Julien To Yansen PARDEDE/IDJKT04/TDE/AREVA-TD@ATD

HOUDINET /FRVBN02
FRVBN 02/
02 /TDE/
TDE /A
REVA- cc Antonio CALDAS-REAL/FRMTG01/TDE/AREVA-TD@ATD,
REVA -TD
David NAPITUPULU/IDJKT04/TDE/AREVA-TD@ATD, Fahri
11/13/2009 08:47 PM ABUBAKAR/IDJKT04/TDE/AREVA-TD@ATD, Joko
bcc
Subject Re: RE 275kV Binjai S/S - TOP Back to Back & Discount
request.

Dear Yansen,

I fully agree with Antonio concerning the necessary visibility we need to support you in this kind of
business.
ITS can rely on us to propose our best offer in order to win projects in Indonesia and especially this one .

So, you can consider a 4% discount on AHT side and the following alternative payment terms proposal :

 5% to be paid at drawings delivery,


 85% at FCA port delivery date,
 10% at provisional acceptance certificate issuance , not later than 12 months from FAT date.

Best Regards,

Julien HOUDINET
Sales Department - SE Asia & Pacific
Areva T&D AHT - Villeurbanne, France
Tel: +33 4 72 68 32 96
Fax: +33 4 72 68 39 22
julien.houdinet@areva-td.com
Yansen PARDEDE/IDJKT04/TDE/AREVA-TD

Yansen
PARDEDE /IDJKT 04/
04 /TDE/
TDE /AR A Antonio CALDAS-REAL/FRMTG01/TDE/AREVA-TD@ATD
EVA-
EVA -TD
cc David NAPITUPULU/IDJKT04/TDE/AREVA-TD@ATD, Fahri
12/11/2009 12:56 ABUBAKAR/IDJKT04/TDE/AREVA-TD@ATD, Joko
PRAKOSO/IDJKT04/TDE/AREVA-TD@ATD, Julien
HOUDINET/FRVBN02/TDE/AREVA-TD@ATD, Martina
DE-LORENZO-POZ/ITVCE01/TDE/AREVA-TD@ATD,
Olivier RUIZ/FRLPT02/TDE/AREVA-TD@ATD, Rosa
TRI-LAKSONO/IDJKT01/TDE/AREVA-TD@ATD, Rosalina
SIMANJUNTAK/IDJKT04/TDE/AREVA-TD@ATD
Objet Re: RE 275kV Binjai S/S - TOP Back to Back & Discount
request.

Dear Antonio,

Below my comment in blue mark.

BR,
Yansen

Antonio CALDAS-REAL/FRMTG01/TDE/AREVA-TD
Antonio
CALDAS -REAL/
REAL /FRMTG01
FRMTG 01/
01 /T To Yansen PARDEDE/IDJKT04/TDE/AREVA-TD@ATD
DE/
DE/AREVA-
AREVA -TD
cc David NAPITUPULU/IDJKT04/TDE/AREVA-TD@ATD, Fahri
11/12/2009 06:20 PM ABUBAKAR/IDJKT04/TDE/AREVA-TD@ATD, Joko
PRAKOSO/IDJKT04/TDE/AREVA-TD@ATD, Julien
HOUDINET/FRVBN02/TDE/AREVA-TD@ATD, Martina
DE-LORENZO-POZ/ITVCE01/TDE/AREVA-TD@ATD,
Olivier RUIZ/FRLPT02/TDE/AREVA-TD@ATD, Rosa
TRI-LAKSONO/IDJKT01/TDE/AREVA-TD@ATD, Rosalina
SIMANJUNTAK/IDJKT04/TDE/AREVA-TD@ATD
Subject RE 275kV Binjai S/S - TOP Back to Back & Discount request.

Dear Yansen,

Could you please let us know the complete project completion time and milestones data in order to
analyse your request.

We need to have :

 Contract award date, exp. February 2010


 TOC date, February 2011
 FAC date, July 2011.

What do you mean by 90% progress ? FOB delivery ?

 85% of total amount 90% will be paid while material arrive at site .
 15% of total amount 90% will be paid while material installed .

Thank you in advance for your reply and also copy of the bidding documentation about this subject .

Best Regards,
Antonio Caldas-Real
ITR System Sales Coordination Manager

AREVA T&D Instrument Transformers


Tel: +33 (0)1 34 96 61 45
Mobile : +33 (0)6 32 80 77 29
email : antonio.caldas-real@areva-td.com
Yansen PARDEDE/IDJKT04/TDE/AREVA-TD

Yansen
PARDEDE /IDJKT 04/
04 /TDE/
TDE /AR A Rosa TRI-LAKSONO/IDJKT01/TDE/AREVA-TD@ATD, Fahri
EVA-
EVA -TD ABUBAKAR/IDJKT04/TDE/AREVA-TD@ATD, Antonio
12/11/2009 08:20 CALDAS-REAL/FRMTG01/TDE/AREVA-TD@ATD, Julien
HOUDINET/FRVBN02/TDE/AREVA-TD@ATD, David
NAPITUPULU/IDJKT04/TDE/AREVA-TD@ATD, Martina
DE-LORENZO-POZ/ITVCE01/TDE/AREVA-TD@ATD
cc Olivier RUIZ/FRLPT02/TDE/AREVA-TD@ATD, Joko
PRAKOSO/IDJKT04/TDE/AREVA-TD@ATD, Rosalina
SIMANJUNTAK/IDJKT04/TDE/AREVA-TD@ATD
Objet 275kV Binjai S/S - TOP Back to Back & Discount request.
Dear Colleagues,

Please be informing that we would like to bid 275kV Binjai S/S and this is ITS Target project as a key to
enter in 275kV network in PLN.
The project will be finance by PLN own fund (APLN) with 0% Down Payment .
Base on our experience for several on going APLN projects , we have tried to negotiate with PLN during
CDA to get DP but PLN refused as this is in accordance to PLN Board of director regulation . We have no
choice otherwise we will reject ...
In regard to the above, we would like to apply back to back condition of TOP to you as mention in the
bidding document below and request you to accept in your proposal .

Down Payment = 0%.


0%.
Progress = 90%
TOC = 5%
FAC = 5%

In addition to the above, please also be informing that we are now in the final stage of our costing and the
result we still 4% above the target price.
We once again request you to review your price and confirm to give at least 4% discount

Please note: our competitor Siemens will be very aggressive to get this project , since they have got
experience in 275kV network. (They have signed the contract 275kV Simangkuk S/S last August'09).

Your confirmation to the above request would be appreciated and waiting for your feedback today .

Kind regards,
Yansen
:._______________
CONFIDENTIALITY : This e-mail and any attachments are confidential and may be privileged . If you
are not a named recipient, please notify the sender immediately and do not disclose the contents to
another person, use it for any purpose or store or copy the information in any medium .