Professional Documents
Culture Documents
TPDA
TPDA
COSTODIRECTO MANO DE OBRA [B] MAQUINARIA [C] [F]BETUN-PETRELEOS(ASFALTO) [H]PINTURA LATEX [X] NO PRINCIPALES
RIOS]
PRECIO
CODIGO DESCRIPCION UNIDAD CANTIDAD UNITARIO PRECIO TOTAL
PRECIO PRECIO PRECIO PRECIO PRECIO PRECIO PRECIO
PRECIO UNITARIO PRECIO TOTAL UNITARIO PRECIO TOTAL UNITARIO PRECIO TOTAL UNTARIO PRECIO TOTAL UNTARIO PRECIO TOTAL UNTARIO TOTAL UNTARIO PRECIO TOTAL
1 DESBOCRE, DESBOQUE Y LIMPIEZA ha 1.18 457.14 539.43 380.95 449.52 35.95 42.42 345.00 407.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0
7 TRANSPORTE DE MATERIAL DE EXCAVACION m3-km 10293.50 0.26 2676.31 0.22 2264.57 0.03 308.81 0.19 1955.77 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0
8 BASE CLASE 4 m3 26993.19 8.21 221614.09 6.84 184633.42 0.16 4318.91 1.60 43189.10 0.00 0.00 5.04 136045.68 0.00 0.00 0.04 1079.73 5.08 137125.41
9 TRANSPORTE DE MATERIAL DE BASE m3-km 433510.63 0.26 112712.76 0.22 95372.34 0.03 13005.32 0.19 82367.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0
10 ASFALTO MC PARA IMPRIMACION l 261576.00 0.58 151714.08 0.48 125556.48 0.05 13078.80 0.25 65394.00 0.16 41852.16 0.00 0.00 0.00 0.00 0.02 5231.52 0.18 47083.68
NO PRINCIPALES X 40263.1336 VARIOS: LUBRICANTES, FILTROS Y GRASAS 3.00% VARIOS: LUBRICANTES, FILTROS Y GRASAS 551129.35 3% 16533.88
1788199.44 100% 551129.35
DESGLOCE DE
DESCRIPCION SIMBOLO COSTO DIRECTO EQUIPOS COSTO DIRECTO
COEFICIENTE
MANO DE OBRA B 101705.39 60624.23 162329.61 0.091
EQUIPOS C 286587.26 286587.26 0.160 FORMULA DE REAJUSTE DE PRECIOS QUEDARIA ASI:
RESPUESTOS DE QUIPOS D 143293.63 143293.63 0.080
COMBUSTIBLES E 44090.35 44090.35 0.025
MEZCLA ASFALTICA F 833216.44 833216.44 0.466
MATERIALES PETROS G 231367.93 231367.93 0.129
PINTURA H 30517.20 30517.20 0.017
NO PRINCIPALES X 40263.13 16533.88 56797.01 0.032
1237070.09 551129.35 1788199.44 1
COSTODIRECTO
PRECIO
CODIGO DESCRIPCION UNIDAD CANTIDAD UNITARIO PRECIO TOTAL
PRECIO UNITARIO PRECIO TOTAL MES1 MES2 MES3 MES4 MES5 MES6 MES7
1 DESBOCRE, DESBOQUE Y LIMPIEZA ha 1.18 457.14 539.43 380.95 449.52 179.8067333559 179.806733356 89.9075332881
7 TRANSPORTE DE MATERIAL DE EXCAVACION m3-km 10293.50 0.26 2676.31 0.22 2264.57 679.3682621349 679.368262135 905.8330769395
8 BASE CLASE 4 m3 26993.19 8.21 221614.09 6.84 184633.42 36926.68392 36926.68392 55390.028373 55390.02338745
9 TRANSPORTE DE MATERIAL DE BASE m3-km 433510.63 0.26 112712.76 0.22 95372.34 19074.46772 19074.46772 28611.70158 28611.70158
10 ASFALTO MC PARA IMPRIMACION l 261576.00 0.58 151714.08 0.48 125556.48 37666.944 37666.944 25111.296 25111.296
MANO DE OBRA
PRECIO UNITARIO PRECIO TOTAL MES1 MES2 MES3 MES4 MES5 MES6 MES7
35.95 42.42 16.9682427199 16.9682427199 8.4845145602 0 0 0 0
0.03 2462.40 738.72 738.72 984.96
0.18 3705.66 1111.698 1111.698 1482.264
0.20 6454.23 0 1936.269132957 1936.269133 1290.846088423 1290.8456456628 0 0
0.15 3088.05 0 926.415 926.415 617.61 617.61 0 0
0.03 11074.48 0 3322.34442 3322.34442 2214.89628 2214.89628 0 0
0.03 308.81 92.6411266548 92.6411266548 123.52269231 0 0 0 0
0.16 4318.91 0 863.78208 863.78208 1295.673178305 1295.6730616947 0 0
0.03 13005.32 0 2601.06378 2601.06378 3901.59567 3901.59567 0 0
0.05 13078.80 0 0 3923.64 3923.64 2615.76 2615.76 0
0.15 22524.60 0 0 4504.92 4504.92 6757.38 6757.38 0
0.04 9959.55 0 0 1991.90984 1991.90984 2987.8648974418 2987.864622558 0
48.26 965.20 0 0 0 0 0 0 965.2
0.11 7992.60 0 0 0 0 0 0 7992.6
0.19 1150.45 0 0 0 0 0 0 1150.45
80.33 160.66 0 0 0 0 0 0 160.66
0.47 1104.50 220.9 220.9 220.9 220.9 220.9 0 0
3.51 7.02 7.02 0 0 0 0 0 0
56.31 168.93 168.93 0 0 0 0 0 0
0.70 14.00 14 0 0 0 0 0 0
1.96 58.80 58.8 0 0 0 0 0 0
0.04 60.00 60 0 0 0 0 0 0
0.00 0.00 0 0 0 0 0 0 0
0.00 0.00 0 0 0 0 0 0 0
MAQUINARIA [C]
PRECIO UNITARIO PRECIO TOTAL
345.00 407.10 162.838490636 162.838490636 81.423018728
0.16 13132.80 3939.84 3939.84 5253.12 0 0 0 0
1.52 31292.24 9387.672 9387.672 12516.896 0 0 0 0
1.72 55506.38 0 16651.91454343 16651.914543 11101.27636044 11101.2725527 0 0
1.25 25733.75 0 7720.125 7720.125 5146.75 5146.75 0 0
0.19 70138.38 0 21041.51466 21041.51466 14027.67644 14027.67644 0 0
0.19 1955.77 586.72713548 586.7271354801 782.31038463 0 0 0 0
1.60 43189.10 0 8637.8208 8637.8208 12956.73178305 12956.730616947 0 0
0.19 82367.02 0 16473.40394 16473.40394 24710.10591 24710.10591 0 0
0.25 65394.00 0 0 19618.2 19618.2 13078.8 13078.8 0
0.62 93101.68 0 0 18620.336 18620.336 27930.504 27930.504 0
0.20 49797.75 0 0 9959.5492 9959.5492 14939.324487209 14939.32311279 0
6.75 135.00 0 0 0 0 0 0 135
0.19 13805.40 0 0 0 0 0 0 13805.4
0.17 1029.35 0 0 0 0 0 0 1029.35
149.00 298.00 0 0 0 0 0 0 298
1.62 3807.00 761.4 761.4 761.4 761.4 761.4 0 0
0 0 0 0 0 0 0
7.88 23.64 23.64 0 0 0 0 0 0
0
0.50 15.00 15 0 0 0 0 0 0
0.00 0.00 0 0 0 0 0 0 0
0.00 0.00 0 0 0 0 0 0 0
0.00 0.00 0 0 0 0 0 0 0
MATERIALES
0.00 0 0 0 0 0 0 0 0
0.00 0 0 0 0 0 0 0 0
0.00 0 0 0 0 0 0 0 0
1.84 59378.916 0 17813.67602321 17813.676023 11875.78401349 11875.779940098 0 0
1.83 37674.21 0 11302.263 11302.263 7534.842 7534.842 0 0
0.00 0 0 0 0 0 0 0 0
0.00 0 0 0 0 0 0 0 0
5.08 137125.4052 0 27425.08104 27425.08104 41137.62341119 41137.619708807 0 0
0.00 0 0
0.18 47083.68 0 0 14125.104 14125.104 9416.736 9416.736 0
5.27 791364.28 0 0 158272.856 158272.856 237409.284 237409.284 0
0.00 0 0
88.54 1770.8 0 0 0 0 0 0 1770.8
0.42 30517.2 0 0 0 0 0 0 30517.2
2.55 15440.25 0 0 0 0 0 0 15440.25
4384.67 8769.34 0 0 0 0 0 0 8769.34
0.80 1880 376 376 376 376 376 0 0
35.00 70 70 0 0 0 0 0 0
103.54 310.62 310.62 0 0 0 0 0 0
30.00 600 600 0 0 0 0 0 0
15.00 450 450 0 0 0 0 0 0
0.20 300 300 0 0 0 0 0 0
250.00 1500 225 225 210 210 210 210 210
80.00 320 80 80 80 80 0 0 0
405.00 810 810 0 0 0 0 0 0
CRONOGRAMA VALORAADO DE TRABAJOS
TIEMPO EN COMPROBACION
PRECIO
CODIGO RUBRO UNIDAD CANTIDAD UNITARIO PRECIO TOTAL MESES
MES 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES 7 MES1 MES2 MES3 MES4 MES5 MES6 MES7
1 DESBOCRE, DESBOQUE Y LIMPIEZA ha 1.18 457.14 539.43 215.77 215.77 107.89 539.43 1 40.00% 40.00% 20.00%
0.47 0.47 0.24 1.18 2 30.00% 30.00% 40.00%
40.00% 40.00% 20.00% 100.00% 1.00 3 30.00% 30.00% 40.00%
7 TRANSPORTE DE MATERIAL DE EXCAVACION m3-km 10293.50 0.26 2676.31 802.89 802.89 1070.53 2676.31 19 100%
3088.04 3088.04 4117.42 10293.50 20 100%
30.00% 30.00% 40.00% 100.00% 1.00 21 100%
8 BASE CLASE 4 m3 26993.19 8.21 221614.09 44322.82 44322.82 66484.23 66484.22 221614.09 22 100%
5398.64 5398.64 8097.96 8097.96 26993.19 23 15.00% 15.00% 14.00% 14.00% 14.00% 14.00% 14.00%
20.00% 20.00% 30.00% 30.00% 100.00% 1.00 24 25.00% 25.00% 25.00% 25.00%
9 TRANSPORTE DE MATERIAL DE BASE m3-km 433510.63 0.26 112712.76 22542.55 22542.55 33813.83 33813.83 112712.76 25 100.00%
FLUJO
PLANILLA
ANTICIPO 30% 30% $ 643,311.89
AMORTIZACION ANTICIPO 5%
FLUJO DE GARANTIAS 5%
DEVOLUCION FG
TOTAL DE INGRESOS $ 2,144,372.98 $ 643,311.89
EGRESOS
MANO DE OBRA 101705.39 2489.6773693747
RUBRO1 42.42 16.9682427199
RUBRO2 2462.40 738.72
RUBRO3 3705.66 1111.698
RUBRO4 6454.23 0
RUBRO5 3088.05 0
RUBRO6 11074.48 0
RUBRO7 308.81 92.6411266548
RUBRO8 4318.91 0
RUBRO9 13005.32 0
RUBRO10 13078.80 0
RUBRO11 22524.60 0
RUBRO12 9959.55 0
RUBRO13 965.20 0
RUBRO14 7992.60 0
RUBRO15 1150.45 0
RUBRO16 160.66 0
RUBRO17 1104.50 220.9
RUBRO18 7.02 7.02
RUBRO19 168.93 168.93
RUBRO20 14.00 14
RUBRO21 58.80 58.8
RUBRO22 60.00 60
RUBRO23 0.00 0
RUBRO24 0.00 0
RUBRO25 0.00 0
SUB-CONTRATOS -
EQUIPOS TERCIARIOS -
GASTOS GENERALES $ 182,271.70 $ 2,062.17
UTILIDAD $ 173,901.83 $ 2,015.29
TOTAL DE EGRESOS $ 2,144,372.98 $ 24,260.88
BALNCE
FLUJO MENSUAL $ 619,051.01
FLUJO ACUMULADO $ 619,051.01
MES2 MES3 MES4 MES5 MES6
154821.08 390613.47 370476.23 454515.35 315345.65
$ 15,729.21 $ 39,821.33 $ 37,761.27 $ 46,331.15 $ 32,203.40
14499.20 38051.41 36012.70 44225.84 31314.48
185049.48 468486.21 444250.19 545072.34 378863.53
10268.91
0
0
0
0
0
0
0
0
0
0
0
0
965.2
7992.6
1150.45
160.66
0
0
0
0
0
0
0
0
0
15267.75
0
0
0
0
0
0
0
0
0
0
0
0
135
13805.4
1029.35
298
0
0
0
0
0
0
0
0
0
56707.59
0
0
0
0
0
0
0
0
0
0
0
0
1770.8
30517.2
15440.25
8769.34
0
0
0
0
0
0
210
0
0
$ 8,363.18 $ - $ -
$ 7,782.92 $ - $ -
$ 98,390.35 $ - $ -
FLUJO
PLANILLA
ANTICIPO 30% 30% $ 643,311.89
PRESTAMO BANCARIO
DEVOLUCION PRESTAMO BANCARIO
AMORTIZACION ANTICIPO 5%
FLUJO DE GARANTIAS 5%
DEVOLUCION FG
TOTAL DE INGRESOS $ 2,144,372.98 $ 643,311.89
EGRESOS
MANO DE OBRA 101705.39 2489.6773693747
RUBRO1 42.42 16.9682427199
RUBRO2 2462.40 738.72
RUBRO3 3705.66 1111.698
RUBRO4 6454.23 0
RUBRO5 3088.05 0
RUBRO6 11074.48 0
RUBRO7 308.81 92.6411266548
RUBRO8 4318.91 0
RUBRO9 13005.32 0
RUBRO10 13078.80 0
RUBRO11 22524.60 0
RUBRO12 9959.55 0
RUBRO13 965.20 0
RUBRO14 7992.60 0
RUBRO15 1150.45 0
RUBRO16 160.66 0
RUBRO17 1104.50 220.9
RUBRO18 7.02 7.02
RUBRO19 168.93 168.93
RUBRO20 14.00 14
RUBRO21 58.80 58.8
RUBRO22 60.00 60
RUBRO23 0.00 0
RUBRO24 0.00 0
RUBRO25 0.00 0
SUB-CONTRATOS
EQUIPOS TERCIARIOS
GASTOS GENERALES $ 182,271.70 $ 2,062.17
UTILIDAD $ 173,901.83 $ 2,015.29
TOTAL DE EGRESOS $ 2,144,372.98 $ 24,260.88
BALNCE
FLUJO MENSUAL $ 619,051.01
FLUJO ACUMULADO $ 619,051.01
MES2 MES3 MES4 MES5 MES6
154821.08 390613.47 370476.23 454515.35 315345.65
$ 15,729.21 $ 39,821.33 $ 37,761.27 $ 46,331.15 $ 32,203.40
14499.20 38051.41 36012.70 44225.84 31314.48
185049.48 468486.21 444250.19 545072.34 378863.53
$ 680,000.00
-
-
$ 15,729.21 $ 39,821.33 $ 37,761.27 $ 46,331.15 $ 32,203.40
$ 14,499.20 $ 38,051.41 $ 36,012.70 $ 44,225.84 $ 31,314.48
$ 185,049.48 $ 468,486.21 $ 444,250.19 $ 545,072.34 $ 378,863.53
$ -680,000.00
$ -163,521.70 $ -113,659.06 $ -29,517.11
$ -27,253.62 $ -18,943.18
$ 102,299.13
$ 354,297.02 $ 246,261.30 $ -508,827.62
10268.91
0
0
0
0
0
0
0
0
0
0
0
0
965.2
7992.6
1150.45
160.66
0
0
0
0
0
0
0
0
0
15267.75
0
0
0
0
0
0
0
0
0
0
0
0
135
13805.4
1029.35
298
0
0
0
0
0
0
0
0
0
56707.59
0
0
0
0
0
0
0
0
0
0
0
0
1770.8
30517.2
15440.25
8769.34
0
0
0
0
0
0
210
0
0
$ 8,363.18 $ - $ -
$ 7,782.92 $ - $ -
$ 98,390.35 $ - $ -