You are on page 1of 7

CHAPTER 22 – DRILLING AND GROUTING

Notes:
1. Rates include all lead and lift for all materials.
2. The rates for drilling are inclusive of cost of taking out cores, logging,
labeling and preservation of cores, maintained in serial order and painting
depths on cores and on the core box, and protection of drill holes till final
measurements.
3. All items where use of water is required are inclusive of water charges and
Air charges and no separate payment is to be made for.
4. Rates for drilling are inclusive of taking out relatively undisturbed sample
(penetration samples) in soil.
5. Rates for drilling are exclusive of the cost of special washing and
conducting percolation tests.
6. When casing pipes are to be left permanently in the holes, rate for drilling
shall be inclusive of labour for fixing casing pipes, but exclusive of the cost
of casing pipes.
7. The rates for drilling are inclusive of all charge for fixing casing pipes, to the
extent necessary and taking out the same after final measurement.
8. Measurements – (a) The linear dimensions shall be measured correct to
the nearest 0.01 m. The area shall be worked out in sqm correct to two
places of decimal and cubical contents in cum correct to two places of
decimal.
(b) The measurement for all types of grouting shall be made on the basis of
cement in the grout actually forced into the holes.
(c) The method of recording the details of grouting operation and determining
the quantity of grout consumed may be adopted as under
(i) For measurement of the quantity of grout injected in each hole, a
grout history sheet on proforma given below shall be recorded giving
grout intake per minute, viscosity of grout mix in form of solids and
water ratio, pressure of injection, time of pumping in water for
lubrication, event of blowing of grout, to keep the grouting system
alive. In addition, various other points of importance observed during
the operation, of grouting are recorded for every 5-10 minutes
intervals and thus the grout history sheet when plotted as shown in
Fig. 1 shall depict the exact amount of grout injected.
Actually this graph from the grout history sheet should be plotted and
form the basis of measurement and payment on actual basis and
depict the factual amount of grout injected. The area under the curve
shall represent the quantity of grout actually injected. A register shall
be maintained of 100 such sheets. Each sheet shall be machine
numbered on both sides.
(ii) Recording of the surface leakage, if any, shall be made in the remark
column of the grout history sheet showing the location. The leakage
should be immediately stopped by reducing the pressure and caulking
suitably. The grout should not be allowed to leak more than 5 percent
by visual judgment.
(iii) Measurement of cement, blown off and circulated in the grout lines,
shall be separately recorded in mass of cement actually used for
purposes of accounting the cement actually used for the enabling
works.
(iv) In case of stage grouting of the hole, cement grouted in each stage
shall be summed up.
Typical Proforma for Grout History Sheet
Date 16-12-1989

Sr. Feature and Hole Depth Method Pressures Grout Time Rate of Remarks
No RD. of Hole No. Drilled Specified Used Consistency consumption about
the type
of
leakage
Consolidation Water
grouting of Cement ratio
Concrete by volume
Dam.
1 100.00 m Fg- 3.0 m Descending 1.5 kg/cm2 3/4 kg/cm2 10:1 8.00 AM 50 L/min No
stage Leakage
(packer)
1 kg / cm2 8.02 AM 50 L / min
1 kg / cm2 8.05 AM 40 L / min
1 kg / cm2 8.10 AM 42 L / min
1 kg / cm2 8.20 AM 30 L / min
1 kg / cm2 8.40 AM 20 L / min
1.5 kg / cm2 8.45 AM 20 L / min
1.5 kg / cm2 8.50 AM 10 L / min
1.5 kg / cm2 9.00 AM 5 L / min
1.5 kg / cm2 9.30 AM Nil
1.5 kg / cm2 9.40 AM Nil
9. The following Indian Standards may be referred to :-
I.S.. No. Title
4078-1980 Code of practice for indexing and storage drill cores (first
revision) (Reaffirmed2000).
4464-1985 Code of practice for Presentation of drilling information and
core description in foundation investigation.
(Reaffirmed2000)
4999-1991 Recommendations for grouting of pervious soils.
(Reaffirmed1999)
5541-1970 Pneumatic portable drilling machine (with amendment
No.1). (Reaffirmed1998)
6066-1994 Recommendations for pressure grouting of rock
foundations in river valley projects. (Reaffirmed2004)
6926-1996 Code of practice for diamond drilling for site investigation
for river valley projects. (Reaffirmed2006)

Item No. Item Unit Rate Remark


2201 (a)Transportation of drilling Job 24786.00
equipment from place of location
to work site and from work site to
place of location.
(b) Departmental shifting of drilling Item 2201 (b)
equipment from workshop to is for
worksite and worksite to departmental
workshop- execution
(i) Loading into truck Job 1863.00
(ii) Unloading from truck Job 1863.00
(iii)Truck charges (distance Km Rate as fixed
counted from workshop to by C. E.
worksite). E&M
2202 Shifting drilling equipment from Job 1863 Payable for
one drill hole to another. exploratory
drilling work
only
2203 Drilling approximately 75 mm dia.
Vertical holes by calyx or any other
rotary process (except diamond
drilling) complete.
(a) In all strata other than rock m 1469.00
(b) In all strata like masonry, m 2203.00
concrete, rock or similar formation
of very hard conglomerate.
Item No. Item Unit Rate Remark
2204 Drilling by diamond drilling, holes
of minimum 75 mm dia. vertical or
at specified Inclination with double
tube core barrel in masonry,
concrete or rock-
(a) 0° to 10° vertically downwards m 6480.00
(b) Exceeding 10° but not m 7128.00
exceeding 45° vertically
downwards.
(c) 0° to 45° vertically upwards m 9072.00
(d) Up to but not including 45° to m 7776.00
the horizontal.
2205 Drilling by diamond drilling, holes
of less than 75 mm dia. vertical or
at specified inclination with double
tube core barrel in masonry
concrete or rock-
(a) 0° to 10° vertically downwards m 5832.00
(b) Exceeding 10° but not m 6426.00
exceeding 450 vertically
downwards.
(c) 0° to 45° vertically upwards m 8154.00
(d) Up to but not including 450 to m 7020.00
the horizontal.
2206 Drilling 35 mm dia. holes in rock by m 330.00
jack hammer up to 6 m.
2207 Drilling 50 mm dia. holes in rock of m 751.00
depth exceeding 6 m by wagon
drill.
2208 Wet percussion drilling 35 to 75
mm dia. holes in open space for
grouting or anchor etc., vertical or
at specified inclination, in masonry
, concrete or rock including
flushing and routine washing of
holes up to 30 minutes-

(a) 0° to 100 vertically downwards m 1620.00


(b) Exceeding 10° but not m 1782.00
exceeding 45° vertically
downwards.
(c) 0° to 450 vertically upwards m 2268.00
Item No. Item Unit Rate Remark
(d) Up to but not including 45° to m 1944.00
the horizontal.
2209 Wet percussion drilling 35 to 75
mm dia. holes in drainage gallery ,
for grouting or anchor etc., vertical
or at specified inclination, in
masonry concrete or rock including
flushing and routine washing of
holes up to 30 minutes.
(a) 0° to 10° vertically downwards m 2160.00
(b) Exceeding 10° but not m 2322.00
exceeding 45° vertically
downwards.
(c) 00 to 450 vertically upwards m 2970.00
(d) Up to but not including 45° to m 2538.00
the horizontal.
2210 Conducting percolation test in the
drill holes at the desired pressure,
Including water supply
arrangements and necessary
accessories etc. complete-
(a) Up to 10 m depth each 459.00
(b) Beyond 10 m depth for every each 92.00 Add in item
addition of 10m depth or part no 2210 (a)
thereof.
2211 Conducting standard penetration
test in the bore holes at every 1.5
m interval from the desired
elevation including cost of all
accessories and arranging of
cores from depths as obtained
(a)Up to 10 m depth each 551.00
(b)Beyond 10 m depth for every each 110.1 Add in item
addition of 10 m depth or part no 2211(a)
thereof.
2212 Redrilling (wet percussion) set or m 405.00
partially set grout holes for Items
no.2208 and 2209.
2213 Special washing of holes, including Per hour 450.00
cleaning, flushing and all related
incidental works etc. complete
Item No. Item Unit Rate Remark
2214 Grouting of 35 to 50 mm dia. holesPer tonne 10956.00
with cement grout mix, at requiredof cement
pressure, including cost of cement
and maintenance of all technical
records, Incidental works,
materials complete.
2215 Providing and fixing black steel
casing pipe including cutting,
threading, etc., complete-
(a) 50 mm dia m 459.00
(b) 64 mm dia m 551.00
(c) 80 mm dia m 734.00
(d) 100 mm dia m 1102.00
2216 Providing and installing metal Kg 248.00
tubing, brass, steel, cast Iron
fittings and valves.
2217 Supplying and installation of each 9180.00
foundation displacement indicator,
complete.
2218 Extra rate for providing wooden each 1377.00 Payable for
core boxes of suitable size for exploratory
preserving 6 m length of core. drilling work
only

You might also like