Divisional Engineer, The Superintending Engineer,
MRT&Transformers/Metro-East OMC/Metro – East,
220KV SS Moulali, II Floor, 220KV GIS SS OU,
Hyderabad. Tarnaka, Hyderabad.
Ref:- Lr.No.CE/PS/SE/PS/DE/SP-1/121/F./D.No.131/19,Dated.01.06.2019.
*****
Vide reference cited, it was requested to adopt the re-trip time of 100msec and Back trip
time of 200msec for LBB in Bus bar protection schemes for all existing and upcoming 220kV and
400kV elements in TSTRANSCO network and requested to submit the report compliance.
Inview of the above, adopted the above revised settings for all 220kV and 400kV elements
in Metro-east circle.
Submitted for favor of information and taking further necessary action please.
Yours Faithfully,
Sd/-
Divisional Engineer,
MRT&Transformers/Metro-East
Copy to:
The Asst. Divisional Engineer/MRT/SD-1/Metro East.
The Asst. Divisional Engineer/MRT/SD-2/Metro East.
The Asst. Divisional Engineer/MRT/SD-3/Metro East.