a1 b1 c1 d1 e1 f1

Executant: UPB -URBAN PROIECT BARLAD


Obiectiv: 015 -FUNDATIE REZERVOR APA 109MC
Obiect: 01 -FUNDATIE REZERVOR
Categorie: 01 -REZISTENTA
Recapitulatie
Material Manopera Utilaj Transport Total
M m U t T
Cheltuieli directe 10,461.99 3,567.50 856.34 1,561.88 16,447.71
din care utilaje
- Vut termice 794.54
- Vut electrice 61.80
- Vut altele 0.00
Alte cheltuieli directe
C.A.S. ### 563.66 563.66
C.A.S.S. 5.200% 185.51 185.51
Aj.somaj 0.500% 17.84 17.84
Acc. munca, boli profes. 0.270% 9.63 9.63
Contr.Concedii Medicale 0.850% 30.32 30.32
Fond garantare salarii 0.250% 8.92 8.92
Mo mo Uo to To
TOTAL CHELT. DIRECTE 10,461.99 4,383.38 856.34 1,561.88 17,263.60
Cheltuieli indirecte Io = ### x To 1,726.36
Profit Po = 5.000% x (To+Io) 949.50
TOTAL GENERAL categorie Vo = To+Io+Po 19,939.45

Ofertant,
a1 b1 c1 d1 e1 f1
Executant: UPB -URBAN PROIECT BARLAD
Obiectiv: 015 -FUNDATIE REZERVOR APA 109MC
Obiect: 01 -FUNDATIE REZERVOR
Categorie: 01 -REZISTENTA
Recapitulatie
Material Manopera Utilaj Transport Total
M m U t T
Cheltuieli directe 10,461.99 3,567.50 856.34 1,561.88 16,447.71
din care utilaje
- Vut termice 794.54
- Vut electrice 61.80
- Vut altele 0.00
Alte cheltuieli directe
C.A.S. ### 563.66 564
C.A.S.S. 5.200% 185.51 186
Aj.somaj 0.500% 17.84 18
Acc. munca, boli profes. 0.270% 9.63 10
Contr.Concedii Medicale 0.850% 30.32 30
Fond garantare salarii 0.250% 8.92 8.92
Mo mo Uo to To
TOTAL CHELT. DIRECTE 10,461.99 4,383.38 856.34 1,561.88 17,263.60
Cheltuieli indirecte Io = ### x To 1,726.36
Profit Po = 5.000% x (To+Io) 949.50
Valoare (in preturi oferta) Vo = To+Io+Po 19,939.45
Valoare (actualizata) V= 1 x Vo 19,939.45
Organizare de santier OS = 0.000% x V 0.00
Total fara TVA 19,939.45
T.V.A. TVA= ### x (V+OS) 3,987.89
TOTAL GENERAL situatie lucrari 23,927.34

Beneficiar, Constructor,
Explicatii Valoare Explicatii
Acc. munca, boli profes. 0.00270 Material pret oferta
C.A.S.S. 0.05200 Manopera pret oferta
Impozit manopera 0.00000 Utilaj pret oferta
Coef.maj. pret material 1.00000 Transport AUTO pret oferta
Chelt.tr.aprov.,depozit. 0.00000 Transport CF pret oferta
Coef.maj. pret tr. auto 1.00000 Alte transporturi pret oferta
Coef.maj. pret tr. C.F. 1.00000 Material beneficiar pret oferta
Transport lei/tona 0.00000 Material demontat-remontat pret oferta
Coef.maj. pret manopera 1.00000 Material pret plata
Coef.maj. pret utilaj 1.00000 Manopera pret plata
Coef.actualiz.inflatie 0.00000 Utilaj pret plata
Salarii maistri 0.00000 Transport AUTO pret plata
C.A.S. 0.15800 Transport CF pret plata
Cheltuieli indirecte 0.10000 Alte transporturi pret plata
Manopera indirecta 0.00000 Material beneficiar pret plata
Aj.somaj 0.00500 Material demontat-remontat pret plata
0.00000 Greutate (T)
Profit 0.05000 Ore manopera
T.V.A. 0.20000 Utilaje termice
Coef.neacop.manopera 0.00000 Utilaje electrice
0.00000 Executant
Organizare de santier 0.00000 Denumire Executant
Coef.mat.demontat-remont 1.00000 Obiectiv
0.00000 Denumire Obiectiv
Fond garantare salarii 0.00250 Obiect
Pondere man.in chelt.uti 0.20000 Denumire Obiect
Pondere man.in chelt.tr. 0.20000 Categorie
Contr.Concedii Medicale 0.00850 Denumire Categorie
Diverse si neprevazute 0.00000
Proiectare 0.00000 Denumire
lnOri 1
Ordin de marime:(lei,mii,milioane) 1.00 Denumire
Curs 1.0000
Moneda Denumire
Mat.ben se scade din total A/General [A/G] G
Explicitez cheltuielile generale ? [D/N] N
Separator zecimal . Coeficient actualizare plata
Antet N

OFERTANT OFERTA

Sistem informatic proiectat de SofteH Plus srl. Tel:323.78.37 Data listarii:10/31/2019 Pag.3
Valoare
10,461.99 lin/pag 54
3,567.50 proiectant N
856.34
1,561.88
0.00
0.00
0.00
0.00
10,461.99
3,567.50
856.34
1,561.88
0.00
0.00
0.00
0.00
62.217
356.0000
794.54
61.80
UPB
URBAN PROIECT BARLAD
015
FUNDATIE REZERVOR APA 109MC
01
FUNDATIE REZERVOR
01
REZISTENTA

OFERTANT