Rab Pengadaan Lampu Jalan
Rab Pengadaan Lampu Jalan
Volume Satuan
I SPESIFIKASI LAMPU
Light Source: LED
Working Temperature(℃): -55
IP Rating: IP65
Certification: CCC, CE, EMC, LVD, RoHS
Place of Origin: Shanghai, China
Item name: 50w cobra head led street light IP65
Power: 50W
Voltage 12 Volt
IP degree: 65
Dimension: 500x210x80mm
Net Weight: 1.8kg
Material: Die-casting aluminum
Frequence: 50-60Hz
Color temperature (CCT): warm white/white/cool white
Item Type: Street Lights
Lamp Body Material: Aluminum
LED Light Source: Epistar
Lamp Power(W): 50
SPESIFIKASI BATTERY
Usage: UPS/Solar power/telcommunication/E-bike 1 Set Rp 5.183.000,00 Rp 5.183.000,00
Sealed Type: Sealed
Maintenance Type: Free
Weight: 10kg
Voltage: 12v
Size: 195*130*155*168mm
Daya 50 Amp
Color: Black
Electrolyte: Sulfuric Acid Thixotropic
Terminal: Copper Terminal
SPESIFIKASI PANEL SURYA
Max. Power (Pmax) 50WP
Max. Power Voltage (Vmp) 16.5V
Max. Power Current (Imp) 3.34A
Open Circuit Voltage (Voc) 21.1V
Short Circuit Current (Isc) 4.23A
Nominal Operating Cell Temp 45±2°C
Max. System Voltage 1000V
Max. Series Fuse 16A
Weight 6.5Kg
Dimension 775 x 680 x 28 mm
Sub Jumlah I Rp 5.183.000,00
II TIANG LAMPU
a. Pipa Besi Ø 3" Tebal 2,2 mm 6 M¹ Rp 70.000,00 Rp 420.000,00
b Besi Handdle dan Atribut 1 set Rp 200.000,00 Rp 200.000,00
c Besi Plat Strip L 4 mm (120 x240) 1 buah Rp 33.500,00 Rp 33.500,00
e Cat Warna Putih (Dasar) 0,25 Kg Rp 70.000,00 Rp 17.500,00
f Cat Warna Hitam/ Alumunium 0,25 Kg Rp 70.000,00 Rp 17.500,00
g Box Battery 1 Ls Rp 250.000,00 Rp 250.000,00
h Pengelasan 1 Ls Rp 213.000,00 Rp 213.000,00
i Mobilisasi 1 Ls Rp 100.000,00 Rp 100.000,00
Sub Jumlah II Rp 1.251.500,00
III Pemasangan Cor + Bahan (Lump Sump)
a Pekerja 1 titik Rp 35.000,00 Rp 35.000,00
b Tukang 1 titik Rp 30.000,00 Rp 30.000,00
c Semen PC @ 50 Kg 0,50 Zak Rp 72.500,00 Rp 36.250,00
d Pasir Beton/Pasang 0,10 M³ Rp 150.000,00 Rp 14.250,00
e Besi 10" KS 28,00 m Rp 7.000,00 Rp 196.000,00
f Besi 8" KS 1,60 m Rp 4.000,00 Rp 6.400,00
g Kerikil 0,15 M³ Rp 135.000,00 Rp 20.580,00
h Sekrup + Baut 19 inch 4,00 buah Rp 10.000,00 Rp 40.000,00
i Mobilisasi 1,00 set Rp 112.000,00 Rp 112.000,00
Sub Jumlah II Rp 490.480,00
IV Pemasangan Instalasi
a Instalasi Lampu dan Handle 1,00 ls Rp 150.000,00 Rp 150.000,00
b Instalasi Pemasangan Lapangan 1,00 ls Rp 100.000,00 Rp 100.000,00
Sub Jumlah IV Rp 250.000,00
Total Sub Jumlah Rp 7.174.980,00
D Jumlah (A+B+C)
E Overhead & Profit (10%) 10% x D
F Harga Satuan Pekerjaan (D+E)
REKAPITULASI
RENCANA ANGGARAN BIAYA ( RAB )
PROPINSI : JAMBI
KABUPATEN : BUNGO
KECAMATAN : JUJUHAN
DUSUN : SIRIH SEKAPUR
PENERANGAN
Kegiatan Kegiatan :
: LAMPU JALAN
Ukuran : 1 SET Bobot Ukuran : Bobot Jumlah Total Bobot
No Uraian
Jumlah : 1 Unit % Jumlah : % %
No. RAB : No. RAB :
Dana GDM Swadaya Dana GDM Swadaya Dana GDM Swadaya
1 2 3 4 5 6 7 8
I LAMPU + PANEL + BATTERY
5.183.000,00 72,24 5.183.000,00 64,79
1 Set
II TIANG LAMPU
a. Bahan 1.251.500,00 17,44 1.251.500,00 15,64
III Pemasangan cor + Bahan
a. Lumpsump 490.480,00 6,84 490.480,00 6,13
III Pemasangan Instalasi
250.000,00 3,48 250.000,00 3,12
( tidak perlu dirinci )
Jumlah 7.174.980,00 100,00 7.174.980,00 89,69
PPH 1,5% 107.624,70 1,35
PPN 10% 717.498,00 8,97
JUMLAH TOTAL 8.000.102,70 100,00
Dibulatkan 8.000.000,00