You are on page 1of 3

Doc.No.

: PRJ 200
Daily Progress Report REV.No.: 00
Eff.Date: 01.02.2018

Client : Adani Gas Ltd Pipe Dia & Thickness :12" & 7.9mm Date: 01-11-2019
Contractor : Tolani Projects Pvt Ltd Pipe Specification :API 5L Gr-X-42M
TPIA : TUV India Location :Riico road to Hindustan zinc Puliya, chittorgarh
PROGRESS Qty Executed
Weekly Last
Sr Total Qty
No
Activity UOM
(Scope)
Planing Week
Today’s Previous Cumulat. Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Total
Progress

1 Pipe Received ( Steel) Mtr. 4690 0 29130.99 29130.99 0 0 0 0 0 0 0


MDPE 125mm
2 Mtr. 0 0 0 0 0 0 0 0 0
Received ( PE)
MDPE 90mm Received
3 Mtr. 0 0 0 0 0 0 0 0 0
( PE)
4 Pipe Stringing Mtr. 4690 254.14 4282.410 4536.55 0 0 0 0 254.14 254.14 0

Main line Welding Nos. 460 4.00 242 246 0 0 0 3 4 7 5

5 Tie in welding Nos. 1 23 24 0 0 2 1 1 4 9

Total Welding Nos. 460 5.00 265 270 0 0 2 4 5 11 14

Radiography taken Nos. 460 0.00 265 265 0 1 2 10 0 13 13

Reviewed Nos. 0 252 252 0 0 0 0 0 0 21

Accepted Nos. 0 252 252 0 0 0 0 0 0 21

Retake / Reshoot Segment - 39 39 0 0 0 0 0 0 0


6
RT/RS Attended Segment - 39 39 0 0 0 0 0 0 0

Repair Segment - 16 16 0 0 0 0 0 0 0

Repair Attended Segment 0 16 16 0 0 0 0 0 0 0

Total Accepted Nos. 0 252 252 0 0 0 0 0 0 13

7 Joint Coating Nos. 460 13 240 253 0 1 1 15 13 30 18

8 Trenching Mtr. 4690 235.22 1745.85 1981.07 0 0 0 140.00 235.22 375.22 326.85

9 Lowering Mtr. 4690 375.22 ### 1962.98 0 0 0 0 375.22 375.22 325.34

10 MDPE 125 Lowering Mtr. 0 0 0.00 0 0 0 0 0 0 0

11 MDPE 90 Lowering Mtr. 0 0 0.00 0 0 0 0 0 0 0

12 MDPE 125 Joints Nos. 0 0 0.00 0 0 0 0 0 0 0

13 MDPE 90 Joints Nos. 0 0 0.00 0 0 0 0 0 0 0

14 Backfilling Nos. 181.63 1,449.32 1630.95 0 36.32 0 0 181.63 218.26 295

15 HDD Mtr. 0 0 0.00 0 0 0 0 0 0 0

Manpower Machinery

Type Nos. Type Name Qty.

Welders 2 Project Manager Hydra 2

Fitters & Grinder 3 Q.A./Q.C Engineer MANORANJAN SHARMA JCB 2

Riggers 5 Site In-charge (Steel) Shajahan P I Welding M/c Set 3

Helpers 4 Project Co-ordinator Ganesh sharma Coating Equipment Set 1

Excavation Labours 3 safety officer Rajan verma Grinding M/c 12

Insulator 2 Foreman Submercible Pump 1

sand blaster 1 Electrician /Mechanic Ajeet Prajapati Power Generator 1

operator & Drivers 6 Store Keeper Dinesh Sharma Trailor / Tractor/LMV 6

Supervisor 1 Planning Engineer

Store Keeper 1 Trenching Supervisor Sugata Dutta

Welding Supervisor Sadam Hussain

Coating Supervisor Pramod kumar

RCM Ramneek singh

Q.A./Q.C Engineer Nitin Kumar

Contractor's Stock Sheet Welder Performance

Qty. Welder Name Jt. Done Repair % of Repair Remarks

Welding Electrode - 6010 625 KG Mukesh Mahato 252

Welding Electrode - 7010P1 1450 KG Balinder Mahato 252

Coating Sleeves 2 KM(280 NOS)Jagannath 18

Warning Mat 20 KM

ANY PROBLEMS :

Contractor TPIA AGL


Sign:
Name:
Date:
GA-Chittorgarh

DPR as on 01.11.2019

Sr.No Activity UOM Todays Previous Cumulative


1 Stringing M 254.14 ### 4536.550
Nos 5 265 270
2 Welding
M 72.64 4211.24 4283.88
3 Lowering M 375.22 1587.76 1962.98
4 Backfilling M 181.63 1449.32 1630.95
Next Day Program As On Date 02.11.2019

S.No. Activity Location Supervisor Name/Engineer Contact No.


1 Mainline Welding KM-05 Manoranjan Sharma 9337814987
2 RT Taken KM-05 & KM-03 Manoranjan Sharma 9337814987
3 Joint Coating KM-05 & KM-02 Pramod Kumar 9048316176
4 Trenching KM-05 Sugata Dutta 9330539235
5 Lowering KM-05 Pramod Kumar 9048316176
6 Tie in joint KM-05 Manoranjan Sharma 9337814987
7 Backfilling KM-05 Sugata Dutta 9330539235
8 RT Review Dark Room Manoranjan Sharma 9337814987

FOR TOLANI PROJECTS PVT LTD