Professional Documents
Culture Documents
What is a Project?
• A temporary endeavor undertaken to create a
‘unique’ product, service, or result.
• As per PMI,
A project is a one-shot, time limited, goal
directed, major undertaking, requiring the
commitment of various skills and resources.
A project should be
• Technically = feasible
• Commercially = viable
• Politically = suitable
• Socially = acceptable
Required Deliverables
Performance
Target
Cost
Budget Limit
Due date
Time
1
8/19/2019
Type of Projects
Project
National International
Non-industrial Industrial
2
8/19/2019
Source: Project Management – A Systems Approach for planning, scheduling and controlling Dr. Kerzner
3
8/19/2019
Project
Identification
Social
Cause
Projects
Business
Cause
Project
Owners
Organizations
Project
Executors
4
8/19/2019
Technical Feasibility
Commercial Viability
Political Suitability
Social Acceptance
Technical Feasibility
5
8/19/2019
Technical Feasibility…contd..
Commercial Viability
6
8/19/2019
Profit/Profitability Models
7
8/19/2019
NPV
Net present value is the present value of net cash inflows generated by a project
including salvage value, if any, less the initial investment on the project.
1 - (1 + i)-n Initial
NPV = R - Investment
(i)
* discount rate, which is the average cost the company pays for capital from borrowing or selling equity
8
8/19/2019
NPV
R1 R2 R3 Initial
NPV = + + + ... - Investment
(1 + i)1 (1 + i)2 (1 + i)3
* discount rate, which is the average cost the company pays for capital from borrowing or selling equity
NPV …contd..
Decision Rule:
1. Accept the project only if its NPV is positive
9
8/19/2019
Calculate the present value of the investment if the discount rate is 18%.
As a PMC decide on project proposal.
Year 1 2 3 4
Present
Value Factor
0.8475 0.7182 0.6086 0.5158
Present
Value of $2,890.68 $2,923.01 $3,544.67 $1,529.31
Cash Flows
Total PV of
Cash $10,888
Inflows
Initial
Investment
8,320
10
8/19/2019
Social Acceptability
Social Impact is defined as “the consequences to human
populations of any pubic or private actions/projects that alter the
ways….
Depth of Impact – The degree to which a project will provide lasting, positive
changes in a person’s or community life.
Changing Paradigms – The degree to which the project will encourage mindset
and behaviour changes.
11
8/19/2019
What is EIA?
12
8/19/2019
Why EIA?
Agriculture
Construction (Road networks, Malls, Townships, Dam etc)
All Industry projects
Electrical projects
Waste disposal
Any developmental projects around Protected Areas / Nature Preserves
Clean Development Mechanism (CDM) projects
13
8/19/2019
The EIA should identify, describe and assess the direct and indirect
effects of a project on the following factors:
Human beings
Fauna and flora
Soil, Water & Air
Climate and the landscape
Material Assets
Cultural Heritage
Interaction between all above factors
14
8/19/2019
15
8/19/2019
16
8/19/2019
17
8/19/2019
18
8/19/2019
19
8/19/2019
20
8/19/2019
Risk Management
• Projects are risky, uncertainty is high
• Project manager must manage this risk
• This is called “risk management”
• Risk varies widely between projects
• Risk also varies widely between organizations
• Risk management should be built on the
results of prior projects
21
8/19/2019
Risk
• Risk is a measure of the probability and consequence of not
achieving a defined project goal.
• Most people agree that risk involves the notion of uncertainty.
• Risk has two primary components for a given event:
– A probability of occurrence of that event
– Impact (or consequence) of the event occurring (amount
at stake)
• Risk for each event can be defined as a function of probability and
• consequence (impact); that is,
• Risk = f (probability, consequence)
OF OCCURANCE
22
8/19/2019
TOLERANCE FOR
RISK
23
8/19/2019
Utility
24
8/19/2019
25
8/19/2019
26
8/19/2019
27
8/19/2019
28
8/19/2019
29
8/19/2019
Risk Identification
• Risk is dependent on technology and
environmental factors
• Delphi method is useful for identifying project
risks
• Other methods include brainstorming,
nominal group techniques, checklists, and
attribute listing
• May also use cause-effect diagrams, flow
charts, influence charts, SWOT analysis
30
8/19/2019
1. Tight Schedule
2. Can’t acquire technical knowledge
3. Client changing scope of the project
4. Cost Escalation
5. Recession
Risk Matrix
Risk Matrix
31
8/19/2019
Example:
4 Costs escalate 3 2 6 36
5 Recession 4 2.5 7 70
32
8/19/2019
Example ….contd..
From the RPN numbers, the biggest threats are: 2 (Can’t acquire technical
knowledge) and 3 (Client changes scope).
Threat 2 has a great severity and threat 3 is quite likely, though the
severity is much less damaging.
The cost threat (4) and the recession threat (5) can probably be ignored
for now since their likelihoods are so low.
The tight schedule (1) will have some consequences and is also
quite likely, but we will see it coming early and can probably take steps to
avoid or mitigate it…..
33