga 369,160.00 436,325.00
L.02 6.667 OH Pekerja 55,000.00 65,000.00 366,685.00 433,355.00
L.04 0.033 OH Mandor 75,000.00 90,000.00 2,475.00 2,970.00
B Bahan
C PERALATAN
D Jumlah A + B + C 369,160.00 436,325.00
E Overhead & Profit (contah 10%) 10% 36,916.00 43,632.50
F Harga Satuan Pekerjaan (D+E) 406,076.00 479,957.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
II A.2.3.1 HARGA SATUAN PEKERJAAN TANAH

1 A.2.3.1.1 1 m3 Menggali Tanah Biasa Sedalam 1 m 47,437.50 56,100.00


A TENAGA 43,125.00 51,000.00
L.01 0.75 OH Pekerja 55,000.00 65,000.00 41,250.00 48,750.00
L.04 0.025 OH Mandor 75,000.00 90,000.00 1,875.00 2,250.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 43,125.00 51,000.00
E Overhead & Profit (contah 10%) 10% 4,312.50 5,100.00
F Harga Satuan Pekerjaan (D+E) 47,437.50 56,100.00
Overhead & Profit (contah 10%)
2 A.2.3.1.2 1 m3 Menggali Tanah Biasa Sedalam 2 m 58,162.50 68,805.00
A TENAGA 52,875.00 62,550.00
L.01 0.90 OH Pekerja 55,000.00 65,000.00 49,500.00 58,500.00
L.04 0.045 OH Mandor 75,000.00 90,000.00 3,375.00 4,050.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 52,875.00 62,550.00
E Overhead & Profit (contah 10%) 10% 5,287.50 6,255.00
F Harga Satuan Pekerjaan (D+E) 58,162.50 68,805.00

3 A.2.3.1.3 1 m3 Menggali Tanah Biasa Sedalam 3 m 69,052.50 81,708.00


A TENAGA 62,775.00 74,280.00
L.01 1.05 OH Pekerja 55,000.00 65,000.00 57,750.00 68,250.00
L.04 0.067 OH Mandor 75,000.00 90,000.00 5,025.00 6,030.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 62,775.00 74,280.00
E Overhead & Profit (contah 10%) 10% 6,277.50 7,428.00
F Harga Satuan Pekerjaan (D+E) 69,052.50 81,708.00

4 A.2.3.1.4 1 m3 Menggali Tanah Keras Sedalam 1 m 63,140.00 74,668.00


TENAGA 57,400.00 67,880.00
L.01 1.000 OH Pekerja 55,000.00 65,000.00 55,000.00 65,000.00
L.04 0.032 OH Mandor 75,000.00 90,000.00 2,400.00 2,880.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 57,400.00 67,880.00
E Overhead & Profit (contah 10%) 10% 5,740.00 6,788.00
F Harga Satuan Pekerjaan (D+E) 63,140.00 74,668.00

5 A.2.3.1.5 1 m3 Menggali Tanah Cadas Sedalam 1 m 95,700.00 113,190.00


A TENAGA 87,000.00 102,900.00
L.01 1.50 OH Pekerja 55,000.00 65,000.00 82,500.00 97,500.00
L.04 0.060 OH Mandor 75,000.00 90,000.00 4,500.00 5,400.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 87,000.00 102,900.00
E Overhead & Profit (contah 10%) 10% 8,700.00 10,290.00
F Harga Satuan Pekerjaan (D+E) 95,700.00 113,190.00

6 A.2.3.1.6 1 m3 Menggali Tanah Lumpur Sedalam 1 m 76,312.50 90,255.00


A TENAGA 69,375.00 82,050.00
L.01 1.200 OH Pekerja 55,000.00 65,000.00 66,000.00 78,000.00
L.04 0.045 OH Mandor 75,000.00 90,000.00 3,375.00 4,050.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 69,375.00 82,050.00
E Overhead & Profit (contah 10%) 10% 6,937.50 8,205.00
F Harga Satuan Pekerjaan (D+E) 76,312.50 90,255.00

7 A.2.3.1.7 1 m2 Mengerjakan Striping Tebing Setinggi 1 m 3,437.50 4,070.00


A TENAGA 3,125.00 3,700.00
L.01 0.05 OH Pekerja 55,000.00 65,000.00 2,750.00 3,250.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 3,125.00 3,700.00
E Overhead & Profit (contah 10%) 10% 312.50 370.00
F Harga Satuan Pekerjaan (D+E) 3,437.50 4,070.00

8 A.2.3.1.8 1 m3 MembuangTanah sejauh 30 m' 20,790.00 24,585.00


A TENAGA 18,900.00 22,350.00
L.01 0.330 OH Pekerja 55,000.00 65,000.00 18,150.00 21,450.00
L.04 0.010 OH Mandor 75,000.00 90,000.00 750.00 900.00

file:///conversion/tmp/scratch/443255086.xls 95/25 abk 2-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B BAHAN
C PERALATAN
D Jumlah A + B + C 18,900.00 22,350.00
E Overhead & Profit (contah 10%) 10% 1,890.00 2,235.00
F Harga Satuan Pekerjaan (D+E) 20,790.00 24,585.00

9 A.2.3.1.9 1 m3 Pengurugan Kembali


11,458.33 13,566.67
Pengurugan Kembali di hitung dari 1/3 kali koefisien Pekerjaan galian
A TENAGA 31,250.00 37,000.00
L.01 0.50 OH Pekerja 55,000.00 65,000.00 27,500.00 32,500.00
L.04 0.050 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 31,250.00 37,000.00
E Overhead & Profit (contah 10%) 10% 3,125.00 3,700.00
F Harga Satuan Pekerjaan (D+E) 34,375.00 40,700.00

10 A.2.3.1.10 1 m3 Pemadatan Tanah (per 20 cm) 34,375.00 40,700.00


A TENAGA 31,250.00 37,000.00
L.01 0.5 OH Pekerja 55,000.00 65,000.00 27,500.00 32,500.00
L.04 0.05 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00
B BAHAN
C PERALATAN
D Jumlah A + B + C 31,250.00 37,000.00
E Overhead & Profit (contah 10%) 10% 3,125.00 3,700.00
F Harga Satuan Pekerjaan (D+E) 34,375.00 40,700.00

11 A.2.3.1.11 1 m3 Urugan Pasir 177,375.00 220,440.00


A TENAGA 17,250.00 20,400.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.04 0.01 OH Mandor 75,000.00 90,000.00 750.00 900.00
B BAHAN 144,000.00 180,000.00
1.2 m3 Pasir Urug 120,000.00 150,000.00 144,000.00 180,000.00
C PERALATAN
D Jumlah A + B + C 161,250.00 200,400.00
E Overhead & Profit (contah 10%) 10% 16,125.00 20,040.00
F Harga Satuan Pekerjaan (D+E) 177,375.00 220,440.00

12 A.2.3.1.12 1 m3 Lapisan Pudel Cmp. 1Kp : 3Ps : 7TL 244,832.50 293,755.00


A TENAGA 83,400.00 97,000.00
L.01 0.800 OH Pekerja 55,000.00 65,000.00 44,000.00 52,000.00
L.02 0.400 OH Tukang Batu 75,000.00 85,000.00 30,000.00 34,000.00
L.03 0.04 OH Kepala Tukang 85,000.00 95,000.00 3,400.00 3,800.00
L.04 0.080 OH Mandor 75,000.00 90,000.00 6,000.00 7,200.00
B BAHAN 139,175.00 170,050.00
0.135 m3 Pasir Pasang 225,000.00 270,000.00 30,375.00 36,450.00
0.400 m3 Kapur Padam 250,000.00 310,000.00 100,000.00 124,000.00
0.080 m3 Tanah Liat 110,000.00 120,000.00 8,800.00 9,600.00
C PERALATAN
D Jumlah A + B + C 222,575.00 267,050.00
E Overhead & Profit (contah 10%) 10% 22,257.50 26,705.00
F Harga Satuan Pekerjaan (D+E) 244,832.50 293,755.00

13 A.2.3.1.13 1 m2 Pemasangan Lapisan Ijuk tebal 10 cm unt Bidang Resapan 56,512.50 78,210.00
A TENAGA 9,375.00 11,100.00
0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B BAHAN 42,000.00 60,000.00
6.00 kg Ijuk 7,000.00 10,000.00 42,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 51,375.00 71,100.00
E Overhead & Profit (contah 10%) 10% 5,137.50 7,110.00
F Harga Satuan Pekerjaan (D+E) 56,512.50 78,210.00

14 A.2.3.1.14 1 m3 Mengurug Sirtu Padat 175,587.50 191,950.00


A TENAGA 15,625.00 18,500.00
0.25 OH Pekerja 55,000.00 65,000.00 13,750.00 16,250.00
0.025 OH Mandor 75,000.00 90,000.00 1,875.00 2,250.00
B BAHAN 144,000.00 156,000.00
1.2 m3 Sirtu 120,000.00 130,000.00 144,000.00 156,000.00
C PERALATAN
D Jumlah A + B + C 159,625.00 174,500.00
E Overhead & Profit (contah 10%) 10% 15,962.50 17,450.00
F Harga Satuan Pekerjaan (D+E) 175,587.50 191,950.00

file:///conversion/tmp/scratch/443255086.xls 95/26 abk 2-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
III A.3.2.1. HARGA SATUAN PEKERJAAN PONDASI
1 A.3.2.1.1 1 m3 Pemasangan Pondasi Batu Belah 1SP : 3 PP 827,612.50 902,742.50
A TENAGA 150,750.00 175,125.00
L.01 1.5 OH Pekerja 55,000.00 65,000.00 82,500.00 97,500.00
L.02 0.750 OH Tukang Batu 75,000.00 85,000.00 56,250.00 63,750.00
L.03 0.075 OH Kepala Tukang 85,000.00 95,000.00 6,375.00 7,125.00
L.04 0.075 OH Mandor 75,000.00 90,000.00 5,625.00 6,750.00
B BAHAN 601,625.00 645,550.00
1.2 m3 Batu Belah 15/20 200,000.00 210,000.00 240,000.00 252,000.00
202 Kg Portland Sement 1,250.00 1,300.00 252,500.00 262,600.00
0.485 m3 Pasir Pasang 225,000.00 270,000.00 109,125.00 130,950.00
C PERALATAN
D Jumlah A + B + C 752,375.00 820,675.00
E Overhead & Profit (contoh 10%) 10% 75,237.50 82,067.50
F Harga Satuan Pekerjaan (D+E) 827,612.50 902,742.50
Overhead & Profit (contoh 10%)
2 A.3.2.1.2 1 m3 Pemasangan Pondasi Batu Belah 1SP : 4 PP 782,650.00 857,367.50
A TENAGA 150,750.00 175,125.00
L.01 1.5 OH Pekerja 55,000.00 65,000.00 82,500.00 97,500.00
L.02 0.750 OH Tukang Batu 75,000.00 85,000.00 56,250.00 63,750.00
L.03 0.075 OH Kepala Tukang 85,000.00 95,000.00 6,375.00 7,125.00
L.04 0.075 OH Mandor 75,000.00 90,000.00 5,625.00 6,750.00
B BAHAN 560,750.00 604,300.00
1.2 m3 Batu Belah 15/20 200,000.00 210,000.00 240,000.00 252,000.00
163 Kg Portland Sement 1,250.00 1,300.00 203,750.00 211,900.00
0.52 m3 Pasir Pasang 225,000.00 270,000.00 117,000.00 140,400.00
C PERALATAN
D Jumlah A + B + C 711,500.00 779,425.00
E Overhead & Profit (contoh 10%) 10% 71,150.00 77,942.50
F Harga Satuan Pekerjaan (D+E) 782,650.00 857,367.50

3 A.3.2.1.3 1 m3 Pemasangan Pondasi Batu Belah 1SP : 5 PP 751,465.00 825,885.50


A TENAGA 150,750.00 175,125.00
L.01 1.5 OH Pekerja 55,000.00 65,000.00 82,500.00 97,500.00
L.02 0.750 OH Tukang Batu 75,000.00 85,000.00 56,250.00 63,750.00
L.03 0.075 OH Kepala Tukang 85,000.00 95,000.00 6,375.00 7,125.00
L.04 0.075 OH Mandor 75,000.00 90,000.00 5,625.00 6,750.00
B BAHAN 532,400.00 575,680.00
1.2 m3 Batu Belah 15/20 200,000.00 210,000.00 240,000.00 252,000.00
136 Kg Portland Sement 1,250.00 1,300.00 170,000.00 176,800.00
0.544 m3 Pasir Pasang 225,000.00 270,000.00 122,400.00 146,880.00
C PERALATAN
D Jumlah A + B + C 683,150.00 750,805.00
E Overhead & Profit (contoh 10%) 10% 68,315.00 75,080.50
F Harga Satuan Pekerjaan (D+E) 751,465.00 825,885.50

4 A.3.2.1.4 1 m3 Pemasangan Pondasi Batu Belah 1SP : 6 PP 729,547.50 803,764.50


A TENAGA 150,750.00 175,125.00
L.01 1.5 OH Pekerja 55,000.00 65,000.00 82,500.00 97,500.00
L.02 0.750 OH Tukang Batu 75,000.00 85,000.00 56,250.00 63,750.00
L.03 0.075 OH Kepala Tukang 85,000.00 95,000.00 6,375.00 7,125.00
L.04 0.075 OH Mandor 75,000.00 90,000.00 5,625.00 6,750.00
B BAHAN 512,475.00 555,570.00
1.2 m3 Batu Belah 15/20 200,000.00 210,000.00 240,000.00 252,000.00
117 Kg Portland Sement 1,250.00 1,300.00 146,250.00 152,100.00
0.561 m3 Pasir Pasang 225,000.00 270,000.00 126,225.00 151,470.00
C PERALATAN
D Jumlah A + B + C 663,225.00 730,695.00
E Overhead & Profit (contoh 10%) 10% 66,322.50 73,069.50
F Harga Satuan Pekerjaan (D+E) 729,547.50 803,764.50

5 A.3.2.1.5 1 m3 Pemasangan Pondasi Batu Belah 1SP : 8 PP 699,490.00 773,415.50


A Tenaga 150,750.00 175,125.00
L.01 1.5 OH Pekerja 55,000.00 65,000.00 82,500.00 97,500.00
L.02 0.750 OH Tukang Batu 75,000.00 85,000.00 56,250.00 63,750.00
L.03 0.075 OH Kepala Tukang 85,000.00 95,000.00 6,375.00 7,125.00
L.04 0.075 OH Mandor 75,000.00 90,000.00 5,625.00 6,750.00

file:///conversion/tmp/scratch/443255086.xls 95/27 abk 3-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 485,150.00 527,980.00
1.2 m3 Batu Belah 15/20 200,000.00 210,000.00 240,000.00 252,000.00
91 Kg Portland Sement 1,250.00 1,300.00 113,750.00 118,300.00
0.584 m3 Pasir Pasang 225,000.00 270,000.00 131,400.00 157,680.00
C PERALATAN
D Jumlah A + B + C 635,900.00 703,105.00
E Overhead & Profit (contoh 10%) 10% 63,590.00 70,310.50
F Harga Satuan Pekerjaan (D+E) 699,490.00 773,415.50

6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 593,450.00 663,382.50
A Tenaga 150,750.00 175,125.00
L.01 1.5 OH Pekerja 55,000.00 65,000.00 82,500.00 97,500.00
L.02 0.750 OH Tukang Batu 75,000.00 85,000.00 56,250.00 63,750.00
L.03 0.075 OH Kepala Tukang 85,000.00 95,000.00 6,375.00 7,125.00
L.04 0.075 OH Mandor 75,000.00 90,000.00 5,625.00 6,750.00
B Bahan 388,750.00 427,950.00
1.2 m3 Batu Belah 15/20 200,000.00 210,000.00 240,000.00 252,000.00
0.17 m3 Kapur Pasang (KP) 250,000.00 310,000.00 42,500.00 52,700.00
0.17 Kg Semen Merah (SM) 175,000.00 185,000.00 29,750.00 31,450.00
0.340 m3 Pasir Pasang 225,000.00 270,000.00 76,500.00 91,800.00
C PERALATAN
D Jumlah A + B + C 539,500.00 603,075.00
E Overhead & Profit (contoh 10%) 10% 53,950.00 60,307.50
F Harga Satuan Pekerjaan (D+E) 593,450.00 663,382.50

7 A.3.2.1.7 1 m3 Pemasangan Pondasi Batu Belah, 1 SP : 3 KP : 10 PP 675,895.00 753,318.50


A Tenaga 150,750.00 175,125.00
L.01 1.5 OH Pekerja 55,000.00 65,000.00 82,500.00 97,500.00
L.02 0.750 OH Tukang Batu 75,000.00 85,000.00 56,250.00 63,750.00
L.03 0.075 OH Kepala Tukang 85,000.00 95,000.00 6,375.00 7,125.00
L.04 0.075 OH Mandor 75,000.00 90,000.00 5,625.00 6,750.00
B Bahan 463,700.00 509,710.00
1.2 m3 Batu Belah 15/20 200,000.00 210,000.00 240,000.00 252,000.00
61 kg Portland Sement 1,250.00 1,300.00 76,250.00 79,300.00
0.147 m3 Kapur Pasang 250,000.00 310,000.00 36,750.00 45,570.00
0.492 m3 Pasir Pasang 225,000.00 270,000.00 110,700.00 132,840.00
C PERALATAN
D Jumlah A + B + C 614,450.00 684,835.00
E Overhead & Profit (contoh 10%) 10% 61,445.00 68,483.50
F Harga Satuan Pekerjaan (D+E) 675,895.00 753,318.50

8 A.3.2.1.8 1 m3 Pemasangan Pondasi Batu Belah, ¼ SP : 1KP : 4 PP 643,995.00 719,262.50


A Tenaga 150,750.00 175,125.00
L.01 1.5 OH Pekerja 55,000.00 65,000.00 82,500.00 97,500.00
L.02 0.750 OH Tukang Batu 75,000.00 85,000.00 56,250.00 63,750.00
L.03 0.075 OH Kepala Tukang 85,000.00 95,000.00 6,375.00 7,125.00
L.04 0.075 OH Mandor 75,000.00 90,000.00 5,625.00 6,750.00
B Bahan 434,700.00 478,750.00
1.2 m3 Batu Belah 15/20 200,000.00 210,000.00 240,000.00 252,000.00
41 kg Portland Sement 1,250.00 1,300.00 51,250.00 53,300.00
0.131 m3 Kapur Pasang 250,000.00 310,000.00 32,750.00 40,610.00
0.492 m3 Pasir 225,000.00 270,000.00 110,700.00 132,840.00
C PERALATAN
D Jumlah A + B + C 585,450.00 653,875.00
E Overhead & Profit (contoh 10%) 10% 58,545.00 65,387.50
F Harga Satuan Pekerjaan (D+E) 643,995.00 719,262.50

9 A.3.2.1.9 1 m3 Pemasang Batu Kosong/Anstamping 407,253.00 448,651.50


A Tenaga 78,390.00 91,065.00
L.01 0.78 OH Pekerja 55,000.00 65,000.00 42,900.00 50,700.00
L.02 0.39 OH Tukang Batu 75,000.00 85,000.00 29,250.00 33,150.00
L.03 0.039 OH Kepala Tukang 85,000.00 95,000.00 3,315.00 3,705.00
L.04 0.039 OH Mandor 75,000.00 90,000.00 2,925.00 3,510.00
B Bahan 291,840.00 316,800.00
1.2 m3 Batu Belah 15/20 200,000.00 210,000.00 240,000.00 252,000.00
0.432 m3 Pasir Urug 120,000.00 150,000.00 51,840.00 64,800.00
C PERALATAN
D Jumlah A + B + C 370,230.00 407,865.00
E Overhead & Profit (contoh 10%) 10% 37,023.00 40,786.50

file:///conversion/tmp/scratch/443255086.xls 95/28 abk 3-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 407,253.00 448,651.50

file:///conversion/tmp/scratch/443255086.xls 95/29 abk 3-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
10 A.3.2.1.10 1 m3 Pasang Pondasi Siklop, 60% Beton Camp. 1PC : 2PB : 3KR & 40% Batu Belah 2,188,081.50 2,414,769.50
A Tenaga 269,225.00 314,825.00
L.01 3.4 OH Pekerja 55,000.00 65,000.00 187,000.00 221,000.00
L.02 0.85 OH Tukang Batu 75,000.00 85,000.00 63,750.00 72,250.00
L.03 0.085 OH Kepala Tukang 85,000.00 95,000.00 7,225.00 8,075.00
L.04 0.15 OH Mandor 75,000.00 90,000.00 11,250.00 13,500.00
B Bahan 1,719,940.00 1,880,420.00
0.480 m3 Batu Belah 15/20 cm 200,000.00 210,000.00 96,000.00 100,800.00
126 Kg Besi Beton 9,500.00 10,500.00 1,197,000.00 1,323,000.00
194 Kg Portland Semen 1,250.00 1,300.00 242,500.00 252,200.00
0.312 m3 Pasir Beton 320,000.00 350,000.00 99,840.00 109,200.00
0.468 m3 Koral Beton 125,000.00 140,000.00 58,500.00 65,520.00
1.8 Kg Kawat Beton 14,500.00 16,500.00 26,100.00 29,700.00
C PERALATAN
D Jumlah A + B + C 1,989,165.00 2,195,245.00
E Overhead & Profit (contoh 10%) 10% 198,916.50 219,524.50
F Harga Satuan Pekerjaan (D+E) 2,188,081.50 2,414,769.50

11 A.3.2.1.11 1 m3 Pasang Pondasi Sumuran diameter 100 cm 768,421.50 840,103.00


A Tenaga 207,725.00 242,310.00
L.01 2.40 OH Pekerja 55,000.00 65,000.00 132,000.00 156,000.00
L.02 0.8 OH Tukang Batu 75,000.00 85,000.00 60,000.00 68,000.00
L.03 0.08 OH Kepala Tukang 85,000.00 95,000.00 6,800.00 7,600.00
L.04 0.119 OH Mandor 75,000.00 90,000.00 8,925.00 10,710.00
B Bahan 490,840.00 521,420.00
0.45 m3 Batu Belah 15/20 cm 200,000.00 210,000.00 90,000.00 94,500.00
194 Kg Portland Semen 1,250.00 1,300.00 242,500.00 252,200.00
0.312 m3 Pasir Beton 320,000.00 350,000.00 99,840.00 109,200.00
0.468 m3 Koral Beton 125,000.00 140,000.00 58,500.00 65,520.00
C PERALATAN
D Jumlah A + B + C 698,565.00 763,730.00
E Overhead & Profit (contoh 10%) 10% 69,856.50 76,373.00
F Harga Satuan Pekerjaan (D+E) 768,421.50 840,103.00

file:///conversion/tmp/scratch/443255086.xls 95/30 abk 3-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

IV A.4.4.1 HARGA SATUAN PEKERJAAN PASANGAN DINDING


1 A.4.4.1.1 1 m2 Pemasangan Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 bata Camp. 1SP: 2PP 206,057.50 229,625.00
A Tenaga 51,950.00 60,600.00
L.01 0.6 OH Pekerja 55,000.00 65,000.00 33,000.00 39,000.00
L.02 0.2 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang Batu 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 135,375.00 148,150.00
140 Buah Bata Merah 450.00 500.00 63,000.00 70,000.00
43.5 Kg Portland Semen (PC) 1,250.00 1,300.00 54,375.00 56,550.00
0.08 m3 Pasir Pasang (PP) 225,000.00 270,000.00 18,000.00 21,600.00
C PERALATAN
D Jumlah A + B + C 187,325.00 208,750.00
E Overhead & Profit (contoh 10%) 10% 18,732.50 20,875.00
F Harga Satuan Pekerjaan (D+E) 206,057.50 229,625.00
Overhead & Profit (contoh 10%)
2 A.4.4.1.2 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP 194,273.75 217,805.50
A Tenaga 51,950.00 60,600.00
L.01 0.6 OH Pekerja 55,000.00 65,000.00 33,000.00 39,000.00
L.02 0.2 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang Batu 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 124,662.50 137,405.00
140 Buah Bata Merah 450.00 500.00 63,000.00 70,000.00
32.95 Kg Portland Semen (PC) 1,250.00 1,300.00 41,187.50 42,835.00
0.091 m3 Pasir Pasang (PP) 225,000.00 270,000.00 20,475.00 24,570.00
C PERALATAN
D Jumlah A + B + C 176,612.50 198,005.00
E Overhead & Profit (contoh 10%) 10% 17,661.25 19,800.50
F Harga Satuan Pekerjaan (D+E) 194,273.75 217,805.50

3 A.4.4.1.3 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP 185,968.75 209,247.50
A Tenaga 51,950.00 60,600.00
L.01 0.6 OH Pekerja 55,000.00 65,000.00 33,000.00 39,000.00
L.02 0.2 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang Batu 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 117,112.50 129,625.00
140 Buah Bata Merah 450.00 500.00 63,000.00 70,000.00
26.55 Kg Portland Semen (PC) 1,250.00 1,300.00 33,187.50 34,515.00
0.093 m3 Pasir Pasang (PP) 225,000.00 270,000.00 20,925.00 25,110.00
C PERALATAN
D Jumlah A + B + C 169,062.50 190,225.00
E Overhead & Profit (contoh 10%) 10% 16,906.25 19,022.50
F Harga Satuan Pekerjaan (D+E) 185,968.75 209,247.50

4 A.4.4.1.4 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP 182,215.00 205,700.00
A Tenaga 51,950.00 60,600.00
L.01 0.6 OH Pekerja 55,000.00 65,000.00 33,000.00 39,000.00
L.02 0.2 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang Batu 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 113,700.00 126,400.00
140 Buah Bata Merah 450.00 500.00 63,000.00 70,000.00
22.2 Kg Portland Semen (PC) 1,250.00 1,300.00 27,750.00 28,860.00
0.102 m3 Pasir Pasang (PP) 225,000.00 270,000.00 22,950.00 27,540.00
C PERALATAN
D Jumlah A + B + C 165,650.00 187,000.00
E Overhead & Profit (contoh 10%) 10% 16,565.00 18,700.00
F Harga Satuan Pekerjaan (D+E) 182,215.00 205,700.00

file:///conversion/tmp/scratch/443255086.xls 95/31 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.4.1.5 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP 182,077.50 206,349.00
A Tenaga 51,950.00 60,600.00
L.01 0.6 OH Pekerja 55,000.00 65,000.00 33,000.00 39,000.00
L.02 0.2 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang Batu 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 113,575.00 126,990.00
140 Buah Bata Merah 450.00 500.00 63,000.00 70,000.00
18.5 Kg Portland Semen (PC) 1,250.00 1,300.00 23,125.00 24,050.00
0.122 m3 Pasir Pasang (PP) 225,000.00 270,000.00 27,450.00 32,940.00
C PERALATAN
D Jumlah A + B + C 165,525.00 187,590.00
E Overhead & Profit (contoh 10%) 10% 16,552.50 18,759.00
F Harga Satuan Pekerjaan (D+E) 182,077.50 206,349.00

6 A.4.4.1.6 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP 170,761.25 194,924.40
A Tenaga 51,950.00 60,600.00
L.01 0.6 OH Pekerja 55,000.00 65,000.00 33,000.00 39,000.00
L.02 0.2 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang Batu 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 103,287.50 116,604.00
140 Buah Bata Merah 450.00 500.00 63,000.00 70,000.00
10.08 Kg Portland Semen (PC) 1,250.00 1,300.00 12,600.00 13,104.00
0.0925 m3 Pasir Pasang (PP) 225,000.00 270,000.00 20,812.50 24,975.00
0.0275 m3 Kapur Pasang (KP) 250,000.00 310,000.00 6,875.00 8,525.00
C PERALATAN
D Jumlah A + B + C 155,237.50 177,204.00
E Overhead & Profit (contoh 10%) 10% 15,523.75 17,720.40
F Harga Satuan Pekerjaan (D+E) 170,761.25 194,924.40

7 A.4.4.1.7 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP 98,683.75 110,214.50
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 63,737.50 69,895.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
18.95 Kg Portland Semen 1,250.00 1,300.00 23,687.50 24,635.00
0.038 m3 Pasir Pasang 225,000.00 270,000.00 8,550.00 10,260.00
C PERALATAN
D Jumlah A + B + C 89,712.50 100,195.00
E Overhead & Profit (contoh 10%) 10% 8,971.25 10,019.50
F Harga Satuan Pekerjaan (D+E) 98,683.75 110,214.50

8 A.4.4.1.8 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP 92,881.25 104,259.10
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 58,462.50 64,481.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
14.37 Kg Portland Semen 1,250.00 1,300.00 17,962.50 18,681.00
0.04 m3 Pasir Pasang 225,000.00 270,000.00 9,000.00 10,800.00
C PERALATAN
D Jumlah A + B + C 84,437.50 94,781.00
E Overhead & Profit (contoh 10%) 10% 8,443.75 9,478.10
F Harga Satuan Pekerjaan (D+E) 92,881.25 104,259.10

file:///conversion/tmp/scratch/443255086.xls 95/32 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.4.4.1.9 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP 89,677.50 101,046.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 55,550.00 61,560.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
11.50 Kg Portland Semen 1,250.00 1,300.00 14,375.00 14,950.00
0.043 m3 Pasir Pasang 225,000.00 270,000.00 9,675.00 11,610.00
C PERALATAN
D Jumlah A + B + C 81,525.00 91,860.00
E Overhead & Profit (contoh 10%) 10% 8,152.50 9,186.00
F Harga Satuan Pekerjaan (D+E) 89,677.50 101,046.00

10 A.4.4.1.10 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP 87,670.00 99,037.40
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 53,725.00 59,734.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
9.68 Kg Portland Semen 1,250.00 1,300.00 12,100.00 12,584.00
0.045 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 79,700.00 90,034.00
E Overhead & Profit (contoh 10%) 10% 7,970.00 9,003.40
F Harga Satuan Pekerjaan (D+E) 87,670.00 99,037.40

11 A.4.4.1.11 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP 86,790.00 98,280.60
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 52,925.00 59,046.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
8.32 Kg Portland Semen 1,250.00 1,300.00 10,400.00 10,816.00
0.049 m3 Pasir Pasang 225,000.00 270,000.00 11,025.00 13,230.00
C PERALATAN
D Jumlah A + B + C 78,900.00 89,346.00
E Overhead & Profit (contoh 10%) 10% 7,890.00 8,934.60
F Harga Satuan Pekerjaan (D+E) 86,790.00 98,280.60

12 A.4.4.1.12 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP 84,535.00 95,975.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 50,875.00 56,950.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
6.50 Kg Portland Semen 1,250.00 1,300.00 8,125.00 8,450.00
0.05 m3 Pasir Pasang 225,000.00 270,000.00 11,250.00 13,500.00
C PERALATAN
D Jumlah A + B + C 76,850.00 87,250.00
E Overhead & Profit (contoh 10%) 10% 7,685.00 8,725.00
F Harga Satuan Pekerjaan (D+E) 84,535.00 95,975.00

file:///conversion/tmp/scratch/443255086.xls 95/33 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
13 A.4.4.1.13 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP 85,910.00 98,230.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 52,125.00 59,000.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
4.5 Kg Portland Semen 1,250.00 1,300.00 5,625.00 5,850.00
0.05 m3 Pasir Pasang 225,000.00 270,000.00 11,250.00 13,500.00
0.015 m3 Kapur Padam 250,000.00 310,000.00 3,750.00 4,650.00
C PERALATAN
D Jumlah A + B + C 78,100.00 89,300.00
E Overhead & Profit (contoh 10%) 10% 7,810.00 8,930.00
F Harga Satuan Pekerjaan (D+E) 85,910.00 98,230.00

14 A.4.4.1.14 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1SM : 1PP 76,092.50 86,977.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 43,200.00 48,770.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
0.018 m3 Semen Merah 175,000.00 185,000.00 3,150.00 3,330.00
0.018 m3 Pasir Pasang 225,000.00 270,000.00 4,050.00 4,860.00
0.018 m3 Kapur Padam 250,000.00 310,000.00 4,500.00 5,580.00
C PERALATAN
D Jumlah A + B + C 69,175.00 79,070.00
E Overhead & Profit (contoh 10%) 10% 6,917.50 7,907.00
F Harga Satuan Pekerjaan (D+E) 76,092.50 86,977.00

15 A.4.4.1.15 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1KP : 1SM : 2PP 76,697.50 87,769.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 43,750.00 49,490.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
0.014 m3 Semen Merah 175,000.00 185,000.00 2,450.00 2,590.00
0.028 m3 Pasir Pasang 225,000.00 270,000.00 6,300.00 7,560.00
0.014 m3 Kapur Padam 250,000.00 310,000.00 3,500.00 4,340.00
C PERALATAN
D Jumlah A + B + C 69,725.00 79,790.00
E Overhead & Profit (contoh 10%) 10% 6,972.50 7,979.00
F Harga Satuan Pekerjaan (D+E) 76,697.50 87,769.00

16 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 190,558.50 224,788.30
A Tenaga 25,975.00 30,300.00
L.01 0.300 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.100 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.010 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 147,260.00 174,053.00
12.500 buah Batako 3,500.00 4,250.00 43,750.00 53,125.00
15.160 kg PC 1,250.00 1,300.00 18,950.00 19,708.00
0.364 m3 Pasir Pasang 225,000.00 270,000.00 81,900.00 98,280.00
0.280 kg Besi Angkur Ø 8 mm 9,500.00 10,500.00 2,660.00 2,940.00

file:///conversion/tmp/scratch/443255086.xls 95/34 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 173,235.00 204,353.00
E Overhead & Profit (contoh 10%) 10% 17,323.50 20,435.30
F Harga Satuan Pekerjaan (D+E) 190,558.50 224,788.30

17 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 192,332.25 227,583.40
A Tenaga 25,975.00 30,300.00
L.01 0.300 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.100 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.010 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00

B Bahan 148,872.50 176,594.00


12.500 buah Batako 3,500.00 4,250.00 43,750.00 53,125.00
12.130 kg PC 1,250.00 1,300.00 15,162.50 15,769.00
0.388 m3 Pasir Pasang 225,000.00 270,000.00 87,300.00 104,760.00
0.280 kg Besi Angkur Ø 8 mm 9,500.00 10,500.00 2,660.00 2,940.00
C PERALATAN
D Jumlah A + B + C 174,847.50 206,894.00
E Overhead & Profit (contoh 10%) 10% 17,484.75 20,689.40
F Harga Satuan Pekerjaan (D+E) 192,332.25 227,583.40

18 A.4.4.1.22 1 m2 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 2PP 240,542.50 310,354.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 192,700.00 251,840.00
30 Buah Terawang / Roster 5,600.00 7,500.00 168,000.00 225,000.00
14 kg Portland Semen 1,250.00 1,300.00 17,500.00 18,200.00
0.032 m3 Pasir Pasang 225,000.00 270,000.00 7,200.00 8,640.00
C PERALATAN
D Jumlah A + B + C 218,675.00 282,140.00
E Overhead & Profit (contoh 10%) 10% 21,867.50 28,214.00
F Harga Satuan Pekerjaan (D+E) 240,542.50 310,354.00

19 A.4.4.1.23 1 m2 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP 237,160.00 306,955.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 189,625.00 248,750.00
30 Buah Terawang / Roster 5,600.00 7,500.00 168,000.00 225,000.00
11 kg Portland Semen 1,250.00 1,300.00 13,750.00 14,300.00
0.035 m3 Pasir Pasang 225,000.00 270,000.00 7,875.00 9,450.00
C PERALATAN
D Jumlah A + B + C 215,600.00 279,050.00
E Overhead & Profit (contoh 10%) 10% 21,560.00 27,905.00
F Harga Satuan Pekerjaan (D+E) 237,160.00 306,955.00

file:///conversion/tmp/scratch/443255086.xls 95/35 abk 4-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
V A.4.4.2 HARGA SATUAN PEKERJAAN PLESTERAN
1 A,4,4,2.1 1 m2 Pemasangan Plesteran 1 Pc : 1 Pp Tebal 15 mm 58,443.00 65,450.22
A Tenaga 30,150.00 35,025.00
L.01 0.3 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.15 OH Tukang batu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 22,980.00 24,475.20
15.504 Kg Portland Semen 1,250.00 1,300.00 19,380.00 20,155.20
0.016 m3 Pasir Pasang 225,000.00 270,000.00 3,600.00 4,320.00
C PERALATAN
D Jumlah A + B + C 53,130.00 59,500.20
E Overhead & Profit (contoh 10%) 10% 5,313.00 5,950.02
F Harga Satuan Pekerjaan (D+E) 58,443.00 65,450.22
Overhead & Profit (contoh 10%)
2 A,4,4,2.2 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 15 mm 52,173.00 59,087.82
A Tenaga 30,150.00 35,025.00
L.01 0.3 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.15 OH Tukang batu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 17,280.00 18,691.20
10.224 Kg Portland Semen 1,250.00 1,300.00 12,780.00 13,291.20
0.020 m3 Pasir Pasang 225,000.00 270,000.00 4,500.00 5,400.00
C PERALATAN
D Jumlah A + B + C 47,430.00 53,716.20
E Overhead & Profit (contoh 10%) 10% 4,743.00 5,371.62
F Harga Satuan Pekerjaan (D+E) 52,173.00 59,087.82
3 A,4,4,2.3 1 m2 Pemasangan Plesteran 1 Pc : 3 Pp Tebal 15 mm 49,549.50 56,478.18
A Tenaga 30,150.00 35,025.00
L.01 0.3 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.15 OH Tukang batu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 14,895.00 16,318.80
7.776 Kg Portland Semen 1,250.00 1,300.00 9,720.00 10,108.80
0.023 m3 Pasir Pasang 225,000.00 270,000.00 5,175.00 6,210.00
C PERALATAN
D Jumlah A + B + C 45,045.00 51,343.80
E Overhead & Profit (contoh 10%) 10% 4,504.50 5,134.38
F Harga Satuan Pekerjaan (D+E) 49,549.50 56,478.18
4 A,4,4,2.4 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 15 mm 47,685.00 54,578.70
A Tenaga 30,150.00 35,025.00
L.01 0.3 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.15 OH Tukang batu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 13,200.00 14,592.00
6.240 Kg Portland Semen 1,250.00 1,300.00 7,800.00 8,112.00
0.024 m3 Pasir Pasang 225,000.00 270,000.00 5,400.00 6,480.00
C PERALATAN
D Jumlah A + B + C 43,350.00 49,617.00
E Overhead & Profit (contoh 10%) 10% 4,335.00 4,961.70
F Harga Satuan Pekerjaan (D+E) 47,685.00 54,578.70
5 A,4,4,2.5 1 m2 Pemasangan Plesteran 1 Pc : 5 Pp Tebal 15 mm 46,728.00 53,662.62
A Tenaga 30,150.00 35,025.00
L.01 0.3 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.15 OH Tukang batu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 12,330.00 13,759.20
5.184 Kg Portland Semen 1,250.00 1,300.00 6,480.00 6,739.20
0.026 m3 Pasir Pasang 225,000.00 270,000.00 5,850.00 7,020.00
C PERALATAN
D Jumlah A + B + C 42,480.00 48,784.20
E Overhead & Profit (contoh 10%) 10% 4,248.00 4,878.42
F Harga Satuan Pekerjaan (D+E) 46,728.00 53,662.62
6 A,4,4,2.6 1 m2 Pemasangan Plesteran 1 Pc : 6 Pp Tebal 15 mm 45,919.50 52,861.38
Tenaga 30,150.00 35,025.00
L.01 0.3 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.15 OH Tukang batu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
Bahan 11,595.00 13,030.80
4.416 Kg Portland Semen 1,250.00 1,300.00 5,520.00 5,740.80
0.027 m3 Pasir Pasang 225,000.00 270,000.00 6,075.00 7,290.00
C PERALATAN
D Jumlah A + B + C 41,745.00 48,055.80
E Overhead & Profit (contoh 10%) 10% 4,174.50 4,805.58
F Harga Satuan Pekerjaan (D+E) 45,919.50 52,861.38

file:///conversion/tmp/scratch/443255086.xls 95/36 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
7 A,4,4,2.7 1 m2 Pemasangan Plesteran 1 Pc : 7 Pp Tebal 15 mm 45,507.00 52,471.98
A Tenaga 30,150.00 35,025.00
L.01 0.3 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.15 OH Tukang batu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 11,220.00 12,676.80
3.936 Kg Portland Semen 1,250.00 1,300.00 4,920.00 5,116.80
0.028 m3 Pasir Pasang 225,000.00 270,000.00 6,300.00 7,560.00
C PERALATAN
D Jumlah A + B + C 41,370.00 47,701.80
E Overhead & Profit (contoh 10%) 10% 4,137.00 4,770.18
F Harga Satuan Pekerjaan (D+E) 45,507.00 52,471.98
8 A,4,4,2.8 1 m2 Pemasangan Plesteran 1 Pc : 8 Pp Tebal 15 mm 45,094.50 52,082.58
A Tenaga 30,150.00 35,025.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.15 OH Tukang batu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 10,845.00 12,322.80
3.456 Kg Portland Semen 1,250.00 1,300.00 4,320.00 4,492.80
0.029 m3 Pasir Pasang 225,000.00 270,000.00 6,525.00 7,830.00
C PERALATAN
D Jumlah A + B + C 40,995.00 47,347.80
E Overhead & Profit (contoh 10%) 10% 4,099.50 4,734.78
F Harga Satuan Pekerjaan (D+E) 45,094.50 52,082.58
9 A.4.4.2.9 1 m2 Pemasangan Plesteran 1 Pc : 1/2 Kp : 3 Pp Tebal 15 mm 46,249.50 53,116.80
A Tenaga 31,170.00 36,360.00
L.01 0.36 OH Pekerja 55,000.00 65,000.00 19,800.00 23,400.00
L.02 0.12 OH Tukang batu 75,000.00 85,000.00 9,000.00 10,200.00
L.03 0.012 OH Kepala Tukang 85,000.00 95,000.00 1,020.00 1,140.00
L.04 0.018 OH Mandor 75,000.00 90,000.00 1,350.00 1,620.00
B Bahan 10,875.00 11,928.00
5.760 Kg Portland Semen 1,250.00 1,300.00 7,200.00 7,488.00
0.003 m3 Kapur Pasang 250,000.00 310,000.00 750.00 930.00
0.013 m3 Pasir Pasang 225,000.00 270,000.00 2,925.00 3,510.00
C PERALATAN
D Jumlah A + B + C 42,045.00 48,288.00
E Overhead & Profit (contoh 10%) 10% 4,204.50 4,828.80
F Harga Satuan Pekerjaan (D+E) 46,249.50 53,116.80
10 A,4,4,2.10 1 m2 Pemasangan Plesteran 1 Pc : 2 Kp : 8 Pp Tebal 15 mm 44,737.00 51,931.00
A Tenaga 31,170.00 36,360.00
L.01 0.36 OH Pekerja 55,000.00 65,000.00 19,800.00 23,400.00
L.02 0.12 OH Tukang batu 75,000.00 85,000.00 9,000.00 10,200.00
L.03 0.012 OH Kepala Tukang 85,000.00 95,000.00 1,020.00 1,140.00
L.04 0.018 OH Mandor 75,000.00 90,000.00 1,350.00 1,620.00
B Bahan 9,500.00 10,850.00
3 kg Portland Semen 1,250.00 1,300.00 3,750.00 3,900.00
0.005 m3 Kapur Padam 250,000.00 310,000.00 1,250.00 1,550.00
0.020 m3 Pasir Pasang 225,000.00 270,000.00 4,500.00 5,400.00
C PERALATAN
D Jumlah A + B + C 40,670.00 47,210.00
E Overhead & Profit (contoh 10%) 10% 4,067.00 4,721.00
F Harga Satuan Pekerjaan (D+E) 44,737.00 51,931.00
11 A,4,4,2.11 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 1 Pp Tebal 15 mm 40,722.00 47,569.50
A Tenaga 31,170.00 36,360.00
L.01 0.36 OH Pekerja 55,000.00 65,000.00 19,800.00 23,400.00
L.02 0.12 OH Tukang batu 75,000.00 85,000.00 9,000.00 10,200.00
L.03 0.012 OH Kepala Tukang 85,000.00 95,000.00 1,020.00 1,140.00
L.04 0.018 OH Mandor 75,000.00 90,000.00 1,350.00 1,620.00
B Bahan 5,850.00 6,885.00
0.009 m3 Semen Merah 175,000.00 185,000.00 1,575.00 1,665.00
0.009 m3 Kapur Padam 250,000.00 310,000.00 2,250.00 2,790.00
0.009 m3 Pasir Pasang 225,000.00 270,000.00 2,025.00 2,430.00
C PERALATAN
D Jumlah A + B + C 37,020.00 43,245.00
E Overhead & Profit (contoh 10%) 10% 3,702.00 4,324.50
F Harga Satuan Pekerjaan (D+E) 40,722.00 47,569.50
12 A,4,4,2.12 1 m2 Pemasangan Plesteran 1 SM : 1 Kp : 2 Pp Tebal 15 mm 41,272.00 48,262.50
A Tenaga 31,170.00 36,360.00
L.01 0.36 OH Pekerja 55,000.00 65,000.00 19,800.00 23,400.00
L.02 0.12 OH Tukang batu 75,000.00 85,000.00 9,000.00 10,200.00
L.03 0.012 OH Kepala Tukang 85,000.00 95,000.00 1,020.00 1,140.00
L.04 0.018 OH Mandor 75,000.00 90,000.00 1,350.00 1,620.00
B Bahan 6,350.00 7,515.00
0.007 m3 Semen Merah 175,000.00 185,000.00 1,225.00 1,295.00
0.007 m3 Kapur Padam 250,000.00 310,000.00 1,750.00 2,170.00
0.015 m3 Pasir Pasang 225,000.00 270,000.00 3,375.00 4,050.00

file:///conversion/tmp/scratch/443255086.xls 95/37 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 37,520.00 43,875.00
E Overhead & Profit (contoh 10%) 10% 3,752.00 4,387.50
F Harga Satuan Pekerjaan (D+E) 41,272.00 48,262.50
13 A,4,4,2.13 1 m2 Pemasangan Plesteran 1 Pc : 2 Pp Tebal 20 mm 69,811.50 79,080.76
A Tenaga 40,350.00 46,880.00
L.01 0.40 OH Pekerja 55,000.00 65,000.00 22,000.00 26,000.00
L.02 0.20 OH Tukang batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.020 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.022 OH Mandor 75,000.00 90,000.00 1,650.00 1,980.00
B Bahan 23,115.00 25,011.60
13.632 kg Portland Semen 1,250.00 1,300.00 17,040.00 17,721.60
0.027 m3 Pasir Pasang 225,000.00 270,000.00 6,075.00 7,290.00
C PERALATAN
D Jumlah A + B + C 63,465.00 71,891.60
E Overhead & Profit (contoh 10%) 10% 6,346.50 7,189.16
F Harga Satuan Pekerjaan (D+E) 69,811.50 79,080.76
14 A,4,4,2.14 1 m2 Pemasangan Plesteran 1Pc : 3Pp Tebal 20 mm 51,910.00 58,818.40
A Tenaga 31,975.00 36,970.00
L.01 0.26 OH Pekerja 55,000.00 65,000.00 14,300.00 16,900.00
L.02 0.2 OH Tukang batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.013 OH Mandor 75,000.00 90,000.00 975.00 1,170.00
B Bahan 19,935.00 21,848.40
10.368 Kg Portland Semen 1,250.00 1,300.00 12,960.00 13,478.40
0.031 m3 Pasir Pasang 225,000.00 270,000.00 6,975.00 8,370.00
C PERALATAN
D Jumlah A + B + C 52,885.00 59,988.40
E Overhead & Profit (contoh 10%) 10% 5,288.50 5,998.84
F Harga Satuan Pekerjaan (D+E) 58,173.50 65,987.24
15 A,4,4,2.15 1 m2 Pemasangan Plesteran 1 Pc : 4 Pp Tebal 20 mm 63,745.00 72,969.60
A Tenaga 40,350.00 46,880.00
L.01 0.40 OH Pekerja 55,000.00 65,000.00 22,000.00 26,000.00
L.02 0.20 OH Tukang batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.020 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.022 OH Mandor 75,000.00 90,000.00 1,650.00 1,980.00
B Bahan 17,600.00 19,456.00
8.320 kg Portland Semen 1,250.00 1,300.00 10,400.00 10,816.00
0.032 m3 Pasir Pasang 225,000.00 270,000.00 7,200.00 8,640.00
C PERALATAN
D Jumlah A + B + C 57,950.00 66,336.00
E Overhead & Profit (contoh 10%) 10% 5,795.00 6,633.60
F Harga Satuan Pekerjaan (D+E) 63,745.00 72,969.60
16 A,4,4,2.16 1 m2 Pemasangan Plesteran 1Pc : 5Pp Tebal 20 mm 62,551.50 71,847.16
A Tenaga 40,350.00 46,880.00
L.01 0.400 OH Pekerja 55,000.00 65,000.00 22,000.00 26,000.00
L.02 0.200 OH Tukang batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.020 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.022 OH Mandor 75,000.00 90,000.00 1,650.00 1,980.00
B Bahan 16,515.00 18,435.60
6.912 Kg Portland Semen 1,250.00 1,300.00 8,640.00 8,985.60
0.035 m3 Pasir Pasang 225,000.00 270,000.00 7,875.00 9,450.00
C PERALATAN
D Jumlah A + B + C 56,865.00 65,315.60
E Overhead & Profit (contoh 10%) 10% 5,686.50 6,531.56
F Harga Satuan Pekerjaan (D+E) 62,551.50 71,847.16
17 A,4,4,2.17 1 m2 Pemasangan Plesteran 1Pc : 6Pp Tebal 20 mm 61,391.00 70,679.84
A Tenaga 40,350.00 46,880.00
L.01 0.40 OH Pekerja 55,000.00 65,000.00 22,000.00 26,000.00
L.02 0.2 OH Tukang batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.022 OH Mandor 75,000.00 90,000.00 1,650.00 1,980.00
B Bahan 15,460.00 17,374.40
5.888 Kg Portland Semen 1,250.00 1,300.00 7,360.00 7,654.40
0.036 m3 Pasir Pasang 225,000.00 270,000.00 8,100.00 9,720.00
C PERALATAN
D Jumlah A + B + C 55,810.00 64,254.40
E Overhead & Profit (contoh 10%) 10% 5,581.00 6,425.44
F Harga Satuan Pekerjaan (D+E) 61,391.00 70,679.84
18 A,4,4,2.18 1 m2 Pemasangan Plesteran 1 SM : 2 Kp : 2 Pp Tebal 20 mm 57,304.50 66,753.50
A Tenaga 44,220.00 51,370.00
L.01 0.440 OH Pekerja 55,000.00 65,000.00 24,200.00 28,600.00
L.02 0.22 OH Tukang batu 75,000.00 85,000.00 16,500.00 18,700.00
L.03 0.022 OH Kepala Tukang 85,000.00 95,000.00 1,870.00 2,090.00
L.04 0.022 OH Mandor 75,000.00 90,000.00 1,650.00 1,980.00

file:///conversion/tmp/scratch/443255086.xls 95/38 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 7,875.00 9,315.00
0.009 m3 Semen Merah 175,000.00 185,000.00 1,575.00 1,665.00
0.009 m3 Kapur Padam 250,000.00 310,000.00 2,250.00 2,790.00
0.018 m3 Pasir Pasang 225,000.00 270,000.00 4,050.00 4,860.00
C PERALATAN
D Jumlah A + B + C 52,095.00 60,685.00
E Overhead & Profit (contoh 10%) 10% 5,209.50 6,068.50
F Harga Satuan Pekerjaan (D+E) 57,304.50 66,753.50
19 A,4,4,2.19 1 m2 Pemasangan Berapen 1 Pc : 5Pp Tebal 15 mm 30,233.50 34,500.62
A Tenaga 15,155.00 17,605.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.075 OH Tukang batu 75,000.00 85,000.00 5,625.00 6,375.00
L.03 0.008 OH Kepala Tukang 85,000.00 95,000.00 680.00 760.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 12,330.00 13,759.20
5.184 Kg Portland Semen 1,250.00 1,300.00 6,480.00 6,739.20
0.026 m3 Pasir Pasang 225,000.00 270,000.00 5,850.00 7,020.00
C PERALATAN
D Jumlah A + B + C 27,485.00 31,364.20
E Overhead & Profit (contoh 10%) 10% 2,748.50 3,136.42
F Harga Satuan Pekerjaan (D+E) 30,233.50 34,500.62
20 A,4,4,2.20 1 m' Pemasangan Plesteran Skoning 1 Pc : 2Pp, lebar 10 mm 45,815.00 52,272.00
A Tenaga 38,100.00 43,360.00
L.01 0.080 OH Pekerja 55,000.00 65,000.00 4,400.00 5,200.00
L.02 0.40 OH Tukang batu 75,000.00 85,000.00 30,000.00 34,000.00
L.03 0.040 OH Kepala Tukang 85,000.00 95,000.00 3,400.00 3,800.00
L.04 0.004 OH Mandor 75,000.00 90,000.00 300.00 360.00
B Bahan 3,550.00 4,160.00
0.5 Kg Portland Semen 1,250.00 1,300.00 625.00 650.00
0.013 m3 Pasir Pasang 225,000.00 270,000.00 2,925.00 3,510.00
C PERALATAN
D Jumlah A + B + C 41,650.00 47,520.00
E Overhead & Profit (contoh 10%) 10% 4,165.00 4,752.00
F Harga Satuan Pekerjaan (D+E) 45,815.00 52,272.00
21 A,4,4,2.23 1 m2 Pemasangan Plesteran Ciprat 1Pc : 2 Pp 35,997.50 41,289.60
Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
Bahan 6,750.00 7,236.00
4.32 Kg Portland Semen 1,250.00 1,300.00 5,400.00 5,616.00
0.006 m3 Pasir Pasang 225,000.00 270,000.00 1,350.00 1,620.00
C PERALATAN
D Jumlah A + B + C 32,725.00 37,536.00
E Overhead & Profit (contoh 10%) 10% 3,272.50 3,753.60
F Harga Satuan Pekerjaan (D+E) 35,997.50 41,289.60
22 A,4,4,2.24 1 m2 Pemasangan Finishing Siar Pasangan Dinding Bata Merah (=20 m') 20,944.00 23,809.94
A Tenaga 15,155.00 17,605.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.075 OH Tukang batu 75,000.00 85,000.00 5,625.00 6,375.00
L.03 0.008 OH Kepala Tukang 85,000.00 95,000.00 680.00 760.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 3,885.00 4,040.40
3.108 Kg Portland Semen 1,250.00 1,300.00 3,885.00 4,040.40
C PERALATAN
D Jumlah A + B + C 19,040.00 21,645.40
E Overhead & Profit (contoh 10%) 10% 1,904.00 2,164.54
F Harga Satuan Pekerjaan (D+E) 20,944.00 23,809.94
23 A,4,4,2.25 1 m2 Pemasangan Finishing Siar Pasangan Dinding Conblock ekspose (=8 m') 10,026.50 11,379.50
A Tenaga 7,115.00 8,265.00
L.01 0.070 OH Pekerja 55,000.00 65,000.00 3,850.00 4,550.00
L.02 0.035 OH Tukang batu 75,000.00 85,000.00 2,625.00 2,975.00
L.03 0.004 OH Kepala Tukang 85,000.00 95,000.00 340.00 380.00
L.04 0.004 OH Mandor 75,000.00 90,000.00 300.00 360.00
B Bahan 2,000.00 2,080.00
1.600 Kg Portland Semen 1,250.00 1,300.00 2,000.00 2,080.00
C PERALATAN
D Jumlah A + B + C 9,115.00 10,345.00
E Overhead & Profit (contoh 10%) 10% 911.50 1,034.50
F Harga Satuan Pekerjaan (D+E) 10,026.50 11,379.50
24 A,4,4,2.26 1 m2 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp 44,852.50 51,157.70
Tenaga 30,150.00 35,025.00
L.01 0.3 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.15 OH Tukang batu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00

file:///conversion/tmp/scratch/443255086.xls 95/39 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
Bahan 10,625.00 11,482.00
6.34 Kg Pc 1,250.00 1,300.00 7,925.00 8,242.00
0.012 m3 PP 225,000.00 270,000.00 2,700.00 3,240.00
C PERALATAN
D Jumlah A + B + C 40,775.00 46,507.00
E Overhead & Profit (contoh 10%) 10% 4,077.50 4,650.70
F Harga Satuan Pekerjaan (D+E) 44,852.50 51,157.70

25 A,4,4,2.27 1 m2 Pemasangan Acian 26,578.75 30,332.50


Tenaga 20,100.00 23,350.00
L.01 0.20 OH Pekerja 55,000.00 65,000.00 11,000.00 13,000.00
L.02 0.10 OH Tukang batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.010 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.010 OH Mandor 75,000.00 90,000.00 750.00 900.00
Bahan 4,062.50 4,225.00
3.25 Kg Portland Semen 1,250.00 1,300.00 4,062.50 4,225.00
C PERALATAN
D Jumlah A + B + C 24,162.50 27,575.00
E Overhead & Profit (contoh 10%) 10% 2,416.25 2,757.50
F Harga Satuan Pekerjaan (D+E) 26,578.75 30,332.50

file:///conversion/tmp/scratch/443255086.xls 95/40 abk 5-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
VI A.4.6.1 HARGA SATUAN PEKERJAAN K A Y U
1 A.4.6.1.1 1 m3 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I 26,618,900.00 27,565,725.00
A Tenaga 2,164,750.00 2,471,000.00
L.01 7 OH Pekerja 55,000.00 65,000.00 385,000.00 455,000.00
L.02 21 OH Tukang Kayu 75,000.00 85,000.00 1,575,000.00 1,785,000.00
L.03 2.10 OH Kepala Tukang 85,000.00 95,000.00 178,500.00 199,500.00
L.04 0.35 OH Mandor 75,000.00 90,000.00 26,250.00 31,500.00
B Bahan 22,034,250.00 22,588,750.00
1.1 m3 Kayu Klas I (Jati) , Balok 20,000,000.00 20,500,000.00 22,000,000.00 22,550,000.00
1.25 kg Paku Biasa 2" - 5 " 13,000.00 15,000.00 16,250.00 18,750.00
1 kg Lem Kayu 18,000.00 20,000.00 18,000.00 20,000.00
C PERALATAN
D Jumlah A + B + C 24,199,000.00 25,059,750.00
E Overhead & Profit (contoh 10%) 10% 2,419,900.00 2,505,975.00
F Harga Satuan Pekerjaan (D+E) 26,618,900.00 27,565,725.00

2 A.4.6.1.2 1 m3 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas II atau III 11,186,725.00 12,272,425.00
Tenaga 1,855,500.00 2,118,000.00
L.01 6.00 OH Pekerja 55,000.00 65,000.00 330,000.00 390,000.00
L.02 18.00 OH Tukang Kayu 75,000.00 85,000.00 1,350,000.00 1,530,000.00
L.03 1.80 OH Kepala Tukang 85,000.00 95,000.00 153,000.00 171,000.00
L.04 0.30 OH Mandor 75,000.00 90,000.00 22,500.00 27,000.00
Bahan 8,314,250.00 9,038,750.00
1.2 m3 Kayu Klas II (Kamfer) , Balok 6,900,000.00 7,500,000.00 8,280,000.00 9,000,000.00
1.25 kg Paku Biasa 2" - 5 " 13,000.00 15,000.00 16,250.00 18,750.00
1 kg Lem Kayu 18,000.00 20,000.00 18,000.00 20,000.00
C PERALATAN
D Jumlah A + B + C 10,169,750.00 11,156,750.00
E Overhead & Profit (contoh 10%) 10% 1,016,975.00 1,115,675.00
F Harga Satuan Pekerjaan (D+E) 11,186,725.00 12,272,425.00

3 A.4.6.1.3 1 m2 Pembuatan & Pemasangan Pintu KlampStandard Kayu Klas II (Kayu Kamfer) 454,217.50 479,979.50
A Tenaga 108,275.00 123,595.00
L.01 0.35 OH Pekerja 55,000.00 65,000.00 19,250.00 22,750.00
L.02 1.05 OH Tukang Kayu 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.105 OH Kepala Tukang 85,000.00 95,000.00 8,925.00 9,975.00
L.04 0.018 OH Mandor 75,000.00 90,000.00 1,350.00 1,620.00
B Bahan 304,650.00 312,750.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 304,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 412,925.00 436,345.00
E Overhead & Profit (contoh 10%) 10% 41,292.50 43,634.50
F Harga Satuan Pekerjaan (D+E) 454,217.50 479,979.50

4 A.4.6.1.4 1 m2 Pembuatan & Pemasangan Daun Pintu Klamp Sederhana Kayu Klas III 454,217.50 479,979.50
Tenaga 108,275.00 123,595.00
L.01 0.35 OH Pekerja 55,000.00 65,000.00 19,250.00 22,750.00
L.02 1.05 OH Tukang Kayu 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.105 OH Kepala Tukang 85,000.00 95,000.00 8,925.00 9,975.00
L.04 0.018 OH Mandor 75,000.00 90,000.00 1,350.00 1,620.00
Bahan 304,650.00 312,750.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 304,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 412,925.00 436,345.00
E Overhead & Profit (contoh 10%) 10% 41,292.50 43,634.50
F Harga Satuan Pekerjaan (D+E) 454,217.50 479,979.50

5 A.4.6.1.5 1 m2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II 675,565.00 732,600.00
A Tenaga 309,250.00 353,000.00
L.01 1.00 OH Pekerja 55,000.00 65,000.00 55,000.00 65,000.00
L.02 3.00 OH Tukang Kayu 75,000.00 85,000.00 225,000.00 255,000.00
L.03 0.30 OH Kepala Tukang 85,000.00 95,000.00 25,500.00 28,500.00
L.04 0.05 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00
B Bahan 304,900.00 313,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 304,000.00 312,000.00
0.050 kg Lem Kayu 18,000.00 20,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 614,150.00 666,000.00
E Overhead & Profit (contoh 10%) 10% 61,415.00 66,600.00
F Harga Satuan Pekerjaan (D+E) 675,565.00 732,600.00

file:///conversion/tmp/scratch/443255086.xls 95/41 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.6.1.6 1 m2 Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Klas I atau II 478,720.00 523,160.00
A Tenaga 247,400.00 282,400.00
L.01 0.800 OH Pekerja 55,000.00 65,000.00 44,000.00 52,000.00
L.02 2.400 OH Tukang Kayu 75,000.00 85,000.00 180,000.00 204,000.00
L.03 0.240 OH Kepala Tukang 85,000.00 95,000.00 20,400.00 22,800.00
L.04 0.040 OH Mandor 75,000.00 90,000.00 3,000.00 3,600.00
B Bahan 187,800.00 193,200.00
0.024 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 182,400.00 187,200.00
0.300 kg Lem Kayu 18,000.00 20,000.00 5,400.00 6,000.00
C PERALATAN
D Jumlah A + B + C 435,200.00 475,600.00
E Overhead & Profit (contoh 10%) 10% 43,520.00 47,560.00
F Harga Satuan Pekerjaan (D+E) 478,720.00 523,160.00

7 A.4.6.1.7 1 m2 Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu Klas I atau II (jati) 1,898,875.00 2,018,500.00
A Tenaga 309,250.00 353,000.00
L.01 1 OH Pekerja 55,000.00 65,000.00 55,000.00 65,000.00
L.02 3 OH Tukang Kayu 75,000.00 85,000.00 225,000.00 255,000.00
L.03 0.3 OH Kepala Tukang 85,000.00 95,000.00 25,500.00 28,500.00
L.04 0.05 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00
B Bahan 1,417,000.00 1,482,000.00
0.064 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,408,000.00 1,472,000.00
0.5 kg Lem Kayu 18,000.00 20,000.00 9,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 1,726,250.00 1,835,000.00
E Overhead & Profit (contoh 10%) 10% 172,625.00 183,500.00
F Harga Satuan Pekerjaan (D+E) 1,898,875.00 2,018,500.00

8 A.4.6.1.8 1 m2 Pembuatan&Pemasangan Pintu kayu lapis (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 cm) 528,951.50 574,805.00
A Tenaga 216,475.00 247,100.00
L.01 0.700 OH Pekerja 55,000.00 65,000.00 38,500.00 45,500.00
L.02 2.100 OH Tukang Kayu 75,000.00 85,000.00 157,500.00 178,500.00
L.03 0.210 OH Kepala Tukang 85,000.00 95,000.00 17,850.00 19,950.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 264,390.00 275,450.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 190,000.00 195,000.00
0.030 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 390.00 450.00
0.500 Ltr Lem Kayu 18,000.00 20,000.00 9,000.00 10,000.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 70,000.00 65,000.00 70,000.00
C PERALATAN
D Jumlah A + B + C 480,865.00 522,550.00
E Overhead & Profit (contoh 10%) 10% 48,086.50 52,255.00
F Harga Satuan Pekerjaan (D+E) 528,951.50 574,805.00

9 A.4.6.1.9 1 m2 Pembuatan&Pemasangan Pintu Plywood rangkap, rangka expose kayu klas I atau II 567,985.00 618,783.00
A Tenaga 247,400.00 282,400.00
L.01 0.800 OH Pekerja 55,000.00 65,000.00 44,000.00 52,000.00
L.02 2.400 OH Tukang Kayu 75,000.00 85,000.00 180,000.00 204,000.00
L.03 0.240 OH Kepala Tukang 85,000.00 95,000.00 20,400.00 22,800.00
L.04 0.040 OH Mandor 75,000.00 90,000.00 3,000.00 3,600.00
B Bahan 268,950.00 280,130.00
0.0256 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 194,560.00 199,680.00
0.03 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 390.00 450.00
0.5 Ltr Lem Kayu 18,000.00 20,000.00 9,000.00 10,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 70,000.00 65,000.00 70,000.00
C PERALATAN
D Jumlah A + B + C 516,350.00 562,530.00
E Overhead & Profit (contoh 10%) 10% 51,635.00 56,253.00
F Harga Satuan Pekerjaan (D+E) 567,985.00 618,783.00

10 A.4.6.1.10 1 m2 Pembuatan & Pemasangan Jalusi mati Kosen Kayu Klas I atau II 1,706,017.50 1,809,445.00
A Tenaga 228,975.00 262,700.00
L.01 0.670 OH Pekerja 55,000.00 65,000.00 36,850.00 43,550.00
L.02 2.000 OH Tukang Kayu 75,000.00 85,000.00 150,000.00 170,000.00
L.03 0.200 OH Kepala Tukang 85,000.00 95,000.00 17,000.00 19,000.00
L.04 0.335 OH Mandor 75,000.00 90,000.00 25,125.00 30,150.00
B Bahan 1,321,950.00 1,382,250.00
0.06 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,320,000.00 1,380,000.00
0.15 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 1,950.00 2,250.00
C PERALATAN
D Jumlah A + B + C 1,550,925.00 1,644,950.00
E Overhead & Profit (contoh 10%) 10% 155,092.50 164,495.00
F Harga Satuan Pekerjaan (D+E) 1,706,017.50 1,809,445.00

file:///conversion/tmp/scratch/443255086.xls 95/42 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.6.1.11 1 m2 Pembuatan & Pemasangan Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I 955,009.00 1,027,235.00
A Tenaga 247,400.00 282,400.00
L.01 0.80 OH Pekerja 55,000.00 65,000.00 44,000.00 52,000.00
L.02 2.40 OH Tukang Kayu 75,000.00 85,000.00 180,000.00 204,000.00
L.03 0.24 OH Kepala Tukang 85,000.00 95,000.00 20,400.00 22,800.00
L.04 0.04 OH Mandor 75,000.00 90,000.00 3,000.00 3,600.00
B Bahan 620,790.00 651,450.00
0.025 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 550,000.00 575,000.00
0.03 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 390.00 450.00
0.3 kg Lem Kayu 18,000.00 20,000.00 5,400.00 6,000.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 70,000.00 65,000.00 70,000.00
C PERALATAN
D Jumlah A + B + C 868,190.00 933,850.00
E Overhead & Profit (contoh 10%) 10% 86,819.00 93,385.00
F Harga Satuan Pekerjaan (D+E) 955,009.00 1,027,235.00

12 A.4.6.1.12 1 m2 Pembuatan&Pemasangan Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II 609,103.00 665,109.50
A Tenaga 262,900.00 300,095.00
L.01 0.850 OH Pekerja 55,000.00 65,000.00 46,750.00 55,250.00
L.02 2.550 OH Tukang Kayu 75,000.00 85,000.00 191,250.00 216,750.00
L.03 0.255 OH Kepala Tukang 85,000.00 95,000.00 21,675.00 24,225.00
L.04 0.043 OH Mandor 75,000.00 90,000.00 3,225.00 3,870.00
B Bahan 290,830.00 304,550.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 190,000.00 195,000.00
0.03 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 390.00 450.00
0.08 kg Lem Kayu 18,000.00 20,000.00 1,440.00 1,600.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 70,000.00 65,000.00 70,000.00
0.5 Lbr Formika 68,000.00 75,000.00 34,000.00 37,500.00
C PERALATAN
D Jumlah A + B + C 553,730.00 604,645.00
E Overhead & Profit (contoh 10%) 10% 55,373.00 60,464.50
F Harga Satuan Pekerjaan (D+E) 609,103.00 665,109.50

13 A.4.6.1.13 1 m3 Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 meter 9,996,030.00 10,943,350.00
A Tenaga 1,237,000.00 1,412,000.00
L.01 4 OH Pekerja 55,000.00 65,000.00 220,000.00 260,000.00
L.02 12 OH Tukang Kayu 75,000.00 85,000.00 900,000.00 1,020,000.00
L.03 1.2 OH Kepala Tukang 85,000.00 95,000.00 102,000.00 114,000.00
L.04 0.2 OH Mandor 75,000.00 90,000.00 15,000.00 18,000.00
B Bahan 7,850,300.00 8,536,500.00
1.1 m3 Kayu Kamfer, balok 6,900,000.00 7,500,000.00 7,590,000.00 8,250,000.00
15 Kg Besi Strip 12,500.00 13,500.00 187,500.00 202,500.00
5.6 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 72,800.00 84,000.00
C PERALATAN
D Jumlah A + B + C 9,087,300.00 9,948,500.00
E Overhead & Profit (contoh 10%) 10% 908,730.00 994,850.00
F Harga Satuan Pekerjaan (D+E) 9,996,030.00 10,943,350.00

14 A.4.6.1.14 1 m3 Pembuatan&Pemasangan Konstruksi Kuda-kuda Expose, Kayu Klas I 28,965,502.50 29,976,760.00


A Tenaga 2,071,975.00 2,365,100.00
L.01 6.7 OH Pekerja 55,000.00 65,000.00 368,500.00 435,500.00
L.02 20.1 OH Tukang Kayu 75,000.00 85,000.00 1,507,500.00 1,708,500.00
L.03 2.01 OH Kepala Tukang 85,000.00 95,000.00 170,850.00 190,950.00
L.04 0.335 OH Mandor 75,000.00 90,000.00 25,125.00 30,150.00
B Bahan 24,260,300.00 24,886,500.00
1.2 m3 Kayu Klas I (jati), balok 20,000,000.00 20,500,000.00 24,000,000.00 24,600,000.00
15 Kg Besi Strip 12,500.00 13,500.00 187,500.00 202,500.00
5.6 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 72,800.00 84,000.00
C PERALATAN
D Jumlah A + B + C 26,332,275.00 27,251,600.00
E Overhead & Profit (contoh 10%) 10% 2,633,227.50 2,725,160.00
F Harga Satuan Pekerjaan (D+E) 28,965,502.50 29,976,760.00

15 A.4.6.1.15 1 m3 Pemasangan konstruksi Gording, Kayu Klas II 9,414,570.00 10,279,170.00


A Tenaga 742,200.00 847,200.00
L.01 2.4 OH Pekerja 55,000.00 65,000.00 132,000.00 156,000.00
L.02 7.2 OH Tukang Kayu 75,000.00 85,000.00 540,000.00 612,000.00
L.03 0.72 OH Kepala Tukang 85,000.00 95,000.00 61,200.00 68,400.00
L.04 0.12 OH Mandor 75,000.00 90,000.00 9,000.00 10,800.00
B Bahan 7,816,500.00 8,497,500.00
1.1 m3 Kayu Klas I (Kamfer), balok 6,900,000.00 7,500,000.00 7,590,000.00 8,250,000.00
15 Kg Besi Strip 12,500.00 13,500.00 187,500.00 202,500.00
3 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 39,000.00 45,000.00
C PERALATAN
D Jumlah A + B + C 8,558,700.00 9,344,700.00
E Overhead & Profit (contoh 10%) 10% 855,870.00 934,470.00

file:///conversion/tmp/scratch/443255086.xls 95/43 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 9,414,570.00 10,279,170.00

file:///conversion/tmp/scratch/443255086.xls 95/44 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
16 A.4.6.1.16 1 m2 Pemasangan Rangka Atap Genteng Keramik, Kayu Klas II 152,806.50 167,365.00
A Tenaga 14,225.00 16,400.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.1 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 124,690.00 135,750.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 6,900,000.00 7,500,000.00 96,600.00 105,000.00
0.0036 m3 Reng (2x3) cm 6,900,000.00 7,500,000.00 24,840.00 27,000.00
0.25 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 3,250.00 3,750.00
C PERALATAN
D Jumlah A + B + C 138,915.00 152,150.00
E Overhead & Profit (contoh 10%) 10% 13,891.50 15,215.00
F Harga Satuan Pekerjaan (D+E) 152,806.50 167,365.00

17 A.4.6.1.17 1 m2 Pemasangan Rangka Atap Genteng Beton, Kayu Klas II 180,130.50 197,065.00
A Tenaga 14,225.00 16,400.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.1 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 149,530.00 162,750.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 6,900,000.00 7,500,000.00 96,600.00 105,000.00
0.0072 m3 Reng (2x3) cm 6,900,000.00 7,500,000.00 49,680.00 54,000.00
0.25 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 3,250.00 3,750.00
C PERALATAN
D Jumlah A + B + C 163,755.00 179,150.00
E Overhead & Profit (contoh 10%) 10% 16,375.50 17,915.00
F Harga Satuan Pekerjaan (D+E) 180,130.50 197,065.00

18 A.4.6.1.18 1 m2 Pemasangan Rangka Atap Sirap, Kayu Klas II 127,897.00 140,448.00


A Tenaga 17,070.00 19,680.00
L.01 0.12 OH Pekerja 55,000.00 65,000.00 6,600.00 7,800.00
L.02 0.12 OH Tukang Kayu 75,000.00 85,000.00 9,000.00 10,200.00
L.03 0.012 OH Kepala Tukang 85,000.00 95,000.00 1,020.00 1,140.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
B Bahan 99,200.00 108,000.00
0.014 m3 Kayu Klas II (Kamfer), balok 6,900,000.00 7,500,000.00 96,600.00 105,000.00
0.2 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 2,600.00 3,000.00
C PERALATAN
D Jumlah A + B + C 116,270.00 127,680.00
E Overhead & Profit (contoh 10%) 10% 11,627.00 12,768.00
F Harga Satuan Pekerjaan (D+E) 127,897.00 140,448.00

19 A.4.6.1.19 1 m2 Pemasangan Rangka Langit-langit (50x1,00) m, kayu Klas II atau III 162,563.50 179,685.00
A Tenaga 38,925.00 44,850.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.30 OH Tukang Kayu 75,000.00 85,000.00 22,500.00 25,500.00
L.03 0.030 OH Kepala Tukang 85,000.00 95,000.00 2,550.00 2,850.00
L.04 0.075 OH Mandor 75,000.00 90,000.00 5,625.00 6,750.00
B Bahan 108,860.00 118,500.00
0.0154 m3 Kayu Klas II (Kamfer), balok 6,900,000.00 7,500,000.00 106,260.00 115,500.00
0.2 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 2,600.00 3,000.00
C PERALATAN
D Jumlah A + B + C 147,785.00 163,350.00
E Overhead & Profit (contoh 10%) 10% 14,778.50 16,335.00
F Harga Satuan Pekerjaan (D+E) 162,563.50 179,685.00

20 A.4.6.1.20 1 m2 Pemasangan Rangka Langit-langit (60x60) cm, kayu Klas II atau III 167,772.00 185,075.00
A Tenaga 36,800.00 42,250.00
L.01 0.2 OH Pekerja 55,000.00 65,000.00 11,000.00 13,000.00
L.02 0.3 OH Tukang Kayu 75,000.00 85,000.00 22,500.00 25,500.00
L.03 0.03 OH Kepala Tukang 85,000.00 95,000.00 2,550.00 2,850.00
L.04 0.01 OH Mandor 75,000.00 90,000.00 750.00 900.00
B Bahan 115,720.00 126,000.00
0.0163 m3 Kayu Klas II (Kamfer), balok 6,900,000.00 7,500,000.00 112,470.00 122,250.00
0.25 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 3,250.00 3,750.00
C PERALATAN
D Jumlah A + B + C 152,520.00 168,250.00
E Overhead & Profit (contoh 10%) 10% 15,252.00 16,825.00
F Harga Satuan Pekerjaan (D+E) 167,772.00 185,075.00

file:///conversion/tmp/scratch/443255086.xls 95/45 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
21 A.4.6.1.21 1 m' Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau II 287,622.50 303,325.00
A Tenaga 22,575.00 25,850.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.020 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 238,900.00 249,900.00
0.0108 m3 Kayu klas I (Jati), papan 22,000,000.00 23,000,000.00 237,600.00 248,400.00
0.10 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 1,300.00 1,500.00
C PERALATAN
D Jumlah A + B + C 261,475.00 275,750.00
E Overhead & Profit (contoh 10%) 10% 26,147.50 27,575.00
F Harga Satuan Pekerjaan (D+E) 287,622.50 303,325.00

22 A.4.6.1.22 1 m' Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau klas II 117,507.50 123,640.00
A Tenaga 22,575.00 25,850.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 84,250.00 86,550.00
0.011 m3 Kayu klas II (Kamfer), papan 7,600,000.00 7,800,000.00 83,600.00 85,800.00
0.05 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 106,825.00 112,400.00
E Overhead & Profit (contoh 10%) 10% 10,682.50 11,240.00
F Harga Satuan Pekerjaan (D+E) 117,507.50 123,640.00

23 A.4.6.1.23 1 m2 Pemasangan Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III 265,732.50 291,769.50
A Tenaga 46,425.00 52,995.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.45 OH Tukang Kayu 75,000.00 85,000.00 33,750.00 38,250.00
L.03 0.045 OH Kepala Tukang 85,000.00 95,000.00 3,825.00 4,275.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 195,150.00 212,250.00
0.028 m3 Kayu klas II (Kamfer), balok 6,900,000.00 7,500,000.00 193,200.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 1,950.00 2,250.00
C PERALATAN
D Jumlah A + B + C 241,575.00 265,245.00
E Overhead & Profit (contoh 10%) 10% 24,157.50 26,524.50
F Harga Satuan Pekerjaan (D+E) 265,732.50 291,769.50

24 A.4.6.1.24 1 m2 Pemasangan Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II 338,310.50 370,309.50
A Tenaga 46,425.00 52,995.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.45 OH Tukang Kayu 75,000.00 85,000.00 33,750.00 38,250.00
L.03 0.045 OH Kepala Tukang 85,000.00 95,000.00 3,825.00 4,275.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 261,130.00 283,650.00
0.028 m3 Kayu klas II (Kamfer), balok 6,900,000.00 7,500,000.00 193,200.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 1,950.00 2,250.00
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm 65,000.00 70,000.00 55,900.00 60,200.00
0.56 Ltr Lem 18,000.00 20,000.00 10,080.00 11,200.00
C PERALATAN
D Jumlah A + B + C 307,555.00 336,645.00
E Overhead & Profit (contoh 10%) 10% 30,755.50 33,664.50
F Harga Satuan Pekerjaan (D+E) 338,310.50 370,309.50

25 A.4.6.1.25 1 m2 Pemasangan Dinding Pemisah Plywood Rangkap Rangka Kayu Klas II 344,388.00 376,805.00
A Tenaga 51,950.00 58,900.00
L.01 0.020 OH Pekerja 55,000.00 65,000.00 1,100.00 1,300.00
L.02 0.600 OH Tukang Kayu 75,000.00 85,000.00 45,000.00 51,000.00
L.03 0.060 OH Kepala Tukang 85,000.00 95,000.00 5,100.00 5,700.00
L.04 0.010 OH Mandor 75,000.00 90,000.00 750.00 900.00
B Bahan 261,130.00 283,650.00
0.028 m3 Kayu klas II (Kamfer), balok 6,900,000.00 7,500,000.00 193,200.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 1,950.00 2,250.00
0.86 Lbr Plywood 120 x 240 cm tebal 4mm 65,000.00 70,000.00 55,900.00 60,200.00
0.56 Ltr Lem 18,000.00 20,000.00 10,080.00 11,200.00
C PERALATAN
D Jumlah A + B + C 313,080.00 342,550.00
E Overhead & Profit (contoh 10%) 10% 31,308.00 34,255.00
F Harga Satuan Pekerjaan (D+E) 344,388.00 376,805.00

file:///conversion/tmp/scratch/443255086.xls 95/46 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
26 A.4.6.1.26 1 m2 Pemasangan Dinding Lambriziring dari Papan klas I 375,925.00 413,050.00
A Tenaga 185,550.00 211,800.00
L.01 0.6 OH Pekerja 55,000.00 65,000.00 33,000.00 39,000.00
L.02 1.8 OH Tukang Kayu 75,000.00 85,000.00 135,000.00 153,000.00
L.03 0.18 OH Kepala Tukang 85,000.00 95,000.00 15,300.00 17,100.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 156,200.00 163,700.00
0.007 m3 Kayu klas I (Jati), papan 22,000,000.00 23,000,000.00 154,000.00 161,000.00
0.1 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 1,300.00 1,500.00
0.15 Kg Paku Sekrup 3,5" 6,000.00 8,000.00 900.00 1,200.00
C PERALATAN
D Jumlah A + B + C 341,750.00 375,500.00
E Overhead & Profit (contoh 10%) 10% 34,175.00 37,550.00
F Harga Satuan Pekerjaan (D+E) 375,925.00 413,050.00

27 A.4.6.1.27 1 m2 Pemasangan Dinding Lambriziring dari Plywood ukuran (120x240) cm 36,525.50 41,360.00
A Tenaga 7,755.00 8,850.00
L.01 0.025 OH Pekerja 55,000.00 65,000.00 1,375.00 1,625.00
L.02 0.075 OH Tukang Kayu 75,000.00 85,000.00 5,625.00 6,375.00
L.03 0.0080 OH Kepala Tukang 85,000.00 95,000.00 680.00 760.00
L.04 0.0010 OH Mandor 75,000.00 90,000.00 75.00 90.00
B Bahan 25,450.00 28,750.00
0.4 Lbr Plywood (120 X 240) cm x 4mm 62,000.00 70,000.00 24,800.00 28,000.00
0.05 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 33,205.00 37,600.00
E Overhead & Profit (contoh 10%) 10% 3,320.50 3,760.00
F Harga Satuan Pekerjaan (D+E) 36,525.50 41,360.00

28 A.4.6.1.28 1 m2 Pemasangan Dinding Bilik, Rangka Kayu Klas III atau IV 118,162.44 128,722.00
A Tenaga 10,050.00 11,675.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.05 OH Tukang Kayu 75,000.00 85,000.00 3,750.00 4,250.00
L.03 0.005 OH Kepala Tukang 85,000.00 95,000.00 425.00 475.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 97,370.40 105,345.00
1.500 m2 Bilik Bambu 20,000.00 22,500.00 30,000.00 33,750.00
0.014 m3 Kayu Klas III (Meranti) 4,800,000.00 5,100,000.00 67,200.00 71,400.00
0.012 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 156.00 180.00
0.003 m' List Kayu 2/4 4,800.00 5,000.00 14.40 15.00
C PERALATAN
D Jumlah A + B + C 107,420.40 117,020.00
E Overhead & Profit (contoh 10%) 10% 10,742.04 11,702.00
F Harga Satuan Pekerjaan (D+E) 118,162.44 128,722.00

file:///conversion/tmp/scratch/443255086.xls 95/47 abk 6-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
VII A.4.1.1 HARGA SATUAN PEKERJAAN BETON
1 A.4.1.1.1 1 m3 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87 920,970.68 1,015,113.00
A Tenaga 119,980.00 140,755.00
L.01 1.65 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 717,266.07 782,075.00
247 Kg Portland Semen 1,250.00 1,300.00 308,750.00 321,100.00
869 Kg Pasir Beton 228.57 250.00 198,628.57 217,250.00
999 Kg Kerikil (maksimum 30 mm) 207.41 240.74 207,200.00 240,500.00
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 837,246.07 922,830.00
E Overhead & Profit (contoh 10%) 10% 83,724.61 92,283.00
F Harga Satuan Pekerjaan (D+E) 920,970.68 1,015,113.00
10%
Overhead & Profit (contoh 10%)
2 A.4.1.1.2 1 m3 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 953,503.03 1,048,750.59
A Tenaga 119,980.00 140,755.00
L.01 1.65 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.28 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.03 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.08 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 746,840.94 812,654.63
276 Kg Portland Semen 1,250.00 1,300.00 345,000.00 358,800.00
828 kg Pasir Beton 228.57 250.00 189,257.14 207,000.00
1,012 kg Kerikil (maksimum 30 mm) 207.41 240.74 209,896.30 243,629.63
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 866,820.94 953,409.63
E Overhead & Profit (contoh 10%) 10% 86,682.09 95,340.96
F Harga Satuan Pekerjaan (D+E) 953,503.03 1,048,750.59

3 A.4.1.1.3 1.00 m3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72 978,977.35 1,074,989.67
A Tenaga 119,980.00 140,755.00
L.01 1.65 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.28 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.03 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.08 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 769,999.40 836,508.33
299 Kg Portland Semen 1,250.00 1,300.00 373,750.00 388,700.00
799 kg Pasir Beton 228.57 250.00 182,628.57 199,750.00
1,017 kg Kerikil (maksimum 30 mm) 207.41 240.74 210,933.33 244,833.33
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 889,979.40 977,263.33
E Overhead & Profit (contoh 10%) 10% 88,997.94 97,726.33
F Harga Satuan Pekerjaan (D+E) 978,977.35 1,074,989.67

4 A.4.1.1.4 1.00 m3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 869,298.86 956,923.81
A Tenaga 83,150.00 97,440.00
L.01 1.200 OH Pekerja 55,000.00 65,000.00 66,000.00 78,000.00
L.02 0.200 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.020 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
B Bahan 707,121.69 772,490.74
230 Kg Portland Semen 1,250.00 1,300.00 287,500.00 299,000.00
893 kg Pasir Beton 228.57 250.00 204,114.29 223,250.00
1,027 kg Kerikil (maksimum 30 mm) 207.41 240.74 213,007.41 247,240.74
200 ltr Air 12.50 15.00 2,500.00 3,000.00
C PERALATAN
D Jumlah A + B + C 790,271.69 869,930.74
E Overhead & Profit (contoh 10%) 10% 79,027.17 86,993.07
F Harga Satuan Pekerjaan (D+E) 869,298.86 956,923.81
5 A.4.1.1.5 1 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 1,009,034.41 1,106,052.44
A Tenaga 119,980.00 140,755.00
L.01 1.65 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 797,324.01 864,747.22
326 Kg Portland Semen 1,250.00 1,300.00 407,500.00 423,800.00
760 Kg Pasir Beton 228.57 250.00 173,714.29 190,000.00
1,029 Kg Kerikil (maksimum 30 mm) 207.41 240.74 213,422.22 247,722.22
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 917,304.01 1,005,502.22
E Overhead & Profit (contoh 10%) 10% 91,730.40 100,550.22

file:///conversion/tmp/scratch/443255086.xls 95/48 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 1,009,034.41 1,106,052.44

file:///conversion/tmp/scratch/443255086.xls 95/49 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.1.1.6 1 m3 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61 1,037,949.28 1,135,787.07
A Tenaga 119,980.00 140,755.00
L.01 1.650 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 823,610.25 891,778.70
352 Kg Portland Semen 1,250.00 1,300.00 440,000.00 457,600.00
731 Kg Pasir Beton 228.57 250.00 167,085.71 182,750.00
1,031 Kg Kerikil (maksimum 30 mm) 207.41 240.74 213,837.04 248,203.70
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 943,590.25 1,032,533.70
E Overhead & Profit (contoh 10%) 10% 94,359.03 103,253.37
F Harga Satuan Pekerjaan (D+E) 1,037,949.28 1,135,787.07

7 A.4.1.1.7 1 m3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 1,059,427.50 1,158,119.11
A Tenaga 119,980.00 140,755.00
L.01 1.650 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 843,135.91 912,080.56
371 Kg Portland Semen 1,250.00 1,300.00 463,750.00 482,300.00
698 Kg Pasir Beton 228.57 250.00 159,542.86 174,500.00
1,047 Kg Kerikil (maksimum 30 mm) 207.41 240.74 217,155.56 252,055.56
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 963,115.91 1,052,835.56
E Overhead & Profit (contoh 10%) 10% 96,311.59 105,283.56
F Harga Satuan Pekerjaan (D+E) 1,059,427.50 1,158,119.11

8 A.4.1.1.8 1 m3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 1,073,968.75 1,172,940.59
A Tenaga 119,980.00 140,755.00
L.01 1.650 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 856,355.22 925,554.63
384 Kg Portland Semen 1,250.00 1,300.00 480,000.00 499,200.00
692 Kg Pasir Beton 228.57 250.00 158,171.43 173,000.00
1,039 Kg Kerikil (maksimum 30 mm) 207.41 240.74 215,496.30 250,129.63
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 976,335.22 1,066,309.63
E Overhead & Profit (contoh 10%) 10% 97,633.52 106,630.96
F Harga Satuan Pekerjaan (D+E) 1,073,968.75 1,172,940.59

9 A.4.1.1.9 1 m3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53 1,099,241.39 1,198,758.00
A Tenaga 119,980.00 140,755.00
L.01 1.650 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 879,330.36 949,025.00
406 Kg Portland Semen 1,250.00 1,300.00 507,500.00 527,800.00
684 kg Pasir Beton 228.57 250.00 156,342.86 171,000.00
1,026 kg Kerikil (maksimum 30 mm) 207.41 240.74 212,800.00 247,000.00
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 999,310.36 1,089,780.00
E Overhead & Profit (contoh 10%) 10% 99,931.04 108,978.00
F Harga Satuan Pekerjaan (D+E) 1,099,241.39 1,198,758.00
10 A.4.1.1.10 1 m3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 1,106,971.37 1,206,618.93
A Tenaga 119,980.00 140,755.00
L.01 1.650 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 886,357.61 956,171.30
413 Kg Portland Semen 1,250.00 1,300.00 516,250.00 536,900.00
681 Kg Pasir Beton 228.57 250.00 155,657.14 170,250.00
1,021 Kg Kerikil (maksimum 30 mm) 207.41 240.74 211,762.96 245,796.30
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 1,006,337.61 1,096,926.30
E Overhead & Profit (contoh 10%) 10% 100,633.76 109,692.63

file:///conversion/tmp/scratch/443255086.xls 95/50 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 1,106,971.37 1,206,618.93

file:///conversion/tmp/scratch/443255086.xls 95/51 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.1.1.11 1 m3 Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm, w/c = 0,49 1,172,415.43 1,278,898.70
A Tenaga 152,600.00 179,025.00
L.01 2.1 OH Pekerja 55,000.00 65,000.00 115,500.00 136,500.00
L.02 0.35 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.105 OH Mandor 75,000.00 90,000.00 7,875.00 9,450.00
B Bahan 913,232.21 983,610.19
439 Kg Portland Semen 1,250.00 1,300.00 548,750.00 570,700.00
670 Kg Pasir Beton 228.57 250.00 153,142.86 167,500.00
1,006 Kg Kerikil (maksimum 30 mm) 207.41 240.74 208,651.85 242,185.19
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 1,065,832.21 1,162,635.19
E Overhead & Profit (contoh 10%) 10% 106,583.22 116,263.52
F Harga Satuan Pekerjaan (D+E) 1,172,415.43 1,278,898.70

12 A.4.1.1.12 1 m3 Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm, w/c = 0,48 1,182,667.26 1,289,354.81
A Tenaga 152,600.00 179,025.00
L.01 2.10 OH Pekerja 55,000.00 65,000.00 115,500.00 136,500.00
L.02 0.350 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.105 OH Mandor 75,000.00 90,000.00 7,875.00 9,450.00
B Bahan 922,552.05 993,115.74
448 Kg Portland Semen 1,250.00 1,300.00 560,000.00 582,400.00
667 Kg Pasir Beton 228.57 250.00 152,457.14 166,750.00
1,000 Kg Kerikil (maksimum 30 mm) 207.41 240.74 207,407.41 240,740.74
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 1,075,152.05 1,172,140.74
E Overhead & Profit (contoh 10%) 10% 107,515.21 117,214.07
F Harga Satuan Pekerjaan (D+E) 1,182,667.26 1,289,354.81

13 A.4.1.1.17 10 Kg Pembesian dg Besi Polos atau Besi Ulir 157,762.00 165,550.00


A Tenaga 9,995.00 11,525.00
L.01 0.07 OH Pekerja 55,000.00 65,000.00 3,850.00 4,550.00
L.02 0.07 OH Tukang Besi 75,000.00 85,000.00 5,250.00 5,950.00
L.03 0.007 OH Kepala Tukang 85,000.00 95,000.00 595.00 665.00
L.04 0.004 OH Mandor 75,000.00 90,000.00 300.00 360.00
B Bahan 133,425.00 138,975.00
10.50 Kg Besi Beton (polos/ulir) 12,500.00 13,000.00 131,250.00 136,500.00
0.150 Kg Kawat Beton 14,500.00 16,500.00 2,175.00 2,475.00
C PERALATAN
D Jumlah A + B + C 143,420.00 150,500.00
E Overhead & Profit (contoh 10%) 10% 14,342.00 15,050.00
F Harga Satuan Pekerjaan (D+E) 157,762.00 165,550.00

14 A.4.1.1.18 10 Kg Kabel Presstresed Polos/strand 119,185.00 132,159.50


A Tenaga 7,150.00 8,245.00
L.01 0.05 OH Pekerja 55,000.00 65,000.00 2,750.00 3,250.00
L.02 0.05 OH Tukang Besi 75,000.00 85,000.00 3,750.00 4,250.00
L.03 0.005 OH Kepala Tukang 85,000.00 95,000.00 425.00 475.00
L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 101,200.00 111,900.00
10.5 Kg Besi presstred polos 9,500.00 10,500.00 99,750.00 110,250.00
0.1 Kg Kawat Beton 14,500.00 16,500.00 1,450.00 1,650.00
C PERALATAN
D Jumlah A + B + C 108,350.00 120,145.00
E Overhead & Profit (contoh 10%) 10% 10,835.00 12,014.50
F Harga Satuan Pekerjaan (D+E) 119,185.00 132,159.50

15 A.4.1.1.19 10 Kg Jaring Kawat baja/Wire Mesh 229,042.00 240,960.50


A Tenaga 3,495.00 4,030.00
L.01 0.025 OH Pekerja 55,000.00 65,000.00 1,375.00 1,625.00
L.02 0.025 OH Tukang Besi 75,000.00 85,000.00 1,875.00 2,125.00
L.03 0.002 OH Kepala Tukang 85,000.00 95,000.00 170.00 190.00
L.04 0.001 OH Mandor 75,000.00 90,000.00 75.00 90.00
B Bahan 204,725.00 215,025.00
10.20 Kg Jaring Kawat Baja dilas 20,000.00 21,000.00 204,000.00 214,200.00
0.05 Kg Kawat Beton 14,500.00 16,500.00 725.00 825.00
C PERALATAN
D Jumlah A + B + C 208,220.00 219,055.00
E Overhead & Profit (contoh 10%) 10% 20,822.00 21,905.50
F Harga Satuan Pekerjaan (D+E) 229,042.00 240,960.50

file:///conversion/tmp/scratch/443255086.xls 95/52 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
16 A.4.1.1.20 1 m2 Memasang Bekisting untuk Pondasi 150,766.00 165,231.00
A Tenaga 52,260.00 60,710.00
L.01 0.52 OH Pekerja 55,000.00 65,000.00 28,600.00 33,800.00
L.02 0.26 OH Tukang Kayu 75,000.00 85,000.00 19,500.00 22,100.00
L.03 0.026 OH Kepala Tukang 85,000.00 95,000.00 2,210.00 2,470.00
L.04 0.026 OH Mandor 75,000.00 90,000.00 1,950.00 2,340.00
B Bahan 84,800.00 89,500.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 80,000.00 84,000.00
0.3 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 3,900.00 4,500.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 137,060.00 150,210.00
E Overhead & Profit (contoh 10%) 10% 13,706.00 15,021.00
F Harga Satuan Pekerjaan (D+E) 150,766.00 165,231.00

17 A.4.1.1.21 1 m2 Memasang Bekisting untuk Sloof 161,766.00 176,781.00


A Tenaga 52,260.00 60,710.00
L.01 0.52 OH Pekerja 55,000.00 65,000.00 28,600.00 33,800.00
L.02 0.26 OH Tukang Kayu 75,000.00 85,000.00 19,500.00 22,100.00
L.03 0.026 OH Kepala Tukang 85,000.00 95,000.00 2,210.00 2,470.00
L.04 0.026 OH Mandor 75,000.00 90,000.00 1,950.00 2,340.00
B Bahan 94,800.00 100,000.00
0.045 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 90,000.00 94,500.00
0.3 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 3,900.00 4,500.00
0.1 Ltr Minyak Bekisting 9,000.00 10,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 147,060.00 160,710.00
E Overhead & Profit (contoh 10%) 10% 14,706.00 16,071.00
F Harga Satuan Pekerjaan (D+E) 161,766.00 176,781.00

18 A.4.1.1.22 1 m2 Memasang Bekisting untuk Kolom 335,588.00 383,135.50


A Tenaga 66,330.00 77,055.00
L.01 0.66 OH Pekerja 55,000.00 65,000.00 36,300.00 42,900.00
L.02 0.33 OH Tukang Kayu 75,000.00 85,000.00 24,750.00 28,050.00
L.03 0.033 OH Kepala Tukang 85,000.00 95,000.00 2,805.00 3,135.00
L.04 0.033 OH Mandor 75,000.00 90,000.00 2,475.00 2,970.00
B Bahan 238,750.00 271,250.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 80,000.00 84,000.00
0.4 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 5,200.00 6,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II 4,800,000.00 5,550,000.00 72,000.00 83,250.00
0.35 Lbr Plywood tebal 9mm 125,000.00 160,000.00 43,750.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 18,000.00 20,000.00 36,000.00 40,000.00
C PERALATAN
D Jumlah A + B + C 305,080.00 348,305.00
E Overhead & Profit (contoh 10%) 10% 30,508.00 34,830.50
F Harga Satuan Pekerjaan (D+E) 335,588.00 383,135.50

19 A.4.1.1.23 1 m2 Memasang Bekisting untuk Balok 351,428.00 401,450.50


A Tenaga 66,330.00 77,055.00
L.01 0.66 OH Pekerja 55,000.00 65,000.00 36,300.00 42,900.00
L.02 0.33 OH Tukang Kayu 75,000.00 85,000.00 24,750.00 28,050.00
L.03 0.033 OH Kepala Tukang 85,000.00 95,000.00 2,805.00 3,135.00
L.04 0.033 OH Mandor 75,000.00 90,000.00 2,475.00 2,970.00
B Bahan 253,150.00 287,900.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 80,000.00 84,000.00
0.4 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 5,200.00 6,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.018 m3 Balok Kayu Klas II 4,800,000.00 5,550,000.00 86,400.00 99,900.00
0.35 Lbr Plywood tebal 9mm 125,000.00 160,000.00 43,750.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 18,000.00 20,000.00 36,000.00 40,000.00
C PERALATAN
D Jumlah A + B + C 319,480.00 364,955.00
E Overhead & Profit (contoh 10%) 10% 31,948.00 36,495.50
F Harga Satuan Pekerjaan (D+E) 351,428.00 401,450.50

20 A.4.1.1.24 1 m2 Memasang Bekisting untuk Lantai 414,788.00 471,135.50


A Tenaga 66,330.00 77,055.00
L.01 0.66 OH Pekerja 55,000.00 65,000.00 36,300.00 42,900.00
L.02 0.33 OH Tukang Kayu 75,000.00 85,000.00 24,750.00 28,050.00
L.03 0.033 OH Kepala Tukang 85,000.00 95,000.00 2,805.00 3,135.00
L.04 0.033 OH Mandor 75,000.00 90,000.00 2,475.00 2,970.00

file:///conversion/tmp/scratch/443255086.xls 95/53 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 310,750.00 351,250.00
0.04 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 80,000.00 84,000.00
0.4 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 5,200.00 6,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.015 m3 Balok Kayu Klas II (Borneo) 4,800,000.00 5,550,000.00 72,000.00 83,250.00
0.35 Lbr Plywood tebal 9mm 125,000.00 160,000.00 43,750.00 56,000.00
6 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 18,000.00 20,000.00 108,000.00 120,000.00
C PERALATAN
D Jumlah A + B + C 377,080.00 428,305.00
E Overhead & Profit (contoh 10%) 10% 37,708.00 42,830.50
F Harga Satuan Pekerjaan (D+E) 414,788.00 471,135.50

21 A.4.1.1.25 1 m2 Memasang Bekisting untuk Dinding 381,788.00 436,760.50


A Tenaga 66,330.00 77,055.00
L.01 0.66 OH Pekerja 55,000.00 65,000.00 36,300.00 42,900.00
L.02 0.33 OH Tukang Kayu 75,000.00 85,000.00 24,750.00 28,050.00
L.03 0.033 OH Kepala Tukang 85,000.00 95,000.00 2,805.00 3,135.00
L.04 0.033 OH Mandor 75,000.00 90,000.00 2,475.00 2,970.00
B Bahan 280,750.00 320,000.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 60,000.00 63,000.00
0.4 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 5,200.00 6,000.00
0.2 Ltr Minyak Bekisting 9,000.00 10,000.00 1,800.00 2,000.00
0.02 m3 Balok Kayu Klas II 4,800,000.00 5,550,000.00 96,000.00 111,000.00
0.35 Lbr Plywood tebal 9mm 125,000.00 160,000.00 43,750.00 56,000.00
3 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 18,000.00 20,000.00 54,000.00 60,000.00
4 Buah Formite/Penjaga jarak / Spacer (alat bantu) 5,000.00 5,500.00 20,000.00 22,000.00
C PERALATAN
D Jumlah A + B + C 347,080.00 397,055.00
E Overhead & Profit (contoh 10%) 10% 34,708.00 39,705.50
F Harga Satuan Pekerjaan (D+E) 381,788.00 436,760.50

22 A.4.1.1.26 1 m2 Memasang Bekisting untuk Tangga 313,093.00 359,485.50


A Tenaga 66,330.00 77,055.00
L.01 0.66 OH Pekerja 55,000.00 65,000.00 36,300.00 42,900.00
L.02 0.33 OH Tukang Kayu 75,000.00 85,000.00 24,750.00 28,050.00
L.03 0.033 OH Kepala Tukang 85,000.00 95,000.00 2,805.00 3,135.00
L.04 0.033 OH Mandor 75,000.00 90,000.00 2,475.00 2,970.00
B Bahan 218,300.00 249,750.00
0.03 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 60,000.00 63,000.00
0.4 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 5,200.00 6,000.00
0.15 Ltr Minyak Bekisting 9,000.00 10,000.00 1,350.00 1,500.00
0.015 m3 Balok Kayu Klas II 4,800,000.00 5,550,000.00 72,000.00 83,250.00
0.35 Lbr Plywood tebal 9mm 125,000.00 160,000.00 43,750.00 56,000.00
2 Btg Dolken Kayu Galam diameter 8 - 10 cm / 4 m 18,000.00 20,000.00 36,000.00 40,000.00
C PERALATAN
D Jumlah A + B + C 284,630.00 326,805.00
E Overhead & Profit (contoh 10%) 10% 28,463.00 32,680.50
F Harga Satuan Pekerjaan (D+E) 313,093.00 359,485.50

23 A.4.1.1.27 1 m2 Memasang Jembatan Cor 90,887.50 98,598.50


A Tenaga 13,025.00 15,195.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.05 OH Tukang Kayu 75,000.00 85,000.00 3,750.00 4,250.00
L.03 0.005 OH Kepala Tukang 85,000.00 95,000.00 425.00 475.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 69,600.00 74,440.00
0.0264 m3 Kayu Terentang 2,000,000.00 2,100,000.00 52,800.00 55,440.00
0.6 kg Paku Biasa 2" - 5" 13,000.00 15,000.00 7,800.00 9,000.00
0.5 m3 Dolken Kayu Galam diameter 8 - 10 / 4 m 18,000.00 20,000.00 9,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 82,625.00 89,635.00
E Overhead & Profit (contoh 10%) 10% 8,262.50 8,963.50
F Harga Satuan Pekerjaan (D+E) 90,887.50 98,598.50

24 A.4.1.1.28 1 m3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) 3,632,304.50 4,007,069.00
A Tenaga 530,520.00 616,365.00
L.01 5.3 OH Pekerja 55,000.00 65,000.00 291,500.00 344,500.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.30 OH Tukang Kayu 75,000.00 85,000.00 97,500.00 110,500.00
L.02 1.05 OH Tukang Besi 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.262 OH Kepala Tukang 85,000.00 95,000.00 22,270.00 24,890.00
L.04 0.265 OH Mandor 75,000.00 90,000.00 19,875.00 23,850.00

file:///conversion/tmp/scratch/443255086.xls 95/54 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 2,771,575.00 3,026,425.00
0.2 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 400,000.00 420,000.00
1.5 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 19,500.00 22,500.00
0.4 Ltr Minyak Bekisting 9,000.00 10,000.00 3,600.00 4,000.00
157.5 Kg Besi Beton Polos 9,500.00 10,500.00 1,496,250.00 1,653,750.00
2.25 Kg Kawat Beton 14,500.00 16,500.00 32,625.00 37,125.00
336 Kg Portland Semen 1,250.00 1,300.00 420,000.00 436,800.00
0.54 m3 Pasir Beton 320,000.00 350,000.00 172,800.00 189,000.00
0.81 m3 Kerikil Beton 280,000.00 325,000.00 226,800.00 263,250.00
C PERALATAN
D Jumlah A + B + C 3,302,095.00 3,642,790.00
E Overhead & Profit (contoh 10%) 10% 330,209.50 364,279.00
F Harga Satuan Pekerjaan (D+E) 3,632,304.50 4,007,069.00

25 A.4.1.1.29 1 m3 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) 4,434,710.50 4,889,423.00
A Tenaga 602,055.00 698,380.00
L.01 5.65 OH Pekerja 55,000.00 65,000.00 310,750.00 367,250.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.56 OH Tukang Kayu 75,000.00 85,000.00 117,000.00 132,600.00
L.02 1.4 OH Tukang Besi 75,000.00 85,000.00 105,000.00 119,000.00
L.03 0.323 OH Kepala Tukang 85,000.00 95,000.00 27,455.00 30,685.00
L.04 0.283 OH Mandor 75,000.00 90,000.00 21,225.00 25,470.00
B Bahan 3,429,500.00 3,746,550.00
0.27 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 540,000.00 567,000.00
2 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 26,000.00 30,000.00
0.6 Ltr Minyak Bekisting 9,000.00 10,000.00 5,400.00 6,000.00
210 Kg Besi Beton Polos 9,500.00 10,500.00 1,995,000.00 2,205,000.00
3 Kg Kawat Beton 14,500.00 16,500.00 43,500.00 49,500.00
336 Kg Portland Semen 1,250.00 1,300.00 420,000.00 436,800.00
0.54 m3 Pasir Beton 320,000.00 350,000.00 172,800.00 189,000.00
0.81 m3 Kerikil Beton 280,000.00 325,000.00 226,800.00 263,250.00
C PERALATAN
D Jumlah A + B + C 4,031,555.00 4,444,930.00
E Overhead & Profit (contoh 10%) 10% 403,155.50 444,493.00
F Harga Satuan Pekerjaan (D+E) 4,434,710.50 4,889,423.00

26 A.4.1.1.30 1 m3 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 7,716,725.50 8,639,103.00
A Tenaga 750,355.00 870,430.00
L.01 7.05 OH Pekerja 55,000.00 65,000.00 387,750.00 458,250.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.65 OH Tukang Kayu 75,000.00 85,000.00 123,750.00 140,250.00
L.02 2.1 OH Tukang Besi 75,000.00 85,000.00 157,500.00 178,500.00
L.03 0.403 OH Kepala Tukang 85,000.00 95,000.00 34,255.00 38,285.00
L.04 0.353 OH Mandor 75,000.00 90,000.00 26,475.00 31,770.00
B Bahan 6,264,850.00 6,983,300.00
0.4 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 800,000.00 840,000.00
4 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 52,000.00 60,000.00
2 Ltr Minyak Bekisting 9,000.00 10,000.00 18,000.00 20,000.00
315 kg Besi Beton Polos 9,500.00 10,500.00 2,992,500.00 3,307,500.00
4.5 kg Kawat Beton 14,500.00 16,500.00 65,250.00 74,250.00
336 Kg Portland Semen 1,250.00 1,300.00 420,000.00 436,800.00
0.54 m3 Pasir Beton 320,000.00 350,000.00 172,800.00 189,000.00
0.81 m3 Kerikil Beton 280,000.00 325,000.00 226,800.00 263,250.00
0.15 m3 Kayu Klas II Balok 4,800,000.00 5,550,000.00 720,000.00 832,500.00
3.5 Lbr Plywood 9 mm 125,000.00 160,000.00 437,500.00 560,000.00
20 Btg Dolken diameter 8 / 4rm 18,000.00 20,000.00 360,000.00 400,000.00
C PERALATAN
D Jumlah A + B + C 7,015,205.00 7,853,730.00
E Overhead & Profit (contoh 10%) 10% 701,520.50 785,373.00
F Harga Satuan Pekerjaan (D+E) 7,716,725.50 8,639,103.00

27 A.4.1.1.31 1 m3 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) 6,066,368.00 6,798,198.00
A Tenaga 650,780.00 755,630.00
L.01 6.35 OH Pekerja 55,000.00 65,000.00 349,250.00 412,750.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.65 OH Tukang Kayu 75,000.00 85,000.00 123,750.00 140,250.00
L.02 1.4 OH Tukang Besi 75,000.00 85,000.00 105,000.00 119,000.00
L.03 0.333 OH Kepala Tukang 85,000.00 95,000.00 28,305.00 31,635.00
L.04 0.318 OH Mandor 75,000.00 90,000.00 23,850.00 28,620.00

file:///conversion/tmp/scratch/443255086.xls 95/55 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 4,864,100.00 5,424,550.00
0.32 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 640,000.00 672,000.00
3.2 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 41,600.00 48,000.00
1.6 Ltr Minyak Bekisting 9,000.00 10,000.00 14,400.00 16,000.00
210 Kg Besi Beton Polos 9,500.00 10,500.00 1,995,000.00 2,205,000.00
3 Kg Kawat Beton 14,500.00 16,500.00 43,500.00 49,500.00
336 Kg Portland Semen 1,250.00 1,300.00 420,000.00 436,800.00
0.54 m3 Pasir Beton 320,000.00 350,000.00 172,800.00 189,000.00
0.81 m3 Kerikil Beton 280,000.00 325,000.00 226,800.00 263,250.00
0.14 m3 Kayu Klas II Balok 4,800,000.00 5,550,000.00 672,000.00 777,000.00
2.8 Lbr Plywood 9 mm 125,000.00 160,000.00 350,000.00 448,000.00
16 Btg Dolken diameter 8 / 4rm 18,000.00 20,000.00 288,000.00 320,000.00
C PERALATAN
D Jumlah A + B + C 5,514,880.00 6,180,180.00
E Overhead & Profit (contoh 10%) 10% 551,488.00 618,018.00
F Harga Satuan Pekerjaan (D+E) 6,066,368.00 6,798,198.00

28 A.4.1.1.32 1 m3 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting) 5,584,975.00 6,255,232.50
A Tenaga 530,775.00 616,650.00
L.01 5.3 OH Pekerja 55,000.00 65,000.00 291,500.00 344,500.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.3 OH Tukang Kayu 75,000.00 85,000.00 97,500.00 110,500.00
L.02 1.05 OH Tukang Besi 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.265 OH Kepala Tukang 85,000.00 95,000.00 22,525.00 25,175.00
L.04 0.265 OH Mandor 75,000.00 90,000.00 19,875.00 23,850.00
B Bahan 4,546,475.00 5,069,925.00
0.32 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 640,000.00 672,000.00
3.2 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 41,600.00 48,000.00
1.6 Ltr Minyak Bekisting 9,000.00 10,000.00 14,400.00 16,000.00
157.5 Kg Besi Beton Polos 9,500.00 10,500.00 1,496,250.00 1,653,750.00
2.25 Kg Kawat Beton 14,500.00 16,500.00 32,625.00 37,125.00
336 Kg Portland Semen 1,250.00 1,300.00 420,000.00 436,800.00
0.54 m3 Pasir Beton 320,000.00 350,000.00 172,800.00 189,000.00
0.81 m3 Kerikil Beton 280,000.00 325,000.00 226,800.00 263,250.00
0.12 m3 Kayu Klas II Balok 4,800,000.00 5,550,000.00 576,000.00 666,000.00
2.8 Lbr Plywood 9 mm 125,000.00 160,000.00 350,000.00 448,000.00
32 Btg Dolken diameter 8 / 4rm 18,000.00 20,000.00 576,000.00 640,000.00
C PERALATAN
D Jumlah A + B + C 5,077,250.00 5,686,575.00
E Overhead & Profit (contoh 10%) 10% 507,725.00 568,657.50
F Harga Satuan Pekerjaan (D+E) 5,584,975.00 6,255,232.50

29 A.4.1.1.33 1 m3 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting) 5,461,494.50 6,138,319.00
A Tenaga 530,520.00 616,365.00
L.01 5.3 OH Pekerja 55,000.00 65,000.00 291,500.00 344,500.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.3 OH Tukang Kayu 75,000.00 85,000.00 97,500.00 110,500.00
L.02 1.05 OH Tukang Besi 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.262 OH Kepala Tukang 85,000.00 95,000.00 22,270.00 24,890.00
L.04 0.265 OH Mandor 75,000.00 90,000.00 19,875.00 23,850.00
B Bahan 4,434,475.00 4,963,925.00
0.24 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 480,000.00 504,000.00
3.2 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 41,600.00 48,000.00
1.6 Ltr Minyak Bekisting 9,000.00 10,000.00 14,400.00 16,000.00
157.5 Kg Besi Beton Polos 9,500.00 10,500.00 1,496,250.00 1,653,750.00
2.25 Kg Kawat Beton 14,500.00 16,500.00 32,625.00 37,125.00
336 Kg Portland Semen 1,250.00 1,300.00 420,000.00 436,800.00
0.54 m3 Pasir Beton 320,000.00 350,000.00 172,800.00 189,000.00
0.81 m3 Kerikil Beton 280,000.00 325,000.00 226,800.00 263,250.00
0.16 m3 Kayu Klas II Balok 4,800,000.00 5,550,000.00 768,000.00 888,000.00
2.8 Lbr Plywood 9 mm 125,000.00 160,000.00 350,000.00 448,000.00
24 Btg Dolken diameter 8 / 4rm 18,000.00 20,000.00 432,000.00 480,000.00
C PERALATAN
D Jumlah A + B + C 4,964,995.00 5,580,290.00
E Overhead & Profit (contoh 10%) 10% 496,499.50 558,029.00
F Harga Satuan Pekerjaan (D+E) 5,461,494.50 6,138,319.00

30 A.4.1.1.34 1 m3 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) 5,586,300.50 6,255,348.00
A Tenaga 602,055.00 698,380.00
L.01 5.65 OH Pekerja 55,000.00 65,000.00 310,750.00 367,250.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.56 OH Tukang Kayu 75,000.00 85,000.00 117,000.00 132,600.00
L.02 1.4 OH Tukang Besi 75,000.00 85,000.00 105,000.00 119,000.00
L.03 0.323 OH Kepala Tukang 85,000.00 95,000.00 27,455.00 30,685.00
L.04 0.283 OH Mandor 75,000.00 90,000.00 21,225.00 25,470.00

file:///conversion/tmp/scratch/443255086.xls 95/56 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 4,476,400.00 4,988,300.00
0.25 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 500,000.00 525,000.00
3 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 39,000.00 45,000.00
1.2 Ltr Minyak Bekisting 9,000.00 10,000.00 10,800.00 12,000.00
210 Kg Besi Beton Polos 9,500.00 10,500.00 1,995,000.00 2,205,000.00
3 Kg Kawat Beton 14,500.00 16,500.00 43,500.00 49,500.00
336 Kg Portland Semen 1,250.00 1,300.00 420,000.00 436,800.00
0.54 m3 Pasir Beton 320,000.00 350,000.00 172,800.00 189,000.00
0.81 m3 Kerikil Beton 280,000.00 325,000.00 226,800.00 263,250.00
0.105 m3 Kayu Klas II Balok 4,800,000.00 5,550,000.00 504,000.00 582,750.00
2.5 Lbr Plywood 9 mm 125,000.00 160,000.00 312,500.00 400,000.00
14 Btg Dolken diameter 8 / 4rm 18,000.00 20,000.00 252,000.00 280,000.00
C PERALATAN
D Jumlah A + B + C 5,078,455.00 5,686,680.00
E Overhead & Profit (contoh 10%) 10% 507,845.50 568,668.00
F Harga Satuan Pekerjaan (D+E) 5,586,300.50 6,255,348.00

31 A.4.1.1.35 1 m' Membuat Kolom Penguat Beton Bertulang (11 x 11) cm 64,138.25 71,497.25
A Tenaga 15,585.00 18,180.00
L.01 0.18 OH Pekerja 55,000.00 65,000.00 9,900.00 11,700.00
L.02 0.02 OH Tukang batu 75,000.00 85,000.00 1,500.00 1,700.00
L.02 0.02 OH Tukang Kayu 75,000.00 85,000.00 1,500.00 1,700.00
L.02 0.02 OH Tukang Besi 75,000.00 85,000.00 1,500.00 1,700.00
L.03 0.006 OH Kepala Tukang 85,000.00 95,000.00 510.00 570.00
L.04 0.009 OH Mandor 75,000.00 90,000.00 675.00 810.00
B Bahan 42,722.50 46,817.50
0.002 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 4,000.00 4,200.00
0.01 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 130.00 150.00
3 Kg Besi Beton Polos 9,500.00 10,500.00 28,500.00 31,500.00
0.045 Kg Kawat Beton 14,500.00 16,500.00 652.50 742.50
4 Kg Portland Semen 1,250.00 1,300.00 5,000.00 5,200.00
0.006 m3 Pasir Beton 320,000.00 350,000.00 1,920.00 2,100.00
0.009 m3 Kerikil Beton 280,000.00 325,000.00 2,520.00 2,925.00
C PERALATAN
D Jumlah A + B + C 58,307.50 64,997.50
E Overhead & Profit (contoh 10%) 10% 5,830.75 6,499.75
F Harga Satuan Pekerjaan (D+E) 64,138.25 71,497.25

32 A.4.1.1.36 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 88,962.50 99,462.00
A Tenaga 25,735.00 30,020.00
L.01 0.297 OH Pekerja 55,000.00 65,000.00 16,335.00 19,305.00
L.02 0.033 OH Tukang batu 75,000.00 85,000.00 2,475.00 2,805.00
L.02 0.033 OH Tukang Kayu 75,000.00 85,000.00 2,475.00 2,805.00
L.02 0.033 OH Tukang Besi 75,000.00 85,000.00 2,475.00 2,805.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 55,140.00 60,400.00
0.003 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 6,000.00 6,300.00
0.02 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 260.00 300.00
3.6 Kg Besi Beton Polos 9,500.00 10,500.00 34,200.00 37,800.00
0.05 Kg Kawat Beton 14,500.00 16,500.00 725.00 825.00
5.5 Kg Portland Semen 1,250.00 1,300.00 6,875.00 7,150.00
0.009 m3 Pasir Beton 320,000.00 350,000.00 2,880.00 3,150.00
0.015 m3 Kerikil Beton 280,000.00 325,000.00 4,200.00 4,875.00
C PERALATAN
D Jumlah A + B + C 80,875.00 90,420.00
E Overhead & Profit (contoh 10%) 10% 8,087.50 9,042.00
F Harga Satuan Pekerjaan (D+E) 88,962.50 99,462.00

file:///conversion/tmp/scratch/443255086.xls 95/57 abk 7-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

VIII A.4.5.2 HARGA SATUAN PEKERJAAN PENUTUP ATAP


1 A.4.5.2.1 1 m2 Pemasangan Atap Genteng Plentong Kecil 77,123.75 85,313.25
A Tenaga 15,112.50 17,557.50
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.075 OH Tukang Kayu 75,000.00 85,000.00 5,625.00 6,375.00
L.03 0.0075 OH Kepala Tukang 85,000.00 95,000.00 637.50 712.50
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 55,000.00 60,000.00
25 Buah Genteng Plentong 2,200.00 2,400.00 55,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 70,112.50 77,557.50
E Overhead & Profit (contoh 10%) 10% 7,011.25 7,755.75
F Harga Satuan Pekerjaan (D+E) 77,123.75 85,313.25

Overhead & Profit (contoh 10%)


2 A.4.5.2.2 1 m2 Pemasangan Atap Genteng Kodok / Glasur 126,670.50 136,240.50
A Tenaga 15,155.00 17,605.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.075 OH Tukang Kayu 75,000.00 85,000.00 5,625.00 6,375.00
L.03 0.008 OH Kepala Tukang 85,000.00 95,000.00 680.00 760.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 100,000.00 106,250.00
25 Buah Genteng Kodok / Glasur 4,000.00 4,250.00 100,000.00 106,250.00
C PERALATAN
D Jumlah A + B + C 115,155.00 123,855.00
E Overhead & Profit (contoh 10%) 10% 11,515.50 12,385.50
F Harga Satuan Pekerjaan (D+E) 126,670.50 136,240.50

3 A.4.5.2.3 1 m2 Pemasangan Atap Genteng Plentong Super / Besar 117,650.50 125,295.50


A Tenaga 15,155.00 17,605.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.075 OH Tukang Kayu 75,000.00 85,000.00 5,625.00 6,375.00
L.03 0.008 OH Kepala Tukang 85,000.00 95,000.00 680.00 760.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 91,800.00 96,300.00
18 Buah Genteng Plentong Super / Besar 5,100.00 5,350.00 91,800.00 96,300.00
C PERALATAN
D Jumlah A + B + C 106,955.00 113,905.00
E Overhead & Profit (contoh 10%) 10% 10,695.50 11,390.50
F Harga Satuan Pekerjaan (D+E) 117,650.50 125,295.50

4 A.4.5.2.4 1 m' Pemasangan Genteng Bubung Plentong 111,155.00 121,132.00


A Tenaga 38,850.00 45,080.00
L.01 0.4 OH Pekerja 55,000.00 65,000.00 22,000.00 26,000.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.002 OH Mandor 75,000.00 90,000.00 150.00 180.00
B Bahan 62,200.00 65,040.00
5 Buah Genteng Bubung Plentong 9,000.00 9,200.00 45,000.00 46,000.00
8 Kg Portland Semen 1,250.00 1,300.00 10,000.00 10,400.00
0.032 m3 Pasir Pasang 225,000.00 270,000.00 7,200.00 8,640.00
C PERALATAN
D Jumlah A + B + C 101,050.00 110,120.00
E Overhead & Profit (contoh 10%) 10% 10,105.00 11,012.00
F Harga Satuan Pekerjaan (D+E) 111,155.00 121,132.00

file:///conversion/tmp/scratch/443255086.xls 95/58 abk 8-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.5.2.5 1 m' Pemasangan Genteng Bubung Kodok / Glasur 97,405.00 107,932.00
A Tenaga 38,850.00 45,080.00
L.01 0.4 OH Pekerja 55,000.00 65,000.00 22,000.00 26,000.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.002 OH Mandor 75,000.00 90,000.00 150.00 180.00
B Bahan 49,700.00 53,040.00
5 Buah Genteng Bubung Kodok / Glasur 6,500.00 6,800.00 32,500.00 34,000.00
8 Kg Portland Semen 1,250.00 1,300.00 10,000.00 10,400.00
0.032 m3 Pasir Pasang 225,000.00 270,000.00 7,200.00 8,640.00
C PERALATAN
D Jumlah A + B + C 88,550.00 98,120.00
E Overhead & Profit (contoh 10%) 10% 8,855.00 9,812.00
F Harga Satuan Pekerjaan (D+E) 97,405.00 107,932.00

6 A.4.5.2.6 1 m' Pemasangan Genteng Bubung Plentong Besar 101,255.00 111,012.00


A Tenaga 38,850.00 45,080.00
L.01 0.4 OH Pekerja 55,000.00 65,000.00 22,000.00 26,000.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.002 OH Mandor 75,000.00 90,000.00 150.00 180.00
B Bahan 53,200.00 55,840.00
4 Buah Genteng Bubung Plentong Besar 9,000.00 9,200.00 36,000.00 36,800.00
8 Kg Portland Semen 1,250.00 1,300.00 10,000.00 10,400.00
0.032 m3 Pasir Pasang 225,000.00 270,000.00 7,200.00 8,640.00
C PERALATAN
D Jumlah A + B + C 92,050.00 100,920.00
E Overhead & Profit (contoh 10%) 10% 9,205.00 10,092.00
F Harga Satuan Pekerjaan (D+E) 101,255.00 111,012.00

7 A.4.5.2.9 1 m2 Pemasangan Atap Asbes Gelombang (2,25x0,92 m) x 5 mm 65,301.50 74,420.50


A Tenaga 14,605.00 16,955.00
L.01 0.14 OH Pekerja 55,000.00 65,000.00 7,700.00 9,100.00
L.02 0.075 OH Tukang Kayu 75,000.00 85,000.00 5,625.00 6,375.00
L.03 0.008 OH Kepala Tukang 85,000.00 95,000.00 680.00 760.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 44,760.00 50,700.00
0.6 Lbr Asbes Gelombang 71,500.00 81,200.00 42,900.00 48,720.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 59,365.00 67,655.00
E Overhead & Profit (contoh 10%) 10% 5,936.50 6,765.50
F Harga Satuan Pekerjaan (D+E) 65,301.50 74,420.50

8 A.4.5.2.10 1 m2 Pemasangan Atap Asbes Gelombang (2,00x0,92 m) x 5 mm 59,433.00 67,809.50


A Tenaga 14,070.00 16,345.00
L.01 0.14 OH Pekerja 55,000.00 65,000.00 7,700.00 9,100.00
L.02 0.07 OH Tukang Kayu 75,000.00 85,000.00 5,250.00 5,950.00
L.03 0.007 OH Kepala Tukang 85,000.00 95,000.00 595.00 665.00
L.04 0.007 OH Mandor 75,000.00 90,000.00 525.00 630.00
B Bahan 39,960.00 45,300.00
0.6 Lbr Asbes Gelombang 63,500.00 72,200.00 38,100.00 43,320.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 54,030.00 61,645.00
E Overhead & Profit (contoh 10%) 10% 5,403.00 6,164.50
F Harga Satuan Pekerjaan (D+E) 59,433.00 67,809.50

file:///conversion/tmp/scratch/443255086.xls 95/59 abk 8-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.4.5.2.12 1 m2 Pemasangan Atap Asbes Gelombang (3,00x1,05 m) x 4 mm 50,248.00 56,732.50
A Tenaga 14,070.00 16,345.00
L.01 0.14 OH Pekerja 55,000.00 65,000.00 7,700.00 9,100.00
L.02 0.07 OH Tukang Kayu 75,000.00 85,000.00 5,250.00 5,950.00
L.03 0.007 OH Kepala Tukang 85,000.00 95,000.00 595.00 665.00
L.04 0.007 OH Mandor 75,000.00 90,000.00 525.00 630.00
B Bahan 31,610.00 35,230.00
0.35 Lbr Asbes Gelombang 85,000.00 95,000.00 29,750.00 33,250.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 45,680.00 51,575.00
E Overhead & Profit (contoh 10%) 10% 4,568.00 5,157.50
F Harga Satuan Pekerjaan (D+E) 50,248.00 56,732.50

10 A.4.5.2.15 1 m2 Pemasangan Atap Asbes Gelombang (2,10x1,05 m) x 4 mm 51,183.00 56,622.50


A Tenaga 14,070.00 16,345.00
L.01 0.14 OH Pekerja 55,000.00 65,000.00 7,700.00 9,100.00
L.02 0.070 OH Tukang Kayu 75,000.00 85,000.00 5,250.00 5,950.00
L.03 0.007 OH Kepala Tukang 85,000.00 95,000.00 595.00 665.00
L.04 0.007 OH Mandor 75,000.00 90,000.00 525.00 630.00
B Bahan 32,460.00 35,130.00
0.51 Lbr Asbes Gelombang 60,000.00 65,000.00 30,600.00 33,150.00
0.12 Kg Paku Pancing 60 x 230 15,500.00 16,500.00 1,860.00 1,980.00
C PERALATAN
D Jumlah A + B + C 46,530.00 51,475.00
E Overhead & Profit (contoh 10%) 10% 4,653.00 5,147.50
F Harga Satuan Pekerjaan (D+E) 51,183.00 56,622.50

11 A.4.5.2.30 1 m2 Pemasangan Atap Genteng Beton 95,139.00 110,880.00


A Tenaga 20,100.00 23,350.00
L.01 0.2 OH Pekerja 55,000.00 65,000.00 11,000.00 13,000.00
L.02 0.1 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.01 OH Mandor 75,000.00 90,000.00 750.00 900.00
B Bahan 66,390.00 77,450.00
11 Lbr Genteng Beton Standrad 6,000.00 7,000.00 66,000.00 77,000.00
0.03 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 390.00 450.00
C PERALATAN
D Jumlah A + B + C 86,490.00 100,800.00
E Overhead & Profit (contoh 10%) 10% 8,649.00 10,080.00
F Harga Satuan Pekerjaan (D+E) 95,139.00 110,880.00

12 A.4.5.2.32 1 m2 Pemasangan Atap Genteng Metal 81,070.00 96,305.00


A Tenaga 20,100.00 23,350.00
L.01 0.2 OH Pekerja 55,000.00 65,000.00 11,000.00 13,000.00
L.02 0.1 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.01 OH Mandor 75,000.00 90,000.00 750.00 900.00
B Bahan 53,600.00 64,200.00
1.02 m2 Genteng Metal 50,000.00 60,000.00 51,000.00 61,200.00
0.20 Kg Paku Biasa Ø ½" - 1" 13,000.00 15,000.00 2,600.00 3,000.00
C PERALATAN
D Jumlah A + B + C 73,700.00 87,550.00
E Overhead & Profit (contoh 10%) 10% 7,370.00 8,755.00
F Harga Satuan Pekerjaan (D+E) 81,070.00 96,305.00

13 A.4.5.2.33 1 m2 Pemasangan Atap Sirap 97,575.50 104,648.50


A Tenaga 30,605.00 35,135.00
L.01 0.166 OH Pekerja 55,000.00 65,000.00 9,130.00 10,790.00
L.02 0.25 OH Tukang Kayu 75,000.00 85,000.00 18,750.00 21,250.00
L.03 0.025 OH Kepala Tukang 85,000.00 95,000.00 2,125.00 2,375.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 58,100.00 60,000.00
30 Lbr Genteng Sirap 1,850.00 1,900.00 55,500.00 57,000.00

file:///conversion/tmp/scratch/443255086.xls 95/60 abk 8-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
0.2 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 2,600.00 3,000.00

file:///conversion/tmp/scratch/443255086.xls 95/61 abk 8-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
C PERALATAN
D Jumlah A + B + C 88,705.00 95,135.00
E Overhead & Profit (contoh 10%) 10% 8,870.50 9,513.50
F Harga Satuan Pekerjaan (D+E) 97,575.50 104,648.50

14 A.4.5.2.34 1 m' Pemasangan Nok Genteng Beton 100,430.00 115,643.00


A Tenaga 40,200.00 46,700.00
L.01 0.4 OH Pekerja 55,000.00 65,000.00 22,000.00 26,000.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.02 OH Mandor 75,000.00 90,000.00 1,500.00 1,800.00
B Bahan 51,100.00 58,430.00
3.5 Buah Nok Genteng Beton 8,500.00 10,000.00 29,750.00 35,000.00
0.05 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 650.00 750.00
10.8 Kg Portland Semen 1,250.00 1,300.00 13,500.00 14,040.00
0.032 m3 Pasir Pasang 225,000.00 270,000.00 7,200.00 8,640.00
1 Kg Semen Warna #REF! #REF! #REF! #REF!
C PERALATAN
D Jumlah A + B + C 91,300.00 105,130.00
E Overhead & Profit (contoh 10%) 10% 9,130.00 10,513.00
F Harga Satuan Pekerjaan (D+E) 100,430.00 115,643.00

15 A.4.5.2.36 1 m' Pemasangan Nok Genteng Metal 54,890.00 62,804.50


A Tenaga 27,250.00 31,595.00
L.01 0.250 OH Pekerja 55,000.00 65,000.00 13,750.00 16,250.00
L.02 0.150 OH Tukang Kayu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.013 OH Mandor 75,000.00 90,000.00 975.00 1,170.00
B Bahan 22,650.00 25,500.00
1.1 Buah Nok Genteng 20,000.00 22,500.00 22,000.00 24,750.00
0.05 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 650.00 750.00

C PERALATAN
D Jumlah A + B + C 49,900.00 57,095.00
E Overhead & Profit (contoh 10%) 10% 4,990.00 5,709.50
F Harga Satuan Pekerjaan (D+E) 54,890.00 62,804.50

16 A.4.5.2.37 1 m' Pemasangan Nok Sirap 44,033.00 49,654.00


A Tenaga 28,200.00 32,290.00
L.01 0.125 OH Pekerja 55,000.00 65,000.00 6,875.00 8,125.00
L.02 0.25 OH Tukang Kayu 75,000.00 85,000.00 18,750.00 21,250.00
L.03 0.025 OH Kepala Tukang 85,000.00 95,000.00 2,125.00 2,375.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
B Bahan 11,830.00 12,850.00
0.4 Lbr Seng Plaat 3" x 6" BJLS 28 26,000.00 28,000.00 10,400.00 11,200.00
0.06 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 780.00 900.00
0.05 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 650.00 750.00

C PERALATAN
D Jumlah A + B + C 40,030.00 45,140.00
E Overhead & Profit (contoh 10%) 10% 4,003.00 4,514.00
F Harga Satuan Pekerjaan (D+E) 44,033.00 49,654.00

17 A.4.5.2.38 1 m2 Pemasangan Atap Seng Gelombang 33,572.00 37,301.00


A Tenaga 12,060.00 14,010.00
L.01 0.12 OH Pekerja 55,000.00 65,000.00 6,600.00 7,800.00
L.02 0.06 OH Tukang Kayu 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 85,000.00 95,000.00 510.00 570.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
B Bahan 18,460.00 19,900.00
0.7 Lbr Seng Gelombang 3" x 6" BJLS 28 26,000.00 28,000.00 18,200.00 19,600.00
0.02 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 260.00 300.00
C PERALATAN
D Jumlah A + B + C 30,520.00 33,910.00
E Overhead & Profit (contoh 10%) 10% 3,052.00 3,391.00
F Harga Satuan Pekerjaan (D+E) 33,572.00 37,301.00
file:///conversion/tmp/scratch/443255086.xls 95/62 abk 8-14
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
18 A.4.5.2.39 1 m' Pemasangan Atap Nok Seng 25,151.50 28,495.50
A Tenaga 14,545.00 16,905.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.07 OH Tukang Kayu 75,000.00 85,000.00 5,250.00 5,950.00
L.03 0.007 OH Kepala Tukang 85,000.00 95,000.00 595.00 665.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
B Bahan 8,320.00 9,000.00
0.3 Lbr Seng Plaat 3" x 6" BJLS 28 26,000.00 28,000.00 7,800.00 8,400.00
0.04 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 520.00 600.00
C PERALATAN
D Jumlah A + B + C 22,865.00 25,905.00
E Overhead & Profit (contoh 10%) 10% 2,286.50 2,590.50
F Harga Satuan Pekerjaan (D+E) 25,151.50 28,495.50

19 A.4.5.2.42 1 m2 Pasang Allumunium Foil / Sisalation 22,990.00 25,954.50


A Tenaga 13,025.00 15,195.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.05 OH Tukang Kayu 75,000.00 85,000.00 3,750.00 4,250.00
L.03 0.005 OH Kepala Tukang 85,000.00 95,000.00 425.00 475.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 7,875.00 8,400.00
1.05 m2 Sisalation / Allumunium Foil 7,500.00 8,000.00 7,875.00 8,400.00
C PERALATAN
D Jumlah A + B + C 20,900.00 23,595.00
E Overhead & Profit (contoh 10%) 10% 2,090.00 2,359.50
F Harga Satuan Pekerjaan (D+E) 22,990.00 25,954.50

file:///conversion/tmp/scratch/443255086.xls 95/63 abk 8-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

IX A.4.5.1 HARGA SATUAN PEKERJAAN LANGIT-LANGIT


1 A.4.5.1.1 1 m2 Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm 28,077.50 30,552.50
A Tenaga 7,795.00 8,925.00
L.01 0.03 OH Pekerja 55,000.00 65,000.00 1,650.00 1,950.00
L.02 0.07 OH Tukang Kayu 75,000.00 85,000.00 5,250.00 5,950.00
L.03 0.007 OH Kepala Tukang 85,000.00 95,000.00 595.00 665.00
L.04 0.004 OH Mandor 75,000.00 90,000.00 300.00 360.00
B Bahan 17,730.00 18,850.00
1.1 Lbr Plat Asbes 16,000.00 17,000.00 17,600.00 18,700.00
0.01 Kg Paku 13,000.00 15,000.00 130.00 150.00
C PERALATAN
D Jumlah A + B + C 25,525.00 27,775.00
E Overhead & Profit (contoh 10%) 10% 2,552.50 2,777.50
F Harga Satuan Pekerjaan (D+E) 28,077.50 30,552.50
Overhead & Profit (contoh 10%)
2 A.4.5.1.2 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x30) cm 92,092.00 99,033.00
A Tenaga 17,070.00 19,680.00
L.01 0.12 OH Pekerja 55,000.00 65,000.00 6,600.00 7,800.00
L.02 0.12 OH Tukang Kayu 75,000.00 85,000.00 9,000.00 10,200.00
L.03 0.012 OH Kepala Tukang 85,000.00 95,000.00 1,020.00 1,140.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
B Bahan 66,650.00 70,350.00
12.0 Lbr Akustik Uk.30 x 30 cm 5,500.00 5,800.00 66,000.00 69,600.00
0.05 Kg Paku 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 83,720.00 90,030.00
E Overhead & Profit (contoh 10%) 10% 8,372.00 9,003.00
F Harga Satuan Pekerjaan (D+E) 92,092.00 99,033.00

3 A.4.5.1.3 1 m2 Pemasangan Langit-langit Akustik Ukuran (30x60) cm 99,302.50 103,081.00


A Tenaga 14,225.00 16,400.00
L.01 0.10 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.10 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 76,050.00 77,310.00
5.80 Lbr Akustik 13,000.00 13,200.00 75,400.00 76,560.00
0.05 Kg Paku 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 90,275.00 93,710.00
E Overhead & Profit (contoh 10%) 10% 9,027.50 9,371.00
F Harga Satuan Pekerjaan (D+E) 99,302.50 103,081.00

4 A.4.5.1.4 1 m2 Pemasangan Langit-langit Akustik Ukuran (60x120) cm 84,012.50 88,165.00


A Tenaga 14,225.00 16,400.00
L.01 0.10 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.10 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 62,150.00 63,750.00
1.50 Lbr Akustik 41,000.00 42,000.00 61,500.00 63,000.00
0.05 Kg Paku 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 76,375.00 80,150.00
E Overhead & Profit (contoh 10%) 10% 7,637.50 8,015.00
F Harga Satuan Pekerjaan (D+E) 84,012.50 88,165.00

5 A.4.5.1.5 1 m2 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 4 mm & 6 mm 41,651.50 47,410.00
A Tenaga 14,225.00 16,400.00
L.01 0.10 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.10 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00

file:///conversion/tmp/scratch/443255086.xls 95/64 abk 9-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00

file:///conversion/tmp/scratch/443255086.xls 95/65 abk 9-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 23,640.00 26,700.00
0.375 Lbr Tripleks (4 mm) 62,000.00 70,000.00 23,250.00 26,250.00
0.03 Kg Paku Tripleks 13,000.00 15,000.00 390.00 450.00
C PERALATAN
D Jumlah A + B + C 37,865.00 43,100.00
E Overhead & Profit (contoh 10%) 10% 3,786.50 4,310.00
F Harga Satuan Pekerjaan (D+E) 41,651.50 47,410.00

6 A.4.5.1.6 1 m2 Memasang Langit-langit Lambriziring Kayu Jati, tebal 6 mm 488,323.00 523,985.00


A Tenaga 113,800.00 131,200.00
L.01 0.8 OH Pekerja 55,000.00 65,000.00 44,000.00 52,000.00
L.02 0.8 OH Tukang Kayu 75,000.00 85,000.00 60,000.00 68,000.00
L.03 0.08 OH Kepala Tukang 85,000.00 95,000.00 6,800.00 7,600.00
L.04 0.04 OH Mandor 75,000.00 90,000.00 3,000.00 3,600.00
B Bahan 330,130.00 345,150.00
0.015 m3 Kayu Jati,Papan 22,000,000.00 23,000,000.00 330,000.00 345,000.00
0.01 Kg Paku 13,000.00 15,000.00 130.00 150.00
C PERALATAN
D Jumlah A + B + C 443,930.00 476,350.00
E Overhead & Profit (contoh 10%) 10% 44,393.00 47,635.00
F Harga Satuan Pekerjaan (D+E) 488,323.00 523,985.00

7 A.4.5.1.7 1 m2 Memasang Langit-langit Gypsu Board, Uk (120x240) tebal 9 mm 37,694.80 41,945.20


A Tenaga 10,050.00 11,675.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.05 OH Tukang Kayu 75,000.00 85,000.00 3,750.00 4,250.00
L.03 0.005 OH Kepala Tukang 85,000.00 95,000.00 425.00 475.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 24,218.00 26,457.00
0.364 Lbr Gypsum Board 62,000.00 68,000.00 22,568.00 24,752.00
0.11 Kg Paku Sekrup 15,000.00 15,500.00 1,650.00 1,705.00
C PERALATAN
D Jumlah A + B + C 34,268.00 38,132.00
E Overhead & Profit (contoh 10%) 10% 3,426.80 3,813.20
F Harga Satuan Pekerjaan (D+E) 37,694.80 41,945.20

8 A.4.5.1.9 1 m2 Memasang Langit-langit Akuatik Uk (60x120) cm & Rangka Allumunium 185,652.50 201,905.00
A Tenaga 71,125.00 82,000.00
L.01 0.5 OH Pekerja 55,000.00 65,000.00 27,500.00 32,500.00
L.02 0.5 OH Tukang Kayu 75,000.00 85,000.00 37,500.00 42,500.00
L.03 0.05 OH Kepala Tukang 85,000.00 95,000.00 4,250.00 4,750.00
L.04 0.025 OH Mandor 75,000.00 90,000.00 1,875.00 2,250.00
B Bahan 97,650.00 101,550.00
3.6 m' Profil Allumunium "T" 3,500.00 4,000.00 12,600.00 14,400.00
0.15 kg Kawat Ø 4 mm 6,500.00 7,000.00 975.00 1,050.00
1.05 bh Ramset 21,500.00 22,000.00 22,575.00 23,100.00
1.5 lmb Akuatik 60 x 120 cm 41,000.00 42,000.00 61,500.00 63,000.00
C PERALATAN
D Jumlah A + B + C 168,775.00 183,550.00
E Overhead & Profit (contoh 10%) 10% 16,877.50 18,355.00
F Harga Satuan Pekerjaan (D+E) 185,652.50 201,905.00

9 A.4.5.1.10 1 m1 List Langit-Langit Kayu Profil 13,552.00 15,009.50


A Tenaga 7,150.00 8,245.00
L.01 0.05 OH Pekerja 55,000.00 65,000.00 2,750.00 3,250.00
L.02 0.05 OH Tukang Kayu 75,000.00 85,000.00 3,750.00 4,250.00
L.03 0.005 OH Kepala Tukang 85,000.00 95,000.00 425.00 475.00
L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 5,170.00 5,400.00
1.05 m1 List Kayu Profil 4,800.00 5,000.00 5,040.00 5,250.00
0.01 Kg Paku 13,000.00 15,000.00 130.00 150.00
C PERALATAN
D Jumlah A + B + C 12,320.00 13,645.00
E Overhead & Profit (contoh 10%) 10% 1,232.00 1,364.50

file:///conversion/tmp/scratch/443255086.xls 95/66 abk 9-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 13,552.00 15,009.50

file:///conversion/tmp/scratch/443255086.xls 95/67 abk 9-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

X A.5.1.1 HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


1 A.5.1.1.1 1 Unit Memasang Closet Duduk / Mono Blok 1,994,393.50 2,103,744.50
A Tenaga 276,085.00 322,495.00
L.01 3.3 OH Pekerja 55,000.00 65,000.00 181,500.00 214,500.00
L.02 1.1 OH Tukang Batu 75,000.00 85,000.00 82,500.00 93,500.00
L.03 0.001 OH Kepala Tukang 85,000.00 95,000.00 85.00 95.00
L.04 0.16 OH Mandor 75,000.00 90,000.00 12,000.00 14,400.00
Buah Bahan 1,537,000.00 1,590,000.00
1 Buah Kloset Duduk / Monoblok 1,450,000.00 1,500,000.00 1,450,000.00 1,500,000.00
0.06 Kelengkapan 6% dari harga Kloset 1,450,000.00 1,500,000.00 87,000.00 90,000.00
C PERALATAN
D Jumlah A + B + C 1,813,085.00 1,912,495.00
E Overhead & Profit (contoh 10%) 10% 181,308.50 191,249.50
F Harga Satuan Pekerjaan (D+E) 1,994,393.50 2,103,744.50
Overhead & Profit (contoh 10%)
2 A.5.1.1.2 1 Unit Memasang Closet Jongkok Porselen 502,425.00 566,390.00
A Tenaga 307,000.00 349,400.00
L.01 1 OH Pekerja 55,000.00 65,000.00 55,000.00 65,000.00
L.02 1.5 OH Tukang Batu 75,000.00 85,000.00 112,500.00 127,500.00
L.03 1.5 OH Kepala Tukang 85,000.00 95,000.00 127,500.00 142,500.00
L.04 0.16 OH Mandor 75,000.00 90,000.00 12,000.00 14,400.00
B Bahan 149,750.00 165,500.00
1 Buah Kloset Jongkok 140,000.00 155,000.00 140,000.00 155,000.00
6 Kg Portland Semen 1,250.00 1,300.00 7,500.00 7,800.00
0.01 m3 Pasir Pasang 225,000.00 270,000.00 2,250.00 2,700.00
C PERALATAN
D Jumlah A + B + C 456,750.00 514,900.00
E Overhead & Profit (contoh 10%) 10% 45,675.00 51,490.00
F Harga Satuan Pekerjaan (D+E) 502,425.00 566,390.00

3 A.5.1.1.4 1 Unit Memasang Urinoir 671,825.00 733,150.00


A Tenaga 146,000.00 168,500.00
L.01 1 OH Pekerja 55,000.00 65,000.00 55,000.00 65,000.00
L.02 1 OH Tukang Batu 75,000.00 85,000.00 75,000.00 85,000.00
L.03 0.1 OH Kepala Tukang 85,000.00 95,000.00 8,500.00 9,500.00
L.04 0.1 OH Mandor 75,000.00 90,000.00 7,500.00 9,000.00
B Bahan 464,750.00 498,000.00
1 Buah Urinoir 350,000.00 375,000.00 350,000.00 375,000.00
0.3 - Perlengkapan 30% Harga Urinoir 350,000.00 375,000.00 105,000.00 112,500.00
6 Kg Portland Semen 1,250.00 1,300.00 7,500.00 7,800.00
0.01 m3 Pasir Pasang 225,000.00 270,000.00 2,250.00 2,700.00
C PERALATAN
D Jumlah A + B + C 610,750.00 666,500.00
E Overhead & Profit (contoh 10%) 10% 61,075.00 66,650.00
F Harga Satuan Pekerjaan (D+E) 671,825.00 733,150.00

4 A.5.1.1.5 1 Unit Memasang Wastafel 510,812.50 779,982.50


A Tenaga 97,125.00 113,575.00
L.01 1.2 OH Pekerja 55,000.00 65,000.00 66,000.00 78,000.00
L.02 0.145 OH Tukang Batu 75,000.00 85,000.00 10,875.00 12,325.00
L.03 0.15 OH Kepala Tukang 85,000.00 95,000.00 12,750.00 14,250.00
L.04 0.1 OH Mandor 75,000.00 90,000.00 7,500.00 9,000.00
B Bahan 367,250.00 595,500.00
1 Buah Wastafel 275,000.00 450,000.00 275,000.00 450,000.00
0.3 - Perlengkapan 30% Harga Wastafel 275,000.00 450,000.00 82,500.00 135,000.00
6 Kg Portland Semen 1,250.00 1,300.00 7,500.00 7,800.00
0.01 m3 Pasir Pasang 225,000.00 270,000.00 2,250.00 2,700.00
C PERALATAN
D Jumlah A + B + C 464,375.00 709,075.00
E Overhead & Profit (contoh 10%) 10% 46,437.50 70,907.50
F Harga Satuan Pekerjaan (D+E) 510,812.50 779,982.50

5 A.5.1.1.6 1 Unit Pemasangan Bathcuip porselen 1,063,672.50 1,139,622.00


A Tenaga 66,975.00 76,020.00
L.01 0.075 OH Pekerja 55,000.00 65,000.00 4,125.00 4,875.00
L.02 0.75 OH Tukang Batu 75,000.00 85,000.00 56,250.00 63,750.00
L.03 0.075 OH Kepala Tukang 85,000.00 95,000.00 6,375.00 7,125.00
L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00

file:///conversion/tmp/scratch/443255086.xls 95/68 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 900,000.00 960,000.00
1 Buah Batchuip 750,000.00 800,000.00 750,000.00 800,000.00
0.2 - Perlengkapan 20% Harga Bathcuip 750,000.00 800,000.00 150,000.00 160,000.00
C PERALATAN
D Jumlah A + B + C 966,975.00 1,036,020.00
E Overhead & Profit (contoh 10%) 10% 96,697.50 103,602.00
F Harga Satuan Pekerjaan (D+E) 1,063,672.50 1,139,622.00

6 A.5.1.1.7 1 Unit Pemasangan Bak Fibreglass vol.1 m3 970,475.00 1,099,175.00


A Tenaga 574,250.00 663,250.00

L.01 3 OH Pekerja 55,000.00 65,000.00 165,000.00 195,000.00


L.02 4.5 OH Tukang Batu 75,000.00 85,000.00 337,500.00 382,500.00
L.03 0.05 OH Kepala Tukang 85,000.00 95,000.00 4,250.00 4,750.00
L.04 0.9 OH Mandor 75,000.00 90,000.00 67,500.00 81,000.00
B Tukang Batu 308,000.00 336,000.00
1 Buah Bak Fibreglass 275,000.00 300,000.00 275,000.00 300,000.00
0.12 - Perlengkapan 12% Bak Fibreglass 275,000.00 300,000.00 33,000.00 36,000.00
C PERALATAN
D Jumlah A + B + C 882,250.00 999,250.00
E Overhead & Profit (contoh 10%) 10% 88,225.00 99,925.00
F Harga Satuan Pekerjaan (D+E) 970,475.00 1,099,175.00

7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,256,354.27 1,413,478.54
A Tenaga 582,750.00 676,200.00
L.01 6.00 OH Pekerja 55,000.00 65,000.00 330,000.00 390,000.00
L.02 3.00 OH Tukang Batu 75,000.00 85,000.00 225,000.00 255,000.00
L.03 0.30 OH Kepala Tukang 85,000.00 95,000.00 25,500.00 28,500.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 559,390.24 608,780.49
150.0 bh Batu Bata 450.00 500.00 67,500.00 75,000.00
120 Kg Portland Semen 0.11 1,250.00 1,300.00 150,000.00 156,000.00
0.3 m3 Pasir Pasang 0.0121 225,000.00 270,000.00 67,500.00 81,000.00
360 buah Porselen 11 x 11 cm 82.6446280992 512.20 524.39 184,390.24 188,780.49
6 Kg Semen Nat 15,000.00 18,000.00 90,000.00 108,000.00
C PERALATAN
D Jumlah A + B + C 1,142,140.24 1,284,980.49
E Overhead & Profit (contoh 10%) 10% 114,214.02 128,498.05
F Harga Satuan Pekerjaan (D+E) 1,256,354.27 1,413,478.54

8 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 333,107.50 375,815.00
A Tenaga 27,825.00 31,650.00
L.01 0.030 OH Pekerja 55,000.00 65,000.00 1,650.00 1,950.00
L.02 0.300 OH Tukang Batu 75,000.00 85,000.00 22,500.00 25,500.00
L.03 0.030 OH Kepala Tukang 85,000.00 95,000.00 2,550.00 2,850.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 302,825.00 341,650.00
E Overhead & Profit (contoh 10%) 10% 30,282.50 34,165.00
F Harga Satuan Pekerjaan (D+E) 333,107.50 375,815.00

9 A.5.1.1.14 1 buah Pemasangan Floor Drain 26,702.50 33,605.00


A Tenaga 9,275.00 10,550.00
L.01 0.010 OH Pekerja 55,000.00 65,000.00 550.00 650.00
L.02 0.100 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.010 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 15,000.00 20,000.00
1 bh Floor Drain 15,000.00 20,000.00 15,000.00 20,000.00

C PERALATAN
D Jumlah A + B + C 24,275.00 30,550.00
E Overhead & Profit (contoh 10%) 10% 2,427.50 3,055.00
F Harga Satuan Pekerjaan (D+E) 26,702.50 33,605.00

file:///conversion/tmp/scratch/443255086.xls 95/69 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
10 A.5.1.1.15 1 bh Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi 35 cm 342,809.50 388,443.00
A Tenaga 179,745.00 209,430.00
L.01 2.160 OH Pekerja 55,000.00 65,000.00 118,800.00 140,400.00
L.02 0.720 OH Tukang Batu 75,000.00 85,000.00 54,000.00 61,200.00
L.03 0.072 OH Kepala Tukang 85,000.00 95,000.00 6,120.00 6,840.00
L.04 0.011 OH Mandor 75,000.00 90,000.00 825.00 990.00
B Bahan 131,900.00 143,700.00
40.00 bh Batu Bata 450.00 500.00 18,000.00 20,000.00
44.00 kg Semen Portland 1,250.00 1,300.00 55,000.00 57,200.00
0.07 m3 Pasir Pasang 225,000.00 270,000.00 15,750.00 18,900.00
0.06 m3 Pasir Beton 320,000.00 350,000.00 19,200.00 21,000.00
0.07 m3 Kerikil 125,000.00 140,000.00 8,750.00 9,800.00
1.60 kg Baja Tulangan 9,500.00 10,500.00 15,200.00 16,800.00
C PERALATAN
D Jumlah A + B + C 311,645.00 353,130.00
E Overhead & Profit (contoh 10%) 10% 31,164.50 35,313.00
F Harga Satuan Pekerjaan (D+E) 342,809.50 388,443.00

11 A.5.1.1.16 1 bh Pemasangan Bak Kontrol Pas.Batu Bata 45 x 45 tinggi 50 cm 514,673.50 582,488.50


A Tenaga 264,385.00 308,235.00
L.01 3.200 OH Pekerja 55,000.00 65,000.00 176,000.00 208,000.00
L.02 1.150 OH Tukang Batu 75,000.00 85,000.00 86,250.00 97,750.00
L.03 0.011 OH Kepala Tukang 85,000.00 95,000.00 935.00 1,045.00
L.04 0.016 OH Mandor 75,000.00 90,000.00 1,200.00 1,440.00
B Bahan 203,500.00 221,300.00
70.00 bh Batu Bata 450.00 500.00 31,500.00 35,000.00
77.00 kg Semen Portland 1,250.00 1,300.00 96,250.00 100,100.00
0.13 m3 Pasir Pasang 225,000.00 270,000.00 29,250.00 35,100.00
0.09 m3 Pasir Beton 320,000.00 350,000.00 28,800.00 31,500.00
0.02 m3 Kerikil 125,000.00 140,000.00 2,500.00 2,800.00
1.60 kg Baja Tulangan 9,500.00 10,500.00 15,200.00 16,800.00
C PERALATAN
D Jumlah A + B + C 467,885.00 529,535.00
E Overhead & Profit (contoh 10%) 10% 46,788.50 52,953.50
F Harga Satuan Pekerjaan (D+E) 514,673.50 582,488.50

12 A.5.1.1.17 1 bh Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm 621,181.00 698,874.00
A Tenaga 264,385.00 308,235.00
L.01 3.200 OH Pekerja 55,000.00 65,000.00 176,000.00 208,000.00
L.02 1.150 OH Tukang Batu 75,000.00 85,000.00 86,250.00 97,750.00
L.03 0.011 OH Kepala Tukang 85,000.00 95,000.00 935.00 1,045.00
L.04 0.016 OH Mandor 75,000.00 90,000.00 1,200.00 1,440.00
B Bahan 300,325.00 327,105.00
123.00 bh Batu Bata 450.00 500.00 55,350.00 61,500.00
114.00 kg Semen Portland 1,250.00 1,300.00 142,500.00 148,200.00
0.18 m3 Pasir Pasang 225,000.00 270,000.00 41,400.00 49,680.00
0.12 m3 Pasir Beton 125,000.00 140,000.00 15,000.00 16,800.00
4.85 kg Baja Tulangan 9,500.00 10,500.00 46,075.00 50,925.00
C PERALATAN
D Jumlah A + B + C 564,710.00 635,340.00
E Overhead & Profit (contoh 10%) 10% 56,471.00 63,534.00
F Harga Satuan Pekerjaan (D+E) 621,181.00 698,874.00

13 A.5.1.1.18 1 m' Pemasangan Pipa Galvanis Ø ½" 32,231.83 47,147.83


A Tenaga 12,510.00 14,445.00
L.01 0.054 OH Pekerja 55,000.00 65,000.00 2,970.00 3,510.00
L.02 0.090 OH Tukang Batu 75,000.00 85,000.00 6,750.00 7,650.00
L.03 0.009 OH Kepala Tukang 85,000.00 95,000.00 765.00 855.00
L.04 0.027 OH Mandor 75,000.00 90,000.00 2,025.00 2,430.00
B Bahan 16,791.67 28,416.67
1.20 m' Pipa Galvanis Ø ½" 10,833.33 18,333.33 13,000.00 22,000.00
0.35 Ls Perlengkapan 35% x pipa 10,833.33 18,333.33 3,791.67 6,416.67
C PERALATAN
D Jumlah A + B + C 29,301.67 42,861.67
E Overhead & Profit (contoh 10%) 10% 2,930.17 4,286.17
F Harga Satuan Pekerjaan (D+E) 32,231.83 47,147.83

file:///conversion/tmp/scratch/443255086.xls 95/70 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
14 A.5.1.1.19 1 bh Pemasangan Kran Ø ½" atau Ø ¾" 54,268.23 81,301.28
A Tenaga 34,325.00 38,900.00
L.01 0.010 OH Pekerja 55,000.00 65,000.00 550.00 650.00
L.02 0.400 OH Tukang Batu 75,000.00 85,000.00 30,000.00 34,000.00
L.03 0.040 OH Kepala Tukang 85,000.00 95,000.00 3,400.00 3,800.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 15,009.75 35,010.25
1.00 bh Kran Air 15,000.00 35,000.00 15,000.00 35,000.00
0.0025 bh Sealtape 3,900.00 4,100.00 9.75 10.25
C PERALATAN
D Jumlah A + B + C 49,334.75 73,910.25
E Overhead & Profit (contoh 10%) 10% 4,933.48 7,391.03
F Harga Satuan Pekerjaan (D+E) 54,268.23 81,301.28

15 A.5.1.1.20 1 m' Pemasangan Pipa Galvanis Ø ¾" 35,073.50 58,514.50


A Tenaga 12,510.00 14,445.00
L.01 0.054 OH Pekerja 55,000.00 65,000.00 2,970.00 3,510.00
L.02 0.090 OH Tukang Batu 75,000.00 85,000.00 6,750.00 7,650.00
L.03 0.009 OH Kepala Tukang 85,000.00 95,000.00 765.00 855.00
L.04 0.027 OH Mandor 75,000.00 90,000.00 2,025.00 2,430.00
B Bahan 19,375.00 38,750.00
1.20 m' Pipa Galvanis Ø ¾" 12,500.00 25,000.00 15,000.00 30,000.00
0.35 Ls Perlengkapan 35% x pipa 12,500.00 25,000.00 4,375.00 8,750.00
C PERALATAN
D Jumlah A + B + C 31,885.00 53,195.00
E Overhead & Profit (contoh 10%) 10% 3,188.50 5,319.50
F Harga Satuan Pekerjaan (D+E) 35,073.50 58,514.50

16 A.5.1.1.21 1 m' Pemasangan Pipa Galvanis Ø 1" 40,756.83 69,881.17


A Tenaga 12,510.00 14,445.00
L.01 0.054 OH Pekerja 55,000.00 65,000.00 2,970.00 3,510.00
L.02 0.090 OH Tukang Batu 75,000.00 85,000.00 6,750.00 7,650.00
L.03 0.009 OH Kepala Tukang 85,000.00 95,000.00 765.00 855.00
L.04 0.027 OH Mandor 75,000.00 90,000.00 2,025.00 2,430.00
B Bahan 24,541.67 49,083.33
1.20 m' Pipa Galvanis Ø 1" 15,833.33 31,666.67 19,000.00 38,000.00
0.35 Ls Perlengkapan 35% x pipa 15,833.33 31,666.67 5,541.67 11,083.33
C PERALATAN
D Jumlah A + B + C 37,051.67 63,528.33
E Overhead & Profit (contoh 10%) 10% 3,705.17 6,352.83
F Harga Satuan Pekerjaan (D+E) 40,756.83 69,881.17

17 A.5.1.1.22 1 m' Pemasangan Pipa Galvanis Ø 1½ " 60,421.17 100,811.33


A Tenaga 21,345.00 24,480.00
L.01 0.108 OH Pekerja 55,000.00 65,000.00 5,940.00 7,020.00
L.02 0.180 OH Tukang Batu 75,000.00 85,000.00 13,500.00 15,300.00
L.03 0.018 OH Kepala Tukang 85,000.00 95,000.00 1,530.00 1,710.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 33,583.33 67,166.67
1.20 m' Pipa Galvanis Ø 1½" 21,666.67 43,333.33 26,000.00 52,000.00
0.35 Ls Perlengkapan 35% x pipa 21,666.67 43,333.33 7,583.33 15,166.67
C PERALATAN
D Jumlah A + B + C 54,928.33 91,646.67
E Overhead & Profit (contoh 10%) 10% 5,492.83 9,164.67
F Harga Satuan Pekerjaan (D+E) 60,421.17 100,811.33

18 A.5.1.1.23 1 m' Pemasangan Pipa Galvanis Ø 3" 160,174.67 173,028.17


A Tenaga 26,780.00 30,715.00
L.01 0.135 OH Pekerja 55,000.00 65,000.00 7,425.00 8,775.00
L.02 0.225 OH Tukang Batu 75,000.00 85,000.00 16,875.00 19,125.00
L.03 0.023 OH Kepala Tukang 85,000.00 95,000.00 1,955.00 2,185.00
L.04 0.007 OH Mandor 75,000.00 90,000.00 525.00 630.00
B Bahan 118,833.33 126,583.33
1.20 m' Pipa Galvanis Ø 3" 76,666.67 81,666.67 92,000.00 98,000.00
0.35 Ls Perlengkapan 35% x pipa 76,666.67 81,666.67 26,833.33 28,583.33
C PERALATAN
D Jumlah A + B + C 145,613.33 157,298.33
E Overhead & Profit (contoh 10%) 10% 14,561.33 15,729.83

file:///conversion/tmp/scratch/443255086.xls 95/71 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 160,174.67 173,028.17

file:///conversion/tmp/scratch/443255086.xls 95/72 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
19 A.5.1.1.24 1 m' Pemasangan Pipa Galvanis Ø 4" 268,158.00 281,011.50
A Tenaga 26,780.00 30,715.00
L.01 0.135 OH Pekerja 55,000.00 65,000.00 7,425.00 8,775.00
L.02 0.225 OH Tukang Batu 75,000.00 85,000.00 16,875.00 19,125.00
L.03 0.023 OH Kepala Tukang 85,000.00 95,000.00 1,955.00 2,185.00
L.04 0.007 OH Mandor 75,000.00 90,000.00 525.00 630.00
B Bahan 217,000.00 224,750.00
1.20 m' Pipa Galvanis Ø 4" 140,000.00 145,000.00 168,000.00 174,000.00
0.35 Ls Perlengkapan 35% x pipa 140,000.00 145,000.00 49,000.00 50,750.00
C PERALATAN
D Jumlah A + B + C 243,780.00 255,465.00
E Overhead & Profit (contoh 10%) 10% 24,378.00 25,546.50
F Harga Satuan Pekerjaan (D+E) 268,158.00 281,011.50

20 A.5.1.1.25 1 m' Pemasangan Pipa PVC tipe AW Ø ½" 18,936.50 23,927.75


A Tenaga 7,140.00 8,190.00
L.01 0.036 OH Pekerja 55,000.00 65,000.00 1,980.00 2,340.00
L.02 0.060 OH Tukang Batu 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 85,000.00 95,000.00 510.00 570.00
L.04 0.002 OH Mandor 75,000.00 90,000.00 150.00 180.00
B Bahan 10,075.00 13,562.50
1.20 m' Pipa PVC Ø ½" 6,500.00 8,750.00 7,800.00 10,500.00
0.35 Ls Perlengkapan 35% x pipa 6,500.00 8,750.00 2,275.00 3,062.50
C PERALATAN
D Jumlah A + B + C 17,215.00 21,752.50
E Overhead & Profit (contoh 10%) 10% 1,721.50 2,175.25
F Harga Satuan Pekerjaan (D+E) 18,936.50 23,927.75

21 A.5.1.1.26 1 m' Pemasangan Pipa PVC tipe AW Ø ¾" 21,494.00 26,059.00


A Tenaga 7,140.00 8,190.00
L.01 0.036 OH Pekerja 55,000.00 65,000.00 1,980.00 2,340.00
L.02 0.060 OH Tukang Batu 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 85,000.00 95,000.00 510.00 570.00
L.04 0.002 OH Mandor 75,000.00 90,000.00 150.00 180.00
B Bahan 12,400.00 15,500.00
1.20 m' Pipa PVC Ø ¾" 8,000.00 10,000.00 9,600.00 12,000.00
0.35 Ls Perlengkapan 35% x pipa 8,000.00 10,000.00 2,800.00 3,500.00
C PERALATAN
D Jumlah A + B + C 19,540.00 23,690.00
E Overhead & Profit (contoh 10%) 10% 1,954.00 2,369.00
F Harga Satuan Pekerjaan (D+E) 21,494.00 26,059.00

22 A.5.1.1.27 1 m' Pemasangan Pipa PVC tipe AW Ø 1" 26,609.00 30,321.50


A Tenaga 7,140.00 8,190.00
L.01 0.036 OH Pekerja 55,000.00 65,000.00 1,980.00 2,340.00
L.02 0.060 OH Tukang Batu 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 85,000.00 95,000.00 510.00 570.00
L.04 0.002 OH Mandor 75,000.00 90,000.00 150.00 180.00
B Bahan 17,050.00 19,375.00
1.20 m' Pipa PVC Ø 1" 11,000.00 12,500.00 13,200.00 15,000.00
0.35 Ls Perlengkapan 35% x pipa 11,000.00 12,500.00 3,850.00 4,375.00
C PERALATAN
D Jumlah A + B + C 24,190.00 27,565.00
E Overhead & Profit (contoh 10%) 10% 2,419.00 2,756.50
F Harga Satuan Pekerjaan (D+E) 26,609.00 30,321.50

23 A.5.1.1.28 1 m' Pemasangan Pipa PVC tipe AW Ø 1½" 28,831.00 33,121.00


A Tenaga 10,710.00 12,285.00
L.01 0.054 OH Pekerja 55,000.00 65,000.00 2,970.00 3,510.00
L.02 0.090 OH Tukang Batu 75,000.00 85,000.00 6,750.00 7,650.00
L.03 0.009 OH Kepala Tukang 85,000.00 95,000.00 765.00 855.00
L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 15,500.00 17,825.00
1.20 m' Pipa PVC Ø 1½" 10,000.00 11,500.00 12,000.00 13,800.00
0.35 Ls Perlengkapan 35% x pipa 10,000.00 11,500.00 3,500.00 4,025.00
C PERALATAN
D Jumlah A + B + C 26,210.00 30,110.00
E Overhead & Profit (contoh 10%) 10% 2,621.00 3,011.00

file:///conversion/tmp/scratch/443255086.xls 95/73 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
F Harga Satuan Pekerjaan (D+E) 28,831.00 33,121.00

file:///conversion/tmp/scratch/443255086.xls 95/74 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
24 A.5.1.1.29 1 m' Pemasangan Pipa PVC tipe AW Ø 2" 38,776.83 45,340.17
A Tenaga 10,710.00 12,285.00
L.01 0.054 OH Pekerja 55,000.00 65,000.00 2,970.00 3,510.00
L.02 0.090 OH Tukang Batu 75,000.00 85,000.00 6,750.00 7,650.00
L.03 0.009 OH Kepala Tukang 85,000.00 95,000.00 765.00 855.00
L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 24,541.67 28,933.33
1.20 m' Pipa PVC Ø 2" 15,833.33 18,666.67 19,000.00 22,400.00
0.35 Ls Perlengkapan 35% x pipa 15,833.33 18,666.67 5,541.67 6,533.33
C PERALATAN
D Jumlah A + B + C 35,251.67 41,218.33
E Overhead & Profit (contoh 10%) 10% 3,525.17 4,121.83
F Harga Satuan Pekerjaan (D+E) 38,776.83 45,340.17

25 A.5.1.1.31 1 m' Pemasangan Pipa PVC tipe AW Ø 3" 77,305.25 94,104.08


A Tenaga 16,027.50 18,382.50
L.01 0.081 OH Pekerja 55,000.00 65,000.00 4,455.00 5,265.00
L.02 0.135 OH Tukang Batu 75,000.00 85,000.00 10,125.00 11,475.00
L.03 0.0135 OH Kepala Tukang 85,000.00 95,000.00 1,147.50 1,282.50
L.04 0.004 OH Mandor 75,000.00 90,000.00 300.00 360.00
B Bahan 54,250.00 67,166.67
1.20 m' Pipa PVC Ø 3" 35,000.00 43,333.33 42,000.00 52,000.00
0.35 Ls Perlengkapan 35% x pipa 35,000.00 43,333.33 12,250.00 15,166.67
C PERALATAN
D Jumlah A + B + C 70,277.50 85,549.17
E Overhead & Profit (contoh 10%) 10% 7,027.75 8,554.92
F Harga Satuan Pekerjaan (D+E) 77,305.25 94,104.08

26 A.5.1.1.32 1 m' Pemasangan Pipa PVC tipe AW Ø 4" 93,104.00 101,363.17


A Tenaga 7,140.00 8,190.00
L.01 0.036 OH Pekerja 55,000.00 65,000.00 1,980.00 2,340.00
L.02 0.060 OH Tukang Batu 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 85,000.00 95,000.00 510.00 570.00
L.04 0.002 OH Mandor 75,000.00 90,000.00 150.00 180.00
B Bahan 77,500.00 83,958.33
1.20 m' Pipa PVC Ø 4" 50,000.00 54,166.67 60,000.00 65,000.00
0.35 Ls Perlengkapan 35% x pipa 50,000.00 54,166.67 17,500.00 18,958.33
C PERALATAN
D Jumlah A + B + C 84,640.00 92,148.33
E Overhead & Profit (contoh 10%) 10% 8,464.00 9,214.83
F Harga Satuan Pekerjaan (D+E) 93,104.00 101,363.17

27 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm 79,882.00 87,912.00
A Tenaga 8,040.00 9,340.00
L.01 0.080 OH Pekerja 55,000.00 65,000.00 4,400.00 5,200.00
L.02 0.040 OH Tukang Batu 75,000.00 85,000.00 3,000.00 3,400.00
L.03 0.004 OH Kepala Tukang 85,000.00 95,000.00 340.00 380.00
L.04 0.004 OH Mandor 75,000.00 90,000.00 300.00 360.00
B Bahan 64,580.00 70,580.00
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,250.00 1,300.00 43,750.00 45,500.00
0.014 m3 Pasir Pasang 225,000.00 270,000.00 3,150.00 3,780.00
0.014 m3 Pasir Urug 120,000.00 150,000.00 1,680.00 2,100.00
- -
C PERALATAN
D Jumlah A + B + C 72,620.00 79,920.00
E Overhead & Profit (contoh 10%) 10% 7,262.00 7,992.00
F Harga Satuan Pekerjaan (D+E) 79,882.00 87,912.00

28 A.5.1.1.34 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm 34,732.50 39,825.50
A Tenaga 6,030.00 7,005.00
L.01 0.060 OH Pekerja 55,000.00 65,000.00 3,300.00 3,900.00
L.02 0.030 OH Tukang Batu 75,000.00 85,000.00 2,250.00 2,550.00
L.03 0.003 OH Kepala Tukang 85,000.00 95,000.00 255.00 285.00
L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00

file:///conversion/tmp/scratch/443255086.xls 95/75 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 25,545.00 29,200.00
1.60 bh pipa tanah 8,000.00 9,500.00 12,800.00 15,200.00
6.80 kg Semen Portlan 1,250.00 1,300.00 8,500.00 8,840.00
0.013 m3 Pasir Pasang 225,000.00 270,000.00 2,925.00 3,510.00
0.011 m3 Pasir Urug 120,000.00 150,000.00 1,320.00 1,650.00
,
C PERALATAN
D Jumlah A + B + C 31,575.00 36,205.00
E Overhead & Profit (contoh 10%) 10% 3,157.50 3,620.50
F Harga Satuan Pekerjaan (D+E) 34,732.50 39,825.50

29 A.5.1.1.35 1 m' Pemasangan Pipa Beton Ø 20 cm 91,478.75 109,764.60


A Tenaga 14,070.00 16,345.00
L.01 0.140 OH Pekerja 55,000.00 65,000.00 7,700.00 9,100.00
L.02 0.070 OH Tukang Batu 75,000.00 85,000.00 5,250.00 5,950.00
L.03 0.007 OH Kepala Tukang 85,000.00 95,000.00 595.00 665.00
L.04 0.007 OH Mandor 75,000.00 90,000.00 525.00 630.00
B Bahan 69,092.50 83,441.00
1.10 bh pipa beton 36,000.00 45,000.00 39,600.00 49,500.00
0.03 m3 Batu Bata 337,500.00 375,000.00 9,112.50 10,125.00
3.920 kg Semen Portlan 1,250.00 1,300.00 4,900.00 5,096.00
0.056 m3 Pasir Pasang 225,000.00 270,000.00 12,600.00 15,120.00
0.024 m3 Pasir Urug 120,000.00 150,000.00 2,880.00 3,600.00
C PERALATAN
D Jumlah A + B + C 83,162.50 99,786.00
E Overhead & Profit (contoh 10%) 10% 8,316.25 9,978.60
F Harga Satuan Pekerjaan (D+E) 91,478.75 109,764.60

30 A.5.1.1.36 1 m' Pemasangan Pipa Beton Ø 100 cm 493,256.50 538,422.50


A Tenaga 38,190.00 44,365.00
L.01 0.380 OH Pekerja 55,000.00 65,000.00 20,900.00 24,700.00
L.02 0.190 OH Tukang Batu 75,000.00 85,000.00 14,250.00 16,150.00
L.03 0.019 OH Kepala Tukang 85,000.00 95,000.00 1,615.00 1,805.00
L.04 0.019 OH Mandor 75,000.00 90,000.00 1,425.00 1,710.00
B Bahan 410,225.00 445,110.00
1.10 bh pipa beton 180,000.00 190,000.00 198,000.00 209,000.00
0.55 m3 Batu Bata 337,500.00 375,000.00 185,625.00 206,250.00
10.300 kg Semen Portlan 1,250.00 1,300.00 12,875.00 13,390.00
0.061 m3 Pasir Pasang 225,000.00 270,000.00 13,725.00 16,470.00
0.069 m3 Pasir Urug 120,000.00 150,000.00 8,280.00 10,350.00
C PERALATAN
D Jumlah A + B + C 448,415.00 489,475.00
E Overhead & Profit (contoh 10%) 10% 44,841.50 48,947.50
F Harga Satuan Pekerjaan (D+E) 493,256.50 538,422.50

file:///conversion/tmp/scratch/443255086.xls 95/76 abk 10-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XI A.4.2.1 HARGA SATUAN PEKERJAAN BESI & ALLUMUNIUM


1 A.4.2.1.1 1 Kg Pemasangan Besi Profil 26,900.50 30,008.00
A Tenaga 8,535.00 9,840.00
L.01 0.06 OH Pekerja 55,000.00 65,000.00 3,300.00 3,900.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 85,000.00 95,000.00 510.00 570.00
L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 15,920.00 17,440.00
1.15 Kg Besi Profil 12,800.00 13,600.00 14,720.00 15,640.00
0.06 Kg Meni Besi 20,000.00 30,000.00 1,200.00 1,800.00
C PERALATAN
D Jumlah A + B + C 24,455.00 27,280.00
E Overhead & Profit (contoh 10%) 10% 2,445.50 2,728.00
F Harga Satuan Pekerjaan (D+E) 26,900.50 30,008.00
Overhead & Profit (contoh 10%)
2 A.4.2.1.2 1 kg Pemasangan Rangka Kuda-kuda Baja IWF 25,580.50 28,028.00
A Tenaga 8,535.00 9,840.00
L.01 0.06 OH Pekerja 55,000.00 65,000.00 3,300.00 3,900.00
L.02 0.06 OH Tukang Besi 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.006 OH Kepala Tukang 85,000.00 95,000.00 510.00 570.00
L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 14,720.00 15,640.00
1.15 kg Besi Baja IWF 12,800.00 13,600.00 14,720.00 15,640.00
C PERALATAN
D Jumlah A + B + C 23,255.00 25,480.00
E Overhead & Profit (contoh 10%) 10% 2,325.50 2,548.00
F Harga Satuan Pekerjaan (D+E) 25,580.50 28,028.00

3 A.4.2.1.3 100 kg Pengerjaan Pekerjaan Perakitan (Kuda-kuda Baja) 75,306.00 87,279.50


A Tenaga 13,460.00 15,545.00
L.01 0.100 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.100 OH Tukang Besi 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.001 OH Kepala Tukang 85,000.00 95,000.00 85.00 95.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 15,000.00 15,800.00
1 ltr Solar 11,250.00 11,300.00 11,250.00 11,300.00
0.1 ltr Minyak Pelumas 37,500.00 45,000.00 3,750.00 4,500.00
C PERALATAN 40,000 48,000
0.800 jam Sewa Alat 50,000 60,000 40,000 48,000
D Jumlah A + B + C 68,460.00 79,345.00
E Overhead & Profit (contoh 10%) 10% 6,846.00 7,934.50
F Harga Satuan Pekerjaan (D+E) 75,306.00 87,279.50

4 A.4.2.1.4 1 m2 Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku 829,317.50 903,875.50
A Tenaga 149,325.00 172,155.00
L.01 1.05 OH Pekerja 55,000.00 65,000.00 57,750.00 68,250.00
L.02 1.05 OH Tukang Besi 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.105 OH Kepala Tukang 85,000.00 95,000.00 8,925.00 9,975.00
L.04 0.052 OH Mandor 75,000.00 90,000.00 3,900.00 4,680.00
B Bahan 604,600.00 649,550.00
15 Kg Besi Siku L.30.30.3 12,800.00 13,600.00 192,000.00 204,000.00
32.8 Kg Besi Plat Baja 12,500.00 13,500.00 410,000.00 442,800.00
0.05 Kg Kawat Las 52,000.00 55,000.00 2,600.00 2,750.00
C PERALATAN
D Jumlah A + B + C 753,925.00 821,705.00
E Overhead & Profit (contoh 10%) 10% 75,392.50 82,170.50
F Harga Satuan Pekerjaan (D+E) 829,317.50 903,875.50

file:///conversion/tmp/scratch/443255086.xls 95/77 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.2.1.5 10 cm Pengerjaan Pengelasan dengan Las Listrik 16,596.25 19,347.90
A Tenaga 4,020.00 4,670.00
L.01 0.04 OH Pekerja 55,000.00 65,000.00 2,200.00 2,600.00
L.02 0.02 OH Tukang Besi 75,000.00 85,000.00 1,500.00 1,700.00
L.03 0.002 OH Kepala Tukang 85,000.00 95,000.00 170.00 190.00
L.04 0.002 OH Mandor 75,000.00 90,000.00 150.00 180.00
B Bahan 2,567.50 2,719.00
0.04 kg Kawat Las 52,000.00 55,000.00 2,080.00 2,200.00
0.03 ltr Solar 11,250.00 11,300.00 337.50 339.00
0.004 ltr Minyak Pelumas 37,500.00 45,000.00 150.00 180.00
C PERALATAN 8,500 10,200
0.170 jam Sewa Alat 50,000 60,000 8,500 10,200
D Jumlah A + B + C 15,087.50 17,589.00
E Overhead & Profit (contoh 10%) 10% 1,508.75 1,758.90
F Harga Satuan Pekerjaan (D+E) 16,596.25 19,347.90

6 A.4.2.1.7 1 m2 Pemasangan Pintu Rolling Door Besi 513,315.00 568,634.00


A Tenaga 166,650.00 191,940.00
L.01 1.2 OH Pekerja 55,000.00 65,000.00 66,000.00 78,000.00
L.02 1.2 OH Tukang Besi 75,000.00 85,000.00 90,000.00 102,000.00
L.03 0.12 OH Kepala Tukang 85,000.00 95,000.00 10,200.00 11,400.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
B Bahan 300,000.00 325,000.00
1 m2 Pintu Gulung Besi 300,000.00 325,000.00 300,000.00 325,000.00
C PERALATAN
D Jumlah A + B + C 466,650.00 516,940.00
E Overhead & Profit (contoh 10%) 10% 46,665.00 51,694.00
F Harga Satuan Pekerjaan (D+E) 513,315.00 568,634.00

7 A.4.2.1.8 1 m2 Pemasangan Pintu Lipat (Folding Door) 486,849.00 546,876.00


A Tenaga 62,590.00 72,160.00
L.01 0.44 OH Pekerja 55,000.00 65,000.00 24,200.00 28,600.00
L.02 0.44 OH Tukang Besi 75,000.00 85,000.00 33,000.00 37,400.00
L.03 0.044 OH Kepala Tukang 85,000.00 95,000.00 3,740.00 4,180.00
L.04 0.022 OH Mandor 75,000.00 90,000.00 1,650.00 1,980.00
B Bahan 380,000.00 425,000.00
1 m2 Pintu Lipat 380,000.00 425,000.00 380,000.00 425,000.00
C PERALATAN
D Jumlah A + B + C 442,590.00 497,160.00
E Overhead & Profit (contoh 10%) 10% 44,259.00 49,716.00
F Harga Satuan Pekerjaan (D+E) 486,849.00 546,876.00

8 A.4.2.1.9 1 m2 Pemasangan Sunscreen Allumunium 419,650.00 474,276.00


A Tenaga 71,500.00 81,160.00
L.01 0.08 OH Pekerja 55,000.00 65,000.00 4,400.00 5,200.00
L.02 0.8 OH Tukang Besi 75,000.00 85,000.00 60,000.00 68,000.00
L.03 0.08 OH Kepala Tukang 85,000.00 95,000.00 6,800.00 7,600.00
L.04 0.004 OH Mandor 75,000.00 90,000.00 300.00 360.00
B Bahan 310,000.00 350,000.00
1 m2 Sunscreen Allumunium 310,000.00 350,000.00 310,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 381,500.00 431,160.00
E Overhead & Profit (contoh 10%) 10% 38,150.00 43,116.00
F Harga Satuan Pekerjaan (D+E) 419,650.00 474,276.00

9 A.4.2.1.10 1 m2 Pemasangan Rolling Door Allumunium 409,475.00 482,900.00


A Tenaga 142,250.00 164,000.00
L.01 1 OH Pekerja 55,000.00 65,000.00 55,000.00 65,000.00
L.02 1 OH Tukang Besi 75,000.00 85,000.00 75,000.00 85,000.00
L.03 0.1 OH Kepala Tukang 85,000.00 95,000.00 8,500.00 9,500.00
L.04 0.05 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00

file:///conversion/tmp/scratch/443255086.xls 95/78 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 230,000.00 275,000.00
1 m2 Rolling Allumunium 230,000.00 275,000.00 230,000.00 275,000.00
C PERALATAN
D Jumlah A + B + C 372,250.00 439,000.00
E Overhead & Profit (contoh 10%) 10% 37,225.00 43,900.00
F Harga Satuan Pekerjaan (D+E) 409,475.00 482,900.00

10 A.4.2.1.11 1 m' Pemasangan Kusen Pintu Allumunium 108,474.30 116,322.25


A Tenaga 6,113.00 7,047.50
L.01 0.043 OH Pekerja 55,000.00 65,000.00 2,365.00 2,795.00
L.02 0.043 OH Tukang Besi 75,000.00 85,000.00 3,225.00 3,655.00
L.03 0.0043 OH Kepala Tukang 85,000.00 95,000.00 365.50 408.50
L.04 0.0021 OH Mandor 75,000.00 90,000.00 157.50 189.00
B Bahan 92,500.00 98,700.00
1.1 m' Profil Allumunium 80,000.00 85,000.00 88,000.00 93,500.00
2 buah Skrup Fixer 750.00 800.00 1,500.00 1,600.00
0.06 Tube Sealant 50,000.00 60,000.00 3,000.00 3,600.00
C PERALATAN
D Jumlah A + B + C 98,613.00 105,747.50
E Overhead & Profit (contoh 10%) 10% 9,861.30 10,574.75
F Harga Satuan Pekerjaan (D+E) 108,474.30 116,322.25

11 A.4.2.1.12 1 m2 Pemasangan Pintu Allumunium Strip Lebar 8 cm 472,766.25 507,029.05


A Tenaga 12,087.50 13,935.50
L.01 0.085 OH Pekerja 55,000.00 65,000.00 4,675.00 5,525.00
L.02 0.085 OH Tukang Besi 75,000.00 85,000.00 6,375.00 7,225.00
L.03 0.0085 OH Kepala Tukang 85,000.00 95,000.00 722.50 807.50
L.04 0.0042 OH Mandor 75,000.00 90,000.00 315.00 378.00
B Bahan 417,700.00 447,000.00
4.4 m' Profil Allumunium 80,000.00 85,000.00 352,000.00 374,000.00
14.6 m' Allumunium Strip 4,500.00 5,000.00 65,700.00 73,000.00
C PERALATAN
D Jumlah A + B + C 429,787.50 460,935.50
E Overhead & Profit (contoh 10%) 10% 42,978.75 46,093.55
F Harga Satuan Pekerjaan (D+E) 472,766.25 507,029.05

12 A.4.2.1.13 1 m2 Pemasangan Pintu Kaca Rangka Allumunium 440,209.00 474,380.50


A Tenaga 12,190.00 14,055.00
L.01 0.085 OH Pekerja 55,000.00 65,000.00 4,675.00 5,525.00
L.02 0.085 OH Tukang Besi 75,000.00 85,000.00 6,375.00 7,225.00
L.03 0.009 OH Kepala Tukang 85,000.00 95,000.00 765.00 855.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 388,000.00 417,200.00
4.4 m' Pintu Allumunium 80,000.00 85,000.00 352,000.00 374,000.00
4.5 m' Profil Kaca 5,000.00 6,000.00 22,500.00 27,000.00
0.27 tube Sealant 50,000.00 60,000.00 13,500.00 16,200.00
C PERALATAN
D Jumlah A + B + C 400,190.00 431,255.00
E Overhead & Profit (contoh 10%) 10% 40,019.00 43,125.50
F Harga Satuan Pekerjaan (D+E) 440,209.00 474,380.50

13 A.4.2.1.14 1 m2 Pemasangan Venetions Blinds & Vertical Blinds 159,307.50 173,189.50


A Tenaga 49,825.00 57,445.00
L.01 0.35 OH Pekerja 55,000.00 65,000.00 19,250.00 22,750.00
L.02 0.35 OH Tukang Besi 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.018 OH Mandor 75,000.00 90,000.00 1,350.00 1,620.00

file:///conversion/tmp/scratch/443255086.xls 95/79 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 95,000.00 100,000.00
1 m2 Venetions Blinds atau Vertical Blinds (tirai) 95,000.00 100,000.00 95,000.00 100,000.00
C PERALATAN
D Jumlah A + B + C 144,825.00 157,445.00
E Overhead & Profit (contoh 10%) 10% 14,482.50 15,744.50
F Harga Satuan Pekerjaan (D+E) 159,307.50 173,189.50

14 A.4.2.1.15 1 m2 Pemasangan Terali Besi Strip (2x3) cm 319,202.28 368,024.87


A Tenaga 237,520.00 273,835.00
L.01 1.67 OH Pekerja 55,000.00 65,000.00 91,850.00 108,550.00
L.02 1.67 OH Tukang Las 75,000.00 85,000.00 125,250.00 141,950.00
L.03 0.167 OH Kepala Tukang 85,000.00 95,000.00 14,195.00 15,865.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 52,663.90 60,733.06
6.177 m' Besi Strip 2x3 1,250.00 1,350.00 7,721.25 8,338.95
27.08 cm Pengelasan 1,659.63 1,934.79 44,942.65 52,394.11
C PERALATAN
D Jumlah A + B + C 290,183.90 334,568.06
E Overhead & Profit (contoh 10%) 10% 29,018.39 33,456.81
F Harga Satuan Pekerjaan (D+E) 319,202.28 368,024.87

15 A.4.2.1.16 1 m2 Pemasangan Kawat Nyamuk 49,179.28 56,333.33


A Tenaga 14,225.00 16,400.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.1 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.0050 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 30,483.43 34,812.12
1.1 m2 Kawat Nyamuk nylon 9,000.00 10,000.00 9,900.00 11,000.00
11.11 cm Pengelasan 1,659.63 1,934.79 18,438.43 21,495.52
1.716 kg Baja Strip (0,2x2) cm 1,250.00 1,350.00 2,145.00 2,316.60
C PERALATAN
D Jumlah A + B + C 44,708.43 51,212.12
E Overhead & Profit (contoh 10%) 10% 4,470.84 5,121.21
F Harga Satuan Pekerjaan (D+E) 49,179.28 56,333.33

16 A.4.2.1.17 1 m2 Pemasangan Jendela Nako & Tralis 61,132.50 68,464.00


A Tenaga 27,775.00 31,990.00
L.01 0.2 OH Pekerja 55,000.00 65,000.00 11,000.00 13,000.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.001 OH Mandor 75,000.00 90,000.00 75.00 90.00
B Bahan 27,800.00 30,250.00
1.1 m2 Jendela Nako 12,000.00 12,500.00 13,200.00 13,750.00
10 buah Paku Skrup 1 - 2,5 cm 200.00 250.00 2,000.00 2,500.00
7 m' Besi Strip 1,800.00 2,000.00 12,600.00 14,000.00
C PERALATAN
D Jumlah A + B + C 55,575.00 62,240.00
E Overhead & Profit (contoh 10%) 10% 5,557.50 6,224.00
F Harga Satuan Pekerjaan (D+E) 61,132.50 68,464.00

17 A.4.2.1.18 1 m' Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm 164,967.00 191,015.00
A Tenaga 43,875.00 50,275.00
L.01 0.20 OH Pekerja 55,000.00 65,000.00 11,000.00 13,000.00
L.02 0.4 OH Tukang Kayu 75,000.00 85,000.00 30,000.00 34,000.00
L.03 0.025 OH Kepala Tukang 85,000.00 95,000.00 2,125.00 2,375.00
L.04 0.01 OH Mandor 75,000.00 90,000.00 750.00 900.00

file:///conversion/tmp/scratch/443255086.xls 95/80 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 106,095.00 123,375.00
1.05 Lbr Seng Plaat 14,000.00 25,000.00 14,700.00 26,250.00
0.015 Kg Paku Biasa 1 - 2,5 cm 13,000.00 15,000.00 195.00 225.00
0.019 m3 Kayu Papan Klas II atau III 4,800,000.00 5,100,000.00 91,200.00 96,900.00
C PERALATAN
D Jumlah A + B + C 149,970.00 173,650.00
E Overhead & Profit (contoh 10%) 10% 14,997.00 17,365.00
F Harga Satuan Pekerjaan (D+E) 164,967.00 191,015.00

18 A.4.2.1.19 1 m' Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm 60,478.00 79,167.00
A Tenaga 33,900.00 38,820.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.3 OH Tukang Kayu 75,000.00 85,000.00 22,500.00 25,500.00
L.03 0.03 OH Kepala Tukang 85,000.00 95,000.00 2,550.00 2,850.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 21,080.00 33,150.00
1.05 Lbr Seng Plaat 14,000.00 25,000.00 14,700.00 26,250.00
0.01 Kg Paku Biasa 1 - 2,5 cm 13,000.00 15,000.00 130.00 150.00
0.5 Kg Besi strip 12,500.00 13,500.00 6,250.00 6,750.00
C PERALATAN
D Jumlah A + B + C 54,980.00 71,970.00
E Overhead & Profit (contoh 10%) 10% 5,498.00 7,197.00
F Harga Satuan Pekerjaan (D+E) 60,478.00 79,167.00

19 A.4.2.1.20 1 m2 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 60x120 cm dinding partisi 154,660.00 179,899.50
A Tenaga 35,600.00 41,045.00
L.01 0.250 OH Pekerja 55,000.00 65,000.00 13,750.00 16,250.00
L.02 0.250 OH Tukang Besi 75,000.00 85,000.00 18,750.00 21,250.00
L.03 0.025 OH Kepala Tukang 85,000.00 95,000.00 2,125.00 2,375.00
L.04 0.013 OH Mandor 75,000.00 90,000.00 975.00 1,170.00
B Bahan 105,000.00 122,500.00
3.50 m' Rangka metal hollow 40.40.2 mm 15,000.00 17,500.00 52,500.00 61,250.00
1.00 Assesoris (perkuatan; las dll) 52,500.00 61,250.00 52,500.00 61,250.00

C PERALATAN
D Jumlah A + B + C 140,600.00 163,545.00
E Overhead & Profit (contoh 10%) 10% 14,060.00 16,354.50
F Harga Satuan Pekerjaan (D+E) 154,660.00 179,899.50

20 A.4.2.1.21 1 m2 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 60x60 cm dinding plafond 186,807.50 217,189.50
A Tenaga 49,825.00 57,445.00
L.01 0.350 OH Pekerja 55,000.00 65,000.00 19,250.00 22,750.00
L.02 0.350 OH Tukang Besi 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.018 OH Mandor 75,000.00 90,000.00 1,350.00 1,620.00
B Bahan 120,000.00 140,000.00
4.00 m' Rangka metal hollow 40.40.2 mm 15,000.00 17,500.00 60,000.00 70,000.00
1.00 Assesoris (perkuatan; las dll) 60,000.00 70,000.00 60,000.00 70,000.00

C PERALATAN
D Jumlah A + B + C 169,825.00 197,445.00
E Overhead & Profit (contoh 10%) 10% 16,982.50 19,744.50
F Harga Satuan Pekerjaan (D+E) 186,807.50 217,189.50

file:///conversion/tmp/scratch/443255086.xls 95/81 abk 11-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XII A.4.6.2 HARGA SATUAN PEKERJAAN KUNCI dan KACA


1 A.4.6.2.2 1 Buah Pemasangan Kunci Tanam Biasa 197,202.50 219,505.00
A Tenaga 39,275.00 44,550.00
L.01 0.01 OH Pekerja 55,000.00 65,000.00 550.00 650.00
L.02 0.5 OH Tukang Kayu 75,000.00 85,000.00 37,500.00 42,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 140,000.00 155,000.00
1 Buah Kunci Tanam Biasa 140,000.00 155,000.00 140,000.00 155,000.00
C PERALATAN
D Jumlah A + B + C 179,275.00 199,550.00
E Overhead & Profit (contoh 10%) 10% 17,927.50 19,955.00
F Harga Satuan Pekerjaan (D+E) 197,202.50 219,505.00
Overhead & Profit (contoh 10%)

2 A.4.6.2.3 1 Buah Pemasangan Kunci Kamar Mandi 135,726.25 152,377.50


A Tenaga 38,387.50 43,525.00
L.01 0.005 OH Pekerja 55,000.00 65,000.00 275.00 325.00
L.02 0.5 OH Tukang Kayu 75,000.00 85,000.00 37,500.00 42,500.00
L.03 0.005 OH Kepala Tukang 85,000.00 95,000.00 425.00 475.00
L.04 0.0025 OH Mandor 75,000.00 90,000.00 187.50 225.00
B Bahan 85,000.00 95,000.00
1 Buah Kunci Tanam Kamar Mandi 85,000.00 95,000.00 85,000.00 95,000.00
C PERALATAN
D Jumlah A + B + C 123,387.50 138,525.00
E Overhead & Profit (contoh 10%) 10% 12,338.75 13,852.50
F Harga Satuan Pekerjaan (D+E) 135,726.25 152,377.50

3 A.4.6.2.4 1 Buah Pemasangan Kunci Selinder 196,226.25 218,377.50


A Tenaga 38,387.50 43,525.00
L.01 0.005 OH Pekerja 55,000.00 65,000.00 275.00 325.00
L.02 0.5 OH Tukang Kayu 75,000.00 85,000.00 37,500.00 42,500.00
L.03 0.005 OH Kepala Tukang 85,000.00 95,000.00 425.00 475.00
L.04 0.0025 OH Mandor 75,000.00 90,000.00 187.50 225.00
B Bahan 140,000.00 155,000.00
1 Buah Kunci Selinder 140,000.00 155,000.00 140,000.00 155,000.00
C PERALATAN
D Jumlah A + B + C 178,387.50 198,525.00
E Overhead & Profit (contoh 10%) 10% 17,838.75 19,852.50
F Harga Satuan Pekerjaan (D+E) 196,226.25 218,377.50

4 A.4.6.2.5 1 Buah Pemasangan Engsel Pintu 21,903.75 27,307.50


A Tenaga 13,912.50 15,825.00
L.01 0.015 OH Pekerja 55,000.00 65,000.00 825.00 975.00
L.02 0.15 OH Tukang Kayu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.0075 OH Mandor 75,000.00 90,000.00 562.50 675.00
B Bahan 6,000.00 9,000.00
1 Buah Engsel pintu 6,000.00 9,000.00 6,000.00 9,000.00
C PERALATAN
D Jumlah A + B + C 19,912.50 24,825.00
E Overhead & Profit (contoh 10%) 10% 1,991.25 2,482.50
F Harga Satuan Pekerjaan (D+E) 21,903.75 27,307.50

5 A.4.6.2.6 1 Buah Pemasangan Engsel Jendela Kupu-kupu 14,602.50 16,555.00


A Tenaga 9,275.00 10,550.00
L.01 0.01 OH Pekerja 55,000.00 65,000.00 550.00 650.00
L.02 0.1 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 4,000.00 4,500.00
1 Buah Engsel Jendela 4,000.00 4,500.00 4,000.00 4,500.00
C PERALATAN
D Jumlah A + B + C 13,275.00 15,050.00
E Overhead & Profit (contoh 10%) 10% 1,327.50 1,505.00
F Harga Satuan Pekerjaan (D+E) 14,602.50 16,555.00
file:///conversion/tmp/scratch/443255086.xls 95/82 abk 12-14
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
6 A.4.6.2.7 1 Buah Pemasangan Engsel Angin 40,961.25 45,589.50
A Tenaga 22,237.50 25,445.00
L.01 0.10 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.20 OH Tukang Kayu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.0005 OH Mandor 75,000.00 90,000.00 37.50 45.00
B Bahan 15,000.00 16,000.00
1 Buah Engsel Angin 15,000.00 16,000.00 15,000.00 16,000.00
C PERALATAN
D Jumlah A + B + C 37,237.50 41,445.00
E Overhead & Profit (contoh 10%) 10% 3,723.75 4,144.50
F Harga Satuan Pekerjaan (D+E) 40,961.25 45,589.50

7 A.4.6.2.9 1 Buah Pemasangan Kait Angin 20,845.00 36,707.00


A Tenaga 13,950.00 15,870.00
L.01 0.015 OH Pekerja 55,000.00 65,000.00 825.00 975.00
L.02 0.15 OH Tukang Kayu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 5,000.00 17,500.00
1 Buah Kait Angin 5,000.00 17,500.00 5,000.00 17,500.00
C PERALATAN
D Jumlah A + B + C 18,950.00 33,370.00
E Overhead & Profit (contoh 10%) 10% 1,895.00 3,337.00
F Harga Satuan Pekerjaan (D+E) 20,845.00 36,707.00

8 A.4.6.2.10 1 Buah Pasang Door Closer 351,656.25 440,797.50


A Tenaga 44,687.50 50,725.00
L.01 0.05 OH Pekerja 55,000.00 65,000.00 2,750.00 3,250.00
L.02 0.5 OH Tukang Kayu 75,000.00 85,000.00 37,500.00 42,500.00
L.03 0.05 OH Kepala Tukang 85,000.00 95,000.00 4,250.00 4,750.00
L.04 0.0025 OH Mandor 75,000.00 90,000.00 187.50 225.00
B Bahan 275,000.00 350,000.00
1 Buah Door Closer 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 319,687.50 400,725.00
E Overhead & Profit (contoh 10%) 10% 31,968.75 40,072.50
F Harga Satuan Pekerjaan (D+E) 351,656.25 440,797.50

9 A.4.6.2.11 1 Buah Pemasangan Kunci Selot 30,662.50 44,319.00


A Tenaga 17,875.00 20,290.00
L.01 0.02 OH Pekerja 55,000.00 65,000.00 1,100.00 1,300.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.001 OH Mandor 75,000.00 90,000.00 75.00 90.00
B Bahan 10,000.00 20,000.00
1 Buah Kunci Selot 10,000.00 20,000.00 10,000.00 20,000.00
C PERALATAN
D Jumlah A + B + C 27,875.00 40,290.00
E Overhead & Profit (contoh 10%) 10% 2,787.50 4,029.00
F Harga Satuan Pekerjaan (D+E) 30,662.50 44,319.00

10 A.4.6.2.13 1 Buah Pemasangan Door Stop 312,331.25 396,159.50


A Tenaga 8,937.50 10,145.00
L.01 0.01 OH Pekerja 55,000.00 65,000.00 550.00 650.00
L.02 0.1 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.0005 OH Mandor 75,000.00 90,000.00 37.50 45.00
B Bahan 275,000.00 350,000.00
1 Buah Door Stop 275,000.00 350,000.00 275,000.00 350,000.00
C PERALATAN
D Jumlah A + B + C 283,937.50 360,145.00
E Overhead & Profit (contoh 10%) 10% 28,393.75 36,014.50
F Harga Satuan Pekerjaan (D+E) 312,331.25 396,159.50

file:///conversion/tmp/scratch/443255086.xls 95/83 abk 12-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
11 A.4.6.2.14 1 Buah Pemasangan Rel Pintu Dorong 256,987.50 325,457.00
A Tenaga 53,625.00 60,870.00
L.01 0.06 OH Pekerja 55,000.00 65,000.00 3,300.00 3,900.00
L.02 0.6 OH Tukang Kayu 75,000.00 85,000.00 45,000.00 51,000.00
L.03 0.06 OH Kepala Tukang 85,000.00 95,000.00 5,100.00 5,700.00
L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 180,000.00 235,000.00
1 Buah Rel Pintu Dorong 180,000.00 235,000.00 180,000.00 235,000.00
C PERALATAN
D Jumlah A + B + C 233,625.00 295,870.00
E Overhead & Profit (contoh 10%) 10% 23,362.50 29,587.00
F Harga Satuan Pekerjaan (D+E) 256,987.50 325,457.00

12 A.4.6.2.15 1 Buah Pemasangan Kunci Lemari 30,082.25 36,153.70


A Tenaga 22,347.50 25,367.00
L.01 0.025 OH Pekerja 55,000.00 65,000.00 1,375.00 1,625.00
L.02 0.25 OH Tukang Kayu 75,000.00 85,000.00 18,750.00 21,250.00
L.03 0.025 OH Kepala Tukang 85,000.00 95,000.00 2,125.00 2,375.00
L.04 0.00130 OH Mandor 75,000.00 90,000.00 97.50 117.00
B Bahan 5,000.00 7,500.00
1 Buah Kunci Lemari 5,000.00 7,500.00 5,000.00 7,500.00
C PERALATAN
D Jumlah A + B + C 27,347.50 32,867.00
E Overhead & Profit (contoh 10%) 10% 2,734.75 3,286.70
F Harga Satuan Pekerjaan (D+E) 30,082.25 36,153.70

13 A.4.6.2.16 1 m2 Pemasangan Kaca tebal 3 mm 87,346.88 95,389.25


A Tenaga 13,406.25 15,217.50
L.01 0.015 OH Pekerja 55,000.00 65,000.00 825.00 975.00
L.02 0.15 OH Tukang Kayu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.00075 OH Mandor 75,000.00 90,000.00 56.25 67.50
B Bahan 66,000.00 71,500.00
1.1 m2 Kaca tebal 3mm 60,000.00 65,000.00 66,000.00 71,500.00
C PERALATAN
D Jumlah A + B + C 79,406.25 86,717.50
E Overhead & Profit (contoh 10%) 10% 7,940.63 8,671.75
F Harga Satuan Pekerjaan (D+E) 87,346.88 95,389.25

14 A.4.6.2.17 1 m2 Pemasangan Kaca tebal 5 mm 99,446.88 108,699.25


A Tenaga 13,406.25 15,217.50
L.01 0.015 OH Pekerja 55,000.00 65,000.00 825.00 975.00
L.02 0.15 OH Tukang Kayu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.00075 OH Mandor 75,000.00 90,000.00 56.25 67.50
B Bahan 77,000.00 83,600.00
1.1 m2 Kaca tebal 5mm 70,000.00 76,000.00 77,000.00 83,600.00
C PERALATAN
D Jumlah A + B + C 90,406.25 98,817.50
E Overhead & Profit (contoh 10%) 10% 9,040.63 9,881.75
F Harga Satuan Pekerjaan (D+E) 99,446.88 108,699.25

15 A.4.6.2.18 1 m2 Pemasangan Kaca Cermin tebal 5 mm 286,996.88 349,489.25


A Tenaga 13,406.25 15,217.50
L.01 0.015 OH Pekerja 55,000.00 65,000.00 825.00 975.00
L.02 0.15 OH Tukang Kayu 75,000.00 85,000.00 11,250.00 12,750.00
L.03 0.015 OH Kepala Tukang 85,000.00 95,000.00 1,275.00 1,425.00
L.04 0.00075 OH Mandor 75,000.00 90,000.00 56.25 67.50
B Bahan 247,500.00 302,500.00
1.1 m2 Kaca Cermin 225,000.00 275,000.00 247,500.00 302,500.00
C PERALATAN
D Jumlah A + B + C 260,906.25 317,717.50
E Overhead & Profit (contoh 10%) 10% 26,090.63 31,771.75
F Harga Satuan Pekerjaan (D+E) 286,996.88 349,489.25

file:///conversion/tmp/scratch/443255086.xls 95/84 abk 12-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XIII A.4.4.3 HARGA SATUAN PEKERJAAN PENUTUP LANTAI dan DINDING


1 A.4.4.3.2 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 30 x 30 cm 92,971.00 102,605.00
A Tenaga 25,205.00 29,280.00
L.01 0.25 OH Pekerja 55,000.00 65,000.00 13,750.00 16,250.00
L.02 0.125 OH Tukang Batu 75,000.00 85,000.00 9,375.00 10,625.00
L.03 0.013 OH Kepala Tukang 85,000.00 95,000.00 1,105.00 1,235.00
L.04 0.013 OH Mandor 75,000.00 90,000.00 975.00 1,170.00
B Bahan 59,314.09 63,997.27
11.87 Buah Ubin Abu-abu 30x30 cm 11.1111111111 3,090.91 3,272.73 36,689.09 38,847.27
10.0 Kg Portland Semen 0.3 1,250.00 1,300.00 12,500.00 13,000.00
0.0450 m3 Pasir Pasang 0.09 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 84,519.09 93,277.27
E Overhead & Profit (contoh 10%) 10% 8,451.91 9,327.73
F Harga Satuan Pekerjaan (D+E) 92,971.00 102,605.00

2 A.4.4.3.3 1 m2 Pemasangan lantai Ubin PC Abu-abu Uk. 20 x 20 cm 92,686.00 102,657.50


A Tenaga 27,215.00 31,615.00
L.01 0.27 OH Pekerja 55,000.00 65,000.00 14,850.00 17,550.00
L.02 0.135 OH Tukang Batu 75,000.00 85,000.00 10,125.00 11,475.00
L.03 0.014 OH Kepala Tukang 85,000.00 95,000.00 1,190.00 1,330.00
L.04 0.014 OH Mandor 75,000.00 90,000.00 1,050.00 1,260.00
B Bahan 57,045.00 61,710.00
26.5 Buah Ubin Abu-abu 20x20 cm 1,280.00 1,360.00 33,920.00 36,040.00
10.4 Kg Portland Semen 1,250.00 1,300.00 13,000.00 13,520.00
0.0450 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 84,260.00 93,325.00
E Overhead & Profit (contoh 10%) 10% 8,426.00 9,332.50
F Harga Satuan Pekerjaan (D+E) 92,686.00 102,657.50

3 A.4.4.3.5 1 m2 Pemasangan lantai Ubin PC Warna Uk. 30 x 30 cm 131,795.50 145,357.50


A Tenaga 26,130.00 30,355.00
L.01 0.26 OH Pekerja 55,000.00 65,000.00 14,300.00 16,900.00
L.02 0.130 OH Tukang Batu 75,000.00 85,000.00 9,750.00 11,050.00
L.03 0.013 OH Kepala Tukang 85,000.00 95,000.00 1,105.00 1,235.00
L.04 0.013 OH Mandor 75,000.00 90,000.00 975.00 1,170.00
B Bahan 93,684.09 101,788.18
11.87 Buah Ubin Warna 30x30 cm 4,090.91 4,181.82 48,559.09 49,638.18
10.0 Kg Portland Semen 1,250.00 1,300.00 12,500.00 13,000.00
1.50 Kg Semen warna 15,000 18,000 22,500.00 27,000.00
0.0450 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 119,814.09 132,143.18
E Overhead & Profit (contoh 10%) 10% 11,981.41 13,214.32
F Harga Satuan Pekerjaan (D+E) 131,795.50 145,357.50

4 A.4.4.3.6 1 m2 Pemasangan lantai Ubin PC Warna Uk. 20 x 20 cm 128,744.00 144,061.50


A Tenaga 27,215.00 31,615.00
L.01 0.27 OH Pekerja 55,000.00 65,000.00 14,850.00 17,550.00
L.02 0.135 OH Tukang Batu 75,000.00 85,000.00 10,125.00 11,475.00
L.03 0.014 OH Kepala Tukang 85,000.00 95,000.00 1,190.00 1,330.00
L.04 0.014 OH Mandor 75,000.00 90,000.00 1,050.00 1,260.00
B Bahan 89,825.00 99,350.00
26.5 Buah Ubin Warna 20x20 cm 1,600.00 1,680.00 42,400.00 44,520.00
10.4 Kg Portland Semen 1,250.00 1,300.00 13,000.00 13,520.00
1.62 Kg Semen warna 15,000.00 18,000.00 24,300.00 29,160.00
0.0450 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 117,040.00 130,965.00
E Overhead & Profit (contoh 10%) 10% 11,704.00 13,096.50
F Harga Satuan Pekerjaan (D+E) 128,744.00 144,061.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
5 A.4.4.3.9 1 m2 Pemasangan lantai Ubin Granito Uk. 40 x 40 cm 341,198.00 583,682.00
A Tenaga 25,205.00 29,280.00
L.01 0.250 OH Pekerja 55,000.00 65,000.00 13,750.00 16,250.00
L.02 0.125 OH Tukang Batu 75,000.00 85,000.00 9,375.00 10,625.00
L.03 0.013 OH Kepala Tukang 85,000.00 95,000.00 1,105.00 1,235.00
L.04 0.013 OH Mandor 75,000.00 90,000.00 975.00 1,170.00
B Bahan 284,975.00 501,340.00
6.63 Buah Ubin Granito 40x40 cm 0.4 36,666.67 68,333.33 243,100.00 453,050.00
9.8 Kg Portland Semen 0.16 1,250.00 1,300.00 12,250.00 12,740.00
1.300 Kg Semen warna 6.25 15,000.00 18,000.00 19,500.00 23,400.00
0.045 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 310,180.00 530,620.00
E Overhead & Profit (contoh 10%) 10% 31,018.00 53,062.00
F Harga Satuan Pekerjaan (D+E) 341,198.00 583,682.00

6 A.4.4.3.16 1 m' Pemasangan Ubin Plin Pc.Abu-abu Uk. 15 x 20 cm 56,699.50 66,403.70


A Tenaga 12,840.00 14,805.00
L.01 0.090 OH Pekerja 55,000.00 65,000.00 4,950.00 5,850.00
L.02 0.090 OH Tukang Batu 75,000.00 85,000.00 6,750.00 7,650.00
L.03 0.009 OH Kepala Tukang 85,000.00 95,000.00 765.00 855.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 38,705.00 45,562.00
5.30 Buah Ubin Plin Pc Abu-abu 15x20 cm 5,100.00 6,000.00 27,030.00 31,800.00
1.2 Kg Portland Semen 1,250.00 1,300.00 1,550.00 1,612.00
0.045 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 51,545.00 60,367.00
E Overhead & Profit (contoh 10%) 10% 5,154.50 6,036.70
F Harga Satuan Pekerjaan (D+E) 56,699.50 66,403.70

7 A.4.4.3.19 1 m' Pemasangan Ubin Plin Pc.Warna Uk. 10 x 20 cm 33,242.00 36,819.20


A Tenaga 12,840.00 14,805.00
L.01 0.090 OH Pekerja 55,000.00 65,000.00 4,950.00 5,850.00
L.02 0.090 OH Tukang Batu 75,000.00 85,000.00 6,750.00 7,650.00
L.03 0.009 OH Kepala Tukang 85,000.00 95,000.00 765.00 855.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 17,380.00 18,667.00
2.65 Buah Ubin Plin Pc SWarna 15x20 cm 5,200.00 5,500.00 13,780.00 14,575.00
1.14 Kg Portland Semen 1,250.00 1,300.00 1,425.00 1,482.00
0.100 Kg Semen Warna 15,000.00 18,000.00 1,500.00 1,800.00
0.003 m3 Pasir Pasang 225,000.00 270,000.00 675.00 810.00
C PERALATAN
D Jumlah A + B + C 30,220.00 33,472.00
E Overhead & Profit (contoh 10%) 10% 3,022.00 3,347.20
F Harga Satuan Pekerjaan (D+E) 33,242.00 36,819.20

8 A.4.4.3.32 1 m2 Pemasangan Lantai Keramik 10x 20 cm 201,126.75 230,056.20


A Tenaga 70,350.00 81,725.00
L.01 0.70 OH Pekerja 55,000.00 65,000.00 38,500.00 45,500.00
L.02 0.350 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 112,492.50 127,417.00
53.00 Buah Keramik 10 x 20 cm 960.00 1,040.00 50,880.00 55,120.00
8.2 Kg Portland Semen 1,250.00 1,300.00 10,237.50 10,647.00
2.75 Kg Semen Warna 15,000.00 18,000.00 41,250.00 49,500.00
0.0450 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 182,842.50 209,142.00
E Overhead & Profit (contoh 10%) 10% 18,284.25 20,914.20
F Harga Satuan Pekerjaan (D+E) 201,126.75 230,056.20
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
9 A.4.4.3.33 1 m2 Pemasangan lantai Keramik Uk. 10 x 10 cm / 5 x 20 cm 208,551.75 238,966.20
A Tenaga 70,350.00 81,725.00
L.01 0.70 OH Pekerja 55,000.00 65,000.00 38,500.00 45,500.00
L.02 0.350 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 119,242.50 135,517.00
106.00 Buah Keramik 10 x 10 cm / 5 x 20 cm 480.00 520.00 50,880.00 55,120.00
8.19 Kg Portland Semen 1,250.00 1,300.00 10,237.50 10,647.00
3.20 Kg Semen Warna 15,000.00 18,000.00 48,000.00 57,600.00
0.0450 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 189,592.50 217,242.00
E Overhead & Profit (contoh 10%) 10% 18,959.25 21,724.20
F Harga Satuan Pekerjaan (D+E) 208,551.75 238,966.20

10 A.4.4.3.34 1 m2 Pemasangan Lantai Keramik 33 x 33 cm 190,069.31 217,939.09


A Tenaga 70,350.00 81,725.00
L.01 0.70 OH Pekerja 55,000.00 65,000.00 38,500.00 45,500.00
L.02 0.35 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 102,440.28 116,401.44
10 Buah Ubin Keramik 33 x 33 cm 5,777.78 6,444.44 57,777.78 64,444.44
8.19 Kg Portland Semen 1,250.00 1,300.00 10,237.50 10,647.00
0.045 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
1.62 Kg Semen Warna 15,000.00 18,000.00 24,300.00 29,160.00
C PERALATAN
D Jumlah A + B + C 172,790.28 198,126.44
E Overhead & Profit (contoh 10%) 10% 17,279.03 19,812.64
F Harga Satuan Pekerjaan (D+E) 190,069.31 217,939.09

11 A.4.4.3.35 1 m2 Pemasangan Lantai Keramik 30 x 30 cm 188,746.50 214,921.50


A Tenaga 70,350.00 81,725.00
L.01 0.70 OH Pekerja 55,000.00 65,000.00 38,500.00 45,500.00
L.02 0.35 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 101,237.73 113,658.18
11.87 Buah Ubin Keramik 30 x 30 cm 4,727.27 5,181.82 56,112.73 61,508.18
10.00 Kg Portland Semen 1,250.00 1,300.00 12,500.00 13,000.00
0.045 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
1.50 Kg Semen Warna 15,000.00 18,000.00 22,500.00 27,000.00
C PERALATAN
D Jumlah A + B + C 171,587.73 195,383.18
E Overhead & Profit (contoh 10%) 10% 17,158.77 19,538.32
F Harga Satuan Pekerjaan (D+E) 188,746.50 214,921.50

12 A.4.4.3.36 1 m2 Pemasangan Lantai Keramik 20 x 20 cm 192,516.50 215,506.50


A Tenaga 70,350.00 81,725.00
L.01 0.70 OH Pekerja 55,000.00 65,000.00 38,500.00 45,500.00
L.02 0.35 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 104,665.00 114,190.00
26.5 Buah Ubin Keramik 20 x 20 cm 2,160.00 2,240.00 57,240.00 59,360.00
10.40 Kg Portland Semen 1,250.00 1,300.00 13,000.00 13,520.00
1.62 Kg Semen Warna 15,000.00 18,000.00 24,300.00 29,160.00
0.045 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 175,015.00 195,915.00
E Overhead & Profit (contoh 10%) 10% 17,501.50 19,591.50
F Harga Satuan Pekerjaan (D+E) 192,516.50 215,506.50
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
13 A.4.4.3.37 1 m2 Pemasangan Lantai Keramik uk.10 x 33 cm, untuk variasi / border 392,898.00 435,831.00
A Tenaga 104,255.00 121,060.00
L.01 1.05 OH Pekerja 55,000.00 65,000.00 57,750.00 68,250.00
L.02 0.525 OH Tukang Batu 75,000.00 85,000.00 39,375.00 44,625.00
L.03 0.053 OH Kepala Tukang 85,000.00 95,000.00 4,505.00 5,035.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 252,925.00 275,150.00
33.0 Buah Ubin Keramik 5,000.00 5,200.00 165,000.00 171,600.00
9.80 Kg Portland Semen 1,250.00 1,300.00 12,250.00 12,740.00
4.37 Kg Semen Warna 15,000.00 18,000.00 65,550.00 78,660.00
0.045 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 357,180.00 396,210.00
E Overhead & Profit (contoh 10%) 10% 35,718.00 39,621.00
F Harga Satuan Pekerjaan (D+E) 392,898.00 435,831.00

14 A.4.4.3.39 1 m' Pemasangan Plint Keramik Ukuran 10x20 cm 31,421.50 36,791.70


A Tenaga 12,840.00 14,805.00
L.01 0.09 OH Pekerja 55,000.00 65,000.00 4,950.00 5,850.00
L.02 0.09 OH Tukang Batu 75,000.00 85,000.00 6,750.00 7,650.00
L.03 0.009 OH Kepala Tukang 85,000.00 95,000.00 765.00 855.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 15,725.00 18,642.00
5.3 Buah Ubin Keramik 2,500.00 3,000.00 13,250.00 15,900.00
1.14 Kg Portland Semen 1,250.00 1,300.00 1,425.00 1,482.00
0.003 m3 Pasir Pasang 225,000.00 270,000.00 675.00 810.00
0.025 Kg Semen Warna 15,000.00 18,000.00 375.00 450.00
C PERALATAN
D Jumlah A + B + C 28,565.00 33,447.00
E Overhead & Profit (contoh 10%) 10% 2,856.50 3,344.70
F Harga Satuan Pekerjaan (D+E) 31,421.50 36,791.70

15 A.4.4.3.40 1 m' Pemasangan Plint Keramik Ukuran 10x10 cm 77,891.00 83,926.70


A Tenaga 12,840.00 14,805.00
L.01 0.09 OH Pekerja 55,000.00 65,000.00 4,950.00 5,850.00
L.02 0.09 OH Tukang Batu 75,000.00 85,000.00 6,750.00 7,650.00
L.03 0.009 OH Kepala Tukang 85,000.00 95,000.00 765.00 855.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 57,970.00 61,492.00
10.6 Buah Ubin Keramik 5,200.00 5,500.00 55,120.00 58,300.00
1.14 Kg Portland Semen 1,250.00 1,300.00 1,425.00 1,482.00
0.003 m3 Pasir Pasang 225,000.00 270,000.00 675.00 810.00
0.05 Kg Semen Warna 15,000.00 18,000.00 750.00 900.00
C PERALATAN
D Jumlah A + B + C 70,810.00 76,297.00
E Overhead & Profit (contoh 10%) 10% 7,081.00 7,629.70
F Harga Satuan Pekerjaan (D+E) 77,891.00 83,926.70

16 A.4.4.3.41 1 m' Pemasangan Plint Keramik Ukuran 5x20 cm 75,559.00 82,760.70


A Tenaga 12,840.00 14,805.00
L.01 0.09 OH Pekerja 55,000.00 65,000.00 4,950.00 5,850.00
L.02 0.09 OH Tukang Batu 75,000.00 85,000.00 6,750.00 7,650.00
L.03 0.009 OH Kepala Tukang 85,000.00 95,000.00 765.00 855.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 55,850.00 60,432.00
10.6 Buah Ubin Keramik 5,000.00 5,400.00 53,000.00 57,240.00
1.14 Kg Portland Semen 1,250.00 1,300.00 1,425.00 1,482.00
0.003 m3 Pasir Pasang 225,000.00 270,000.00 675.00 810.00
0.05 Kg Semen Warna 15,000.00 18,000.00 750.00 900.00
C PERALATAN
D Jumlah A + B + C 68,690.00 75,237.00
E Overhead & Profit (contoh 10%) 10% 6,869.00 7,523.70
F Harga Satuan Pekerjaan (D+E) 75,559.00 82,760.70
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
17 A.4.4.3.43 1 m2 Pemasangan Lantai Marmer Ukuran 1.00x1.00 cm 664,358.75 687,524.20
A Tenaga 70,350.00 81,725.00
L.01 0.7 OH Pekerja 55,000.00 65,000.00 38,500.00 45,500.00
L.02 0.35 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 533,612.50 543,297.00
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
8.19 kg Portland Semen 1,250.00 1,300.00 10,237.50 10,647.00
0.045 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
0.65 kg Semen Warna 15,000.00 18,000.00 9,750.00 11,700.00
C PERALATAN
D Jumlah A + B + C 603,962.50 625,022.00
E Overhead & Profit (contoh 10%) 10% 60,396.25 62,502.20
F Harga Satuan Pekerjaan (D+E) 664,358.75 687,524.20

18 A.4.4.3.44 1 m2 Pemasangan Lantai Karpet 185,454.50 203,967.50


A Tenaga 24,220.00 27,925.00
L.01 0.17 OH Pekerja 55,000.00 65,000.00 9,350.00 11,050.00
L.02 0.17 OH Tukang Batu 75,000.00 85,000.00 12,750.00 14,450.00
L.03 0.017 OH Kepala Tukang 85,000.00 95,000.00 1,445.00 1,615.00
L.04 0.009 OH Mandor 75,000.00 90,000.00 675.00 810.00
B Bahan 144,375.00 157,500.00
1.05 m2 Karpet 125,000.00 130,000.00 131,250.00 136,500.00
0.35 kg Lem 37,500.00 60,000.00 13,125.00 21,000.00
C PERALATAN
D Jumlah A + B + C 168,595.00 185,425.00
E Overhead & Profit (contoh 10%) 10% 16,859.50 18,542.50
F Harga Satuan Pekerjaan (D+E) 185,454.50 203,967.50

19 A.4.4.3.46 1 m2 Pemasangan Lantai Parquet Jati 327,360.00 372,047.50


A Tenaga 70,350.00 81,725.00
L.01 0.70 OH Pekerja 55,000.00 65,000.00 38,500.00 45,500.00
L.02 0.35 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 227,250.00 256,500.00
1.05 m2 Parquet Jati 195,000.00 210,000.00 204,750.00 220,500.00
0.6 Kg Lem Vynil 37,500.00 60,000.00 22,500.00 36,000.00
C PERALATAN
D Jumlah A + B + C 297,600.00 338,225.00
E Overhead & Profit (contoh 10%) 10% 29,760.00 33,822.50
F Harga Satuan Pekerjaan (D+E) 327,360.00 372,047.50

20 A.4.4.3.48 1 m2 Pemasangan Dinding Porselen 11 x 11 cm 221,621.16 251,127.32


A Tenaga 100,500.00 116,750.00
L.01 1.00 OH Pekerja 55,000.00 65,000.00 55,000.00 65,000.00
L.02 0.50 OH Tukang Batu 75,000.00 85,000.00 37,500.00 42,500.00
L.03 0.050 OH Kepala Tukang 85,000.00 95,000.00 4,250.00 4,750.00
L.04 0.050 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00
B Bahan 100,973.78 111,547.56
86 bh Porselen 512.20 524.39 44,048.78 45,097.56
9.30 Kg Portland Semen 82.6446280992 1,250.00 1,300.00 11,625.00 12,090.00

2.750 Kg Semen Warna 0.0121 15,000.00 18,000.00 41,250.00 49,500.00

0.018 m3 Pasir Pasang 0.11 225,000.00 270,000.00 4,050.00 4,860.00


C PERALATAN
D Jumlah A + B + C 201,473.78 228,297.56
E Overhead & Profit (contoh 10%) 10% 20,147.38 22,829.76
F Harga Satuan Pekerjaan (D+E) 221,621.16 251,127.32

21 A.4.4.3.49 1 m2 Pemasangan Dinding Keramik 10x20 cm, 218,080.50 249,309.50


A Tenaga 90,450.00 105,075.00
L.01 0.9 OH Pekerja 55,000.00 65,000.00 49,500.00 58,500.00
L.02 0.45 OH Tukang Batu 75,000.00 85,000.00 33,750.00 38,250.00
L.03 0.045 OH Kepala Tukang 85,000.00 95,000.00 3,825.00 4,275.00
L.04 0.045 OH Mandor 75,000.00 90,000.00 3,375.00 4,050.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 107,805.00 121,570.00
53 Buah Keramik 960.00 1,040.00 50,880.00 55,120.00
9.3 Kg Portland Semen 1,250.00 1,300.00 11,625.00 12,090.00
0.018 m3 Pasir Pasang 225,000.00 270,000.00 4,050.00 4,860.00
2.75 Kg Semen Warna 15,000.00 18,000.00 41,250.00 49,500.00
C PERALATAN
D Jumlah A + B + C 198,255.00 226,645.00
E Overhead & Profit (contoh 10%) 10% 19,825.50 22,664.50
F Harga Satuan Pekerjaan (D+E) 218,080.50 249,309.50

22 A.4.4.3.50 1 m2 Pemasangan Dinding Keramik 20x20 cm, 203,659.50 235,559.50


A Tenaga 90,450.00 105,075.00
L.01 0.9 OH Pekerja 55,000.00 65,000.00 49,500.00 58,500.00
L.02 0.45 OH Tukang Batu 75,000.00 85,000.00 33,750.00 38,250.00
L.03 0.045 OH Kepala Tukang 85,000.00 95,000.00 3,825.00 4,275.00
L.04 0.045 OH Mandor 75,000.00 90,000.00 3,375.00 4,050.00
B Bahan 94,695.00 109,070.00
26.0 Buah Keramik 1,920.00 2,200.00 49,920.00 57,200.00
9.3 Kg Portland Semen 1,250.00 1,300.00 11,625.00 12,090.00
0.018 m3 Pasir Pasang 225,000.00 270,000.00 4,050.00 4,860.00
1.94 Kg Semen Warna 15,000.00 18,000.00 29,100.00 34,920.00
C PERALATAN
D Jumlah A + B + C 185,145.00 214,145.00
E Overhead & Profit (contoh 10%) 10% 18,514.50 21,414.50
F Harga Satuan Pekerjaan (D+E) 203,659.50 235,559.50

23 A.4.4.3.53 1 m2 Pemasangan Dinding Keramik 10x20 cm, 218,080.50 249,309.50


A Tenaga 90,450.00 105,075.00
L.01 0.9 OH Pekerja 55,000.00 65,000.00 49,500.00 58,500.00
L.02 0.45 OH Tukang Batu 75,000.00 85,000.00 33,750.00 38,250.00
L.03 0.045 OH Kepala Tukang 85,000.00 95,000.00 3,825.00 4,275.00
L.04 0.045 OH Mandor 75,000.00 90,000.00 3,375.00 4,050.00
B Bahan 107,805.00 121,570.00
53.0 Buah Keramik 960.00 1,040.00 50,880.00 55,120.00
9.3 Kg Portland Semen 1,250.00 1,300.00 11,625.00 12,090.00
0.018 m3 Pasir Pasang 225,000.00 270,000.00 4,050.00 4,860.00
2.75 Kg Semen Warna 15,000.00 18,000.00 41,250.00 49,500.00
C PERALATAN
D Jumlah A + B + C 198,255.00 226,645.00
E Overhead & Profit (contoh 10%) 10% 19,825.50 22,664.50
F Harga Satuan Pekerjaan (D+E) 218,080.50 249,309.50

23 A.4.4.3.54 1 m2 Pemasangan Dinding Keramik 20x20 cm, 204,715.50 236,769.50


A Tenaga 90,450.00 105,075.00
L.01 0.9 OH Pekerja 55,000.00 65,000.00 49,500.00 58,500.00
L.02 0.45 OH Tukang Batu 75,000.00 85,000.00 33,750.00 38,250.00
L.03 0.045 OH Kepala Tukang 85,000.00 95,000.00 3,825.00 4,275.00
L.04 0.045 OH Mandor 75,000.00 90,000.00 3,375.00 4,050.00
B Bahan 95,655.00 110,170.00
26.5 Buah Keramik 1,920.00 2,200.00 50,880.00 58,300.00
9.3 Kg Portland Semen 1,250.00 1,300.00 11,625.00 12,090.00
0.018 m3 Pasir Pasang 225,000.00 270,000.00 4,050.00 4,860.00
1.94 Kg Semen Warna 15,000.00 18,000.00 29,100.00 34,920.00
C PERALATAN
D Jumlah A + B + C 186,105.00 215,245.00
E Overhead & Profit (contoh 10%) 10% 18,610.50 21,524.50
F Harga Satuan Pekerjaan (D+E) 204,715.50 236,769.50

24 A.4.4.3.55 1 m2 Pemasangan Dinding Marmer Ukuran 1.00x1.00 cm 731,698.12 764,832.32


A Tenaga 130,650.00 151,775.00
L.01 1.3 OH Pekerja 55,000.00 65,000.00 71,500.00 84,500.00
L.02 0.65 OH Tukang Batu 75,000.00 85,000.00 48,750.00 55,250.00
L.03 0.065 OH Kepala Tukang 85,000.00 95,000.00 5,525.00 6,175.00
L.04 0.065 OH Mandor 75,000.00 90,000.00 4,875.00 5,850.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 534,530.11 543,527.11
1.06 buah Marmer 475,000.00 480,000.00 503,500.00 508,800.00
3.003 buah Paku 12 cm 35.00 35.00 105.11 105.11
12.44 kg Portlan Semen 1,250.00 1,300.00 15,550.00 16,172.00
0.025 m3 Pasir Pasang 225,000.00 270,000.00 5,625.00 6,750.00
0.65 kg Semen Warna 15,000.00 18,000.00 9,750.00 11,700.00
C PERALATAN
D Jumlah A + B + C 665,180.11 695,302.11
E Overhead & Profit (contoh 10%) 10% 66,518.01 69,530.21
F Harga Satuan Pekerjaan (D+E) 731,698.12 764,832.32

25 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 217,153.75 240,515.00
A Tenaga 70,350.00 81,725.00
L.01 0.70 OH Pekerja 55,000.00 65,000.00 38,500.00 45,500.00
L.02 0.35 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 127,062.50 136,925.00
1.10 m2 Batu Paros 95,000.00 102,000.00 104,500.00 112,200.00
11.75 Kg Portland Semen 1,250.00 1,300.00 14,687.50 15,275.00
0.035 m3 Pasir Pasang 225,000.00 270,000.00 7,875.00 9,450.00
C PERALATAN
D Jumlah A + B + C 197,412.50 218,650.00
E Overhead & Profit (contoh 10%) 10% 19,741.25 21,865.00
F Harga Satuan Pekerjaan (D+E) 217,153.75 240,515.00

26 A.4.4.3.59 1 m2 Pemasangan Lantai Vynil uk.30 x 30 cm 128,632.90 144,732.50


A Tenaga 33,970.00 39,420.00
L.01 0.35 OH Pekerja 55,000.00 65,000.00 19,250.00 22,750.00
L.02 0.175 OH Tukang Batu 75,000.00 85,000.00 13,125.00 14,875.00
L.03 0.017 OH Kepala Tukang 85,000.00 95,000.00 1,445.00 1,615.00
L.04 0.002 OH Mandor 75,000.00 90,000.00 150.00 180.00
B Bahan 82,969.00 92,155.00
11.87 bh Vynil 30x30cm 6,200.00 6,500.00 73,594.00 77,155.00
0.25 kg Lem 37,500.00 60,000.00 9,375.00 15,000.00

C PERALATAN
D Jumlah A + B + C 116,939.00 131,575.00
E Overhead & Profit (contoh 10%) 10% 11,693.90 13,157.50
F Harga Satuan Pekerjaan (D+E) 128,632.90 144,732.50

27 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 36,762.00 43,978.00
Tenaga 17,070.00 19,680.00
L.01 0.12 OH Pekerja 55,000.00 65,000.00 6,600.00 7,800.00
L.02 0.12 OH Tukang Batu 75,000.00 85,000.00 9,000.00 10,200.00
L.03 0.012 OH Kepala Tukang 85,000.00 95,000.00 1,020.00 1,140.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
Bahan 16,350.00 20,300.00
0.003 m3 Papan Kayu Klas II 5,200,000.00 6,500,000.00 15,600.00 19,500.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00

C PERALATAN
D Jumlah A + B + C 33,420.00 39,980.00
E Overhead & Profit (contoh 10%) 10% 3,342.00 3,998.00
F Harga Satuan Pekerjaan (D+E) 36,762.00 43,978.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp

XIV A.4.7.1 HARGA SATUAN PEKERJAAN PENGECATAN

1 A.4.7.1.1 1 m2 Pengikisan / pengerokan Permukaan Cat Tembok Lama 9,982.50 11,737.00


A Tenaga 8,475.00 10,020.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.04 0.0030 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 600.00 650.00
0.05 Kg Soda Api 12,000.00 13,000.00 600.00 650.00
C PERALATAN

D Jumlah A + B + C 9,075.00 10,670.00


E Overhead & Profit (contoh 10%) 10% 907.50 1,067.00
F Harga Satuan Pekerjaan (D+E) 9,982.50 11,737.00

2 A.4.7.1.2 1 m2 Pencucian Bidang Permukaan Tembok yang Pernah dicat 9,927.50 11,737.00
A Tenaga 8,475.00 10,020.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.04 0.0030 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 550.00 650.00
0.05 Kg Sabun 11,000.00 13,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 9,025.00 10,670.00
E Overhead & Profit (contoh 10%) 10% 902.50 1,067.00
F Harga Satuan Pekerjaan (D+E) 9,927.50 11,737.00

3 A.4.7.1.3 1 m2 Pengerokan Karat Cat Lama permukaan Baja dg cara manual 10,340.00 12,232.00
A Tenaga 8,850.00 10,470.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.04 0.0080 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 550.00 650.00
0.05 Kg Sabun 11,000.00 13,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 9,400.00 11,120.00
E Overhead & Profit (contoh 10%) 10% 940.00 1,112.00
F Harga Satuan Pekerjaan (D+E) 10,340.00 12,232.00

4 A.4.7.1.4 1 m2 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) 37,416.50 43,384.00
A Tenaga 5,260.00 6,155.00

L.01 0.070 OH Pekerja 55,000.00 65,000.00 3,850.00 4,550.00

L.02 0.009 OH Tukang Cat 75,000.00 85,000.00 675.00 765.00

L.03 0.006 OH Kepala Tukang 85,000.00 95,000.00 510.00 570.00

L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00

B Bahan 28,755.00 33,285.00


0.2000 kg Cat Menie 25,000.00 30,000.00 5,000.00 6,000.00

0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00

0.1700 kg Cat Dasar 34,000.00 36,500.00 5,780.00 6,205.00

0.2600 kg Cat Penutup 50,000.00 58,000.00 13,000.00 15,080.00

0.0100 bh Kuas 7,500.00 8,000.00 75.00 80.00

0.0300 kg Pengencer 13,000.00 20,000.00 390.00 600.00

0.2000 lbr Amplas 3,800.00 4,100.00 760.00 820.00

C PERALATAN
D Jumlah A + B + C 34,015.00 39,440.00
E Overhead & Profit (contoh 10%) 10% 3,401.50 3,944.00
F Harga Satuan Pekerjaan (D+E) 37,416.50 43,384.00

5 A.4.7.1.5 1 m2 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penutup) 50,099.50 57,893.00
A Tenaga 12,290.00 14,125.00

L.01 0.070 OH Pekerja 55,000.00 65,000.00 3,850.00 4,550.00

L.02 0.105 OH Tukang Cat 75,000.00 85,000.00 7,875.00 8,925.00

L.03 0.004 OH Kepala Tukang 85,000.00 95,000.00 340.00 380.00

L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00

file:///conversion/tmp/scratch/443255086.xls 95/92 abk 14-14


HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 33,255.00 38,505.00
0.2000 kg Cat Menie 25,000.00 30,000.00 5,000.00 6,000.00

0.1500 kg Plamuur 25,000.00 30,000.00 3,750.00 4,500.00

0.1700 kg Cat Dasar 34,000.00 36,500.00 5,780.00 6,205.00

0.3500 kg Cat Penutup 50,000.00 58,000.00 17,500.00 20,300.00

0.0100 bh Kuas 7,500.00 8,000.00 75.00 80.00

0.0300 kg Pengencer 13,000.00 20,000.00 390.00 600.00

0.2000 lbr Amplas 3,800.00 4,100.00 760.00 820.00

C PERALATAN
D Jumlah A + B + C 45,545.00 52,630.00
E Overhead & Profit (contoh 10%) 10% 4,554.50 5,263.00
F Harga Satuan Pekerjaan (D+E) 50,099.50 57,893.00

6 A.4.7.1.6 1 m2 Pelaburan Bidang Kayu dg Teak Oil 29,991.50 32,263.00


A Tenaga 12,505.00 14,210.00
L.01 0.04 OH Pekerja 55,000.00 65,000.00 2,200.00 2,600.00
L.02 0.063 OH Tukang Cat 75,000.00 85,000.00 4,725.00 5,355.00
L.03 0.063 OH Kepala Tukang 85,000.00 95,000.00 5,355.00 5,985.00
L.04 0.0030 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 14,760.00 15,120.00
0.36 Ltr Teak Oil 41,000.00 42,000.00 14,760.00 15,120.00
C PERALATAN
D Jumlah A + B + C 27,265.00 29,330.00
E Overhead & Profit (contoh 10%) 10% 2,726.50 2,933.00
F Harga Satuan Pekerjaan (D+E) 29,991.50 32,263.00

7 A.4.7.1.7 1 m2 Pelaburan Bidang Kayu dg Politur 37,570.50 43,575.40


A Tenaga 8,285.00 9,490.00
L.01 0.04 OH Pekerja 55,000.00 65,000.00 2,200.00 2,600.00
L.02 0.06 OH Tukang Cat 75,000.00 85,000.00 4,500.00 5,100.00
L.03 0.016 OH Kepala Tukang 85,000.00 95,000.00 1,360.00 1,520.00
L.04 0.0030 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 25,870.00 30,124.00
0.15 Ltr Politur 35,000.00 42,000.00 5,250.00 6,300.00
0.372 Ltr Politur Jadi 35,000.00 42,000.00 13,020.00 15,624.00
2 Lbr Ampelas 3,800.00 4,100.00 7,600.00 8,200.00
C PERALATAN
D Jumlah A + B + C 34,155.00 39,614.00
E Overhead & Profit (contoh 10%) 10% 3,415.50 3,961.40
F Harga Satuan Pekerjaan (D+E) 37,570.50 43,575.40

8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 7,603.75 8,899.00
A Tenaga 5,950.00 7,040.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
B Bahan 962.50 1,050.00
0.35 Ltr Residu atau Ter 2,750.00 3,000.00 962.50 1,050.00
C PERALATAN
D Jumlah A + B + C 6,912.50 8,090.00
E Overhead & Profit (contoh 10%) 10% 691.25 809.00
F Harga Satuan Pekerjaan (D+E) 7,603.75 8,899.00

9 A.4.7.1.9 1 m2 Pelaburan Bidang Kayu dg Vernis 30,541.50 34,595.00


A Tenaga 22,385.00 25,790.00
L.01 0.16 OH Pekerja 55,000.00 65,000.00 8,800.00 10,400.00
L.02 0.16 OH Tukang Cat 75,000.00 85,000.00 12,000.00 13,600.00
L.03 0.016 OH Kepala Tukang 85,000.00 95,000.00 1,360.00 1,520.00
L.04 0.0030 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 5,380.00 5,660.00
0.15 Ltr Vernis 25,000.00 25,000.00 3,750.00 3,750.00
0.05 Ltr Dempul 25,000.00 30,000.00 1,250.00 1,500.00
0.1 Lbr Ampelas 3,800.00 4,100.00 380.00 410.00
- -
C PERALATAN
D Jumlah A + B + C 27,765.00 31,450.00
E Overhead & Profit (contoh 10%) 10% 2,776.50 3,145.00
F Harga Satuan Pekerjaan (D+E) 30,541.50 34,595.00
file:///conversion/tmp/scratch/443255086.xls 95/93 abk 14-14
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
10 A.4.7.1.10 1 m2 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar 16,484.05 19,451.85
2 lap. Cat Penutup)
A Tenaga 6,585.50 7,523.50
L.01 0.02 OH Pekerja 55,000.00 65,000.00 1,100.00 1,300.00
L.02 0.063 OH Tukang Cat 75,000.00 85,000.00 4,725.00 5,355.00
L.03 0.0063 OH Kepala Tukang 85,000.00 95,000.00 535.50 598.50
L.04 0.0030 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 8,400.00 10,160.00
0.1 Kg Plamir 20,000.00 32,000.00 2,000.00 3,200.00
0.1 Kg Cat Dasar 12,000.00 15,000.00 1,200.00 1,500.00
0.26 Kg Cat Penutup 2 kali 20,000.00 21,000.00 5,200.00 5,460.00
C PERALATAN
D Jumlah A + B + C 14,985.50 17,683.50
E Overhead & Profit (contoh 10%) 10% 1,498.55 1,768.35
F Harga Satuan Pekerjaan (D+E) 16,484.05 19,451.85

11 A.4.7.1.11 1 m2 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup) 11,343.20 12,802.90
A Tenaga 5,272.00 6,059.00
L.01 0.028 OH Pekerja 55,000.00 65,000.00 1,540.00 1,820.00
L.02 0.042 OH Tukang Cat 75,000.00 85,000.00 3,150.00 3,570.00
L.03 0.0042 OH Kepala Tukang 85,000.00 95,000.00 357.00 399.00
L.04 0.0030 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 5,040.00 5,580.00
0.12 Kg Cat Dasar 12,000.00 15,000.00 1,440.00 1,800.00
0.18 Kg Cat Penutup 2 kali 20,000.00 21,000.00 3,600.00 3,780.00
C PERALATAN
D Jumlah A + B + C 10,312.00 11,639.00
E Overhead & Profit (contoh 10%) 10% 1,031.20 1,163.90
F Harga Satuan Pekerjaan (D+E) 11,343.20 12,802.90

12 A.4.7.1.12 1 m2 Pengecatan Tembok dengan Kalkarium 6,261.20 7,214.90


A Tenaga 5,272.00 6,059.00
L.01 0.028 OH Pekerja 55,000.00 65,000.00 1,540.00 1,820.00
L.02 0.042 OH Tukang Cat 75,000.00 85,000.00 3,150.00 3,570.00
L.03 0.0042 OH Kepala Tukang 85,000.00 95,000.00 357.00 399.00
L.04 0.0030 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 420.00 500.00
0.1 Kg Kalkarium 4,200.00 5,000.00 420.00 500.00
- -
C PERALATAN
D Jumlah A + B + C 5,692.00 6,559.00
E Overhead & Profit (contoh 10%) 10% 569.20 655.90
F Harga Satuan Pekerjaan (D+E) 6,261.20 7,214.90

13 A.4.7.1.13 1 m2 Pelaburan Tembok dengan Kapur Sirih 11,372.35 13,397.45


A Tenaga 8,521.00 10,069.50
L.01 0.150 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.001 OH Tukang Cat 75,000.00 85,000.00 75.00 85.00
L.03 0.0001 OH Kepala Tukang 85,000.00 95,000.00 8.50 9.50
L.04 0.0025 OH Mandor 75,000.00 90,000.00 187.50 225.00
B Bahan 1,817.50 2,110.00
0.15 Kg Kapur Sirih 7,500.00 8,000.00 1,125.00 1,200.00
0.1 lbr Amplas 3,800.00 4,100.00 380.00 410.00
0.25 ikat Alang-alang 1,250.00 2,000.00 312.50 500.00
C PERALATAN
D Jumlah A + B + C 10,338.50 12,179.50
E Overhead & Profit (contoh 10%) 10% 1,033.85 1,217.95
F Harga Satuan Pekerjaan (D+E) 11,372.35 13,397.45

14 A.4.7.1.14 1 m2 Pelaburan Tembok lama dengan Kapur Sirih (pemeliharaan) 5,667.75 6,646.75
A Tenaga 2,805.00 3,297.50
L.01 0.040 OH Pekerja 55,000.00 65,000.00 2,200.00 2,600.00
L.02 0.005 OH Tukang Cat 75,000.00 85,000.00 375.00 425.00
L.03 0.0005 OH Kepala Tukang 85,000.00 95,000.00 42.50 47.50
L.04 0.0025 OH Mandor 75,000.00 90,000.00 187.50 225.00
file:///conversion/tmp/scratch/443255086.xls 95/94 abk 14-14
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 2,347.50 2,745.00
0.30 Kg Kapur Sirih 4,250.00 4,750.00 1,275.00 1,425.00
0.2 lbr Amplas 3,800.00 4,100.00 760.00 820.00
0.25 ikat Alang-alang 1,250.00 2,000.00 312.50 500.00
C PERALATAN
D Jumlah A + B + C 5,152.50 6,042.50
E Overhead & Profit (contoh 10%) 10% 515.25 604.25
F Harga Satuan Pekerjaan (D+E) 5,667.75 6,646.75

15 A.4.7.1.15 1 m2 Pemasangan Wallpaper 74,236.25 88,467.50


A Tenaga 17,987.50 20,425.00
L.01 0.020 OH Pekerja 55,000.00 65,000.00 1,100.00 1,300.00
L.02 0.200 OH Tukang Cat 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.0200 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.0025 OH Mandor 75,000.00 90,000.00 187.50 225.00
B Bahan 49,500.00 60,000.00
1.20 lbr Wall Paper 35,000.00 40,000.00 42,000.00 48,000.00
0.2 kg Lem 37,500.00 60,000.00 7,500.00 12,000.00

C PERALATAN
D Jumlah A + B + C 67,487.50 80,425.00
E Overhead & Profit (contoh 10%) 10% 6,748.75 8,042.50
F Harga Satuan Pekerjaan (D+E) 74,236.25 88,467.50

16 A.4.7.1.16 1 m2 Pengecatan Permukaan Baja dg Meni Besi 20,715.75 24,546.50


A Tenaga 16,457.50 18,715.00
L.01 0.02 OH Pekerja 55,000.00 65,000.00 1,100.00 1,300.00
L.02 0.2 OH Tukang Cat 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.002 OH Kepala Tukang 85,000.00 95,000.00 170.00 190.00
L.04 0.0025 OH Mandor 75,000.00 90,000.00 187.50 225.00
B Bahan 2,375.00 3,600.00
0.1 Kg Meni Besi 20,000.00 30,000.00 2,000.00 3,000.00
0.01 Kg Perekat / Lem 37,500.00 60,000.00 375.00 600.00
C PERALATAN
D Jumlah A + B + C 18,832.50 22,315.00
E Overhead & Profit (contoh 10%) 10% 1,883.25 2,231.50
F Harga Satuan Pekerjaan (D+E) 20,715.75 24,546.50

17 A.4.7.1.17 1 m2 Pengecatan Permukaan Baja dg Meni Besi & Perancah 43,422.50 50,586.25
A Tenaga 33,100.00 38,187.50
L.01 0.25 OH Pekerja 55,000.00 65,000.00 13,750.00 16,250.00
L.02 0.225 OH Tukang Cat 75,000.00 85,000.00 16,875.00 19,125.00
L.03 0.0225 OH Kepala Tukang 85,000.00 95,000.00 1,912.50 2,137.50
L.04 0.0075 OH Mandor 75,000.00 90,000.00 562.50 675.00
B Bahan 6,375.00 7,800.00
0.1 Kg Meni Besi 20,000.00 30,000.00 2,000.00 3,000.00
0.01 Kg Perekat / Lem 37,500.00 60,000.00 375.00 600.00
0.002 m3 Perancah Kayu 2,000,000.00 2,100,000.00 4,000.00 4,200.00
C PERALATAN
D Jumlah A + B + C 39,475.00 45,987.50
E Overhead & Profit (contoh 10%) 10% 3,947.50 4,598.75
F Harga Satuan Pekerjaan (D+E) 43,422.50 50,586.25

file:///conversion/tmp/scratch/443255086.xls 95/95 abk 14-14

You might also like