208.
Petersen Pottery
ANALYSIS OF OPERATIONS
‘After 6 months of operations using the new cost system Petersen was disturbed over the Tack of
attention paid to the standards. He felt that the potters were just too set in their ways to pay any
attention to the “confusing” new system, As one of the potters observed, “I have been making these
fixtures a lot longer than these new ideas had been around, and I don’t see how a bunch of numbers that
some hot-shot accountant puts together are going to help me make any berter toilets.” The result was
that although the standards existed, they were seldom met.
in reviewing the June production results, the following actual costs were noted in connection
with manufacturing 1145 toilets:
Materials Purchased
Clay 30,000 Ib @ §.92/lb
Glaze 6,000 Ib @ $.78/Ib
Materials Used
Clay 28,900 Ib
Glaze
Direet Labor
Molding 1.200 hr @S15.25/hr
Glazing 600 hr @ $15.00he
Overhead Assigned to Toilets: $6,100 (82,300 variable cost and $3,800 fixed cost)
‘The sales manager was unhappy that production was 55 units below plan. ‘The cost
‘accountant was unhappy about continuing unfavorable variances. Before proceeding with further
analysis, Petersen met with his most experienced master potter, Jim Sedgefield, to discuss the variances
from the standards, He was seriously considering implementing a new and much faster “pressure
casting” mold system to replace the existing manual system, When Sedgeficld arrived Clive explained
the problem: “Sim, you agrecd when we set them up that the standards are reasonable and yet you
never meet them. It looks like we will have unfavorable variances again this mouth as well as more
missed shipping dates.” Sedgefield was not impressed. “Well Clive,” he said, “T newer have
linderstood this system at all. Why don’t you ask that fast-talking, accountant to explain the variances?
He seems to know what these numbers mean, AILI know is, we seemed (o spend all month fisssing with
that new brand of clay you said was going to be cheaper for us. Do you want mee to make lots of toilets
‘or good toilets?”
QUESTIONS
Analyze the variances for the month using whatever
Format you like.
‘What conclusions are suggested regarding cost performance for the month?
‘What suggestions do you have for Mr. Petersen regarding his new standard cost system?A Note on Computing Manufacturing
Cost Variances
For use with Petersem Pottery case
1 “PRIME” COSTS
‘The tenm “prime” costs refers to those costs which can be directly identified with one unit of product.
‘Another term for “prime” cost is “direct” cost or “variable” cost, You will often hear the terms
‘direct material cost or “direct” labor cost. Traditionally, labor has been considered a prime cost by
most companies, “Indirect” material and “indirect” labor cosis are considered to be part of
manufacturing overhead or “burden” rather than part of prime cost. Example of these four cost
categories are shown belo
Cost Category Cost Classification Example
Direct Labor Prime Cost Cost for a worker's time spent
assembling a product,
Inditect Labor Overhead Cost Cost for a worker's time spent
repairing manufacturing
equipment
Direct Material Prime Cost Cost of stee! used in manufseturing
an automobile
Indirect Material Overhead Cost Cost of supplies used in maintaining
manufacturing equipment
‘Today, many companies treat manufacturing Jubor cost more as fixed than as_volume
dependent, In this case, the only “prime” or “direct” cost is raw material
rhe standard for any’ element of prime cost Involves two components: a prieé component and
a quantity component. The standard cost isthe standard quantity to be used multiplied by the standard
pice per unit of measure. For example, if an clectrie motor contains four bushings andl each bushing
‘Should cost $.25, then the standard cost for bushings is $1.00 (standard quantity of 4 X the standard
price per unit of $.25). Variances are usually computed for each of the two components. The formulas
for calculating the varlances are as follows:
Price variance (PW)= (AP - SP) X AQ
‘Quantity variance (QV) (AQ - SQ) K SP
Total variance (TW)- PV + QV
where SP = standard price
AP = actual price
8Q= standard quantity
AQ= actual quantitySince the total variance is the difference between
the standard cost allowance (SP X SQ) and the actual cost
incurred (AP X AQ), you should be able to verify for
yourself that the price and quantity variance in the above
formulas do sum to the total variance.
We can illustrate these calculations with. the
following example which assumes that both material and
Jabor cost are volume dependent
Calon!
‘Standacel per Vit
2 pounds per unit at $1.00 per
‘pound = $2.00 por unit
3 hours per unit at $4.00 per
hour = 512.00 per unit
Production 10 units. Therefore, the
standard cost allowanec:
{s $20 for material and $120
for labor
Actual Costs
Material Used 25 pounds which were
purchased at a cast of $.80
per pound, fora cost of $20,
Labor Used 25 hours at an average
sate of $5.00 per hour, for a
cost of $125.
Material Price variance: ($1.00- $.80)
‘X25 lb = $5 Favorable
Quanity variance: (20-25)
$1.00/ib = $5 Unfavorable
‘Votal variance:
$20 - $20
Labor Price variance: (84 - $5) 25
25. Unfavorable
Quantity variance: (30 - 25) X
Safhr = $20 Favorable
Total variance: $25U + $20F=
$5U = $120 - $125
We suggest that you pot worry about whether 10
put standard or actual first in the formulas or about trying
to keep teack of whether a negative result is Tavorable ot
tnfavorable. Instead, just think about whether the
direction of the variance is good or bad and forget about
algebraic signs.
A Complication “The Joint” Variance. Ifyou
Took closely at the variangc formulas above, you will see
that quantity variance is computed using standard prices
While, the price variance is computed using actal
quantities. ‘(bis Is logically inconsistent, but it makes
Sense to most people. Most people feel that price
Petersen Pottery — Note on CMCV_
fwuotuations should not be considered when measuring the
variance due to quantity fluctuations-—vary only oe
component at atime, However, most people also feel that
the price variance should be measured over the actual
quantities for which the price difference obtains, not the
Gandard quantities. Some people do not like this logical
inconsistency. They prefer to vary only one component at
fitime in both the price and quantity variance caleulations.
‘They then set up a third variance Goint variance) caused
by the: joint fluctuation in both prices and quantities.
‘Under this approach the formulas are as Follows:
PV=(AP -SP) XSQ
QV =(AQ- SQ) XSP
IV =(AP- SP) K (AQ- SQ)
TV=PV+QV1IV
can be illustrated graphically as follows, assuming
both price and quantity variations are unfavorable:
‘Two. Variances Approach
‘Actual |—_—__—___———_
Price Price
Variance
Standard
Price Standard ‘Quantity
Cost Varianee
Standard Usage Actual Usage
ees Approach
Actual |_————,———— —_q
Price Price Joint
Variance Variatice
Standart
Price Standard Quantity
L Cost ‘Variance
Standard Usage Actual Usage
Ik is impossible to give a commonsense interpretation 10
the joint variance when one of the two ‘components varies
favorably and the other varies unfavorably. Furthermore,
most authors believe that purchasing agents should be
sessed for price variations on quantities actually
purchased but that pfocuction managers should be
assessed for quantity differences scaled with standard
prices (ignoring price fluctuations). For these reasons,
they favor the simpler, two variance approach.
“The two variance equality set up in this note (PY
+ QV = TV) is often violated in practice in regard. to
tpalerial variances, ‘Thal is, many firms prefer to compute
the price variance over quantities: purchased and the
quantity variance over quantities wed. Since purchase
and usage quantities often differ in any given period, thePetersen Pottery — Note on CMCV
two variances cannot be aggregated algebraicly. They
can, however, still be combined for cost reporting
purposes to get a picture of purchasing and usage
variances together.
Suppose, for example, that in our earlier illus-
tration material purchases totaled 30 pounds at $,80 even
though only 25 pounds were used in production. The
‘material variance calculation could then be as follows:
Price variance: ($1.00 - $.80) X 30 Ib = $6 Favorable
Quantity variance: (20 - 25) X $1.00/Ib= $5 Unfavorable
‘Total variance: S6F + $5U = SIF # $20 - $20
A labor price varianee is often called a “labor
rate” variance and a labor quantity variance is often called
a “labor efficiency” variance. A material quantity variance
is often called a “material usage” variance and a material
price vatance is often called a “purchase price” variance.
Ul, OVERHEAD COSTS
Conventional Overhead Budgets. Budgets for
piime costs hinge on unit-level standard costs. Ones
standard prime costs per unit are determined, the budget
for any given period is just the standard cost per unit
times the number of units produced. A simple approach
like this works becanse prime costs are variable costs,
‘The cost allowance or budget thus varies directly as
production volume varies.
Because manufacturing overhead costs typically
do not vary directly with volume, it is. a more difficult tasle
to determine allowable overhead at any given level of
production.
Fixed Budgets. One approach to overhead
budgeting ignores the volume dependence issue entirely.
‘This approach is called fixed overhead budgeting. Under
fa fixed-budget approach, management determines the
amount of overhead which should be incurred at the
normal or most likely production level. This expense total
becomes the budget against which cost performance is
measured, regardless of the level of production output
actually achieved. To the extent that manufacturing
‘overhead costs do vary with production, the fixed-budget
approach does not yield meaningful variance data when
actual output varies from planned output. There is no
conceptual support for a fixed-budget approach to
manufacturing, overhead, but many companies stilluse it.
Flexible Budgets. The more conceptually sound
approach to determining ovethead standards in
conventional cost aecounting is called flexéble budgeting
‘A flexible manufacturing overhead budget specifies
allowable cost at each possible output level. Once &
period is over and the actual production volume is known,
the “flexed” cost allowance is determined by reference to
the flexible budget for that level of output. This is a direct
21
parallel to the way a budget for direct material is
determined, If all manufact-uring overhead is either pure
“variable” or pure “fixed,” @ flexible budget is just a
formula of the following type:
Budget allowance = a+bx
where a= fixed overhead costs for the period
b= variable overhead costs per unit
x= units produced during the period
‘An example of a simplified exible budget is
siown below:
Capacity “Normal”
Utilzation:! 40% .. 80% .. 100%
Units Produced 4,008,000 "10,000.
Allowed
Overhead Cost Behavi
Depreciation $1,000 $1,000 $1,000 Pure non-variable
or “fixed”
Supervision 300 1,000 1,500 “Step” cost?
Supplies 400 "800 1,000 Pore variable at
8.10 per unit
Power 600 800 900 Semivariable ($400
+ 5.05 per unit)
Total $2,500 $3,600 $4,400
1 Its assumed that volume would never fall below 40% of
capacity or above 100%
2A step” cost is one which doesn't vary directly with
production but does increase in lump-sum jumps when volume
rises substantially, An example would be adding a second
foreman when volume rose to the level that a second shift was
needed.
Flexible Budget Formula
Up to 80% of capacity: $1,900 + $.15 per unit
‘Above 80% utilization: $2,400 + $.15 per unit
Overhead Absorption
Under GAAP or IRS rules, manufacturing overhead is
considered to be part of product costs. It is therefore
necessary to find some way of charging or “absorbing”
manufacturing overhead into inventory. However, the
simple approach of charging actual manufacturing
‘overhead each period directly to work-in-process (WIP)
inventory is usually not considered to be an acceptable
approach for two reasons:
1. Variances are not considered to “add value” to the
inventory, Thus, overhead variances are not
considered to be product costs. Thus, only allowable
‘overhead is to be “inventoried.”
2. Volume considerations also affect the decision of how
‘much overhead to absorb in inventory. Suppose, for
‘example, that depreciation is $1,000 per period. Alsosuppose that 1 unit is produced in period 1 and 1,000
units are produced fp period 2. Tt doesn't secm “fait”
to most accountants to say that in period one, the one
unit caries a cost of $1,000 for depreciation ($1,000
depreciation + 1 unit) and in period two, each unit
only $1 ($1,000 depreciation + 1,000 unit). A_unit
cant really be “more valuable” just because fewer
‘were produced that month
“Fair” allocation of depreciation to inventory seems
to requite a concept of “normal” volume. The $1,000
dopreciation expense is incurred as a “reasonable”
charge on the assumption that some reasonable or
normal number of units will be produced on the
equipment. It is this normal volume level over which
the planned overhead should be spread, so. the
argument goes.
For these two reasons, conventional practice for
charging manufacturing overhead into inventory is to use
‘a “normal absorption rate.” This rate is computed as
planned overhead cost at normal production volume (per
the flexible budget) divided by that normal volume. In the
‘example above, the normal volume is 8,000 units (80% of
capacity). AC this level of output, budgeted overhead is
$3,600, The “normal absorption rate” is thus
$3,600/8,000, or $.45 per unit.
‘in single-product firms, output can be expressed
in units of product. In multiproduct firms, however, itis
necessary to set some other measure of capacity
‘iilzation, such #5 labor hours, labor dollars, or machine
hours. The choice of a volume measure in a particular
pusiness should be based on which variable best measures
the lovel of capacity utilization for that business
Of course, the notion that anyone measure of
activity can capture the essence of capacity utilization
geross manufacturing departments ignores the richness
‘which activity-based costing tries to capture
‘The accounting works as follows. A T-account
js established in the books of account called “Factory
overhead” or “burden” or something equivalent. Actua)
manufacturing overhead expenses are charged (debited) to
{his ‘T-account. Overhead is absorbed into inventory by
crediting the “factory overhead” account and debiting the
Wworkcin-process inventory in an amount equal to the
absorption rate times the actual volume attained, In our
example, if actual volume was 6,000 units, $2,700 of
overhead would be charged to WIP (6,000 X 8.45).
“This absorption process will only “clear” the
factory overhead account if pwo conditions are both met
1. factual volume equals planned volume.
‘Manufacturing overhead cost does not vary: directly
‘with production. The absorption rate, however, is a
pure variable rate. Thus, absorbed overhead will only
Petersen Pottery — Note on CMCV.
equal planned overhead at one particular volume
Jevel—that level used in computing the absorption
rate
2. factual overhead expenses equal planned expenses
per the flexible budget, Since only budgeted
‘overhead ig absorbed, any differences between
“budgeted costs and actual costs will not be “cleared”
from the factory overhead T-account,
‘At the end of any accounting period, there is usually a
residual balance in the factory overhead account resulting
fom failure to meet one or both of these two conditions.
‘This end-of-period residual in the factory overhead T-
account is sometimes called the “book” overhead variance
‘because it is what shows up in the books of account. It is
also sometimes called the total overhead variance.
‘Normal accounting practice is to charge this
variance to cost of goods sold for the month as a period
expense.
‘Analyzing the Total Overhead Variance
Using the same example from above with actual
production of 7,000 units, we can produce the following
cost table:
Flexible Budget
Allowance
at Actual Actual
Volume of Exponseat Spending
Cost tem 7.000 Units _Actual Volume __Varlanes
Depreciation $1,000 $1,100 sioou
Supervision 1,000 1,050 sou
Supplies 700 690 10F
Power 70 79 20
Total $3,450 mao Sua
‘Manufacturing Overhead Absorbed into Inventory
"7000 X S.45 = $3.150___
|As shown in the table, the difference between
‘acual overhead incurred and the flexible budget at this
evel of output is called the ovethead “spending” variance.
It measures cost control performance under the
assumption that the flexible budget is a usefull cost
benchmark,
‘The total variance which shows up in the T-
account is equal to the difference between actual overhead
{the debits) and absorbed overhead at actual volume tthe
sredit), In this example, the total variance is $460U (3610
= 3150).
‘The variance which is useful in measuring cost
‘control effectiveness (the spending, varkance) is equal to
the difference between actual overhead and allowed
overhead at actual volume. For the example, this 1s‘Petersen Pottery — Note on CMCV
$1G0U, Tn order to present an analysis which “balances,”
‘cost accountants need to have some name for the
difference between the total variance and the spending
variance, Using a little algebra, we can see that the
quantity for which we need # name, “the plug,” is allowed
OHL- absorbed OH:
Actual Allowed Actual
Minus = + = Minus = Minus
Allowed Absorbed Absorbed
Spending Total
Variance «+ | Pug? = = Varian
$1600 +9300U = $460
Regarding the plug, we have already observed
that allowed OH will only equal absorbed OF when #he
firm operates at normal volume, Why? Because
budgeted overhead does not vary directly as production
varies, but absorbed overhead is purely variable, by
convention. ‘The absorption rate is set to just absorb into
inventory the planned overhead when the firm actually
operates at its normal volume, The idea here is that the
normal absorption rate is the normal amount of
manufacturing overhead cach unit should carry.
Standard (absorbed) overhead cost per unit, for
purposes of valuing inventories, is thus equal to a
proportional share of normal overhead when production
volume is at normal levels. ‘The plug variance (allowed
OM - absorbed OH) results from the difference between
planned and actual production volume. It is usually called
the “production volume variance.” ‘The dollar amount of
this production volume variance fas no particular
management significance whatsoever. The dollar amount
ig just the plug required to reconcile a managerially
significant number (the spending variance) to a number
which shows up in the income statement (the total
variance), The production volume variance does result
‘rom variation between planned and actual production
‘volume. In this sense, the name is appropriate. However,
the amount is not managerially useful—the amount is just
aplug. For our example, the amount is $300U! as shown
| above.
Going one step further, we can talk about what
comprises the “plug.” It does not include any variable
‘overhead because items which are directly variable with
| production are treated identically in the absoxption rate
| GAS per unit) and in the flexible budget (6.15 per anit)
“They thus cancel out in computing the difference between
allowed and absorbed cost, In our illustration, for
“ exanmple, the absorption rate of $.45 per unit includes $.15
| of variable cost and the flexible budget also includes $.15
per unit of variable cost ($.10 for supplies and $.05 for
power). At acmal volume ‘of 7,000 units, therefore, both
= the allowed OH of $3,450 and the absorbed OH of $3,150
include $1,050 of variable cost. This $1,050 thus does
not contribute anything to the difference between $3,450
and $3,150.
The difference is the fixed-cost portion of the
absorption rate (8.30) times the unfavorable volume
fluctaation of 1,000 units, or $300U. The §.30 fixed cost
portion of the absorption rate is equal to the $2,400 of
planned fixed overhead at normal volume divided by the
volume measure of 8,000 units. When operating at the
7,000 unit level, we are allowed $2,400 of fixed
manufacturing overhead, but we only absorb $2,100
(7,000 x$.3).
Il. MANAGERIAL USE OF VARIANCES
Itis very widely assumed in “cost accounting circles” that
variances calculated according to the techniques explained
here in Parts I and JI represent useful management
information. We will summarize here the particular slant
on this point of view from four of the “top 20” MBA
programs as reflected in textbaoks written by faculty
members there,
‘A. Stanford Business School (Professor Charles
Horngren)
“Standard costs are the building blocks of
budgeting and feedback system. A standard cost
is a carefully predetermined cost that should be
attained.”
“jp practice, direct materials and direct labor are
often said to be controlled with the help of
standard costs.”
perfect standards are expressions of the
absolute minimum costs possible under the best
conceivable conditions, No provision is made
for waste, spoilage, machine breakdowns, and
the like. Those who favor this approach maintain
that the resulting unfavorable variances will
constantly remind managers of the perpetual
need for improvernent in all phases of operations.
Perfect standards are not widely used, however,
‘because they have an adverse effect on. employee
motivation”
“Currently attainable standards are costs that can
be achieved by a specified level of effort
Allowances are made for normal spoilage, waste,
and nonproductive time, ‘There are at least two
popular interpretations of the meaning of
‘currently attainable’ standards. The first
interpretation has standards set just tightly
enough so thal employees regard their fulfillment
as highly probable if normal effort and diligence
are exercised, ‘That is, variances should be
negligible. A second interpretation of eurrently
atainable standards is that standards are set24
tightly. That is, employees regard their
fulfillment as possible, though unlikely.”
“Managers responsible for variances should be
required to explain them, In addition, managers
who have control over the causes of the
variances should be held accountable for
avoiding unfavorable variances of correeting the
factors causing them. The primary function of
variances is explanation. The main goal is to
understand what is affecting costs and revenues
so that managers can make better decisions in the
future.”
“Variances do not, by themselves show why the
budget (standard) was not achieved. But they
raise questions, provide clues, and direct
attention.”
“Because there are so many interdependences
among, activities, a variance should not lead a
manager to jump to conclusions, By themselves,
such variances merely raise questions and
provide clues. They are attention directors, not
answer givers.”
Colgate - Darden Business School (Professors
Brandt Allen and William Rotch)
“There are three important ways in which
standard costing systems assist management:
1. The automatic built-in provision of
variances helps identify areas that need
management's attention.
2. The development of a database of
standard costs and quantities supports
pricing decisions and helps the overall
planning process.
3, The use of standard product costs
simplifies inventory accounting.”
‘The Vanderbilt Business School (Professor
Germain Boer)
“A standard, as defined by the Oxford English
Dictionary, is a definite level of excellence or a
definite degree of quality, viewed as a preseribed
object of endeavor or a measure of what is
adequate for some purpose. A standard, as used
in management accounting, is a predetermined
cost.”
“The primary purpose of standards is to measure
the difference between what costs are and what
costs should be for the purpose of controlling
cosis. In a more general sense, the benefits of
Petersen Pottery — Note on CMCV
standards can be classified as follows:
1 Better control over costs and thus income
through the identification of variances
‘between actual and standard costs.
2. More informative income statements
which can illustrate the profit impact of
‘variances by showing excess costs as
‘waste and cost savings as gains.
3, Ease and expedition of cost accounting
since all inventories can be valued at
standard.
4. Basic data are provided for planning and
special studies,
5. Other benefits include:
‘a. The planning required to set-up
standards.
b. Coordination and cooperation is
‘enhanced. by and within all areas.
¢. Standards set total and individual
goals.”
“Standards should be based on a scientific study
cof the quantities of material and units of labor
which should be used to produce the product;
‘hat is, they should be engineered standards. The
setting of standards is the responsibility of the
technical staff of a plant, such as industrial
engineers, design engineers, and chemists.
Unless the supervisor agroes that a standard is
fair, their reaction to variances will be defensive
rather than corrective. After the standard
quantities are set, they are normally submitted to
the accountants for conversion into standard
costs.”
“Two types of standards have been found
acceptable for cost control purposes: (1) the
attainable standard, and (2) the perfect standard
The former can be used for cost control and. for
the development of standard costs. ‘The latter is
used only for cost control and may supplement
the use of attainable standards. The basic
consideration in selecting either or both types is
hhow well they will serve the purposes of cost
control”
“Attainable direct materials standards are based
on the type and quantity of material whieh should
be used to produce a finished product of
specified quality. Allowance is made for normal
losses in initial processing, and considering this,Petersen Pottery — Note on CMCV.
the yield in quantity of finished or semicfinished
product is determined.”
“When standard costs are used, allowances are
set for spoilage at each operation.”
“Under a standard cost system, a standard
percentage of total production is set as the
quantity of seconds expected ta be produced,”
“Brom practical experience, it is evident that
perfect operation can never be attained. ‘Thus,
perfect standards should be taken as the direction
in which attainable standards should move.”
Cornell Business School (Professor Ronald
Wilton)
“Standards should not be determined by the
managerial accountant alone. People generally
will be more committed to meeting standards if
they are allowed to participate in setting them.”
“Some managers believe that perfect standards
motivate employees to achieve the lowest cost
possible. ‘They claim that since the standard is
theoretically attainable, employees will have an
incentive #0 come as close as possible to
achieving it.
Other managers and many behavioral
scientists disagree. They feel that perfect
standards discourage employees, since they are
so unlikely to be attained. Moreover, setting
unrealistically difficult standards may encourage
employees to sacrifice product quality to achieve
Tower costs. By skimping on raw-material
quality of the attention given manual production
tasks, employees may be able to lower the
production cost. However, this lower cost may
come at the expense of a higher rate of defective
‘units. ‘Thos, the fitm ultimately may incur higher
‘costs than necessary as defective products are
rewmed by customers or serapped upon
inspeetion.”
“Practical standards allow for such occurrences
as occasional machine breakdowns and normal
amounts of raw-material waste. Attaining a
Practical standard keeps employees on their toes,
without demanding miracles. Most behavioral
theorists believe that practical standards
encourage more positive _and productive
employee attitudes then do perfect standards.”
215
“Standard costs and variance analysis are usefial
in diagnosing organizational performance. These
tools help managers to discern 'the story behind
the story’ - the details of operations that underlie
reported cost and profit numbers. Standard
costs, budgets, and variances are also used to
evaluate the performance of individuals and
depariments. The performance of individuals,
relative to standards or budgets, often Is used to
help determine salary increases, bonuses, and
promotions. When standards and variances
affect employee reward strucmres, they can
profoundly influence behavior.”
“A. standardl-costing system offers. six clear
advantages if used properly:
1. Standard costs provide a basis for sensible
cost comparisons. It would make no sense
to compare budgeted costs at one (planned)
activity level with actual costs incurred at a
different (actual) activity level. Standard
casts enable the managerial accountant to
compute the stmdard allowed cost, given
actual output, which then serves as a
sensible benchmark to compare with the
actual cost
2, Computation of standard costs and cost
variances enables managers to omploy
management by exception. This approach
conserves valuable management time.
3. Variances provide a means of performance
evaluation and rewards for employees.
4. Since the variances are used in performance
evaluation, they provide motivation for
employees to adhere to standards.
5. Use of standard costs in product costing
results in more stable product costs than if
actual production costs were used. Actual
costs often fluctuate erratically, whereas
standard costs are changed only periodically.
6. A standard-costing system is usually less
expensive than an actual costing system.
IV. A FINAL THOUGHT
Tt is problematic today whether this point of view from
section [l—standard costs and variances are useful to
management—represents best thinking in the 1990s or
merely a 1990s recapitulation of best thinking in the
1960s. Exploring this dilemma is beyond the scope of
this note