B.M. CONSTROTECH PVT. LTD.

- TELANGAN
Suppliers - UBL Malleppally
Group Summary
1-Apr-2019 to 11-Jun-2019
Particulars Debit Date
M/s Aco Systems and Solutions Pvt Ltd 65797.00 4/17/2019
M/s Harshita Glazing & Cladding Enterprises 2750832.00 5/23/2019
M/s Karan Infra Solutions 50000.00 5/9/2019
M/s Shakti Hormann Pvt Ltd 547482.00 4/29/2019
M/s Ultratech Cement Limited 62695.00 2/7/2019
M/s Uniplus Engineering 58800.00 5/16/2019
Grand Total 3535606.00
Payment Remark Remark
E payment against PO BMCPL\2019-20\012 . 100% ADVANCE Bill Required
advance against working bill Bill Required
E payment -Bool lift hire charges Bill Required
e-Payment PO BMCPL\18-19\1011 PI\137 Bill Required
e-Payment -bmcpl /208-19/823 -5000 AAC block Bill Required
E-Payment -Boom lift hire charges Bill Required