A 3 0 3 0 3 0 0 B 6 0 6 2 8 2 2 C 3 0 3 3 6 3 0 D 5 A 3 8 3 8 0 0 E 2 C 3 5 6 8 3 3 F 6 B, D, E 8 14 8 14 0 0 G 9 A 3 12 3 12 0 0
1. What are the critical path activities?
- A, G & A, D, F 2. What is the ES of Activity D? -3 3. What is the LF of Activity E? -8 4. What is the LS of Activity E? -6 5. What is the TF of Activity B? -2 6. What is the FF of Activity F? -0 7. What is the ES of Activity B? -0 8. What is the EF of Activity A? -3 9. What is the TF of Activity G? -0 10. What is the LF of Activity D? -8 11. What is the LF of Activity B? -8 12. What is the FF of Activity B? -2 13. What is the FF of Activity E? -3 14. What is the LF of Activity G? - 12 15. What is the total project duration? - 14