Professional Documents
Culture Documents
HSPK Gedung NOV 2015
HSPK Gedung NOV 2015
HARGA
NO. PERALATAN SATUAN MINIMUM MAKSIMUM
(Rp) (Rp)
KET.
DAFTAR U PAH PE K E R JA
HARGA
NO. URAIAN PEKERJA SATUAN MINIMUM MAKSIMUM KET.
(Rp) (Rp)
1 Pekerja Hr 55,000 65,000
10 T u k a n g c a t Hr 75,000 85,000
11 K e p . t k . c a t Hr 85,000 95,000
12 T u k a n g p l i t u r Hr 75,000 85,000
13 T u k a n g j a l a n Hr 60,000 65,000
14 T u k a n g g a l i Hr 60,000 65,000
16 T k . l e i d e n g Hr 75,000 85,000
17 M a s i n i s Hr 150,000 175,000
18 P e m b . M a s i n i s Hr 100,000 110,000
19 P e n j a g a a p i Hr 50,000 65,000
20 P e n j a g a m a l a m Hr 60,000 65,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
I BAHAN DASAR
1 BATU KALI Bulat Utuh m3 160,000 170,000
Bulat Belah m3 180,000 190,000
Pecah 10/15 m3 200,000 210,000
Pecah 5/7 m3 210,000 230,000
Pecah 3/5 m3 230,000 250,000
2 KERIKIL Timbun m3 120,000 130,000
Sawur / Koral m3 240,000 260,000
Beton 0,5/1 m3 260,000 300,000
Beton ,1/2 m3 280,000 310,000
Beton ,2/3 m3 280,000 325,000
Biasa m3 125,000 140,000
Tras Giling m3 215,000 290,000
3 BATU BATA ex lokal bh 450 500
4 UBIN PORSELIN
Lokal 11 X 11 putih dos 42,000 43,000
11 X 11 warna dos 45,000 46,000
Lokal 15 X 15 putih dos 45,000 47,500
15 X 15 warna dos 46,000 49,000
5 MOZAIK PORSELIN
10 X 20 cm m2 48,000 52,000
15 X 15 cm m2 48,000 52,000
20 X 20 cm m2 48,000 55,000
20 X 25 cm m2 49,000 56,000
VII . B A H A N P I P A
1 Pipa PVC SII SCJ , S - 12,5 (10 bar)
Pipa PVC DN 20 ( ½" ) AW JIS btg 26,000 35,000 panjang 4 m
Pipa PVC DN 25 ( ¾" ) AW JIS btg 32,000 40,000 panjang 4 m
Pipa PVC DN 32 ( 1" ) AW JIS btg 44,000 50,000 panjang 4 m
Pipa PVC DN 40 ( 1½" ) btg 60,000 69,000 panjang 6 m
Pipa PVC DN 63 ( 2" ) btg 95,000 112,000 panjang 6 m
Pipa PVC DN 90 ( 3" ) btg 210,000 260,000 panjang 6 m
Pipa PVC DN 110 ( 4" ) btg 300,000 325,000 panjang 6 m
Pipa PVC DN 160 ( 6" ) btg 625,000 650,000 panjang 6 m
Pipa PVC DN 200 ( 8" ) btg 950,000 1,100,000 panjang 6 m
Pipa PVC DN 250 ( 10" ) btg 1,400,000 1,500,000 panjang 6 m
Pipa PVC DN 315 ( 12" ) btg 2,050,000 2,100,000 panjang 6 m
VIII . B A H A N L A N G I T - L A N G I T
1 AKUSTIK-uk : 30 X 30 lbr 5,500 5,800
30 X 60 lbr 13,000 13,200
60 X 120 lbr 41,000 42,000
List Kayu Profil m' 4,800 5,000
2 SOFT BOARD-uk: 4'X 8'
Gypsum tebal 9 mm lbr 62,000 68,000
3 HARD BOARD-uk: 4'X 8' lbr 68,000 72,000
GYPROC uk.120cmx240cmx9mm lbr 57,500
4 PLY WOOD
Teak wood
90 X 210 X 3 mm lbr 50,000 65,000
. 120 X 240 X 3 mm lbr 90,000 95,000
. 90 X 210 X 4 mm lbr 65,000 70,000
. 90 X 210 X 9 mm lbr 115,000 125,000
. 90 X 210 X 12 mm lbr 160,000 180,000
. 90 X 210 X 15 mm lbr 225,000 240,000
. 90 X 210 X 18 mm lbr 295,000 310,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
Tripleks
. 120 X 240 X 3 mm lbr 50,000 55,000
. 120 X 240 X 4 mm lbr 62,000 70,000
. 120 X 240 X 6 mm lbr 75,000 80,000
Multipleks
. 120 X 240 X 9 mm lbr 125,000 160,000
. 120 X 240 X 12 mm lbr 145,000 180,000
. 120 X 240 X 15 mm lbr 185,000 280,000
. 120 X 240 X 18 mm lbr 210,000 310,000
Formika ukuran pintu lbr 68,000 75,000
IX . B A H A N F I N I S H I N G
1 KAYU
Menie kg 25,000 30,000
Dempul plamur kg 25,000 30,000
Ambril/amplas lbr 3,800 4,100
Batu Apung kg 29,000 31,000
Cat dasar kg 34,000 36,500
. Emco kg 51,000 55,000
. Yunior 66 (nippon paint) kg 50,000 58,000
- Koas bh 7,500 8,000
. Deculux kg 55,000 58,000
. Siralax ons 10,000 18,000
. Spiritus ltr 11,000 13,500
. Plitur jadi ltr 35,000 42,000
2 TEMBOK
Kalkarium kg 4,200 5,000
Kapur sirih kg 4,250 4,750
Plamur kg 20,000 32,000
Cat Tembok kg 20,000 21,000
Sintex 5 kg 100,000 105,000
Danabride 5 kg 100,000 110,000
Catylac 5 kg 105,000 120,000
Mowilex 5 kg 275,000 300,000
3 BESI
Menie kg 20,000 30,000
Cat mengkilat kg 35,000 58,000
Cat kg 36,000 42,500
Thinner A ltr 15,000 16,000
Minyak cat ltr 13,000 20,000
Thinner Super ltr 12,000 25,000
Residu (teer/aspal) drum 55,000 60,000
Fibre glass (tanki air)
kapasitas 550 liter. bh 875,000 1,250,000
kapasitas 1100 liter. bh 1,650,000 1,700,000
Lem Aica Aibon kg 37,500 60,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
X.BAHAN KACA
1 POLOS 3 mm m2 60,000 65,000
5 mm m2 70,000 76,000
2 ES KABUR 3 mm m2 70,000 75,000
5 mm m2 80,000 88,000
3 RAY BAND 3 mm m2 70,000 75,000
5 mm m2 80,000 85,000
1 KABEL LISTRIK
NYA : . 1 X 1 1/2 mm2 m' 3,100 3,300
SPLN LMK 1 X 2 1/2 mm2 m' 3,700 3,900
. 1X4 mm2 m' 5,700 6,000
1X6 mm2 m' 8,500 8,900
NYY :. 2 X 1 1/2 mm2 m' 9,000 9,450
PRIMA 2 X 2 1/2 mm2 m' 15,000 15,500
. 2X4 mm2 m' 27,000 28,000
2X6 mm2 m' 35,000 37,000
3 X 1 1/2 mm2 m' 13,200 14,000
3 X 2 1/2 mm2 m' 20,000 21,000
3X4 mm2 m' 34,500 36,500
3X6 mm2 m' 50,000 53,000
NYM :. 2 X 1 1/2 mm2 m' 7,000 8,000
PRIMA 2 X 2 1/2 mm2 m' 10,900 11,500
. 2X4 mm2 m' 21,000 23,000
3 X 1 1/2 mm2 m' 12,500 14,000
3 X 2 1/2 mm2 m' 19,000 22,000
3X4 mm2 m' 30,000 35,000
3X6 mm2 m' 43,000 48,000
2 SKAKELAR
Out bauw . Seri bh 15,000 21,000
. Engkel bh 12,000 15,000
In bauw . Seri bh 11,500 16,500
. Engkel bh 9,500 12,000
XV . POMPA AIR.
1 POMPA AIR TANGAN
Dragon buatan Indonesia bh 275,000 310,000
2 POMPA AIR LISTRIK
Sanyo 100 watt bh 975,000 1,050,000
Fuji 250 watt bh 1,450,000 1,500,000
Shimizu . 100 watt bh 450,000 510,000
. 90 watt bh 350,000 380,000
Dab . 125 watt bh 350,000 400,000
. 175 watt bh 425,000 450,000
X VI . PAVING BLOCK
1 SQUARE Abu-abu m2 50,000 65,000
Merah/hitam m2 52,500 70,000
2 HOLLAND Abu-abu m2 50,000 65,000
Merah/hitam m2 52,500 70,000
3 UNIDECOR Abu-abu m2 42,000 55,000
Merah/hitam m2 52,500 70,000
4 UNI Abu-abu m2 50,000 65,000
Merah/hitam m2 52,500 70,000
5 TRIHEX Abu-abu m2 50,000 65,000
Merah/hitam m2 52,500 70,000
6 OLYMPIA HEXA Abu-abu m2 50,000 65,000
7 HEXAGONAL Abu-abu m2 52,500 70,000
Merah/hitam m2 50,000 65,000
8 CASTLE Abu-abu m2 52,500 70,000
9 TRAPEZ Abu-abu m2 50,000 65,000
10 TRAPEZ GRASS BLOCK
Abu-abu m2 50,000 65,000
11 STANDARD GRASS BLOCK ABU-ABU BH 7,500 8,500
12 BATACO BH 3,500 4,250
13 KANSTEEN m' 15,000 27,000
HARGA
NO. J E N I S B A H A N SAT MINIMUM MAKSIMUM KET
(Rp) (Rp)
XVII. L A I N - L A I N
1 KREI 25 MM m2 45,000 50,000
2 Sliding Pintu J4 bh 180,000 235,000
3 Naco per Daun bh 12,000 12,500
4 Rolling door Besi m2 300,000 325,000
Rolling door Almunium m2 230,000 275,000
5 Awning Almunium m2 210,000 225,000
6 Kusen Almunium 4" Putih m' 80,000 85,000
7 WIDE FLANGE BEAM
150 X 75 X 5 X 7 X 12 btg 1,500,000 1,550,000
8 ASPAL.
Aspal Ex Pertamina isi Net 160 kg drum 1,650,000 1,700,000
1 A.2.2.1.2 Pagar Sementara dari Seng Gelombang Tinggi 2,00 m m' 535,617.50 622,627.50
13 A.2.3.1.13 Pemasangan Lapisan Ijuk tebal 10 cm unt Bidang Resapan m2 56,512.50 78,210.00
6 A.3.2.1.6 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP m3 593,450.00 663,382.50
10 A.3.2.1.10 Pasang Pondasi Siklop, 60% Beton Camp. 1PC : 2PB : 3KR & 40% Batu Belah m3 2,188,081.50 2,414,769.50
1 A.4.4.1.1 Pemasangan Dinding Bata Merah ukuran (5x11x22) cm Tebal 1 bata Camp. 1SP: 2PP m2 206,057.50 229,625.00
2 A.4.4.1.2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3PP m2 194,273.75 217,805.50
3 A.4.4.1.3 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP m2 185,968.75 209,247.50
4 A.4.4.1.4 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP m2 182,215.00 205,700.00
5 A.4.4.1.5 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 6PP m2 182,077.50 206,349.00
7 A.4.4.1.7 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP m2 98,683.75 110,214.50
8 A.4.4.1.8 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP m2 92,881.25 104,259.10
9 A.4.4.1.9 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 4PP m2 89,677.50 101,046.00
10 A.4.4.1.10 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP m2 87,670.00 99,037.40
11 A.4.4.1.11 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP m2 86,790.00 98,280.60
12 A.4.4.1.12 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP m2 84,535.00 95,975.00
13 A.4.4.1.13 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3KP : 10PP m2 85,910.00 98,230.00
14 A.4.4.1.14 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1SM : 1PP m2 76,092.50 86,977.00
15 A.4.4.1.15 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1KP : 1SM : 2PP m2 87,769.00 87,769.00
16 A.4.4.1.20 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP m2 190,558.50 224,788.30
17 A.4.4.1.21 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP m2 192,332.25 227,583.40
18 A.4.4.1.22 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 2PP m2 240,542.50 310,354.00
19 A.4.4.1.23 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP m2 237,160.00 306,955.00
22 A,4,4,2.24 Pemasangan Finishing Siar Pasangan Dinding Bata Merah (=20 m') m2 20,944.00 23,809.94
23 A,4,4,2.25 Pemasangan Finishing Siar Pasangan Dinding Conblock ekspose (=8 m') m2 10,026.50 11,379.50
24 A,4,4,2.26 Pemasangan Finishing Siar Pas.Batu Kali Adukan 1Pc : 2Pp m2 44,852.50 51,157.70
1 A.4.6.1.1 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas I m3 26,618,900.00 27,565,725.00
2 A.4.6.1.2 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas II atau III m3 11,186,725.00 12,272,425.00
3 A.4.6.1.3 Pembuatan & Pemasangan Pintu KlampStandard Kayu Klas II (Kayu Kamfer) m2 454,217.50 479,979.50
4 A.4.6.1.4 Pembuatan & Pemasangan Daun Pintu Klamp Sederhana Kayu Klas III m2 454,217.50 479,979.50
5 A.4.6.1.5 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II m2 675,565.00 732,600.00
6 A.4.6.1.6 Pembuatan & Pemasangan Pintu & Jendela Kaca Kayu Klas I atau II m2 478,720.00 523,160.00
7 A.4.6.1.7 Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu Klas I atau II (jati) m2 1,898,875.00 2,018,500.00
9 A.4.6.1.9 Pembuatan&Pemasangan Pintu Plywood rangkap, rangka expose kayu klas I atau II m2 567,985.00 618,783.00
10 A.4.6.1.10 Pembuatan & Pemasangan Jalusi mati Kosen Kayu Klas I atau II m2 1,706,017.50 1,809,445.00
11 A.4.6.1.11 Pembuatan & Pemasangan Pintu Teakwood Rangkap, Rangka Expose Kayu Klas I m2 955,009.00 1,027,235.00
12 A.4.6.1.12 Pembuatan&Pemasangan Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II m2 609,103.00 665,109.50
13 A.4.6.1.13 Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 meter m3 9,996,030.00 10,943,350.00
16 A.4.6.1.16 Pemasangan Rangka Atap Genteng Keramik, Kayu Klas II m2 152,806.50 167,365.00
17 A.4.6.1.17 Pemasangan Rangka Atap Genteng Beton, Kayu Klas II m2 180,130.50 197,065.00
19 A.4.6.1.19 Pemasangan Rangka Langit-langit (50x1,00) m, kayu Klas II atau III m2 162,563.50 179,685.00
20 A.4.6.1.20 Pemasangan Rangka Langit-langit (60x60) cm, kayu Klas II atau III m2 167,772.00 185,075.00
21 A.4.6.1.21 Pemasangan Listplank Uk. (3x20)cm Kayu klas I atau II m' 287,622.50 303,325.00
22 A.4.6.1.22 Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau klas II m' 117,507.50 123,640.00
23 A.4.6.1.23 Pemasangan Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III m2 265,732.50 291,769.50
24 A.4.6.1.24 Pemasangan Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II m2 338,310.50 370,309.50
25 A.4.6.1.25 Pemasangan Dinding Pemisah Plywood Rangkap Rangka Kayu Klas II m2 344,388.00 376,805.00
27 A.4.6.1.27 Pemasangan Dinding Lambriziring dari Plywood ukuran (120x240) cm m2 36,525.50 41,360.00
28 A.4.6.1.28 Pemasangan Dinding Bilik, Rangka Kayu Klas III atau IV m2 118,162.44 128,722.00
1 A.4.1.1.1 Membuat Beton mutu f'c=7,4 Mpa (K100), slum (12±2)cm, w/c = 0,87 m3 920,970.68 1,015,113.00
2 A.4.1.1.2 Membuat Beton mutu f'c=9,8 Mpa (K125), slum (12±2)cm, w/c = 0,78 m3 953,503.03 1,048,750.59
3 A.4.1.1.3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72 m3 978,977.35 1,074,989.67
4 A.4.1.1.4 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 m3 869,298.86 956,923.81
5 A.4.1.1.5 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 m3 1,009,034.41 1,106,052.44
6 A.4.1.1.6 Membuat Beton mutu f'c=16,9 MPa (K200), slum (12±2)cm, w/c = 0,61 m3 1,037,949.28 1,135,787.07
7 A.4.1.1.7 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 m3 1,059,427.50 1,158,119.11
8 A.4.1.1.8 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 m3 1,073,968.75 1,172,940.59
9 A.4.1.1.9 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53 m3 1,099,241.39 1,198,758.00
10 A.4.1.1.10 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 m3 1,106,971.37 1,206,618.93
11 A.4.1.1.11 Membuat Beton mutu f'c=28,8 MPa (K325), slum (12±2)cm, w/c = 0,49 m3 1,172,415.43 1,278,898.70
12 A.4.1.1.12 Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm, w/c = 0,48 m3 1,182,667.26 1,289,354.81
24 A.4.1.1.28 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) m3 3,632,304.50 4,007,069.00
25 A.4.1.1.29 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) m3 4,434,710.50 4,889,423.00
26 A.4.1.1.30 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) m3 7,716,725.50 8,639,103.00
28 A.4.1.1.32 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting) m3 5,584,975.00 6,255,232.50
29 A.4.1.1.33 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting) m3 5,461,494.50 6,138,319.00
30 A.4.1.1.34 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) m3 5,586,300.50 6,255,348.00
31 A.4.1.1.35 Membuat Kolom Penguat Beton Bertulang (11 x 11) cm m' 64,138.25 71,497.25
32 A.4.1.1.36 Membuat Ring Balok Beton Bertulang (10 x 15) cm m' 88,962.50 99,462.00
1 A.4.5.1.1 Pemasangan Langit-langit Asbes (1,00x1,00) m, tebal 4 mm, 5 mm & 6 mm m2 28,077.50 30,552.50
8 A.4.5.1.9 Memasang Langit-langit Akuatik Uk (60x120) cm & Rangka Allumunium m2 185,652.50 201,905.00
7 A.5.1.1.8 Memasang Bak Mandi Batu Bata Vol. 0,30 m3 Unit 1,256,354.27 1,413,478.54
8 A.5.1.1.12 Pemasangan Bak Cuci Piring Stainless stell buah 333,107.50 375,815.00
10 A.5.1.1.15 Pemasangan Bak Kontrol Pas.Batu Bata 30x30 tinggi 35 cm bh 342,809.50 388,443.00
12 A.5.1.1.17 Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm bh 621,181.00 698,874.00
27 A.5.1.1.33 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm m' 79,882.00 87,912.00
28 A.5.1.1.34 Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm m' 34,732.50 39,825.50
4 A.4.2.1.4 Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku m2 829,317.50 903,875.50
17 A.4.2.1.18 Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm m' 164,967.00 191,015.00
18 A.4.2.1.19 Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm m' 60,478.00 79,167.00
19 A.4.2.1.20 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 60x120 cm dinding partisi m2 154,660.00 179,899.50
20 A.4.2.1.21 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 60x60 cm dinding plafond m2 186,807.50 217,189.50
13 A.4.4.3.37 Pemasangan Lantai Keramik uk.10 x 33 cm, untuk variasi / border m2 392,898.00 435,831.00
25 A.4.4.3.58 Pemasangan Dinding Batu Paros / Batu Tempel Hitam m2 217,153.75 240,515.00
27 A.4.4.3.63 Pemasangan Plint Kayu Klas II Ukuran 2x10 cm m' 36,762.00 43,978.00
2 A.4.7.1.2 Pencucian Bidang Permukaan Tembok yang Pernah dicat m2 9,927.50 11,737.00
3 A.4.7.1.3 Pengerokan Karat Cat Lama permukaan Baja dg cara manual m2 10,340.00 12,232.00
4 A.4.7.1.4 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) m2 37,416.50 43,384.00
5 A.4.7.1.5 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penutup) m2 50,099.50 57,893.00
10 A.4.7.1.10 Pengecat Tembok Baru (1lap.Plamir, 1lap Cat Dasar m2 16,484.05 19,451.85
11 A.4.7.1.11 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup) m2 11,343.20 12,802.90
14 A.4.7.1.14 Pelaburan Tembok lama dengan Kapur Sirih (pemeliharaan) m2 5,667.75 6,646.75
17 A.4.7.1.17 Pengecatan Permukaan Baja dg Meni Besi & Perancah m2 43,422.50 50,586.25
13 A.2.3.1.13 1 m2 Pemasangan Lapisan Ijuk tebal 10 cm unt Bidang Resapan 56,512.50 78,210.00
A TENAGA 9,375.00 11,100.00
0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B BAHAN 42,000.00 60,000.00
6.00 kg Ijuk 7,000.00 10,000.00 42,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 51,375.00 71,100.00
E Overhead & Profit (contah 10%) 10% 5,137.50 7,110.00
F Harga Satuan Pekerjaan (D+E) 56,512.50 78,210.00
6 A.3.2.1.6 1 m3 Pemasangan Pondasi Batu Belah 1SP : 1KP : 2PP 593,450.00 663,382.50
A Tenaga 150,750.00 175,125.00
L.01 1.5 OH Pekerja 55,000.00 65,000.00 82,500.00 97,500.00
L.02 0.750 OH Tukang Batu 75,000.00 85,000.00 56,250.00 63,750.00
L.03 0.075 OH Kepala Tukang 85,000.00 95,000.00 6,375.00 7,125.00
L.04 0.075 OH Mandor 75,000.00 90,000.00 5,625.00 6,750.00
B Bahan 388,750.00 427,950.00
1.2 m3 Batu Belah 15/20 200,000.00 210,000.00 240,000.00 252,000.00
0.17 m3 Kapur Pasang (KP) 250,000.00 310,000.00 42,500.00 52,700.00
0.17 Kg Semen Merah (SM) 175,000.00 185,000.00 29,750.00 31,450.00
0.340 m3 Pasir Pasang 225,000.00 270,000.00 76,500.00 91,800.00
C PERALATAN
D Jumlah A + B + C 539,500.00 603,075.00
E Overhead & Profit (contoh 10%) 10% 53,950.00 60,307.50
F Harga Satuan Pekerjaan (D+E) 593,450.00 663,382.50
3 A.4.4.1.3 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 4PP 185,968.75 209,247.50
A Tenaga 51,950.00 60,600.00
L.01 0.6 OH Pekerja 55,000.00 65,000.00 33,000.00 39,000.00
L.02 0.2 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang Batu 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 117,112.50 129,625.00
140 Buah Bata Merah 450.00 500.00 63,000.00 70,000.00
26.55 Kg Portland Semen (PC) 1,250.00 1,300.00 33,187.50 34,515.00
0.093 m3 Pasir Pasang (PP) 225,000.00 270,000.00 20,925.00 25,110.00
C PERALATAN
D Jumlah A + B + C 169,062.50 190,225.00
E Overhead & Profit (contoh 10%) 10% 16,906.25 19,022.50
F Harga Satuan Pekerjaan (D+E) 185,968.75 209,247.50
4 A.4.4.1.4 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 5PP 182,215.00 205,700.00
A Tenaga 51,950.00 60,600.00
L.01 0.6 OH Pekerja 55,000.00 65,000.00 33,000.00 39,000.00
L.02 0.2 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang Batu 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 113,700.00 126,400.00
140 Buah Bata Merah 450.00 500.00 63,000.00 70,000.00
22.2 Kg Portland Semen (PC) 1,250.00 1,300.00 27,750.00 28,860.00
0.102 m3 Pasir Pasang (PP) 225,000.00 270,000.00 22,950.00 27,540.00
C PERALATAN
D Jumlah A + B + C 165,650.00 187,000.00
E Overhead & Profit (contoh 10%) 10% 16,565.00 18,700.00
F Harga Satuan Pekerjaan (D+E) 182,215.00 205,700.00
6 A.4.4.1.6 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22) cm Tebal 1 Bata Camp. 1SP : 3 KP :10PP 170,761.25 194,924.40
A Tenaga 51,950.00 60,600.00
L.01 0.6 OH Pekerja 55,000.00 65,000.00 33,000.00 39,000.00
L.02 0.2 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang Batu 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 103,287.50 116,604.00
140 Buah Bata Merah 450.00 500.00 63,000.00 70,000.00
10.08 Kg Portland Semen (PC) 1,250.00 1,300.00 12,600.00 13,104.00
0.0925 m3 Pasir Pasang (PP) 225,000.00 270,000.00 20,812.50 24,975.00
0.0275 m3 Kapur Pasang (KP) 250,000.00 310,000.00 6,875.00 8,525.00
C PERALATAN
D Jumlah A + B + C 155,237.50 177,204.00
E Overhead & Profit (contoh 10%) 10% 15,523.75 17,720.40
F Harga Satuan Pekerjaan (D+E) 170,761.25 194,924.40
7 A.4.4.1.7 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 2PP 98,683.75 110,214.50
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 63,737.50 69,895.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
18.95 Kg Portland Semen 1,250.00 1,300.00 23,687.50 24,635.00
0.038 m3 Pasir Pasang 225,000.00 270,000.00 8,550.00 10,260.00
C PERALATAN
D Jumlah A + B + C 89,712.50 100,195.00
E Overhead & Profit (contoh 10%) 10% 8,971.25 10,019.50
F Harga Satuan Pekerjaan (D+E) 98,683.75 110,214.50
8 A.4.4.1.8 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 3PP 92,881.25 104,259.10
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 58,462.50 64,481.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
14.37 Kg Portland Semen 1,250.00 1,300.00 17,962.50 18,681.00
0.04 m3 Pasir Pasang 225,000.00 270,000.00 9,000.00 10,800.00
C PERALATAN
D Jumlah A + B + C 84,437.50 94,781.00
E Overhead & Profit (contoh 10%) 10% 8,443.75 9,478.10
F Harga Satuan Pekerjaan (D+E) 92,881.25 104,259.10
10 A.4.4.1.10 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 5PP 87,670.00 99,037.40
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 53,725.00 59,734.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
9.68 Kg Portland Semen 1,250.00 1,300.00 12,100.00 12,584.00
0.045 m3 Pasir Pasang 225,000.00 270,000.00 10,125.00 12,150.00
C PERALATAN
D Jumlah A + B + C 79,700.00 90,034.00
E Overhead & Profit (contoh 10%) 10% 7,970.00 9,003.40
F Harga Satuan Pekerjaan (D+E) 87,670.00 99,037.40
11 A.4.4.1.11 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 6PP 86,790.00 98,280.60
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 52,925.00 59,046.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
8.32 Kg Portland Semen 1,250.00 1,300.00 10,400.00 10,816.00
0.049 m3 Pasir Pasang 225,000.00 270,000.00 11,025.00 13,230.00
C PERALATAN
D Jumlah A + B + C 78,900.00 89,346.00
E Overhead & Profit (contoh 10%) 10% 7,890.00 8,934.60
F Harga Satuan Pekerjaan (D+E) 86,790.00 98,280.60
12 A.4.4.1.12 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 8PP 84,535.00 95,975.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 50,875.00 56,950.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
6.50 Kg Portland Semen 1,250.00 1,300.00 8,125.00 8,450.00
0.05 m3 Pasir Pasang 225,000.00 270,000.00 11,250.00 13,500.00
C PERALATAN
D Jumlah A + B + C 76,850.00 87,250.00
E Overhead & Profit (contoh 10%) 10% 7,685.00 8,725.00
F Harga Satuan Pekerjaan (D+E) 84,535.00 95,975.00
14 A.4.4.1.14 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1SP : 1SM : 1PP 76,092.50 86,977.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 43,200.00 48,770.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
0.018 m3 Semen Merah 175,000.00 185,000.00 3,150.00 3,330.00
0.018 m3 Pasir Pasang 225,000.00 270,000.00 4,050.00 4,860.00
0.018 m3 Kapur Padam 250,000.00 310,000.00 4,500.00 5,580.00
C PERALATAN
D Jumlah A + B + C 69,175.00 79,070.00
E Overhead & Profit (contoh 10%) 10% 6,917.50 7,907.00
F Harga Satuan Pekerjaan (D+E) 76,092.50 86,977.00
15 A.4.4.1.15 1 m2 Pemasangan Dinding Bata Merah Ukuran (5x11x22)cm Tebal 1/2 Bata Camp. 1KP : 1SM : 2PP 76,697.50 87,769.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 43,750.00 49,490.00
70 Buah Bata Merah 5 x 11 x 22 450.00 500.00 31,500.00 35,000.00
0.014 m3 Semen Merah 175,000.00 185,000.00 2,450.00 2,590.00
0.028 m3 Pasir Pasang 225,000.00 270,000.00 6,300.00 7,560.00
0.014 m3 Kapur Padam 250,000.00 310,000.00 3,500.00 4,340.00
C PERALATAN
D Jumlah A + B + C 69,725.00 79,790.00
E Overhead & Profit (contoh 10%) 10% 6,972.50 7,979.00
F Harga Satuan Pekerjaan (D+E) 76,697.50 87,769.00
16 A.4.4.1.20 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 3PP 190,558.50 224,788.30
A Tenaga 25,975.00 30,300.00
L.01 0.300 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.100 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.010 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 147,260.00 174,053.00
12.500 buah Batako 3,500.00 4,250.00 43,750.00 53,125.00
15.160 kg PC 1,250.00 1,300.00 18,950.00 19,708.00
0.364 m3 Pasir Pasang 225,000.00 270,000.00 81,900.00 98,280.00
0.280 kg Besi Angkur Ø 8 mm 9,500.00 10,500.00 2,660.00 2,940.00
17 A.4.4.1.21 1 m2 Pemasangan Dinding HB/CB 10, speci camp. 1SP : 4PP 192,332.25 227,583.40
A Tenaga 25,975.00 30,300.00
L.01 0.300 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.100 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.010 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
18 A.4.4.1.22 1 m2 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 2PP 240,542.50 310,354.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 192,700.00 251,840.00
30 Buah Terawang / Roster 5,600.00 7,500.00 168,000.00 225,000.00
14 kg Portland Semen 1,250.00 1,300.00 17,500.00 18,200.00
0.032 m3 Pasir Pasang 225,000.00 270,000.00 7,200.00 8,640.00
C PERALATAN
D Jumlah A + B + C 218,675.00 282,140.00
E Overhead & Profit (contoh 10%) 10% 21,867.50 28,214.00
F Harga Satuan Pekerjaan (D+E) 240,542.50 310,354.00
19 A.4.4.1.23 1 m2 Pemasangan Dinding Terawang (Rooster) Uk, (12x11x24)cm Camp. 1SP : 4PP 237,160.00 306,955.00
A Tenaga 25,975.00 30,300.00
L.01 0.30 OH Pekerja 55,000.00 65,000.00 16,500.00 19,500.00
L.02 0.1 OH Tukang Batu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 189,625.00 248,750.00
30 Buah Terawang / Roster 5,600.00 7,500.00 168,000.00 225,000.00
11 kg Portland Semen 1,250.00 1,300.00 13,750.00 14,300.00
0.035 m3 Pasir Pasang 225,000.00 270,000.00 7,875.00 9,450.00
C PERALATAN
D Jumlah A + B + C 215,600.00 279,050.00
E Overhead & Profit (contoh 10%) 10% 21,560.00 27,905.00
F Harga Satuan Pekerjaan (D+E) 237,160.00 306,955.00
2 A.4.6.1.2 1 m3 Pembuatan & Pemasangan Kosen Pintu & Jendela Kayu klas II atau III 11,186,725.00 12,272,425.00
Tenaga 1,855,500.00 2,118,000.00
L.01 6.00 OH Pekerja 55,000.00 65,000.00 330,000.00 390,000.00
L.02 18.00 OH Tukang Kayu 75,000.00 85,000.00 1,350,000.00 1,530,000.00
L.03 1.80 OH Kepala Tukang 85,000.00 95,000.00 153,000.00 171,000.00
L.04 0.30 OH Mandor 75,000.00 90,000.00 22,500.00 27,000.00
Bahan 8,314,250.00 9,038,750.00
1.2 m3 Kayu Klas II (Kamfer) , Balok 6,900,000.00 7,500,000.00 8,280,000.00 9,000,000.00
1.25 kg Paku Biasa 2" - 5 " 13,000.00 15,000.00 16,250.00 18,750.00
1 kg Lem Kayu 18,000.00 20,000.00 18,000.00 20,000.00
C PERALATAN
D Jumlah A + B + C 10,169,750.00 11,156,750.00
E Overhead & Profit (contoh 10%) 10% 1,016,975.00 1,115,675.00
F Harga Satuan Pekerjaan (D+E) 11,186,725.00 12,272,425.00
3 A.4.6.1.3 1 m2 Pembuatan & Pemasangan Pintu KlampStandard Kayu Klas II (Kayu Kamfer) 454,217.50 479,979.50
A Tenaga 108,275.00 123,595.00
L.01 0.35 OH Pekerja 55,000.00 65,000.00 19,250.00 22,750.00
L.02 1.05 OH Tukang Kayu 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.105 OH Kepala Tukang 85,000.00 95,000.00 8,925.00 9,975.00
L.04 0.018 OH Mandor 75,000.00 90,000.00 1,350.00 1,620.00
B Bahan 304,650.00 312,750.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 304,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 412,925.00 436,345.00
E Overhead & Profit (contoh 10%) 10% 41,292.50 43,634.50
F Harga Satuan Pekerjaan (D+E) 454,217.50 479,979.50
4 A.4.6.1.4 1 m2 Pembuatan & Pemasangan Daun Pintu Klamp Sederhana Kayu Klas III 454,217.50 479,979.50
Tenaga 108,275.00 123,595.00
L.01 0.35 OH Pekerja 55,000.00 65,000.00 19,250.00 22,750.00
L.02 1.05 OH Tukang Kayu 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.105 OH Kepala Tukang 85,000.00 95,000.00 8,925.00 9,975.00
L.04 0.018 OH Mandor 75,000.00 90,000.00 1,350.00 1,620.00
Bahan 304,650.00 312,750.00
0.040 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 304,000.00 312,000.00
0.05 Kg Paku Biasa 2" - 5 " 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 412,925.00 436,345.00
E Overhead & Profit (contoh 10%) 10% 41,292.50 43,634.50
F Harga Satuan Pekerjaan (D+E) 454,217.50 479,979.50
5 A.4.6.1.5 1 m2 Pembuatan & Pemasangan Daun Pintu Panel, Kayu Klas I atau II 675,565.00 732,600.00
A Tenaga 309,250.00 353,000.00
L.01 1.00 OH Pekerja 55,000.00 65,000.00 55,000.00 65,000.00
L.02 3.00 OH Tukang Kayu 75,000.00 85,000.00 225,000.00 255,000.00
L.03 0.30 OH Kepala Tukang 85,000.00 95,000.00 25,500.00 28,500.00
L.04 0.05 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00
B Bahan 304,900.00 313,000.00
0.04 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 304,000.00 312,000.00
0.050 kg Lem Kayu 18,000.00 20,000.00 900.00 1,000.00
C PERALATAN
D Jumlah A + B + C 614,150.00 666,000.00
E Overhead & Profit (contoh 10%) 10% 61,415.00 66,600.00
F Harga Satuan Pekerjaan (D+E) 675,565.00 732,600.00
7 A.4.6.1.7 1 m2 Pembuatan & Pemasangan Pintu & Jendela Jalusi Kayu Klas I atau II (jati) 1,898,875.00 2,018,500.00
A Tenaga 309,250.00 353,000.00
L.01 1 OH Pekerja 55,000.00 65,000.00 55,000.00 65,000.00
L.02 3 OH Tukang Kayu 75,000.00 85,000.00 225,000.00 255,000.00
L.03 0.3 OH Kepala Tukang 85,000.00 95,000.00 25,500.00 28,500.00
L.04 0.05 OH Mandor 75,000.00 90,000.00 3,750.00 4,500.00
B Bahan 1,417,000.00 1,482,000.00
0.064 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,408,000.00 1,472,000.00
0.5 kg Lem Kayu 18,000.00 20,000.00 9,000.00 10,000.00
C PERALATAN
D Jumlah A + B + C 1,726,250.00 1,835,000.00
E Overhead & Profit (contoh 10%) 10% 172,625.00 183,500.00
F Harga Satuan Pekerjaan (D+E) 1,898,875.00 2,018,500.00
8 A.4.6.1.8 1 m2 Pembuatan&Pemasangan Pintu kayu lapis (Plywood) Rangkap rangka Kayu Klas II (lbr s/d 90 cm) 528,951.50 574,805.00
A Tenaga 216,475.00 247,100.00
L.01 0.700 OH Pekerja 55,000.00 65,000.00 38,500.00 45,500.00
L.02 2.100 OH Tukang Kayu 75,000.00 85,000.00 157,500.00 178,500.00
L.03 0.210 OH Kepala Tukang 85,000.00 95,000.00 17,850.00 19,950.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 264,390.00 275,450.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 190,000.00 195,000.00
0.030 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 390.00 450.00
0.500 Ltr Lem Kayu 18,000.00 20,000.00 9,000.00 10,000.00
1.000 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 70,000.00 65,000.00 70,000.00
C PERALATAN
D Jumlah A + B + C 480,865.00 522,550.00
E Overhead & Profit (contoh 10%) 10% 48,086.50 52,255.00
F Harga Satuan Pekerjaan (D+E) 528,951.50 574,805.00
9 A.4.6.1.9 1 m2 Pembuatan&Pemasangan Pintu Plywood rangkap, rangka expose kayu klas I atau II 567,985.00 618,783.00
A Tenaga 247,400.00 282,400.00
L.01 0.800 OH Pekerja 55,000.00 65,000.00 44,000.00 52,000.00
L.02 2.400 OH Tukang Kayu 75,000.00 85,000.00 180,000.00 204,000.00
L.03 0.240 OH Kepala Tukang 85,000.00 95,000.00 20,400.00 22,800.00
L.04 0.040 OH Mandor 75,000.00 90,000.00 3,000.00 3,600.00
B Bahan 268,950.00 280,130.00
0.0256 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 194,560.00 199,680.00
0.03 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 390.00 450.00
0.5 Ltr Lem Kayu 18,000.00 20,000.00 9,000.00 10,000.00
1 Lbr Plywood tebal 4 mm uk.90x220cm 65,000.00 70,000.00 65,000.00 70,000.00
C PERALATAN
D Jumlah A + B + C 516,350.00 562,530.00
E Overhead & Profit (contoh 10%) 10% 51,635.00 56,253.00
F Harga Satuan Pekerjaan (D+E) 567,985.00 618,783.00
10 A.4.6.1.10 1 m2 Pembuatan & Pemasangan Jalusi mati Kosen Kayu Klas I atau II 1,706,017.50 1,809,445.00
A Tenaga 228,975.00 262,700.00
L.01 0.670 OH Pekerja 55,000.00 65,000.00 36,850.00 43,550.00
L.02 2.000 OH Tukang Kayu 75,000.00 85,000.00 150,000.00 170,000.00
L.03 0.200 OH Kepala Tukang 85,000.00 95,000.00 17,000.00 19,000.00
L.04 0.335 OH Mandor 75,000.00 90,000.00 25,125.00 30,150.00
B Bahan 1,321,950.00 1,382,250.00
0.06 m3 Kayu Klas I (Jati), papan 22,000,000.00 23,000,000.00 1,320,000.00 1,380,000.00
0.15 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 1,950.00 2,250.00
C PERALATAN
D Jumlah A + B + C 1,550,925.00 1,644,950.00
E Overhead & Profit (contoh 10%) 10% 155,092.50 164,495.00
F Harga Satuan Pekerjaan (D+E) 1,706,017.50 1,809,445.00
12 A.4.6.1.12 1 m2 Pembuatan&Pemasangan Pintu Teakwood Rangkap Lapis Formika,Rangka expose Kayu Klas II 609,103.00 665,109.50
A Tenaga 262,900.00 300,095.00
L.01 0.850 OH Pekerja 55,000.00 65,000.00 46,750.00 55,250.00
L.02 2.550 OH Tukang Kayu 75,000.00 85,000.00 191,250.00 216,750.00
L.03 0.255 OH Kepala Tukang 85,000.00 95,000.00 21,675.00 24,225.00
L.04 0.043 OH Mandor 75,000.00 90,000.00 3,225.00 3,870.00
B Bahan 290,830.00 304,550.00
0.025 m3 Kayu Klas II (Kamfer), papan 7,600,000.00 7,800,000.00 190,000.00 195,000.00
0.03 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 390.00 450.00
0.08 kg Lem Kayu 18,000.00 20,000.00 1,440.00 1,600.00
1 Lbr Teakwood (90 x 220) cm x 4 mm 65,000.00 70,000.00 65,000.00 70,000.00
0.5 Lbr Formika 68,000.00 75,000.00 34,000.00 37,500.00
C PERALATAN
D Jumlah A + B + C 553,730.00 604,645.00
E Overhead & Profit (contoh 10%) 10% 55,373.00 60,464.50
F Harga Satuan Pekerjaan (D+E) 609,103.00 665,109.50
13 A.4.6.1.13 1 m3 Pembuatan&Memasang Konstruksi Kuda-kuda Konvensional Kayu I; II & III Bentang 6 meter 9,996,030.00 10,943,350.00
A Tenaga 1,237,000.00 1,412,000.00
L.01 4 OH Pekerja 55,000.00 65,000.00 220,000.00 260,000.00
L.02 12 OH Tukang Kayu 75,000.00 85,000.00 900,000.00 1,020,000.00
L.03 1.2 OH Kepala Tukang 85,000.00 95,000.00 102,000.00 114,000.00
L.04 0.2 OH Mandor 75,000.00 90,000.00 15,000.00 18,000.00
B Bahan 7,850,300.00 8,536,500.00
1.1 m3 Kayu Kamfer, balok 6,900,000.00 7,500,000.00 7,590,000.00 8,250,000.00
15 Kg Besi Strip 12,500.00 13,500.00 187,500.00 202,500.00
5.6 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 72,800.00 84,000.00
C PERALATAN
D Jumlah A + B + C 9,087,300.00 9,948,500.00
E Overhead & Profit (contoh 10%) 10% 908,730.00 994,850.00
F Harga Satuan Pekerjaan (D+E) 9,996,030.00 10,943,350.00
17 A.4.6.1.17 1 m2 Pemasangan Rangka Atap Genteng Beton, Kayu Klas II 180,130.50 197,065.00
A Tenaga 14,225.00 16,400.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.1 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 149,530.00 162,750.00
0.014 m3 Kayu Klas II (Kamfer), Kaso-kaso (5x7) cm 6,900,000.00 7,500,000.00 96,600.00 105,000.00
0.0072 m3 Reng (2x3) cm 6,900,000.00 7,500,000.00 49,680.00 54,000.00
0.25 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 3,250.00 3,750.00
C PERALATAN
D Jumlah A + B + C 163,755.00 179,150.00
E Overhead & Profit (contoh 10%) 10% 16,375.50 17,915.00
F Harga Satuan Pekerjaan (D+E) 180,130.50 197,065.00
19 A.4.6.1.19 1 m2 Pemasangan Rangka Langit-langit (50x1,00) m, kayu Klas II atau III 162,563.50 179,685.00
A Tenaga 38,925.00 44,850.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.30 OH Tukang Kayu 75,000.00 85,000.00 22,500.00 25,500.00
L.03 0.030 OH Kepala Tukang 85,000.00 95,000.00 2,550.00 2,850.00
L.04 0.075 OH Mandor 75,000.00 90,000.00 5,625.00 6,750.00
B Bahan 108,860.00 118,500.00
0.0154 m3 Kayu Klas II (Kamfer), balok 6,900,000.00 7,500,000.00 106,260.00 115,500.00
0.2 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 2,600.00 3,000.00
C PERALATAN
D Jumlah A + B + C 147,785.00 163,350.00
E Overhead & Profit (contoh 10%) 10% 14,778.50 16,335.00
F Harga Satuan Pekerjaan (D+E) 162,563.50 179,685.00
20 A.4.6.1.20 1 m2 Pemasangan Rangka Langit-langit (60x60) cm, kayu Klas II atau III 167,772.00 185,075.00
A Tenaga 36,800.00 42,250.00
L.01 0.2 OH Pekerja 55,000.00 65,000.00 11,000.00 13,000.00
L.02 0.3 OH Tukang Kayu 75,000.00 85,000.00 22,500.00 25,500.00
L.03 0.03 OH Kepala Tukang 85,000.00 95,000.00 2,550.00 2,850.00
L.04 0.01 OH Mandor 75,000.00 90,000.00 750.00 900.00
B Bahan 115,720.00 126,000.00
0.0163 m3 Kayu Klas II (Kamfer), balok 6,900,000.00 7,500,000.00 112,470.00 122,250.00
0.25 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 3,250.00 3,750.00
C PERALATAN
D Jumlah A + B + C 152,520.00 168,250.00
E Overhead & Profit (contoh 10%) 10% 15,252.00 16,825.00
F Harga Satuan Pekerjaan (D+E) 167,772.00 185,075.00
22 A.4.6.1.22 1 m' Pemasangan Listplank Uk. (3x30)cm Kayu klas I atau klas II 117,507.50 123,640.00
A Tenaga 22,575.00 25,850.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.2 OH Tukang Kayu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.02 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 84,250.00 86,550.00
0.011 m3 Kayu klas II (Kamfer), papan 7,600,000.00 7,800,000.00 83,600.00 85,800.00
0.05 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 106,825.00 112,400.00
E Overhead & Profit (contoh 10%) 10% 10,682.50 11,240.00
F Harga Satuan Pekerjaan (D+E) 117,507.50 123,640.00
23 A.4.6.1.23 1 m2 Pemasangan Rangka Dinding Pemisah (60x120) cm Kayu klas II atau III 265,732.50 291,769.50
A Tenaga 46,425.00 52,995.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.45 OH Tukang Kayu 75,000.00 85,000.00 33,750.00 38,250.00
L.03 0.045 OH Kepala Tukang 85,000.00 95,000.00 3,825.00 4,275.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 195,150.00 212,250.00
0.028 m3 Kayu klas II (Kamfer), balok 6,900,000.00 7,500,000.00 193,200.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 1,950.00 2,250.00
C PERALATAN
D Jumlah A + B + C 241,575.00 265,245.00
E Overhead & Profit (contoh 10%) 10% 24,157.50 26,524.50
F Harga Satuan Pekerjaan (D+E) 265,732.50 291,769.50
24 A.4.6.1.24 1 m2 Pemasangan Dinding Pemisah Teakwood Rangkap Rangka Kayu Klas II 338,310.50 370,309.50
A Tenaga 46,425.00 52,995.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.45 OH Tukang Kayu 75,000.00 85,000.00 33,750.00 38,250.00
L.03 0.045 OH Kepala Tukang 85,000.00 95,000.00 3,825.00 4,275.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 261,130.00 283,650.00
0.028 m3 Kayu klas II (Kamfer), balok 6,900,000.00 7,500,000.00 193,200.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 1,950.00 2,250.00
0.86 Lbr Teakwood 120 x 240 cm tebal 4mm 65,000.00 70,000.00 55,900.00 60,200.00
0.56 Ltr Lem 18,000.00 20,000.00 10,080.00 11,200.00
C PERALATAN
D Jumlah A + B + C 307,555.00 336,645.00
E Overhead & Profit (contoh 10%) 10% 30,755.50 33,664.50
F Harga Satuan Pekerjaan (D+E) 338,310.50 370,309.50
25 A.4.6.1.25 1 m2 Pemasangan Dinding Pemisah Plywood Rangkap Rangka Kayu Klas II 344,388.00 376,805.00
A Tenaga 51,950.00 58,900.00
L.01 0.020 OH Pekerja 55,000.00 65,000.00 1,100.00 1,300.00
L.02 0.600 OH Tukang Kayu 75,000.00 85,000.00 45,000.00 51,000.00
L.03 0.060 OH Kepala Tukang 85,000.00 95,000.00 5,100.00 5,700.00
L.04 0.010 OH Mandor 75,000.00 90,000.00 750.00 900.00
B Bahan 261,130.00 283,650.00
0.028 m3 Kayu klas II (Kamfer), balok 6,900,000.00 7,500,000.00 193,200.00 210,000.00
0.15 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 1,950.00 2,250.00
0.86 Lbr Plywood 120 x 240 cm tebal 4mm 65,000.00 70,000.00 55,900.00 60,200.00
0.56 Ltr Lem 18,000.00 20,000.00 10,080.00 11,200.00
C PERALATAN
D Jumlah A + B + C 313,080.00 342,550.00
E Overhead & Profit (contoh 10%) 10% 31,308.00 34,255.00
F Harga Satuan Pekerjaan (D+E) 344,388.00 376,805.00
27 A.4.6.1.27 1 m2 Pemasangan Dinding Lambriziring dari Plywood ukuran (120x240) cm 36,525.50 41,360.00
A Tenaga 7,755.00 8,850.00
L.01 0.025 OH Pekerja 55,000.00 65,000.00 1,375.00 1,625.00
L.02 0.075 OH Tukang Kayu 75,000.00 85,000.00 5,625.00 6,375.00
L.03 0.0080 OH Kepala Tukang 85,000.00 95,000.00 680.00 760.00
L.04 0.0010 OH Mandor 75,000.00 90,000.00 75.00 90.00
B Bahan 25,450.00 28,750.00
0.4 Lbr Plywood (120 X 240) cm x 4mm 62,000.00 70,000.00 24,800.00 28,000.00
0.05 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 650.00 750.00
C PERALATAN
D Jumlah A + B + C 33,205.00 37,600.00
E Overhead & Profit (contoh 10%) 10% 3,320.50 3,760.00
F Harga Satuan Pekerjaan (D+E) 36,525.50 41,360.00
28 A.4.6.1.28 1 m2 Pemasangan Dinding Bilik, Rangka Kayu Klas III atau IV 118,162.44 128,722.00
A Tenaga 10,050.00 11,675.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.05 OH Tukang Kayu 75,000.00 85,000.00 3,750.00 4,250.00
L.03 0.005 OH Kepala Tukang 85,000.00 95,000.00 425.00 475.00
L.04 0.005 OH Mandor 75,000.00 90,000.00 375.00 450.00
B Bahan 97,370.40 105,345.00
1.500 m2 Bilik Bambu 20,000.00 22,500.00 30,000.00 33,750.00
0.014 m3 Kayu Klas III (Meranti) 4,800,000.00 5,100,000.00 67,200.00 71,400.00
0.012 Kg Paku Biasa 1/2" - 1" 13,000.00 15,000.00 156.00 180.00
0.003 m' List Kayu 2/4 4,800.00 5,000.00 14.40 15.00
C PERALATAN
D Jumlah A + B + C 107,420.40 117,020.00
E Overhead & Profit (contoh 10%) 10% 10,742.04 11,702.00
F Harga Satuan Pekerjaan (D+E) 118,162.44 128,722.00
3 A.4.1.1.3 1.00 m3 Membuat Beton mutu f'c=12,2 Mpa (K150), slum (12±2)cm, w/c = 0,72 978,977.35 1,074,989.67
A Tenaga 119,980.00 140,755.00
L.01 1.65 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.28 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.03 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.08 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 769,999.40 836,508.33
299 Kg Portland Semen 1,250.00 1,300.00 373,750.00 388,700.00
799 kg Pasir Beton 228.57 250.00 182,628.57 199,750.00
1,017 kg Kerikil (maksimum 30 mm) 207.41 240.74 210,933.33 244,833.33
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 889,979.40 977,263.33
E Overhead & Profit (contoh 10%) 10% 88,997.94 97,726.33
F Harga Satuan Pekerjaan (D+E) 978,977.35 1,074,989.67
4 A.4.1.1.4 1.00 m3 Membuat Lantai Kerja Beton mutu f'c=7,4 MPa (K100), slum (3-6)cm, w/c = 0,87 869,298.86 956,923.81
A Tenaga 83,150.00 97,440.00
L.01 1.200 OH Pekerja 55,000.00 65,000.00 66,000.00 78,000.00
L.02 0.200 OH Tukang Batu 75,000.00 85,000.00 15,000.00 17,000.00
L.03 0.020 OH Kepala Tukang 85,000.00 95,000.00 1,700.00 1,900.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
B Bahan 707,121.69 772,490.74
230 Kg Portland Semen 1,250.00 1,300.00 287,500.00 299,000.00
893 kg Pasir Beton 228.57 250.00 204,114.29 223,250.00
1,027 kg Kerikil (maksimum 30 mm) 207.41 240.74 213,007.41 247,240.74
200 ltr Air 12.50 15.00 2,500.00 3,000.00
C PERALATAN
D Jumlah A + B + C 790,271.69 869,930.74
E Overhead & Profit (contoh 10%) 10% 79,027.17 86,993.07
F Harga Satuan Pekerjaan (D+E) 869,298.86 956,923.81
5 A.4.1.1.5 1 m3 Membuat Beton mutu f'c=14,5 MPa (K175), slum (12±2)cm, w/c = 0,66 1,009,034.41 1,106,052.44
A Tenaga 119,980.00 140,755.00
L.01 1.65 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 797,324.01 864,747.22
326 Kg Portland Semen 1,250.00 1,300.00 407,500.00 423,800.00
760 Kg Pasir Beton 228.57 250.00 173,714.29 190,000.00
1,029 Kg Kerikil (maksimum 30 mm) 207.41 240.74 213,422.22 247,722.22
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 917,304.01 1,005,502.22
E Overhead & Profit (contoh 10%) 10% 91,730.40 100,550.22
7 A.4.1.1.7 1 m3 Membuat Beton mutu f'c=19,3 MPa (K225), slum (12±2)cm, w/c = 0,58 1,059,427.50 1,158,119.11
A Tenaga 119,980.00 140,755.00
L.01 1.650 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 843,135.91 912,080.56
371 Kg Portland Semen 1,250.00 1,300.00 463,750.00 482,300.00
698 Kg Pasir Beton 228.57 250.00 159,542.86 174,500.00
1,047 Kg Kerikil (maksimum 30 mm) 207.41 240.74 217,155.56 252,055.56
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 963,115.91 1,052,835.56
E Overhead & Profit (contoh 10%) 10% 96,311.59 105,283.56
F Harga Satuan Pekerjaan (D+E) 1,059,427.50 1,158,119.11
8 A.4.1.1.8 1 m3 Membuat Beton mutu f'c=21,7 MPa (K250), slum (12±2)cm, w/c = 0,56 1,073,968.75 1,172,940.59
A Tenaga 119,980.00 140,755.00
L.01 1.650 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 856,355.22 925,554.63
384 Kg Portland Semen 1,250.00 1,300.00 480,000.00 499,200.00
692 Kg Pasir Beton 228.57 250.00 158,171.43 173,000.00
1,039 Kg Kerikil (maksimum 30 mm) 207.41 240.74 215,496.30 250,129.63
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 976,335.22 1,066,309.63
E Overhead & Profit (contoh 10%) 10% 97,633.52 106,630.96
F Harga Satuan Pekerjaan (D+E) 1,073,968.75 1,172,940.59
9 A.4.1.1.9 1 m3 Membuat Lantai Kerja Beton mutu f'c=24,0 MPa (K275), slum (12±2)cm, w/c = 0,53 1,099,241.39 1,198,758.00
A Tenaga 119,980.00 140,755.00
L.01 1.650 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 879,330.36 949,025.00
406 Kg Portland Semen 1,250.00 1,300.00 507,500.00 527,800.00
684 kg Pasir Beton 228.57 250.00 156,342.86 171,000.00
1,026 kg Kerikil (maksimum 30 mm) 207.41 240.74 212,800.00 247,000.00
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 999,310.36 1,089,780.00
E Overhead & Profit (contoh 10%) 10% 99,931.04 108,978.00
F Harga Satuan Pekerjaan (D+E) 1,099,241.39 1,198,758.00
10 A.4.1.1.10 1 m3 Membuat Beton mutu f'c=26,4 MPa (K300), slum (12±2)cm, w/c = 0,52 1,106,971.37 1,206,618.93
A Tenaga 119,980.00 140,755.00
L.01 1.650 OH Pekerja 55,000.00 65,000.00 90,750.00 107,250.00
L.02 0.275 OH Tukang Batu 75,000.00 85,000.00 20,625.00 23,375.00
L.03 0.028 OH Kepala Tukang 85,000.00 95,000.00 2,380.00 2,660.00
L.04 0.083 OH Mandor 75,000.00 90,000.00 6,225.00 7,470.00
B Bahan 886,357.61 956,171.30
413 Kg Portland Semen 1,250.00 1,300.00 516,250.00 536,900.00
681 Kg Pasir Beton 228.57 250.00 155,657.14 170,250.00
1,021 Kg Kerikil (maksimum 30 mm) 207.41 240.74 211,762.96 245,796.30
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 1,006,337.61 1,096,926.30
E Overhead & Profit (contoh 10%) 10% 100,633.76 109,692.63
12 A.4.1.1.12 1 m3 Membuat Beton mutu f'c=31,2 MPa (K350), slum (12±2)cm, w/c = 0,48 1,182,667.26 1,289,354.81
A Tenaga 152,600.00 179,025.00
L.01 2.10 OH Pekerja 55,000.00 65,000.00 115,500.00 136,500.00
L.02 0.350 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.105 OH Mandor 75,000.00 90,000.00 7,875.00 9,450.00
B Bahan 922,552.05 993,115.74
448 Kg Portland Semen 1,250.00 1,300.00 560,000.00 582,400.00
667 Kg Pasir Beton 228.57 250.00 152,457.14 166,750.00
1,000 Kg Kerikil (maksimum 30 mm) 207.41 240.74 207,407.41 240,740.74
215 ltr Air 12.50 15.00 2,687.50 3,225.00
C PERALATAN
D Jumlah A + B + C 1,075,152.05 1,172,140.74
E Overhead & Profit (contoh 10%) 10% 107,515.21 117,214.07
F Harga Satuan Pekerjaan (D+E) 1,182,667.26 1,289,354.81
24 A.4.1.1.28 1 m3 Membuat Pondasi Beton Bertulang (150 kg Besi + Bekisting) 3,632,304.50 4,007,069.00
A Tenaga 530,520.00 616,365.00
L.01 5.3 OH Pekerja 55,000.00 65,000.00 291,500.00 344,500.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.30 OH Tukang Kayu 75,000.00 85,000.00 97,500.00 110,500.00
L.02 1.05 OH Tukang Besi 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.262 OH Kepala Tukang 85,000.00 95,000.00 22,270.00 24,890.00
L.04 0.265 OH Mandor 75,000.00 90,000.00 19,875.00 23,850.00
25 A.4.1.1.29 1 m3 Membuat Sloof Beton Bertulang (200 kg Besi + Bekisting) 4,434,710.50 4,889,423.00
A Tenaga 602,055.00 698,380.00
L.01 5.65 OH Pekerja 55,000.00 65,000.00 310,750.00 367,250.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.56 OH Tukang Kayu 75,000.00 85,000.00 117,000.00 132,600.00
L.02 1.4 OH Tukang Besi 75,000.00 85,000.00 105,000.00 119,000.00
L.03 0.323 OH Kepala Tukang 85,000.00 95,000.00 27,455.00 30,685.00
L.04 0.283 OH Mandor 75,000.00 90,000.00 21,225.00 25,470.00
B Bahan 3,429,500.00 3,746,550.00
0.27 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 540,000.00 567,000.00
2 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 26,000.00 30,000.00
0.6 Ltr Minyak Bekisting 9,000.00 10,000.00 5,400.00 6,000.00
210 Kg Besi Beton Polos 9,500.00 10,500.00 1,995,000.00 2,205,000.00
3 Kg Kawat Beton 14,500.00 16,500.00 43,500.00 49,500.00
336 Kg Portland Semen 1,250.00 1,300.00 420,000.00 436,800.00
0.54 m3 Pasir Beton 320,000.00 350,000.00 172,800.00 189,000.00
0.81 m3 Kerikil Beton 280,000.00 325,000.00 226,800.00 263,250.00
C PERALATAN
D Jumlah A + B + C 4,031,555.00 4,444,930.00
E Overhead & Profit (contoh 10%) 10% 403,155.50 444,493.00
F Harga Satuan Pekerjaan (D+E) 4,434,710.50 4,889,423.00
26 A.4.1.1.30 1 m3 Membuat Kolom Beton Bertulang (300 kg Besi + Bekisting) 7,716,725.50 8,639,103.00
A Tenaga 750,355.00 870,430.00
L.01 7.05 OH Pekerja 55,000.00 65,000.00 387,750.00 458,250.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.65 OH Tukang Kayu 75,000.00 85,000.00 123,750.00 140,250.00
L.02 2.1 OH Tukang Besi 75,000.00 85,000.00 157,500.00 178,500.00
L.03 0.403 OH Kepala Tukang 85,000.00 95,000.00 34,255.00 38,285.00
L.04 0.353 OH Mandor 75,000.00 90,000.00 26,475.00 31,770.00
B Bahan 6,264,850.00 6,983,300.00
0.4 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 800,000.00 840,000.00
4 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 52,000.00 60,000.00
2 Ltr Minyak Bekisting 9,000.00 10,000.00 18,000.00 20,000.00
315 kg Besi Beton Polos 9,500.00 10,500.00 2,992,500.00 3,307,500.00
4.5 kg Kawat Beton 14,500.00 16,500.00 65,250.00 74,250.00
336 Kg Portland Semen 1,250.00 1,300.00 420,000.00 436,800.00
0.54 m3 Pasir Beton 320,000.00 350,000.00 172,800.00 189,000.00
0.81 m3 Kerikil Beton 280,000.00 325,000.00 226,800.00 263,250.00
0.15 m3 Kayu Klas II Balok 4,800,000.00 5,550,000.00 720,000.00 832,500.00
3.5 Lbr Plywood 9 mm 125,000.00 160,000.00 437,500.00 560,000.00
20 Btg Dolken diameter 8 / 4rm 18,000.00 20,000.00 360,000.00 400,000.00
C PERALATAN
D Jumlah A + B + C 7,015,205.00 7,853,730.00
E Overhead & Profit (contoh 10%) 10% 701,520.50 785,373.00
F Harga Satuan Pekerjaan (D+E) 7,716,725.50 8,639,103.00
27 A.4.1.1.31 1 m3 Membuat Balok Beton Bertulang (200 kg Besi + Bekisting) 6,066,368.00 6,798,198.00
A Tenaga 650,780.00 755,630.00
L.01 6.35 OH Pekerja 55,000.00 65,000.00 349,250.00 412,750.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.65 OH Tukang Kayu 75,000.00 85,000.00 123,750.00 140,250.00
L.02 1.4 OH Tukang Besi 75,000.00 85,000.00 105,000.00 119,000.00
L.03 0.333 OH Kepala Tukang 85,000.00 95,000.00 28,305.00 31,635.00
L.04 0.318 OH Mandor 75,000.00 90,000.00 23,850.00 28,620.00
28 A.4.1.1.32 1 m3 Membuat Balok Beton Bertulang (150 kg Besi + Bekisting) 5,584,975.00 6,255,232.50
A Tenaga 530,775.00 616,650.00
L.01 5.3 OH Pekerja 55,000.00 65,000.00 291,500.00 344,500.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.3 OH Tukang Kayu 75,000.00 85,000.00 97,500.00 110,500.00
L.02 1.05 OH Tukang Besi 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.265 OH Kepala Tukang 85,000.00 95,000.00 22,525.00 25,175.00
L.04 0.265 OH Mandor 75,000.00 90,000.00 19,875.00 23,850.00
B Bahan 4,546,475.00 5,069,925.00
0.32 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 640,000.00 672,000.00
3.2 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 41,600.00 48,000.00
1.6 Ltr Minyak Bekisting 9,000.00 10,000.00 14,400.00 16,000.00
157.5 Kg Besi Beton Polos 9,500.00 10,500.00 1,496,250.00 1,653,750.00
2.25 Kg Kawat Beton 14,500.00 16,500.00 32,625.00 37,125.00
336 Kg Portland Semen 1,250.00 1,300.00 420,000.00 436,800.00
0.54 m3 Pasir Beton 320,000.00 350,000.00 172,800.00 189,000.00
0.81 m3 Kerikil Beton 280,000.00 325,000.00 226,800.00 263,250.00
0.12 m3 Kayu Klas II Balok 4,800,000.00 5,550,000.00 576,000.00 666,000.00
2.8 Lbr Plywood 9 mm 125,000.00 160,000.00 350,000.00 448,000.00
32 Btg Dolken diameter 8 / 4rm 18,000.00 20,000.00 576,000.00 640,000.00
C PERALATAN
D Jumlah A + B + C 5,077,250.00 5,686,575.00
E Overhead & Profit (contoh 10%) 10% 507,725.00 568,657.50
F Harga Satuan Pekerjaan (D+E) 5,584,975.00 6,255,232.50
29 A.4.1.1.33 1 m3 Membuat Dinding Beton Bertulang (150 kg Besi + Bekisting) 5,461,494.50 6,138,319.00
A Tenaga 530,520.00 616,365.00
L.01 5.3 OH Pekerja 55,000.00 65,000.00 291,500.00 344,500.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.3 OH Tukang Kayu 75,000.00 85,000.00 97,500.00 110,500.00
L.02 1.05 OH Tukang Besi 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.262 OH Kepala Tukang 85,000.00 95,000.00 22,270.00 24,890.00
L.04 0.265 OH Mandor 75,000.00 90,000.00 19,875.00 23,850.00
B Bahan 4,434,475.00 4,963,925.00
0.24 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 480,000.00 504,000.00
3.2 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 41,600.00 48,000.00
1.6 Ltr Minyak Bekisting 9,000.00 10,000.00 14,400.00 16,000.00
157.5 Kg Besi Beton Polos 9,500.00 10,500.00 1,496,250.00 1,653,750.00
2.25 Kg Kawat Beton 14,500.00 16,500.00 32,625.00 37,125.00
336 Kg Portland Semen 1,250.00 1,300.00 420,000.00 436,800.00
0.54 m3 Pasir Beton 320,000.00 350,000.00 172,800.00 189,000.00
0.81 m3 Kerikil Beton 280,000.00 325,000.00 226,800.00 263,250.00
0.16 m3 Kayu Klas II Balok 4,800,000.00 5,550,000.00 768,000.00 888,000.00
2.8 Lbr Plywood 9 mm 125,000.00 160,000.00 350,000.00 448,000.00
24 Btg Dolken diameter 8 / 4rm 18,000.00 20,000.00 432,000.00 480,000.00
C PERALATAN
D Jumlah A + B + C 4,964,995.00 5,580,290.00
E Overhead & Profit (contoh 10%) 10% 496,499.50 558,029.00
F Harga Satuan Pekerjaan (D+E) 5,461,494.50 6,138,319.00
30 A.4.1.1.34 1 m3 Membuat Tangga Beton Bertulang (200 kg Besi + Bekisting) 5,586,300.50 6,255,348.00
A Tenaga 602,055.00 698,380.00
L.01 5.65 OH Pekerja 55,000.00 65,000.00 310,750.00 367,250.00
L.02 0.275 OH Tukang batu 75,000.00 85,000.00 20,625.00 23,375.00
L.02 1.56 OH Tukang Kayu 75,000.00 85,000.00 117,000.00 132,600.00
L.02 1.4 OH Tukang Besi 75,000.00 85,000.00 105,000.00 119,000.00
L.03 0.323 OH Kepala Tukang 85,000.00 95,000.00 27,455.00 30,685.00
L.04 0.283 OH Mandor 75,000.00 90,000.00 21,225.00 25,470.00
31 A.4.1.1.35 1 m' Membuat Kolom Penguat Beton Bertulang (11 x 11) cm 64,138.25 71,497.25
A Tenaga 15,585.00 18,180.00
L.01 0.18 OH Pekerja 55,000.00 65,000.00 9,900.00 11,700.00
L.02 0.02 OH Tukang batu 75,000.00 85,000.00 1,500.00 1,700.00
L.02 0.02 OH Tukang Kayu 75,000.00 85,000.00 1,500.00 1,700.00
L.02 0.02 OH Tukang Besi 75,000.00 85,000.00 1,500.00 1,700.00
L.03 0.006 OH Kepala Tukang 85,000.00 95,000.00 510.00 570.00
L.04 0.009 OH Mandor 75,000.00 90,000.00 675.00 810.00
B Bahan 42,722.50 46,817.50
0.002 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 4,000.00 4,200.00
0.01 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 130.00 150.00
3 Kg Besi Beton Polos 9,500.00 10,500.00 28,500.00 31,500.00
0.045 Kg Kawat Beton 14,500.00 16,500.00 652.50 742.50
4 Kg Portland Semen 1,250.00 1,300.00 5,000.00 5,200.00
0.006 m3 Pasir Beton 320,000.00 350,000.00 1,920.00 2,100.00
0.009 m3 Kerikil Beton 280,000.00 325,000.00 2,520.00 2,925.00
C PERALATAN
D Jumlah A + B + C 58,307.50 64,997.50
E Overhead & Profit (contoh 10%) 10% 5,830.75 6,499.75
F Harga Satuan Pekerjaan (D+E) 64,138.25 71,497.25
32 A.4.1.1.36 1 m' Membuat Ring Balok Beton Bertulang (10 x 15) cm 88,962.50 99,462.00
A Tenaga 25,735.00 30,020.00
L.01 0.297 OH Pekerja 55,000.00 65,000.00 16,335.00 19,305.00
L.02 0.033 OH Tukang batu 75,000.00 85,000.00 2,475.00 2,805.00
L.02 0.033 OH Tukang Kayu 75,000.00 85,000.00 2,475.00 2,805.00
L.02 0.033 OH Tukang Besi 75,000.00 85,000.00 2,475.00 2,805.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 55,140.00 60,400.00
0.003 m3 Kayu Klas III (Terentang) 2,000,000.00 2,100,000.00 6,000.00 6,300.00
0.02 Kg Paku Biasa 2" - 5" 13,000.00 15,000.00 260.00 300.00
3.6 Kg Besi Beton Polos 9,500.00 10,500.00 34,200.00 37,800.00
0.05 Kg Kawat Beton 14,500.00 16,500.00 725.00 825.00
5.5 Kg Portland Semen 1,250.00 1,300.00 6,875.00 7,150.00
0.009 m3 Pasir Beton 320,000.00 350,000.00 2,880.00 3,150.00
0.015 m3 Kerikil Beton 280,000.00 325,000.00 4,200.00 4,875.00
C PERALATAN
D Jumlah A + B + C 80,875.00 90,420.00
E Overhead & Profit (contoh 10%) 10% 8,087.50 9,042.00
F Harga Satuan Pekerjaan (D+E) 88,962.50 99,462.00
C PERALATAN
D Jumlah A + B + C 49,900.00 57,095.00
E Overhead & Profit (contoh 10%) 10% 4,990.00 5,709.50
F Harga Satuan Pekerjaan (D+E) 54,890.00 62,804.50
C PERALATAN
D Jumlah A + B + C 40,030.00 45,140.00
E Overhead & Profit (contoh 10%) 10% 4,003.00 4,514.00
F Harga Satuan Pekerjaan (D+E) 44,033.00 49,654.00
5 A.4.5.1.5 1 m2 Memasang Langit-langit Tripleks Uk (120x240) cm, Tebal 3 mm, 4 mm & 6 mm 41,651.50 47,410.00
A Tenaga 14,225.00 16,400.00
L.01 0.10 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.02 0.10 OH Tukang Kayu 75,000.00 85,000.00 7,500.00 8,500.00
L.03 0.01 OH Kepala Tukang 85,000.00 95,000.00 850.00 950.00
8 A.4.5.1.9 1 m2 Memasang Langit-langit Akuatik Uk (60x120) cm & Rangka Allumunium 185,652.50 201,905.00
A Tenaga 71,125.00 82,000.00
L.01 0.5 OH Pekerja 55,000.00 65,000.00 27,500.00 32,500.00
L.02 0.5 OH Tukang Kayu 75,000.00 85,000.00 37,500.00 42,500.00
L.03 0.05 OH Kepala Tukang 85,000.00 95,000.00 4,250.00 4,750.00
L.04 0.025 OH Mandor 75,000.00 90,000.00 1,875.00 2,250.00
B Bahan 97,650.00 101,550.00
3.6 m' Profil Allumunium "T" 3,500.00 4,000.00 12,600.00 14,400.00
0.15 kg Kawat Ø 4 mm 6,500.00 7,000.00 975.00 1,050.00
1.05 bh Ramset 21,500.00 22,000.00 22,575.00 23,100.00
1.5 lmb Akuatik 60 x 120 cm 41,000.00 42,000.00 61,500.00 63,000.00
C PERALATAN
D Jumlah A + B + C 168,775.00 183,550.00
E Overhead & Profit (contoh 10%) 10% 16,877.50 18,355.00
F Harga Satuan Pekerjaan (D+E) 185,652.50 201,905.00
7 A.5.1.1.8 1 Unit Memasang Bak Mandi Batu Bata Vol. 0,30 m3 1,256,354.27 1,413,478.54
A Tenaga 582,750.00 676,200.00
L.01 6.00 OH Pekerja 55,000.00 65,000.00 330,000.00 390,000.00
L.02 3.00 OH Tukang Batu 75,000.00 85,000.00 225,000.00 255,000.00
L.03 0.30 OH Kepala Tukang 85,000.00 95,000.00 25,500.00 28,500.00
L.04 0.03 OH Mandor 75,000.00 90,000.00 2,250.00 2,700.00
B Bahan 559,390.24 608,780.49
150.0 bh Batu Bata 450.00 500.00 67,500.00 75,000.00
120 Kg Portland Semen 0.11 1,250.00 1,300.00 150,000.00 156,000.00
0.3 m3 Pasir Pasang 0.0121 225,000.00 270,000.00 67,500.00 81,000.00
360 buah Porselen 11 x 11 cm 82.6446280992 512.20 524.39 184,390.24 188,780.49
6 Kg Semen Nat 15,000.00 18,000.00 90,000.00 108,000.00
C PERALATAN
D Jumlah A + B + C 1,142,140.24 1,284,980.49
E Overhead & Profit (contoh 10%) 10% 114,214.02 128,498.05
F Harga Satuan Pekerjaan (D+E) 1,256,354.27 1,413,478.54
8 A.5.1.1.12 1 buah Pemasangan Bak Cuci Piring Stainless stell 333,107.50 375,815.00
A Tenaga 27,825.00 31,650.00
L.01 0.030 OH Pekerja 55,000.00 65,000.00 1,650.00 1,950.00
L.02 0.300 OH Tukang Batu 75,000.00 85,000.00 22,500.00 25,500.00
L.03 0.030 OH Kepala Tukang 85,000.00 95,000.00 2,550.00 2,850.00
L.04 0.015 OH Mandor 75,000.00 90,000.00 1,125.00 1,350.00
B Bahan 275,000.00 310,000.00
1 unit Bak Cuci Piring 225,000.00 250,000.00 225,000.00 250,000.00
1 bh Water drain 50,000.00 60,000.00 50,000.00 60,000.00
C PERALATAN
D Jumlah A + B + C 302,825.00 341,650.00
E Overhead & Profit (contoh 10%) 10% 30,282.50 34,165.00
F Harga Satuan Pekerjaan (D+E) 333,107.50 375,815.00
C PERALATAN
D Jumlah A + B + C 24,275.00 30,550.00
E Overhead & Profit (contoh 10%) 10% 2,427.50 3,055.00
F Harga Satuan Pekerjaan (D+E) 26,702.50 33,605.00
12 A.5.1.1.17 1 bh Pemasangan Bak Kontrol Pas.Batu Bata 60x60 tinggi 60 cm 621,181.00 698,874.00
A Tenaga 264,385.00 308,235.00
L.01 3.200 OH Pekerja 55,000.00 65,000.00 176,000.00 208,000.00
L.02 1.150 OH Tukang Batu 75,000.00 85,000.00 86,250.00 97,750.00
L.03 0.011 OH Kepala Tukang 85,000.00 95,000.00 935.00 1,045.00
L.04 0.016 OH Mandor 75,000.00 90,000.00 1,200.00 1,440.00
B Bahan 300,325.00 327,105.00
123.00 bh Batu Bata 450.00 500.00 55,350.00 61,500.00
114.00 kg Semen Portland 1,250.00 1,300.00 142,500.00 148,200.00
0.18 m3 Pasir Pasang 225,000.00 270,000.00 41,400.00 49,680.00
0.12 m3 Pasir Beton 125,000.00 140,000.00 15,000.00 16,800.00
4.85 kg Baja Tulangan 9,500.00 10,500.00 46,075.00 50,925.00
C PERALATAN
D Jumlah A + B + C 564,710.00 635,340.00
E Overhead & Profit (contoh 10%) 10% 56,471.00 63,534.00
F Harga Satuan Pekerjaan (D+E) 621,181.00 698,874.00
27 A.5.1.1.33 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 20 cm 79,882.00 87,912.00
A Tenaga 8,040.00 9,340.00
L.01 0.080 OH Pekerja 55,000.00 65,000.00 4,400.00 5,200.00
L.02 0.040 OH Tukang Batu 75,000.00 85,000.00 3,000.00 3,400.00
L.03 0.004 OH Kepala Tukang 85,000.00 95,000.00 340.00 380.00
L.04 0.004 OH Mandor 75,000.00 90,000.00 300.00 360.00
B Bahan 64,580.00 70,580.00
1.60 bh pipa tanah 10,000.00 12,000.00 16,000.00 19,200.00
35.00 kg Semen Portlan 1,250.00 1,300.00 43,750.00 45,500.00
0.014 m3 Pasir Pasang 225,000.00 270,000.00 3,150.00 3,780.00
0.014 m3 Pasir Urug 120,000.00 150,000.00 1,680.00 2,100.00
- -
C PERALATAN
D Jumlah A + B + C 72,620.00 79,920.00
E Overhead & Profit (contoh 10%) 10% 7,262.00 7,992.00
F Harga Satuan Pekerjaan (D+E) 79,882.00 87,912.00
28 A.5.1.1.34 1 m' Pemasangan Pipa Air Limbah Jenis Pipa Tanah Ø 15 cm 34,732.50 39,825.50
A Tenaga 6,030.00 7,005.00
L.01 0.060 OH Pekerja 55,000.00 65,000.00 3,300.00 3,900.00
L.02 0.030 OH Tukang Batu 75,000.00 85,000.00 2,250.00 2,550.00
L.03 0.003 OH Kepala Tukang 85,000.00 95,000.00 255.00 285.00
L.04 0.003 OH Mandor 75,000.00 90,000.00 225.00 270.00
4 A.4.2.1.4 1 m2 Pembuatan Pintu Besi Plat Baja tebal 2 mm rangkap, rangka baja Siku 829,317.50 903,875.50
A Tenaga 149,325.00 172,155.00
L.01 1.05 OH Pekerja 55,000.00 65,000.00 57,750.00 68,250.00
L.02 1.05 OH Tukang Besi 75,000.00 85,000.00 78,750.00 89,250.00
L.03 0.105 OH Kepala Tukang 85,000.00 95,000.00 8,925.00 9,975.00
L.04 0.052 OH Mandor 75,000.00 90,000.00 3,900.00 4,680.00
B Bahan 604,600.00 649,550.00
15 Kg Besi Siku L.30.30.3 12,800.00 13,600.00 192,000.00 204,000.00
32.8 Kg Besi Plat Baja 12,500.00 13,500.00 410,000.00 442,800.00
0.05 Kg Kawat Las 52,000.00 55,000.00 2,600.00 2,750.00
C PERALATAN
D Jumlah A + B + C 753,925.00 821,705.00
E Overhead & Profit (contoh 10%) 10% 75,392.50 82,170.50
F Harga Satuan Pekerjaan (D+E) 829,317.50 903,875.50
17 A.4.2.1.18 1 m' Pemasangan Talang Datar/Jurai , Seng BJLS 28 Lebar 90 cm 164,967.00 191,015.00
A Tenaga 43,875.00 50,275.00
L.01 0.20 OH Pekerja 55,000.00 65,000.00 11,000.00 13,000.00
L.02 0.4 OH Tukang Kayu 75,000.00 85,000.00 30,000.00 34,000.00
L.03 0.025 OH Kepala Tukang 85,000.00 95,000.00 2,125.00 2,375.00
L.04 0.01 OH Mandor 75,000.00 90,000.00 750.00 900.00
18 A.4.2.1.19 1 m' Pemasangan Talang 1/2 Lingkaran Ø 15 cm, Seng Plaat BJLS 30 Lebar 45 cm 60,478.00 79,167.00
A Tenaga 33,900.00 38,820.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.02 0.3 OH Tukang Kayu 75,000.00 85,000.00 22,500.00 25,500.00
L.03 0.03 OH Kepala Tukang 85,000.00 95,000.00 2,550.00 2,850.00
L.04 0.008 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 21,080.00 33,150.00
1.05 Lbr Seng Plaat 14,000.00 25,000.00 14,700.00 26,250.00
0.01 Kg Paku Biasa 1 - 2,5 cm 13,000.00 15,000.00 130.00 150.00
0.5 Kg Besi strip 12,500.00 13,500.00 6,250.00 6,750.00
C PERALATAN
D Jumlah A + B + C 54,980.00 71,970.00
E Overhead & Profit (contoh 10%) 10% 5,498.00 7,197.00
F Harga Satuan Pekerjaan (D+E) 60,478.00 79,167.00
19 A.4.2.1.20 1 m2 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 60x120 cm dinding partisi 154,660.00 179,899.50
A Tenaga 35,600.00 41,045.00
L.01 0.250 OH Pekerja 55,000.00 65,000.00 13,750.00 16,250.00
L.02 0.250 OH Tukang Besi 75,000.00 85,000.00 18,750.00 21,250.00
L.03 0.025 OH Kepala Tukang 85,000.00 95,000.00 2,125.00 2,375.00
L.04 0.013 OH Mandor 75,000.00 90,000.00 975.00 1,170.00
B Bahan 105,000.00 122,500.00
3.50 m' Rangka metal hollow 40.40.2 mm 15,000.00 17,500.00 52,500.00 61,250.00
1.00 Assesoris (perkuatan; las dll) 52,500.00 61,250.00 52,500.00 61,250.00
C PERALATAN
D Jumlah A + B + C 140,600.00 163,545.00
E Overhead & Profit (contoh 10%) 10% 14,060.00 16,354.50
F Harga Satuan Pekerjaan (D+E) 154,660.00 179,899.50
20 A.4.2.1.21 1 m2 Pemasangan Rangka Besi Hollow 1 x 40.40.2mm; Modul 60x60 cm dinding plafond 186,807.50 217,189.50
A Tenaga 49,825.00 57,445.00
L.01 0.350 OH Pekerja 55,000.00 65,000.00 19,250.00 22,750.00
L.02 0.350 OH Tukang Besi 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.018 OH Mandor 75,000.00 90,000.00 1,350.00 1,620.00
B Bahan 120,000.00 140,000.00
4.00 m' Rangka metal hollow 40.40.2 mm 15,000.00 17,500.00 60,000.00 70,000.00
1.00 Assesoris (perkuatan; las dll) 60,000.00 70,000.00 60,000.00 70,000.00
C PERALATAN
D Jumlah A + B + C 169,825.00 197,445.00
E Overhead & Profit (contoh 10%) 10% 16,982.50 19,744.50
F Harga Satuan Pekerjaan (D+E) 186,807.50 217,189.50
25 A.4.4.3.58 1 m2 Pemasangan Dinding Batu Paros / Batu Tempel Hitam 217,153.75 240,515.00
A Tenaga 70,350.00 81,725.00
L.01 0.70 OH Pekerja 55,000.00 65,000.00 38,500.00 45,500.00
L.02 0.35 OH Tukang Batu 75,000.00 85,000.00 26,250.00 29,750.00
L.03 0.035 OH Kepala Tukang 85,000.00 95,000.00 2,975.00 3,325.00
L.04 0.035 OH Mandor 75,000.00 90,000.00 2,625.00 3,150.00
B Bahan 127,062.50 136,925.00
1.10 m2 Batu Paros 95,000.00 102,000.00 104,500.00 112,200.00
11.75 Kg Portland Semen 1,250.00 1,300.00 14,687.50 15,275.00
0.035 m3 Pasir Pasang 225,000.00 270,000.00 7,875.00 9,450.00
C PERALATAN
D Jumlah A + B + C 197,412.50 218,650.00
E Overhead & Profit (contoh 10%) 10% 19,741.25 21,865.00
F Harga Satuan Pekerjaan (D+E) 217,153.75 240,515.00
C PERALATAN
D Jumlah A + B + C 116,939.00 131,575.00
E Overhead & Profit (contoh 10%) 10% 11,693.90 13,157.50
F Harga Satuan Pekerjaan (D+E) 128,632.90 144,732.50
27 A.4.4.3.63 1 m' Pemasangan Plint Kayu Klas II Ukuran 2x10 cm 36,762.00 43,978.00
Tenaga 17,070.00 19,680.00
L.01 0.12 OH Pekerja 55,000.00 65,000.00 6,600.00 7,800.00
L.02 0.12 OH Tukang Batu 75,000.00 85,000.00 9,000.00 10,200.00
L.03 0.012 OH Kepala Tukang 85,000.00 95,000.00 1,020.00 1,140.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
Bahan 16,350.00 20,300.00
0.003 m3 Papan Kayu Klas II 5,200,000.00 6,500,000.00 15,600.00 19,500.00
0.05 kg Paku Sekrup 5 cm 15,000.00 16,000.00 750.00 800.00
C PERALATAN
D Jumlah A + B + C 33,420.00 39,980.00
E Overhead & Profit (contoh 10%) 10% 3,342.00 3,998.00
F Harga Satuan Pekerjaan (D+E) 36,762.00 43,978.00
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
2 A.4.7.1.2 1 m2 Pencucian Bidang Permukaan Tembok yang Pernah dicat 9,927.50 11,737.00
A Tenaga 8,475.00 10,020.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.04 0.0030 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 550.00 650.00
0.05 Kg Sabun 11,000.00 13,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 9,025.00 10,670.00
E Overhead & Profit (contoh 10%) 10% 902.50 1,067.00
F Harga Satuan Pekerjaan (D+E) 9,927.50 11,737.00
3 A.4.7.1.3 1 m2 Pengerokan Karat Cat Lama permukaan Baja dg cara manual 10,340.00 12,232.00
A Tenaga 8,850.00 10,470.00
L.01 0.15 OH Pekerja 55,000.00 65,000.00 8,250.00 9,750.00
L.04 0.0080 OH Mandor 75,000.00 90,000.00 600.00 720.00
B Bahan 550.00 650.00
0.05 Kg Sabun 11,000.00 13,000.00 550.00 650.00
C PERALATAN
D Jumlah A + B + C 9,400.00 11,120.00
E Overhead & Profit (contoh 10%) 10% 940.00 1,112.00
F Harga Satuan Pekerjaan (D+E) 10,340.00 12,232.00
4 A.4.7.1.4 1 m2 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 2 Lp Cat Penutup) 37,416.50 43,384.00
A Tenaga 5,260.00 6,155.00
C PERALATAN
D Jumlah A + B + C 34,015.00 39,440.00
E Overhead & Profit (contoh 10%) 10% 3,401.50 3,944.00
F Harga Satuan Pekerjaan (D+E) 37,416.50 43,384.00
5 A.4.7.1.5 1 m2 Pengecatan Bidang Kayu Baru (1 lp Plamuur, 1 lp Cat dasar, 3 Lp Cat Penutup) 50,099.50 57,893.00
A Tenaga 12,290.00 14,125.00
C PERALATAN
D Jumlah A + B + C 45,545.00 52,630.00
E Overhead & Profit (contoh 10%) 10% 4,554.50 5,263.00
F Harga Satuan Pekerjaan (D+E) 50,099.50 57,893.00
8 A.4.7.1.8 1 m2 Pelaburan Bidang Kayu dg Cat Residu & Ter 7,603.75 8,899.00
A Tenaga 5,950.00 7,040.00
L.01 0.1 OH Pekerja 55,000.00 65,000.00 5,500.00 6,500.00
L.04 0.006 OH Mandor 75,000.00 90,000.00 450.00 540.00
B Bahan 962.50 1,050.00
0.35 Ltr Residu atau Ter 2,750.00 3,000.00 962.50 1,050.00
C PERALATAN
D Jumlah A + B + C 6,912.50 8,090.00
E Overhead & Profit (contoh 10%) 10% 691.25 809.00
F Harga Satuan Pekerjaan (D+E) 7,603.75 8,899.00
11 A.4.7.1.11 1 m2 Pengecatan Tembok Lama (1lap.Plamir, 2lap Cat Penutup) 11,343.20 12,802.90
A Tenaga 5,272.00 6,059.00
L.01 0.028 OH Pekerja 55,000.00 65,000.00 1,540.00 1,820.00
L.02 0.042 OH Tukang Cat 75,000.00 85,000.00 3,150.00 3,570.00
L.03 0.0042 OH Kepala Tukang 85,000.00 95,000.00 357.00 399.00
L.04 0.0030 OH Mandor 75,000.00 90,000.00 225.00 270.00
B Bahan 5,040.00 5,580.00
0.12 Kg Cat Dasar 12,000.00 15,000.00 1,440.00 1,800.00
0.18 Kg Cat Penutup 2 kali 20,000.00 21,000.00 3,600.00 3,780.00
C PERALATAN
D Jumlah A + B + C 10,312.00 11,639.00
E Overhead & Profit (contoh 10%) 10% 1,031.20 1,163.90
F Harga Satuan Pekerjaan (D+E) 11,343.20 12,802.90
14 A.4.7.1.14 1 m2 Pelaburan Tembok lama dengan Kapur Sirih (pemeliharaan) 5,667.75 6,646.75
A Tenaga 2,805.00 3,297.50
L.01 0.040 OH Pekerja 55,000.00 65,000.00 2,200.00 2,600.00
L.02 0.005 OH Tukang Cat 75,000.00 85,000.00 375.00 425.00
L.03 0.0005 OH Kepala Tukang 85,000.00 95,000.00 42.50 47.50
L.04 0.0025 OH Mandor 75,000.00 90,000.00 187.50 225.00
file:///conversion/tmp/scratch/443255086.xls 95/94 abk 14-14
HARGA BAHAN/UPAH JUMLAH
No. SNI KODE KOEF SAT. URAIAN PEKERJAAN MINIMUM MAKSIMUM MINIMUM MAKSIMUM
Rp Rp Rp Rp
B Bahan 2,347.50 2,745.00
0.30 Kg Kapur Sirih 4,250.00 4,750.00 1,275.00 1,425.00
0.2 lbr Amplas 3,800.00 4,100.00 760.00 820.00
0.25 ikat Alang-alang 1,250.00 2,000.00 312.50 500.00
C PERALATAN
D Jumlah A + B + C 5,152.50 6,042.50
E Overhead & Profit (contoh 10%) 10% 515.25 604.25
F Harga Satuan Pekerjaan (D+E) 5,667.75 6,646.75
C PERALATAN
D Jumlah A + B + C 67,487.50 80,425.00
E Overhead & Profit (contoh 10%) 10% 6,748.75 8,042.50
F Harga Satuan Pekerjaan (D+E) 74,236.25 88,467.50
17 A.4.7.1.17 1 m2 Pengecatan Permukaan Baja dg Meni Besi & Perancah 43,422.50 50,586.25
A Tenaga 33,100.00 38,187.50
L.01 0.25 OH Pekerja 55,000.00 65,000.00 13,750.00 16,250.00
L.02 0.225 OH Tukang Cat 75,000.00 85,000.00 16,875.00 19,125.00
L.03 0.0225 OH Kepala Tukang 85,000.00 95,000.00 1,912.50 2,137.50
L.04 0.0075 OH Mandor 75,000.00 90,000.00 562.50 675.00
B Bahan 6,375.00 7,800.00
0.1 Kg Meni Besi 20,000.00 30,000.00 2,000.00 3,000.00
0.01 Kg Perekat / Lem 37,500.00 60,000.00 375.00 600.00
0.002 m3 Perancah Kayu 2,000,000.00 2,100,000.00 4,000.00 4,200.00
C PERALATAN
D Jumlah A + B + C 39,475.00 45,987.50
E Overhead & Profit (contoh 10%) 10% 3,947.50 4,598.75
F Harga Satuan Pekerjaan (D+E) 43,422.50 50,586.25