Question 1 (1 point)

Saved
True or False: PERT assumes each activity duration has a range
that follows a statistical distribution.
Question 1 options:
True
False

Question 2 (1 point)

Saved
When using PERT, the average project duration is calculated as:
Question 2 options:
The sum of the weighted average activity times for all of the project activities.

The sum of the most likely activity times for all of the project activities on the critical path.
The sum of the weighted average activity times for all of the project activities on the critical path.
The sum of the pessimistic activity times for all of the project activities.

Question 3 (1 point)

Saved
The critical path for the network below is:
Question 3 options:
1-3-6-7
1-2-4-6-7 and 1-2-5-6-7
1-2-4-6-7
1-2-5-6-7

Question 4 (1 point)

Saved
For the network below, using PERT what is the average project
duration?

Question 4 options:
93
116
86
83

Question 5 (1 point)

Saved
For the network below, what is the probability of completing the
project in 93 time units?

Question 5 options:
approximately 86%

approximately 50%

approximately 16%

approximately 34%