1.0 INTRODUCTION 5.7 Hard landscape 134 APPENDICES
1.1 Overview 2 5.8 Furniture 136
2.1 Context 8 5.11 Landscape management 152 A1.2 Condition A4: Phasing Details 367
4.0 PHASE 1 RMA MASTERPLAN 7.2 Millennium Mills 186 A3.5 Bird hazard management plan 382
4.2 Layout 44 7.4 Plot 1 282 A3.7 Bird survey results 387
5.6 Industrial archaeology - found landscape 132 9.2 Design Code compliance 417
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 1
1.0
Introduction
1.1 OVERVIEW
1.1.1 INTRODUCTION In terms of further planning context, the
location of Phase 1 was included as part of
1.1.2 PURPOSE OF THE extensive consultation with LBN planning
and design officers, in addition its Design
This Design and Access Statement (DAS) has the ‘Site Wide Phasing Plan’ submitted under DAS Review Panel (DRP), at pre-application stages.
been prepared on behalf of The Silvertown Approval of Details application reference The proposals have also been informed by
Partnership LLP (TSP, the Applicant) to 19/01395/AOD relating to Condition A3 (Phasing This DAS has been prepared to accompany a series of public consultation events, which
accompany a Reserved Matters Application for Strategy). the Phase 1 RMA. have allowed the local community and other
Phase 1 (the Phase 1 RMA) of Outline Planning local stakeholders to input in the Phase 1 RMA
Permission reference 14/01605/OUT (the OPP) Certain details of Phase 1 were also included The purpose of this document is to set proposals.
granted on the 19th of August 2016 by the under Approval of Details application out the proposed design and architectural
London Borough of Newham (LBN) regarding reference 19/01923/AOD relating to Condition approach concerning the Phase 1 RMA In addition, this document identifies how the
the redevelopment of the site known as A4 (Phasing Details). This established the proposals, notably in relation to their Phase 1 RMA proposals relate to the OPP and
Silvertown Quays (the Site). principles of Phase 1 RMA in relation to proposed Scale, Appearance, Layout, Access relevant approved documents, notably the
phasing; affordable housing; public open and Landscaping approach (in accordance following:
In summary, the OPP was approved with all space, public realm and landscaping; car, with Condition A1 of the OPP).
• The series of Parameter Plans approved
matters reserved except for Access for the cycle, motorcycle and powered two wheeled
under the OPP;
redevelopment of the Site for mixed use vehicle parking; shared energy infrastructure; A variety of architectural teams have
purposes, including the alteration, partial waste and servicing; and the chargeable been involved in designing the Phase 1
development(s) comprised in that Phase for • The OPP ‘Design Code’ document;
demolition and conversion of the Millennium RMA proposals, and Prior + Partners has
Mills and the construction of buildings the purposes of the Community Infrastructure undertaken a masterplanning role in
Levy Regulations 2010 (as amended). The • Relevant aspects of the Reserved Matters
across the Site to include Brand buildings coordinating this process to help ensure a
Phase 1 RMA has been submitted to be Specification at Annexe A of the OPP.
(Sui Generis), Residential (Use Class C3), ‘coordinated variety’ of design throughout
Office (Use Class B1), Retail (Use Classes A1- consistent with these approved details. Phase 1 RMA. The full project team is included
A5), Leisure (Use Class D2), Education (Use in Section 1.1.5 The team on page 5.
Class D1), Hotels (Use Class C1), other Non- This DAS explains the design of the Phase 1
Residential floor space such as community RMA proposals, including how the proposals The overall design of the proposals is the
use (Use Class D1) and associated works. relate to the above planning context and result of an iterative process, including
requirements of the OPP.
The Phase 1 RMA description of development
is:
2 Introduction | 1.0
1.1.3 THE PHASE 1 RMA
SITE
The Phase 1 RMA Site is located in the western
part of the Site. The Phase 1 RMA Site is
designed to link Royal Victoria Dock with
North Woolwich Road, establishing a vital
north-south connection from the outset of
the project for residents and visitors to use.
Phase 1 includes the Millennium Mills building
and proposes new development to the south
and west of Silo D, ensuring both heritage
assets are embraced. The Phase 1 RMA Site
is also deliberately located to the west of
the Site to provide direct connections to and
integrate with the existing Britannia Village
community. The development of Phase 1 RMA
will also serve to partially screen Britannia
Village from future construction Phases 2-7.
OPP Boundary
Figure 1.1 Aerial view of the Phase 1 RMA Site within the OPP Boundary
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 3
1.1.4 TIMELINE
30th September
RMA
Submission
COMMUNITY
CONSULTATION Ongoing online public consultation
18th & 21th May 13th & 16th July 7th September
Public consultation Public consultation Public consultation
Workshops / Site Visit Emerging Proposals Detailed Proposals
4 Introduction | 1.0
1.1.5 THE TEAM Company Discipline Website
This DAS has been prepared by Prior + Acoustic engineer, security and
Hilson Moran hilsonmoran.com
Partners with input from the project team. facade access
Meinhardt Facade engineer (commercial) meinhardtgroup.com
The client team - The Silvertown Partnership Wintech Facade engineer (residential)
Lendlease www.lendlease.com AKT II Structural engineer akt-uk.com
Starwood Capital www.starwoodcapital.com Hurley Palmer Flatt Vertical transportation engineer hurleypalmerflatt.com
Allford Hall Monaghan Morris Architect - Plots 2, 3 & 4 ahmm.co.uk
Landowner
Alinea Cost consultant - Plots 2 & 3 alineacostconsulting.com
Greater London Authority www.london.gov.uk
Arcadis Cost consultant - Plot 4 arcadis.com
Hurley Palmer Flatt MEP engineer - Plots 2 & 3 hurleypalmerflatt.com
Hilson Moran MEP engineer - Plot 4 hilsonmoran.com
The project team dRMM Architect - Plot 1 drmm.co.uk
Pollard Thomas Edwards Architect - Plots 5 & 8 pollardthomasedwards.co.uk
Company Discipline Website
MaccreanorLavington Architect - Plots 6 & 7 maccreanorlavington.com
Prior + Partners Masterplan / lead designer priorandpartners.com
Energy and overheating - Plots 1,
Churchman Thornhill Finch Landscape architect churchmanthornhillfinch.co.uk Bryden Wood brydenwood.co.uk
5, 6, 7 & 8
West 8 Landscape architect west8.com Lendlease Principal Designer www.lendlease.com
DP9 Planning dp9.co.uk Turner and Townsend Principal Designer Advisor turnerandtownsend.com
Kanda Consulting Community engagement kandaconsulting.co.uk
Arup Transport and waste arup.com
AECOM Infrastructure engineering aecom.com
Lord Consultants Accessibility lordconsultants.org.uk
Bickerdike Allen Partners Acoustics bickerdikeallen.com
Eddowes Aviation Safety Aviation eddowesaviationsafety.com
CONSIL Daylight www.consiluk.com
Greengage Ecology greengage-env.com
Donald Insall Associates Heritage donaldinsallassociates.co.uk
Michael Grubb Studio Lighting michaelgrubbstudio.com
Beckett Rankine Marine civil engineering beckettrankine.com
BuroHappold Sustainability burohappold.com
RWDI Wind rwdi.com
BRCS Approved inspector brcs.co.uk
Table 1.1 The project team
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 5
2.0
The Site
2.1 CONTEXT
2.1.1 SITE LOCATION
WITHIN LONDON
Silvertown Quays is located in East London,
and the opening of the new Elizabeth Line will
improve connectivity to central London, with
travel times to Central London of 15 minutes
(to Tottenham Court Road Station), and 50
minutes to Heathrow Airport.
Stratford
King’s Cross
Liverpool London
Tottenham
Street City
Court Road Custom
Line Canary
et h Paddington House Airport
El izab Wharf
London
15 min Bridge 4 min
Victoria Silvertown
Heathrow
Airport
50 min
London City
Canary SILVERTOWN Airport
Wharf
O2 Arena
Silvertown
Tunnel
(proposed)
River Thames
Major activity areas
Woolwich
National Rail
Millennium
London Underground Leisure Park
Elizabeth line
Royal Docks
Commercial concentration
OPP Boundary
Borough boundary
Figure 2.2 Silvertown Quays within Newham
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 9
2.1.3 SURROUNDING
CONTEXT
The residential neighbourhood of Britannia
Village lies directly to the west of the Site,
comprising of residential-led development and
community uses including a primary school
and community centre. ExCel
Connaught Bridge
and the Thames Barrier Park. There are
a number of existing and emerging new
developments to the south of North Woolwich Royal Victoria Dock
Road, notably Royal Wharf, Barrier Park East,
Barrier Point and Pontoon Dock. In addition, London City
the River Thames and the Thames Barrier are Airport
Rank Hovis
located to the south of the Site, and Lyle Park Millennium
Mills
is located to the southwest.
Silvertown
London City Airport is located to the east on
the opposite side of Connaught Bridge. Britannia Village Pontoon
Dock
Mill Road
Silo D
exhibition and conference centre, is located to
the north of the Site, on the opposite side of
Royal Victoria Dock. The Royal Victoria Bridge lwich Road
Nort h Woo
currently provides a high-level pedestrian
footbridge connection across Royal Victoria Tate & Lyle Barrier
Park East
Dock.
Thames
Royal Barrier
Wharf Park
Barrier
Lyle Park Point
Residential Community
Commercial Culture
Hotel Airport
River Thames
ExCel Phase 1 RMA Boundary
PEDESTRIAN
MOVEMENT Custom House
Prince Regent
Royal
The Site currently benefits from a Public Victoria
Transport Accessibility Levels (PTALs) rating
of 2. Pontoon Dock DLR Station is the closest ExCel
station and is located to the south, on the
opposite side of North Woolwich Road.
Custom House Station is located to the north Connaught bridge
of the Site, on the other side of Royal Victoria
Dock, beyond the ExCel Exhibition Centre.
It currently provides DLR services and will
also benefit from a new Crossrail station The Crystal
(the Elizabeth Line) once these works are London
completed. City Airport
Wesley Avenue
2.1.5 VEHICULAR
MOVEMENT Silvertown
Airport
Main roads
Figure 2.4 Wider context public transport, pedestrian and vehicular routes
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 11
2.2 HERITAGE
The Site is currently largely vacant. Historically Millennium Mills
it was used for dock related activities
London’s enclosed dock system was
including cargo handling, ship repair, the grain
established at the end of the 18th-century,
mills and flour milling.
prompted by severe congestion and lack of
safe trading on the Thames. The development
The main existing remnants from this previous
of the steamship in the mid-19th-century
use comprise of Silo D (a Grade II listed grain
saw a second wave of dock construction, as
silo structure located within the southwest of
it became necessary to construct ever larger
the Site) and Millennium Mills (a locally listed
and deeper docks to accommodate the vast
building located within the northwest of the
new vessels.
Site). The Site includes Pontoon Dock itself.
The vast majority of the remainder of the Site
The Millennium Mills complex consists
comprises of vacant brownfield land.
of four linked industrial structures dating
from c1905, 1933 and 1953. The buildings
Refer to separately prepared ‘Heritage Report’
are located on the southern edge of Royal
as part of this Application. A summary is
Victoria Dock, to the west of Pontoon Dock.
provided in this section.
The buildings are not statutorily listed, or
located in a conservation area, but have been
identified together as a complex as ‘locally-
listed’ by Newham Council. This means, in
heritage planning terms, that the complex is
considered a ‘non-designated heritage asset’. Figure 2.6 1957 Photograph of Millennium Mills Figure 2.7 Millennium Mills in 1960s, PLA Archives
Silo D
Figure 2.5 Built heritage within the Site Figure 2.8 Current Millennium Mills Figure 2.9 Millennium Mills in 1917, PLA Archives
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 13
2.3 OPPORTUNITIES AND CONSTRAINTS
2.3.1 OPPORTUNITIES Royal
Albert
Location Emirates Air Line Dock
Relationship to water
Two major water bodies (Royal Victoria Dock
and Pontoon Dock) offer opportunities for
interaction and views. London
City
Proximity to public transport Millennium Mills Airport
The Elizabeth Line at Custom House, the DLR,
Emirates Air Line (EAL) cable car, several bus
Wesley Avenue
routes and the pier at Royal Wharf are all in
close proximity and form excellent public
transport connectivity. Britannia
Village
Industrial heritage
The specific industrial background of the Site
sets up its identity and industrial character.
Phase 1 RMA has been designed with this Silo D
Mill Road
Royal
Wharf
Phase 1 RMA Boundary
OPP Boundary
)
Pub lic safe ty zon e (PSZ
+34.95 AOD
Utilities
+39.95 AOD
Inner horizontal surface
There are a large amount of redundant (IHS) +49.95 AOD 45m above
+44.95 AOD
utilities on the Site related to past industrial runway
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 15
Figure 3.1 Silvertown Quays OPP illustrative masterplan
3.0
The Outline Planning Permission
3.1 PARAMETER PLANS
The approved Parameter Plans (PP) formally
NOTES NOTES
Fletcher Priest Architects is a Limited Liability Partnership registered in Fletcher Priest Architects is a Limited Liability Partnership registered in
England and Wales (OC336568) at the below address. ≡ this drawing England and Wales (OC336568) at the below address. ≡ this drawing
is to be read in conjunction with the design risk assesment prepared by is to be read in conjunction with the design risk assesment prepared by
fpa. ≡ this drawing is to be read in conjunction with other drawings and fpa. ≡ this drawing is to be read in conjunction with other drawings and
specification produced by fpa and other members of the design team. ≡ specification produced by fpa and other members of the design team. ≡
(c) UKMap Copyright. The GeoInformation Group 2013 Licence No. (c) UKMap Copyright. The GeoInformation Group 2013 Licence No.
KEY: KEY:
Buildings to be demolished
Buildings to be retained
05 UC SH 080514
04 UC SH 280414
03 LT SH 170414
02 UC SH 200314
01 UC SH 120314
0 UC SH 040314
REV DESCRIPTION BY CHK DATE
07 18.09.2019 Planning amendments RB CC
06 04.03.2014 Outline planning submission
Rev Date Description Drawn Checked
Client
20 Triton Street
Regent’s Place
London NW1 3BF
Consultant
70 Cowcross Street
London
EC1M 6EJ
2B
1
2A
5
PARAMETER PLAN 04
6
8
7
1251 GA 03004
Project
RB CC TSP
Date Scale Size
1251 GA 03003 07
Figure 3.3 Parameter Plan 03: Proposed Site Levels Figure 3.5 Parameter Plan 04: Works to Existing Structures
Buildings to be retained
KEY:
Access point (pedestrian) 10m L.O.D Key public open spaces. Maximum
envelope
Access point (pedestrian/cycle/
vehicular)10m L.O.D Key public open spaces. Minimum area
Modifications to North Woolwich Road Open space area including water and
areas intersected by secondary street
Proposed primary roads +/- 10m L.O.D. (as identified on Parameter Plan 05) +/-
10m L.O.D highlighted with dashed line.
Proposed secondary roads +/- 10m Water is to be maximum 3m deep.
L.O.D.
Area of water, including buildings
Tertiary road +/- 10m LOD, can be covering not more than 50% of the
omitted to allow larger development area, +/- 10m L.O.D highlighted with
plots dashed line. Water is to be maximum
3m deep.
Primary pedestrian streets where
cycling is permissible and with fire Existing dock retained
access and out of house servicing
OS7
+/-10m L.O.D. Outline of existing dock wall in area
OS5
OS4
Figure 3.6 Parameter Plan 05: Roads and Routes Figure 3.8 Parameter Plan 06: Open Space
0 5 10 20 50m
N
Key
Outline planning permission boundary
Buildings to be retained
Buildings subject to part demolition
*
and rebuild, and part restoration
Extension to existing building with maximum
building heights as existing Millennium Mills
building
20 Triton Street
Regent’s Place
London NW1 3BF
Consultant
70 Cowcross Street
London
EC1M 6EJ
2B
1
2A
6
8
7
Project
PARAMETER PLAN 07
MAXIMUM BUILDING HEIGHTS
Purpose of drawing
CC GM TSP
Date Scale Size
20.08.2019 1:1500 A1
Drawing number Revision
1251 GA 03007 06
Figure 3.7 Parameter Plan 07: Maximum Building Heights Figure 3.9 Parameter Plan 08: Development Zones
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 19
3.2 APPROVED QUANTUM OF DEVELOPMENT
Parameter Plan 08 sets out Development
Zones.
1 145,000 29,000 24,000 29,000 3,300 9,000 16,000 1,900 700 213,000
1,900
2 0 0 53,000 0 800 0 0 1,400 56,00
7 0 0 0 0 0 0 0 0 0 0
Maximum
Floorspace 222,000 179,000 300,000 44,500 10,000 20,400 16,000 19,800 6,900 3,800 670,000
Permitted
Table 3.1 Development Zones and land use quantum as set out in Condition B4 of the OPP
Sustainability Code for Sustainable homes, BREEAM and Passive design techniques.
Key spaces The Waterfront, The Dock, The Diagonal and North Woolwich Road
Development Zone 1. Character Description, Quantum, Layout, Scale and enclosure, Access,
Millennium Mills District Landscape, Appearance and Millennium Mills
Development Zone 2. Character Description, Quantum, Layout, Scale and enclosure, Access,
Silo D District Landscape and Appearance
Development Zone 3. Character Description, Quantum, Layout, Scale and enclosure, Access,
Dock District Landscape and Appearance
Development Zone 4. Character Description, Quantum, Layout, Scale and enclosure, Access,
Ironworks District Landscape and Appearance
Development Zone 5.
Character Description, Quantum, Layout, Scale and enclosure, Access,
Eastern Residential
Landscape and Appearance
Neighbourhood
Phase 1 RMA Boundary Development Zones 6+7. Character Description, Quantum, Layout, Scale and enclosure, Access,
Eastern Waterfront Landscape and Appearance
OPP Boundary
Figure 3.10 Extract from Parameter Plan 08 showing Table 3.2 Design Code summary
Development Zones relevant to Phase 1 RMA
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 21
3.4 BRAND USE
Offices / headquarters
The Phase 1 RMA places Brand Use at the
heart of the design concept.
Silvertown Brand Strategy
The Silvertown Brand Strategy is outlined in
the Draft Brand Marketing Strategy approved
The role of brand within the
The office buildings identified in the masterplan are
masterplan
under the S106 Agreement.
HOSPITALITY
generally located
A key aspect of the OPP is thein the southern
inclusion of part of
The strategy is forthe site to comprise a
Silvertown
southern
The evolution part of the site,
of brands
DLR station.
near Brands
Destination the Pontoon Dock
that are closely identified
with Silvertown and its immediate locality
will be prioritised, providing a more authentic
Brands have evolved over the course of the
FOOD AND
BEVERAGE RE
destination experience for visitors and PARKING
2.7.10 Buildings should engage withlocal
21st Century; the rise of internet shopping,
enabling
the decline of the traditional high street and
the public
businesses andat ground
organisations
floor; frontages should to
be mainly glazed and
benefit from the Brand approach. They
the fractioning of global corporates have
will be further defined and established prior
facilitated changes to the perception of
‘brands’. blank elevations avoided.
to occupation of the Brand Units through Figure 3.11 Trading House illustration (from Design Code)
promotional activities to be carried out by
2.7.11 Lobbies
These changes should
have facilitated growth be
in designed as active frontages
umbrella, destination and community / small
TSP.
withenterprises
and medium-sized a direct relationship
(SME) brands. to the adjacent public
realm.
2.7.12 Buildings are to have an uncluttered and simple
roof profile with all plant equipment concealed
O
Figure 3.12 Peckham Levels, London Figure 3.13 Ponce City Market, Atlanta
1. Brands based on the iconic identities of the Figure 3.14 The Brand spectrum showing example Brands
existing buildings: including Millennium Mills,
the Hovis Building and Silo D.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 23
4.0
Phase 1 RMA masterplan
4.1 VISION
Silvertown Quays offers the opportunity to from - inspiration to draw into design and Place Principles Place Pillars
create a unique and exciting place, celebrating inform the development.
Let it Rip Turn up the Volume Create an active waterscape
heritage, activating the water and creating a
new centre for the Royal Docks. Place Narrative
Once the engine room of London, Silvertown Place water at the heart of the Silvertown
In Silvertown, an entrepreneurial attitude has big personality and huge horizons. Its experience to become its defining
The vision for Silvertown Quays was set out turns bright ideas into bold realities - with industrial heritage provides a continuum characteristic.
in the OPP, and in preparation of the RMA this space to let rip and radical partnerships to between the tribes and subcultures of future
was supplemented with a vision document, make a place without precedence. and past. A place to expect the unexpected. Millennium Mills As A Cultural Beacon
the ‘Place Platform’, adding extra layers to the
ambition for Phase 1 RMA.
Somewhere that's empowering - where self- For the entrepreneurial and self-made Create a new regional destination for London
made culture gives local talent a chance to
4.1.1 PLACE PLATFORM shine bright. Where the Royal Docks global Silvertown is internationally connected and
with layers of activity that guarantee a good
‘day out’ for visitors.
outlook welcomes the world in all its vivid will be locally self-sustaining.
Silvertown Quays is a site that has captured
wonders. Where new energy brings the flow Establish a new centre of gravity
the imagination of some of the worlds most
back to Silvertown, yet a growing community Building on its entrepreneurial past, this will
creative minds. Founded by industrialist J.W.
is rooted in a place they call home. be a proud place that incubates talent and Establish a much needed centre for the Royal
Silver, it's been a place that has pioneered
production, inspired ground-breaking grows jobs. Docks, a place to meet neighbours and make
Enlightened, entrepreneurial, empowering: friends; a heart for the community.
performance, intrigued urban explorers and
Silvertown is born from brilliance. Embrace radical partnerships
marked the frontier of architectural thinking.
Bring back the flow
With the input of key stakeholders and Understanding local talent and culture –
industry leaders, and testing through public building meaningful long-term relationships Thinking outside our site boundary to re-
consultation, we have developed a Place – bringing people and organisations together connect the disparate communities of the
Platform for Silvertown - a dynamic manifesto from different disciplines and minds to Royal Docks, and Newham.
for the development that will evolve as we collaborate and add value.
gain more knowledge about this site, its
context and community, and as activation and Meet the world and wonder
place unfolds. Comprising of Place Pillars and
Place Principles, it is an overarching narrative A place that was once the gateway to the
for Place that will inject life, culture and world and is surrounded with international
people; our guiding light for the development neighbours. Silvertown will be an emporium
that expresses our aspiration for the site and of cultures – a microcosm of London that will
sets out our direction for the coming years. determinedly remain open to the world. A
place in Newham that represents the diversity
The Place Principles establish the attitude of Newham.
required to execute a site of this scale
and stature. They are a tool that enables
constructive debate around alternative
scenario's and helps stakeholder teams
resolve which decision to take.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 27
PLACE PILLARS
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 29
Principle 1 - Creating a ‘piece of city’ Principle 2 - Respecting the heritage of the site
Silvertown Quays should grow into a piece of robust, Retained heritage assets (Silo D, Millennium Mills and
4.1.2 THE OPP MASTERPLAN PRINCIPLES legible and familiar urban fabric that is accessible for
all, containing streets and spaces, a mixture of uses that
Rank Hovis) will be brought back into productive use.
Parts of the docks, including bodies of water and sections
support one another. of the existing dock wall, will become integral parts of the
These masterplan principles were established in the OPP Design Code. design and help determine character of Silvertown Quays.
Principle 1 - Creating a ‘piece of city’ Principle 2 - Respecting the heritage of the Principle 3 - Establishing key views Principle 4 - Responding to primary
Silvertown Quays should grow into a piece of robust, site Within the site, strategic and glimpsed views to Silo transport connections
legible and familiar urban fabric that is accessible for Principle
D and Millennium 3 - Establishing
Mills will organisekeythe
views
alignment Principle 4 - Responding to primary transport
Retained heritage assets (Silo D, Millennium Mills The connections to Crossrail and the DLR will form
all, containing streets and spaces, a mixture of uses of streets and distant
Within views
the site, to Canary
strategic Wharfviews
and glimpsed connections
andto Silo D and a primary
and Rank Hovis) will be brought back into productive axis to form the armature of pedestrian
that support one another. use. Parts of the docks, including bodies of water Millennium
the River Thames will Mills will organise the
be established. alignment
Buildings will The connections
of streets movement to Crossrail
and public and the DLR will form
activity.
and sections of the existing dock wall, will become and
be set out so distant
that views toof
glimpses Canary
waterWharf
will and
be the River Thames
visible a primary axis to form the armature of pedestrian
integral parts of the design and help determine from within will
thebe established.
urban fabric Buildings
and from willhigher
be set out so that
levels in movement and public activity.
character of Silvertown Quays. buildings. glimpses of water will be visible from within the urban
fabric and from higher levels in buildings.
Principle 5 - A new focus for the south of Principle 6 - Response to existing and Principle 7 - Plot configurations Principle 8 - Phasing
the docks emerging context The parcels of land formed by primary routes will Development that can be phased and where each
The masterplan will help to provide a focus for public Routes through the site will be aligned with existing create a robust plan that allows for a number of plot phase contains a mix of uses.
life, introducing new local retail and community roads in the immediate context to form good quality configurations and is adaptable to changes in use.
uses and creating a mixed use focus that will be connections. Land use distribution shall be considered
used by existing and new neighbours, including the in the context of the wider area.
communities in Britannia Village, Barrier Park East and
Minoco Wharf/Royal Wharf.
Create neighbourhoods around North-south link Make use of the water Gateway in the north,
the heritage of the Site neighbourhood in the south
Royal Victoria
Dock
Mills Quarter
Silo D Quarter
Finger
dock
Millennium Mills and Silo D are the starting The visual connection between the two Mills Quarter is located on Royal Victoria Mills Quarter is the main gateway to the Site.
point for two new neighbourhoods, their existing buildings, as well as a desire Dock, and Silo D Quarter on the finger dock Silo D Quarter complements two residential
character defined by these heritage assets. line between existing and proposed of Pontoon Dock. Both present a unique neighbourhoods, Britannia Village to the west
These neighbourhoods will form a new heart neighbourhoods and public transport, make opportunity to break the hard edge of and Royal Wharf to the south, and forms a
for the Royal Docks. the north-south connection a key move for Pontoon Dock and make use of the water, buffer to minimise construction disruption to
the Phase 1 RMA. creating an active waterscape. the west.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 31
4.1.4 PHASE 1 RMA IN
CONTEXT
At the heart of the Royal Docks, Silvertown
Quays is a new centre of gravity for the
surrounding areas. Both quarters, Silo D
Quarter and Mills Quarter, are defined with
the aim to link into existing context and
communities, making use of existing road
connections.
Figure 4.5 Thames Barrier Park Figure 4.6 Boxley Street, Britannia Village Figure 4.7 Barrier Park East
Hotels
BUSINESS AND
COMMERCE
SPORTS AND
RESIDENTIAL RECREATION
Excel
Mills Quarter
Britannia Village
Silo D Quarter
Silo D
Pontoon Dock
Station
Thames
Barrier Park
Royal Wharf
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 33
Mills Quarter
Silo D Quarter
For future phases, Phase 1 RMA will set the
standard for architectural quality across
the Site, the massing and facade treatment
along North Woolwich Road, the relationship
of buildings to the water and the use of
industrial heritage and found landscape
across the Site.
Figure 4.11 Illustration of Silo D Park Figure 4.12 Illustration of Silo D Park
Mills
Quarter
2B
1
3 DZ6
2A
DZ3
4
5 Silo D
Quarter
DZ5
Mill Road
6 DZ4
8
lwich Road
North Woo
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 35
4.1.6 OPEN SPACE Water Dock Waterfront precedent photos
Figure 4.16 Granary Square, London Figure 4.17 Ice Watch by Olafur Eliasson and Minik
Rosing, Tate Modern, London
Dock Waterfront
Silvertown
2B
Place
1
3
2A
Mills Square
Figure 4.19 Kingsland Basin, London Figure 4.20 Regent’s Canal at King’s Cross, London
Pontoon Dock
5
Silo D Park
Mill Road
ger
F in k
6 doc
8
lwich Road
North Woo
Figure 4.18 Phase 1 RMA open space Figure 4.21 Terrace along River Lee Navigation, Figure 4.22 East Village, Stratford
Hackney Wick, London
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 37
4.1.7 PHASE 1 RMA
CONNECTIONS
Royal Victoria Dock Bridge provides a key
connection into the Site from the north (the
Bridge will be subject to a separate planning
application).
Millennium Mills
Wesley Avenue
Silvertown Avenue
Evelyn Road
oolwic h Road
Nort h W
ay
Cunningham
Barrier Point
W
Admiralty
d
ar
Avenue
Avenue
bo
Road
ar
St
Figure 4.23 'Trident' of routes into Royal Wharf Figure 4.25 The Site with Pontoon Dock DLR and Royal Wharf in the background
Thames
Barrier
Park
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 39
4.1.8 CHARACTER
AREAS
Landmarks Heritage Access + movement
Phase 1 RMA is divided into two distinct Millennium Mills as a new cultural beacon Bring back the flow - celebrating the Site’s Pedestrian environment with easy access to
character
s: Ground floor plan showingareas, each
uses and reflecting
public access the different
Illustrative view of the proposed ground floor interior of the Mills
industrial past public transport
living, working and recreational elements of
the new Silvertown Quays. Each area has a
distinct character, defined by its location and
primary activities.
1. Mills Quarter
This is one of the most intensely animated
areas of the masterplan characterised by
intensive public activity, both within the
public realm and on the ground floor of the
buildings. It will be a regional destination for
visitors.
Mills from across the Dock Illustrative view of the proposed refurbished Mills from across the Dock
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 41
2. Silo D Quarter
Set around the grade II listed Silo D, this is a
predominantly residential area.
Landmarks Heritage Access + movement
Silo D will be set in a park, and the south Grade II listed Silo D & finger dock serve as Bring back the flow - celebrating the Site’s Pedestrian environment with easy access to
facing finger dock will be accessible and the focal point of the area industrial past public transport
activated. The plots surrounding the park will
be designed as a backdrop to the Silo D.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 43
4.2 LAYOUT
4.2.1 ILLUSTRATIVE Plots and urban grain Key areas
Phase 1 RMA consists of eight building plots 1 Royal Victoria Dock Bridge
MASTERPLAN that frame a series of significant public
spaces and exceptional streets. Building 2 Millennium Mills
The illustrative masterplan shows Phase
massing relates to the context of the existing
1 RMA in existing context. It aims to
heritage assets, whilst creating building blocks 3 Mills Square
demonstrate how the plots and public realm
with enough space and light for amenity in
combine to create successful spaces and
courtyards. 4 Silvertown Place
buildings.
The urban grain balances permeability whilst 5 Dock Waterfront
Public realm structure
defining activate streets and spaces.
The Phase 1 RMA public realm is shaped by 6 Silvertown Avenue
the design principles and key moves described
in Section 4.1.2 and 4.1.3, and was structured 7 Silo D
by the Parameter Plans.
8 Silo D Park
The aim has been to create a clearly legible
network of streets and spaces, a ‘piece of 9 Silo D Bridge
city’. Legibility is reinforced by key vistas
towards Millennium Mills and Silo D (as 10 Pontoon Dock Station
described in the Design Code, see also
Section 9.2.2 Key vistas on page 419) 11 Thames Barrier Park
5 5
4
2 PLOT 2B
PLOT 3
PLOT 1 PLOT 2A
Mills way
Wesley Avenue
PLOT 4
12
6
Evelyn Walk
PLOT 5
Silvertown Street
7
Mill Road
9 de
Bar
a l si
Can
r ier
P oin
PLOT 6
t Ro
Sil o
PLOT 8
ad
DW
PLOT 7
ay
10
ich Road
North Woolw
13
11
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 45
4.2.2 LAND USE Royal Victoria Dock Bridge
alignment and pontoons
Rayleigh Road
and adjacent Plot 4. This commercial cluster 2B
Place Hovis Yard
will offer active ground floor uses showcasing
brands, with exhibition, event, gathering Mills Square
1 3
and flexible working space accompanied by
2A
dedicated Brand retail.
Hovis Street
Mills way
The Phase 1 RMA will also include Local A1
Silvertown Avenue
Wesley Avenue
Retail and Food and Beverage A3-5 uses. 4
Silvertown Street
a maximum of 800 sqm Food & Beverage
A1 Retail 5
A3-A5, 1,900 sqm Community & Education
D1 and no allowance for other uses except Dedicated
residential). The focus is on activating the Brand Food and
Beverage A3-A5 DZ3
edge of Silo D Park, marking the arrival to the
Mill Road
Site at Silvertown Street, and activating the Food and Silo D Park
corners of the plots at North Woolwich Road Beverage A3-A5 DZ4
with community uses.
Local Retail A1
Barr
e
6 a l sid
Can
ier P
Sil o
8
o int
DW
Ro a d
Brand
ay
7
lwich Road
North Woo
Community
Residential
Core, circulation
Other
Figure 4.30 Ground level uses
DZ1 Brand
49,931
(Excl. Retail)
Dock Waterfront
Office (B1) 16,865
Silvertown
Rayleigh Road
2B*
Place Hovis Yard
Residential (C3) 87,989
Mills Square
1 3
2A* Brand A1 Retail 115
Hovis Street
Mills way Dedicated Brand
172
Food and Beverage
Silvertown Avenue
Wesley Avenue
A3-A5
4*
Local Retail
511
A1
DZ3
Mill Road
Silo D Park
DZ4 *Note:
Upper floors of Plots 2A, 2B and
Barr
Ro a d
ay
7
lwich Road
North Woo Office+Brand
Brand
Residential
Core, circulation
Figure 4.31 Typical upper level uses
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 47
Active frontages Royal Victoria Dock Bridge
alignment and pontoons
Frontages have been designed to complement are indicative and subject
to change under separate Royal Victoria Dock Bridge
the streetscape, with a range of retail uses planning application.
(Local A1, Food and Beverage A3-5) along
key open spaces and residential lobbies
positioned to activate streets.
Dock Waterfront
Active frontages are concentrated at the main
Silvertown
Rayleigh Road
entrances to the Site, the proposed Royal 2B
Place Hovis Yard
Victoria Dock Bridge landing to the north and
Silvertown Street to the south, as well as
Mills Square
along the key open spaces, Mills Square and 1 3
Silo D Park. 2A
Hovis Street
Mills way
Because of the specific layout of Phase 1 RMA,
in particular the newly introduced north- Wesley Avenue
4
south connection (Silvertown Avenue), the
Silvertown Avenue
active frontages strategy as described in the
Design Code was updated. Figure 4.33 shows
the updated strategy, with added focus on
Silvertown Avenue and key open spaces.
The frontages strategy for North Woolwich
Road, to activate the corners of the plots, is Evelyn Walk
partly derived from the area limitations on Figure 4.33 Updated active frontages strategy
active uses in DZ2, as well as the decision to Dedicated Brand
Silvertown Street
Main frontages
prioritise Silo D Park for Food and Beverage A1 Retail 5
A3-5 uses. Open spaces
Dedicated Brand
A3-A5 Food and
Beverage
Mill Road
Food and Silo D Park
Beverage A3-A5
de
Bar
Local A1 Retail a l si
Can
r ier
6
P oin
Sil o
8
t Ro
DW
Brand
ad
ay
7
lwich Road
North Woo
Community
Residential
Core, circulation
Other
Figure 4.32 Active frontages in Phase 1 RMA
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 49
4.2.3 MEANWHILE USES Royal Victoria Dock Bridge
alignment and pontoons
are indicative and subject
Meanwhile uses will be the subject of to change under separate Royal Victoria Dock Bridge
planning application.
separate applications in the future but this
indicative section is included in the DAS
because of the important role they will play
in the creation of a place in Phase 1 RMA to Dock Waterfront
complement the construction phasing.
Silvertown
Rayleigh Road
2B
Uses described below are subject to change, Place Hovis Yard
and future planning applications.
Mills Square
1 3
Connecting north and south 2A
Hovis Street
Mills way
Line station, the north-south connection
Wesley Avenue
through the Phase 1 RMA Site will generate
4
high pedestrian footfall. A combination of
Silvertown Avenue
1
community spaces and pop-up retail will be Construction
used to improve the experience of the route compound
and help make it a destination as well as a 3
thoroughfare.
Silvertown Street
Square, the space to the south will be used
5 2
as a laboratory for future uses taking place in
the square, while after delivery it will create
an edge, helping define the square.
5
Mill Road
Silo D Silo D Park
Silo D lies at the heart of a residential 4
community, the forming of which can start de
a l si
Bar
early with meanwhile uses around Silo D 6 Can
r ier
that will test permanent uses, and with
P oin
community gardens along the finger dock. 8
Sil o
t Ro
DW
7
ad
ay
lwich Road
North Woo
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 51
4.2.4 DESIGN Starting point: The OPP Initial scheme development desire to link the proposed Phase 1 RMA
Development to the surrounding context.
The OPP sets the design parameters for the The scheme was further developed
EVOLUTION scheme. The starting point for designing the three-dimensionally in conjunction with
scheme was therefore the OPP Parameter LBN planning officers and DRP input,
The design for Phase 1 RMA has evolved from
Plans. balancing the Parameter Plans constraints
from the approved Parameters and Design
Codes into a fully resolved scheme creating for development quantum and maximum
a new centre for the Royal Docks with world building heights with the Phase 1 RMA
class open spaces, high quality homes and a design ambitions, particularly around the
new piece of city for London. creation of the two new neighbourhoods
Mills Quarter and Silo D Quarter and the
Custom
House
Station
Pontoon
Dock Station
Thames
Barrier
Park
Royal Wharf
High street
Figure 4.36 The OPP illustrative masterplan Figure 4.37 Axonometric initial scheme development
Figure 4.38 Axonometric detailed scheme development Figure 4.39 Axonometric proposed scheme layout
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 53
4.3 SCALE
4.3.1 MASSING
Massing and scale of proposed buildings has
Response to
been carefully considered in order to improve waterfront
townscape, with a focus on creating a sense
+5m
of arrival and place and providing clarity
and comfort at street level. Interest and 2B 2B
wayfinding is provided along key routes by
variation in height and designs, especially at 1 3 1 2A 3
key junctions and spaces. 2A
Response to +39.9m
the Mills
Building heights are constrained by OPP
Response to Response to +49.9m
Parameter Plan 07 (overlaid onto the plan 4
circus the Mills 4
on Figure 4.40), which are largely based on
the City Airport height restrictions, with the
addition of restrictions around Millennium
Mills, Silo D and a zone adjoining West
Silvertown.
+25m +44.9m
5 5
to Mill Road
Response
6 6
+5m
8 8
7 7
+49.9m
Response to
North Woolwich
Road
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 55
4.4 APPEARANCE
4.4.1 KEY VIEWS Response to waterfront Elevation Prominent Facade to No
The waterfront is the main gateway to the Site designed base at emphasise projecting
A set of basic guidelines underpin the design for people arriving from Custom House. Plot as primary bridge arrival views from balconies
of all buildings across the Site. 1 should relate to Millennium Mills and the gateway apartments
waterfront as well as acknowledge the arrival
• The base, middle and top of each building experience. Top
are clearly identified, considering the
individual building as well as adjacent plots
Void
Top
Building proportions
to respond to
Millennium Mills
1A Key view - far 1B Key view - middle
Bridge approach
Articulation of the
Top
facade to reflect
Millennium Mills
Middle
Base
2B
2A
Facade
1 3 treatment to
respond to circus
3B 4
3A
2A
Scale in
5 relation to
context
6
Lower volume
8 relates to the
7
human scale
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 57
Design principles - Silo D Quarter Response to North Woolwich Road Views to
For the southern section of Phase 1 RMA, Plots 6, 7 and 8 need to propose continuity the river
along North Woolwich Road. Consideration
three additional key elevations were used to
should be given to rhythm of facade openings
define building mass and articulation, forming and views.
a starting point for the plot architects to
Top
develop their designs.
Plot 8 Plot 7
The Silvertown Street facade is again a
backdrop to Silo D, and due to its length,
the rhythm and repetition are important Silvertown Street Explore continuity Parapet Plots 5 and 6
considerations for the design. The elevation along Plots 5 and 6 should be across Plots 5 detail similar rhythm
designed with consideration for the rhythm and and 6 with level and repetition
repetition of both facades. Between Plots 6 and difference
7, the entrance to the Site should be treated as
a main gateway.
Top
Middle
Base
Plot 6 Plot 5
Base
Base
Response to Silo D
Different
Facade treatment
designed as within same
backdrop to parameters Base to
Silo D respond to
residential use
and Canalside
Base
Silvertown Street
Facade
2B designed as
1 2A backdrop to
3
5A
5
6A
6 5C
Base
8
7 4B
6B
4A
4C
6A Key view - far 6B Key view - close
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 59
4.4.2 MATERIAL Mills Quarter
CONCEPT
The choice of materials will be defined by the
following key concepts:
Mills Quarter
Silo D Quarter
Figure 4.43 Plot 1 materiality Figure 4.44 Plots 2A, 2B, 3 and 4 materiality
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 61
4.4.3 VIEWS
In addition to the Site key vistas set out in the
Design Code, additional illustrative views have
been added for Phase 1 RMA specifically.
Mills Square
The view in Figure 4.46, looking north from
Mills Way, shows Mills Square with Millennium
Mills as its backdrop. It illustrates potential
activities within the square as well as the
relationship of the existing building with the
new open space.
Figure 4.47 Illustrative view of Millennium Mills and Plot 1 from ExCel
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 63
Finger dock
The view in Figure 4.48, from Plot 6 looking
east, is focused on the finger dock in front
of Silo D and shows water activation and the
relationship of Silo D and Plots 7 and 8 with
the finger dock.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 65
4.5 ACCESS
4.5.1 WIDER CONTEXT 4.5.2 ACCESS TO Emirates Air Line cable car
The EAL cable car is approximately 1.3km
PEDESTRIAN AND PUBLIC TRANSPORT to the northwest of the Site, using the
CYCLING ROUTES Public transport networks in the vicinity of
pedestrian footbridge to cross the Royal
Victoria Dock. The EAL runs across the River
the Site are broadly consistent with those
In the wider context, Silvertown Quays will Thames from the Royal Docks to Greenwich
identified in the OPP, with recent changes
play a key role in connecting cyclists and Peninsular with a cabin arrival every 30
limited to minor frequency alterations.
pedestrians in a system of linked waterfront seconds. Bicycles are accepted on the EAL.
routes to the Lea Valley Trail Network, Canary Bus services
Wharf, and the Thames Waterfront, as well as Public Transport Accessibility
London-wide cycle routes. The OPP Transport Assessment (TA) identified Levels
seven bus routes accessible from the Site.
PTALs are a measure of the accessibility of
It is noted that bus route 573, a temporary a chosen location to the public transport
service during Crossrail construction, has network, taking account of walking time
been discontinued since the OPP TA. This and service frequency. PTALs are graded on
service has been replaced with services 473 a scale between 1 and 6b, whereby 6b is
and 474 run along the eastern and southern the accessible location. The Site currently
boundary of the Site, on Connaught Bridge achieves a PTAL score of 2. The future year
and North Woolwich Road respectively. PTAL forecast on the WebCat website is an
increase to PTAL 3 by the year 2031.
Docklands Light Railway
DLR services are available from six stations
within 960m (threshold for inclusion in a
PTAL Assessment) of the Site. Each station
is located on one of two lines, the Beckton
line to the north of Victoria Dock, and the
Woolwich Arsenal line running along North
Woolwich Road.
2B
2A 3
1
Mill Road
lwich Road
6 8 North Woo
7
Elizabeth Line
DLR
Riverboat
Pedestrian routes
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 67
4.5.3 MOVEMENT Royal Victoria Dock Bridge
alignment and pontoons
Rayleigh Road
Place
Phase 1 RMA Site. 2B
2B
Hovis Yard
Hovis Street
access point is proposed at Silo D Way, Mil ls way
providing a greater level of choice for north- Wesley Avenue
south movements.
Silvertown Avenue
4
4
All roads and routes are implemented, with a
number of additions:
Silvertown Street
• Out of hours servicing is proposed along 5
Mills Way (note: permitted Limit of
5
Deviation [L.O.D.] is used for this route);
Primary road
Mill Road
• A one-way servicing road is proposed along
Secondary road Silo D Park
Canalside;
Tertiary road de
a l si
Barri
• A tertiary road (Hovis Steet) is introduced Can
east of Plots 3 and 4 Pedestrian + servicing 6
er Po
route
6
Sil o
8
8
int R
Pedestrian + out of
hours servicing route
DW
7
o ad
7
ay
Pedestrian route
lwich Road
North Woo
Phase 1 RMA Boundary
OPP Boundary
KEY:
Buildings to be retained
Figure 4.53 Parameter Plan 05 - Roads and routes extract overlay with Phase 1 RMA Boundary and Plots
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 69
REV DESCRIPTION BY CHK DATE
Cycling routes Street is shallower than along Silo D Way and Royal Victoria Dock Bridge
Barrier Point Road (refer to Figure 4.75 on page alignment and pontoons
Cycling routes through the Site connect to are indicative and subject
85) so this route is expected to receive the to change under separate Royal Victoria Dock Bridge
the wider network of cycling routes towards
highest pedestrian flow. planning application.
Stratford, Canning Town, Wanstead Park, Royal
Albert Docks and Woolwich Ferry as shown in
A lower volume of residents living east or
Figure 4.54. Within the Site, cyclists follow the
people traveling by DLR are expected to go
pedestrian routes as outlined below. Dock Waterfront
down Silo D Way and use the potential second
North Woolwich Road crossing. Silvertown
Rayleigh Road
Pedestrian routes 2B
Place Hovis Yard
The key pedestrian movement through the
Primary
Site is in a north-south direction, from the Mills Square pedestrian
1 3
main arrival point off Royal Victoria Dock 2A route
Bridge to Silo D through Silo D Avenue. Secondary
Mil ls way
Hovis Street
Cycling routes pedestrian
route
At this point, the main pedestrian flow is Cycling routes Phase 1 RMA Wesley Avenue Tertiary
expected to continue down Silvertown Street, shared with cars Boundary 4 pedestrian
Silvertown Avenue
across North Woolwich Road into Royal Wharf. Cycling routes OPP route
This crossing is the most centrally located for shared with Boundary
Royal Wharf, and the gradient along Silvertown footways Dedicated
Brand A1
Retail
To Stratford
Evelyn Walk Dedicated
To Wanstead Park Brand A3-
A5 Food and
Beverage
Silvertown Street
To Royal
5
Food and
To Greenwich Peninsula Albert
Beverage A3-
via Emirates Air Line Docks
A5
Mill Road
Local A1 Retail
To Canning Town
Silo D Park
Residential
e
l sid
Barri
a
Can Brand
6
er Po
Community
Sil o
8
int R
Building
entrance
DW
To Woolwich
o ad
Ferry 7 Planning
ay
approved
signalised
crossing – not
yet installed
Proposed
Nor th Woolwich Road unsignalised
crossing
Figure 4.54 Cycling routes Figure 4.55 Pedestrian routes
Rayleigh Road
Phase 1 RMA Boundary
be low (reflected in car parking provision), 2B
Place Hovis Yard
most vehicle movements within the Site are OPP Boundary
anticipated to be delivery and service vehicles.
Maximum estimated flow of Mills Square
1 3
Future phases vehicles per hour (v/h)
2A
Hovis Street
4 5 -5 9 v/ h
Silvertown Avenue, the vehicular connection
to the Millennium Mills from Silvertown Wesley Avenue
4
Silvertown Avenue
30-44 v/h
Avenue will be restricted in future phases.
Evelyn Walk
15-29 v/h
Silvertown Street
<15 v/h
Mill Road
Silo D Park
v/ h
< 15
<15 v/h
al side
1 5 -2
6
er Po
Mill Road
Sil o
8
int R
DW
30-44 v/h
o ad
h
7
ay
lwich Road
lwich North Woo
North Woo
Ro a d
Figure 4.56 Vehicular roads in future phasing Figure 4.57 Vehicular roads Phase 1 RMA
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 71
4.5.4 SERVICING Royal Victoria Dock Bridge
alignment and pontoons
Rayleigh Road
2B
other access points and internal streets. Place Loading Bay
Hovis Street
is expected to occur via Access 1 at North Mil ls way
Woolwich Road. The exception to this is for
Plot 7 and Plot 8, whereby vehicles will access Wesley Avenue 4
Silvertown Avenue
at Access 2 and exit at Access 1. Again this will Loading Bay
Silvertown Street
narrower usable width than the internal street 5
network serving Phase 1 RMA. Furthermore,
the internal street network seeks to
encourage Phase 1 RMA traffic to utilise Servicing road
Mill Road
the internal street network where possible,
Servicing locations Silo D Park
including the provision of a turn-around area
for cars and vans within the primary north- Refuse collection location
de
Barri
south route. As described in “Vehicular a l si
Can
routes” on page 71, the Phase 1 RMA street P Parking entrance Servicing
er Po
Bay
network essentially presents a ‘temporary’ Car club bay 6 Serv icing Bay
Sil o
situation. In future, Mills Way will be restricted
int R
8
to vehicle traffic from the remainder of the Servicing bay
DW
o ad
Phase 1 RMA street network and will be P
P 7
ay
On street parking P
serviced from elsewhere within the wider lwich Road
North Woo
masterplan. Site entrance Serv icing Bay
OPP boundary
AC C E S S 1
Figure 4.58 Phase 1 RMA servicing routes
ROAD HIERARCHY
will cater for deliveries associated with
minor ground-level retail uses, removal vans, Pedestrian connection
residential deliveries, etc. In most cases, these
Primary road
loading bays will also be suitable for refuse
collection which will be expected to occur
Rayleigh Road
Secondary road
2B
outside of typical delivery periods.
Tertiary road
The exception to the above is Plot 5, which Out of hours servicing road 1 3
features fewer units compared to other plots; 2A
Site vehicle entrance P
loading (and waste collection) is proposed to
occur from the kerbside.
Refuse collection location
For those residential plots with commercial 4
P Parking entrance
SERVICING
Loading bay
Commercial plots (including
Millennium Mills) On street parking
Mill Road
• Plots 2B & 3 – a designated (internal) Residential
loading yard at the northeast side of the
two plots (3 bays); and Brand
ACTIVE LANDUSE
OPP boundary
Figure 4.59 Routes overlay diagram
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 73
4.5.5 PARKING the Silvertown Quays development will
provide a minimum of five car club bays for
Royal Victoria Dock Bridge
alignment and pontoons
Rayleigh Road
2B
unit (7%) on a passive / ‘as required’ basis, designated within the OPP.
totalling a potential provision of 0.10 disabled
parking spaces per unit (10%). In addition, a • Housing composition - Phase 1 RMA will
1 3
rate of 0.018 spaces per residential unit (17 predominantly comprise 1-2 bedroom 2A
spaces) is proposed for standard residential housing. P
use; the provision is requested following
officer advice to cater for essential users and • Highways impacts - A car-lite development
family units. is expected to have a lesser impact on 4
the highway network surrounding the Site
Disabled persons parking is also proposed for during peak hours in comparison to a
the non-residential uses. development which provides parking, as
was consented for the scheme under the
Further aspects of Phase 1 RMA which will OPP.
support a low car parking development
Plot Stand- Blue Motorcycle
include: no. ard badge
Total
parking
Mill Road
Docks East RPZ. Future residents of Phase 1 Plot 6 - 5 5
RMA will not be eligible to purchase parking
permits. Plot 7 - 5 5 3
• Car club bays - as per the S106 agreement, Car club bay Phase 1 RMA
Boundary
Blue badge parking
OPP Boundary
Figure 4.60 Phase 1 RMA parking strategy
following documents: areas within each plot have had regard to the
impact of noise and smell on the occupants
• Waste Management Guidelines for of neighbouring properties, both existing and
Architects and Property Developers proposed.
Silvertown
Rayleigh Road
• BS5906:2005 Waste Management in 2B
Storage areas within each plot have been Place
Buildings – Code of Practice designed to allow a minimum of 150mm
clearance around and between each bin
Please refer to the Waste Management 1 3
within a storage area. Where there is more 2A
Strategy for further details.
than one bin within a storage area, there must
be 2m clearance in front of each bin to enable
Internal storage (within units) it to be accessed and safely moved without
To encourage tenants of new developments needing to move any of the other containers. 4
to recycle waste, the proposed Phase 1 RMA All doors and alleys are at least 2m wide
Development will provide adequate internal to allow for safe manoeuvring of bins. The
storage for the segregation of recyclable minimum internal height for a bin storage area
materials from other waste streams. and any access doorways is 2m. There will
be no other internal fixtures or fittings that
Communal storage areas (within reduce the clearance above the bins, so that
plots) their lids can be opened fully.
Within each plot, tenants will have access to
Access and pulling distances
communal 1,100 litre eurobins, clearly labelled 5
Bin storage areas will be located within
Mill Road
to distinguish between refuse and recycling.
a specified minimum distance of a point
The eurobins will be available for recycling of where the collection vehicle can safely stop
the following items: for loading. The maximum distances that
operatives should be required to wheel
• Mixed paper and card containers, measured from the furthest point
within the storage/collection area to the Servicing road
• Plastic bottles loading position at the back of the vehicle, are: 6
Refuse
• 15m for any wheeled container up to collection
• Food tins and drink cans 8
location
240-litres, and
Bin storage areas provided within each plot Refuse areas
will be easily accessible for the dwellings that • 10m for any container greater than 7
they serve, with residents being required to Site entrance lwich Road
240-litres. North Woo
walk no further than 30m from their front
Phase 1 RMA
door (excluding vertical distances) when This ensures that the stopping point(s) for
Boundary
carrying refuse and recycling. the vehicle are safe, legal and designed to
minimise any obstruction to traffic. OPP boundary
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 75
4.5.8 CYCLE PARKING Cycle parking per plot Royal Victoria Dock Bridge
alignment and pontoons
are indicative and subject
Long and short-stay cycle parking will be Plot Long-stay Short-stay to change under separate
planning application.
provided in accordance with the minimum number cycle req. cycle req.
rates specified in Condition T1 of the OPP.
Rayleigh Road
within each plot, and will be secure, covered
and easily accessible. End-of-trip facilities are 2B
proposed for the larger non-residential plots Plot 2B
(Plots 2-4) which include showers, lockers 254 488 1 2A 3
and change rooms. Short-stay cycle parking Plot 3
for visitors and customers will be located in
publicly accessible locations within the public Plot 4 125
realm, be visible, overlooked, and situated
as close as possible to final destinations in Plot 5 60 1 4
accordance with guidance provided in the
London Cycle Design Standards (LCDS). Plot 6 158 24
Plot 7 383 7
Plot 8 447 8
Mill Road
On plot cycle
parking
On plot
(upper floor) 6
cycle parking
8
Visitor cycle
parking
7
lwich Road
Phase 1 RMA North Woo
Boundary
OPP
Boundary
Rayleigh Road
Quays should be kept to a minimum and furniture such as lighting columns where * 2B
Mill Road
The aim is to create a legible, safe and
informative suite of signage appropriate to the
Legible London
requirements of wayfinding, interpretation and
education themes.
Monolith Totem signage
*
Raingarden Trail signage
• Directional signage will generally be from
the Legible London range;
* Play Trail signage 6
Edible Plants Trail
• Public safety will always underline all signage 8
decisions taken relating to traffic and
pedestrian signage; Industrial Heritage
signage 7 *
lwich Road
Civic Open Space North Woo
OPP Boundary
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 77
4.5.10 STREETS
SECTIONS 1 2A
2B
S1 3
A new network of streets will become part
S2
of the urban grain of the Royal Docks and 4
S3
London. This network needs to provide
continuity with its surroundings as well as
reflect the character of the Site.
5 SILVERTOWN AVENUE
• North Woolwich Road 22m
6
LBN are currently developing a vision
for North Woolwich Road with the aim
of turning it from the car-dominated 8
7
thoroughfare it is at the moment into an
PLOT 2
PLOT 1
urban boulevard. Our proposal anticipates
and informs this ongoing study by LBN,
however amendments may be required to Phase 1 RMA Boundary
the North Woolwhich Road frontages and Maximum building
highway infrastructure interfaces once heights (as defined in
LBN have developed their preferred design Parameter Plan 07)
solution to the road.
• Silvertown Avenue
Main pedestrian and cycle connection
though the Site, connecting the new Royal
Victoria Dock Bridge with Millennium
Mills and Silo D. Its character changes
throughout: the northern end at the bridge
landing forms an arrival space. Traveling
south, it then narrows before the start of
a pedestrian prioritised space connecting Retail Retail
Silvertown Street with Wesley Avenue. The
last section leading to the park is again
pedestrian and cycle only.
• Wesley Avenue
Vehicular connection to Britannia Village,
mainly serving Plot 1.
5.0 2.0 6.0 4.0 5.0
zone
Spill out
Footway
zone
Pedestrian
Footway
zone
Spill out
Rain garden
Planting
Rain garden
Planting
Figure 4.64 Illustrative section 1. Silvertown Avenue - Plot 1 & Plot 2
SILVERTOWN AVENUE
WESLEY AVENUE 18m
16m
Residential lobby
2.5 3.0 5.5-5.8 2.0 2.5 3.2 1.6 6.0 3.2 4.0
Footway
Loading bay
Carriageway
Rain garden
Planting
Footway
Footway
Rain garden
Planting
Rain garden
Planting
Footway
space
prioritised
Pedestrian
Figure 4.65 Illustrative section 2. Wesley Avenue- Plot 1 Figure 4.66 Illustrative section 3. Silvertown Avenue
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 79
• Evelyn Walk
This pedestrian and cycle street connects
Britannia Village with the main Phase 1 RMA 2B
roads, Silvertown Street and Silo D Avenue. 1 2A 3
S4
5
6
8
7 +25m AOD
PLOT 5
EVELYN WALK
Phase 1 RMA Boundary 16m
Maximum building
heights (as defined in
Parameter Plan 07)
Residential
Privacy Zone
Footway
Rain Garden
Planting
Footway
Figure 4.67 Illustrative section 4. Evelyn Walk- Plot 5
S5
8
7
PLOT 8
SILO D
CANALSIDE
Phase 1 RMA Boundary
Maximum building
heights (as defined in
Parameter Plan 07)
Residential
1.5
Privacy zone 6.1-7.6
space
prioritised
Pedestrian
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 81
• Silvertown Street
Silvertown Street is designated in the OPP
as a primary road and forms the main 2B
vehicular access to the Phase 1 RMA Site. 1 2A 3
It’s designed as a ‘conventional’ kerbed
road with a 5.5m carriageway. Its character 4
changes throughout, starting as a main
gateway between Plots 6 and 7, changing
into a parkside road with retail and spill-out
spaces, and again into a residential road 5
with front gardens.
• Silo D Way 6 8
S7 S8
PLOT 6
This is a pedestrian connection linking S6 7
North Woolwich Road to Silo D Park and
beyond via a new pedestrian bridge. The SILVERTOWN STREET
street negotiates an approximate level 18m
Phase 1 RMA Boundary
difference of 3m and will therefore provide
a ‘zig-zag’ accessible route as well as a Maximum building
heights (as defined in
more direct stepped route. The pedestrian Parameter Plan 07)
nature of this space allows for landscape
and play areas to be inserted.
Retail Community
zone
Spill out
Footway
Rain garden
Parking /
Carriageway
Loading bay
Footway
Figure 4.69 Illustrative section 6. Silvertown Street- Plot 6 & Plot 7
PLOT 8
PLOT 8
SILO D WAY BARRIER POINT ROAD
16m 16-19m
Width varies
Rain garden
Planting
Footway
Footway
parking
Planting /
Carriageway
Footway
Footway
Figure 4.70 Illustrative section 7. Silo D Way- Plot 7 & Plot 8 Figure 4.71 Illustrative section 8. Barrier Point Road- Plot 8
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 83
The site offers extensive scope for redevelopment, being • works of repair and restoration of the dock walls
largely devoid of buildings, historic or otherwise. The • infilling and excavation of parts of the dock area
huge scale of the few existing historic buildings on the • the placing of structures in, on or over the dock area
site and their robust industrial aesthetic also supports • alterations and conversion of the Millennium Mills
the principle of high-density redevelopment. The complex;
0 50 100 M
proposed Silvertown Quays will impact on the following • development in the setting of Silo D.
heritage aspects:
4.5.11 LEVELS Further details of this are set out in Chapters 5-8 of this
document. A full assessment is set out in Chapter 4 of the
Environmental Statement (Cultural Heritage).
Existing site levels
The levels within the Site rise substantially Millennium Rank’s Premier Mills The Royal Victoria Dock .00
from around +1.7m to +2.5m AOD at North Mills (Rank Hovis) +5
0
+5.0
significant level change between North +5.00
Woolwich Road and the southwestern
edge of the Site. currently delinated by the +4 +2.00
.00
landscaped bank just north of the footpath.
The historic maps show how the industrial Historic finger
working dock areas were raised up to dock +3.00 docks not
currently visible
level, whilst the residential areas remained at
the low lying original marshes level.
+1
Pontoon Dock .00
The dock wall level is at +5.18m AOD and the +5.00
existing water level sits at around +4.25m +2.0 Silo D
0 +5.00
AOD The bottom of Pontoon Dock basin is
Existing heritage context
at around -2.25m AOD and the main Royal
+5.00
Victoria Dock is at around -5.5m AOD The
+2.00
finger docks are shallower at around 0m AOD.
+3.00
+1.00 +4.00
+2.00
+1.00
Figure 4.72 Existing site levels
+3.00 +2.0
0
+3.
00
+4.00
Figure 4.73 Raised bank along North Woolwich Road Figure 4.74 Royal Victoria & Royal Albert Docks, 1918, Port of London Authority
Royal Victoria & Royal Albert Docks,1918, Port of London Authority
Rayleigh Road
The level change between the Phase 1 RMA 2B
Site’s three intersecting roads and North
Woolwich Road is resolved differently along 2A 3
1
Hovis Street
each:
+4.5 Mill s way
• Silvertown Street will follow a gentle
gradient along the length of Plot 6
Silvertown Avenue
Wesley Avenue
• Silo D Way, which is pedestrian-only, will 4
provide an accessible zig-zag route and a
stepped direct route
Silvertown Street
robust surface water drainage design.
Mill Road
5
+4.5
+5.00 +4.0
Barr
+4.50
+4.00 de
+3.5 a l si
ier P
+3.50 Can
6
o int
+3.00
8
Sil o
+2.50 +3.0
Ro a d
+2.00
DW
+2.5 7
+1.50
ay
+1.00 +2.0
Phase 1 RMA
ic h Ro a d
Boundary Woolw
Nor t h
OPP Boundary
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 85
4.5.12 ACCESSIBILITY The Development will be designed to be as
inclusive as possible for:
Overview Scope
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 87
Phase 1 Masterplan proposals and • Refuse strategy The Commission for Architecture and the Built • To design inclusively, which means
inclusive design strategy Environment published a guide called The designing beyond the minimum
• A flexible framework for future phases Principles of Inclusive Design in 2006, which requirements of the Building Regulations
Lifetime neighbourhoods states that inclusive design: Part M to ensure that all people, regardless
The Phase 1 Masterplan also follows the of age, sex or ability can use and enjoy the
The aspiration for the Phase 1 Masterplan is principles of Lifetime Neighbourhoods • Places people at the heart of the design
aligned to the OPP which is to accommodate built environment;
published by the Department for process;
inclusive design as part of mainstream Communities and Local Government in
provision rather than as ‘special needs’ • To address the anticipated, substantial
December 2011. These are as follows: • Acknowledges diversity and difference; increase of older people in proportion to
arrangements. This is in line with Lifetime
Neighbourhood principles referred to in the • Walkable neighbourhood: All outdoor the working-age population in the near
• Offers choice where a single design future and their needs;
OPP Design Code as well as in more recent spaces, services and facilities, including car
solution cannot accommodate all users;
London Plan policy, which aim to create parking spaces, are at walkable distances
sustainable communities by designing places from all homes; • To meet the aims of the Equality Act,
• Provides for flexibility in use; and where applicable; and
that are accessible, inclusive and safe thereby
responding to current and future demographic • Transport: There is good provision of public
• Provides buildings and environments that • To follow design guidance given in relevant
changes, including the anticipated increase of transport nearby;
are convenient and enjoyable to use for British Standards and other currently
older people of working-age population. everyone
• Housing: Homes will be designed to published good practice guidance about
The Phase 1 Masterplan considers inclusive adapt to the needs of the residents, These criteria are important factors in meeting the needs of disabled people.
design by reference to the following provisions when becoming older and/ or potentially recommending the most inclusive (not just Guidance for Lifetime Neighbourhoods and
that will serve all users including disabled and disabled. accessible) solutions for a development within current accessible and inclusive housing
older people. the client’s resources. Inclusive environments standards is a key reference for the project,
London Plan policy 7.2 states the need
seek to remove obstacles for all potential ensuring that physical barriers to access
• Integrated amenities to deliver inclusive, not just accessible
users, especially people who have one or for all people, including older and disabled
environments. Inclusive design is central to
more of the protected characteristics listed in people and children are avoided, providing a
• A permeable street network the policies of the London Plan, with mention
the Equality Act 2010. welcoming and comfortable environment
of it throughout the text of the plan. Policy 7.2
• Transport strategy and services states: Access aims Summary of objectives
“The Mayor will require all new development Silvertown Quays will incorporate the • Parking: Accessible car-parking spaces
• A network of public spaces
in London to achieve the highest standards of following access principles: (Blue Badge) will be provided in accordance
• Clearly defined public, communal and accessible and inclusive design and supports • To maximise access to all parts of the with Condition T2.
private spaces the principles of inclusive design which seek development, its facilities and services for
to ensure that developments: all future residents, visitors and members • Drop-off: Drop-off/pick-up points for taxis,
• Commercial and community use buildings of staff in the Development; Dial-a- Ride and community transport
• Can be used safely, easily and with dignity
minibuses will be located at key points.
by all regardless of disability, age, gender,
• A broad mix of dwelling types and sizes • To meet local, regional and national access
ethnicity or economic circumstances; and
and inclusive design policies; • Public spaces: The proposals will provide
• Accessible housing and parking new public spaces with pocket urban
• Are convenient and welcoming with no
• To ensure that appropriate access squares as gathering points for recreation,
disabling barriers, so everyone can use
• An integrated build form standards are met at the outset and resting and wayfinding.
them independently without undue effort,
separation or special treatment.” as part of mainstream, inclusive design
• A mixed tenure wherever possible; • Planting and landscape features will
include seats and resting places at a
minimum of every 50m;
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 89
improvements on North Woolwich Road. Public Realm, External Areas and • Out of hours servicing street - As per the Integration with Future Masterplan
These include two new access points and a Approaches OPP Parameters Plan, the street to the
signalised junction onto North Woolwich Road. south of Millennium Mills (Plots 2-3) is The Phase 1 development will need to operate
Access strategy designated as a primary pedestrian route, effectively both in isolation, and ultimately as
with out of hours servicing. part of the wider OPP masterplan.
The Phase 1 RMA site provides car parking There is a strong network of spaces between
is in accordance with Condition T2 with the the buildings within the Phase 1 development Provisions to ensure clarity and safety for all The key feature of the post-Phase 1 street
objective to be ‘car light’ having regard to the that can be freely accessed by the public, users include: network is that vehicular access to Millennium
draft new London Plan. including parks, squares, roads, pedestrian Mills from Silvertown Avenue / Wesley Road
areas, cycle routes and open space, including • Design distinguishing clearly between the
would be closed. As a result, Plots 2-4 would
Wheelchair accessible parking is proposed the dockside. The provisions are covered in needs of pedestrians, vehicles and cycles.
be accessed from the east under future
at a rate of 0.03 spaces per residential unit more detail in the earlier past of Section 4.5 Appropriate signage and material changes
scenarios.
(3%). An allowance has also been made to (access) and section 5 (landscaping) of this will be implemented to ensure safe
incorporate an additional 0.07 spaces per unit DAS. movement of pedestrians and cyclists at all Sitewide play strategy
(7%) on a passive / ‘as required’ basis, totalling times.
a potential provision of 0.10 disabled parking The play strategy will be provided on-site
Pedestrian access routes (PARs) are defined
spaces per unit (10%). • Ensuring a simple and unobstructed in accordance with the LB Newhams Play
as the most direct and convenient pedestrian
footway network is promoted and any Standards and reference noted with regards
routes linking key parts of the Development.
Residential accessible parking provision unavoidable overlap between pedestrians to the GLA 2012 Supplementary Planning
They are designed to be inclusive and have
has been designed to be as close to each and vehicles will be minimised and closely Guidance ‘Shaping Neighbourhoods: Play and
access features such as gentle gradients,
residential plot as practicable, either on plot managed. Informal Recreation’. Please refer to section 5
suitable surfaces and rest points.
or roadside within the public realm. Level (landscaping) of this DAS for further detail.
resting places will also be provided along The PARs for the Development include: • The accessibility requirements of partially
routes, where a 40m distance is exceeded. sighted and disabled people will be a major Accessibility and Inclusive Design has been
• Pedestrian footways alongside roads, factor in the determination of surface included within design proposals for play
For the commercial plots, Millennium Mills and edge types, so as to provide a legible within residential courtyards and residential
and Plot 4 will not provide car parking • Approaches to building entrances; and safe environment in conjunction with play streets with reference made to BS 8300
for staff or visitors within the proposed current accessibility requirements. Vol 1 and accessible play guidance such as
development but will include accessible • Any route that connects with an adjacent Developing Accessible Play Space: A Good
parking bay provision in close proximity within pedestrian route or public space. Practice Guide, published by the Department
• The lighting of the public realm has been
the public ream. for Communities and Local Government.
There are four street types proposed within developed in line with the OPP Design
Phase 1 as detailed as below: Code. Water and open space strategy
Further detail regarding accessible bay
locations can be found in the individual plot • Primary street - These streets will form • Pedestrian footways take into account Water is a key part of the vision of this site,
sections of this DAS and also in the Transport the primary vehicular routes and will roughness and slip resistance to ensure a and the masterplan and landscape design aim
statement associated with this RMA in the accommodate on-street cycling. comfortable and safe walking experience. to make the most out of this asset. Central to
Transport statement associated with this this strategy is to make the water accessible,
RMA. • Secondary street - These will • The use of tactile and hazard warning as well as define the character for the
accommodate some vehicle movement and paving will be provided in compliance with different ways water appears throughout the
accommodate on-street cycling. British Standards, Building Regulations and site (Royal Victoria Dock, Pontoon Dock, finger
Department for Transport (DfT) guidance. canals, SuDS, etc.).
• Tertiary street - Designed to accommodate
low levels of traffic with pedestrian and All such instances will be developed with
cyclist priority. consideration of the OPP Design Code and all
associated design guidance.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 91
The strategy should include best practice Residential layouts The layouts of the units are also designed • S
pecification of suitable surface materials,
procedures for the evacuation of disabled to meet Categories 2 and 3 of the Building including provision of sufficient tonal
Overview
people from all parts of the buildings, Regulations and to meet the criteria of the contrast where required. (make these all
including BS 9999:2017 and Regulatory Reform This section covers the approach to inclusive Nationally Described Space Standard. bullet points)
(Fire Safety) Order Supplementary Guidance. design for the residential units and how
Features of the residential units that are
they will be designed to meet the relevant Any changes to these aspects of the
not designed, specified or assessed prior to
Normal provisions for residential buildings standards and regulations. Please refer to the proposals during detailed design will need to
the planning application that will need to be
will apply to the residential levels of the sample layouts in the residential plot specific be carefully considered to ensure compliance
compliant at completion include:
Development whereby only the residents of sections of this DAS. with Building Regulations is maintained.
an affected unit will evacuate. Others are • O
pening forces of doors to Category 3
protected as the residential units themselves The provision consists of the following Features of the residential common parts that units;
function as safe refuges. dwelling types: are not designed, specified or assessed prior
to the planning application that will need to • L
evel thresholds for all entrance doors and
All designated escape routes will allow
Table: be compliant at completion include: balcony doors (including to terraces above
wheelchair users and others to reach a safe Plot ADM 4(2) ADM 4(3) TOTAL habitable rooms for Category 3 dwellings);
• Appropriate and accessible directional
area from each part of the Development. No signage to parts of the development and to
• P
rovision of accessible utility services and
1 234 31 265 residential units;
Alarm systems will provide visual as well as controls;
audible signals in isolated locations such as 5 36 0 36
• E
xternal lighting, including lighting of
staff and customer WCs. 6 88 18 106 • P
rovision of sockets and switches in
entrances;
accessible locations;
7 224 16 240
8 267 29 296 • Entrance shelters;
• Glazing heights and window guarding; and
TOTAL 849 94 943 • L
evel thresholds to all communal
entrances, individual residential unit • Window operation.
Table 4.3 Acccessible housing provisions
entrances and balconies; Category 2 units
• O
pening forces of doors to entrances and All M4(2) provision dwellings will be single
General arrangement common areas; storey apartments apart from 8 maisonettes
in Plot 5 and 5 maisonettes on Plot 8.
The residential plots will deliver 943 dwellings
• S
urface materials in common parts to have
of which 90% are designed to ADM 4(2) and There is lift access to the upper level
sufficient tonal contrast and lighting where
10% (93 units) to ADM 4(3). apartments within the apartment blocks and
required;
all units meet the requirements of Part M,
The external approaches to residential the London Plan Housing SPG (parts relating
• D
etailing of internal stairs and ramps,
entrances, the entrances, lobbies and to accessible homes) and the Nationally
including tactile warning (exterior only) and
common areas, including vertical circulation Described Space Standard.
handrails to both sides;
that have been reviewed at this stage are
designed to meet the guidance of Approved
• D
etailing of lift cars, controls and audio
Document M, Volume 1, Categories 2 and 3 in
information;
all respects.
• D
etailing of sanitary and kitchen facilities
for residents’ facilities; and
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 93
5.0
Landscape
5.1 INTRODUCTION
The Landscape Strategy describes the OPP Condition A7 Play Space • External lighting statement - refer to
landscape and public realm proposals for Section 5.10 Lighting strategy
Requires that “the details approved in respect
the phase 1 RMA including the planting
of play space(s), park(s), communal amenity
strategy, SUDs/drainage strategy and play • Ecology mitigation and management plan -
space and private amenity space pursuant to
strategy. It also includes information relating refer to Section 5.13 Ecology management
Conditions A1 and A2 shall be implemented
to the lighting strategy and the ecological plan
in full prior to Occupation of 50% of the
management plan.
residential units within the relevant phase to
• Bird hazard management plan - refer to
which they relate”.
This section specifically sets out the Appendix A3 Bird hazard management plan
requirements of the relevant OPP conditions
For the relevant context to this condition refer
and RMA specification and details how these • Dock walls - refer to Section 5.9 Dock
to Section 5.5 Play strategy and relevant plot
requirements are addressed. walls
landscape subsections.
Key Planning Conditions
Reserved Matters Specification
The following describes key conditions Requirements
relevant to landscape, and the RMA
requirements: Condition A2 identifies relevant requirements
of the Reserved Matters Specification. The
OPP Condition A4 RMA specification is annexed to the decision
notice, and requires that the following
The phase 1 RMA is being submitted further landscaping relevant matters be addressed as
to a recent application seeking approval of part of the Phase 1 RMA:
details under Condition A4 (Phasing Details).
This condition includes details for approval • Hard landscaping (including samples
by LBN of “the area, location and programme of paving and hard surfaces) - refer to
for construction of public open space, public Section 5.7 Hard landscape
realm and landscaping to be provided in that
phase”. • Soft landscaping/planting - refer to
Section 5.3 Planting strategy
OPP Condition A6 Planting
Sets out that “all landscaping plans and • Green and brown roofs - refer to Section
all planting should make such planting 5.3 Planting strategy
unattractive to birds so as not to have an
adverse effect on the safety of operations • SUDS/finished levels - refer to Section 5.4
at London City Airport by encouraging bird SUDS/drainage strategy
roosting and creating sources of food and
birds, and thereby presenting a bird strike • Public realm and Landscape Management
threat to aircraft operating at the Airport”. and Maintenance Scheme - refer to
Section 5.11 Landscape management
For response to this condition refer to Section
5.13 Ecology management plan. • Landscape delivery plan - refer to Section
5.12 Landscape delivery plan
96 Landscape | 5.0
Figure 5.1 Photo looking north showing finger dock Silo D and Millennium Mills
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 97
5.2 LANDSCAPE MASTERPLAN
Silvertown Quays presents a unique enlivens and activates the proposed public
opportunity to harness the history of a former spaces
industrial dockland, reinterpret and reinvent it
within the frame of a public realm and mixed- • A permeable, inclusive and legible public
use neighbourhood to create a strong sense of realm prioritising pedestrians and cyclists,
place unlike anywhere in London. allowing people to cohabit with vehicles
safely
The Landscape Strategy illustrates how
the landscape proposals have evolved and • Value, understand and reinterpret the
been informed by site analysis / context, ecological richness and sense of urban
architectural proposals and consultations with wild that characterises the existing open
LBN and other stakeholders. mosaic habitat found on the existing site
in the setting of a new urban realm and
This section covers the key spaces in the residential community
public realm as well as each strand of the
landscape strategy including proposed • Maximise urban greening and permeable
materials, furniture, trees and planting, surfaces, use soft landscape to define
biodiverse green roofs, play, SuDS, biodiversity, streets zones, create intimacy, frame
landscape management and phasing / spaces and programme, moderate urban
delivery. microclimate by mitigating effects of sun,
heat, wind, and urban flooding; engender
Aims wellness, biodiversity and resilience
• Celebrate the industrial and maritime
heritage with a ‘found’ landscape through • Respond positively to microclimate by
the retention and retracing of historic providing places to soak up the sun or
features, reuse of existing materials and seek shelter each day throughout the year
specification of a new durable materials
and planting palette that articulates • A landscape that is intrinsically playful
the sense of permanence and its post- with opportunities for children and adults
industrial and pioneer qualities to play across the public realm from
streets squares parks and courtyards,
• Place water at the heart of the Silvertown including opportunities for future
experience by creating opportunities for waterborne play and leisure use of the
access to the water and recreation on dock
the water, and integrate water features
and drainage thoughtfully throughout the
public realm so that water in its many
forms becomes the defining characteristic
of living and working at Silvertown Quays.
98 Landscape | 5.0
INDICATIVE ROYAL
VICTORIA DOCK
BRIDGE
DOCK WATERFRONT
SILVERTOWN
PLOT 2 HOVIS
RAYLIEGH ROAD
PLACE
YARD
PLOT 1 PLOT 3
MILLS
SQUARE
HOVIS STREET
MILLS WAY
WESLEY AVENUE
PLOT 4
SILVERTOWN AVENUE
EVELYN WALK
PLOT 5
SILO D PARK
SILVERTOWN STREET
SILO D
MILL ROAD
BRIDGE
BAR
ID E
PLOT 6 ALS
RIER
CAN
P O IN
S I LO
PLOT 8
T RO
DW
PLOT 7
A
AY
D
ICH ROA
ORT H WOOLW
A1020 N
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 99
5.2.1 MILLS SQUARE movements in later phases allowing the
street to become almost completely
pedestrianised. Eventually the only vehicles
Legibility entering the square via Mills Way will be
Established originally as a working yard either to facilitate events in the square,
directly to the south of Millennium Mills the servicing of Plot 2A via the northeast
the proposed public space forms the corner of the square or for emergency
primary civic space to the north of the OPP vehicles. Vehicular access into Mills Square
masterplan, just east of the main axial route and Mills Way will be managed with
that connects Silo D with the proposed retractable bollards and street furniture, this
Royal Victoria Dock Bridge crossing the Dock. is described in more detail in Section 5.8
The space is defined by the locally listed Furniture.
Millennium Mills and proposed Plot 3 forming
a strong enclosure to the north, east and
west sides, with access provided through
these buildings via an open ground floor
plan intended to offer maximum flexibility
and multiple routes between the dock edge
and Silvertown Street. Direct access from
Mills Way is provided into the space for
pedestrians and to enable servicing.
Millennium Mills
The OPP indicative masterplan includes
the addition of buildings to the south of
Mills Square which will close the space on
the southern side but set back to retain
good sunlight across the space. Mills Way
to the south will have diminished vehicle
Figure 5.4 Photo Millennium Mills south facade Figure 5.5 Photo Millennium Mills western facade
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 101
R E T A I L S P I L L- O U T R E T A I L S P I L L- O U T
R E T A I L S P I L L- O U T
2
IN-SITU
SEATING
CONCRETE
BRICK
PINE TREES IN PAVING
LIGHTING LIGHTING LIGHTING
SELF-BINDING
MAST MAST MAST
R E T A I L S P I L L- O U T
GRAVEL
BRICK
IN-SITU
PAVING
BRICK CONCRETE
PAVING
NICHES WITH NICHES WITH
NICHES WITH
RISING BENCHES BENCHES
BENCHES RISING
BOLLARDS
PIONEER PLANTING BOLLARDS
PIONEER PLANTING PIONEER PLANTING
AND TREES
AND TREES AND TREES
CYCLE CONCRETE
CONCRETE CONCRETE
RACKS BLOCKS
BLOCKS BLOCKS
4
MILLS WAY
3
Figure 5.7 Illustrative plan - Mills Square. Numbers 1-4 represent location of views on following page
Figure 5.8 View 1: Mills Square with active fountains looking west Figure 5.9 View 2:Mills Square with active fountains looking east
Figure 5.10 View 3: From Mills Way Figure 5.11 View 4: From Mills Way
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 103
Programming and events
The following spatial studies have been
prepared that demonstrate the flexibility of
Mills Square. It will accommodate events
such as performances of various scales,
food / seasonal markets as well as its more
everyday uses i.e. during weekday lunchtimes
when workers in the adjacent commercial
space will use the square at lunchbreaks,
and summer days and school holidays when
the water features will take centre stage.
Figure 5.14 Large scale performance - Area 750m2 with ~1500 people to a density of 1-5no people/m2
Figure 5.16 Summer weekend, water play ~400people Figure 5.18 Small scale performance - Area 250m2 with ~500 people to a density of 1-5no people/m2
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 105
Scale / programme comparison
The following studies compare the scale of
significant civic spaces and demonstrate
how a flexible programme may be
accommodated in Mills Square.
Figure 5.19 Granary Square (Townshend L.A.) Figure 5.26 South Bank Centre Food Market Figure 5.24 Somerset House Figure 5.28 Museum of Contemporary Art Barcelona
(MACBA)
Figure 5.20 Granary Square with outline of Mills Square Figure 5.22 South Bank with outline of Mills Square Figure 5.25 Somerset House with outline of Mills Square Figure 5.29 MACBA with outline of Mills Square
Figure 5.21 Mills Square with outline of Granary Square Figure 5.23 Mills Square with outline of South Bank Figure 5.27 Mills Square with outline of Somerset House Figure 5.30 Mills Square with outline of MACBA
Figure 5.33 City Dune, Copenhagen (SLA) Figure 5.36 High Line (Field Operations)
Figure 5.34 Lettenareal Promenade (Krebs Und Herde) Figure 5.40 Concrete tining finish
Figure 5.32 Stortorget, Kalmar (Caruso St John) Figure 5.35 Zollhallen Plaza (Ramboll/Dreisetl) Figure 5.38 Granary Square (Townshend LA) Figure 5.41 Clay pavers Bermondsey Square (East)
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 107
5.2.2 DOCK the setting of an open mosaic garden
interspersed by seating and opportunities
WATERFRONT for children’s play
The Dock Waterfront will become the primary • Receives midday sun throughout the year
ROYAL VICTORIA
threshold into the Site welcoming visitors and will be a good place to enjoy lunch DOCK BRIDGE
arriving by foot or bicycle from the new Royal
• Accommodates spill-out from the retail
Victoria Dock Bridge and connecting the Phase
offers in the east of Plot 1 and west of Plot
1 RMA Site to Custom House DLR Station and
2 alongside a generous pedestrian street
the ExCel Centre on the north side. This RMA
will be supplemented by future applications
• Includes sculptural wind mitigation MILLS NORTH TERRACE
for the new Royal Victoria Dock pedestrian
screens to benefit micro climate (design is PLOT 1 WATERSIDE
and cycle bridge, and associated works to
subject to separate planning application)
the existing pontoons and waterfront areas. SILVERTOWN
This design intent is shown indicatively on the
Mills North Terrace PLACE
plan opposite. The waterside is intended to
be activated through a series of interventions. The waterfront promenade adjoins the north
These include a wave deck which allows entrance terrace of Millennium Mills which
access to the water via steps; extending negotiates a 1.2m level change to its original
access from the dock and greening of the FFL via steps, tectonic seating plinths and
existing jetties/dolphins and activation of the accessible slopes for pedestrians and cyclists.
Lightship, greening around and underneath the This level change enjoys views of the dock
new bridge. and is modulated into a series of accessible
routes, plateau and seating set at different
The waterfront comprises of the three zones levels with niches and spaces for meeting /
described below that will ultimately create gathering. The north facing aspect means that
a continuous dockside experience from the spaces directly adjacent to the mills will
Britannia Village in the west, through Dock be shaded during the middle of the day but it
enjoys light in the early morning and evening. Figure 5.42 Landscape analysis diagram
Waterfront, and east to the Hovis Building in
Phase 2. The entrance on the dockside is colonised
with trees, planted apertures punctuate a
Silvertown Place ground plane of large format concrete panels
and evokes the concept of colonisation. Views
The future Royal Victoria Dock Bridge will land
of the Hovis building to the east are framed
in this location offering an important moment
by clear stem and multi-stem trees providing
of orientation for visitors and a key confluence
a legible route to its future entrance on the
of routes and uses:
west flank wall.
INDICATIVE PROPOSAL
FOR WAVE DECK AND
PLANTING DOCKSIDE
TREES
WATERFRONT
WATERFRONT 3PIONEER
PROMENADE
PROMENADE PIONEER
DOCKSIDE TREES/PLANTING
TREES TREES/PLANTING MILLS NORTH TERRACE
WATERFRONT STEPS AND SEATING
PROMENADE 1 2
PIONEER
PLANTING/
GARDEN
SILVERTOWN
PLACE
4
Figure 5.43 Illustrative Plan - Dock Waterfront indicatively showing future proposals for jetties, wave-deck and the new Victoria Dock Bridge. Numbers 1-4 represent location of views on following page.
Figure 5.44 Lettenareal Promenade and Lido (Krebs Und Herde) Figure 5.45 Zollhallen Plaza (Ramboll/Dreisetl) Figure 5.46 Chicago Riverwalk (Sasaki)
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 109
Figure 5.47 View 1: Looking south onto Silvertown Avenue and Silo D Figure 5.48 View 2: Looking northwest from Mills North Terrace
Figure 5.49 View 3: Dock Promenade and Mills North Terrace looking west Figure 5.50 View 4: Looking north on Silvertown Place
Figure 5.51 Tate Modern (Herzog and De Meuron/Vogt LA) Figure 5.54 Royal Festival Hall riverside
Figure 5.52 Tate Modern with outline of Silvertown Quays Waterfront Figure 5.55 Royal Festival Hall riverside with outline of Silvertown Quays Waterfront
Figure 5.53 Silvertown Quays Waterfront with outline of Tate Modern Figure 5.56 Silvertown Quays Waterfront with outline of Royal Festival Hall riverside
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 111
5.2.3 SILO D PARK of uses such as cafe, brewery or gallery that
provides a multifunctional use as park pavilion
activating the park. These uses will be tested
Legibility as part of the meanwhile programme before a
The importance of Silo D to the Site is permanent solution is selected. A location on
illustrated by the OPP defined street layout the west flank is preferred that will activate
where Silvertown Avenue provides a linkage and be visible from the most trafficked
to Millennium Mills via a key route. Silo D pedestrian route. The west-side extension is
lies at the southern extent of this Avenue sunny in the afternoon to evening and it is
which changes in character from the open envisaged to integrate a waterside jetty that
civic spaces of the Mills, Royal Victoria Dock enjoys sun most of the day.
in the north to the neighbourhood feel of
Silo D Quarter. The park provides a welcome Role of Silo D Park
dwelling space and re-orientates pedestrians Silo D park will provide a community focus
/ cyclists as 3 routes converge. Access to and open space resource with children’s play
Silvertown Street is expected to be the for the adjacent residential community from
primary route with ~50% of pedestrian flow. Plots 5, 6, 7 and 8. Phase 1 lies within LBN’s
The route via Silo D Bridge over the Finger register of open space deprivation and the
Dock accessing Silo D Way and Barrier Point parks function responds to this with spaces
Road are expected to accommodate ~30% and for family and play. The space adopts a
~20% of pedestrian flows respectively. The parkland aesthetic with grass areas and large
route to Silvertown Street is clearly expressed canopy and flowering trees. The footpaths
using direct desire lines and eastern routes are expressed with in-situ concrete and brick
are clearly legible and gravitate alongside Silo with areas of self-binding gravel. Granite setts
D. found on site adjoining the Silo building will be
retained and the historic finger dock outline
Silo D is traced into the park and up into Silvertown
Figure 5.57 Landscape analysis diagram
Figure 5.58 Photo of Silo D and finger dock Figure 5.59 Existing photo of Silo D from the north
SILVERTOWN
2 AVENUE
1
BOLLARDS
NATURAL
PLAY
BRICK
LOW BRICK NATURAL
PAVING
WALL PAVING PLAY Figure 5.61 Duisberg Nord (Latz photo © Christa Panick)
FINGERDOCK
PAVING
SELF-BINDING
GRAVEL
LOW
WALL
INDICATIVE SILO D
BOLLARDS TABLE
SILVERTOWN STREET
A
NATURAL
S IL
PLAY
OD
LOW
BRI
DOCK EDGE
WALL SLEEPERS
DG
GRANITE
E
SETTS
DOCK EDGE
SLEEPERS
A DE
A LSI
CAN SILO D
TERRACES WITH
SEATING NICHES WAY
AND PIONEER
PLANTING
Figure 5.60 Illustrative Plan - Silo D Park. Numbers 1-4 represent location of views on following page (see fig 1.69 for section A) Figure 5.64 Karls Adventure Village, Berlin (Berliner)
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 113
Figure 5.65 View 1: Looking southwest - Silo D Park Figure 5.66 View 2: Looking southeast - Silo D Park
Figure 5.67 View 3: Looking southwest - Silo D Park Figure 5.68 View 4: Looking northeast from Silvertown Street
SILVERTOWN
STREET
SILO D
BRIDGE
EXISTING GRANITE
PAVING AND
AMPHITHEATRE DOCK EDGE
SLEEPERS
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 115
5.2.4 SILO D BRIDGE For residents of Plots 7 and 8, the bridge will
become part of their daily life, crossing it as
Concept
Inspired by the efficient and asymmetrical
part of their commute or making their way
Masterplan context towards the north of the Site. The Bridge
crane structure currently appended to Silo
D itself, the bridge responds to the unique
From a masterplan perspective, Silo D Bridge offers the opportunity to make crossing the
design character of the silo and the Site’s
is a vital link for north-south movement finger dock an experience, part of a daily
utilitarian heritage. The durable weathered
through the Site. At its southern end, ritual.
steel finish ties it into the heritage of the site
Silvertown Avenue splits, and while the
and overarching landscape strategy. It will be
primary direction of travel is expected to be Lastly, given the importance placed on water
the first of a family of bridges throughout the
west to Silvertown Street, Silo D Bridge still and the relationship to water throughout the
area of canals. Its scale and design respond
carries a significant amount of pedestrians Site, the new bridge plays an important part
to the intimate water condition of the tighter,
making their way to Pontoon Dock DLR or in the realisation of these ambitions.
smaller finger docks as opposed the open
other destinations to the south-east.
water for Royal Victoria Dock and larger, more
exposed Pontoon Dock stretches. Figure 5.71 Reference to the Site’s utilitarian heritage
The setting of the Bridge, next to Silo D and
Silo D Park, adds to its significance. It needs
%*EQMP]SJ'EREP&VMHKIW-RWTMVIHF]7MPS('VERI
to complement both, in terms of form and
scale.
%*EQMP]SJ'EREP&VMHKIW-RWTMVIH
0ERKYEKISJ'VERIW%W]QQIXV]-GSRMG7X]PI
0ERKYEKISJ'VERIW%W]QQIXV]-GSRMG7X]PI
Silvertown Avenue
Silo D
Silo D Bridge
e
a l sid Q
Can
Barri
er Po
Sil o
'SRXIQTSVEV]'VERI
int R
*EQMP]SJFVMHK
'SRWXVYGXMSRXLIQSWX
DW
QEXIVMEPMX]GSPS
IƽGMIRXWXVYGXYVI
o ad
TVSƻPILIMKLX[
ay
(EVOFVMHKIHIG
HEVORIWW%RS
[SYPHFIQSVI
lwich Road
Q
North Woo
Q
Figure 5.70 Silo D Bridge will provide a key pedestrian connection Figure 5.72 Crane structure appended to Silo D Figure 5.73 Scale and height, Westersingel, Rotterdam
6IJIVIRGI;IWXIVWMRKIP6SXXIVHEQ
%QE^MRKLIVMXEKIGVERIEVXMJEGXEX7MPS(
116 'SRGITX7OIXGLIW
Landscape | 5.0
Proposal
The Silo D Bridge facilitates another key
desire line connecting the highway and public
realm areas around Plots 7 and 8 as well as
those travelling from North Woolwich Road
to provide step free access to Silo D Park and
the development to the north.
Figure 5.76 Proposed bridge passage Figure 5.77 Proposed bridge elevation
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 117
Figure 5.78 Silo D Bridge side view
Figure 5.79 Silo D Bridge approach Figure 5.80 Silo D Bridge internal view
Figure 5.81 Silo D Bridge aerial view Figure 5.83 Silo D Bridge night view
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 119
5.3 PLANTING STRATEGY
The post-industrial landscape found on site is
referred to as ‘Open Mosaic Habitat (OMH) on
Previously Developed Land’, and is designated
as a UK Biodiversity Action Plan (UK BAP)
priority habitat.
Precedents
Figure 5.98 South Gardens (CTF Photo ©A Pollok-Morris)
Examples of successful low-input naturalistic
plantings are shown and described as follows:
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 121
5.3.2 TREE STRATEGY • Enhance ecological biodiversity of the site
and support varied fauna
The tree planting strategy is inspired by the
conditions and naturalistic plant communities • Respond to Civil Aviation Authority
found on site and within OMH. Species concerns regarding bird strike hazard to
selection and distribution avoids the formal Civil Aviation - refer to separate section
traditions of uniformity or baroque ‘green
architecture’, and instead articulates a sense • Ensure sufficient soil resource/volume is
of wildness found on the site. Naturalistic available to all trees in accordance with
and opportunist distributions of plant current best practice
communities are proposed that will appear to
have colonised the site over time, informed by Dockside Trees
varied site conditions. Generally large canopy species that are
associated with windswept waterside
Tree Selection Criteria conditions - Black Pine, Willow Oak, Sea
• Create a strong local identity for the Buckthorn, Honey Locust and Serviceberry
Silvertown Quays site and emphasise the
hierarchy of public realm and streets with Rain/Pioneer Garden Trees
pioneer species to the north and late Species that are commonly found as pioneer
successional species to the south species and are able to withstand seasonal
inundation - Cut-leaved Alder, Hazel, Downy
• Utilise a diverse range of species and Birch, River Birch, Spindle, Eastern Redbud
canopy sizes in accordance with best
practice and for reasons of biosecurity and Marker Trees
climate resilience
Denote key thresholds and junctions and
provide legibility - Chinese Elm, Honey Locust,
• Responsive to localised site conditions
Black Poplar, Willow Oak
i.e. microclimate (exposure to sun, wind), Dockside trees
soil resource, localised watershed, ground
coverings
Parkland Trees Marker trees
A combination of large canopy and fruiting/
Pioneer/Rain Garden trees
• Large canopy, long lived trees are flowering species to provide shade, ecological
preferred where possible to provide value and seasonal variation - Mulberry, Parkland trees
significant long term green infrastructure Broad-leaved Cockspur Thorn, Black Pine, Sea
with multifaceted benefits such as - Buckthorn North Woolwich road trees
cooling/shade, wind mitigation, pollution Courtyard Trees
mitigation and ecological services, well- Courtyard Trees/Copse
being, Described in the Plot sections of the DAS. Courtyard Copse
Figure 5.101 Quercus phellos - Willow Oak Figure 5.110 Ulmus ‘New Horizon’ - Elm
Figure 5.102 Hippophae salificifolia - Sea Buckthorn Figure 5.105 Gleditsia triacanthos - Honey Locust
Figure 5.108 Sorbus torminalis - Wild Service Tree Figure 5.111 Alnus ‘Imperialis’ - Cut Leaf Alder
Figure 5.103 Betula pubescens - Downy Birch Figure 5.106 Pinus sylvestris - Scots Pine Figure 5.109 Populus nigra betulifolia - Black Poplar Figure 5.112 Amelanchier lamarkii - Serviceberry
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 123
5.3.3 GROUND the reuse of site won materials and soils
which will be investigated at the next stage of
PLANTING STRATEGY the project
Figure 5.117 Fennel, Cytisus Figure 5.120 Scabious, Wild Carrot, Fennel
Figure 5.115 Centranthus, Fennel, Salsify, Papaver Figure 5.118 Cistus, Euphorbia, Artemisia, Tulbaghia Figure 5.121 Sanguisorba, Filipendula Figure 5.124 Erica arborea (Tree Heather)
Figure 5.116 Stipa, Achillea, Allium, Fennel Figure 5.119 Verbascum, Perovskia, Allium Figure 5.122 Pilosella aurantiaca Figure 5.125 Tamarix (Salt Cedar)
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 125
5.3.4 BIODIVERSE Guidelines 2018.
Log Pile
PLANTING
MULCH
SUBSTRATE
DRAINAGE/RESERVOIR Figure 5.131 Typical biodiverse green roof build-up of planting, mulches, 100-200mm substrate and drainage layer
ROOT MEMBRANE
PROTECTION FLEECE
Figure 5.127 Components of a Biodiverse Green Roof VEGETATION BARRIER
Optigreen System Type "Solar Green Roof" Figure 5.132 Habitat Feature - Sand Lens
FigureSun
Solution: 5.128 LABAN
Root 15° biodiverse green roof (©Dusty Figure 5.129 PV and Green Roof - Biosolar Roof
Gedge) 2850 mm - 3600 mm
1270 mm - 2000 mm
1680
mm
1680
mm
dow
Sha
15°
900 mm
15°
500 mm
300 mm gravel
Figure 5.130 Biosolar Roof detail (©Optigreen) Figure 5.133 Habitat Feature - Ephemeral Water
Suitable substructure *
Optigreen Solar Module Support "Sun Root 15°" (60 mm) Gravel strip 16/32
L-shaped fixing profile Waterprofing membrane (root resistant according to FLL)*
Silvertown Quays Phase 1 Reserved Matters
Module Support Application | Design and Access Statement 127
Photovoltaic Module Optigreen Protection and Storage Fleece Type RMS 500
Figure 5.140 Permavoid Blue Roof System - proposed on the podium courtyards to plots 1, 7 and 8 (Polypipe)
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 129
5.5 PLAY STRATEGY
Children’s play forms an intrinsic element playable spaces’ within plots therefore play
in the public realm and plot courtyards and will be provided off-plot within adjacent
responds to high intensity programming. As public realm spaces.
such play is integrated within the landscape 10m²
and all features have been considered Residential Play Streets 10m² 85m² 20m² 10m² 10m²
for their potential play value within wider
Play is embedded into the pedestrianised
multifunctional spaces.
residential streets as ‘play-on-the-way’. Evelyn
80m²
Walk, Silo D Way and Silvertown Avenue.
Play will be provided on-site in accordance 20m² 90m²
Large scale rain gardens will form a playable
with the LB Newham Play Standards 10m² 45m²
landscape suitable for the 0-8 range where 90m²
which defer to Greater London Authority
plants and trees are interwoven with play 130m²
2012 Supplementary Planning Guidance
opportunities including check-dams (Silo
‘Shaping Neighbourhoods: Play and Informal
D Way), logs and stepping stones, granite
Recreation’.
boulders, found objects and ribbon-like raised
• Play value is provided on site through a pathways.
combination of conventional equipped play
features, wherever possible integrated in Public Realm
the landscape Will accommodate play for all ages but with
an emphasis on the older age ranges from
• Natural play in the form of playable 5-11 and 12+. The water play features of Mills
landscape and informal playable elements Square and the Play tower in Silo D Park are 30m²
with intrinsic but unprescribed play value described in the previous section of the DAS. 25m² 20m²
will be provided within multifunctional 20m²
These spaces alongside the Pioneer Gardens
spaces. of Silvertown Place will be complimented with 55m²
integrated playable features such as slopes, 30m²
• Where feasible there is a preference step stones, parkour furniture, salvaged 20m²
45m²
to create play features that can be industrial artefacts, logs and timber sleepers. 100m² 30m²
manipulated, including loose sand, water 10m²
25m² 0-4 years
and movable objects. Child Yield 30m² 10m²
80m² 70m² 5-11 years
Child yield for each of the plots has been 40m²
• Play features will reflect the unique genius 70m²
calculated in accordance with the 2012 SPG 12+ years
loci of the site, its industrial past and
rather than the recent ‘GLA Population Yield
its functionality (i.e. rain gardens). Site Silo D Local Park
Calculator’ (amended June 2019) as this is not 120m²
reclaimed artefacts and materials will be
aligned with the age ranges set out in the SPG 100m²
40m²
salvaged for possible reuse as playable 70m²
(i.e. 0-4 years, 5-11 and 12+).
objects that have an educational/ heritage 130m²
value. 80m² 65m²
50m²
80m²
Residential Courtyards 40m² 80m²
Doorstep play facilities are focussed in plot
courtyards for 0-5 years. It is practical to
include play for slightly older children, i.e.
siblings, so the age provision is ~0-8 years. It
is not considered practical to provide ‘local Figure 5.142 Play Strategy
Table 5.1 Plot 1 child yield Table 5.3 Plot 6 child yield Table 5.5 Plot 8 child yield
Assessing child occupancy and play space requirements Assessing child occupancy and play space requirements
Alternative Alternative
local Total (sq m local Total (sq m
GLA benchmark benchmark play space) GLA benchmark benchmark play space)
(sqm)* (sqm)** required (sqm)* (sqm)** required
10 404.0 10 264.0
10 404.0 10 264.0
* GLA benchmark standard=minimum of 10sqm of dedicated play space per child * GLA benchmark standard=minimum of 10sqm of dedicated play space per child
** Borough's local benchmark ** Borough's local benchmark
Table 5.2 Plot 5 child yield Table 5.4 Plot 7 child yield
Figure 5.144 Domino Park (Field Operations) Figure 5.147 Granary Square (Townshend LA)
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 131
5.6 INDUSTRIAL ARCHAEOLOGY - FOUND LANDSCAPE
Alongside the retained buildings, Silvertown In addition reclaimed material such as stone
provides a rich layering of historic artefacts cobbles/granite setts, timber sleepers, logs
and industrial archaeology which includes from felled trees, concrete blocks can be
train tracks, jetties, dock walls and re-purposed as informal seating, natural
cobblestones. play elements, edging elements and possibly
feature pavings.
Industrial artefacts from the Mills building and
Silo D will be salvaged where practical and Found aggregate material such as gravels,
celebrated as public art and/or play features crushed stone, brick and concrete can
in the public realm to create a reference to potentially be reused on site to create Open
the place and its history. Remnant building Mosaic Habitat conditions in the public
slabs provide a scale and reference to the realm Pioneer Gardens or biodiverse green
industrial heritage of the site and provide roofs. Manilla rope often found discarded on
inspiration for the proposed hard landscape. dockland landscapes is a suitable material for
habitat features on green roofs.
The existing pre-cast concrete dock wall
capping’s will be retained and extended as a
detail common to the dock walls in the Site.
Existing dockside bollards and capstans will
be retained in place wherever practical.
Historic Buildings
Cobbles retained/repaired
Cobbles to be lifted
Relaid Cobbles
Existing Bollards
Existing Capstans
Figure 5.149 Map showing the Graving Docks at the Victoria Docks, 1859. (PLA Archives)
Plate 43: Map showing the Graving Docks at the Victoria Docks, 1859. PLA Archives
Figure 5.150 Aerial photo showing remnant concrete slabs (©Google) Figure 5.156 Photo flour sack slide
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 133
5.7 HARD LANDSCAPE
The proposed hard landscape is inspired by extend in a series of directional strips along
the varied utilitarian aesthetic found on this the street gradually diminishing as it moves
post-industrial site. This is informed by its away from royal dock. The brick relates to
degradation over time as hard surfaces their the language of brick masonry panels found
joints and interstices have been colonised on Millennium Mills and the Hovis Building
over time by opportunist plants, lichens and façades.
mosses.
Silvertown Avenue and Mills Way
The proposed paving palette aims to engage
Here the concrete plates gradually give way
with and express the scale, grain and patina of
to a greater dominance of brick paving which
the found landscape. Different materials have
is proposed in 2 formats - a slim 50x200mm
been proposed to emphasise the function,
laid in herringbone pattern for shared spaces
character and legibility of spaces across
and a 200x200mm staggered bond clay unit
the phase 1 public realm landscape and are
to define safe routes for pedestrians. A 60mm
described as follows:
high kerb demarcates shared space and safe
pedestrian routes. This transition is reinforced
Dock Waterfront by the presence of seating, rain garden edges
The Royal Victoria Dock waterfront is the key and a ductile iron channel drain. On junctions
threshold and it is characterised by the scale a paving feature is inlaid in panels into the
and language of an industrial landscape. To tie brick surface to denote the shared surface
in consistently with the Royal Dock frontage and warn vehicles/motorists and pedestrians
and Britannia Village to the west the pre-cast alike.
concrete dock coping and the band of granite
setts will be continued into the phase 1 site. Residential Streets and Canalside Asphalt
Behind this large slabs of in-situ concrete will
On the residential streets of Barrier Point Brick tiles staggered bond
evoke the remnant concrete aprons found
Road, Wesley Avenue and Hovis Street the
to the north with staggered joints and will Brick herringbone
material palette changes in character to
provide the main walking surface along the
reflect a conventional London street. Asphalt Site won granite setts
dock. These panels give way in places and
carriageways are inlaid with aggregate,
appear to be broken and in-filled with pioneer Large precast concrete plates
standard 100mm high kerbs and concrete
planting or ‘repaired’ with a brick paved. The
small unit paving define pedestrian routes.
entrance to the Mills will be a continuation In-situ concrete
Silvertown Street will consist of the same
of this theme and extended into steps ramps
palette but with 60mm high kerbs. On Fingerdock Paving
etc.
Canalside vehicular traffic is expected to
Small unit concrete blocks
be minimal therefore small unit paving
Silvertown Place is employed as a shared surface with a Self binding gravel
On Silvertown Place the slab pattern breaks contrasting paving to demarcate a safe
down and a new geometry is found with a pedestrian route (subject to Road Safety Concrete pavers
combination of planting and large pre-cast Audit). Granite setts
concrete plates. These mingle with planting
and brick panels and form a directional Mills Square and Silo D Park Precast concrete bridge
device emphasising the line of the dock. The
Refer to previous sections of this DAS for a
concrete plates are employed in 2 sizes and
description of the materiality of these key
spaces. Figure 5.157 Hard Landscape Strategy
Figure 5.160 Precast concrete plates and planting Figure 5.162 Tegel (tile) clay pavers laid staggered bond Figure 5.165 Granite panels to denote shared Figure 5.169 Asphalt with rolled chippings
junctions
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 135
5.8 FURNITURE
The palette of street furniture, seating and established spacing rules to allow pedestrians
habitat features has been carefully selected to pass through. Where appropriate measures
to articulate the function of the proposed will be visually enhanced with Corten to
landscape and instil it with the sites intrinsic articulate the industrial qualities of the site.
historic and landscape character. *
Litter Bins
Dock Edge Generally litter bins will be integrated
To retain the character of the dock as into landscape features where possible
a visually open dock edge the existing including benches and rain gardens. For
treatments of post and chain and post and consistency litter bins are proposed with
wire railings are to be replaced with a passive a similar aesthetic to the bollards and will
edge protection treatment consisting of a accommodate HVM where required.
continuous line of 3m long timber sleeper
benches set out with 600mm gaps. These Wind Screens
provide a good degree of safety without
Screens are required to the east of plot 1
precluding access to the waters edge for
to mitigate the effect of wind in the public
leisure uses.
realm. The proposed screens are shown in
the visualisations the Dock Waterfront section
Rescue equipment consisting of life rings will
of the DAS and consist of vertical steel and
be provided on the dock edge every 20m.
timber fins.
Figure 5.178 Emergency Life Ring Figure 5.181 Insect Hotel, South Gardens (CTF)
Figure 5.173 Drifter picnic bench (Streetlife) Figure 5.176 Corten PAS 68 bollards Figure 5.179 TfL Legible London ‘Monolith’ Figure 5.182 Loggery, Kings Crescent (muf)
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 137
5.9 DOCK WALLS
The purpose of this section is to satisfy The
Reserved Matters Specification xvii (Annexe
5.9.2 SURVEY RESULTS
A of the OPP Decision Notice) in relation to
dock walls; details such as the layout, finished General
levels and materials to be used on external An above and below water level survey of the
surfaces are to be provided. WALL E2
three walls has been carried out to assess WALL E3
their condition; the survey was combined with
5.9.1 EXISTING DOCK an assessment of archive drawings for each
of the frontage sections. A summary of the
WALLS IN PHASE 1 RMA findings of the condition survey is provided
SITE below.
Figure 5.183 Existing dock wall locations and Phase 1 RMA Boundary
Figure 5.184 View of existing dock wall at location E2 Figure 5.185 View of existing dock wall at locations E3 Figure 5.186 View of existing dock wall at location C4
from Royal Victoria Dock from Royal Victoria Dock from Pontoon Docks
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 139
5.9.6 WALL E2 Materials 5.9.7 WALL E3 Finished Levels
The repair of the walls will vary from simple The dock walls are not the primary flood
A new sheet pile wall, tie-rods and sheet pile
Layout mortar patchwork, replacement of cracked defence for the area. However, the minimum
brickwork, and strengthening works where anchor wall are proposed to replicate the required land side dock level for the new
Wall E2 will maintain the line of the existing existing appearance of the water frontage
cracks in the coping have appeared. The wall development is set at +5.18m AOD based
wall.
will require future maintenance at intervals on the required minimum flood level. A new
throughout the life of the structure. The new frontage will be constructed concrete capping beam will be installed to
As the dock walls form a secondary flood approximately 1-2m in front of the existing raise the wall to the proposed finished level of
defence, the Environment Agency does not wall, with the anchor wall located 12m back
stipulate a minimum access strip. However,
Street Furniture approximately +5.2m AOD.
so as to remain independent of any building
LRD requires that a minimum of 1m access Details of the street furniture are provided in foundations, as well as providing sufficient
Section 5.8 Furniture.
Materials
strip is provided. The retained existing dock access for future maintenance. The wall will
wall will require access for inspection on be clad with pre-cast concrete sections with A new steel sheet pile wall, tie-rods and sheet
an annual basis and possibly maintenance Lighting the front face terminating below the lowest pile anchor wall are proposed to maintain
every ten to twenty years of the life of the impounded water level to provide long term the existing appearance of water frontage.
Details of the lighting are provided in Section
new development. Access to dock walls for corrosion protection to the sheet piles. The wall will be clad with pre-cast concrete
5.10 Lighting strategy.
maintenance will be via access roads on sections with the front face terminating below
land side. Access is also available from the the lowest impounded water level to minimise
Layout the effects of corrosion on the sheet piles and
water.
assure the design life of the structure.
Wall E3 will follow the existing line of the wall
Waterside safety equipment including safety
with a minor offset to incorporate the existing
ladders, lifebuoys and throw lines will be Street Furniture
structure.
provided along Wall E2 in line with best Details of the street furniture are provided in
practice. Section 5.8 Furniture.
As the dock walls form a secondary flood
defence the Environment Agency does not
Finished Levels stipulate a minimum access strip. However, Lighting
The dock walls are not the primary flood LRD requires that a minimum of 1m access Details of the lighting are provided in Section
defence for the area as the primary defence strip is provided. The new frontage is 5.10 Lighting strategy.
is the Thames flood walls combined with the not expected to require any significant
King George V lock flood gate and the Thames maintenance for 50 years or more. Access
Barrier. However, the minimum required land to dock wall will be required for occasional
side dock level for the new development is inspection and, eventually, for maintenance.
set at +5.18m AOD based on the required This access will be via the site’s access roads.
minimum flood level. A new concrete capping Access is also available from the water. The
beam will be installed to raise the wall to anchor walls will be located 12m behind the
the proposed finished level of approximately new dock wall so not to interfere or clash
+5.2m AOD. with the building foundations.
Finished Levels
The dock walls are not considered to be the
primary flood defence for the area. However,
the minimum required land side dock level for
the new development varies between +5.18m
AOD to the lowest level of +3.50m AOD. The
top of the wall will remain at its current level
of +5.18m AOD.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 141
5.10 LIGHTING STRATEGY
5.10.1 PURPOSE 5.10.2 SITE SURVEY
The purpose of this lighting strategy is Michael Grubb Studio (the lighting consultant)
to create a uniquely lit environment for undertook a survey of the surrounding area
Silvertown which defines it, not only as a and site on the evening of 15th August 2019.
desirable residential location, but as a vibrant The purpose of the survey was to review
destination. A place to be that, at its heart, and record existing lighting conditions during
focuses on people connecting them with twilight hours and after dusk.
space. Due consideration will also be paid to:
• U
se lighting to inspire and create a
character and identity for the site
• Protect and support surrounding habitats Figure 5.190 West of Site - Residential and Silo D Figure 5.191 Approach to Millennium Mills along dock
waterfront
This section provides key strategic principles
to establish an overall approach and
aesthetic, as well as set up lighting principles
for the Site as a whole to support an
attractive and cohesive look after dark.
Figure 5.192 South of Site - Exit from DLR towards Figure 5.193 Millennium Mills (left hand side) from Royal Victoria Bridge
Silvertown
Figure 5.194 Inspiration from the past Figure 5.195 The colour spectrum
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 143
5.10.4 COLOUR
TEMPERATURE
A warm and welcoming environment will be
created for Silvertown by selecting a warm
colour palette of lamps. The principle being to
retain the warmth associated with sunset and
sunrise.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 145
5.10.8 SUSTAINABILITY 5.10.9 ECOLOGY 5.10.10 AVIATION The scheme has been developed in
accordance with CAP 393 Air Aviation: The
The extent and manner with regard to the use Artificial lighting can cause disturbance to London City airport and its runway are Order and Regulations, which requires:
of light will become a very visible symbol for ecological systems because animals, insects situated approximately 1km to the east • No strobe, laser or flashing lights should
the development’s sustainability credentials. and plants can all be affected adversely and of the Site. Particular attention has been be included in the lighting scheme on or
the waterside location of the site also needs given to ensure that lighting installed does around the airport’s vicinity.
Light is a highly visible form of energy use that to be taken into consideration to protect the not adversely affect the safe and efficient
not only exploits the earth’s precious natural ecology along the river. For this reason, the movement of aircraft by distracting from • The colour of lighting could cause it to be
resources but also creates unwanted impacts lowest appropriate amount of light has been visual aids or runway lighting. Lighting follows mistaken for an aeronautical ground light.
such as light pollution. The amount of light, used to achieve the needs of the various British Standard 5489, Part 8, which states In particular, white lights in a runway or
its distribution and direction and the manner routes and spaces. Lighting will be controlled the area within which a road lighting scheme linear pattern as well as red, green or blue
in which it is delivered and controlled must all with minimal light spilling upwards. Additional may affect the safe use of an aerodrome lights.
be carefully designed. Over-lighting and light glare control accessories shall be used where is 4.8 kilometres beyond the aerodrome
pollution (particularly light trespass) will be appropriate. boundary. • Light angle and alignment of lighting can
avoided. distract and confuse pilots by causing
Artificial night lighting harms species directly London City Airport operates an aerodrome glare. Lights should be adequately shielded
Light levels will be minimised when and where by triggering unnatural periods of attraction safeguarding policy to ensure the Airport and avoid an upward angle above the
possible but without compromise to safety or repulsion which can lead to disruptions in is consulted on planning applications and horizontal.
and security. S2 and S3 class is proposed for reproductive cycles by fixation, disorientation activities which may affect the safe operation
all pedestrian areas of the site. or by interfering with feeding and sustenance. of aircraft. • Light levels and the overall illumination
Light can also have an effect on the life of should not be at a level which detracts
Efficient light sources, control gear and plants as well as on the animals that use from the effectiveness of the approach and
luminaire optics will help to focus light onto plants for feeding or nesting. runway lighting.
the desired surfaces, whilst defined areas of
unlit public realm - i.e. the River Thames - will Many studies show that different species of • Lit signage should not cause distraction to
ensure that a connection to nature and the birds are affected by certain wavelengths pilots and will need to be assessed.
night sky is clearly promoted. of light in different ways. Where rare and
protected species are known to exist,
research should be undertaken to establish
whether the intensity of artificial light or
specific wavelengths of light should be
minimised generally or at specific times of the
evening/year to help protect species.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 147
5.10.14 ROUTES, SPACES & ARCHITECTURE
Routes have been considered with regard • The Green Island in Silvertown Place
to their intended users, whether these
are pedestrians, cyclists, motorists or any • Silo D Park and associated F&B break out
combination of the three. areas
Dock Waterfront
The external environment is open to the Feature lighting to certain key buildings will
Green
public 24/7, with certain areas being more provide a focal point and establish them as
Island
active than others after dark necessitating a landmark with the Silvertown Quays site.
appropriate feature lighting. Feature buildings include Millennium Mills, Silo
D and the Silo D Bridge across the finger dock. Mills
• M
ills Square is at the heart of the Site, Square
hosting a variety of restaurants, bars and
retail stores with water feature.
Silo D Park
Millenium Mills
Millennium Mills is the heart of Silvertown.
The atmosphere during the day will differ to
the lit night-time space where the pace will be
slower and people will have more time to rest
and socialise. The facade of the Millennium
Mills building will be lit to provide a dramatic
backdrop to the Square creating a destination,
or if desired, lighting could be altered
temporarily to commemorate or celebrate
an event. Lighting the building will connect it
to the Square bringing it down to a human
scale. Spotlights on Feature Lighting Columns
will provide light and focus on key focal points
within the site. Integrated lighting within the
play areas or within seating will add accents
of light and further define the depth of the
space.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 151
5.11 LANDSCAPE MANAGEMENT
As described in previous sections the Planting/Habitat Type Maintenance Task Frequency Season/Month
landscape proposals are deeply influenced Trees Guying: check, retighten if required, remove if feasible once tree is fully Annually and after high Autumn
established winds
by a found OMH brownfield landscape Mulch: replenish organic and/or mineral mulches Twice annually Spring / Autumn
Productive Fruit Trees/ Formative pruning to improve productivity of fruit trees, wall fruit (espalier) Annually Apples/pear winter
typology where plant succession is arrested Wall Fruit Cherry late summer
Mulch: replenish organic mulches to maintain good soil health 2 x annually Spring, Autumn
by the limitations of available soil substrate, Guying: check, retighten if required, remove if feasible and once tree Annually and after high Autumn
established winds
nutrients and moisture as well as the largely Windfall fruit: remove/reuse/compost Annually Autumn
unmitigated effects of microclimate on the Rain Gardens/Pioneer
Gardens/Courtyard
Perennials: Check, stake and tie taller perennials
Perennials/Grasses: Deadhead/cut to ground herbaceous species. NB allow
Fortnightly, as required
Annually
Spring to Summer
Late winter/early
existing site. Understorey seed heads to stand throughout winter
Weed: Remove self-seeded trees and other unwanted/weed species 4x annually
autumn
Spring, Summer, Early
Autumn
Mulch: replenish organic and/or mineral mulches 2 x annually Spring, Autumn
Therefore a key priority in the maintenance Leaves/litter: remove/compost Every 2 weeks and as
required
All year - primarily
autumn, winter
and management of the proposed landscape Check Dams (in sloping Rain Gardens): Inspect and clear inlets/outlets,
repair erosion, remove sediment
Monthly/as required All year
will be to retain this spirit of naturalness and Species Rich Lawn Mowing: Carried out to maintain a tight sward in well used areas Every 2 weeks April to September
MILL ROAD
Building Phase 1 This phase will deliver Silo D Bridge unifying
the proposed links between the Docks, Silo
The first phase prioritises a robust
D Park and Silvertown Avenue with North
placemaking strategy with the early delivery Plot 6
Woolwich Road and the existing community to 1.6
of key public realm spaces. This includes
the south.
Silvertown Avenue - the axial route connecting
Millennium Mills, the future Victoria Dock 0 5 10 20 50 m
N
Building
Royal Victoria Dock Bridge alignment is indicative and
subject to change under separate planning application.Phase 4 Plot 8
footbridge and Silo D, and the associated Silo 1.8
Key
D Park which will provide children’s playspace Plot 1 will be the final residential plot to be Phase 1 boundary
Outline planning permission boundary
Plot 7
and amenity resource for the burgeoning delivered. The western portion of the Dock 1.7
Plot 2a*, 5, 6 Building Phase 1
Silo D neighbourhood. The new north-south Waterfront public realm will be delivered at Temporary
energy centre
connection will be ground-breaking in finally this stage thus completing the links along the Plot 2b, 7 Building Phase 2 AD
LWICH RO
RTH WOO
linking the existing communities to the south Dock Waterfront. Plot 8 NO
Building Phase 3
Plot 1 Building Phase 4
with the docks and beyond and will provide a Plot 3, 4 Building Phase 5 STATION
infrastructure for London. This phase will seePlotthe 2A last remaining Plot 2B
7th floor)
Plot 2Aii (new façade works & fit out to
Plot 1 1.2A 1.2B 8th floor to 12th floor)
1.1
commercial plots delivered completing Mills
This phase will establish new pedestrian links Square and providing a permanent link with Public realm/landscaping Phase 1
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 153
EVELYN ROAD
5.13 ECOLOGY MANAGEMENT PLAN
5.13.1 EXECUTIVE The priority species and habitats for
Silvertown Quays, addressed through the
5.13.2 INTRODUCTION Also required are:
SUMMARY actions in this document are: Greengage Environmental was commissioned ‘xvi. Management arrangements, particularly
by TSP to produce an EMP to support for retained and/or created ecological
• Open mosaic habitat on previously
Greengage Environmental was commissioned the Phase 1 RMA of the Silvertown Quays habitats’.
developed land;
by TSP to produce an Ecological Management development. Specifically, the report
Plan (EMP) to support the Phase 1 RMA of the provides details regarding habitat mitigation, The report also provides details to support
• Invertebrates;
Silvertown Quays development. Specifically, compensation and enhancement, required the following conditions of Outline Planning
the report provides details regarding habitat through the Reserved Matters Specification Permission ref: 14/01605/OUT:
mitigation, compensation and enhancement, • Birds – existing species such as peregrine
(Falco peregrinus) and black redstart xvi and xx (Outline Planning Permission ref: • A
1 Reserved Matters Approval – provides
required through the Reserved Matters 14/01605/OUT). Condition EC1 also requires
Specification xvi and xx (Outline Planning (Phoenicurus ochruros), and target landscaping details;
species including house sparrow (Passer an Ecological Management Plan however, a
Permission ref: 14/01605/OUT). Condition separate Approval of Details application will
EC1 also requires an Ecological Management domesticus); • A6 Planting; and
be submitted to discharge this condition.
Plan however, a separate Approval of Details
application will be submitted to discharge • Bats; and • A11 Green and Brown Roofs.
The Reserved Matters Specification xx.
this condition. This separate document will be requires the following details in relation to Please refer to the Ecological Management
materially the same as the EMP as set out in • Jersey cudweed.
habitat mitigation: Plan, submitted as part of this application, for
this section of the DAS. Key landscaping features include, but are not details about aquatic habitat mitigation and
limited to, the following: ‘…details of habitat mitigation. This shall enhancement.
Phase 1 RMA Site is located in the western include a report where relevant detailing:
part of the Site and comprises Development • Biodiverse living roofs;
Plots 1, 2A (i and ii), 2B, 3, 4, 5, 6, 7 and 8, a. specifications of any green and brown roofs
along with associated public realm and • Green walls;
including their method of construction and
landscaping. Together Plots 2A, 2B and 3 on-going management for five years;
comprise the proposals for the existing • Biodiversity friendly landscaping;
Millennium Mills building. b. details of the ground level planting
• Bird and bat boxes; and
(demonstrating how it has been designed to
Baseline ecological surveys have determined maximise its benefit within the context of the
the site supports protected species and • Invertebrate features – bee bricks, habitat
scheme’
therefore a number of mitigation measures panels and loggeries.
are required to be implemented. These
An ecologist will be present to oversee the
measures are detailed within this report.
placement and installation of the key actions
described in this report.
The proposals will see the loss of an area of
brownfield open mosaic habitat, a S41 habitat
Monitoring proposals for the Site in light of
of principle importance. Therefore, further
the enhancement features include a post
to the species specific mitigation, actions
construction review and visits in years 1, 3 and
included within the landscaping proposals
5 post completion.
have been designed to compensate for this
loss.
This document addresses terrestrial areas of
the Site.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 155
Baseline survey results Invertebrates Bats 2019 Surveys
The Site was subject to a suite of ecological • Silvertown Quays is a site of moderate • A single common pipistrelle (Pipistrellus Updated surveys are in progress to reconfirm
surveys completed in 2013 to support the conservation importance for invertebrates pipistrellus) was recorded emerging from the baseline and where relevant these have
Outline Planning Application (ref: 14/01605/ overall, and is unlikely to be one of the and returning to a roost in the main been used to inform this report. These
OUT). Of specific relevance to this report are most important sites in London. Millennium Mills building with two common surveys include:
the following: pipistrelle recorded emerging from the
• Phase 1 Habitat;
• Brown-banded Carder-bee (Bombus adjacent building in 2013.
• Preliminary Ecological Appraisal (Arup,
humilis), a rare and declining Section 41
December 2013, file ref 601093-12); • Invertebrate;
species, was found. • Common pipistrelles were also thought to
be foraging within these buildings.
• Invertebrate Survey (Mark Telfer on behalf • Breeding bird;
• Silvertown Quays supports what appears
of Arup, November 2013);
to be a nationally important population of • Updated surveys in 2019 have recorded
the rare flower-bug (Anthocoris minki) on a a single common pipistrelle returning • Bat;
• Breeding Bird Survey (Arup, November 2013,
single poplar tree. to a roost in the main Millennium Mills
file ref 231513-25); and • Reptile; and
with two common pipistrelle returning to
• Thin strips of planted trees and shrubs roosts in the adjacent building. The nature
• Bat Survey (Arup, October 2013, file ref • Aquatic.
along the eastern, southern and western (e.g summer day) of these roosts will
230916-00).
edges of the site supported a small number be confirmed following additional roost The only additional finding of note is the
The key findings of the above are summarised of Red Data Book or Nationally Scarce characterisation surveys to be completed presence of a protected plant species, Jersey
below: species. by the end of August 2019. cudweed (Gnaphalium luteoalbum), in the
Breeding Birds Phase 1 RMA Site.
Habitat Survey • Bat droppings were noted on bat boxes
• A total of 42 species of bird were recorded hung from poles along the dock side to the Baseline Summary
• Phase 1 RMA Site supports a unique
assemblage of post-industrial brownfield during the 2013 surveys. north of the Millennium Mills building.
The recommendations mitigation,
habitats. compensation and enhancement, outlined
• Peregrine falcon were recorded on site on within this report have been informed by the
• The industrial heritage of the Site and multiple occasions although no nesting results of these surveys, in addition to best
subsequent years of dereliction have left behaviour was observed. practice, policy drivers and BAP targets.
a patchwork of substrate types, of varying
depths, drainage regimes and topographies. • Two black redstart nests were recorded on In particular, local BAP species such as
This has resulted in a mosaic of grassland, the Millennium Mills building. solitary bees and house sparrow will be
ephemeral/short perennial, scrub and bare considered in designs, alongside bats and
ground, classified as Open Mosaic Habitat other notable invertebrates.
on Previously Developed Land. This is a S41
Priority Habitat of Principle Importance.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 157
Bats Millennium Mills building and all new buildings.
The number and form of boxes is described
5.13.6 JERSEY CUDWEED be sent to the Millennium Seed Bank at Royal
Botanic Gardens, Kew, to be dried, frozen and
Roosting
in the Enhancement chapter, although boxes Jersey cudweed was identified as present stored until the biodiverse roof is complete.
Surveys in 2019 have found evidence of a incorporated into the Millennium Mills building within Phase 1 RMA Site of Silvertown Quays
potential active roost in the buildings of will in effect form compensation for lost during ecological surveys undertaken in 2019 To supplement this the plants and ~5cm
Phase 1 RMA (specifically the Millennium Mills potential opportunities currently afforded. on land adjacent to rubble spoil piles to the of the underlying substrate, a fine sandy
building). Measures to address impacts upon south of Millennium Mills. aggregate mix, will be collected using hand
these, in addition to the existing bat boxes Lighting tools and stored in bags at the development
hung along the dockside, will be implemented. The proposed Phase 1 RMA Development site. These bags will be marked with signage
Demolition / Construction
A European Protected Species licence (EPSL) works would result in disturbance of this area. to indicate its contents and reasons for
from Natural England will be required for Care will be taken to reduce disturbance to The plants are also growing next to a track retention. Upon completion of the biodiverse
these works. The mitigation methodology is foraging and commuting bats using the Site. which is frequently used by film crews, site roofs this substrate will be used to create
summarised below and will be provided in This will include timing works in daylight hours security and other site visitors, resulting in a aggregate piles.
greater detail in the EPSL application. when bats are inactive and keeping noise high risk of accidental disturbance.
disturbance to a minimum. No additional The seed will be collected and sent to Kew
Demolition / site preparation works affecting artificial lighting will be left on overnight. As Jersey cudweed is listed on Schedule 8 of by a named ecologist on an A31 Conservation
the area of the building around the roost will such, light, noise and general disturbance the Wildlife and Countryside Act, 1981 (as Licence. The named ecologist will then also
be undertaken when bats are least likely to be through construction activity will be limited to amended) making it an offence to deliberately oversee collection and storage of the plants
using the roost. The optimal timing for this will within hours that bats are not active. pick, collect, cut, uproot or destroy plants. and substrate, and installation of the living
be confirmed following the additional roost roof, including the spreading of seed. 25% of
Operation Jersey cudweed location and status
characterisation surveys discussed above. collected seed will be retained by Kew in case
An ecological clerk of works (ECoW) will be Lighting design has been designed for wildlife further seeding is required.
Approximately 75 Jersey cudweed plants were
on hand during removal of relevant roosting friendliness. Generally, lighting is considerate observed growing adjacent to a spoil bund to Biodiverse roof specifications
features, roofing elements or disturbance to of the site’s use as a wildlife corridor, the south of the Millennium Mills buildings in
previously inaccessible roof voids. avoiding unnecessary lighting, using low-UV spring 2019. The biodiverse roof will be substrate-based
component warm white LED bulbs which are with a low nutrient substrate ranging between
Prior to demolition a minimum of 4x. Bat downward facing with asymmetric beams, Mitigation strategy ~120-200mm. The substrate will be composed
boxes (Schwegler 1FF2 or similar) will be shielded from spill. Proposals follow guidance of recycled crushed brick, expanded clay
The proposed approach entails the collection
installed in suitable trees around the site provided by the Bat Conservation Trust and shale and recycled organic content (for
of a seedbank from on-site plants which
peripheries as a precautionary measure in Institute of Lighting Professionals3. example Bauder’s Biodiverse Substrate1). This
will then be relocated to a newly created
case any bats are discovered during the should be installed at a sufficient depth,
biodiverse roof on the Millennium Mills
works; the location of these bat boxes will be varying between 120mm and 200mm across
building as part of the Phase 1 consented
determined by the ECoW. the roof providing variation in microclimatic
development works. Precedent for this
condition, creating a range of potential niches.
approach has been set by other Greengage
The bat boxes with evidence of roosting Sandy piles and mounds of the reclaimed
projects, including 45 Millharbour on the Isle
located along the dock side north of substrate from the current jersey cudweed
of Dogs, where Jersey cudweed has been
the Millennium Mills building will require growth location will also be provided. The
confirmed as successfully growing following
relocating. These will be moved to trees 45 Millharbour case study discussed above
relocation onto a purposefully created
being retained as part of the masterplan evidences that these habitat types provide
biodiverse roof on the 14th floor of a new
scheme. Detail relating to this relocation will suitable conditions for cudweed growth.
residential block.
be secured through a European Protected
Species Mitigation Licence with Natural Management and monitoring
Under licence, seed will be collected by hand
England. The living roofs will be subject to standard
from the existing plant stock at the Site in
August – Early-September 2019. This seed will maintenance and management as per supplier
Bat boxes will be embedded within the
• Roof plan Plot 6 - SQP1-CTF-6-LAN-DGA- Invertebrate habitat - Each plot to have bespoke inverte-
LXX-LAN162 other brate habitat wall feature
Table 5.7 Ecological design principles for compensation and enhancement features
• Roof plan Plot 7 - SQP1-CTF-7-LAN-DGA-
LXX-LAN172
www.greengage-env.com
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement Project Number 551197
159
July 2019
1 to 1000 at A3
Basemap data: Google Earth
• Public realm planting plan 2/2 SQP1-CTF-X- Rain gardens are included, incorporating a completion, i.e. with completion year 0, the A single report will be produced each
LAN-DGA-L00-LAN308 species rich palette of wild grasses, flowering monitoring visit would be undertaken in years monitoring period.
perennials/biennials ferns and shrubs, all of 1, 3 and 5.
Principles for incorporation of ecological
which are tolerant of seasonal inundation and This report will include recommendations for
design features which have been considered
intervening dry spells. This would consist of a general high- any adjustments to the agreed monitoring
by each plot are outlined in Table 5.7.
level Biodiversity Assessment which scheme to reflect changing conditions at the
A biodiverse species rich lawn turf is proposed would compare the condition of the site Site.
Living roofs to all lawn areas. This turf is tolerant of high against baseline targets for the ecological
As is in Table 5.7, landscaping proposals will levels of wear, but also contains a wildflower enhancement features as well as compare Recommendations for management and
compensate for ground level habitats (OMH) element and is therefore mown less the overall ecological character of the site maintenance actions will also be detailed.
that are to be lost as a consequence of the frequently to allow the sward to flower. year on year over the course of the five-year This may include removal of nuisance/invasive
development with living roofs providing a monitoring programme. species, supplementary plug planting for
significant contribution to this. The concept Installation rooftops, or changing frequencies of mowing/
is to create an interconnected network This inspection would record the condition vegetation management, for example.
A suitably qualified ecologist will be
of stepping-stones which cross the site, of the various habitats across the site
present to oversee installation of the key
providing opportunities for the movement confirming presence/absence of nuisance or The summary report and key
habitat features, including the living roofs,
of invertebrates and birds roof-to-roof, and invasive species; it will also record any other recommendations will also be made available
invertebrate features and bird and bat boxes.
between roofs and ground level habitats. unforeseeable changes with regard to ecology to relevant architects and landscape
Invertebrate habitat structure is provided
on every biodiverse living roof. This includes
5.13.8 MONITORING AND across the site such as colonisation of living
roofs by new species, or observation of field
architects working on the current and future
phases of the wider development so that
features such as log piles, sandy piles, MANAGEMENT signs or potential for other notable/protected lessons can be learnt and any biodiversity
ephemeral water features and rope coils species that aren’t currently considered within design interventions optimised for future
which will reinforce their brownfield industrial This section provides an overview of the this monitoring scheme. plots.
character, provide aesthetic interest and also relevant management and monitoring actions
support biodiversity. for ecological features incorporated into the
Site as part of Phase 1 RMA. Feature Specification
Ground level landscaping Extensive biodiverse roofs will require little maintenance following initial
Herbaceous and shrub planting at ground Monitoring install and irrigation during establishment.
Extensive biodiverse
A single inspection will be undertaken annually. Drainage outlets will be
level looks to mirror the OMH currently at Site A suitably qualified ecologist will undertake living roof
inspected and cleared where necessary, nuisance species such as butterfly
with reference also to notable sites along the the monitoring programme that will measure bush or Canadian fleabane will be removed.
Thames Gateway Corridor such as Canvey the success of the enhancement features and
Wick. This intrinsically relies on the creation Roof gardens will be managed as per ground level landscapes. Irrigation
the site’s overall biodiversity value, observing
systems will be regularly checked and monitored. Litter and nuisance weed
of a variety of low nutrient, free draining any natural colonisation, the success of the Intensive living roof
species will be removed, with at least bi-annual checks by an experienced
substrates which support low-maintenance planting / seed mixes across the living roofs landscaping maintenance company.
drought-tolerant species including native, and and ground floor landscaping, and the use of
Climber / trellis system living walls will require limited management beyond
non-native Mediterranean or steppe grassland the site by key biodiversity indicators. Green wall – climber / upkeep of irrigation, standard weed control and management if spreading
type species (where ecological value can be trellis growth over windows/doorways. Specialist landscaping management
justified). The proposed monitoring scheme in this companies will be used.
instance will take the form of a visit during
Maintenance is an often-overlooked aspect of artificial invertebrate nesting
Tree species have been selected for their construction to ensure compliance with Invertebrate habitat
habitats. Nest tubes and features will be cleaned at the end of each summer
value for wildlife, ability to withstand urban the design requirements, followed by an features
where practical to do so.
conditions and climate resilience. immediate post construction site review. This
The features require very limited maintenance once installed. Any boxes that
will then be followed by a high level bi-annual Bird and bat boxes
are damage will be replaced.
site inspection beginning the year following
Table 5.8 Ecological Management Actions – to be repeated annually for first 5 years post completion
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 161
6.0
Pre-application discussions
6.1 CONSULTATION PROCESS
6.1.1 CONSULTATION The following methods of engagement
have been used to involve local people in
PROCESS developing the proposals:
FEEDBACK floor for public access and cultural activities. There was support for the north-south
pedestrian link through Phase 1 RMA and
Access to the water: a desire to see the dock edge made more
The consultation process has recorded
accessible through improved pedestrian and
consistently high levels of support for the The proposed approach to activating the
cycle access. Improved east-west routes that
overall approach to Phase 1. As the principle finger dock and providing opportunities to
take people off North Woolwich Road and
of development was previously established enjoy or use the water were highly supported.
the new proposed Royal Victoria Dock Bridge
by the OPP, feedback has largely focused
Access to green space: across Royal Victoria Dock were also noted
on ensuring that Phase 1 delivers benefits
priorities.
and amenities for the existing communities.
Feedback suggested that access to green
The top priorities for this phase of the
space was high on the local agenda, and A full account of the consultation undertaken
Development were recorded as:
there was a particular interest in ensuring on the proposed Phase 1 RMA Development
that green spaces are provided near the and the feedback received can be found in the
1. Providing public access to Millennium Mills
water – as is the case with Silo D Park. It was Statement of Community Involvement which
important to local people that public spaces Figure 6.5 Stage 2 consultation
accompanies this Application.
2. Providing local amenities (cafés, shops, etc.)
felt ‘accessible’ and not exclusive.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 165
6.2 DESIGN REVIEW PANELS
6.2.1 INTRODUCTION
A significant pre-application engagement
process has been undertaken with LBN
planning officers including weekly meetings
with officers to review design and technical
matters, and an extensive and bespoke
DRP programme to ensure sufficient and
co-ordinated input from the Panel. This
comprised of a monthly programme of Custom House
dedicated half day DRP meetings and a Station
Pontoon Dock
Station
consistent panel of DRP members. It enabled
effective design advice, which produced
demonstrable improvement to the design
quality of this Application. We acknowledge
and thank the Panel for their input.
Feedback
Figure 6.7 DRP 01 routes and access points drawing
The Panel were very pleased to see proposals
come forward after a hiatus. They expressed
the need for a more thorough analysis of the
Consented Scheme, to see the scope to make
a more compelling overall proposition within
the approved Parameter Plans including a Millennium
Mills
linkages.
Figure 6.8 DRP 01 Figure 6.9 DRP 01 illustrative masterplan Figure 6.10 DRP 01 Phase 1 and future phases
Landscape Seamless
connection
Mills
SiloSquare, Silo D reference
D Park activity Park and Silvertown Airport Public
Water feature Flexible
Airport Public
Safety Zone
Flexible Safety Zone
Avenue were presented, along with design (PSZ) and integrated events (PSZ) Moored
events Moored
plaza heritage heritage elements plaza heritage
vessels vessels
principles and strategies. Refurbished
jetty for Refurbished
“maritime jetty for
Walking walk” “maritime
and Heritage Walking walk”
Shade trees
Feedback
cycling wayfinding/
route placemaking
and Heritage
element cycling wayfinding/
route placemaking
element
The Panel didn’t find the material presented
specific enough to the Site. They stressed
Daily scenario Special event scenario
theActivated
importance
waterfront with floatingof
dock the ‘found’
terrace, Melbourne, landscape
Australia Local festivals and market, Auckland, New Zealand Flexible events
lawns
Mills Square
unique character andRoyal identity of Silvertown
Docks Waterfront
Figure 6.11 DRP 01 Mills Square urban plaza scenario
et
Quays.
A flexible, metropolitan events plaza
with an iconic backdrop. The heart of
They hoped to see
A space more
for movement betweenevidence
Mills
Square and the Bridge landing. Home to
at
Silvertown Quays. maritime heritage.
forthcoming reviews of how the materiality
and rich character of the Site has informed Mills Silo Connector Mills Square Royal Docks Waterfront
A shared space with a focus on A flexible, metropolitan events plaza A space for movement between Mills
the proposals for the public realm. pedestrian and cyclist experience, street with an iconic backdrop. The heart of Square and the Bridge landing. Home to
Daily scenario Annual event scenario Green plaza / lunch time park
A daily centre of activity, King’s Cross, UK Laneway Music Festival, Melbourne, Australia Every day park, flexible, green and fringed by active frontage terraces,
New York, USA
Daily scenario Special event scenario
Maritime history Green lawn
Activated waterfront with floating dock terrace, Melbourne, Australia Local festivals and market, Auckland, New Zealand Flexible events
ds Heritage ships and industrial harbour equipment as An iconic green plaza, Drexel Square, Philadelphia, USA lawns
outdoor museum, Rotterdam, Netherlands
Strong street
canopy
Plan view Water edge view from the southwest Market scenario view from the north
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 167
STREET SECTIONS
6.2.3 DRP 02 (25 APRIL) North South connector and primary road section
Feedback
hours servicing
hours servicing
Planting zone-
Planting zone
Zone - Out of
Planting zone
Privacy zone
Carriageway
Privacy zone
Carriageway
Pedestrian
Pedestrian
Footway
Footway
Footway
Footway
parking
Mill Road Existing Existing condition
parking
2 2.5 2
The Panel was pleased to see the refinements
6.5 2 3
2 2
2 2.5 2 6.5 2 3 2
2
14
2
2
2 14 2
PLOT 2
Site Boundary
PLOT 1
+2.5 +2.5
Residential Lobby Podium Retail Residential Lobby Podium
Retail +5 Brand Retail
Planting zone-
Planting zone-
Spill out Zone
Planting zone-
Planting zone-
Spill out Zone
Carriageway
Carriageway
Footway
Footway
Pedestrian
Footway
Footway
parking
parking
parking
parking
Zone
2 2
2 2.5 2 6.5 2 3 2 2.5 2 6.5 2 3
4 14 4
18m
James Street, London 22m Nordbahnhof, Vienna 7.6m 11.8m 12.3m 17.5m 18m
James Street, London
Figure 6.16 DRP 02 illustrative masterplan Figure 6.17 DRP 02 sections Plots 1 and 2 Figure 6.18 DRP 02 sections Plots 6 and 7
Feedback
The Panel felt a comprehensive and
MILLS RELICS REPURPOSED IN STUDY OF OTHER RELICS FROM MILLENNIUM
compelling landscape strategy for the whole Floating cinema, Toronto, Canada
THE LANDSCAPE MILLS TAGGED FOR LANDSCAPE
site was lacking from the presentation, and Swimming Pool / Lido, 200 people
4 BRIDGE LANDING
PARK
4 5
4
WATERFRONT
RETAIN + REUSE LIGHTSHIP AND SS ROBIN RETAIN CRANE EXISTING CONCRETE DOCK PROPOSED SILVERTOWN FAMILY OF BENCHES PROPOSED SEATING EDGES INSPIRED BY CONCRETE CAP
S D STRUCTURE WALL CAP INSPIRED BY CONCRETE CAP
2 6
Transformed park for destination events - outdoor
cinema, Miami Beach, USA
3
2
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 169
3 BIRCH GROVE
P of a set of clear diagrams on movement and framework had been established, and the strategies and proposals for Mills Square,
servicing, as well as the presentation of a Panel indicated they were looking forward to Dock Waterfront, Silvertown Avenue and Silo
comprehensive public realm drawing. commenting in more detail on the Phase 1
5 D Park.
RMA buildings.
The main part of the session was the first
presentation of the building designs 4by the Feedback
ROUTES OVERLAY
Figure 6.23 DRP 03 ecological biotopes
MILLENNIUM MILLS PLACE
WATERFRONT CONNECTIVITY + CIRCUITS HISTORY OF CACOPHONY OF WATERFRONT ACTIVITY A NEW FLOATING ECOLOGICAL BIOTOPE
architects of each plot. VENETIAN
ACTIVATED
MOMENT PLINTH EMERGENT PATCHWORK OF PAVING EXTENDING FROM MILLENNIUM MILLS COLUMN GRID
ecology. They indicated their support for the WATER QUALITY TREATMENT
SQUARE TO WATER: A CONNECTED CARPET TO BRITANNIA
ROAD HIERARCHY
1
P 3 defined. Tertiary pedestrian route
5
Pedestrian
Figure 6.24 DRP 03 Mills Square connections
REFLECTING THE INDUSTRIAL RAILS AND COLUMN GRID
WATER JETS
ACTIVATE SQUARE
THE YARD
Out of hours servicingENTRANCE
road ATROAD
WOOLWICH
N
SQUARE, GATEWAY,
4 AND WATERFRONT
8 KEY
Refuse collection location
View of Silo D Avenue (looking north) Primary pedestrian route
ON STREET
ACTIVITIES
7 5 Secondary pedestrian route
Vehicles on pedestrian avenue precedents Parking entrance
6
KEY
ROAD HIERARCHY
Primary pedestrian route Tertiary pedestrian route
5
P P
Secondary pedestrian route
Car club bay
ROAD HIERARCHY
7 Parking entrance
CROSSINGS
Car club bay
P P
Loading bay
Refuse collection location
ON STREET
ACTIVITIES
Loading bay
Pedestrian connections
Proposed pedestrian signalised crossing WATERFRONT WITH NEW
Site vehicle entrance
Primary road
On street parking
Secondary road
Tertiary road Site vehicle entrance ECOLOGICAL BIOTOPE
Out of hours servicing road
P
8 Refuse collection location
ON STREET
Parking entrance
ACTIVE LANDUSE
7
Existing pedestrian signalised crossing
6
CROSSINGS
ACTIVE LANDUSE
Community active frontage
Proposed pedestrian signalised crossing
Previous
Previous
Previous
proposal
proposal
proposal
(25.4.2019)
(25.4.2019)
(25.4.2019) Updated
Updated
Updated
proposal
proposal
proposal Alternative
Alternative
Alternative
updated
updated
updated
proposal
proposal
proposal
Masterplan options
To answer questions about the flexibility
of the OPP parameters, three options were
presented for future phases:
8 8 8 8 8 8 8 8 8
6 6 6 7 7 7 6 6 6 7 7 7 6 6 6 7 7 7
Figure 6.26 DRP 03 Consented Scheme Figure 6.27 DRP 03 re-interpretation of the diagonal Figure 6.28 DRP 03 ‘What if’ option
route
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 171
Plot 1 Plots 2A, 2B and 3 Plot 4
dRMM established plot specific constraints The position of the proposed new core was The initial proposals presented at DRP 03.
and opportunities which had helped to inform supported.
the key design moves for the massing. The
design principles were also reiterated as key Regarding the re-building of the east shoulder
moves which support the design development of the north elevation of Millennium Mills,
of the scheme. DRP suggested amending the setting out
of the openings to more closely match the
Proposed parking provision of 10% (with asymmetry of the existing. They supported
3% wheelchair accessible) was presented, the aspiration to capture the quality and
a reduction from the OPP quantum and character of the existing building.
supported by LBN and Arup.
The presented scheme showed side
dRMM proposed the principle communal extensions within Mills Square to Plots 2A and
residential entrance and concierge located 2B. DRP were concerned that too much of the
from the circus. Concept for this was to link existing building could be obscured.
the first-floor communal garden with the
ground floor entrance. Activation on this
southwest corner was supported.
Figure 6.33 DRP 03 Plot 2B
Figure 6.31 DRP 03 Plot 1 view from Rayleigh Road Figure 6.34 DRP 03 Plot 3 Figure 6.36 DRP 03 Plot 4 south elevation
Figure 6.37 DRP 03 Plot 5 Figure 6.39 DRP 03 Plots 6 and 7 north view
Figure 6.38 DRP 03 Plot 5 plan Figure 6.40 DRP 03 Plots 6 and 7 ground floor axo Figure 6.42 DRP 03 Plot 8 views from Silo D Park and massing
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 173
6.2.5 DRP 04 (21 JUNE)
This DRP was aimed at presenting detailed
proposals for the plots. An illustrative plan
showing the ground floors of the plots in
relation to the public realm was presented as
an introduction.
Feedback
The Panel felt the coordination between
the plot architects to create the necessary
coordinated variety to establish a strong
sense of place an identity could be improved.
Figure 6.44 DRP 04 Plot 1 Silvertown Place Figure 6.49 DRP 04 Plots 3 (right) and 4 (left)
Figure 6.45 DRP 04 Plot 1 view from Rayleigh Road Figure 6.48 DRP 04 Plot 3 Figure 6.50 DRP 04 Plot 4
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 175
Plot 5 Plots 6 and 7 Plot 8
The DRP 04 scheme responded to concerns The development of the ground floor was The DRP 04 scheme further progressed
over the massing in relation to the existing well received, including ideas for the entry the ‘alternative massing’ option with four
flats, reducing the massing to five stories, with sequence and the opportunities for a mix blocks. The revised massing and plot strategy
the corner at six stories to accentuate the of uses around Plot 7’s courtyard. It was responded to DRP 03 comments to improve
entrance at the junction of Silvertown Street suggested that the relationship between daylighting to homes and amenity, and
and Evelyn Walk. With overall support for the Plot 7’s smaller masses and the courtyard introduced an improved courtyard design
housing typology, the elevational treatment should be assessed, and these were reduced developed with the landscape architects.
and materiality were explored through a series following DRP 04. There was encouragement Further DRP 03 comments recommended
of studies. The elevations took inspiration Figure 6.52 DRP 04 Plot 5 street elevation to explore a range of approaches to private a review of the ground floor in regard to
from various contemporary buildings, as well amenity to respond to the location of legibility, entrances and experience of the
as the architectural language of dockside homes, this was also developed further. user. The legibility and hierarchy of the
warehouses and the historic Millennium Most significantly the need to develop the entrances and core locations was carefully
Mills and Silo D across the Site. A number of architectural expression for both buildings considered during the redesign of the
options for the treatment of the gallery were was strongly highlighted. Developing the lower and upper ground floor. The material
illustrated and discussed. character and appearance of both building strategy of ‘anchor building’, ‘enclosure’ and
was the primary focus for proposals following ‘containers’ was introduced, defining the
DRP 04. locations, types and hierarchy of materials.
Figure 6.54 DRP 04 Plot 5 street section Figure 6.58 DRP 04 ground floor and landscape
Figure 6.55 DRP 04 Plot 5 gallery section Figure 6.57 DRP 04 Plots 6 and 7 cycle store entrance Figure 6.59 DRP 04 Plot 8 view from south
Green wall
SILO D AVENUE
Phase 1 RMA masterplan /
There were still questions about the spaces
landscape Silo D dock
around Silo D, as they didn’t seem to be
To demonstrate a coordinated approach, the responding to how the Phase 1 RMA will need
two sessions – on Mills Quarter and Silo D to function in terms of the use of Silo D itself.
Quarter respectively – started with a recap There was also a question about Silo D Way,
of the masterplan, showing the distinct as there was the expectation this would be a Recliners and decking
character of the two Quarters and the heavily used route and the character currently Biodiverse green roo
design guidelines that were set up to ensure seemed to be more like that of a dwelling High quality material finish along dock edge
SILVERTOWN STREET
the design of the three-way junction and the and desire lines in Mills Square and the DO
CK
Programming analysis Millennium Square plan D
A SILO
courtyards of the individual plots. function and legibility of the green buffer. The
A
hierarchy, functions and servicing strategy of
1
B
Again, the plots were presented in further the space need to be clarified. Tegula pavers
1
SIL
the stated concept of colonisation. Illustrative POOLS
B
OD
Feedback proposals for the dockside pontoons would
TREES IN
WA
SELF BINDING BENCHES
GRAVEL TREES IN
Y
PLAYSCAPE/ SELF BINDING
2 A
the masterplan and public realm very useful Seasonal event scenario - 750 people
and were provided with greater assurances Timber benches along dock edge
St Leonards Circus
Figure 6.60 DRP 05 masterplan overview Figure 6.61 DRP 05 three-way junction SMALL UNIT
Flatiron Square (Witherford Watson Mann)
Figure 6.63 DRP 05 Mills Square public realm
PAVING
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement
Main Street Junction landscape plan 177
BLOCK
BOLLARDS
St Leonards Circus
Plot 1 Plots 2A, 2B and 3 Plot 4
Comments from DRP 04 were for ground DRP noted that the architecture had been DRP noted that the materiality of fenestration
floor to be understood within the public developed and refined and praised the result. and secondary infill elements will be very
realm context, and that principle communal important to the character and appearance
residential entrance was vast with convoluted DRP noted that the location of the lift core of these buildings. AHMM made reference to
internal corridors. The ground floor extension within Mills Square is logical, but the Barbican and its timber windows, infill
configuration was therefore readdressed, and that its southern elevation lacks the elegance detailing and deep balconies that can be
the back of house areas made more yard like. and fine grain of the existing buildings. They inhabited and planted, helping to provide relief
recommended that further refinements and from the extensive hammered concrete.
The residential amenity was elaborated improvements should be explored, including
upon with greater detail for the cores, lobby, the introduction of a canopy to emphasise the
private balconies and communal courtyard. entrance into the building at this point.
The landscape concepts of the green frames
edging the private amenity on podium and the
glades proposed to the central space were
well received.
Figure 6.66 DRP 05 Plot 1 view from Rayleigh Road. Figure 6.69 DRP 05 Plot 3 Figure 6.72 DRP 05 Plots 3 and 4
on maisonettes and providing generous cycle storage and lobby spaces to Plot 7 of the entrance and cores for each block in
DOUBLE PANEL 01
SIDE PANEL 01
amenity space to the family homes. Facade was supported and it was suggested that order to appropriately activate the frontages,
studies illustrated the approach to materiality a connection to the courtyard could be respond to the context and provide the best Millennium Mills
and detailing, whilst also addressing the explored, this has been incorporated. The journey home. The residents’ experience was
DOUBLE PANEL 02
SIDE PANEL 02
masterplan guidelines. The use of light brick range of private amenity for Plot 7 was illustrated in vignettes of each entrance.
and red brick to accentuate the corner, plus supported however more clarity was required Facade studies reinforced the architectural Silo D
base proportions picked out with subtle brick for how internalised amenity would be concept, approach to details and adherence
SIDE PANEL 03
FULLY GLAZED
detailing, explored the relationship between integrated into homes, this has been further to masterplan guidelines. Blocks B, C and Figure 6.78 DRP 05 Plot 8 North Woolwich Road view
View along North Woolwich Road
Plots 5 and 6. developed following the DRP 05. D are proposed in a warm brick ‘enclosure’
BRICK INFILL PANELS WITHIN A GRID BRICK DETAIL APPROACH
Anchor building elevation treatment
exterior and light brick ‘container’ interior, Simple white brick finish
SIMPLE BRICK
whilst Block A sits as a defined object in
01
detailed red brick. The brick detailing in Block BURRIDGE GARDENS, HAWKINS BROWN
CHAMFERED BRICK
02
Blocks B, C & D which defines and unites the
buildings. The special brick detailing within the HAMPSTEAD GREEN, MORRIS+CO
Figure 6.75 DRP 05 facade studies Figure 6.77 DRP 05 Plot 7 south elevation bay study
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 179
6.2.7 DRP 06 For Mills Square, the Chair commented that
the extent of the space will be defined by the
Plot architecture Plot 1
The Chair re-emphasised the requirement for The adjustments to the plan, layout and
CHAIR WORKSHOP phase 2 buildings to the south, and that it is
distinctive place-making architecture to firmly landscape were welcomed and helped to
important that this feels like a large, singular
(11 SEPTEMBER) public space. The extent of cycle parking
establish the unique character and identity of
this new city district.
address previous concerns regarding the
orientation and privacy of homes within this
along the dock edge felt excessive.
plot as well as access to the cycle and refuse
Masterplan Further assurances were requested at storage areas from the car park.
For Silo D Park, more singularity and
The Chair noted that generally, the application stage about the materiality and
simplicity in terms of the colour and surface
refinements to the masterplan that are detailing of the elevations to set a benchmark It was noted that the constraints of
treatment of the ground plane in this area
possible within the approved parameters are for quality when the material samples and construction required more detailed
was encouraged. Tracing the line of the
positive and result in a finer urban grain and mock up façade panels are being considered. consideration. In particular, the difficulties in
historic dock edge in cut granite, inset with
a clearer hierarchy of routes and spaces than achieving the parapet curve in both plan and
interpretive material in key locations was
the original indicative masterplan. elevation should be anticipated as well as
strongly supported.
detailing for weathering.
Landscape
It was noted that the landscape design had
been developed positively and that the key Silvertown Plot 1 | DRP #6 - C
2
4
2 dRMM Architects
Silvertown Plot 1 | DRP #6 - Chair’s Presentation
4
Dark metal panel facade cladding to ground
floor and Block D fins
17
2
26 6
3.
Figure 6.81 DRP06 Dock Waterfront 1. 21 Figure 6.83 DRP06 View towards Silo D 2. Figure 6.84 DRP06 Plot 1 north facade Figure 6.85 DRP06 Plot 1 facade detail
Block A Section and North Bay Elevation
Right: detail of the north 25
Detailed Information
Plot 7 Bay Studies 1
Silvertown Street
PLOT 8
Communal VISUALS
Garden
2
entrance canopy
Repairs where required / fenestration
- eg. concrete and
lintels and cills, exposed steel concrete
1
1 0
0 1
1 2
2 5
5mm 1 0 1 2 5m
BAY STUDIES - TYPICAL BAY / BASE / GRID
rebars, repair to brickwork and application of protective coatings. Metres
Metres 1:100
1:100 Metres 1:100
detail
The existing buildings will be insulated internally to meet Part L.
A
2
3
3 1 3 D
C
5
1
1
2
4
2
1
5
4 5
1
5 1
4 4
2
4 5
1
1 4
3 1
2
5
3
1 2
2
5 5
2
2
DRP MATERIALITY OPTION 01 OPTION 02 OPTION 03 OPTION 04
5
2
3 4
CONTAINERS
DRAFT
2 Existing concrete infill
3
3 Existing concrete lintel Detail axonometric callout
4 Proposed replacement window frame Section Bay study elevation Bay study axonometric Detail axonometric callout
Bay study elevation Bay study axonometric
Section
1 2 3 4 5
09/09/19 CONSULTANTS
5-AE-DSC-LXX-A252
5-AE-DSC-LXX-A252 19-004 CLIENT LENDLEASE
5-AE-DSC-LXX-A252
09/09/19
09/09/19 SILVERTOWN QUAYS PLANNING CONSULTANT 09/09/19
DP9
19-004
19-004 PHASE
Stage 2 1 RMA 19-004
COST CONSULTANT ARCADIS
1 ISO_Plot 2A&2B_Typical Bays_Type 8 2 ISO_Plot 2A&2B_Typical Bays_Type 9 3 ISO_Plot 2A&2B_Typical Bays_Type 2B 4 SILVERTOWN
ISO_Plot 2A&2B_Typical Bays_Type
SILVERTOWN
PHASE
Stage
PHASE
Stage 21
2
2BQUAYS
1 RMA
RMA
Copy 1
QUAYS Strip Sections
STRUCTURAL ENGINEER AKT ll SILVERTOWN QUAYS
PHASE
Stage 2 1 RMA
Blush brick Cant brick panel Textured feature panel Smooth feature panel Light metalwork
Silo D Quarter
Mill Road
Road
oolwich
Nor t h W
Responding to
Millennium Mills
Creating an active and the Royal
waterscape by MILLENNIUM
bringing people S Docks
closer to water MILLS
as a new cultural
beacon Vibrant mixed use
district with destination
retail and brand
Gateway arrival exhibition
and part of the
wider docks
network MILLS SQUARE
A new destination HOVIS
for London PLOT 4 STREET
Servicing
Articulation
of the facade
to reflect
Millennium Mills
PLOT 1
Massing to step
down towards
Britannia Village
P SILVERTOWN
AVENUE
WESLEY Key pedestrian
AVENUE route towards Silo D
Primary road
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 185
7.2 MILLENNIUM MILLS
7.2.1 INTRODUCTION
Millennium Mills is a cherished symbol of
N
the industrial past, its redevelopment will
be the beacon of the Site’s regenerated
future. The buildings define the gateway to
the development. The Millennium Mills brand
will bring back the flow to the Site, providing
activating uses / jobs / cultural draw and
energy. After years of inactivity on the Site,
the primary aim is to restore and activate, and
use Millennium Mills to establish a new centre
of gravity.
Guiding principle
The guiding principle is to retain as much of
the existing character as possible. While parts
of the building will require replacement the
majority of the existing internal structure and
fabric will remain. New additions like lifts
and stairs are proposed to make the existing
usable. These new elements are intentionally
positioned outside of the existing structure to
minimise demolition. Where new elements are
proposed they are designed to be in keeping
with the historic architectural character
and industrial typology of Millennium Mills.
Clear, simple, strong buildings largely made
of concrete with their structure and function
expressed honestly. For a more detailed
explanation of the architectural history of the
existing buildings, refer to the Heritage Report
by Donald Insall Associates.
Plot 2B Plot 2A
Figure 7.3 Plots 2A and 2B north elevation Figure 7.4 Illustrative masterplan. Note: Royal Victoria Dock Bridge alignment and pontoons are indicative and subject to change under separate planning application.
01 5 10 25m
The proposal engages with, and celebrates this history, General view of the North elevation before the fire Millennium Mills before the fire
while retaining the overall form and character of the
buildings.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 187
Land use Plot 2Ai GEA (sq.m.) Plot 2B GEA (sq.m.) Plot 3 GEA (sq.m.)
Plots 2A, 2B and 3 are commercial buildings
Brand (Excl. Retail) 7,965 Brand (Excl. Retail) 11,572 Brand (Excl. Retail) 12,973
set around Mills Square. Each plot is a mixture
of Brand Use, Dedicated Brand A1 Retail,
Dedicated Brand Retail
Dedicated Brand A3-5 Food and Drink, and 35 Dedicated Brand A1 45 Dedicated Brand A1 35
A1
A3-A5 Food and Drink, and Office Use;
Dedicated Brand A3-A5 Dedicated Brand A3-A5 Dedicated Brand A3-A5
• Brand Use 24 124 24
Food and Beverage Food and Beverage Food and Beverage
Sui Generis Use to showcase and promote
corporate, educational and other brands Food and Beverage Food and Beverage Food and Beverage
305 2,885 723
including some or all of the following mix of (A3-A5) (A3-A5) (A3-A5)
uses: demonstration, exhibition, museum,
research and development, education, Office (B1) 0 Office (B1) 10,515 Office (B1) 0
offices, workshops, display.
Total 8,329 Total 25,141 Total 13,755
• Dedicated Brand A1 Retail Use
• Dedicated Brand A3-A5 Food and Drink Use Table 7.1 Plot 2Ai area schedule Table 7.2 Plot 2B area schedule Table 7.3 Plot 3 area schedule
Total 6,639
Amount of development
Plot 2A is a ground plus 12 storey building Table 7.4 Plot 2Aii area schedule
forming the west wing of Millennium Mills,
Plot 2B is a ground plus 10 storey building
at the centre of the development facing the PLOT 2B PLOT 3
square and the docks; and Plot 3 is a ground
plus 7 storey building forming the east wing,
PLOT 2Aii
Office B1
1:15
1:15 1:15 1:15
1:15
Figure 7.7 Ground floor plan Figure 7.8 First floor plan Figure 7.9 Plot 2A second, Plot 2B & Plot 3 first Figure 7.10 Plot 2A third, Plot 2B & Plot 3 second
Figure 7.11 Plot 2A fourth, Plot2B & Plot3 third Figure 7.12 Plot 2A fifth Figure 7.13 Plot 2A sixth, Plot 2B & Plot 3 fourth Figure 7.14 Plot 2A seventh, Plot 2B & Plot 3 fifth
Figure 7.15 Plot 3 sixth Figure 7.16 Plot 2A eigth, Plot 2B sixth, Plot 3 seventh Figure 7.17 Plot 2A ninth, Plot 2B seventh, Plot 3 roof
STAIR
06
1:15
Office B1
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 189
7.2.2 DESIGN PRINCIPLES
Key moves
The diagrams to the right set out the key
urban moves. 4 5
1 3
A fun front door to draw pedestrian 1 3
4
movement along the dock edge to the
entrance. Mills
Square 3
2 2
Mills Square will provide the major public 2
1
space of the masterplan. This will become
a large south facing multifunctional space
to host a range of events- a place to attract
visitors and service locals, for everyone to
have fun, to relax and to enjoy.
1 Fun front door 1 Public route during operating hours, to be 1 East / west route
secured out of hours
2 Mills Square 2 Clear visual connection
2 Mills Square - primary public space
3 Visible lifts - animating the front elevation 3 Raised cantilever for improved connection
3 Shared core in corner
4 Arrival point of proposed Silvertown Bridge
4 Brand entrance space
5 Raised dock edge / entrance space
Figure 7.24 Phase 2Ai- Lower floors of Plot 2A Figure 7.25 Phase 2Aii- Upper floors of Plot 2A
Figure 7.26 Phase 2B- All floors of Pot 2B and shared core Figure 7.27 Phase 3 - Plot 3
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 191
7.2.3 LAYOUT
N
Site layout
The adjacent diagram shows the principal
layout of the scheme. The plan is derived
from the historical arrangement of the existing
buildings. The approach is to extend Plot 3 to
the south and east creating a primary public
space called ‘Mills Square’. Super
Plot 2B core
Core positions
There are two shared cores proposed, which
provide vertical access and escape for Plots Plot
2A, 2B and 3. 2A
Plot 2A is serviced by a core located outside
of the existing fabric set within Mills Square to
the east side to avoid interrupting Silvertown
core
Place and to provide a second means of
escape for Plot 2B. The core is positioned in
Mills Square
Plot 3
the centre of the plan to minimise circulation
distances.
Historic arrangement
Millennium Mills comprises a collection of
constantly changing buildings which have
been chopped and changed over time. The
complex was originally a flour mill, then later
used to store animal feed and various other
products.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 193
Ground floor arrangement
The ground plan is made up of a series of
active frontages facing the key public spaces. N
Plot 2A entrance is on Silvertown Place visible
from the bridge landing.
12 10
11 09
10 08
09 07
08 06 07
07 06
05
06 05
05 04 04
04 03 03
03 02 02
02
01 01
01
00 00 00
2A 2B 3
Figure 7.31 Ground floor plan
01 5 10 25m
1:15
1:15
1:15 1:15
1:15
Office B1
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 195
Buried plant
Buried plant rooms have been proposed
beneath the raised slab of the shared lift
lobby of Plots 2B and 3, and beneath Mills
Square.
3
2
4 Access hatches
N
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 197
Brand Use
In accordance with the OPP, Millennium Mills
is to be a commercial building containing a
mixture of Brand, Dedicated Brand A1 Retail,
Dedicated Brand A3-A5 Food and Drink and
A3-A5 Food and Drink uses, and Office use.
Figure 7.37 Image above illustrates an example of the Dedicated Brand A3-A5 Food and Drink use at ground floor for Plot 2A
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 199
First floor arrangement
The first floor is primarily Brand Use for Plots
2A, 2B and 3. This level of Plots 2A and 2B
are connected to ground floor with existing
openings.
1 Brand Use 3
Future provision for bigger room
2 Cycle store and facilities
First floor Brand Use in Plot 2B is
4 Terrace 2
5 Lift Lobby
12 10
11 09
10 08
09 07
08 06 07
07 06
05
06 05
05 04 04
04 03 03
03 02 02
02
01 01 01
N
00 00 00
2A 2B 3
Figure 7.38 First floor plan 01 5 10 25m
BAR
Figure 7.40 Diagram showing the future flexibility of the Plot 3 bigger room
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 201
Typical floor arrangement
The cores are positioned to be shared and
to provide a second means to escape. They
are located outside of the existing footprint
to minimise demolition and retain as much
as possible. The existing silos within Plots
2A and 2B are removed to create open floor
plates designed to be as flexible as possible
to future tenant requirements.
12 10
11 09
10 08
09 07
08 06 07
07 06
05
06 05
05 04 04
04 03 03
03 02 02
02
01 01 01
N
00 00 00
2A 2B 3
Figure 7.41 Typical floor plan 01 5 10 25m
Plot 3
Figure 7.44 Multiple tenancy split for Plots 2A and 2B Figure 7.45 Illustrative typical floor plan showing possible layout
01 5 10 25m
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 203
Plot 3 Roof
There will be a biodiverse roof on Plot 3 which
will have the appearance of a wild and found N
landscape, featuring planting to suit biodiverse
requirements.
Plot 2A Plot 2B
Plot 2B
Plot 3
1
1 Lift Lobby
2 Biodiverse Roof
12 10
11 09
10 08
09 07
08 06 07
07 06
05
06 05
05 04 04
04 03 03
03 02 02
02
01 01
01
00 00 00
2A 2B 3
Figure 7.46 Illustrative plan showing Plot 3 roof
01 5 10 25m
3 3
2
4
Plot 2B
Plot 3
1
1 Lift Lobby
2 Terrace
3 Plant
4 Existing parapets
12 10
11 09
10 08
09 07
08 06 07
07 06
05
06 05
05 04 04
04 03 03
03 02 02
02
01 01
01
00 00 00
2A 2B 3
Figure 7.47 Illustrative Plot 2B level 09 plan showing possible layout of rooftop amenity
01 5 10 25m
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 205
Plot 2B Level 10
Plot 2A Plot 2B
Plot 2B
Plot 3
2 Accessible Terrace
12 10
11 09
10 08
09 07
08 06 07
07 06
05
06 05
05 04 04
04 03 03
03 02 02
02
01 01
01
00 00 00
2A 2B 3
Figure 7.48 Illustrative Plot 2B level 10 plan showing possible layout of rooftop amenity
01 5 10 25m
Plot 2A Plot 2B
4 2 2
1 3
9
6
7
Plot 2B 8
Plot 3
1 BMU Track
2 Lift Overrun
3 Ramp to Terrace
5 1
4 Escape Stair
4
5 Tenant Plant Space
9 Biodiverse roof
Figure 7.49 Illustrative roof plan
01 5 10 25m
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 207
7.2.4 SCALE
Existing and proposed massing Hovis Hovis
The diagrams to the right explain the existing Plot Plot 2B Plot 2C
mass and the proposed extensions and 2A Plot Plot 2B Plots 2B and 3
2A
additions. Shared Core
Following the OPP Plot 2C has been partially Mills Square Mills Square Plot 3
demolished in accordance with separate
planning application ref: 15/01357/FUL.
A single bay of structure and the facade Figure 7.50 Diagram of the existing plots positions Figure 7.51 Diagram of the proposed plots positions
remains and is supported with temporary
Max height +54.93m AOD Max height +54.93m AOD
propping unable to stand independently
without the support of the demolished
part behind. The proposal is to remove the 2
remaining section of 2C and re-build to
1
closely match the existing elevation in scale, 2 3 3
appearance and material and set within 1
the existing envelope established by the
maximum height parameter plan 07. The 4
4
existing structure and facade is in very poor Max height
+39.9m AOD
state of disrepair with a very tight structural
grid 3x6m which makes it unsuitable for
future uses. The new structure and facade 5
will form the new supercore providing access
to both Plots 2B and 3. 5
1 The east shoulder of Millennium Mills will The proposed massing has been reviewed +54.930m AOD
match the height of the existing building. with the aviation consultant. Refer to Aviation
+54.447m AOD
4.5% Slope +51.810m AOD
4% Slope 3 2
Safeguarding Report for further information. 1
2 The rooftop pavilion will not exceed the
height of the existing rooftop. A BMU is proposed on the roof of Plot 2B to +39.900m AOD
4
provide safe access to clean and maintain
3 The new build ‘missing tooth’ matches the
the façades of the existing building. This will
height of the rooftop extension and does not temporarily exceed the maximum height of
exceed the maximum height of the existing the existing building when in operation. Refer
building. to Aviation Safeguarding Report for further
details.
4 The new build Plot 3 does not exceed the
parameter plan height 0.00m AOD
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 209
Site sections
The existing Millennium Mills buildings will
be the tallest buildings in the proposed
masterplan, but sit comfortably within the
proposed neighbouring buildings which are
medium rise.
1 Mills Square 4
2 Plot 2A in elevation 4
3 Brand Use
2 4
4 Office Use
5 Terrace 3
6 A3-A5 Retail 3
7 Tenant Plant Space
3
3
1
3 2
6
7
2
6
2
2
2 2
2 2
2
2
2
2
2
5 1
1 Lobby
2 Brand Use
3 Plot 2A Tooth in elevation
4 Plot 3 biodiverse roof
5 Mills Square
6 Office Use
N
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 211
7.2.5 APPEARANCE
Appearance of existing facade
The collection of existing Millennium Mills
buildings have been constructed and
changed over time, but share a number of
characteristics.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 213
Photo 109: Exposed reinforcing bars on window top lintel on Nort
Photo 141: View of north facing roof terrace and levels 9 and 10 Facade of block B
Nbhfn fnfs
Image
Figure 7.61 Existing concrete parapets to Plots 2A and 2B. Aspiration is Figure 7.62 Existing concrete Piers to south elevation of Plot 2B. Aspiration Figure 7.63 Existing concrete Piers to north elevation of Plot 2B. Aspiration
to retain the exposed materials, protective coatings maybe required as is to retain the exposed materials, protective coatings maybe required as is to retain the exposed materials, protective coatings maybe required as
Photo 142: Terrace interface with block A showing varying wall thicknesses, features
described. described. described.
on the wall and exposed aggregates to the roof Photo
level112:
wallExposed reinforcing bars on pier on south elevation
and parapets
North elevation
May 2019 Page 104
m Mills\1. MHT\Facade\Inspections\Site Visit Reports\190528 Millenium mills preliminary facade survey report - Rev 01.docx
ation Report
External Façade condition
Meinhardt Façade Technology
Photo 50: Exposed reinforcing bars on West elevation and cut section of
Item 1. Block A – Exposed reinforcing bars on window and
Block A - South Elevation
Figure 7.64 Existing south elevation of Plot 2A with painted concrete Figure 7.65 Existing west elevation of Plot 2A with painted concrete walls Figure 7.66 Existing window openings of Plot 2A with very damaged
: Projecting Columns
piers, andrender
brick infill with beams in relation
over and to thelintels
exposed concrete face ofcills.
Photo
and the
51:infill
andbrickwork
Exposed reinforcing
exposed concretebars
lintelson West
and cills. elevation
Aspiration is to retain the exposed concrete lintels and cills. Aspiration is to retain as many as possible and
Aspiration is to retain the exposed materials and repair as required, materials and repair as required, protective coatings maybe required as repair as required, many may need to be removed and replaced.
protective coatings maybe required as described. described. Photo 35: Exposed reinforcing bars on concrete window ci
2260 | Revision 01 | 26 May 2019 Page 41
H:\Projects\2527 - Silvertown Millennium Mills\1. MHT\Facade\Inspections\Site Visit Reports\190528 Millenium mills preliminary facade survey report - Rev 01.docx
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 215
Image
• 3, Rumford Place, Liverpool (1929-36)
Key Works
• W&R Jacob Biscuit Factory
Plate 22. Millennium Mills from the South, • Castner Kelner Chemical Factory
1984
Images opposite illustrate the character and Figure 7.70 Beams and columns shaped to improve
bearing capacity and reduce mass to be considered
joy of the internal existing concrete frame.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 217
Typological study
A process of research and investigation into
industrial buildings led to an understanding
of the common characteristics, qualities and
aesthetics. This informed the approach to
develop a strong and appropriate architectural
language.
Figure 7.74 Typical detail for east and west elevations of Plot 2A
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 219
Elevation silhouettes
The below elevation diagrams illustrate how
the previous typology studies have informed
the design of a structural silhouette which
creates unique characters to each individual
elevation. Differing playful geometries, vertical
and horizontal emphasis, depth, bay types
and different parapets are the kit of parts
implemented to express a found industrial
architecture.
1 4
2
3
N
1 2
Infill to Plot 2A, with a tighter grid and Plot 3 west elevation, a top expressed as a
unbroken vertical columns help express the projecting horizontal cornice, a large deeply
slenderness of the volume. recessed portico framing an entrance while
providing a terrace at 1st floor level help
create variety to the elevation facing Mills
Square.
Plot 3 south elevation, vertical sheer walls with horizontally textured Plot 3 east elevation, differing bay widths 10.5m and 4.5m, 2-storey high Plots 2B and 3 super core north elevation,
concrete, 2-storey high truss supporting the cantilever to the southeast truss, parapets with one as a projecting cornice another with continuous taking from the language of the existing
corner and a typical bay at 4.5m centres. All create a variety in the vertical columns a shallowly recessed portico frame are all offset facade, the super core elevation has much
silhouette and contrast to the east and west elevations. against the simple silhouette of the new super core. less depth, window apertures are expressed in
vertical slots and capped with a flush parapet.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 221
Conceptual approach Expressing the structure
Inspired by the existing we want to create an The new buildings have their structure
architecture specific to the place. expressed clearly and powerfully, which also
articulates the uses within.
An architecture true to the industrial
typologies that have characterised the Site.
The facade is the stability system
An architectural language that ‘Does what The facade will also act as the stability
is says on the tin’. To paraphrase Alberti ‘ system, in combination with stability walls of
‘Nothing need be added and nothing can be an escape core. This is expressed as a sheer
taken away’. wall in concrete on the southern facade of
Plot 3.
We have created a Kit of Parts that can
repeated and adapted and used for all the Figure 7.76 Image showing 4.5m and Figure 7.77 Image showing shear wall Figure 7.78 Image showing cornice
new build elements. The way that industrial
Material 9m grid projecting spandrels for stability for weight and staining, corbels to
support a cantilever
buildings have always been built without The structure of the building will be concrete.
ornament but with great beauty. The facade will also be concrete with
glazing set between. The concrete lintels
Kit of parts for the architecture and upstands project to create shading.
The framing for the glazing is colour to
A set of details to be used in combination to
compliment the concrete and introduce
create a playful rich tapestry of depth / light
further variety.
and shade from a common set of elements.
True to the industrial typology
Figure 7.80 Images showing coloured window frames complimenting the concrete structure
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 223
Concrete finish 1 2
The concrete finish is to be visible both
inside and out for all new build buildings
and extensions. The images opposite shown
an aspiration for the quality of the surface
finish. With the imperfections adding to
the character, board marks, day joints, tie
holes and small blow hos are visible and are
expected to an extent. The images show a
relatively consistent colour finish is desirable
and excessive making good discouraged.
3 4
List of Images
4 S9 architects
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 225
Elevations
North elevation
The north elevation is characterised by a
repeated array of vertical concrete columns
with brick infill set between two strong
shoulders. As described before the eastern
shoulder will be re-built. The proposal for the
replacement mass aims to retain the scale
and character of the existing elevation and
closely match the fenestration and material.
2
1 4
N 6 Pending tenant use and ground floor activation, a mix of glazing and louvres will be required.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 227
Figure 7.86 View of entrance to Plot 2B
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 229
South elevation Plots 2A & 2B
This elevation faces onto Mills Square.
New doors at ground floor will increase
permeability.
1 Revealed brick spandrels 6 Doors at ground floor Shopfront design and advertising to
be subject to separate applications for
planning permission and advertising
2 Window openings to match existing 7 Double height recessed glazing consent
5 New doors
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 231
West elevation of Plot 2A
The proposal for the west elevation of Plot 2A
seeks to retain the character of the existing
building. A new build ‘missing tooth’ infill will
close the gap between the 1933 and 1954
building with a strong simple silhouette with
clear vertical emphasis.
4 New doors
Plot 2A Plot 4
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 233
East elevation of Plot 2A
On this elevation, the new build ‘missing tooth’
infill extends to ground creating space for a
new external core for Plot 2A. Three bays of
glazing will provide views out from the lift
lobby and make visible the vertical circulation
from the square.
4 New doors 4
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 235
Plot 3
As described before, the architecture of Plot
3 is derived from the robust aesthetic of the
existing Millennium Mills buildings. An exposed
concrete frame clearly reveals the structural
logic. A hierarchy of spaces is expressed
with depth creating amenity and through
the deliberate thickening of the structural
elements to create order and the strong
robust aesthetic.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 237
East elevation of Plot 3
This elevation faces east towards London City
airport and the service yard, and is primarily
characterised by the structural challenge of
creating the cantilever. A steel truss encased
in concrete has been incorporated into the
facade language to transfer the loads from
the upper floors to allow for the cantilever
to create a clearly visible east / west route
through the masterplan.
The proposal is to continue the kit of parts Figure 7.98 East elevation of Plot 3 Plot 3 Plot 2B / Hovis Yard Hovis
referencing the robust aesthetic of Millennium
Mills. The exposed concrete frame clearly
reveals the structure, and a hierarchy of 1 Double height recessed glazing Shopfront design and advertising to
spaces and functions. be subject to separate applications for
planning permission and advertising
2 Recessed window
Plant is located to the northern end of the consent
east facing façade, with the louvres set within Signage design to be subject to separate
into two full 4.5m bays. 3 Expressed concrete frame
applications for planning permission and
advertising consent
4 Steel truss encased in concrete
N
5 Loading bay
1 Uplights to columns
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 239
Typical detail for north and south
elevations of Plot 2B
The proposal is to retain the existing
appearance of the facade. A number of repairs
may need to be completed on the facade,
including repair to concrete lintels and cills,
exposed steel rebars, repair to brickwork and
application of protective coatings. The existing
buildings will be insulated internally to meet
4
Part L.
1 2 1
Figure 7.100 Typical detail for north and south elevations of Plot 2B
Figure 7.101 Typical detail for east and west elevations of Plot 2A
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 241
Typical detail for east and west
elevations of Plot 3
The proposal is to express the concrete
structural frame as part of the facade and be
insulated from the inside.
1 2
2 2
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 243
7.2.6 LANDSCAPE
Plots 2A/2B roofs
Hard and soft landscape terraces are located
at the top floors of Plots 2A and 2B as
indicated. These provide external amenity for
the tenants.
Accessible terrace
Figure 7.107 Rooftop locations Figure 7.108 Axonometric view of the typical rooftop
facade
2
1
1 Stair upstand
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 245
7.2.7 ACCESS
Servicing strategy
Refuse strategy
For Plot 2A, refuse from the upper floors will
be taken down the goods lift to the refuse
store at ground to be collected from the
square out of hours.
Delivery strategy
For Plot 2A, deliveries will arrive via the
square. Hours of servicing to comply with the
OPP.
LOADING
For Plots 2B and 3, deliveries will arrive via the FROM SQUARE
loading bay / Hovis Yard. Hours of servicing to
comply with the OPP.
Refuse Store
Refuse Route
Deliveries Route N
Access
Cycle facilities
Cycle stands
Cycle lockers
1
Showers 3 5
4
1 Cycle Lift
2 Cycle Stair
3 Cycle Store
4 Showers
5 Lockers N
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 247
7.2.8 ACCESSIBILITY AND Car parking Careful consideration of colour scheme,
surfaces, signage and lighting requirements
AD M and BS6465 and provide both ambulant
and cubicles in each of the Male and Female
Millennium Mills will not provide car parking
INCLUSIVE DESIGN for staff or visitors within the proposed
will be developed as the scheme progresses. facilities. Wash-hand basins will be designed
to work and welfare standards. Accessible
development but will include accessible Corridor doorsets will provide adequate
Accessibility and inclusive design provisions WCs will be handed on alternate floors to
parking bay provision in close proximity within effective clear width and appropriate opening
are being designed in line with ADM Vol 2 2015 offer users choice.
the public realm. force.
and BS 8300 2018.
These facilities will be designed in accordance
Please also refer to Section 4.5.12 of this DAS Cycling and end of journey Vertical circulation with the recommendations in Approved
for a detailed commentary of the access and facilities Upper floor office accommodation is
Document M and BS8300.
inclusive design strategy for the Phase 1 RMA.
The proposal indicates provision for bicycle accessed from the lift and stair cores at all
levels.
Egress and fire strategy
storage and toilet / changing facilities at
Pedestrian access It is noted that the Egress Strategy will adopt
first floor level accessed off the street
Staircase provision - This is being developed BS9999:2017 principles and are covered by
Pedestrian access points to the Brand, Retail with powered door access and cycle lift to
to meet the requirements of Approved the separate Fire Consultant report by Buro
and office land uses are described as follows: encourage the use of cycling to and from the
Document K and M of the Building Regulations Happold. Details will be developed during
building.
• Plots 2A and 2B are designed to be highly and BS 8300 Vol 2. the project and this should include specific
permeable for pedestrians at the ground
level. Access is available through Plot 2A
Ground floor access Split-levels - there is also a split-level provisions for disabled people.
Ground floor level accommodation contains between new build and existing with a link
east-west connecting Silvertown Place to
Brand Use, Dedicated Brand Retail (A1); through via stairs and lift for Millennium Mills
Mills Square, and through Plot 2B north-
Dedicated Brand Food and Drink (A3-A5); which will require careful design development
south connecting Mills Square to the Dock
and Food and Beverage (A3-A5); with step to provide step free access going forward.
Waterfront.
free access and will be developed for future Passenger lifts – Passenger lift provision
• Pedestrian access for Brand/office staff tenant fit out in line with accessibility and exceeds minimum dimensional requirements
and visitors to the Plot 2A lift core is inclusive design requirements. with travel speeds to suit the intended height
provided from the east and western
of travel and frequency of use. The provision
frontages, via Silvertown Place or Mills Horizontal circulation will also allow for use of a Fire Fighting lift.
Square.
Corridors will follow the relevant guidance
• The ‘supercore’ for Plots 2B and 3 is located for ADM Vol 2 and BS 8300 Vol 2 with all Sanitary provisions
at the northeast corner of Mills Square and core access corridors having a width that will There are accessible visitor toilet facilities
can be access from either the north or ensure a high level of access for wheelchair on the ground floor level for each building
south. users. section. The dimensions and layout of
Upper level circulation is generally open plan, the cubicle will be designed to meet the
Building entrances requirements of ADM Vol 2 and BS 8300 Vol 2.
with the only corridors proposed serving the
Design development of the entrance doors, WC and Lift Bank locations – this reduces the Accessible shower and changing facilities are
weather protection and signage considers all barrier that doors can present to accessible also provided at first floor level adjoining the
relevant aspects of inclusive design noted circulation. bicycle storage.
including requirements within Approved
Document M Vol 2 of the Building Regulations On the upper floors, WC provision is
and BS 8300 Vol 2. centralized off each floor with standard,
Ambulant, Enlarged and Accessible WC
facilities being located adjacent on each floor
level. WCs will accord with requirements of
Visible
stairs
The architectural appearance and approach 2.0 Site Matters
for Plot 4 is similar to Millennium Mills and 2.05 Site History
Plot 3. The aspiration is to create a collection The assemblage of buildings were constructed in
phases during the interwar years and 1950’s but
were styled to era’s preceeding their repsective
of coherent buildings reminiscent of the construction date. Block A (Inter War) has a late
Victorian style and the newer blocks take cues
from the 1930’s Art Deco movement. As such, the
The proposal engages with, and celebrates this history, General view of the North elevation before the fire Millennium Mills before the fire
4
buildings.
11092 | Millennium Mills | Design & Access Statement | December 2014 Page 16
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 251
Room Key Room Key Room Key
Land use
Boundaries Boundaries Boundaries
Amount of development
Room Key Room Key 1 Room Key
1
01 Entrance 01 Entrance 01 Entrance
SQP1-AHMM-4-AE-DEL-LXX-A-200 02 Cycle Parking 02 Cycle Parking SQP1-AHMM-4-AE-DEL-LXX-A-200 02 Cycle Parking
03 Cycle Parking: Showers 03 Cycle Parking: Showers 03 Cycle Parking: Showers
04 Loading Bay 04 Loading Bay 04 Loading Bay
05 Plant Room 05 Plant Room 05 Plant Room
Figure 7.116 Ground floor plan Figure 7.117 First floor plan
DRAFT Figure 7.118 Second floor plan
DRAFT Figure 7.119 Third floor plan
DRAFT
07 Lift Lobby 07 Lift Lobby 07 Lift Lobby
08 Fire Fighting Lobby 08 Fire Fighting Lobby 08 Fire Fighting Lobby
0 2 10 20 m 0 2 10 20 m 0 2 10 09 Refuse20Store
m 0 2 10 09 Refuse20Store
m 09 Refuse Store
10 Lift: Passenger 10 Lift: Passenger 10 Lift: Passenger
2A
2A
2A
2A
models / drawings for which they are solely responsible. 1 3 models / drawings for which they are solely responsible. 1 3 models / drawings for which they are solely responsible. 1 3 models / drawings for which they are solely responsible. 1 3
- any use of this drawing by parties other than the party for whom it was prepared or 5 London NW1 3BF
- any use of this drawing by parties other than the party for whom it was prepared or 5 London NW1 3BF
- any use of this drawing by parties other than the party for whom it was prepared or 5 London NW1 3BF
- any use of this drawing by parties other than the party for whom it was prepared or 5 London NW1 3BF
for purposes other than those for which it was prepared for purposes other than those for
Purpose which it was prepared
of drawing
Brand Use (excluding retail) for purposes other than those for
Purpose which it was prepared
of drawing
Brand Use (excluding retail) for purposes other than those
Purposefor which it was prepared
of drawing
Brand Use (excluding retail)
1
SQP1-AHMM-4-AE-DEL-LXX-A-201
1
SQP1-AHMM-4-AE-DEL-LXX-A-201 1
SQP1-AHMM-4-AE-DEL-LXX-A-201 1
SQP1-AHMM-4-AE-DEL-LXX-A-201
1
SQP1-AHMM-4-AE-DEL-LXX-A-203
1
SQP1-AHMM-4-AE-DEL-LXX-A-203 1
SQP1-AHMM-4-AE-DEL-LXX-A-203
Room Key
01 Entrance
02 Cycle Parking
03 Cycle Parking: Showers
1 1 04 Loading Bay
05 Plant Room
SQP1-AHMM-4-AE-DEL-LXX-A-200 06 Plant Room: External
SQP1-AHMM-4-AE-DEL-LXX-A-200
07 Lift Lobby
e
08 Fire Fighting Lobby abov
tline
09 Refuse Store ildi ng ou
t 3 bu
of Plo
10 Lift: Passenger tive line
Indica
11 Lift: Passenger/Firefighting
Figure 7.120 Fourth floor plan Figure 7.121 Fifth floor plan
DRAFT Figure 7.122 Sixth floor plan
DRAFT Figure 7.123 Seventh floor plan
DRAFT
12 Lift: Goods
13 Lift: Goods/Passenger
0 2 10 20 m 0 2 10 20 m 0 2 10 20 m 0 2 10 20 m
14 Lift: Cycle
15 Balcony/Terrace
Client job title Client job title Client job title 16 Brown Roof Client
NOTE NOTE NOTE NOTE
When this drawing is issued in uncontrolled CAD format it will be accompanied by a 18158_Millennium Mills & Plot 4
When this drawing is issued in uncontrolled CAD format it will be accompanied by a 18158_Millennium Mills & Plot 4
When this drawing is issued in uncontrolled CAD format it will be accompanied by a 18158_Millennium Mills & Plot 4
When this drawing is issued in uncontrolled CAD format it will be accompanied byArea
a Use Key
PDF version and is issued to enable the recipient to prepare their own documents / 2B PDF version and is issueddrawing
to enable the recipient to prepare their own documents / 2B PDF version and is issued to enable the recipient to prepare their own documents / 2B PDF version and is issued to enable the recipient to prepare their own documents / 2B
title / location drawing title / location drawing title / location Brand Use (excluding retail)
2A
2A
2A
2A
models / drawings for which they are solely responsible. 1 3 models / drawings for which they are solely responsible. 1 3 models / drawings for which they are solely responsible. 1 3 models / drawings for which they are solely responsible. 1 3
The recipient should report all drawing errors, omissions and discrepancies to the
architect. All dimensions should be checked on site by the contractor and such 4
Floor Plan - Fourth Floor
The recipient should report all drawing errors, omissions and discrepancies to the
architect. All dimensions should be checked on site by the contractor and such 4
Floor Plan - Fifth Floor
The recipient should report all drawing errors, omissions and discrepancies to the
architect. All dimensions should be checked on site by the contractor and such 4
Floor Plan - Sixth Floor
The recipient should report all drawing errors, omissions and discrepancies to the
architect. All dimensions should be checked on site by the contractor and such
Dedicated Brand A1 Retail
4
dimensions shall be the contractor’s responsibility. dimensions shall be the contractor’s responsibility. dimensions shall be the contractor’s responsibility. dimensions shall be the contractor’s responsibility. Dedicated A3-A5 Brand Food
20 Triton Street 20 Triton Street 20 Triton Street 20 Triton Street
Allford Hall Monaghan Morris Limited accepts no responsibility or liability for:- Regent's Place Allford Hall Monaghan Morris Limited accepts no responsibility or liability for:- Regent's Place Allford Hall Monaghan Morris Limited accepts no responsibility or liability for:- Regent's Place Allford Hall Monaghan Morris Limited accepts no responsibility or liability for:- Office B1 Regent's Place
- any use of this drawing by parties other than the party for whom it was prepared or 5 London NW1 3BF
- any use of this drawing by parties other than the party for whom it was prepared or 5 London NW1 3BF
- any use of this drawing by parties other than the party for whom it was prepared or 5 London NW1 3BF
- any use of this drawing by parties other than the party for whom it was prepared or Residential C3 5 London NW1 3BF
for purposes other than those for which it was prepared for purposes other than those
Purposefor which it was prepared
of drawing for purposes other than those forofwhich
Purpose drawing it was prepared for purposes other than those for
Purpose of which it was prepared
drawing
- any alterations or additions to or discrepancies arising out of changes to the - any alterations or additions to or discrepancies arising out of changes to the - any alterations or additions to or discrepancies arising out of changes to the - any alterations or additions to or discrepancies arising out of changes to the Food & Drink A3-A5
INFORMATION INFORMATION INFORMATION
Consultant Consultant Consultant Consultant
background information on which the drawings are based that was current at the 6 background information on which the drawings are based that was current at the 6 background information on which the drawings are based that was current at the 6 background information on which the drawings are based that was current at the 6
A3-A5
1
Table 7.5 Plot 4 area schedule Figure 7.124 Eighth floor plan SQP1-AHMM-4-AE-DEL-LXX-A-200
Figure 7.125 Basement floor plan
0 2 10 20 m
NOTE
0 2 10 20 m
Client
NOTE
job title
DRAFT Client
2A
2A
models / drawings for which they are solely responsible. 1 3 models / drawings for which they are solely responsible. 1 3
The recipient should report all drawing errors, omissions and discrepancies to the
architect. All dimensions should be checked on site by the contractor and such 4
Floor Plan - Eighth Floor
The recipient should report all drawing errors, omissions and discrepancies to the
architect. All dimensions should be checked on site by the contractor and such 4
dimensions shall be the contractor’s responsibility. dimensions shall be the contractor’s responsibility.
20 Triton Street 20 Triton Street
Allford Hall Monaghan Morris Limited accepts no responsibility or liability for:- Regent's Place Allford Hall Monaghan Morris Limited accepts no responsibility or liability for:- Regent's Place
- any use of this drawing by parties other than the party for whom it was prepared or 5 London NW1 3BF
- any use of this drawing by parties other than the party for whom it was prepared or 5 London NW1 3BF
for purposes other than those for which it was prepared for purposes other than those
Purpose for which it was prepared
of drawing
- any alterations or additions to or discrepancies arising out of changes to the - any alterations or additions to or discrepancies arising out of changes to the
INFORMATION
Consultant Consultant
background information on which the drawings are based that was current at the 6 background information on which the drawings are based that was current at the 6
time of issue, and which occur to that information after it has been issued by AHMM 8 time of issue, and which Drawn
occur to that information after it has been issued by AHMM 8
- any loss or degradation of the information held in this drawing resulting from the
7
ALLFORD HALL MONAGHAN MORRIS
- any loss or degradation of the information held in this drawing resulting from the
Checked 7Approved
ALLFORD HALL MONAGHA
translation from the original file format to any other file format or from the recipients
reading of it in any other programme or any version of the programme other than FD
translation from the original file format to any other file format or from the recipients
FG
reading of it in any other programme or any version of the programme other than
that which was used to prepare it ARCHITECTS Ltd that which was used to prepare
Date it Scale Size ARCHITECTS Ltd
Brand Use Views to Mills Square
LOBBY
BRAND USE AND
south or Mills Square to the northwest.
1
The Brand Use at ground floor is a showcase
and exhibition space for the tenants of the
brand space above, and sits alongside the A3-
A5 uses. 2
2 Office
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 253
7.3.2 DESIGN
PRINCIPLES N
Figure 7.130 Ground floor plan of Plot 4 in context to Plot 3 and Millennium Mills
0 5 10 25m
Public space to the south Activating to the south, west & north Core position and building shape Front door
10.5m
2B 2B
2A 3 2A 3
4 4
9m
N N N
The building opens up to the south with its In line with the OPP, large, flexible Brand The building is simple and rectangular in The primary entrance to the building is from
primary elevation and projecting balconies all space on ground floor activates the southern, shape. It is formed on a 9m x 10.5m frame the north via Mills Square. The entrance in this
facing this way. western and northern elevations. with the core located in the centre of location allows for a large, adaptable Brand
the northern facade of the building. This entrance lobby and showcase facade along
At ground and first floors, the facade is A visible entrance lobby and lift core on the maximises the depth of the floor plate to the west elevation, with A3-A5 Uses along the
recessed in line with the OPP, and create a north facade activates Mills Way. accommodate a range of Brand Uses. southern elevation.
purposeful and enjoyable south facing public
space.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 255
7.3.3 LAYOUT
N
Ground floor arrangement
The ground floor of the building is principally
made up of a series of active frontages with
views to the south and west. 8 4 4
3
1 Lobby and Brand Use 4
2 Lift Lobby
4 Plant room
5 Cycle facilities
6 Loading bay
7 Refuse store
8 FM facilities Figure 7.132 Ground floor plan
0 5 10 25m
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 257
Typical floor arrangement
N
With the core located along the northern
elevation of the building, the floorplates are
generous and flexible, offering the opportunity
for single tenants or multiple tenants per
4
floor.
5
1 Brand Use
2 Lift Lobby
3 Stairs
4 WCs
2
4
3 3 3 3 3
4 4 4 4 4
2 Level 08 terrace
4 Indicative PV zone
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 259
7.3.4 SCALE
Proposed massing 5
Plot 4 is a ground + 8 storey building with a
maximum height that is in-keeping with the KEY
6 4
PLOT 4: North East Isometric
surrounding context Figure 7.137 and complies
with the Parameter Plan.
2 The building steps in section to the east in line 02 24/05/2019 Draft Elevations and Typical Bays
CLIENT LENDLEASE
PLANNING CONSULTANT DP9
.9
PDF version and is issued to enable the recipient to prepare their own documents /
+39
models / drawings for which they are solely responsible.
The recipient should report all drawing errors, omissions and discrepancies to the
architect. All dimensions should be checked on site by the contractor and such
dimensions shall be the contractor’s responsibility.
3
- any loss or degradation of the information held in this drawing resulting from the
translation from the original file format to any other file format or from the recipients
reading of it in any other programme or any version of the programme other than
OD
that which was used to prepare it
mA
- the accuracy of survey information provided by others or for any costs, claims,
proceedings and expenses arising out of reliance on such information
- any scaling from this drawing other than by the local planning authority solely for
+4 4 LOCATION
N
2B
2A 3
1 Plot 4
4
2 Plot 3
ALLFORD HALL MONAGHAN MORRIS
ARCHITECTS Ltd
MORELANDS, 5-23 OLD STREET LONDON EC1V 9HL
TEL 020 7251 5261 FAX 020 7251 5123 WEB WWW.AHMM.CO.UK 3 Plots 2B and 3 - shared super core
1
job title
18158_Millennium Mills & Plot 4
4
drawing title / location
PLOT 4_Facade Full Building Isometrics
Plot 2B - roof extension
drawn by checked scale status
KP FG @A1 INFORMATION
ty
e ni 5 Plot 2A - roof extension
project zone classification drawing no. revision
ic Am 18158 4 (SK)_2105 02
P ub l
6 Plot 2A - missing tooth filled in
© Allford Hall Monaghan Morris Limited
7 Plot 2A - existing
1 2
+44.9m AOD
Long section 1 5 3
Cross section 2
1
Parameter Plan 07 Maximum building heights
1 Brand Use
4
2 Traditional A3-A5 Uses
3 Office Use
4 Balconies/Terrace 6 5 5 2 7
5 Plant
5
6 Mills Way
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 261
7.3.5 APPEARANCE Facade approach
To be in-keeping with the character of the
Inspired by form, material and existing buildings, Plot 4’s structure will be
existing details clearly expressed on its facade, articulating
the uses within.
Note: The architectural approach is the
same as Plot 3. Please refer to Section Bringing the concrete frame to the facade
7.2.5 Appearance on page 212 for further of the building celebrates the structure of
information. the proposal and allows it to perform many
functions;
Kit of parts for the architecture • Shade the internal floor plates
A set of details are used to create a rich,
playful tapestry of depth and light/shade from • Reduce the window-to-wall ratio, reduce
a common set of elements, while remaining cost and improve project viability
Projecting spandrels Solid tops for weight and rigidity
true to the industrial typology of the existing • Create depth
buildings.
• Provide architectural quality that is
Elements of the new build facades include: appropriate to the surrounding context and
• Spandrels for drips and shading place
Figure 7.140 Images of the architectural kit of parts Projections for amenity 5.25m and 9m grids
Stability system
In combination with the core to the north,
shear walls provide stability and are exposed North Elevation East Elevation
on the facade as simple concrete walls. The
core is expressed in concrete and punctuated
with glazing to the stairwells and lift lobbies
to create variety.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 263
Depth and light and shade
The depth of the expressed frame and
shading elements create light and shade that
adds richness and variety to each elevation.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 265
Concrete surface finishes
The proposal is for the visible external
concrete surface finish to be similar to the
new build elements of Millennium Mills.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 267
Elevations
The following pages show the elevations of
Plot 4 in the context of Millennium Mills and
Plot 3.
6
7 5
Plot 4
Figure 7.146 North elevation of Plot 4
4 Glazing to core 10 8
5 Entrance
6 Signage zone 10
7 Doors to plant and services
8 Shear wall
9 Terrace Level 08
Plot 4
10 Balconies Figure 7.147 South elevation of Plot 4 and the Millennium Mills in the background
10
3
7 7
Plot 4
Figure 7.148 East elevation of Plot 4 and Plot 3
2 8
10
Plot 4
Figure 7.149 West elevation of Plot 3 and Plot 4
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 269
North elevation
This more solid elevation is playfully
proportioned with clear, robust massing and
characterful elements such as shear walls
and entrance canopies that create delight.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 271
View looking east on Mills Way
Standing in Mills Square, Plot 4 can be seen
separated from Plot 3 by Mills Way. Trees and
landscaping create a pleasant street-scape.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 273
Typical detail for the east and
west elevations
The east and west façades of Plot 4 are set
out at 5.25m centres with two bays between
each grid line.
2 1
DRAFT
CONSULTANTS
1 ISO_Plot 4_Typical Bay_Type 1a 2 ISO_Plot 4_Typical Bay_Type 2a 3 ISO_Plot 4_Typical Bay_Type 2b 4 ISO_Plot 4_Typical Bay_Type 3a STRUCTURAL ENGINEER AKT ll
MECHANICAL ENGINEER HILSON MORAN
LANDSCAPE WEST 8
TRANSPORT & WASTE ARUP
FIRE & SUSTAINABILITY BURO HAPPOLD
APPROVED INSPECTOR BRCS
FACADE CONSULTANT MEINHARDT
2
models / drawings for which they are solely responsible.
Concrete lintel and upstand between columns The recipient should report all drawing errors, omissions and discrepancies to the
architect. All dimensions should be checked on site by the contractor and such
dimensions shall be the contractor’s responsibility.
4 Horizontal coloured metal fin - any loss or degradation of the information held in this drawing resulting from the
translation from the original file format to any other file format or from the recipients
reading of it in any other programme or any version of the programme other than
that which was used to prepare it
- the accuracy of survey information provided by others or for any costs, claims,
LOCATION
N
2B
4
Typical detail for the north and
south elevations
The north and south façades of Plot 4 are set
out at 9m centres. The facade consists of a 6
chamfered concrete lintel and upstand, which
is supported between the external columns.
3
4
Extended pressed coloured metal cill
CLIENT LENDLEASE
NOTE
When this drawing is issued in uncontrolled CAD format it will be accompanied by a
PDF version and is issued to enable the recipient to prepare their own documents /
models / drawings for which they are solely responsible.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement The recipient should report all drawing errors, omissions and discrepancies to the
architect. All dimensions should be checked on site by the contractor and such 275
dimensions shall be the contractor’s responsibility.
Room Key
01 Entrance
02 Cycle Parking
03 Cycle Parking: Showers
04 Loading Bay
05 Plant Room
06 Plant Room: External
14 Lift: Cycle
15 Balcony/Terrace
16 Brown Roof
Office B1
Residential C3
Food & Drink A3-A5
Local A1 Retail
Boundaries
Outline Planning
Permission Boundary
Figure 7.161 Indicative entrance signage scoping plan Figure 7.159 View of entrance signage from east of Plot 4 Figure 7.160 View of entrance signage from west of Plot 4
276
NOTE
Client job title
DRAFT Mills Quarter | 7.0
When this drawing is issued in uncontrolled CAD format it will be accompanied by a 18158_Millennium Mills & Plot 4
PDF version and is issued to enable the recipient to prepare their own documents / 2B drawing title / location
2A
01 Entrance
02 Cycle Parking
03 Cycle Parking: Showers
bay CONSULTANTS
CLIENT LENDLEASE
04 Loading Bay
05 Plant Room
06 Plant Room: External
PLANNING CONSULTANT
COST CONSULTANT
Figure 7.166 View of retail/other signage
DP9
ARCADIS
07 Lift Lobby
08 Fire Fighting Lobby
1
10 Lift: Passenger
3 Pending tenant use and ground floor activation, a Dedicated Brand A1 Retail
Dedicated A3-A5 Brand Food
models / drawings for which they are solely responsible. Local A1 Retail
The recipient should report all drawing errors, omissions and discrepancies to the Local A2-A5 Retail
architect. All dimensions should be checked on site by the contractor and such Community & Education D1
dimensions shall be the contractor’s responsibility.
Outline Planning
Permission Boundary
for purposes other than those for which it was prepared
- any alterations or additions to or discrepancies arising out of changes to the
background information on which the drawings are based that was current at the
time of issue, and which occur to that information after it has been issued by AHMM
- any loss or degradation of the information held in this drawing resulting from the
translation from the original file format to any other file format or from the recipients
2
reading of it in any other programme or any version of the programme other than
that which was used to prepare it
- the accuracy of survey information provided by others or for any costs, claims,
proceedings and expenses arising out of reliance on such information
- any scaling from this drawing other than by the local planning authority solely for
the purposes of the planning application to which it relates
LOCATION
N
1
2B
2A 3
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement
NOTE
Client job title
DRAFT 277
When this drawing is issued in uncontrolled CAD format it will be accompanied by a 18158_Millennium Mills & Plot 4
PDF version and is issued to enable the recipient to prepare their own documents / 2B drawing title / location
2A
1 Up-lighting to columns
1
2 Up-lighting to L02 soffit and balconies
2A
1
5 Cycle end of journey facilities models / drawings for which they are solely responsible.
The recipient should report all drawing errors, omissions and discrepancies to the
Cycle lockers
3
architect. All dimensions should be checked on site by the contractor and such 4
dimensions shall be the contractor’s responsibility.
6 Lifts to brand and office floors Showers & changing
Allford Hall Monaghan Morris Limited accepts no responsibility or liability for:-
- any use of this drawing by parties other than the party for whom it was prepared or 5
for purposes other than those for which it was prepared
- any alterations or additions to or discrepancies arising out of changes to the
background information on which the drawings are based that was current at the 6
time of issue, and which occur to that information after it has been issued by AHMM 8
7
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement - any loss or degradation of the information held in this drawing resulting from the
translation from the original file format to any other file format or from the recipients
279
reading of it in any other programme or any version of the programme other than
that which was used to prepare it
- the accuracy of survey information provided by others or for any costs, claims,
proceedings and expenses arising out of reliance on such information
Vertical circulation These facilities will be designed in accordance
with the recommendations in Approved N
Upper floor office accommodation is
Document M and BS8300.
accessed from the lift and stair core and
provides for a flat floorplate at all upper
Egress and fire strategy
levels. This should provide scope to ensure
access and circulation routes can meet It is noted that the Egress Strategy will adopt
Approved Document M Vol 2 and BS 8300 BS9999:2017 principles and are covered by
2018 Vol 2 requirements. the separate Fire Consultant report by Buro
Happold. Details will be developed during
Staircase provision - This is being developed the project and this should include specific
to meet the requirements of Approved provisions for disabled people.
Document K and M of the Building Regulations
and BS 8300 Vol 2.
Vol 2.
Client
NOTE
Accessible shower and changing facilities are When this drawing is issued in uncontrolled CAD format it will be accompanied by a
PDF version and is issued to enable the recipient to prepare their own documents / 2B
2A
models / drawings for which they are solely responsible. 1 3
also provided at ground floor level adjacent to The recipient should report all drawing errors, omissions and discrepancies to the
architect. All dimensions should be checked on site by the contractor and such
dimensions shall be the contractor’s responsibility.
4
- any use of this drawing by parties other than the party for whom it was prepared or 5 London NW1 3BF
Checked
Accessible WC
0 2 10 20 m
Servicing strategy
N
Refuse strategy
Delivery strategy
LOADING BAY
0 5 10 25m
Figure 7.171 Ground floor plan highlighting refuse and delivery routes
0 2 10 20 m Goods lift
Refuse store
NOTE
Loading bay When this drawing is issued in uncontrolled CAD format it will be accompanied by a
PDF version and is issued to enable the recipient to prepare their own documents / 2B
2A
models / drawings for which they are solely responsible. 1 3
Refuse route The recipient should report all drawing errors, omissions and discrepancies to the
architect. All dimensions should be checked on site by the contractor and such 4
dimensions shall be the contractor’s responsibility.
Deliveries route Allford Hall Monaghan Morris Limited accepts no responsibility or liability for:-
- any use of this drawing by parties other than the party for whom it was prepared or 5
for purposes other than those for which it was prepared
- any alterations or additions to or discrepancies arising out of changes to the
background information on which the drawings are based that was current at the 6
time of issue, and which occur to that information after it has been issued by AHMM 8
7
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement - any loss or degradation of the information held in this drawing resulting from the
translation from the original file format to any other file format or from the recipients
281
reading of it in any other programme or any version of the programme other than
that which was used to prepare it
- the accuracy of survey information provided by others or for any costs, claims,
proceedings and expenses arising out of reliance on such information
7.4 PLOT 1
7.4.1 INTRODUCTION
Proposed scheme
Plot 1 is a mixed-use development of
residential apartments up to 13 storeys, with
Local A1 Retail and A3-A5 Food and Beverage
ground floor uses.
Land use
Plot 1 GEA (sqm.)
147 x 1 bed
Mix
118 x 2 bed
Affordable Homes 8
N
Table 7.7 Plot 1 unit numbers Figure 7.172 Illustration of Plot 1
Plot 1
1. Prioritise the pedestrian experience of 2. Respond to the Millennium Mills building form 3. Address the Rayleigh Road/Wesley Avenue
Silvertown Place Circus
COMPLETING THE CIRCUS PERCEIVED VALUE
KEY CORNER MILLENNIUM MILLS SILHOUETTE ROOF TOP VALUE
1954
1933
SPILLERS
4. Key corner form when viewing Plot 1 from 5. Capitalise on the opportunity for views 6. Provide rooftop amenity and communal uses
primary masterplan route
RDENS PUBLIC SPACE 1ST FLOORCOURTYARD
VALUE GARDENS PUBLICCOURTYARD
SPACE GARDENS 1ST FLOOR VALUE PUBLIC SPACE 1ST FLOOR VALU
7. Lower level experience of the waterscape 8. Orientation of the courtyard as a sun trap
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 283
7.4.3 LAYOUT
Ground floor arrangement
The ground floor of the development includes
Local A1 Retail and A3-A5 Food and beverage
tenancies located along the north and east
frontages, and within the southwest corner
facing Rayleigh Road Circus. It is proposed
that a restaurant will occupy the northeast
corner unit and a café to the southeast.
Flexible retail uses are proposed for the other
units. The northern retail units are afforded a
pedestrian service entrance off Rayleigh Road,
limiting the need for servicing from the dock
promenade or from Silvertown Place.
Key: Entrances:
A3-A5 Food and
Beverage Primary communal
residential
Local A1 Retail
Secondary
Lobby, Shared Space communal residential
C
O
N
C
C
O
I
N
E
C
R
C I
G
O E
E
N R
C G
I E
E
R
G
E
C
O
N
C
C I
O E
N R
C G
E C
I O
E N
R C
G I
E E
R
G
E
01
01
01
Arrival at Silvertown Place Principal Lobby Landscaped light-well Landscaped courtyard Residential cores Apartment entrance
Figure 7.174 Residents journey throughout the building
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 285
01
01
01
Typical upper floors
The upper levels of the development are
arranged around the residents’ communal
courtyard at the first floor. The arrangement
of the buildings has been informed by
maximising the potential views of all homes
towards the docks and other key landmarks.
At the upper levels, the buildings reads as Figure 7.176 First floor plan Figure 7.177 Eleventh floor plan
three distinct elements: Blocks A, B and C.
The space formed between Blocks B and C is
8 storeys.
Key:
1 bed
2 bed
Projecting balcony
Private terrace
0 10 20 50 m N
Block C
Residents
Roof Terrace
Key:
Green roof
Roof terrace
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 287
Typical dwelling layouts
Plot 1 is comprised of one and two bedroom
apartments. The homes have been arranged
with larger units located at the corner of the Bedroom 1
Living/Kitchen/Dining
Bedroom 2
in accordance with OPP parameters and Living/Kitchen/Dining Utility
Bedroom 1
CLIENT:
THE ORIGINAL HARDCOPY OF THIS DRAWING HAS BEEN EXECUTED TO SCALE AND IS
BASED ON AVAILABLE SURVEY INFORMATION.
Bedroom 1
NOTES: Living/Kitchen/Dining
Living
Bedroom 1 Living/Kitchen/Dining
Storage
Storage
Living/Kitchen/Dining
Utility
Bedroom 2
Living/Kitchen/Dining Living/Kitchen/Dining Utility
Utility Living/Kitchen/Dining
Utility
Bedroom 2
Bedroom 2
Bedroom 2
Utility
Utility Storage
Bedroom 1
2 Level 02_WAD_1B2P_2
2 Level 02_WAD_1B2P_2
1Bedroom
: 150 1 Floor Plans
1 : 150 Floor Plans Bedroom 1
Bedroom 1
Bedroom 2
8
82
90
Bedroom 2
_1
8
82
IP
90
W
_1
IP
W
Living/Kitchen/Dining
Utility
REV DESCRIPTION DR CHK QA DATE
KEY
y
Bedroom 1
KEY
PROJECT
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement SILVERTOWN PLOT 1
PROJECT STATUS
289
SCALE SIZE
en
Av
sl ey
We
The first floor apartments to all buildings and Figure 7.187 North / south section AA
to the top floors of Blocks A, B and C have a
taller ceiling level, intended to improve the
natural daylight to these apartments and
increase the views towards the dock and Max +49.9m AOD
waterscape.
Key:
1 bed A3-A5 Retail
2 bed A1 Retail
A
Figure 7.186 Section location plan Lobby, Shared Space
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 291
Typical upper floors
The upper levels of the development are
arranged around the residents’ communal
courtyard at the first floor. The arrangement
of the buildings has been informed by
maximising the potential views of all homes
towards the docks and other key landmarks.
At the upper levels, the buildings reads as Figure 7.176 First floor plan Figure 7.177 Eleventh floor plan
three distinct elements: Blocks A, B and C.
The space formed between Blocks B and C is
8 storeys.
Key:
1 bed
2 bed
Projecting balcony
Private terrace
0 10 20 50 m N
Block C
Residents
Roof Terrace
Key:
Green roof
Roof terrace
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 287
Typical dwelling layouts
Plot 1 is comprised of one and two bedroom
apartments. The homes have been arranged
with larger units located at the corner of the Bedroom 1
Living/Kitchen/Dining
Bedroom 2
in accordance with OPP parameters and Living/Kitchen/Dining Utility
Bedroom 1
CLIENT:
THE ORIGINAL HARDCOPY OF THIS DRAWING HAS BEEN EXECUTED TO SCALE AND IS
BASED ON AVAILABLE SURVEY INFORMATION.
Bedroom 1
NOTES: Living/Kitchen/Dining
Living
Bedroom 1 Living/Kitchen/Dining
Storage
Storage
Living/Kitchen/Dining
Utility
Bedroom 2
Living/Kitchen/Dining Living/Kitchen/Dining Utility
Utility Living/Kitchen/Dining
Utility
Bedroom 2
Bedroom 2
Bedroom 2
Utility
Utility Storage
Bedroom 1
2 Level 02_WAD_1B2P_2
2 Level 02_WAD_1B2P_2
1Bedroom
: 150 1 Floor Plans
1 : 150 Floor Plans Bedroom 1
Bedroom 1
Bedroom 2
8
82
90
Bedroom 2
_1
8
82
IP
90
W
_1
IP
W
Living/Kitchen/Dining
Utility
REV DESCRIPTION DR CHK QA DATE
KEY
y
Bedroom 1
KEY
PROJECT
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement SILVERTOWN PLOT 1
PROJECT STATUS
289
SCALE SIZE
en
Av
sl ey
We
The first floor apartments to all buildings and Figure 7.187 North / south section AA
to the top floors of Blocks A, B and C have a
taller ceiling level, intended to improve the
natural daylight to these apartments and
increase the views towards the dock and Max +49.9m AOD
waterscape.
Key:
1 bed A3-A5 Retail
2 bed A1 Retail
A
Figure 7.186 Section location plan Lobby, Shared Space
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 291
7.4.5 APPEARANCE
Appearance and façade treatment
The external appearance of the Plot 1
has been developed with reference to
the post-industrial history of the Site and
with reference to the distinctive adjacent
Millennium Mills.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 293
Materiality ROOF TERRACE
Figure 7.193 Materiality axo Figure 7.198 Precedent 325 Kent by Figure 7.199 Precedent Central
Shop Architects Cross by Buckley Gray Yeoman
3
4
Vertical textured concrete
or GRC
3
4 1
1 5
4
6
Figure 7.201 Section Figure 7.202 Building B bay elevation Figure 7.203 Building B bay axonometric
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 295
Building D bay study 1
Building D is an extension of the ground
floor plinth treatment. The main bulk of the
building is refined to included faceted metal
cladding to provide texture and depth to the
façade.
Mid-tone metal panel
facade cladding -multiple
tones 1
2
3
1 3
Figure 7.204 Bay location plan Figure 7.205 Section Figure 7.206 Building D bay elevation 0 2 5 10 m
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 297
Illustrative views
Figure 7.211 shows Plot 1 as proposed from
Rayleigh Road Circus looking west.
Figure 7.210 Illustrative view location plan Figure 7.211 View of Plot 1 from Rayleigh Road Circus
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 299
7.4.6 LANDSCAPE
Podium garden
Plot 1 will include a podium level shared
garden, accessible to all blocks with private
amenity space adjacent to all first floor
dwellings.
Viewing deck
Grow gardens Glade Viewing deck
Slide Copse
Figure 7.218 Section A
Private
amenity
space
Glade
Planted
buffer
Shared
amenity
space
Sand
play
B B
Glade C
Copse
Figure 7.219 Section B - typical section through defensible space
Water play
Lightwell
Copse C
Copse
Grow gardens
1:500
Figure 7.217 Podium landscape layout
A Figure 7.220 Section C - lightwell access from concierge to podium
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 301
Materials
Routes through the garden will comprise
small unit clay pavers. Private amenity spaces
will have a distinct patterned concrete finish,
to complement the building facade and
indicate areas within private demise. Places to
sit will be provided informally on lawns and
dedicated hardwood benches will be located
facing into the central space to prevent
overlooking into private amenity spaces.
Figure 7.223 FSC Figure 7.222 Insect hotel Figure 7.224 Illustrative view of podium landscape
hardwood timber bench
The podium will be a playful landscape with Allowance has been made in the podium
water and sand play integrated at the edges build up for soil depths to support a verdant
of the central lawn. The north lawn will soft landscape. Tree planting will include
include playful undulating topography and a large multi-stems, fruiting species and dense
slide will form the edge of the lawn along the copse planting to provide screening to the
level change. surrounding residential units.
Figure 7.226 Myrtus Figure 7.229 Jasminum Figure 7.231 Alium Figure 7.233 Stipa gigantea
The under-story planting mix will include
a rich variety of shrub, perennial and grass
species including fruiting shrubs to meet the
requirement for fruiting plant species as set
out in the OPP.
Figure 7.225 Slide Figure 7.227 Water pump Figure 7.228 Cercis Figure 7.230 Ribes rubrum Figure 7.232 Achillea Figure 7.234 Anemanthele
Biodiverse
green roof Residents’
roof terrace
Figure 7.236 Plot 1 roofscape layout A Figure 7.239 Raised planted beds
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 303
7.4.7 ACCESSIBILITY Car parking
Vehicular access to the Plot 1 on-plot car park
AND INCLUSIVE DESIGN at ground floor level is provided directly from
Wesley Avenue.
Introduction
The scheme is set around the central Centrally, the residents’ car park provides 26
landscaped courtyard that provides a link parking spaces, making up 9% of residential
between the residential cores. The principal units. Of this provision, 3% will be provided as
lobby and concierge are located facing wheelchair accessible spaces (9 No.).
Silvertown Place, providing a key address
for Plot 1 and activating the main pedestrian Accessible housing provisions
thoroughfare into the masterplan. The four residential buildings comprise a
communal circulation core of stair and lifts.
Plot 1 provisions have been designed in line
with ADM Vol. 1 for the residential elements Each core is accessible from the ground floor,
and Vol. 2 for the communal use, courtyard either by a dedicated entrance lobby (Blocks A
and retail elements. and D) or the shared principal lobby (located
between and connecting Blocks B and C).
Please also refer to Section 4.5.12 of this DAS Residents’ cycle storage and refuse collection
for a detailed commentary of the access and is also located off this.
inclusive design strategy for the Phase 1 RMA.
All residential cores have direct access to the
Pedestrian access raised courtyard garden located at first floor
Pedestrian access to residential lobby areas level, while the principal lobby will also be
on the ground floor are located on the connected to this via an external stair.
western, eastern and southern sides of Plot 1.
All homes are designed to exceed the
Pedestrian access to the retail units at the nationally described space standard (NDSS),
northern edge of Plot 1 is provided directly and will have private amenity space accessed
from Dock Waterfront and Silvertown Place. directly from the living room, as either a
Direct access to retail units to the south is balcony or podium terrace.
provided off Wesley Avenue and Silvertown
Avenue. M4(3) Category 3: Wheelchair user dwellings
will be provided contributing to the overall
Phase 1 RMA total of 10%, while the remainder
will meet the M4(2) Category 2: Accessible
and adaptable dwellings standard.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 305
8.0
Silo D Quarter
8.1 INTRODUCTION TO SILO D QUARTER
Silo D Quarter is a predominantly residential
neighbourhood set around Silo D and Silo D
Park. For more detail refer to Section 4.1.8
Character areas on page 40.
Mill Road
Plot 6
Woolwich Road, as well as serving as a Plot 8
backdrop to Silo D.
Architects: Pollard Thomas Edwards
Plot 7
d
ic h Roa
Woolw
Nor t h
SILO D PLOT 8
SILVERTOWN
STREET
PLOT 7
M
ill
Ro
ad
PLOT 6
Gateway to
the Site
ad
Ro
h
Massing steps ic
w
down to context
o ol
W
r th
No
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 309
8.2 PLOT 5
8.2.1 INTRODUCTION
Proposed scheme
Plot 5 sits within the context of Silo D Park on
the south-west side of the Site adjacent to
the existing homes along Mill Road.
Number of units 36
8 x 3 bed maisonettes
6 x 3 bed flats
Mix
10 x 2 bed flats
12 x 1 bed flats
Dual aspect 36
Affordable homes 36 N
• Appropriate response to existing and Providing gallery access that wraps around
future context two sides of the garden space, all homes PM PM AM AM
ROUTES ROUTES GREEN SPACE / GARDENS GREEN SPACE / GARDENS
can enjoy dual aspects. This access gallery Address the corner and Developed around east and west
1 2
• Address junction of Evelyn Walk and features front doors and additional amenity street frontage orientation and day-lit amenity
Silvertown Street pockets overlooking the garden space, MILLENIUM MILLS MILLENIUM MILLS
• Provide an appropriate relationship with environment. The end of the galleries become
Plot 6 generous private amenity for the 3 bed flats.
MILLENIUM MILLS MILLENIUM MILLS
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 311
8.2.3 SITE LAYOUT
Ground and first floor
arrangement
On the ground floor are entrances to the eight
family maisonettes, each with their own front
door accessed from either Silvertown Street
or Evelyn Walk. At this level the kitchen dining
rooms face onto the street and living rooms
to the garden. The living rooms lead into small
private amenity which then links to the larger
sunny shared garden.
Primary communal
residential Private residential
Figure 8.9 Journey home diagram Figure 8.8 View through entrance to garden
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 313
Typical upper floor arrangements
The second, third and fourth floors have a 0 5 10 25m N
variety of dual aspect homes all accessed
off the generous gallery which overlooks the
shared garden.
Roof level
At roof level there is a green roof, accessed
for maintenance purposes only.
Lobby, Shared
space
Core, Circulation
Projecting balcony
Private terrace
Figure 8.10 Second - Fourth Floor Plan Figure 8.11 Fifth Floor Plan Figure 8.12 Roof Plan
Residential approach
3 BED HOMES
TYPE
TYPE
5.1 Decking
5.1 Decking
Flat_Dual
Flat_Dual
Aspect_50.9
Aspect_50.9
m2 m2 TYPE
TYPE
5.2_Dual
5.2_Dual
Aspect_63.5
Aspect_63.5
m2 m2
quality dwellings that are both functional and
3 BED HOMES
PRODUCT
PRODUCTBOOK:
BOOK:
N/A N/A PRODUCT
PRODUCTBOOK:
BOOK:
N/A N/A
enjoyable.
2 BED HOMES
1 BED HOMES
LIVING
LIVING
/ KITCHEN
/ KITCHEN
/ DINING
/ DINING LIVING
LIVING
/ KITCHEN
/ KITCHEN
/ DINING
/ DINING LI
views.
CIRCULATION
CIRCULATION CIRCULATION
CIRCULATION C
3 BED HOMES
2 BED HOMES
CIRCULATION CIRCULATION
• Dual aspect living rooms to capitalise upon
CIRCULATION CIRCULATION
views
• Large format windows to optimise daylight
and views
Gallery
Figure 8.15 Typical 2 bed home Figure 8.16 Typical 3 bed maisonette
E 5.1 Decking Flat_Dual Aspect_50.9 m2 TYPE 5.2_Dual Aspect_63.5 m2 TYPE 5.3 Decking Flat_Dual Aspect_104.8 m2
ODUCT BOOK: N/A Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement
PRODUCT BOOK: N/A PRODUCT BOOK: N/A 315
LIVING / KITCHEN / DINING LIVING / KITCHEN / DINING
E
LIVING
LIVING
/ KITCHEN
/ KITCHEN
/ DINING
/ DINING
TYPE
TYPE
5.4_Dual
5.4_Dual
Aspect_101.8
Aspect_101.8
m2 m2
PRODUCT
PRODUCTBOOK:
BOOK:
N/A N/A
8.2.5 SCALE
Scale and massing
The Design Code highlights Development Zone
2 as a ‘buffer to the surrounding area beyond’
and will act as an ‘intermediate scale’ in order
to reduce the impact on the existing Britannia
Village development. Britannia Village ranges
in size from low-rise terraces to mid-rise
apartment blocks.
2B
DZ2_5_MAX PARAMETER
HEIGHT
DZ2_5_MAX PARAMETER
Sections
HEIGHT
5-Level 05
5-Level 05
1 2A
As illustrated on the site sections there is a 5-Level 04 5-Level 05
3
5-Level 04
5-Level 03
5-Level 02 5-Level 03
5-Level 01
5-Level 00
5-Level 00
An attractive planted boundary treatment 5-Level 00
5-Level 05
5-Level 04
away from the face of the existing flats on
5-Level 03 5-Level 04
5-Level 01 5-Level 02
The generous gallery that lines the western 5-Level 01
5
5-Level 00
5-Level 00
5-Level 05 5_Roof
5-Level 05
5-Level 04 5-Level 05
5-Level 04
Lobby, Shared Space 1 Bed
5-Level 03 5-Level 04
5-Level 03
6
5-Level 01
5-Level 00
5-Level 01
Other
5-Level 00
8
5-Level 00
Figure 8.20 Section C - east / west
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement
7 317
8.2.6 APPEARANCE
Appearance and facade treatment
Figure 8.21 illustrates the approach to facade
treatment, hierarchy and materiality.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 319
Materiality
A very light textured brick and mortar is 2
proposed for Plot 5 that will complement the
brick choices for Plot 6.
4 Red metalwork
3
4
Plot 6 Plot 5
Figure 8.27 Detail of Silvertown Street elevation Figure 8.28 Corner of Silvertown Street & Evelyn Way
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 321
DRP
OPTION 01 OPTION 02 OPTION 03 OPTION 04
MATERIALITY
1
references the top of the Millennium Mills.
2A 4
4
brickwork through to the inside.
1
Both the corner entrance, and the paired front
doors to the maisonettes, are proposed as a Brick texture 4
3
deep red colour referencing red detailing in parapet
the Millennium Mills building. Balconies are
designed with a simple white balustrade and
soffits. 2
4
4
4 Metal window
system with
pressed metal cill 2
5 Metalwork
Figure 8.29 Materials Figure 8.30 Section Figure 8.31 Elevation Figure 8.32 Detail axonometric callout
2B
in the deep red colour used on the street 3
facade.
1 2A
1 1
The deck contains a planter edge detail 4
that aids privacy and allows personalisation
outside each front door. 3 5
2 Brick texture
The same light textured brick and mortar is parapet
proposed for all of Plot 5 5
3
4
3 Smooth concrete 4
or similar
1
3
4
4
4 Metal window 1
system with
pressed metal cill 3
5 1 4
5 Metalwork
Figure 8.33 Materials Figure 8.34 Section Figure 8.35 Elevation Figure 8.36 Detail axonometric callout
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 323
Figure 8.37 View down Silvertown Street
Garden layout
Plot 5 has a ground level ‘back garden’
character and can accommodate large
trees and verdant planting. Tree planting PLOT 5
is beneficial to the west facade to provide
privacy to the neighbouring properties on Mill
Road to the west and to mitigate the effects
of thermal gain.
STREET
GLA policy guidance and the level change
provides an opportunity for playful elements
such as slides and climbing walls.
SILVERTOWN
ROAD
Gathering space
Private amenity space
Tree
Yard
Neighbouring property
Planted edges Figure 8.41 Play integrated into soft landscape
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 325
Defensible
space
Pedestrian
space
SUDS
zone
Carriageway
Entrance court
Copse
Planted buffer
Shared amenity
space
Private amenity space
Copse
Toddler swing
Private amenity
space
B B A A
Copse
Copse Seesaw
Copse Water
1:250 catchpool
Figure 8.48 Patterned Figure 8.49 Water Figure 8.50 Illustrative view of Plot 5 garden
concrete catchpool
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 327
8.2.8 ACCESSIBILITY Car parking
On street parking is provided outside the
AND INCLUSIVE DESIGN family homes. One wheelchair accessible
space is provided on street in the public realm
Introduction for Plot 5.
Plot 5 sits within the context of Silo D Park
on the southwest side of the Site adjacent to Accessible housing provisions
the existing homes along Mill Road, and within All homes in Plot 5 are designed in line with
Development Zone 2. Approved Document M 4(2).
Plot 5 provides 36 affordable homes and ADM4(3) units are not provided in Plot 5 due to
associated cycle and refuse stores together the plot specific flood constraint of bedrooms
with a shared amenity space. not being allowed on the ground floor of the
eight maisonettes.
The plot provisions have been designed in line
with ADM Vol 1 for the residential elements Additionally, the provision of two passenger
and Vol 2 for the communal access use and lifts for so few units would have made the
courtyard elements. service charges very high. The Plot 5 garden
area is also steeply sloping because of the
Please also refer to Section 4.5.12 of this DAS relationship with existing levels.
for a detailed commentary of the access and
inclusive design strategy for the Phase 1 RMA. Therefore affordable wheelchair homes would
be better located in Block D on Plot 8 where
Pedestrian Access a core with two lifts serves a larger number
There is no vehicle access (for car parking or of homes and there is direct level access to a
servicing) provided on-plot for Plot 5, with central shared podium garden.
these activities to be accommodated on-
street. In addition wheelchair accessible parking can
be provided at the lower ground floor.
Residential units located on the ground floor
of Plot 5 will have direct access from the
street - either Silvertown Street (to the east)
or Evelyn Road (to the north).
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 329
8.3 PLOT 6
8.3.1 INTRODUCTION
Proposed scheme
The building is the first block on the
masterplan when approaching from the west.
It meets North Woolwich Road and Silvertown
Street to the east. The facade design of its
two main frontages respond to these two
different conditions with a more detailed
treatment to North Woolwich Road and a
calmer frontage to Silvertown Street.
Land use
Plot 6 GEA (sq.m.)
Food and Beverage
795
(A3-A5)
61 x 1 bed flats
Mix
45 x 2 bed flats
Dual aspect 52
N
Affordable homes 45
1. Clearly define North Woolwich Road 2. Contribute to a terrace of residential 3. Create a landscape buffer between new
buildings and existing homes
4. Create a clear relationship with Silo D and 5. Step height down from Plot 7 to the terraced 6. Maximise the potential for expansive views
the water houses of Mill Road
Figure 8.63 Design principles of Plot 6
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 331
8.3.3 LAYOUT
Combined ground floor
The plan opposite amalgamates the lower
ground (level 0) and upper ground (level 1)
plans to better depict how the building meets
the sloping ground plane.
N
01 5 0 25 m
Other
Figure 8.64 Combined ground floor plan showing uses that meet the street
Figure 8.65 Axonometric showing combined ground floor with all uses that meet Figure 8.66 Illustrative view of entrance lobby
the street with proposed street levels
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 333
Lower ground floor arrangement
The lower ground floor is at the same level as
North Woolwich Road. On the southern end of
the building a retail unit brings activity to the
main road and the ‘feature’ brick garden wall
defines the boundary of the garden marking
the beginning of the new neighbourhood.
The community space is placed at the point of
levels changing to maximise the opportunity
for a double height space. Two residential
cores are accessed at this level, each with
bicycle and refuse storage, independent
vertical circulation to residential levels and
providing direct access to the garden.
Other
N
01 5 0 25 m
1 Bed
2 Bed
Projecting balcony
N
01 5 0 25 m
Dual aspect
Figure 8.68 Upper ground floor plan
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 335
Typical level arrangement
The organisation of homes on the residential
levels maximises opportunity for dual aspect
homes, with larger units located on the
corners but also dual aspect one bedroom
through flats in the gaps between cores.
1 Bed
2 Bed
Projecting balcony
N
Dual aspect 01 5 0 25 m
N
01 5 0 25 m
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 337
Typical dwelling layouts
Residential approach
0 1 2.5m Figure 8.72 Typical one bed dual aspect unit layout Figure 8.74 Typical two bed unit layout
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 339
8.3.4 SCALE
Scale and massing
The scale of the building mediates between
the existing two storey Victorian homes
(around +12.0m AOD) to the west and the 14
storey (+49.9m AOD) maximum datum for
the OPP along North Woolwich Road which
is set by City Airport’s aerodrome navigation
requirements.
Through retail unit Figure 8.79 Section A - through communal garden and entrance lobby
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 341
8.3.5 APPEARANCE
Appearance and facade treatment
Plot 6 is intended to be a considerate and
contextual piece of city. It has a role to play in
marking the arrival at a new place but it is a
building which mediates between the adjacent
existing and emerging conditions.
01 5 0 25 m
Figure 8.89 South elevation to North Woolwich Road Figure 8.90 North elevation to Plot 5
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 343
Materiality and language
Aspects: The building has three distinct
façade types: the ‘front’ addresses Silvertown
Street, the ‘gable’ presents to North Woolwich
Road; the ‘back’ looks towards the garden and
Mill Road.
0 1 3m
Figure 8.93 2 South Elevation to the North Woolwich Road Figure 8.94 3 West Elevation to garden
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 345
Detail study - base
The base is defined by varied olive grey
brick, laid in fluted panels to separate each
premises and define the building’s base. They
frame generous residential entrances and well
proportioned retail shopfronts. A textured
spandrel panel defines the openings and 1
compliments the primary buff brick. 1
Figure 8.95 Stock brick
4 2
5 6
Figure 8.99 5 Recon stone or feature brick Figure 8.100 Axonometric of base meeting
middle section where North Woolwich Road
6 Recon stone or pressed metal cill meets Silvertown Street
6 4
Figure 8.101 Axonometric of top meeting middle section Figure 8.102 Material quality precedents, clockwise
from top: Maccreanor Lavington, 3144, DSDHA
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 347
Illustrative views
Views have been identified capture Plot 6’s
relationship with its historic context and the
emerging neighbourhood. These are shown on
the following pages.
Figure 8.103 View locations Figure 8.104 View 1 - Looking east along North Woolwich Road
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 349
8.3.6 LANDSCAPE
Garden layout
The level change from the proposed Plot
6 building line to the boundary of the Mill
Road properties is quite significant in places,
especially towards the north where there
is ~1:3 gradient. This will be used as an
opportunity for placemaking and play. To the
north the steepest level change is utilised to
form an amphitheatre and small bouldering
wall for children.
Figure 8.107 Gathering spaces within the soft
landscape
Resident access to Plot 6 is via three cores
distributed evenly along the building. Much of
the rear facade is likely to be inactive frontage
ROAD
Grow garden
Due to its narrow plan form and extent of Figure 8.108 Tree planting in grass terraces
level change across its width, the approach Movement route
is to create a singular path that navigates
between levels. Along its length, spaces will Block core
open out into ‘niches’ each with different
Trees/shrubs
character and programme. The path ties in
with each of the 3 core entrances.
Fruiting species
Amphitheatre
Copse
Water
catchpool
Terraced apple
Seating niche orchard
Garden path
B B
Seating niche
Figure 8.112 Section A
Walled fruit
garden
Copse
A Copse A
Grow garden
Sunken glade
1:250 1
Figure 8.110 Plot 6 plan (north) Figure 8.111 Plot 6 plan (south) Figure 8.113 Section B
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 351
Materials
Much of the garden will be a richly planted
soft landscape with a garden path to provide
access through the sloping site. The route
through the garden will comprise a clay paver
and resin bound gravel path.
Figure 8.116 Drainage Figure 8.117 Water Figure 8.128 Illustrative view of Plot 6
channel catchpool
Seating niches with timber benches will Long-lived tree species will be planted along
be located along the garden path providing the western boundary, providing screening. A
small gathering spaces. At the south of the weeping beech tree will add character to the
garden, raised planters will allow residents an grow garden area at the south of the garden.
opportunity for growing fruit and vegetables. Along the path, the garden will be densely
planted with understory shrubs, perennials
and ground cover species. Figure 8.120 Espalier Figure 8.122 Rubus Figure 8.124 Knautia Figure 8.126 Stipa
malus phoenicolasius macedonia arundinacea
The stepped terraces will be planted with an
apple orchard and further espalier fruiting
trees will be trained on the walls surrounding
the grow garden area ensuring the garden
provides one fruiting tree or shrub per
dwelling. The boundary wall will be planted
Figure 8.118 Seating niche Figure 8.119 Raised grow with native climbing species. Figure 8.121 Fagus Figure 8.123 Morus nigra Figure 8.125 Rosemarinus Figure 8.127 Stipa
gardens sylvatica ‘pendula’ officinalis tenuissima
The provisions have been designed in line with All homes are designed to exceed the
ADM Vol 1 for the residential elements and Vol nationally described space standard (NDSS),
2 for the communal access use, garden and and will have private amenity space accessed
retail elements. directly from the living room.
Please also refer to Section 4.5.12 of this DAS M4(3) Category 3: Wheelchair user dwellings
for a detailed commentary of the access and will be provided contributing to the overall
inclusive design strategy for the Phase 1 RMA. Phase 1 RMA total of 10%, while the remainder
will meet the M4(2) Category 2: Accessible
Pedestrian access and adaptable dwellings standard.
Pedestrian access is provided to three
separate residential lobbies directly from
Silvertown Street on the eastern side of Plot
6. Pedestrian access to the ground level
community and retail units is proposed via
Silvertown Street and North Woolwich Road,
respectively.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 353
8.4 PLOT 7
8.4.1 INTRODUCTION
Proposed scheme
Plot 7 meets four distinct street conditions;
The historic dockside to the north; the
proposed pedestrian connection of Silo D Way
to the east; the busy North Woolwich Road
to the south and Silvertown Street, a new
high street to the west. These varied street
conditions offer great opportunity and each
of the building’s façades has been designed to
relate to its adjacent streetscape.
Land use
Plot 7 GEA (sq.m.)
99 x 1 bed flats
Mix 92 x 2 bed flats
49 x 3 bed flats
1. Clearly define North Woolwich Road 2. Maximise the potential for expansive views 3. Provide a strong backdrop to Silo D
4. Create a clear relationship with Silo D and 5. Step height down from North Woolwich 6. Make a virtue of the challenges
the water Road to Silo D
Figure 8.130 Design principles of Plot 7
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 355
8.4.3 LAYOUT
Combined ground floor
The plan opposite amalgamates the lower
ground (level 0) and upper ground (level 1)
plans to better depict how the building meets
the sloping ground plane.
Lower ground
floor
Figure 8.132 Entrance on North Woolwich Road Figure 8.133 Approaching the resident’s concierge from Silvertown Street
Figure 8.134 Axonometric showing combined ground floor with all uses that meet Figure 8.135 The courtyard provides a calm secondary route for residents to their
the street with proposed street levels homes
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 357
Lower ground floor arrangement
Active uses on the lower ground floor have
been located along North Woolwich Road.
This includes two residential entrances, who’s
lobbies are connected by centralised cycle
parking. Particular care has been taken to
incorporate this cycle parking in naturally lit,
visible and overlooked communal spaces in
order to promote a healthy lifestyle as well as
to increase security and overlooking.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 359
Typical floor arrangement
The approach to typical residential levels
and, in particular to the provision of
private amenity ,is divided into two distinct
approaches. One addresses middle floors
(levels 02-10) while the other addresses
top floors (levels 11-13) in order to ensure
the strategy responds to the conditions of
individual homes.
es s ed
Ac c h pos
V hatc Pro f Plant
AO Roo (Resi)
a
Are
AOV Access
hatch
ed 14
pos
Pro f Plant Lvl
Roo (Resi)
a
Are
Lv l 08
Lvl 14 Lv l 04
Green roof
Communal roof
terrace
01 5 0 25 m N
Private terrace
Figure 8.142 Roof level plan
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 361
Typical dwelling layouts
Residential approach
Homes have been developed to provide quality Figure 8.143 Typical one bed unit layout with projecting balcony Figure 8.144 Typical one bed unit layout with winter garden
and address the following priorities:
• Open plan (sprinklered layouts) to optimise
space
• Standard 7m deep apartment plans to
provide wider, better proportioned rooms
• Shallower plan lead to better daylight
penetration
• Generous living rooms
• Well-designed built in storage
• Some split bedroom arrangements offer
greater privacy for sharers
• Dual aspect living rooms to capitalise upon
views
• Large format windows to optimise daylight
and views
Figure 8.145 Typical two bed split bedroom unit layout with projecting balcony Figure 8.146 Typical two bed unit layout with winter garden
0 1 2.5m
Figure 8.149 Level 1 two bed unit layout with internalised amenity
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 363
8.4.4 SCALE
Scale and massing
The axonometric drawing reveals stepping in
the massing. Two primary bars are oriented
east-west and rise to 14 storeys stepping
down to 11 storeys to the north to minimise
any impact of overshadowing Silo D Park.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 365
8.4.5 APPEARANCE
Appearance and façade treatment
Plot 7 is intended to be a considerate and
contextual piece of city. It has a role to play
in marking the arrival at a new place but it
is essentially a background building which
responds sympathetically to the surrounding
conditions – existing and emerging. Figure 8.153 Two distinct buildings with a shared order Figure 8.154 Civic façades addressing public spaces
The strategy of a base, middle and top outlined in the masterplan Architectural The thin flank walls of Plot 7 have special treatment to address surrounding public
Guidelines has been adopted to suit each block. The position of these bands relate realm and provide a backdrop to Silo D.
MaccreanorLavington is also the author of established heights in the masterplan.
Plot 6 which forms the opposing frontage
to Silvertown Street – the entry to the Site.
We have developed the appearance and
materiality of these two buildings in tandem,
not as a pair but as an ensemble. They
share facade strategies which are based on
the principles outlined in the Masterplan
Architectural Guidelines.
The strategic ideas, illustrated on this page Figure 8.155 An active street frontage Figure 8.156 Organising fenestration and balconies
in no particular order, show how the façades Opportunities for ground floor uses that activate street frontage are maximised. Flank walls have no projecting balconies in order to address North Woolwich Road
This has been materially defined as a ‘special’ base. and provide a clear backdrop to Silo D
have been conceptually structured and
organised. They have been overlaid in the
final diagram to show how each façade is
adapted to its place whilst remaining part of a
unified building.
Silo D:
One of the opportunities that Plot 7 holds is a
close proximity to Silo D with its idiosyncratic
industrial quality and elegant silhouette. Figure 8.158 South elevation to North Woolwich Road Figure 8.159 East elevation to Silo D Way
Without wishing to mimic, or to make over-
elaborate or over-simplistic associations, we
have tried to create a building which makes
the most of its setting and which has a subtle
but reciprocal relationship with the Silo D,
through form, symmetry, order, colour and
motif.
Figure 8.160 North elevation to Canalside Figure 8.161 West elevation to Silvertown Street
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 367
Materiality
Order: The new masterplan guidance suggests
that the residential buildings should be
ordered with a tripartite base middle and top.
The bay studies on the opposite page clearly
show how this has been established through
the change of material and form. This is
described below:
Figure 8.166 2 North Elevation to the Canalside 3 East Elevation to Silo D Way
PHASE
Plot 1 RMA
7 - Bay Study Sections
Figure 8.165
0 1 3m
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 369
Detail study - base
A white brick base is set at a constant level
around the entire block against the changing
ground plane. The facings are a blend of white
feature bricks to add variation, depth and
texture (to affect a ‘hand-made’ quality). The 1
larger shop front windows use brick corbelling 1
to provide a simple T-shape motif that is Figure 8.167 Stock brick
derived from Silo D. There are no projecting
balconies to residential windows within the 6
base so establishing a clean urban relationship
4
with the street.
The base provides a clear contrast to the
middle section that is in the primary stock brick 5
2
- a strong blend of rusty pinks, chalky buffs 2
and muddy grey facings with a considerable
level of contrast when viewed up close. Figure 8.168 Varied white ‘Feature’ brick
3
5
3
5 6
Figure 8.173 Axonometric of top Figure 8.174 Material quality precedents, clockwise
meeting middle section from top: Collectief Noord, Maccreanor Lavington,
Duggan Morris
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 371
Illustrative views
Views have been identified to capture Plot 7’s
relationship with its historic context and the
emerging neighbourhood. These are shown on
the following pages.
Figure 8.175 View locations Figure 8.176 View 1 - Looking west along the finger dock
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 373
8.4.6 LANDSCAPE
Courtyard layout
The courtyard in Plot 7 is partly at ground
level to the north but to the south it extends
over a lower ground floor building podium.
space
Shared amenity
zone
Planted buffer
amenity space
Private
Railing /gate
Copse
Private amenity
A
Stepping stones
A
Copse
Glade
Private radial paving
Copse
amenity
Seesaw Glade
Copse
Private
Private Figure 8.182 Section A - Typical section through
amenity private amenity space
Water channel
amenity
1:500
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 375
Materials
Plot 7 is in close proximity to the characterful
granite paving details around the dock edge.
This has informed the material choice for the
courtyard with a mix of site won, new granite
setts and clay pavers forming a circular paving
pattern. A cast concrete channel will provide
drainage for rainwater to be directed to the
dock at surface level. Drifter benches, similar
to those used along the dock edges will
provide seating in the courtyard.
Figure 8.186 Drainage Figure 8.187 Drifter Figure 8.200 Illustrative view of Plot 7 courtyard
channel benches
Residents’
amenity terrace
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 377
8.4.7 ACCESSIBILITY Car parking
Five (5) wheelchair accessible spaces are
AND INCLUSIVE DESIGN included within the ground floor curtilage.
Pedestrian access
Primary pedestrian access to the three
residential entrances is from the footway of
North Woolwich Road and Silo D Way.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 379
8.5 PLOT 8
8.5.1 INTRODUCTION
Proposed scheme
Plot 8 is a development of residential homes
designed as four distinct buildings, from 8 -
15 storeys, that address each of the varied
edge conditions. This arrangement, central
landscaped courtyard for all residents,
maximises the opportunities for dual aspect
homes and makes the most of special views.
Land use
Plot 8 GEA (sq.m.)
Residential (C3)
27,054
(Including ancillary)
Affordable homes 89 N
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 381
8.5.3 LAYOUT
Combined ground floor
arrangement
The lower ground and ground floor
arrangement is designed to:
ck B
• Maximise active frontages Blo
by
Lob
e
ierg
• Address the complex level changes around Lob
by Con
c
each boundary
Cyc
• Provide a servicing strategy for Plot 8 from by
le
Lob
stor
e
Barrier Point Road
Cyc
le
stor
The public realm flows around each block,
e
with visual links and access points through to
the courtyard garden. Each block has its own
UGF
entrance lobby and core, linking to the shared
podium garden that includes play and shared LGF
Refuse
amenity for all residents. Entrance lobbies for
Blocks A and B are reached from Canalside Plant
Plant
Cycle st
Cycle st
Lobby
Lobby, Shared 2 Bed C
by
Block
ore
Lob
space
ore
Core, Circulation 3 Bed ity
Commun
D
Private terrace Other Block
Primary communal
Public use entrance
residential entrance
Secondary communal
Other entrance
residential entrance
Private residential N
0 5 10 25m
entrance
Figure 8.208 Combined lower & upper ground floor plan
Block A
Block B
SILO D SILO D
Blocks C and D
N .W. R N .W. R
OA D
The entrance lobbies for Blocks C and D sit OA D
PONTOON
next to each other on the North Woolwich DOCK
C D
N .W. N .W.
R OA D R OA D
PONTOON PONTOON
DOCK DOCK
Figure 8.211 Blocks C & D entrances Figure 8.212 Journey home diagrams
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 383
Lower ground floor arrangement
Refuse storage is arranged as a central
managed strategy with one large bin holding
area in the lower ground. This will be picked
up on collection day from Barrier Point Road.
Other
0 5 10 25m N
Cyc
by
le
Lob
stor
have a mixture of internal amenity and inset
e
balconies that deal with the challenging levels
Cyc
le
Stor
on these boundaries. Homes on this level that
e
adjoin the courtyard have private terraces
with planting arranged to provide screening
and privacy.
Other 3 Bed
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 385
Typical upper floor arrangements
The upper levels of the development are
arranged in four distinct blocks each with
their own core that allow views and light into
the central courtyard and maximises the
opportunities for dual aspect homes.
0 5 10 25m N
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 387
8.5.4 TYPICAL
DWELLING LAYOUTS 0.5
Metres
0 0.5 1 2.5 m
1:50
0.5 0 0.5 1 2.5 m
Metres 1:50
Residential approach
Scale: 1 : 200
enjoyable.
All residential units are covered by a sprinkler
system. This has provided the opportunity
to explore open plan apartment layouts and
wherever possible living spaces have been B
views. D C
D C
Figure 8.218 Typical ground floor maisonette Figure 8.219 Typical 2 bed home
Scale: 1 : 50
72.8 sqm
Metres 1:50
views
• Large format windows to optimise daylight
and views
A D C
D C
SQP1-PTE-08-ZZ-DR-A-001202
OMS-1B-B WAD 07/31/19
19-004
Scale: 1 : 50
Silvertown Quays Phase 1
63.3sqm
SQP1-PTE-08-ZZ-DR-A-001201 DZ2
14.08.19 1B-2P WAD - PTE-8-OMS-1B-B
Typical 1 bed Platform
19-004
OMS/AR/SO-1B-A column locations
Silvertown Quays Phase 1
Scale: 1 : 50 DZ2
52.6sqm 1B-2P PTE-8-OMS/AR/SO-1B-A
Figure 8.220 Typical 1 bed home Figure 8.221 1 bed wheelchair home 0 1 2 5m
Metres
0 0.5 1 2.5 m
1:50
Block B
projecting balconies. A
Block C
D C
SQP1-PTE-08-ZZ-DR-A-001226
09/10/19
Figure 8.222 and Figure 8.223 illustrate a dual
SQP1-PTE-08-ZZ-DR-A-001209
19-004
08/14/19
19-004
OMS-2B-L SILVERTOWN QUAYS
Silvertown Quays Phase 1
Scale: 1 : 50 PHASE 1 RMA
DZ2
Scale: 1 : 50
Metres 1:50
Block D
Scale: 1 : 50
AR-3B-A
86.6sqm
D C
SQP1-PTE-08-ZZ-DR-A-001219
08/14/19
19-004
SILVERTOWN QUAYS
PHASE 1 RMA
DZ2
3B-5P PTE-8-AR-3B-B
91.6sqm
Internalised
amenity
Figure 8.224 Typical corner 3 bed home Figure 8.225 Lower 3 bed home with internal amenity
Scale: 1 : 200
Spatial Plan
0.5
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 389
Metres
DZ2
3B-5P PTE-8-AR-3
Silvertown Quays P
19-004
08/14/19
SQP1-PTE-08-ZZ-
0
0.5
A
D
1
8.5.5 SCALE
Scale and massing
The residential apartments are arranged in
four distinct blocks that allow light into the
central courtyard, make the most of special
views and maximise the opportunity for dual
aspect homes.
RAYLEIGH ROAD
1 2A MILLS
SQUARE
3
HOVIS STREET
MILLS WAY
WESLEY AVENUE
Sections 4
PHASE 1 BOUNDARY
North-south section
SILOreferences
The three-storey base treatment D
Figure 8.227 North / south section
PARK
the DLR height as it passes Plot 8 and its 8_Maximum
49900
BARR
8-Level 14
East-west section
B
D
8-Level 13
IER P
SILVERTOWN STREET
6
the arrangement of homes and balconies
OINT
8-Level 11
8-Level 10
A
8-Level 09
DW
7
8-Level 08
8-Level 04
Illustrated here is the cross section about half PONTOON DOCK DLR
AD
LWICH RO & Education
8-Level 03
CAR ENTRANCE
Other BLOCK D
SILO D WAY BLOCK C BARRIER POINT ROAD
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 391
8.5.6 APPEARANCE
Appearance and facade treatment
The external appearance of the four blocks
that form Plot 8 has been developed with
reference to the unique location of each
block; the industrial history of the Site and
the distinctive form of Silo D. The following
principles have informed the design of Plot 8.
1 Interior
• Facades with character that respond to
their unique context
• Relationship to Plot 7
3 Base
4 Anchor
1 South Elevation - North Woolwich Road 2 East Elevation - Barrier Point Road
4
Figure 8.232 Elevations
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 393
Materiality
Approach to base, middle and top
Interior – Homes within the Enclosure Walls
The base of Blocks B, C and D is expressed
Within the courtyard and off the streets these
in feature textured concrete (or similar)
facades and the homes contained within the
responding to the sculptural form of the DLR
enclosure walls are expressed in a simpler
set at three storeys on North Woolwich Road,
treatment and are proposed in a white brick,
moving along the building to become two
reflecting light around the internal courtyard
storeys as ground levels rise to the Canalside.
and providing a backdrop for the lush green
This datum is picked up in the detailing in the
planting and textures on the podium garden.
duplexes in the Anchor Building and unifies
a range of different uses around the ground
Anchor – The Anchor building Block A
floor.
The Anchor building which sits on Canal Side
The brick detailing to the middle and top
will be clad in a special textured brick detail in
reflect the facade principles in the red
a rich red colour that references the remnants
brick grid enclosure to streets; the homes
of rust around the site in the retained
contained within the courtyard and the key
buildings and provides a strong backdrop to
Anchor Building.
the white Silo D.
Figure 8.233 Stacked double cant brick detail Figure 8.234 Offset example of Double cant brick -
CF Moller, Olympic Village Stratford
Enclosure - Facades on main streets
The balcony detail will reference the old
historic warehouse buildings and generous
The proposed enclosure to North Woolwich
windows will let light flood in and maximise
Road; Silo D Way and Barrier Point Road above
the potential of spectacular views.
SIDE PANEL 02
SIDE PANEL 03
SIDE PANEL 01
the base is a red blush brick arranged in a
strong simple grid.
DOUBLE PANEL 02
FULLY GLAZED
sizes; arrangements and offsets that provide a
calm ordered treatment, rich with variety.
Figure 8.238 View towards Block A from Silo D Way Figure 8.239 View across basin towards Blocks A & B Figure 8.240 View up Barrier Point Road towards Millennium Mills
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 395
OPP BOUNDARY
DOCK WATERFRONT
RTOWN
ACE 2B HOVIS
YARD
2ABay studyMILLS
SQUARE
3
- external facade
1
1 0
HOVIS STREET
responding to MILLS
the sculptural
WAY form of the
DLR. There are no projecting balconies in the
1 Brick type 1 5
base level. This concrete base is arranged in
the grid with the textured detail and window
4
arrangement echoing the detailing of the
brickwork above.
Textured concrete
3
sits above the concrete datum; detailing here PONTOON DOCK
or similar
includes a daubed mortar treatment.
1
Windows and metalwork in complementary
tones are used throughout.
235
75
75
Recon stone or
4 5
brick detail
D
RK 3
3
SILO GE
BRID
BARR
3
6
D
6
IER P
5 Metal window
system with 4
OINT
3 09/0
ROA
19-0
DW
SILV
D
7 PHA
DZ2
AY
Bay
6 Metalwork
DOCK WATERFRONT
RTOWN
ACE 2B HOVIS
YARD
0.5 0 0.5 1 2.5 m
3
- internal facade
SQUARE
Within the courtyard and off the streets these
1
internal facades and the homes contained
HOVIS STREET
within the enclosure walls are expressed in 3
MILLS WAY
a simpler treatment and are proposed in a
white brick, reflecting light around the internal
courtyard and providing a backdrop for the 1 Brick type 2
lush green planting and textures on the
podium garden.
4
The façade is topped with a brick parapet that 1
sits above the concrete datum; detailing here 4
includes a daubed mortar treatment. 5
4
Light toned metalwork railings on the
projecting balconies is offset by a warm 2 Textured concrete
or similar 1
red base and soffit detail. Windows and
metalwork in complementary tones are used
4
throughout.
SILVERTOWN AVENUE
PONTOON DOCK
3 Recon stone or
brick detail
5
D 4
RK 5
SILO GE
BRID
BARR
4 Metal window 1
D
system with
IER P
19-004
SILVERTOWN QUAYS
8
SILO
4 PHASE 1 RMA
DZ2
ROA
Internal Balconies
DW
7
AY
5 Metalwork
DOCK WATERFRONT
RTOWN
ACE 2B HOVIS
YARD
2ABay studyMILLS
3
- anchor building
SQUARE
The Anchor building is clad throughout in
a special textured brick detail in a rich red 3
HOVIS STREET
0.5 0 0.5
colour that references
MILLS WAYthe remnants of rust
Metres
around the site in the retained buildings and
provides a strong backdrop to the white Silo
D. This textured brickwork is arranged in a 1 Brick type 3 4
4
strong grid that contains generous windows
designed to reference the historic warehouse 3
building.
4
The Concrete detailing that runs around the
base of Plot 8 is picked up in the duplexes at 3
the base of the Anchor building. 1
1
The façade is topped by the brick frame that 2 Textured concrete 5
continues up to form a crown that contains or similar
and frames the residents roof garden. 3
5
The balcony detail will reference the old
SILVERTOWN AVENUE
1
4
151
D
235
235
RK
3
SILO GE
BRID
BARR
2
4 Metal window
D
system with 4
IER P
8
SILO
ROA
2
DW
7 SQP1-0
AY
09/09/19
19-004
SILVERTOWN
5 Metalwork
PHASE 1 RMA
DZ2
Bay Study - No
Figure 8.249 Materials PONTOON
Figure 8.250 Section DOCK
Figure DLRElevation
8.251 Figure 8.252 Detail axonometric callout
AD
WICH RO
NORT H WOOL
398 Silo D Quarter | 8.0
Figure 8.253 View east along North Woolwich Road
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 399
Figure 8.254 View from Silo D Park
‘Playful’ level change Copse trees Figure 8.258 Playful topography within soft landscape
Central amenity zone
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 401
C
Defensible Shared Dock
A space space edge
Railing /gate
ce
A
le spa
e n s ib
D ef
tennis
Copse B
Glade
Private
amenity
space
B
Copse
Grow gardens
1:500
Figure 8.265 Clay pavers Figure 8.266 Clay pavers Figure 8.276 Illustrative view of plot 8 courtyard
A large circular bench will surround the Open canopy tree species such as alnus
courtyard’s central tree, providing a spot for glutinosa lacianata and betula pubescens will
residents to enjoy views towards the finger ensure light reaches the understory planting
dock and Silo D. Robust play objects such as and lawns. A characterful semi-mature
the concrete table tennis and granite boulders Saphora japonica tree will be located at
will be located at the edges of the courtyard. centre of courtyard.
Figure 8.269 Alnus glutinosaFigure 8.277 Ribes uva-crispa Figure 8.272 Aster Figure 8.274 Stipa tenuissima
The level changes of the grass verges will be
enticing play spaces with tactile grass species
growing around the play boulders.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 403
Roofscape
The roofs of Plot 8 will work hard to provide
additional residents amenity space, rainwater
harvesting and ecological benefits. The
roofscape combines biodiverse green roofs on
A
Blocks C and D and communal roof terraces
Residents’
on Blocks A and B. Residents’
amenity terrace
amenity terrace
The proposed rooftop amenity space layout
responds to the opportunities of views and
micro-climate and offers a range of uses for
residents including passively irrigated grow Figure 8.279 Biodiverse green roof
gardens and landscaped seating areas. The A
raised parapet on Block A will frame views
towards the docks and Silo D.
The homes include a mix of tenures, open All homes are designed to exceed the
market sale; affordable rent and intermediate. nationally described space standard (NDSS),
and most will have private amenity space,
The plot provisions have been designed in line internal or external.
with ADM Vol 1 for the residential elements
and Vol 2 for the communal access use, M4(3) Category 3: Wheelchair user dwellings
courtyard and community use elements. will be provided contributing to the overall
Phase 1 RMA total of 10%, while the remainder
Please also refer to Section 4.5.12 of this DAS will meet the M4(2) Category 2: Accessible
for a detailed commentary of the access and and adaptable dwellings standard.
inclusive design strategy for the Phase 1 RMA.
Pedestrian Access
Plot 8 sits between the Canalside to the north
and North Woolwich Road in the southwestern
corner of the Silvertown Quays OPP.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 405
9.0
OPP compliance
9.1 PARAMETER PLAN COMPLIANCE
The Phase 1 RMA plots layout has been
overlaid onto the Parameter Plans approved
under Condition B1 of the OPP to demonstrate
compliance.
NOTES
Fletcher Priest Architects is a Limited Liability Partnership registered in
1.2B
1.1 1.2A 1.3
1.4
04 UC SH 280414
03 LT SH 170414
02 UC SH 030414
01 UC SH 120314
0 UC SH 040314
REV DESCRIPTION BY CHK DATE
1.5
1.6
1.8
1.7 PARAMETER PLAN 01
SITE PLAN
1251 GA 03001 04
SCALE
1:1500 @A1 1:3000 @A3
DATE / DRAWN BY / CHECKED BY
04.03.2014 / UC / SH
OPP Boundary
LEVELS
fpa. ≡ this drawing is to be read in conjunction with other drawings and
specification produced by fpa and other members of the design team. ≡
all dimensions are in millimeters unless otherwise stated. ≡ do not
scale this drawing. ≡ any discrepancies in dimensions are to be
reported to the architect. ≡ all information subject to detail site survey.
Millennium Mills is the only existing building (c) UKMap Copyright. The GeoInformation Group 2013 Licence No.
LANDMLON100003121118
Parameter Plan.
Buildings to be retained
for the surrounding park and buildings, is not Existing dock levels, bathymetry to top
of silt, AOD in metres. The underlying
bed level is typically around -4m AOD
Rank Hovis
Millennium Mills
1.2B
1.1 1.2A 1.3
1.4
04 UC SH 080514
03 UC SH 280414
02 LT SH 170414
01 UC SH 120314
0 UC SH 040314
REV DESCRIPTION BY CHK DATE
1.5
Silo D
1.6
1.8
1.7
PARAMETER PLAN 02
DEMOLITION PLAN AND
EXISTING SITE LEVELS
DRAWING NUMBER / REVISION
1251 GA 03002 04
SCALE
1:1500 @A1 1:3000 @A3
DATE / DRAWN BY / CHECKED BY
04.03.2014 / UC / SH
OPP Boundary
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 409
9.1.3 PARAMETER PLAN
03: PROPOSED SITE
LEVELS
0 5 10 20 50m
N
red) and proposed Phase 1 RMA site levels if Outline planning permission boundary
Buildings to be retained
different from existing (in blue), see Figure 9.3. Buildings subject to part demolition
and rebuild, and part restoration
+0.0m Proposed site levels (as existing based
on topographical survey received from
Arup 2013.11.25), A.O.D in metres
1.4
1.5 Client
20 Triton Street
Regent’s Place
London NW1 3BF
Consultant
1.8
1.7 1
2B
2A
3
6
8
7
Project
PARAMETER PLAN 03
PROPOSED SITE LEVELS
Purpose of drawing
RB CC TSP
OPP Boundary Date Scale Size
Figure 9.3 Phase 1 RMA Site and plots layout overlay onto Parameter Plan 03: Proposed Site Levels
Proposed Phase 1 RMA plots
OPP Boundary
Phase 1 RMA Boundary Figure 9.4 Phase 1 RMA proposed site levels in AOD
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 411
9.1.4 PARAMETER PLAN
04: WORK TO EXISTING
STRUCTURES NOTES
Fletcher Priest Architects is a Limited Liability Partnership registered in
England and Wales (OC336568) at the below address. ≡ this drawing
is to be read in conjunction with the design risk assesment prepared by
fpa. ≡ this drawing is to be read in conjunction with other drawings and
specification produced by fpa and other members of the design team. ≡
Dock walls within Phase 1 RMA will be all dimensions are in millimeters unless otherwise stated. ≡ do not
scale this drawing. ≡ any discrepancies in dimensions are to be
reported to the architect. ≡ all information subject to detail site survey.
KEY:
Buildings to be retained
Millennium Mills is subject to part demolition partly infilling, bridging and submerging
(natural) elements. Diversity is desirable
for microclimatic variance, ecological
and rebuild, and part restoration, as permitted enrichment and visual interest
1.2B
1.1 1.2A 1.3
1.4
05 UC SH 080514
04 UC SH 280414
03 LT SH 170414
02 UC SH 200314
01 UC SH 120314
0 UC SH 040314
REV DESCRIPTION BY CHK DATE
1.5
1.6
1.8
1.7
PARAMETER PLAN 04
1251 GA 03004 05
SCALE
1:1500 @A1 1:3000 @A3
DATE / DRAWN BY / CHECKED BY
04.03.2014 / UC / SH
OPP Boundary
the Parameter Plan within the +/- 10m Limits scale this drawing. ≡ any discrepancies in dimensions are to be
reported to the architect. ≡ all information subject to detail site survey.
Of Deviation. (c) UKMap Copyright. The GeoInformation Group 2013 Licence No.
LANDMLON100003121118
KEY:
page 68”
Outline of existing dock wall in area
where modification to dock is proposed
(for reference)
1.2B
cycling is not permissible and with fire
access and out of house servicing
+/-10m L.O.D.
1.4
pedestrian bridge
1.6
1.8
1.7
PARAMETER PLAN 05
ROADS AND ROUTES
1251 GA 03005 07
SCALE
1:1500 @A1 1:3000 @A3
DATE / DRAWN BY / CHECKED BY
04.03.2014 / VJ /SH
OPP Boundary
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 413
9.1.6 PARAMETER PLAN
06: OPEN SPACE
Open spaces in Phase 1 RMA, OS 2.1, OS2.2
NOTES
(partly outside Phase 1 RMA), OS2.3, OS2.4, Fletcher Priest Architects is a Limited Liability Partnership registered in
England and Wales (OC336568) at the below address. ≡ this drawing
is to be read in conjunction with the design risk assesment prepared by
OS3 (outside Phase 1 RMA), and OS4, have fpa. ≡ this drawing is to be read in conjunction with other drawings and
specification produced by fpa and other members of the design team. ≡
all dimensions are in millimeters unless otherwise stated. ≡ do not
scale this drawing. ≡ any discrepancies in dimensions are to be
been provided to comply with or exceed reported to the architect. ≡ all information subject to detail site survey.
the minimum area as indicated in Table 9.1 (c) UKMap Copyright. The GeoInformation Group 2013 Licence No.
LANDMLON100003121118
Buildings to be retained
OS2.2 Public Amenity 1,300 1,300 OS2.4 OS7 where modification to dock is proposed
(for reference)
OS2.3 1.2B
Orientation/way finding, 2,300 3,100
OS2.3 OS2.2
public amenity and display 1.2A
1.1 OS2.1
OS2.4 Waterside Amenity 2,200 2,700 1.3
OS6
OS3 Public Amenity 900 900 1.4 OS1.1 OS8
Waterside Amenity and 1,400 2,500 OS3
OS4
community use
OS5 Orientation, public amenity 1,000
REV DESCRIPTION BY CHK DATE
Propose Phase 1 RMA plots Figure 9.7 Phase 1 RMA open spaces overlay onto Parameter Plan 06: Open Space
*
and rebuild, and part restoration
to the OPP to vary ‘Parameter Plan 07 - Extension to existing building with maximum
building heights as existing Millennium Mills
building
Maximum Building Heights’. The Non-material Outline of existing dock wall in area where
modification to dock is proposed (for reference)
new core to the Millennium Mills building. Maximum building heights as existing
2A
3
6
8
7
Project
PARAMETER PLAN 07
MAXIMUM BUILDING HEIGHTS
Purpose of drawing
CC
Checked
GM
Approved
TSP
Date Scale Size
20.08.2019 1:1500 A1
Phase 1 RMA Boundary Drawing number Revision
1251 GA 03007 06
Figure 9.8 Phase 1 RMA Site and plots layout overlay onto Parameter Plan 07: Maximum Building Heights
Proposed Phase 1 RMA plots
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 415
9.1.8 PARAMETER PLAN
08: DEVELOPMENT
ZONES
Development Zones as defined in Parameter
Plan 08 define the maximum floorspace
permitted across the Site. Phase 1 RMA falls
within DZ1, DZ2 and DZ4 and doesn’t exceed
the maximum floorspace permitted.
1.2B
1.1 1.2A 1.3
1.4
1.5
1.6
1.8
1.7
Figure 9.9 Phase 1 RMA Site and plots layout overlay onto Parameter Plan 08: Development Zones
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 417
9.2.3 VEHICULAR Proposal
ROUTES - SECONDARY
ROADS
Design Code 2.2.14 states that ‘Secondary
Roads will have a minimum overall width of
18m and will have two-way vehicular traffic
with a total carriageway width of 5.5m’.
WESLEY AVENUE
16m
Design Code
Residential lobby
PLOT 1
um overall
vehicular
h of 5.5m.
h a minimum
side of the
Footway
Loading bay
Carriageway
rain garden
Planting
Footway
table rooms
om the public
etween 1-3m
e pavement to Figure 9.10 Illustrative section through a typical Figure 9.11 Illustrative section through
Secondary
Illustrative Roadthrough
section (from aDesign
typical Code) proposed Secondary Road (Wesley
Secondary Road Avenue)
1
1
Figure 9.15 2. Illustrative view towards Silo D from Figure 9.16 2. Illustrative view towards Silo D from
north
2. (fromview
Illustrative Design Code)
towards Silo D from north east north (proposal)
2
1. Illustrative view towards Silo D from east
1. Illustrative view along the Diagonal towards
Millennium Mills
Design Code Proposal
3
2
Figure 9.12 Key vista location plan Figure 9.17 3. Illustrative view towards Silo D from Figure 9.18 3. Illustrative view towards Silo D from
east (from Design Code) east (proposal)
3. Illustrative view towards Silo D from north
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement SILVERTOWN QUAYS | DESIGN CODE 27 419
e design and
s, emphasising
apes.
9.2.5 MASSING AND Proposal
RESIDENTIAL PRIVACY
Design Code 3.3.1 states that ‘Distance
between habitable rooms should be a
minimum of 18m.’
idential privacy
Design Code
should
18 m
the plot is
duced provided
quatly protected
PLOT 7
Community
PLOT 8
Community
uld include use
ws or obscure
g of windows to
18 m
2.0-4.0 2.0
width varies
rain garden
Planting
width varies
rain garden
Planting
Footway
Footway
Minimum 18m setback to all
Figurehabitable rooms 18m setback to all habitable
9.19 Minimum Figure 9.20 Illustrative section pedestrian street. Silo
rooms (from Design Code) D way- Plot 7 & Plot 8
FRONTAGE
Design Code 2.6 describes primary, secondary
and other active frontages. 80%
84%
2B
58%
1 2A 3
The updated strategy for active frontages for
100%
Phase 1 RMA, shown in Figure 4.33 on page 72%
48, builds upon the strategy set out in the 4
81%
Design Code (see Figure 9.22), but diverts
to incorporate the newly introduced north-
south route (Silvertown Avenue) and shifts Location of primary and secondary active frontages
Figure 9.22 Location of primary and secondary active
the focus to activating key open spaces. The frontage (from Design Code)
5
updated strategy also tries to reconcile the
limited area available for active uses (retail, Primary active frontages
community) in DZ2 by only activating corners
Secondary active frontages
of plots on North Woolwich Road.
Mill Road
%
100
6
There is a requirement for 80% of primary 57% 8
7
frontages to be active (see Figure 9.21), and 91%
73%
ages along
efined on
outes indicated
minantly
nd floor
of shop/brand
nal entrances
n the plan
e public realm
80% 80%
building Primary active frontages: 80% of the ground floor
brank building9.21
Figure frontages should
Primary comprise
active of shop/ 80% of the
frontages:
es (communal brand frontages,
ground office lobbies
floor building or communal
frontages should comprise of
s. entrances. frontages, office lobbies or communal
shop/brand
to feel part of entrances (from Design Code)
of the ground
eet should
g entrances, Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 421
storage. Any
ontinuous
Appendix
A1
Drawings
A1.1 CONDITION A3: PHASING STRATEGY
0 5 10 20 50 m
N
Key
Phase 1 boundary
Outline planning permission boundary
Phase 1.0 - Excluded works phase. No floorspace
Phase 1.1 - Plot 1
*Phase 1.2Ai - Plot 2Ai
(make exisiting building watertight, exisiting façade works
& fit out Ground to 7th floor)
*Phase 1.2Aii - Plot 2Aii
(new façade works & fit out to 8th floor to 12th floor)
Phase 1.2B - Plot 2B
Royal Victoria Dock Bridge alignment is indicative and subject to Phase 1.3 - Plot 3
change under separate planning application.
Phase 1.4 - Plot 4
Phase 1.5 - Plot 5
Phase 1.6 - Plot 6
Phase 1.7 - Plot 7
Phase 1.8 - Plot 8
Phase 1.9 - Public realm and landscaping phase
No floorspace
Phase 1.10 - Temporary energy centre
Note: Plot 2A (comprising Plot 2Ai and 2Aii) constitutes a single phase
of the development for the purposes of the Community Infrastructure
Levy 2010 (as amended).
Phase 1: Buildings shown are indicative and subject to change based on future
Reserved Matters Application
Phase 2- 7: Buildings within Phases 2-7 will be set out in future Reserved
1.2B
Matters Applications and this Site Wide Phasing Strategy shall be amended
accordingly
1.2A*
strategy approved pursuant to Condition A3, which phases may comprise any
component part of the Development and may either individually or collectively
1.1 1.3
comprise Excluded Works, Construction Works, a Development Plot (or
Development Plots), a Building (or Buildings), landscaping and infrastructure
PHASE 3 or, in any case, part thereof and each and every such phase described on the
approved phasing strategy shall constitute a separate phase of the
development authorised by this planning permission for the purposes of the
Community Infrastructure Levy Regulations 2010 (as amended).
For the avoidance of doubt, the ‘Excluded Works’, each of the ‘Plots’, the
‘Public Realm and Landscaping’ and the ‘Temporary Energy Centre’ identified
within Phase 1 each constitute a separate phase of the development for the
purposes of the Community Infrastructure Levy 2010 (as amended).
PHASE 2
02 26.07.2019 Planning amendments CC GM
1.5 01
00
09.07.2019
16.05.2019
For review
For review (submitted with drawing no. MP-1803-003)
CC
CC
GM
GM
Rev Date Description Drawn Checked
Client
20 Triton Street
Regent’s Place
London NW1 3BF
PHASE 5
Consultant
PHASE 7
1.6
70 Cowcross Street
London
EC1M 6EJ
1.8
2B
1
2A
3
1.7 4
6
8
7
Project
SITE WIDE -
PHASING PLAN
Purpose of drawing
CC GM TSP
Date Scale Size
03.09.2019 1:1250 A1
Drawing number Revision
SQP1-PP-X-MP-DGA-L00-MP102 03
EVELYN ROAD
Plot 5
1.5
MILL ROAD
20 Triton Street
Regent’s Place
Plot 8
London NW1 3BF
1.8 Consultant
Plot 7
1.7 70 Cowcross Street
London
EC1M 6EJ
ROAD
OLWICH
2B
NORTH WO
1
2A
3
STATION
5
DOCK DLR
PONTOON
6
8
7
Project
PHASE 1 -
CONSTRUCTION PHASING PLAN
Purpose of drawing
03.09.2019 1:1000 A1
Drawing number Revision
SQP1-PP-X-MP-DGA-L00-MP153 02
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 367
0 5 10 20 50 m
N
Royal Victoria Dock Bridge alignment is indicative and
subject to change under separate planning application.
Key
Phase 1 boundary
Outline planning permission boundary
Servicing road
Servicing locations
Refuse collection location
Loading bay
P Parking entrance
Car club bay
Servicing bay
On street parking
Motorcycle parking (5 spaces)
Plot 5 accessible parking
Plot 2A Plot 2B
Additional accessible parking (65 spaces) to
Plot 1 1.2A 1.2B achieve 10% provision (indicative only)
1.1 Short-stay cycle parking
LOADING BAY
Site entrance
Temporary energy centre
LOADING BAY
Plot 5 Plot 7
36 Number of homes 240 Number of homes
1 Car parking 5 Car parking
60 Cycle parking 383 Cycle parking
1 Short-stay cycle parking 7 Short-stay cycle parking
3 Motorcycle parking
Plot 6 Plot 8
EVELYN ROAD
106 Number of homes 297 Number of homes
5 Car parking 10 Car parking
Plot 5 158 Cycle parking 447 Cycle parking
1.5 24 Short-stay cycle parking 8 Short-stay cycle parking
MILL ROAD
1.6 Rev
Client
Date Description Drawn Checked
20 Triton Street
Regent’s Place
Plot 8
London NW1 3BF
Servicing
bay 1.8 Consultant
Servicing bay
Plot 7
1.7 70 Cowcross Street
London
EC1M 6EJ
P
P P NORTH WO
OLWICH
ROAD
1
2B
2A
3
4
Servicing
bay
STATION
5
DOCK DLR
PONTOON
6
8
7
Project
PHASE 1 -
PARKING AND SERVICING PLAN
Purpose of drawing
03.09.2019 1:1000 A1
Drawing number Revision
SQP1-PP-X-MP-DGA-L00-MP152 02
Key
Phase 1 boundary
Outline planning permission boundary
Private
Intermediate
Affordable Rent
Mixed tenure - Affordable Rent/Intermediate
Mixed tenure - Intermediate/Private
Royal Victoria Dock Bridge alignment is indicative and subject to
change under separate planning application. Temporary energy centre
PLOT 2B
1.2B
PLOT
PLOT 1 2A PLOT 3
1.1 1.2A 1.3
265
HOMES
PLOT 4
1.4
36
HOMES
PLOT 5 01
00
17.07.2019
09.07.2019
Planning amendments
For review
CC
CC
GM
GM
1.5 Rev Date Description Drawn Checked
Client
20 Triton Street
Regent’s Place
London NW1 3BF
106
HOMES
Consultant
70 Cowcross Street
PLOT 6 297
HOMES
London
EC1M 6EJ
1.6
240 PLOT 8
HOMES
1.8
2B
1
2A
3
PLOT 7 4
1.7
5
6
8
7
Project
PHASE 1 –
AFFORDABLE HOUSING PHASE PLAN
Purpose of drawing
CC GM TSP
Date Scale Size
03.09.2019 1:1250 A1
Drawing number Revision
SQP1-PP-X-MP-DGA-L00-MP154 02
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 369
Appendix
A2
Secured by Design
A2.1 SECURED BY DESIGN
The Development has been initially registered The following table is a record of the in- Counter Terrorism
for Secure by Design, as confirmed by person meetings with the DOCO and CTSAs to
In the process of engagement with the CTSAs,
Christine Keen, the Designing Out Crime date:
the terrorism threat was clearly articulated as:
Officer (DOCO) for LBN. Reserved Matters
Specification xxi. of the OPP has a 31st January 2019 CTSAs 10. Consequential collateral damage arising
requirement to demonstrate how the Secured from an Improvised Explosive Device (IED)
By Design accreditation can be secured and 8th February 2019 Christine Keen, DOCO being used at nearby iconic targets outside
how these principles and practices will be of the Development.
incorporated in the Development. 15th May 2019 CTSAs
11. Vehicle as a Weapon (VaW) attacks within
To ensure Secure By Design principles are 30th May 2019 Christine Keen, DOCO the Development.
being followed the team have undertaken
a review of relevant local policies, current 6th August 2019 Christine Keen, DOCO These two identified threats have
legislation, and planning guidance, including: subsequently been addressed during this
8th August 2019 CTSAs and Christine design Phase by considering the following
• The National Planning Policy Framework measures:
Keen, DOCO
(NPPF 2018)
Counter Terrorism Security Advisors (CTSA) Blast Mitigation: Through consultation
• Government Issued “Planning Practice with a qualified Structural Blast Engineer
identified risks and areas of focus, established
Guidance” including specific notes on (SBE) on the Register of Security Engineers
criteria for mitigation measures, and evaluated
Design (2014) and Health and Wellbeing and Specialists (RSES), blast mitigation
the RIBA Stage 2 design in order to ensure
(2017) measures to the glazing and façades of the
Secure by Design principles are appropriately
applied to Phase 1. Development, and structural implications
• Secured by Design New Homes (2014) on the buildings using both theoretical and
Both the DOCO and CTSA were satisfied empirical guidance, thereby defining what
• Secured by Design: Homes (2016) is required for the glazing, framing and
with the process of early and in-depth
engagement. They have confirmed their building cores. It is planned that following any
• Secured by Design: Commercial clarification for the CTSA, this document will
support that Secured By Design had been
Development (2015) discharge the planning requirements in terms
considerately addressed. Key general Secure
By Design principles, as well more detailed of blast mitigation.
• Crowded Places Guidance (2017)
considerations related to Counter Terrorism
(CT) and CCTV, have been discussed and Hostile Vehicle Mitigation: In order to provide
• Protecting crowded places: design and a proportionate defence against VaW attacks,
agreed with the DOCO and the CTSAs.
technical issues (2014) that recognises both the seriousness of such
an attack, but also the need to provide a high
Furthermore, TSP and various members of the
quality urban landscape, a Vehicle Dynamics
design team have met with Christine Keen,
Assessment (VDA) will be prepared for agreed
whilst developing the design for Phase 1.
areas within the Phase that are ‘crowded
spaces’ consistent with the UK Government
Owing to the Development being a public
definition (Home Office, CPNI, NaCTSO, March
space a number of Counter Terrorism Design
2014).
Advisors (CTSA) have also been consulted as
part of this process.
Further technical detail can be supplied on
request.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 373
Appendix
A3
Bird hazard management plan
A3.1 EXECUTIVE SUMMARY
Greengage Environmental was commissioned A baseline assessment of potential bird
by TSP to produce a Bird Hazard Management activity was made during a site visit and
Plan (BHMP) to support the Phase 1 RMA orientation on 1st March 2019 as part of the
of the Silvertown Quays Development. Preliminary Ecological Appraisal. A review of
Specifically, the report is required under the the valuable habitats and features on site as
Reserved Matters Application Specification xvi well as those within the immediate vicinity
and xxii, and Conditions A1, A6 and A11. and any green corridors or wildlife linkages
to the proposed development site was
Phase 1 is located in the western part of the undertaken. Actual bird presence, types of
Site and comprises Development Plots 1, 2A activity, opportunities for nesting and other
(i and ii), 2B, 3, 4, 5, 6, 7 and 8, along with field signs to indicate current site usage by
associated public realm and landscaping. birds was recorded and further wintering and
Together Plots 2A, 2B and 3 comprise the breeding bird surveys were undertaken in
proposals for the existing Millennium Mills February 2019 and spring / summer of 2019
building. respectively.
The Phase 1 RMA Site is located ~600m away This BHMP describes which steps have been
from London City Airport and therefore within taken to minimise the attractiveness of the
the statutory radius (13km) for aerodrome development to birds that could endanger the
safeguarding consultation. safe movement of aircraft and the operation
of the London City Airport and includes a
The Site lies beneath flight paths close to commentary on landscaping, architectural
the westerly end of the runway at London and roof design, and waste storage and
City Airport in an area subject to aerodrome collection.
safeguarding, the process by which airspace
required for safe and efficient take off and Input and advice are provided on how to
landing at airports is maintained free of manage the buildings, habitats and features,
new development. General design measures discouraging bird roosting, nesting and
relating to aviation safeguarding are discussed ‘loafing’ by certain species and establish a
in the Aviation Safeguarding Report produced regular monitoring regime that will ensure
by Eddowes Aviation Safety Ltd. mitigation procedures continue to work post-
development.
This BHMP refers to ‘Airport Operators
Association/Civil Aviation Authority’s
Safeguarding of Aerodromes Advice Note 3:
Wildlife Hazard around Aerodromes’.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 377
A3.3 BACKGROUND
Site location and description Description of development
The Site extends to 27.4 hectares and is Please refer to Chapter 1.0 Introduction for
centred on National grid Reference TQ 4180 the Phase 1 RMA and the OPP description of
2231, OS Co-ordinates (541226, 180318). The development.
Phase 1 RMA Site sits in the western part of
the Site and extends to 5.58 hectares.
Figure A3.1 Millennium Mills within which large numbers of pigeons were observed with Canada geese using the Figure A3.2 Silo D, dense scrub and dock habitats
Open Mosaic Habitat in foreground to feed and nest
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 379
Overwintering birds
Date Cloud cover Rain Wind Visibility
Two visits were undertaken in February 2019,
7/2/19 30-50% no breezy good
on the 7th and 22nd. The Site was walked
for a one day period by an experienced 22/2/19 0-5% no Calm good
ornithologist using 10x42 Leica binoculars Table A3.1 Conditions for overwintering bird survey visits
and a Swarovski telescope. Surveys were
conducted where possible in favourable Species Max Comments
weather conditions avoiding heavy rain and Number
strong winds which could suppress bird
Cormorant Phalacrocorax carbo 7 Roosting alongside west facing edge of inner dock
activity especially vocalisations. Details of the
prevailing weather conditions are summarized Grey Heron Ardea cinerea 1 Overflying travelling east
in Table A3.1. Great Crested Grebe Podiceps
15 Seen in docks
cristata
All birds seen and heard were recorded and
Shelduck Tadorna tadorna 5 Roosting alongside west facing edge of inner dock
their locations marked on a map. In addition
the numbers of individual birds of each Egyptian Goose Alopochen Pair on SS Robin to the north of the Millennium
2
species were recorded. These surveys focused aegyptiaca Mills building
on the entire Silvertown Quays Site and the Canada Goose Branta canadensis 6 Pairs on wharves around the Site on both visits
full survey results are accordingly described
Mute Swan Cygnus olor 1 Seen in docks
here.
Mallard Anas platyrhynchos 2 Pair seen in dock near Silo D
In total 32 bird species were recorded at the Pair observed feeding over site and perching on the
Peregrine Falco peregrinus 2
Site and in the surrounding docks during the Millennium Mills building.
February visits. Moorhen Gallinula chloropus 1 Observed in inner dock near Silo D
Species observed which are considered as Observed in inner dock near Silo D and Royal
Coot Fulica atra 1
Victoria Dock near SS Robin
high risk to aerodrome safety are summarised
in Table A3.2. Roosting in mixed flock on dockside to the east of
Herring Gull Larus argentatus 5
the Site.
Other small passerine species were Lesser Black-backed Gull Roosting in mixed flock on dockside to the east of
4
encountered, including grey wagtail, dunnock, L.fuscus the Site.
stonechat and great tit, although these are Roosting in mixed flock on dockside to the east of
not considered high risk species and are not Mew (Common) Gull L.canus 12
the Site.
considered further.
Black headed Gull Larus Roosting in mixed flock on dockside to the east of
30
ridibundus the Site. Frequent in open water of docks.
Feral Pigeon Columba livia 30 Present in Millennium Mills building and Silo D
Wood Pigeon Columba palumbus 20 Present in small parties across the Site
Present across the Site within vegetation and on
Magpie Pica pica 4
buildings
Present across the Site within vegetation and on
Carrion Crow Corvus corone 4
buildings
Table A3.2 High risk bird species observed in February overwintering bird surveys
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 381
A3.5 BIRD HAZARD MANAGEMENT PLAN
In understanding the potential for bird strike
hazards at the Site, a view has to be taken on
A3.5.1 POTENTIAL FOR A3.5.2 DESIGN This report should be read in conjunction
with the relevant landscape drawings, the
the likelihood of the proposed development ATTRACTION TO BIRDS CONSIDERATIONS references for these are listed below:
of providing nesting/roosting/loafing
• Masterplan with roof layout - 529-CTF-XX-
opportunities within the built structures, The surveys clearly indicate that the Site
Landscaping XX-DR-L-1004
enhancing the ecological value of the Site, is currently of high value for a number of
and increasing the potential for foraging high risk species. Of greatest note is the All areas of dense vegetation in the centre
on discarded food waste or through poorly of Phase 1 RMA Site will be lost as a • Roof plan - SQP1-CTF-1-LAN-DGA-LXX-
abundance of gulls and geese which tend to
maintained bins and waste management consequence of the proposed development. LAN112
favour the open areas of bare ground and
areas. These all have the potential to increase disturbed habitats to loaf, roost and nest.
the concentration of birds on site. Trees running along the southern Phase 1 RMA • R
oof plan Plot 5 - SQP1-CTF-5-LAN-DGA-
Boundary will also be lost. LXX-LAN152
The dense vegetation is favoured most by
An increase in bird activity of such a nature, the smaller passerine species which are not
near airports, has been associated with considered as significant nuisance to aircrafts Areas of the Site which are currently bare • R
oof plan Plot 6 - SQP1-CTF-6-LAN-DGA-
a perceived increase risk in potential bird at low numbers. ground, being favoured by species such as LXX-LAN162
strikes although the nature of bird activity, the Canada geese will become building or fall
species and the time of the year are all key Conservation objectives for the Site seek to under the footprint of road infrastructure/ • R
oof plan Plot 7 - SQP1-CTF-7-LAN-DGA-
aspects in determining the likelihood of these prioritise habitats for small passerine birds, public realm landscaping. LXX-LAN172
events. Concern is given to any development invertebrates and other species such as bats.
or proposal that may have the potential to This would include the discouragement of Consequently, through the very nature of the • R
oof plan Plot 8 - SQP1-CTF-8-LAN-DGA-
significantly increase bird activity within the larger gull and geese species currently found proposed scheme, the development will result LXX-LAN182
general proximity of the aerodromes. in abundance at the Site. in reduced opportunities for loafing, roosting
and nesting by high risk species. • P
ublic realm planting plan 1/2 SQP1-CTF-1-
Therefore, as discussed in detail below, the Designs could therefore stand to actively LAN-DGA-L01-LAN307
strategic approach employed for the proposed improve conditions at the Site in terms of However, the development proposals also
development has been to: flight safety, whilst still achieving ecological include extensive new planting across the • P
ublic realm planting plan 2/2 SQP1-CTF-X-
goals of improving general ecological value. Site. Primarily, the proposed landscaping LAN-DGA-L00-LAN308
• Assess the potential for birds to be includes:
attracted to the development;
Considerations which have bene embedded
• Living roofs in the form of extensive
within designs are discussed below.
• Design-out as far as practical the features biodiverse roofs and podium garden
that would enable birds to nest or loaf or intensive roofs;
be attracted to the Site in any way;
• Tree planting along streets and on podium
• Recommend a management and levels; and
monitoring regime to identify any problems
that might arise and measures to address • Rain gardens.
these if they do; and
• S
elect deterrents, anti-perching devices
and bird exclusion products that could be
used as necessary should bird strike risks
arise.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 383
A3.5.3 MANAGEMENT nuisance birds however, so bird control
through nest or egg removal is possible under
AND MONITORING certain licence conditions obtained from
Natural England for preserving air safety and
would be considered as part of the BHMP
Management schemes
where necessary.
The development includes large areas of
extensive and intensive green roofs (totalling Review of the Management Plan
>500sqm) and therefore the roof spaces will
The Bird Hazard Management Plan shall be
need to be monitored for bird activity.
subject to review to reflect changes in habitat
or populations of bird species. Should the
All of the roof areas will be accessible to
aerodrome(s) deem it necessary, a meeting
conduct foot inspections which will be carried
between London City Airport, the applicant
out regularly by an appointed member of the
and / or Newham Council will be convened at
facilities building team or site maintenance
the earliest opportunity to discuss and agree
staff for the lifetime of the development.
any changes which may be necessary.
The inspections will be weekly during bird
breeding season (the breeding seasons for
Inspection and site access
gulls typically runs from April to June) and at London City Airport or their nominated
regular intervals outside the breeding season representatives will be allowed access to the
dictated by levels of bird activity. These Site by prior arrangement, to evaluate the
inspections will take place to look for activity success of the Bird Hazard Management Plan,
on and around the building and will focus review records/documentation, and to assess
around the car parking areas, roof spaces, any remaining bird strike hazard.
ledges and service areas. Should these
inspections highlight unexpected bird activity Long term management
then suitable deterrent/scaring techniques will
This Bird Hazard Management Plan will
be implemented, as described in the following
remain enforceable by London City Airport
sections.
Limited, Newham Council, the UK Civil
Aviation Authority (CAA) or any successor to
A log of any bird activity recorded will be these bodies throughout the existence of the
kept from these inspections; an example of building. These obligations will be passed
which is contained in Section A3.8 on page to any subsequent owners/operators of the
389. The name of the person undertaking building and land.
the survey will be included with ultimate
responsibility for the log will rest with the
Building Manager (or another suitable person).
DEVICES • Spikes
Falcon decoy
Deterrents, anti-perching devices and Given the actual presence of a pair of
bird exclusion products are used to deter • Netting peregrines in the locality, the use of a
pigeons, gulls, corvids, and other birds from falcon decoy is not considered necessary.
Further information on these deterrents is The number of falcons is not predicted to
roosting and perching on specific areas of
given below. increase as a consequence of the proposals
buildings. Some of these products have a
wider application such as the protection of and therefore their continued presence only
agricultural land and even ponds or lakes, but
Bird trip wire stands to benefit risk through discouragement
the following are products that are designed Bird wire is a discreet, low-profile anti- of pigeons.
to be used to protect buildings and for the perching deterrent currently available. It is
control of urban birds. designed for ledges and areas where large Sonic devices
birds have been temporarily “resting”, and Bird deterrent sonic devices are occasionally
Deterrents such as decoy falcons are where a low visibility product is essential. used to scare nuisance birds by emitting an
products that act to scare or deter a bird from Bird wire typically consists of a nylon-coated ultrasonic, high pitched sound that causes
its roosting or perching place. Anti-roosting wire tensioned by springs between stainless disturbance to birds. These devices will be
products, such as anti-roosting spikes and steel posts, which when mounted, offers an avoided at Silvertown Quays owing to the
bird trip wire are designed to physically unstable landing area for large pest birds. potential impact upon local bat populations
prevent a bird from landing on ledges, recorded at the Site. In addition, the ultrasonic
guttering and other architectural features. Bird Bird spikes sound is typically audible to the human ear
exclusion products like nylon bird netting are Whilst spikes are not aesthetically pleasing and can be a particular nuisance to women
usually installed to physically prevent a bird consideration will be given to their use if and children within hearing range. This
from gaining access to an area rather than a necessary and these will be retrofitted at a deterrent is therefore not considered suitable
specific perch. suitable density or at suitable distances from for the Site.
each other to exclude the relevant species
All bird control products have problems should the initial deterrent measures and
associated with their use and installation and inbuilt design be ineffective.
one of the biggest disadvantages associated
with bird control products is that they fail to Netting
deal with the source of the problem.
In extreme circumstances, netting for the roof
However, in the instances where the above areas may be used and will deter bird landing
described monitoring regime has identified an with the netting being of a suitable gauge and
area within the proposed development where weight to exclude the target species. It will be
issues have arisen, then basic bird deterrent suspended at a suitable tension to ensure that
measures will be reviewed and installed as birds landing on the netting will not cause
necessary. sagging onto the roof. However, the netting
must not be too taut as this will allow birds
to land. The netting must also be inspected
on a regular basis to make sure it is in full
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 385
A3.6 CONCLUSIONS
This report was compiled with reference which was seemingly of high value for geese, Reference
to the proposed Phase 1 RMA of Silvertown gulls and waterfowl. Living roofs will be
AOA/CAA, Safeguarding of Aerodromes,
Quays and surveys of the Site where existing provided however these will replicate total
Advice Note 3 - Wildlife Hazards around
bird activity was noted. Guidance was in the area of Open Mosaic Habitat currently at site,
Aerodromes
AIA/CAA’s ‘Advice note 3: Wildlife Hazards’ was and being broken up into smaller areas will be
followed. less attractive to nuisance species like Canada
http://www.aoa.org.uk/wp-content/
geese.
uploads/2016/09/Advice-Note-3-Wildlife-
The report includes an assessment of the
Hazards-2016.pdf
baseline conditions and recorded levels of Overall there will be a loss in area of open
activity of birds at site and in the general vegetation and there will be no increase in
CAA, Wildlife hazard management at
vicinity. Furthermore, it assesses the potential open dock area.
aerodromes
for birds to be attracted to the Site either
in terms of naturalised features that are Nonetheless, proposals should monitor
https://publicapps.caa.co.uk/docs/33/CAP772_
introduced through the landscaping scheme any activity that occurs on site, particularly
Issue2.pdf
or through architectural detail in the design. associated with living roofs and areas of
landscaping.
The Site is vacant brownfield land and
currently affords numerous opportunities for Should there be an increase in activity
a range of high risk species. The proposals by nuisance species compared with pre-
will be designed with biodiversity in mind development conditions then a set of
however has a focus on low risk bird species management responses have been identified
and species of no risk such as invertebrates that include physical deterrents, anti-perching
and bats. Proposals are likely to inherently devices and exclusion products.
result in a reduced risk given the loss of
expansive areas of open and bare ground
Figure A3.3 Red list bird sightings Figure A3.5 Green list bird sightings
Green = 8th May, Red = 20th May, Blue = 29th June
Figure A3.4 Amber list bird sightings Figure A3.6 Distribution of wintering bird sightings Feb 2019
Red = 8th April, Orange = 8th May, Buff = 20th May, blue = 29th June
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 387
Fig 5. Distribution of wintering bird sightings Feb 2019.
*Notes on species present, pressure level (High = >30 Pigeons, gulls, corvids, starlings; Medium = 5-30 birds; Low = <5 birds; None =
zero birds), distance from site and behaviour (Sc = scavenging; P = prospecting; L = loafing; N = nesting). NB include details of inspections
where no hazardous birds were recorded.
*Notes on species present, pressure level (High = >30 Pigeons, gulls, corvids, starlings; Medium = 5-30 birds; Low = <5 birds; None = zero birds), distance
from site and behaviour (Sc = scavenging; P = prospecting; L = loafing; N = nesting). NB include details of inspections where no hazardous birds were
recorded.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 389
Appendix
A4
Design Code Compliance Schedule
A4.1 DESIGN CODE COMPLIANCE SCHEDULE
The Design Code comprises Chapters 1 and
3-12 (dated December 2014), and the Chapter
2 extract that was updated in January 2015.
1 Introduction
2 Layout
The fire brigade will require suitable access to the entire site, including all individual buildings and any basement areas. As the
2.1.4 individual buildings develop, it must be demonstrated that each building parcel meets the functional objectives of the Building P. 16
Regulations for fire service access and facilities
Inclusive Design
2.1.5 Footways should be level or gently sloping and accessible and safe for everyone to use with place to stop and rest P. 16
2.1.6 Footways should be free of clutter and provide ample space for general circulation P. 16
Materials and Design
2.1.7 Streets will have different materials assigned to different places depending on their character and use P. 16
2.1.8 All materials should be of high quality, durable and resilient and where possible be representative of the local dock character P. 16
The paving types used for vehicle and pedestrian routes should as far as possible be in accordance with the diagram to the right Refer to 'Hard landscape' chapter in Landscape Section 5 of 'Design and Access
2.1.9 and shall emphasize the character of the area, with due consideration given to the needs of cyclists, wheelchair users and those P. 16 Statement' (DAS) which explains how the proposed landscaping emphasise the
with pushchairs. character of the area.
Cycling Network
Cycling is encouraged in all parts of the site for amenity and commuting purposes, except for along the Diagonal which will be a
2.1.10 pedestrian only route. Strategic routes allowing integration into the wider network of cycle movement beyond the site should be in P. 17
accordance with the illustrative proposed cycle network diagram shown below
Proposed cycle networks should tie into the existing cycle network in the wider area, to create straightforward connections that
2.1.11 P. 17
encourage cycling.
To balance the needs of pedestrians and cyclists, street designs will seek ways of accommodating both users while minimising
2.1.12 conflict. This will be a low speed environment which means driving and cycling at a leisurely pace. When sharing the road, P. 17
drivers will keep to the speeds of cyclists and all vehicles giving priority to pedestrians.
It was agreed at the scoping stage (3 September 2019) that the Cycling Level of
Service (CLoS) assessment outlined in point ‘x’ in the Reserved Matters
The design of streets should respond to the London Cycling Design Standards or its successors. A Cycling Level of Service Specification (Annexe A of OPP) would no longer be necessary following a wider
2.1.13 (CLoS) assessment should be undertaken to establish the appropriate strategies to support the needs of cyclists within the P. 17 streetscape corridor review along North Woolwich Road being undertaken by
context of the site. LBN and Transport for London (refer to Section 4.8.1). This is likely to result in
improvements to cycle infrastructure along this corridor, thereby superseding the
requirement for a CLoS assessment as part of the Phase 1 RMA application.
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 393
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
A series of primary, secondary and tertiary vehicle routes shall be provided in accordance with the diagram shown on P. 18.
2.2.1 P. 18
Primary and secondary routes must be in accordance with Parameter Plan 05.
Tertiary and servicing routes may be provided in addition to those on Parameter Plan 05 to provide vehicular access to all
2.2.2 P. 18
development blocks
As noted in 2.1.10, cycling is allowed and encouraged on all vehicle routes within the site. All streets will be designed to provide a
2.2.3 good level of service for cyclists. This will be a low speed environment, which means driving and cycling at a leisurely pace, P. 18
drivers keeping to the speeds of cyclists and all vehicles giving priority to pedestrians.
Primary Roads
Proportions and Size
Primary Roads will have a minimum overall width of 18m and will have two-way vehicular traffic. When cyclists are required to
2.2.4 P. 19
share the road with motorised vehicles, carriageway widths will be designed to protect cyclists’ safety.
2.2.6 Inset parking and planting zones with a minimum of 2m width can be located on either side of the road P. 19
Low speed cycling should be encouraged alongside other road users. This will be a low speed environment, which means driving
2.2.8 P. 19
and cycling at a leisurely pace, drivers keeping to the speeds of cyclists and all vehicles giving priority to pedestrians.
All dwellings with ground floor habitable rooms and front doors accessed directly from the public realm shall have a privacy zone
2.2.9 P. 19
of 1-3m depth measured from the back of the pavement to the building line
Landscaping
2.2.10 Primary roads should be constructed with an engineered asphalt carriage way, bordered by a min. 200mm wide concrete kerb P. 19
Primary roads are characterized by formal tree planting. The species and
Primary roads should be characterised by formal tree planting of uniform species selection at regular planting distances to either
2.2.12 P. 19 ? planting distances are set out in the landscaping plan. In some instances these
side of the carriage way, with planting distances not exceeding 20m
distances exceed the 20m
2.2.13 Tree species shall be of a category that commonly grows taller than 15m P. 19
2.2.14 Tree planting zones should be defined by kerb and shall be graded to provide for rainwater harvesting P. 19
Secondary Roads
Proportions and Size
2.2.16 Inset parking and planting zones with a minimum of 2m width can be located on either side of the road P. 20
Low speed cycling should be encouraged alongside other road users. This will be a low speed environment, which means driving
2.2.17 P. 20
and cycling at a leisurely pace, drivers keeping to the speed of cyclists and all vehicles giving priority to pedestrians.
All dwellings with ground floor habitable rooms and front doors accessed directly from the public realm shall have a privacy zone
2.2.18 P. 20
of 1-3m depth measured from the back of the pavement to the building line
Landscaping
Wesley Avenue - Please refer to the proposed plans, sections and elevations
'SQP1-CTF-X-LAN-DGA-L00-LAN302' and 'SQP1-CTF-X-LAN-DGA-L00-
2.2.19 Secondary roads should be constructed using granite unit paving bordered by a min. 200mm wide flush kerb P. 20 ?
LAN303' and Section 5 'Landscape' in the DAS which explains the materials and
finishes for Wesley Avenue
Wesley Avenue - Please refer to the proposed plans, sections and elevations
'SQP1-CTF-X-LAN-DGA-L00-LAN302' and 'SQP1-CTF-X-LAN-DGA-L00-
2.2.20 Associated pedestrian footways should be constructed of granite unit paving in a contrasting finish P. 20 ?
LAN303' and Section 5 'Landscape' in the DAS which explains the materials and
finishes for Wesley Avenue
Secondary roads should be characterised by formal tree planting of uniform species selection at regular planting distances to
2.2.21 P. 20 ? No trees are proposed along Wesley Avenue
either side of the carriage way, with planting distances not exceeding 20m
2.2.22 Tree species shall be of a category that commonly grows taller than 15m P. 20 ? No trees are proposed along Wesley Avenue
2.2.23 Tree planting zones should be defined by kerb and shall be graded to provide for rainwater harvesting P. 20 ? No trees are proposed along Wesley Avenue
Tertiary Road
Proportions and Size
2.2.25 Inset parking and planting zones with a minimum of 2m width can be located on either side of the road P. 21
Low speed cycling should be encouraged alongside other road users. This will be a low speed environment, which means driving
2.2.26 P. 21
and cycling at a leisurely pace, drivers keeping to the speed of cyclists and all vehicles giving priority to pedestrians.
All dwellings with ground floor habitable rooms and front doors accessed directly from the public realm shall have a privacy zone
2.2.27 P. 21
of 1m depth measured from the back of the pavement to the building line
Tertiary roads may be "shared surface" streets with a continuous hard material across the full width and no change in level for
2.2.28 P. 21
kerbs
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 395
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
Landscaping
Shared streets and kerb-free areas should have tactile surfaces to segregate path routes and functions and act as a warning
2.2.30 P. 21
device for people with sight loss and learning difficulties; all routes will be designed to be safe and inclusive for all pedestrians.
Tertiary roads shared surface should be constructed using different tones of paving material to informally demarcate (traffic)
2.2.31 P. 21
zones
2.2.32 Planting, trees and furniture elements further assist in delineation of traffic zones P. 21
Tertiary routes should be characterised by informal tree planting where space is available. Tree positions shall be min. 3m from
2.2.33 P. 21
building facades
2.2.34 Tree species selection shall be in keeping with available space between buildings and as required for traffic to pass P. 21
2.2.35 Tree planting zones should be graded to provide for rainwater harvesting P. 21
Pedestrian routes should be safe pedestrian zones, without traffic and with step-free, level or gently-sloping circulation routes.
2.3.3 P. 22
Accessible routes (Ars) are to be step-free with gradients gentler than 1:20
Details of the delivery and servicing plan will be submitted under Condition B7 in
2.3.4 Servicing routes may only take place within primary pedestrian routes if timing is managed and limited to "out of hours" periods P. 22
the future
Landscaping
Innovative strategies should be applied to delineate through routes through public realm areas and zones as necessary including
2.3.5 P. 22
the use of (tree) planting and furniture elements
Seating should be provided every 50m on pedestrian routes alongside primary and secondary roads, bus routes and other high
2.3.6 P. 22
pedestrian flow routes
2.3.7 Paths within public open spaces and footways should have a smooth, firm and slip resistant surface P. 22
2.3.8 Recreational routes and park pathways may be constructed using self-binding crushed (Breedon) gravel P. 22
2.3.9 Pedestrian routes must include public lighting and CCTV for security and should be directly overlooked for natural surveillance P. 22
As specified in the Development Specification and Framework, the former dock will be reconfigured and retained as a central
Outside Phase 1
2.4.1 water feature. The Dock/OS1.1 on Parameter Plan 06 should have no more than 50% of its area in-filled by buildings or other P. 23
RMA
structures.
Outside Phase 1
2.4.2 A dam/bridge structure will separate the Royal Victoria Dock from the reconfigured dock area within the site. P. 23
RMA
The inclusion of water encompassed by dock walls and quays in the Silvertown Quays development shall reflect and be
2.4.3 P. 23
reminiscent of the site’s dockland heritage, as set out in section 5.3.
2.4.4 Further guidance on the design of the water bodies on site is set out in section 5.3 (Water). P. 23
Development in The Dock should be legible as freestanding object buildings that positively address all sides and should allow Outside Phase 1
2.4.5 P. 24
glimpsed views towards Royal Victoria Dock and Excel. RMA
Outside Phase 1
2.4.6 Development in The Dock should be to a lower scale than the surrounding buildings around the dock edge. P. 24
RMA
Outside Phase 1
2.4.7 Buildings in the Pontoon Dock should be perceived as freestanding floating objects. P. 24
RMA
There should be a publicly accessible pedestrian route across the Dock, as well as along the eastern and western sides, as set Outside Phase 1
2.4.8 P. 25
out on Parameter Plan 05. RMA
The majority of the top surface of the existing dock wall should be visible in the public realm and buildings may be set back at
2.4.10 P. 25
ground level to achieve this.
2.4.11 Landscape design should reflect the historic dock context as set out in section 8.2 (The Dock). P. 25
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 397
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
Key views have been considered and discussed during pre-Apps and DRPs.
2.5.1 The masterplan should be developed with consideration to key views set out at P. 26 P. 26 Please refer to Section 9.2.4 'Key Vistas' Chapter 9 ' OPP Compliance ' in the
DAS.
Outside Phase 1
2.5.2 The alignment of The Diagonal should include glimpsed views of Millennium Mills as shown in View 1 P. 26
RMA
Key views have been considered and discussed during pre-Apps and DRPs.
2.5.3 Millennium Mills should be visible from across the Dock. This can be over the top of buildings as indicated in View 2 P. 26 Please refer to Section 9.2.4 'Key Vistas' Chapter 9 ' OPP Compliance ' in the
DAS.
The alignments of streets and built form should allow direct glimpsed views of Silo D from the north, east and south east. This
2.5.4 P. 27
can be over the top of buildings so long as the majority of the body of the silo is visible, as indicated on the images below
Primary frontages, defined as frontages along the primary pedestrian routes (as defined on Parameter Plan 05) and the other
For Phase 1 RMA active frontages please refer to Section 9.2.6 'Building
2.6.1 routes indicated on the plan on P. 28, should be predominantly active and 80% or more of the ground floor building frontages P. 28 ?
frontage' in Chapter 9 'OPP Compliance ' in the DAS
should comprise of shop/brand frontages, office lobbies or communal entrances to residential buildings
Secondary frontages, as identified on the plan on P. 28, should positively address the public realm and at least 50% of the ground
For Phase 1 RMA active frontages please refer to Section 9.2.6 'Building
2.6.2 floor building frontages should comprise of shop/brand frontages, office lobbies or entrances (communal or individual) to P. 28 ?
frontage' in Chapter 9 'OPP Compliance ' in the DAS
residential buildings
2.6.4 Building frontage must be in accordance with the site wide Access and Appearance guidance in sections 4.0 and 6.0 P. 28
2.7.2 Buildings should engage with the public at ground floor; frontages should be mainly glazed and blank elevations avoided P. 29
2.7.3 Lobbies should be designed as active frontages with a direct relationship to the adjacent public realm P. 29
2.7.4 Building frontages can be individually expressed but should be aligned with the street and emphasise street making P. 29
2.7.5 The ground and first floor may be designed as flexible space for showrooms, display and curated experiences P. 29
Buildings are to have an uncluttered and simple roof profile with all plant equipment concealed within the main silhouette of the
2.7.6 P. 29
building
2.7.7 Signage is integral to this building typology and should be sympathetic to the building and streetscape P. 29
Commercial and public buildings will be designed to the appropriate Building Regulation Standards including Approved
2.7.8 P. 29
Documents Part M and K
Offices/Headquarters
Outside Phase 1
2.7.9 Office buildings should mainly be located in the southern part of the site, near the Pontoon Dock DLR station P. 30
RMA
Outside Phase 1
2.7.10 Buildings should engage with the public at ground floor; frontages should be mainly glazed and blank elevations avoided P. 30
RMA
Outside Phase 1
2.7.11 Lobbies should be designed as active frontages with a direct relationship to the adjacent public realm P. 30
RMA
Buildings are to have an uncluttered and simple roof profile with all plant equipment concealed within the main silhouette of the Outside Phase 1
2.7.12 P. 30
building RMA
Commercial and public buildings will be designed to the appropriate Building Regulation Standards including Approved Outside Phase 1
2.7.13 P. 30
Documents Part M and K RMA
Residential
2.7.14 Residential buildings should be mainly located in Silo D district and eastern residential neighbourhood P. 31
Homes are designed in line wity the Housing SPG (November 2012), with the
2.7.15 All new homes shall be designed in line with the London Housing Design Guide P. 31 exception of internal space standards which are to comply with 2016 SPG
(NDSS)
All new homes shall be designed to Lifetime Homes standards with 10% to Wheelchair Housing standards or demonstrate why Lifetime Homes have been deleted. The Phase 1 RMA has been designed to
2.7.16 P. 31 ?
the specific characteristics of a particular building or part of the site mean this is not possible comply with M4(2) and M4(3)
As set out in the London Housing Design Guide, the number of dwellings accessed from a single core should not exceed eight Plot 7 in one core has 9 units per level at floors 2 & 3 only. This was discussed
2.7.17 P. 31 ?
per floor in Pre-app 5 as massing better encloses the courtyard.
2.7.18 Dual aspect and through living units should be integrated into building designs where possible P. 31
Plot 1: 52% approx. Plot 6: 51% approx. However, across Phase 1 RMA, there
2.7.20 Single aspect units should not exceed 50% in any block P. 31 ? are no single aspect north facing units and the total number of single aspect units
is below 50%.
2.7.22 All units should meet or exceed the size in the London Plan P. 31
2.7.24 Breaks in blocks to provide views should also serve to improve sunlight penetration to courtyards, as set out in section 3.4 P. 31
2.7.25 Breaks in blocks must not create uncertainty about the status of private and public realm P. 31
Parking
Refer to Transport Statement included in Phase 1 RMA. Car parking levels are
2.7.26 Car parking to be provided on plot to a ratio of (on average) 0.5 spaces per unit as set out in the DSF P. 31 ? proposed below the maximum levels set out in Condition T2 in compliance with
the emerging London Plan Policy
2.7.27 Cycle parking standards should be provided in accordance with the DSF P. 31
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 399
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
Landscape
Private amenity space for residential units may be provided by private gardens at podium/ground level, balconies, terraces or
2.7.28 P. 32
winter gardens. Refer to section 5.5
Any residential ground floor use should have a defensible space to create separation between residences and the public footway
2.7.30 P. 32 ? Plot 7 on Canalside: Raised sill condition for privacy
and trafficked route beyond
Pavilions
Pavilions should primarily be located along the street running between the Diagonal and the Theatre Plaza and within the Dock Outside Phase 1
2.7.31 P. 32
area RMA
Outside Phase 1
2.7.32 There should be pedestrian access around all sides of the pavilion with a minimum width of 2m to the adjacent building/pavilion P. 32
RMA
Outside Phase 1
2.7.33 Pavilions should be designed with predominantly active frontages P. 32
RMA
Outside Phase 1
2.7.34 The massing of pavilion buildings should be designed to contrast to the larger volumes of the adjacent building typologies P. 32
RMA
Pavilions can be placed in the public realm areas defined on Parameter Plan 06 but need to respect, and not obscure, the views Outside Phase 1
2.7.35 P. 32
and principles set out in section 2.5 and 2.6 RMA
Commercial and public buildings will be designed to the appropriate Building Regulation Standards including Approved Outside Phase 1
2.7.36 P. 32
Documents Part M and K RMA
Dock wall to be kept at existing levels. Please refer to 'Flood Risk Statement of
2.8.1 All dock walls (new and existing walls to be retained) shall have a minimum level of at least +5.18m AOD P. 33 ?
Conformity'
2.8.2 All rooms that may be considered "sleeping accommodation" must have a finished floor level of at least +5.5m AOD P. 33
Plot 5: Lower Ground Floor maisonettes located below 5.5m AOD. All sleeping
2.8.3 It is recommended that all other residential floor uses should be located above +5.5m AOD if possible P. 33 ?
accommodation on upper floor above 5.5m AOD
2.8.4 Floor uses below +5.5m AOD should be prioritised for the most flooding insensitive uses, such as car parking P. 33
2.8.5 Flood resilient fixtures and fittings should be installed on floors below +5.5m AOD, this should include raising electrical fixtures P. 33
Plots 7 and 8 include some non-residential uses below +5.5m AOD that do not
have internal stairs to upper levels. However there is direct level egress from
these uses to the public realm. In the highly unlikely event of the River Thames
2.8.6 All floors below +5.5m AOD shall have direct access to stairwells linking to floors above +5.5m AOD P. 33 ? being breached due to failure of flood defences happening concurrently with a
1:200 year event then there would be equivalent time for people to vacate these
units. A Flood Evacuation Plan will be submitted under Condition F4 of the OPP
addressing this issue. There is no sleeping accommodation below +5.5m AOD.
A Flood Management Plan for the development shall be prepared in collaboration with London Borough of Newham (LBN) and
2.8.7 P. 33 To be submitted under condition F4
the Environment Agency (EA) and any requirements arising incorporated into the design of the development
3.1 Townscape
Each new block should respect the design and scale of the neighbouring buildings, emphasising the creation of attractive
3.1.1 P. 36
streetscapes
3.2.1 Buildings shall be in accordance with the maximum development heights set out on Parameter Plan 07 P. 36
To create consistent, formal edges and coherent building frontages along key public open spaces and along streets through the
3.2.2 site, buildings shall be in accordance with the shoulder heights and prevailing heights set out in the Development Zone sections P. 36
of the document
The massing of residential buildings should be controlled to allow good light penetration to all units and minimise any
3.4.1 overshadowing. Building designs should promote sunlight in courtyard spaces. Light and views for the individual residential units P. 37 Refer to Sunlight/daylight assessment
and communal amenity space should be maximised.
Residential blocks can be broken up in different distinct volumes to provide views through the blocks and to improve sunlight
3.4.2 penetration to courtyard spaces. Breaks in the building line must not compromise the creation of strong and consistent street P. 37
lined
Habitable spaces within apartments should as far as possible be located where the sunlight and daylight assessment has shown
3.4.3 P. 37
results which allows to provide good daylight
3.5 Wind
Any negative impact on the microclimate of existing surrounding buildings and public realm should be mitigated having regard to
3.5.1 P. 37 Refer to Micro-climate/Wind report
Lawson criteria for wind comfort and safety
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 401
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
4 Access
4.1 Entrances
Communal Entrances (Commercial and Residential)
The location and articulation of entrances, both residential and commercial, should be considered in order to create a positive
4.1.1 P. 40
sense of destination and address-making across the site
All primary access to dwellings shall be directly from the street. Residential communal core entrances must be accessed directly
4.1.2 P. 40
from the public realm and not via, for example, a podium or courtyard space
Lifetime Homes have been deleted. The Phase 1 RMA has been designed to
4.1.3 Entrances must provide adequate weather protection to meet Lifetime Homes guidance P. 40 ?
comply with M4(2) and M4(3)
4.1.4 The appearance of entrances should be in accordance with the guidance in section 6.1 P. 40
4.1.9 The appearance of individual street level entrances should be in accordance with the guidance in section 6.1 P. 40
Refer to Transport Statement included in Phase 1 RMA. Car parking levels are
4.2.1 Car parking should be provided in accordance with the DSF P. 41 ? proposed below the maximum levels set out in Condition T2 in compliance with
the emerging London Plan Policy
Accessible car parking spaces should be provided in accordance with the Local Authority and GLA requirements. Blue badge Refer to Transport Statement included in Phase 1 RMA. Car parking levels are
4.2.2 bays should be provided to BDS8300:2009 ratios in public and staff car parks and 1:1 for wheelchair accessible/adaptable P. 41 proposed below the maximum levels set out in Condition T2 in compliance with
homes. High top vehicle conversions should be accommodated in basement car parks or on-street the emerging London Plan Policy
The intention is that the car park entrances will be recessed to comply with the
Design Code but this is subject to agreement with the ‘Designing Out Crime
4.2.2 Car park entrances should be legible but recessive in the elevational design of the building frontage in which they are located P. 41
Officer’ (DOCO) who will assess ‘Secured By Design’ (SBD) New Homes 2019
certification.
Entrances to car parks beneath buildings, whether to basements or at-grade podium areas, should be carefully integrated with
4.2.3 P. 41
building designs to minimise their potentially negative impacts on streets and public realm for residents and visitors alike
Car park entrances should be located to minimise through traffic on predominantly residential streets and to minimise
4.2.4 P. 41
interference with public open spaces
4.2.5 As set out in section 2.7, ground floors should be designed to wrap car parks with other uses P. 41
4.2.6 Car park entrances shall be enclosed with louvered grilles or gates to minimise inward views when closed P. 41
Code for Sustainable Homes has been deleted. The Phase 1 RMA has been
4.2.7 Access to car park and refused areas must be in accordance with Code for Sustainable Homes standards P. 41
designed to comply with LBN HQM Level 3
4.3 Servicing
Servicing from frontages onto public open spaces and key pedestrian routes (as defined on Parameter Plan 05) should be
4.3.1 P. 42
avoided
Service entrances should be broken up with active uses which can include entrances to uses at upper levels and food/beverage
4.3.2 P. 42
uses, predominantly at corners
4.4.1 Cycle parking provision shall be in accordance with the standards set in the DSF P. 42
In plots 2 and 3, the cycle parking has been located at first floor with provision for
Bicycle parking should be designed, either at entrance level or within podium/basement, so that it is visible but unobtrusive.
4.4.2 P. 42 ? stairs and lift access direct from separate entrances.
Parking should be designed and located to be easily accessible for users
Plot 5: Cycle store located in the rear garden by access through gate
Individual or communal cycle storage outside the home shall be secure, sheltered and adequately lit, with convenient access to
4.4.3 P. 42
the street
4.4.4 As set out in section 2.7, cycle parking entrances and openings should be minimised P. 42
Drop-off/pick-up points for taxis, Dial-a-Ride and community transport minibuses will be located at key points on the site within
4.5.1 P. 43
50m of all public building entrances and key public facilities
Refuse store design should be considered within the context of a refuse collection strategy to determine suitable locations and
4.6.1 P. 43
management requirements etc
Refuse stores and substations are located in the most discreet locations
4.6.2 The location of refuse stores and substations should avoid primary building frontages P. 43 ?
possible.
4.6.3 As set out in section 2.7, refuse storage entrances/openings at street level should be minimised P. 43
4.6.4 Residential waste stores should be sized for weekly refuse collections and fortnightly collections of recycled waste P. 43
4.6.5 Bins within these waste stores should be no more than 10m from the vehicle collection point P. 43
The design of all waste storage, collection and transport provisions need to be specifically assessed to avoid attractions of birds
4.6.6 P. 43
either directly (food scraps) or indirectly (vermin)
4.6.8 Refuse store and substation frontages shall be in accordance with the guidance defined in Appearance, section 6 P. 43
To maximise access to all parts of the development, its facilities and services for all future residents, visitors and members of
P. 44
staff in the development;
To meet local, regional and national access and inclusive design policies; P. 44
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 403
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
To ensure that appropriate access standards are met at the outset and as part of mainstream, inclusive design wherever
P. 44
possible;
To design inclusively, which means designing beyond the minimum requirements of the Building Regulations Part M to ensure
P. 44
that all people, regardless of age, sex or ability can use and enjoy the built environment;
To address the anticipated, substantial increase of older people in proportion to the working-age population in the near future and
P. 44
their needs;
Outside Phase 1
To meet the aims of the Equality Act, where applicable; P. 44
RMA
To follow design guidance given in relevant British Standards and other currently published good practice guidance about
P. 44
meeting the needs of disabled people;
To use the Guidance for Lifetime Neighbourhoods and Lifetime Homes standards as a key reference for the project, ensuring that
Lifetime Homes have been deleted. The Phase 1 RMA has been designed to
physical barriers to access for all people, including older and disabled people and children are avoided, providing a welcoming P. 44 ?
comply with M4(2) and M4(3)
and comfortable environment that serves its users rather than hindering them.
The standards
The Phase 1 RMA has been designed to comply with the Housing
Supplementary Planning Guidance November 2012, with the exception of
Housing Supplementary Planning Guidance, London Plan 2011 Implementation Framework, Mayor of London, November 2012; P. 45 ? residential internal space standards which comply with Housing SPG 2016
(consistent with the nationally described space standards) and the external
amenity standards (refer to 5.5.2).
The Building Regulations 2010, Access to and Use of Buildings, Approved Document M (2004 edition incorporating 2010 and
P. 45 ? The Phase 1 RMA is being designed in relation to Part M 2016
2013 amendments), HMSO, 2013;
The Building Regulations 2010, Fire safety, Volume 1 - Dwelling houses, Approved Document B (2006 edition incorporating 2010 The Phase 1 RMA has been designed to comply with the 2010 Regs (2019 as
P. 45
and 2013 amendments), HMSO, 2013; amended)
The Building Regulations 2010, Fire safety, Volume 2 - Buildings other than Dwelling houses, Approved Document B (2006 The Phase 1 RMA has been designed to comply with the 2010 Regs (2019 as
P. 45
edition incorporating 2007, 2010 and 2013 amendments) HMSO, 2013; amended)
The Building Regulations 2010, Protection from falling, collision and impact, Approved Document K (1998 edition incorporating
The Phase 1 RMA has been designed to comply with the 2010 Regs (2019 as
2000, 2010 and 2013 amendments), HMSO, P. 45
amended)
2013;
British Standard 8300:2009 (Amended 2010) Design of Buildings and their Approaches to Meet the Needs of Disabled People -
P. 45 The Phase 1 RMA has been designed to comply with BS8300:2018
Code of Practice, British Standards Institution, 2010;
British Standard 9999:2008 Code of Practice for Fire Safety in the Design, Management and use of Buildings, British Standards The Phase 1 RMA has been designed to comply with the 2010 Regs (2019 as
P. 45
Institution, 2008; amended))
The Phase 1 RMA complies with the relevant Conditions attached to the OPP,
Core Strategy, London Borough of Newham, January 2012; P. 45
which were based on the Core Strategy 2012
The Phase 1 RMA complies with the relevant Conditions attached to the OPP,
LB Newham Housing Policies SP3, H1, H2, H3, J3, INF8; P. 45
which were based on the Core Strategy 2012
5 Landscape
Play space provisions should be provided in accordance with the DSF. This play space will include
- Doorstep play space for children under 5 within 100m of dwellings (residences with private/semi-private gardens are excluded
from the requirement)
5.1.1 P. 48
- Local play space for children aged 5-11 within 400m of dwellings
- Neighbourhood and youth play space for children aged 12+ within 800m of dwellings
- Open space that would be playable for children of all ages and their families
The quantum of provision will be in accordance with the Mayor's SPG on Play space, amounting to a total of 10 sqm per child
5.1.2 P. 48
(the number of children being a factor of the number, size and type of residential dwellings that will come forward)
Small playable space to be provided within residential courtyards where necessary to complement the play spaces in the public
5.1.3 P. 48
realm
Public realm areas may include "playable space" providing settings and elements as play incentives rather than any particular
5.1.4 P. 48
designated "playground" with prescriptive equipment
Playable space shall be non-prescriptive about usage by age groups and will aim to invite, encourage and challenge the ability
5.1.5 P. 48
level of all target ranges
5.1.6 Play opportunities shall cate for children of all abilities, however dedicated "disabled play-equipment" shall be avoided P. 48
Areas where children may play shall have surface treatment to accommodate anticipated usage e.g. grass for fields and low use,
5.1.7 P. 48
bark or grit in medium usage areas, wet-pour (rubber or asphalt) for wheeled and high intensity uses
5.1.9 Unnecessary segregation of play space from the rest of the public realm, through railing etc, should be avoided P. 48
5.2 Biodiversity
75% of all species targeted or selected shall be native to the London region. Should non-native species play a part in the
5.2.1 P. 49
ecological design their role or benefit shall be explained
A long term biodiversity management strategy shall be submitted to ensure habitats remain functional or to outline how habitats
5.2.2 P. 49
may evolve
Multi-purpose, recreation and amenity grassland, including lawns and fields, shall be species rich to increase soil and plant
5.2.3 P. 49
diversity to attract invertebrates
Large shade trees shall be provided in appropriate positions (parks, squares, streets) to support and sustain micro-climatic
5.2.5 conditions, in particular in those public spaces which are likely to be used for congregation of large numbers of people during the P. 49
summer months
5.2.6 SUDS features including swales and soakage zones shall be integrated in the public realm design where possible P. 49
Soakage zones shall be designed appropriately including accepting primary run-off and holding capacity, filled with permeable
5.2.7 soils, able to withstand occasional (storm water) flooding, designed to drain between planting zones and street tree pits and with P. 49
conventional overflow provisions in extended or excessive rain fall conditions
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 405
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
5.2.10 A number of green/brown roof typologies should be used to create a diversity/mosaic of different habitat types P. 50
All green and brown roof areas should include structural opportunities for wildlife, such as invertebrate, bird and bat boxes, as
5.2.11 P. 50
appropriate
5.2.13 Roof gardens shall include features to encourage wildlife including environmental conditions and species variety P. 50
5.2.14 Substrate depths shall be varied in order to allow for differentiation of habitats for invertebrates P. 50
Substrates shall not be less than 100mm to provide adequate water holding capacity to maintain vegetation through summer, to
5.2.15 P. 50
provide evaporative cooling and insulation
Green/brown roofs need to be designed in detail to address restrictions around aircraft movement and prevention of attraction of
5.2.16 P. 50
groups of larger bird species
The advice of ecologists with experience in biodiversity and green roof design shall be sought in the preparation of detailed
5.2.17 P. 50
design
5.3 Water
The inclusion of water encompassed by dock walls and quays in the Silvertown Quays development shall reflect and be
5.3.1 P. 51
reminiscent of the site’s docklands heritage.
Proposed areas of water shall be interconnected to allow for uninterrupted water flows for optimal water quality and allowing
5.3.2 P. 51
fauna migration throughout the system.
Silo D and the surrounding open space and finger dock has been designed as an
5.3.4 All quays shall be fitted with appropriate balustrades or fall protection. P. 51 ? integrated area. They are integrated as a singular element of the public realm.
Balustrades are not provided but fall protection is provided via street furniture
5.3.5 For ecological management and diversity water should generally be 1.8m deep, with the option to make certain areas shallower. P. 51
5.3.6 To help moderate water temperatures in summer and winter some areas should be deeper (3-4m). P. 51
5.3.7 The detailed design of the water areas should maximise the ecological benefit. P. 51
The use of culverts and pipes (to connect bodies of water) shall be avoided as they form physical and behavioural barriers.
5.3.8 P. 51
Ecological connectivity shall be achieved by the inclusion of road bridges over water.
Dock wall
Dock wall to be kept at existing levels. Please refer to 'Flood Risk Statement of
5.3.9 All dock walls (new and existing walls to be retained) shall have a minimum level of at least +5.18m AOD. P. 51 ?
Conformity'
Dock walls will have a maintenance and repair strategy that will achieve an
5.3.10 The design life of all dock walls (new and existing walls to be retained) from the time of development shall be 120 years. P. 51
operational life of 120 years.
5.3.11 New lengths of dock wall shall achieve modern stability criteria and be designed according to contemporary standards. P. 51
A clear access strip shall be provided around the entire perimeter of dock wall that is sufficient to adequately maintain the walls All buildings are located over 5m from dock edges to allow for maintenance,
5.3.12 (e.g. allow access for plant) for the design life of the proposed development (120 years). This access strip must be 1m wide P. 51 however removable street furniture is located within 1m (which do not preclude
(measured from the quay edge) as a minimum. A preferred minimum of 5m is strongly recommended. sufficient access to adequately maintain the walls)
Bridges
5.3.13 Bridges should have projecting edges to emphasise the connection between the waterbodies on either side P. 51
5.4.1 The planting plan should be kept simple to create a strong image and enforce identity P. 52
The species selection needs to meet the constraints as imposed by airport safety requirements; the amount, compositions and
5.4.2 density of trees needs to be assessed with regard to air safety. The species will be of domestic and exotic origin and shall not be P. 52
a food source for bird species
Street Trees
The use of semi advanced stock is recommended along the main streets as these are more robust and may provide more
5.4.3 P. 52
substantial initial impact
5.4.4 The use of trees should underpin the function, importance or hierarchy of roads in the urban structure P. 52
Species selection (appearance and size), planting frequency (density, light/shade) and placement within the cross sectional
5.4.5 P. 52
context (edge or median planting), should be made to add to and enforce identity
Trees in Parks
5.4.6 Parks should where possible be planted with advanced or semi advanced specimens P. 52
5.4.7 Trees in parks should be planted either as individual feature specimens of in formal or informal groups P. 52
Trees on Roofs
Trees to be used on podium and roof terraces shall be smaller and shall be pre-grown in containers or otherwise need to be able
5.4.9 to withstand the wind loads of roof level development. Those trees shall be positioned on podiums or in an artificial planting P. 52
environment will be supplied with a minimum of 15/20m cubed soil/growing medium
Grass
All grass used should have a rich and thick green quality, make reference to the family of London City parks and use high quality
5.4.10 P. 52
English grass
5.4.11 To avoid bird attraction, any grass species to be used is to be supplied as turf P. 52
5.5.1 Private amenity space may be provided by private gardens at podium/ground level, balconies, terraces or winter gardens P. 53
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 407
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
Please refer to Section 9.2.2 'Private amenity space' Chapter 9 ' OPP
Compliance ' in the DAS.
Internalised amenity: TSP have discussed with LBN that internalised amenity will
be provided to some homes where external space would be compromised by
context (with additional space sized to meet min area requirements of the
5.5.2 Private amenity space should be provided in accordance with the London Housing SPG P. 53 ? National Space Standards)
Where external amenity is provided:
- 1B over provided (6sqm)
- 2B3P compliant (6sqm)
- 2B4P non-compliant (6sqm)
- 3B compliant (size varies)
Opportunities shall be identified to introduce public art into the public realm in order to highlight and reference the past, present
5.6.1 P. 53 Not applicable
and future of a particular context
Even though most constructed elements lend themselves as a canvas or object for incorporation of artistic expression, public art
5.6.2 P. 53 Not applicable
shall be integrated into the integral elements of the public realm as a whole rather than feature as "add-ons"
5.6.3 Public art implementation should be rich, plentiful and innovative P. 53 Not applicable
6 Appearance
6.1 Frontages
6.1.1 Frontages (primary, secondary and other frontages) should be located in accordance with the guidelines in section 2.7 P. 56
All building frontages facing onto the public open spaces shall:
- Positively address the open spaces they define by including active frontages, frequent building entrances and windows and
6.1.2 balconies to enhance the natural surveillance of the public realm P. 56
- Be predominantly made up by active ground floor frontages
- Generally not include car parking entrances and vents and service and access doors
As set out in section 2.7, frontages that are not defined as primary or secondary active frontages should be designed to feel part
For Phase 1 RMA active frontages please refer to Section 9.2.6 'Building
6.1.3 of the building and not more than 25% of the ground floor frontage on each individual street should be taken up with refuse, car P. 56 ?
frontage' in Chapter 9 'OPP Compliance ' in the DAS
parking entrances, service entrances or cycle parking storage
All buildings and public realm design should aim to create safe and active streets with all buildings positively addressing the
6.1.4 P. 56
public realm
6.1.5 Blind facades at the end of building blocks are to be avoided and corner buildings should positively address all streets P. 56
Residential Use
Duplex homes at the base of buildings should as far as possible accommodate at least one habitable room or kitchen, at ground
6.1.7 P. 56
level overlooking the street
Entrances
6.1.9 Entrances should be located and designed in accordance with the guidance in section 4.1 (Access - entrances) P. 57
Communal entrances should be expressed in the articulation of elevations, for instance with double-height ordering, strongly
6.1.10 P. 57
legible canopies, signage, lighting or by their position adjacent to courtyard entrances
Individual dwelling entrances at street level provide an important expression of domesticity and subdivision of larger building
6.1.11 P. 57
form. Private front entrances should create rhythm within street frontages and create a positive sense of address
Individual street level entrances should provide a positive sense of address, particularly where single dwellings are located in
6.1.12 P. 57
buildings with larger numbers of apartment at upper floors
Residential entrances should balance legibility and a welcoming sense of arrival with sufficient privacy in relation to ground floor
6.1.13 P. 57
habitable rooms
The rooftop should be treated as the fifth elevation and the design should integrate plant and other rooftop equipment into the
6.2.1 P. 58
overall design concept
Buildings are to have an uncluttered and simple roof profile with all plant equipment concealed within the main silhouette of the
6.2.2 P. 58
building
Where overlooked from neighbouring buildings, plant equipment should be housed within solid or perforated roof enclosures that
6.2.3 P. 58
are designed to screen equipment or in other ways integrated into the overall building design
6.2.4 All plant and machinery should be accessible for easy maintenance P. 58
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 409
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
Signage on rooftops is permitted but should be sympathetic to the building and view from adjacent, taller buildings should be
6.2.5A P. 59
considered
Terraces and green roofs are encouraged, as set out in section 5.5, and can play a valuable part as amenity space for occupiers
6.2.5B P. 59
and visitors as well as forming valuable habitats for wildlife. Refer to section 5.2 for guidance on green and brown roods
Any frontage allocated for servicing or plant equipment should be designed to minimise negative effects on the public realm.
6.3.1 P. 60
Where ventilation grilles are unavoidable, they should be limited in extent and integrated into the architecture of the buildings
Refuse store and substation frontages should be integrated within the broader elevational treatment of the buildings in which they
6.4.1 P. 60
are located
6.4.2 Materials and fixings should be suitably robust to withstand repeated heavy treatment by refuse operatives and residents P. 60
6.4.3 Refuse stores must be visually screened from the surrounding streetscape P. 60
Refuse stores and substations could have negative impacts and should therefore by carefully integrated with the designs of
6.4.4 P. 60
buildings
6.4.5 The extend of their frontages shall be in accordance with section 2.7 P. 60
Entrances to service areas within buildings should be carefully integrated with building designs and shall be enclosed with
6.5.1 P. 61
louvered grilles or gates to minimise inward views when closed
Off-street parking above ground level should avoid fronting directly onto the public realm, and be set back behind other permitted
6.6.1 uses. Openings into the car park are only permitted for vehicular access and ventilation, subject to codes on Appearance in P. 61
section 6
Where exposed edges are appropriate - for instance breaks in blocks to provide views and to improve sunlight penetration to
6.6.2 P. 61
courtyards - the podium edge must be carefully designed to minimise negative impacts and help define the street edges
6.7 Balconies
Balconies may be designed as projecting, recessed or semi-recessed, but should be fully integrated within the compassion of the
6.7.1 P. 62
building and the architectural detail of the facades
6.7.2 Balconies should not have open surfaces that allow water to drip through on those below P. 62
The provision of solar shading devices on building facades is permitted but should be fully integrated within the composition of
6.8.1 P. 62
the building and the architectural detail of the facades
6.9 Lighting
Provision of lighting within public realm should enhance qualities of landscape, adding legibility and variety to reinforce design
6.9.1 P. 63
strategies of proposals
Specification of public realm lighting locations and fittings shall minimise spill into neighbouring dwellings and towards sensitive
6.9.3 P. 63
ecological receptors
6.9.4 Pole top and bollard lighting shall be used for paths and program elements P. 63
6.9.5 Feature up-lighting shall be considered for the night-time display of formal tree planting P. 63
6.9.6 LED and fibre-optic lighting may be used on and in surfaces to illuminate pavements at night P. 63
The main public spaces shall be fitted with purposely designed lights with minimal use of poles and posts. The public realm
6.9.7 should be kept free of obstacles and lights and illumination should be wall mounted or attached to elements, structures and P. 63
facades as much as possible
6.9.8 Provision of street lighting and public realm lighting should meet adoptability and Secure by Design standards P. 63
6.9.9. Provision of lighting within and on buildings should meet Secure by Design standards and other design standards P. 63
Wherever on site outdoor lighting is proposed as part of a development it should be energy efficient, minimising light lost to the
6.9.10 P. 63
sky and, as far as feasible, solar powered
6.9.11 Light fittings will be positioned so that the lights do not interfere with the London City Airport traffic P. 63
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 411
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
7 Sustainability
Code for Sustainable Homes has been deleted. The Phase 1 RMA has been
7.1.1 Residential development will be required to be assessed against the Code for Sustainable Homes P. 66
designed to comply with LBN HQM Level 3
The development will achieve Level 4 of the Code as a minimum (of the equivalent level of any subsequently adopted national Code for Sustainable Homes has been deleted. The Phase 1 RMA has been
7.1.2 P. 66
standard on sustainable design and construction) designed to comply with LBN HQM Level 3
7.2 BREEAM
Major developments (non-residential) will be required to be assessed against the Building Research Establishment
7.2.1 P. 67
Environmental Assessment Method (BREEAM)
The development will achieve "Very Good" as minimum (or the equivalent level of any subsequently adopted national standard
7.2.2 P. 67
on sustainable design and construction)
7.3.1 Passive design techniques should be considered at the detailed design stage P. 67
7.3.2 Elements to be considered may include window placement and glazing types, thermal insulation, thermal massing and shading P. 67
8 Key Spaces
Due to airport safety zone restrictions the design shall avoid public realm provisions that will encourage people to congregate
8.1.2 P. 70
and/or stay in the area
The water's edge should be predominantly "hard", and the water's edge pavements should be of a coarse natural cobbled stoned
8.1.4 P. 70
finish to reflect the "rough" industrial heritage context of the site
Soft landscape design shall respond to the water's edge conditions and shall be employed to both emphasise the site's
8.1.5 P. 70
relationship (e.g. view lines) with the adjacent Royal Victoria Dock as well as mitigate some of its environmental exposure
The east and west side should be linked with pedestrian bridges across the mount of Pontoon Dock as set out on Parameter Plan Outside Phase 1
8.1.6 P. 70
05 RMA
Scale and Enclosure
Outside Phase 1
8.1.7 Due to airport safety restrictions, no building is permitted immediately adjacent to the waterfront to the east of the Dock P. 71
RMA
To the west of the Dock, built form may project out to the face of the dock wall, with pedestrian and vehicular access underneath, Outside Phase 1
8.1.8 P. 71
as is the case at present with the Rank Hovis building RMA
8.1.9 The buildings should be set back 5m at ground floor to provide pedestrian access P. 71
8.2.7 The buildings should be set back 5m at ground floor to provide pedestrian access. P. 73
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 413
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
8.4.3 Existing (London Plane) tree planting should be retained and incorporated wherever possible P. 76
As set out in section 2.7, 80% of the ground floor building frontage along the central bit of North Woolwich Road should be active Outside Phase 1
8.4.5 P. 76
(i.e. shop/brand frontage, office lobbies or communal entrances) RMA
9.2 Quantum
9.2.1 Uses within DZ1 should be in accordance with the Development Specification and Framework (DSF) P.78
9.3 Layout
Street Alignment
Buildings along the diagonal pedestrian route leading from North Woolwich Road to Millennium Mills should be set out in Outside Phase 1
9.3.1 P.79
accordance with guidance in section 2.6 (Key vistas). RMA
Buildings should be set out with the existing quay wall in mind and in accordance with the guidance in section 2.4 (Relationship to
9.3.2 P.79
the existing dock)
Outside Phase 1
9.3.3 To the west of the Dock, built form may project out to the face of the dock wall, with pedestrian and vehicular access underneath. P.79
RMA
9.3.4 The buildings should be set back 5m at ground floor to provide pedestrian access. P.79
Permeability
The ground floor of Millennium Mills should be permeable to increase links to Royal Victoria Dock and should include at least one
9.3.5 P.80
point where non-occupants can walk through the building.
Frontages should be broken to assist permeability. Lines of sight should be established between the centre of the development
9.3.6 P.80
zone and its edges. This view should run through to visually connect Millennium Mills to the south district.
The area bordered by The Diagonal, The Dock and the square in front of Millennium Mills should be broken at least once to the
9.3.7 P.80
south and west and twice to the north and east (see middle diagram).
The area to the west of The Diagonal may be developed as one plot, with or without publicly accessible routes(s) subdividing it, Outside Phase 1
9.3.8 P.80
as illustrated by the bottom diagram on this page. RMA
Consideration should be given to the small grain and scale of the buildings along Mill Street, the existing street immediately to the
9.4.1 P. 81
west.
Buildings along the main roads and routes defined on Parameter Plan 05 should help to define the character of the street and
9.4.2 P. 81
create a coherent frontage
To help define the public open spaces, the buildings opposite Millennium Mills and Rank Hovis should create a strong urban Outside Phase 1
9.4.3 P. 81
edge with breaks no wider than 8m. RMA
Outside Phase 1
9.4.4 Buildings along The Diagonal should be developed in accordance with the guidance in section 8.3. P. 81
RMA
9.4.5 Building frontages can be individually expressed but should be aligned with the street. P. 81
9.5 Access
Outside Phase 1
9.5.1 Servicing of trading house / offices along The Diagonal will be from the parallel streets to the east and west. P. 82
RMA
Service entrances on these parallel streets can take up a maximum of 25% of the elevation and should be broken up with active Outside Phase 1
9.5.2 P. 82
uses which can include entrances to uses at upper levels and food/beverage uses, predominantly at corners RMA
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 415
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
There should be a publicly accessible pedestrian route along the entirety of the dock area, this includes a route through the
9.5.3 P. 82
ground floor of the Rank Hovis building
9.6 Landscape
Millennium Mills Square and Surrounding Places
9.6.1 Unrestricted public access should be provided all around the Millennium Mills P. 83
The different spaces around Millennium Mills should be linked with a common "language" providing continuity, visual and
9.6.2 P. 83
aesthetic homogeneity whilst providing a unique atmosphere
The design for these spaces should respond to the Millennium Mills' architecture and include both seating areas and event space
9.6.3 P. 83
for temporary outdoor exhibitions and pavilions.
Outside Phase 1
9.6.4 Design for the space to the south of Rank Hovis should include spaces to rest and soft landscaping P. 83
RMA
Local materials should be used reflecting Millennium Mills' heritage and the remaining train tracks to the north of Millennium Mills
9.6.5 P. 83
should be incorporated into the public realm design and be recognised for their heritage qualities
Design should include a focal point in the intersection of The Diagonal and the east-western pedestrian route, this may be in the Outside Phase 1
9.6.6 P. 83
form of a water feature RMA
9.6.7 Tree planting (with large species) should be incorporated to provide climatic moderation, provide human scale and ambience P. 83
Outside Phase 1
9.6.8 The landscape design for The Diagonal should be in accordance with guidance in section 8.3 P. 83
RMA
The design intent for representation of the historic and existing dock edge should be in accordance with the guidance in section
9.6.9 P. 83
8.2
At a reserved matters stage, detailed design proposals should study how the local landscaping around Pontoon Dock Square can
9.6.10A P. 83
mitigate against wind in this area and seating areas should be carefully positioned in the least windy areas.
Diagonal Square
Outside Phase 1
9.6.10B The majority of the existing dock wall should be visible in the public realm, as set out in section 8.2 P. 84
RMA
Outside Phase 1
9.6.11 Unifying surface treatment should be used to define the square P. 84
RMA
Outside Phase 1
9.6.12 The water should be continuous through The Diagonal and access made over a bridge structure P. 84
RMA
Outside Phase 1
9.6.13 Facades may be connected with arcades to define the square P. 84
RMA
Outside Phase 1
9.6.14 Unifying tree planting should be used to define the square P. 84
RMA
Detailed design of the square should take into account the key routes through the space and create opportunity for spill out areas Outside Phase 1
9.6.15 P. 84
from adjacent cafes and brand spaces RMA
9.7 Appearance
9.7.1 Buildings should engage with the public at ground floor level; frontages should be mainly glazed and blank elevations avoided P. 85
Buildings are to have an uncluttered and simple roof profile with all plant equipment concealed within the main silhouette of the
9.7.2 P. 85
building and in accordance with section 6.2 (Rooftop Equipment)
9.7.3 Rooftop amenity spaces in the form of communal, private or public terraces are encouraged P. 85
Signage and advertising should be incorporated into the building design and be sympathetic to the overall expression of the
9.7.4 P. 85
building
9.7.5 Consideration should be given to the fifth elevation (the view of the building from above) refer to section 6.2 (Rooftop Equipment) P. 85
9.8.1 As set out in Parameter Plan 07, the maximum building heights for Millennium Mills is as existing P. 86
Where rebuilding the new construction will be in keeping with the original industrial palette of white painted brickwork and large,
9.8.2 P. 86
openable windows
9.8.3 Where area of the building are to be rebuilt, they should retain the historic height of the existing buildings P. 86
The ground floor should be permeable to increase the link to Royal Victoria Dock and include at least one point where non-
9.8.4 P. 86
occupants can walk through the buildings, as set out in section 9.3
Detailed proposals should activate the ground floor and may introduce uses within the building that aim to attract visitors to the
9.8.5 P. 86
building
9.8.6 The ground floor may include space for temporary installations and uses P. 86
The main entrance should serve as simple graphic identification to signify routes into the building and may use part of the
9.8.7 P. 86
retained existing canopy, either in its entirety, or as an architectural motif.
New double glazed windows will retain the industrial character of the building whilst significantly improving the thermal comfort.
9.8.8 P. 86
High and low level opening vents will provide natural ventilation to occupants.
9.8.9 If the buildings are refurbished in phases, temporary hoarding should help to activate frontages and aid navigation P. 86
Frontage onto Millennium Mills Square to the south should be predominantly active and 80% of the ground floor building frontage
9.8.10 P. 86
should be lined with shop frontages, lobbies and communal entrances, as set out in section 2.7
Temporary Landscape
Any temporary landscape shall reflect the "incubator" nature of the Millennium Mills business model and shall allow for optimal
9.8.9 P. 87
flexibility and versatility
The landscape design should provide a "canvas to work on". The landscape should be perceived as temporary until the adjacent
9.8.10 P. 87
buildings in the Millennium Mills district are developed
Many of the initial functions and events will be of an experimental nature and the outdoor environment should be simple to allow
9.8.11 P. 87
for event management to create their own temporary, event related outdoor environment
The temporary landscape should be simply related to the Mills building architecture and should include both hard (utilitarian
9.8.12 P. 87
pavements) and soft (hard wearing lawns) areas
To define the space around the Mills, both towards the south as well as along the Royal Victoria Dock side, temporary fast
9.8.13 P. 87
growing (sacrificial) tree planting (e.g. Poplar cultivars) may be planted to provide peripheral shelter and shade
9.8.14 Guidance for the permanent landscaping for the spaces around Millennium Mills is set out in section 9.6 P. 87
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 417
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
10.2 Quantum
10.2.1 Uses within DZ2 should be in accordance with the Development Specification and Framework (DSF). P.91
10.3 Layout
Existing shallow HV and comms services planned for diversion. Deep level
Development on the most southern plot needs to consider the "below ground" utilities running across this plot; any structure
sewer easements, design interfaces and access arrangements subject to a
10.3.1 needs to be offset a minimum of 3m from this easement unless there is a specific agreement with Thames Water in place and P. 91
Thames Water Build over agreement, a process initiated by Aecom and being
unrestricted 24hr access from Thames Water is provided
progressed by plot teams
10.3.3 The tertiary street running north-south should be activated with community uses or residential entrances P. 91
The buildings along North Woolwich Road should have active frontage, either in the form of non-residential uses or communal
10.3.4 P. 91
residential entrances onto this street and not turn their backs to it
Consideration should be given to the small grain and scale of the buildings along Mill Street, the existing street immediately to the
10.4.1 P. 92
west, and any adjacent buildings should be set back a minimum of 18m from existing windows
Consideration should be given to the impact on sun and daylight provision to the properties along Mill Street. Detailed analysis
10.4.3 P. 92
should be carried out as part of the Reserved Matters Applications
The buildings along the street running parallel with Mill Street should have a shoulder height of 5 storeys, with built form above
10.4.4 P. 92
this permitted subject to keeping within the permitted heights
The buildings on the corner of North Woolwich Road and the primary road (running north-south) should be considered together
10.4.5 P. 92
so they form a strong formal relationship and express an entrance to the site
Consideration should be given to the impact of sun and daylight provision to the properties along Mill Street. Detailed analysis
10.4.6 P. 92
should be carried out as part of the Reserved Matters Applications
10.5 Access
Any residential parking along the western side of the north-south secondary street should be at the level of North Woolwich Road
10.5.1 P. 93
(which is susceptible to flooding) raising the residential accommodation above the flood plain
Development should avoid creating a platform for development separate from the street and entrances should be accessed
10.5.2 P. 93
directly from street
Blank elevations should be avoided as far as possible and in accordance with the Site Wide guidance in section 6.1, but where
10.5.3 P. 93
unavoidable because of site levels and flood plain issues, they should be offset by large and articulated communal entrances.
10.6 Landscape
Silo D and the surrounding open space and finger dock has been designed as an
Silo D, its surrounding open space and the adjacent (remnant) finger pier should be regarded as one integral (heritage) design
10.6.1 P. 94 ? integrated area. They are integrated as a singular element of the public realm.
element. Existing dock edge, balustrades and the semi-circular paving feature shall be integrated in the urban realm design
Balustrades are not provided but fall protection is provided via street furniture
The urban design intent to provide a setting for Silo D as a free-standing building, to display its unique architecture should be
10.6.2 P. 94
respected. The landscape design shall follow suit and tree planting shall merely be used to unify the space and building within
The public realm design should respond to and relate to the building's architecture and orthogonal nature and should reflect the
10.6.3 P. 94
original industrial design language
10.6.4 Selection of materials should clearly relate to the Silo D architecture, site and setting P. 94
10.6.5 The "historic character" of the finger pier shall be underscored by the presence of water lilies in the former dock P. 94
10.7 Appearance
Plots that form a backdrop to Silo D in the key vistas set out in section 2.6 should be carefully designed to appear as background
10.7.1 P. 95
elements
Expression of shoulder heights can be achieved in different ways, for example through the use of different materials, by massing
10.7.2 P. 95
or through set-backs
The buildings along North Woolwich Road should have partly active frontages, either in form of non-residential uses or communal
10.7.3 P. 95
residential entrances facing onto North Woolwich Road
Silvertown Quays Phase 1 Reserved Matters Application | Design and Access Statement 419
Design Compliance
Design Code Page Design Rationale
Code Ref. Check
12.2 Quantum
12.2.1 Uses within DZ4 should be in accordance with the Development Specification and Framework (DSF). P.91
12.3 Layout
Outside Phase 1
12.3.1 The development zone should be split into at least three distinct buildings with a publicly accessible route between them P. 105
RMA
Buildings should be set back a minimum 5m from kerb along North Woolwich Road and in accordance with the guidance in
12.3.2 P. 105
section 8.4 (North Woolwich Road)
Along the secondary road to the north, buildings opposite the dock should be set back a minimum 5m to create an increased
12.3.3 P. 105
public realm area for café/restaurant spill out and for the office buildings to the east and west to have entrances onto
Outside Phase 1
12.3.4 The building along the east site of The Diagonal should be designed in accordance with the guidelines in section 8.3 P. 105
RMA
Outside Phase 1
12.3.5 Plot layout should allow for future pedestrian bridge crossing over North Woolwich Road to the DLR station P. 105
RMA
12.4.1 Buildings may be built to the full permitted height on Parameter Plan 07 P. 106
Along North Woolwich Road small-scale mitigation measures, in the form of trees or a canopy may be required to mitigate
12.4.2 P. 106
against wind
12.5 Access
On plot parking should be accessed from the north. Direct access into car park from North Woolwich Road is not permitted. The
12.5.1 P. 106
building to the west of the Diagonal should be serviced from the west via a tertiary road
Drop-off and set-down/pick-up points to be located at designated places, off the main vehicle carriageway, so vehicles can stop Outside Phase 1
12.5.2 P. 106
to allow passengers to get into or out of the vehicle and unload mobility equipment RMA
Outside Phase 1
12.5.3 Drop-off/pick-up points should be located to minimise impact on pedestrian accessibility P. 106
RMA
Outside Phase 1
12.5.4 Landscaping to allow for drop-off/pick-up points next to all key residential and public entrances P. 106
RMA
Outside Phase 1
12.5.5 Drop-off/pick-up points should preferably be located within 10-20m, and no more than 50m, of entrances to key facilities P. 106
RMA
Outside Phase 1
12.5.6 All pavements to be detailed to provide kerbed areas to accommodate taxi wheelchair ramps P. 106
RMA
Entrances should as far as possible be positioned away from the corners of the buildings, which are the areas most exposed to
12.5.7 P. 106
wind
Outside Phase 1
12.5.8 Access to the DLR station may be via a pedestrian bridge over North Woolwich Road, as set out on Parameter Plan 05 P. 106