PERHITUNGAN VOLUME PENULANGAN LAPIS BAWAH ARAH HORIZONTAL

Keterangan Panjang
Detail Besi Lebar Area Jarak Penulangan Jumlah Panjang Total
Penulangan (m) (m) (m) besi (m2)
1 D25-150 9.88 2.00 0.15 13 128.44
2 D25-150 6.26 2.00 0.15 13 81.38
3 2D32-150 9.88 3.06 0.15 40 395.2
4 D32-150 6.54 3.06 0.15 20 130.8
5 2D32-150 8.6 7.12 0.15 94 808.4
6 2D32-150 7.82 7.12 0.15 94 735.08
7 2D32-150 10.24 2.56 0.15 34 348.16
8 D32-150 5.98 2.56 0.15 17 101.66
TOTAL 2729.12

PERHITUNGAN VOLUME PENULANGAN LAPIS BAWAH ARAH VERTIKAL

Keterangan Panjang
Detail Besi Lebar Area Jarak Penulangan Jumlah Panjang Total
Penulangan (m) (m) (m) besi (m2)
1 2D32-200 7.32 2.00 0.2 20 146.4
2 2D32-200 9.1 2.00 0.2 20 182
3 2D32-200 7.32 7.68 0.2 76 556.32
4 2D32-200 9.1 7.68 0.2 76 691.6
5 2D32-200 7.32 5.06 0.2 50 366
6 2D32-200 7.32 5.06 0.2 50 366
7 D32-200 9.1 5.06 0.2 25 227.5
TOTAL 2527.52