Professional Documents
Culture Documents
I. INTRODUCTION .......................................................................................... 1
i
(c) The Court Allowed Plaintiff to Present Unauthenticated
Evidence to Witness on Direct Examination (Rule 901)
ii
TABLE OF AUTHORITIES
Cases
i
I. INTRODUCTION
Judgment entered on January 14, 2019, by Honorable David Palmer of the Maricopa
September 21, 2018 and October 25, 2018. Plaintiff filed its Complaint against
business practices, which was apparently done to falsely discredit him in the eyes of
the Court. Further, Plaintiff/Appellee called a hostile witness and former tenant of
Defendant /Appellant whose testimony was “hearsay” and the Court allowed despite
had been terminated are irrelevant. Defendant/Appellant could not have anticipated
ii
Plaintiff/Appellee’s reliance on false testimony and was not able to effectively cross
misrepresentations with evidence to support them, but the Court did not review all
the parts of the Motion, declined to review the Notice and affirmed the Judgment.
presented to the Superior Court and find that the Judgment was entered in error and
i
II. ISSUES PRESENTED
ii
(d) The Court Would Not Allow Defendant /Appellant
/Appellant to Present Authenticated Evidence for Cross
Examination
i
III. STATEMENT OF JURISDICTION
minute entry on January 14, 2019, after a two (2) day bench trial held on
September 21, 2018, and October 25, 2018, and Defendant/Appellant filed a timely
Notice of Appeal on February 13, 2019 and a Rule 59 Motion to Amend the
2019, corrected by Notice of Errata on February 15, 2019. On April 13, 2019,
2019, the Superior Court issued a minute entry denying Defendant /Appellant’s
April 13, 2019. The Court has jurisdiction over the appeal pursuant to A.R.S. §12-
ii
IV. STATEMENT OF THE CASE
breach of contract and the judicial foreclosure on the mechanic’s lien not because
leniency to the Defendant /Appellant appearing “pro se” and did not even offer the
The Court found Defendant /Appellant in breach of the Contract for failing
to pay Appellee but failed to consider the Contractual requirement to apply credits
statutory requirements required to perfect the Mechanic’s Lien and further failed to
file a Notice of Lis Pendens both of which are necessary in a foreclosure action.
Jeff Suer and Dan Edwards included statements that Defendant /Appellant
concluded were acts of Perjury and were shown in his Rule 59 Motion by trial
one altered document, a forgery. Defendant /Appellant then asked the Court to
refer the acts of Perjury and forgery to the Maricopa County Prosecutor's office for
rehash the case. The Court accepted that argument stating that it had not read the
text in detail. The comments included: “Defendant seeks what amounts to legal
advice in asking the court for direction on the initiation of an investigation by the
ii
V. STATEMENT OF FACTS
Contract”) was for restoration work after an accidental fire. The second was an
Addendum for addition of a second story to the property. A further Addendum was
signed on December 20, 2014 in the amount of $9,151.68, primarily for building
code upgrades that were not included in the Base Contract or Addendum ("Second
Addendum").
The Base Contract in the amount of $125,722.89 signed on or about June 30,
2014 (as corrected on or about December 19, 2014); the Addendum signed on
complete. The second Addendum was signed on December 20, 2014 in the
amount of $9,151.68, primarily for building code upgrades that were not included
started and work on it was substantially completed in the summer of 2016 and that
i
Defendant /Appellant paid for the goods and services required under the Base
Contract.
Plaintiff/Appellee stated that he advanced the costs for materials and labor
for the construction of the second story. Following termination of the Contract
before completion, Defendant /Appellant refused to pay Plaintiff when invoiced for
by failing to pay the final amount due that it stated was $44,708.55, allowing for
and allowed him to occupy the Property constituting an illegal residential tenant
and to complete work and obtain a Certificate of Occupancy from the City of
Phoenix.
of the work (materials and labor) for completion of either the Base Contract or the
/Appellant $43,820.96 for the amount overpaid for work not completed on the
Base Contract. Defendant /Appellant denied he retained any other contactors and
did not retain tenant Dan Edwards to do any work on the Property and evicted him
Base Contract was signed and at least 249 days after the Building Permit was
issued.
of progress, including failure to obtain the building permit until October 21, 2015,
in Gorilla’s Final Revised Invoice (EIR 220) for work on the Addendum was the
testimony of Witness Jeff Suer. who said that based on his experience 80% of the
Contracted work was completed. The invoice stated that the 80% was a ‘draw,’ a
an interim payment with a final payment when 100% of the work is complete. The
based on accounting records, not a Contractor’s estimate. There were neither any
corroborating documents nor any other testimony to support Suer’s opinion. for
example, that could have included the ‘draw’ schedule to show what work was
The Final Revised Invoice is, however, fraudulent because the statement of
work completed includes ‘paint’ of the entire interior and exterior, but an email
i
from Suer to Brown (EIR 219) states that only limited preparation for painting was
completed on part of the interior, none on the exterior. Other items not completed
includes ‘plumbing trim’ meaning faucets, shower heads, towel bars, etc. implying
that all fixtures were installed, but that was not true. Of the plumbing fixtures, at
least the jetted tub (“Jacuzzi”) and steam shower were not installed.
ii
VI. STANDARD OF REVIEW
The Court should review de novo the trial court’s conclusions of law and its
interpretation of the pertinent statutes. Pence v. Glacy, 207 Ariz. 426, 428 ¶ 10
(App. 2004). The Court should also review de novo whether the trial court’s “entry
of [summary] judgment was proper.” Schwab v. Ames Constr., 207 Ariz. 56, 60 ¶
17 (App. 2004). On review, the Court “view[s] the evidence and reasonable
inferences from it in the light most favorable to the non-moving party.” Allstate
Final Revised Invoice (EIR 220) for work on the Addendum was the testimony of
Witness Jeff Suer who said that based on his opinion, he estimated that at least
80% of the Contracted work was completed. The invoice described the 80% as a
to justify an interim payment with a final payment to make the total 100% when all
i
of the work is complete. The final amount upon termination of a partially
nor any other testimony to support Suer’s opinion. As examples, that could have
included the ‘draw’ schedule to show what work was included in an 80% draw;
The Final Revised Invoice for the Addendum describes work completed as:
‘80% draw for the two-story addition as of today we have completion of the plans,
Windows, roof, stucco, drywall, doors, trim and paint’, resulting in an amount
payable, with sales tax, of $40,281.96. The Invoice is fraudulent because the
statement of work completed includes ‘paint’ of the entire interior and exterior, but
an email from Suer to Brown (EIR 219) states that only limited preparation for
painting was completed on part of the interior, none on the exterior. Other items
not completed included installation of plumbing fixtures. The invoice states work
bars, etc. implying that all fixtures were installed, but that was not true. Of the
plumbing fixtures, at least the jetted tub (“Jacuzzi”) and steam shower were not
installed.
ii
Plaintiff/Appellee stated in the Complaint that “after Gorilla invoiced Brown
for the goods and services provided for the Second Story addition, Brown ordered
Gorilla to stop work and has refused to pay” which is not true. The stop work order
was issued on July 18, 2016. Gorilla emailed the invoice to Brown on August 12,
2016.
in a “timely manner” which was a requirement of the Base Contract that included
the following:
“Time is of the essence” in the Contract is not limited to the construction, but
includes the process of obtaining the building permit required for Construction to
begin. Although there is no specific timeline specified in the Contract, Gorilla’s lack
of diligence is apparent from the incredibly long elapsed time from the time the Base
Contract was signed to initiation of construction. It took Plaintiff 392 days from the
i
date the Base Contract was signed to submit the application for the Building Permit
and 86 additional days to obtain approval. It was 494 days before construction began,
which is more than three times the 120-150 days expected for completion of
construction as stated in the Contract. The 102 days it took Plaintiff to obtain
approval of the permit application from the City of Phoenix and initiate construction
in the Addendum in order to track the timeliness of the work. Brown insisted on
regular reports because he lived out of state and was unable to personally track the
progress. Thus, they were of critical importance but Gorilla only provided seven (7)
reports to Defendant /Appellant instead of the 104 weekly reports required over the
two (2) year period. Plaintiff’s failure to provide the reports and failure to complete
The Mechanic’s Lien had at least five (5) major defects, each of which is
ii
The preliminary 20-day notice was dated November 20, 2015 but should
have been issued within 20 days after the work first commenced. Plaintiff
commenced work on the demolition and planning for the restoration and new
construction shortly after the Base Contract was signed on or about June 30, 2014,
The Amended Preliminary 20-Day Notice dated April 13, 2016 states an
amount of $210,000, which is considerably more than the total of all of the
The Mechanic’s Lien (EIR 221) includes on Page 3, paragraph 5 the date of
completion ‘unknown and/or ongoing’ but the latest date would have been on or
about August 4, 2016, the date the final work on the HVAC system was completed.
Lienor's demand for all unpaid invoices after deducting all just credits and offsets
is $ 44,708.55, the lien amount is $ 44,708.55 plus $350 collection costs which
was computed. The total amount of the Lien is invalid because it includes the
amount of at least six identified invoices or receipts totaling $4,768.25 (EIR 259-
264) for work completed and/or invoiced more than 20 days prior to November 21,
the amount of $42,000 dated November 20, 2015, an Amended Preliminary 20-
Day Notice dated April 13, 2016 in the amount of $210,000; an invoice called
Home Remodel Overages dated August 17, 2016 which appears to total
$14,004.68 (There is no basis in the Contract for most of the items in this invoice)
and a final invoice dated August 17, 2016 in the total amount of $40,281.96 for
work on the Addendum. The invoice describes work completed as: ‘80% draw two
for the two-story addition as of today we have completion of the plans, permits,
stucco, drywall, doors, trim and paint’, resulting in an amount payable, with sales
tax, of $40,281.96. The fifth document is the Addendum with a total of $47,775
plus tax before adjustments: for work charged elsewhere in whole or in part; (items
numbered 11 Front door $1,000, 14-16 totaling $3,050); declined (item 18 $650)
and/or not completed (item number 17 added kitchen island cabinet cabinets and
countertop $1,000). The total of those reductions is $5,700, reducing the total value
of work that could have been completed on the Addendum to $47,775- $5,700=
$42,075. An 80% draw would be $33,660 plus 5.39% sales tax, a total of $35,474.
Thus, the maximum due on the Invoice would be $35,474 less the value of the
painting not completed and the installation of the plumbing fixtures, which would
ii
have to be determined. There would also have to be an adjustment for ‘all just
Plaintiff/Appellee did not provide any statement of ‘all just credits and
some of the credits and offsets due only to demonstrate that the lien does not
appear to be deducting ‘all just credits and offsets.’ These are a general credit of
$4,000 (EIR 223) and one associated with the Addendum ($17,125-$11,707 credit
for floor tile in the Base Contract =$5,418.09) (EIR 225) as stated in paragraph 8
on page 4. The total of credits and offsets due from these two sources is $5,418.09
+ $4,000 = $9,418.09.
not completed on the Base Contract is significantly larger. (Trial Exhibit 211)
Contract on June 30, 2015 and commenced work shortly thereafter on demolition
and planning of the renovations. Brown was served with the twenty-day notice of
the intent to file a mechanic’s lien on November 20, 2015, more than 16 months
i
after work commenced. Scottsdale Mem’l Health Sys., Inc. v. Clark, 157 Ariz.
461, 463 (1988) (holding that under A.R.S. § 33-992 the priority date for a
work, rather than the date on which the lien was recorded.”); Id. notice shall be
given no later than twenty days after claimant first furnishes labor, professional
services, materials, machinery, fixtures or tools to the jobsite….” Further, the work
on the addition under the Addendum was not a separate contract as defined under
A.R.S. §33-993(B). Further, Plaintiff’s Second 120 Day Notice is also invalid
because the amount stated $210,000.00 and in excess of the all the total Contracted
work.
Therefore, the Notice of Claim of Mechanic’s Lien is invalid for the above
stated reasons and Brown was entitled to withhold a progress payment pursuant to
A.R.S §33-1129.01(D)(1) because he did not approve Gorilla’s invoice amount and
provided a timely objection within 14 days by email to Gorilla. Gorilla clearly failed
to follow the statutory requirement and Courts enforce and recognize that mechanics'
lien claimants are required to strictly comply or lien-based recovery is barred. See,
e.g., Scottsdale Mem'l Health Sys. v. Clark, 157 Ariz. 461, 470, 759 P.2d 607, 616
(1988); Arizona's lien statutes are remedial in nature and should be liberally
construed to primarily protect laborers and materialmen who enhance the value of
ii
another's property. Performance Funding, L.L.C. v. Ariz. Pipe Trade Trust Funds,
203 Ariz. 21, 24, ¶ 10, 49 P.3d 293, 296 (App. 2002). At the same time, the statutory
Constr. Co. v. Pace Corp., 172 Ariz. 226, 229, 836 P.2d 439, 442 (App. 1992). These
seemingly inconsistent principles are harmonized by requiring that all the statutory
steps for perfecting a lien be followed, but permitting substantial compliance with
any particular step so long as the purposes of the mechanic's lien statutes are
achieved. Id.
requirement for a foreclosure action and further failed to record a Lis Pendens
required pursuant to A.R.S. §33-998(A) which requires the lien claimant to file a
notice of pendency of action within five days of filing the action or raising the
and not discretionary. The requirement being added in 1996 serves two purposes: to
provide notice of the pending litigation to anyone interested in the property and to
prevent third persons from acquiring an interest in the property during the pendency
of the litigation that would interfere with the court's ability to grant suitable and
i
equitable relief”. Hatch Cos. Contracting, Inc. v. Arizona Bank, 170 Ariz. 553, 556,
826 P.2d 1179, 1182 (App. 1992). The amendment established a bright line
pendens within the time period prescribed by A.R.S. §333-998(A) and §312-
1191(A) resulted in the extinguishment of its lien and the right of action to which it
was attached.
Finally, Plaintiff knew at the time it recorded its invalid Notice of Claim of
Mechanic’s Lien that the twenty-day notice was untimely and deficient and should
A.R.S. § 33-420(A). "When the party's ignorance of the invalidity of a lien arose
from the party's own failure to take basic steps to assure its validity." Delmastro &
Eells v. Taco Bell Corp., 228 Ariz. 134, 263 P.3d 683 (App.2011).
The Court ruled that the signature page of a contract was a different
document than the full text of signed contract (Allowing Plaintiff/Appellee to use
documents but denying Defendant /Appellant use of the entire Contracts. [A.R.E.
Rule 1006 states if a party introduces all or part of a writing or recorded statement,
ii
an adverse party may require the introduction, at that time, of any other part--or
the same time]. Further, the Court ruled that the signature page of the Base
Contract was a different document than the full text of the document.
Motion for Summary Judgment. The Affidavit describes the work he did on the
Property and the status of completion when he became involved. However, the
Court told Defendant /Appellant he would give the “Affidavit the weight it
The evidence presented to the Court through the Rule 59 Motion and Overall
fraud upon the Court and justifies relief under A.R.C.P. Rule 59(a)(1)(2). Fraud on
the court is a variety of extrinsic fraud. See, e.g., Dockery v. Cent. Ariz. Light &
Power Co., 45 Ariz. 434, 450–51, 45 P.2d 656, 662–63 (1935). The doctrine may
i
allow relief when, by fraud, a party has prevented “a real contest before the court
of the subject matter of the suit or put differently, has committed “some intentional
act or conduct ... [that] has prevented the unsuccessful party from having a fair
submission of the controversy.” Bates v. Bates, 1 Ariz.App. 165, 169, 400 P.2d
593, 597 (1965). The court has the power to set aside a judgment “[w]hen a party
obtains a judgment by concealing material facts and suppressing the truth with the
227 Ariz. 288, 299, ¶ 42, 257 P.3d 1168, 1179 (App.2011) (complaint contained
false statements and material omissions, and counsel made false statements in ex
parte hearing); see also Gordon v. Gordon, 35 Ariz. 357, 364–65, 278 P. 375, 377–
78 (1929) (wife lied in affidavit about where husband lived to excuse her failure to
provide notice).
A judgment resulting from a fraud upon the court may be set aside by
motion or by an independent action. Cypress, 227 Ariz. at 299, ¶ 42, 257 P.3d at
1179. Bates, 1 Ariz.App. at 168, 400 P.2d at 596 (when judgment is the product of
extrinsic fraud, “equity will act to prevent a failure of justice, for fraud is the arch
states "A person commits perjury by making a false sworn statement in regard to a
the statement (1) be made in the course of an official proceeding, (2) while under
oath, (3) is false, (4) believed by the speaker to be false, and (5) a material
material to the case). In this case both witnesses committed perjury during trial
and while under oath which the Court relied upon for his findings. Therefore, the
VIII. CONCLUSION
accounting of the amount actually due on the invoice less all credits and
i
from the Lien, including the amount of the Judgment and attorney's fees
awarded to Plaintiff/Appellee.
otherwise claimed.
ii