Professional Documents
Culture Documents
1
Aggregate Planning
Organizations cannot predict exactly the quantity and timing of
demand for specific products or services months in advance
under the seasonal variations in demand with uneven demand
Corporate Economic,
Strategies and Competitive, Aggregate
policies and political demand
conditions forecasts
Establishes operations
Business Plan and capacity strategies
Establishes
Aggregate plan
operations capacity
Planning Sequence 4
The aggregate plan will guide the more detailed planning that eventually
leads to a master schedule.
Establishes operations
برنامه کسب وکار and capacity strategies
Establishes
برنامه ادغامی operations capacity
Establishes schedules
زمانبندی اصلی
for specific products
Planning Sequence 5
Demand and Capacity Options
6
Demand Options (proactive strategy)
Pricing: pricing differentials are used to shift demand from peak
periods to off-peak periods (e.g., early bird specials)
Hire & lay off workers: changes in workforce level will have on
capacity(e.g., different # workers at different time interval)
9
General procedure for Aggregate Planning
Period 1 2 3 4 5 6 Total
Forecast 200 200 300 400 500 200 1,800
11
Example 1 – Aggregate Planning
12
Example 1 - Solution
Period 1 2 3 4 5 6 Total
Forecast 200 200 300 400 500 200 1800
Output
Regulr 300 300 300 300 300 300 1800
Overtime 0 0 0 0 0 0
Subcontract 0 0 0 0 0 0
Output-Forecast 100 100 0 -100 -200 100 0
Inventory
Beginning 0 100 200 200 100 0
Ending 100 200 200 100 0 0?
Average 50 150 200 150 50 0 600
Backlog 0 0 0 0 100 ? 0 100
Cost
Output
Regular $600 600 600 600 600 600 $3,600
Overtime 0 0 0 0 0 0
Subcontract 0 0 0 0 0 0
Hire/lay off 0 0 0 0 0 0
Inventory $50 150 200 150 50 0 $600
Back orders $0 0 0 0 500 0 $500
Total $650 750 800 750 1150 600 $4,700
13
Example 1 - Cumulative Graph
Demand
Exceeds
output
Surplus
Output
14
Disaggregating the Aggregate Plan
For the production plan to be translated into meaningful terms for
15
Disaggregating the Aggregate Plan
Master schedule: The result of disaggregating an
aggregate plan; shows quantity and timing of specific
end items for a scheduled horizon
16
Example: Disaggregating the Aggregate Plan
Inputs Outputs
Beginning inventory Projected inventory
Master
Forecast Master production schedule
Scheduling (MPS)
Customer orders Uncommitted inventory
(Available-to-promise (ATP))
These have been evenly distributed over the four weeks in each
month: 30 per week in June and 40 per week in July
June July
1 2 3 4 1 2 3 4
Forecast 30 30 30 30 40 40 40 40
19
Available-to-promise (ATP) inventory
Beginning
Inventory
June July
64 1 2 3 4 1 2 3 4
Forecast 30 30 30 30 40 40 40 40
Customer 33 20 10 4 2
orders
(committed)
20
Projected On-hand Inventory
(It is computed week by week until it becomes negative)
JUNE JULY
64 1 2 3 4 5 6 7 8
Forecast 30 30 30 30 40 40 40 40
Customer Orders
(committed) 33 20 10 4 2
Projected on-hand
Forecast is larger than
inventory 31 1 -29
Customer orders in week 3
1-30=-29
Customer orders are
Forecast is larger than
larger than forecast in
Customer orders in week 2
week 1: 64-33=31
31-30=1 21
Determining the MPS and Projected on-
hand inventory (lot size: 70 pumps)
Every time projected inventory becomes negative, this is a signal
that production will be needed to replenish inventory
Another production (lot of 70 pumps) is added to the schedule
22
Projected on-hand inventory and MPS
are added to Master Schedule
Projected on-hand 41
inventory
11 41 1 31 61
MPS 70 70 70 70
23
Uncommitted Inventory
Ex: (in the 1st week) from beginning inventory plus the MPS
(zero) subtract the sum to obtain amount that is available to
promise: 64 + 0 – (33 + 20) = 11
ATP quantity is only calculated for the first week and for other
weeks in which there is an MPS quantity.
24
ATP(Available-to-promise) inventory quantities
have been added to master schedule
For 1st week, ATP = Beginning Inventory + MPS quantity – (‘look-ahead’ quantity)
For weeks other than 1st week, ATP = MPS quantity – (‘look-ahead’ quantity)
25
Example
Forecast for each period is 70 units. The starting inventory is zero
MPS rule is to schedule production if the projected inventory on hand is negative
Production lot size is 100 units
Starting
Inv. = 0 1 2 3 4
Forecast 70 70 70 70
Customer
Orders 80 50 30 10
Projected
On-hand
Inventory
MPS
ATP
(A) (C = A - B) (MPS + C)
Period Inventory from (B) Net Inventory Projected
Previous Period Requirements* Before MPS MPS Inventory
1 0
2
3
4
26
* Requirements equal the larger of forecast and customer orders in each period
Example
Forecast for each period is 70 units. The starting inventory is zero
MPS rule is to schedule production if the projected inventory on hand is negative
Production lot size is 100 units
Starting
Inv. = 0 1 2 3 4
Forecast 70 70 70 70
Customer
Orders 80 50 30 10
Projected
On-hand
Inventory 20 50 80 10
MPS 100 100 100 0
ATP
? ? ? ?
(A) (C = A - B) (MPS + C)
Period Inventory from (B) Net Inventory Projected
Previous Period Requirements* Before MPS MPS Inventory
1 0 80 -80 100 20
2 20 70 -50 100 50
3 50 70 -20 100 80
4 80 70 10 0 10
27
* Requirements equal the larger of forecast and customer orders in each period
Example
Determine the amount of inventory that is uncommitted (ATP)
Starting
Inv. = 0 1 2 3 4
Forecast
70 70 70 70
Customer
Orders 80 50 30 10
Projected
On-hand
Inventory
MPS
ATP
ATP is only calculated for the first week and for other weeks in which there is an MPS
28
Example
Determine the amount of inventory that is uncommitted (ATP)
Starting
Inv. = 0 1 2 3 4
Forecast
70 70 70 70
Customer
Orders 80 50 30 10
Projected
On-hand 20 50 80 10
Inventory
ATP is only calculated for the first week and for other weeks in which there is an MPS
29
Independent and Dependent Demand
Independent Demand
(uncertain)
A Dependent Demand
(certain)
B(4) C(2)
demand)
MRP (Material Requirements Planning)
32
BOM (Bill-of-Materials)
34
A product structure tree for end item X
A product structure tree is useful in illustrating how the BOM is
used to determine the quantities of each of the ingredients
(requirements) needed to obtain a desired number of end items.
End Item
35
Example 1
a. Determine the quantities of B, C, D, E, and F needed
to assemble one X
b. Determine the quantities of these components that
will be required to assemble 10 Xs, taking into
account the quantities on hand (i.e., in inventory) of
various components:
Component On Hand
B 4
C 10
D 8
E 60
36
Example 1 – Solution
10 Xs will require
B: 2 X 10 = 20, 20 - 8 = 16
C: 1 X 10 = 10, 10 - 10 = 0 (no lower-level components required)
D: 3 X 16 = 48, 48 - 8 = 40
E: 4 X 40 = 160, 160 - 60 = 100.
1 X 16 = 16, 100 + 16 = 116 38
F: 0
MRP Processing
Week # Beg. 1 2 3 4 5 6 7 8
Inv
Items:
Gross
Requirements
Scheduled receipts
Projected on hand
Net requirements
Planned-order
receipts
Planned-order
releases 39
MPR Processing
Gross requirements
Total expected demand during each time period without regard to amount
on hand.
Scheduled receipts
Open orders (orders that have been placed and are scheduled to arrive
from vendors by the beginning of a period)
Net requirements
40
Actual amount needed in each time period
MPR Processing
Planned-order receipts
Quantity expected to received by the beginning of the period
Lot-for-lot ordering: equal net requirements
Lot-size ordering: exceed net requirements
Planned-order releases
Indicates a planned amount to order in each time period;
equals planned-order receipts offset by lead time.
This amount generates gross requirements at the next
level in the assembly or production chain.
41
Inventory Requirements
Net requirements:
Net Requirements = Gross Requirements – Available Inventory
Available Inventory:
Available Inventory = Projected on-hand – Safety stock
42
Example
A firm that produces wood shutters and bookcases has received two orders
for shutters: one for 100 shutters and one for 150 shutters
The 100-unit order is due for delivery at the start of week 4 of the current
schedule, and 150-unit order is due for delivery at the start of week 8
Each shutter consists of two frames and four slatted wood sections. Wood
sections are made by the firm, and fabrication takes one week. The frames
are ordered and lead time is two weeks. Assembly of shutters requires one
week
There is a scheduled receipt of 70 wood sections in (at the beginning of)
week 1
Shutter
LT: 1 week
44
Example
MRP schedule with lot-for-lot ordering
Planned-order
receipts 100 150
Planned-order
releases 100 150
45
Lot-for-lot ordering (i.e., planned-order release equal to net requirements)
Example
MRP schedule with lot-for-lot ordering
100 150
times times
2 2
Planned-order
200 300
receipts
Planned-order 300
releases 200
46
Example
MRP schedule with lot-for-lot ordering
100 150
times times
4 4
Planned-order
330 600
receipts
Planned-order 600
releases 330
47
MRP Outputs
MRP systems have the ability to provide management with a fairly
broad range of outputs. These are often classified as primary reports,
which are the main reports, and secondary reports, which are
optional outputs
49
Thank you!!