Project EjemploYoutube

Solve

Change Gant

Critical Graph

Update Schedule

Activity Data Activity Time Estimates


Most
Critical Name Description Predecessors Color Min. Likely
1 1 Start Activity Start 0 0
2 1 A Activity A 4 8
3 0 B Activity B A 2 8
4 1 C Activity C A 8 12
5 0 D Activity D A 4 6
6 0 E Activity E B 1 2
7 1 F Activity F E C 6 8
8 0 G Activity G E C 2 3
9 1 H Activity H F 2 2
10 0 I Activity I F 6 6
11 1 J Activity J D G H 4 6
12 1 K Activity K I J 2 2
13 1 End Activity End 0 0
15
Times(Proj. Weeks)
Due 40.167
Critical 40.167
Var. 10.028
SD. 3.1667
On Time Prob. 0.5
Slack 0.0003
Late 0
Current 0

vity Time Estimates Schedule Limits Schedule Decisions


Time Activity Early Late Early Late Sched.
Max. Mean S.D. Var. Weeks Delay Sort Start Start Finish Finish Slack Start
0 0 0 0 0 0 1 0 0.0003 0 0.0003 0.0003 0
10 7.6667 1 1 7.6667 0 2 0 0.0003 7.6667 7.667 0.0003 0
24 9.6667 3.6667 13.444 9.6667 0 3 7.6667 8.0003 17.333 17.667 0.3337 7.6667
16 12 1.3333 1.7778 12 0 4 7.6667 7.667 19.667 19.667 0.0003 7.6667
10 6.3333 1 1 6.3333 0 5 7.6667 25 14 31.334 17.334 7.6667
3 2 0.3333 0.1111 2 0 6 17.333 17.667 19.333 19.667 0.3337 17.333
20 9.6667 2.3333 5.4444 9.6667 0 7 19.667 19.667 29.333 29.334 0.0003 19.667
4 3 0.3333 0.1111 3 0 8 19.667 28.334 22.667 31.334 8.667 19.667
2 2 0 0 2 0 9 29.333 29.334 31.333 31.334 0.0003 29.333
6 6 0 0 6 0 10 29.333 32 35.333 38 2.667 29.333
12 6.6667 1.3333 1.7778 6.6667 0 11 31.333 31.334 38 38 0.0003 31.333
3 2.1667 0.1667 0.0278 2.1667 0 12 38 38 40.167 40.167 0.0003 38
0 0 0 0 0 0 13 40.167 40.167 40.167 40.167 0.0003 40.167
Schedule Decisions
Sched. Perc.
Finish Finished
0 0%
7.6667 0%
17.333 0%
19.667 0%
14 0%
19.333 0%
29.333 0%
22.667 0%
31.333 0%
35.333 0%
38 0%
40.167 0%
40.167 0%
Project Graphic EjemploYoutube

Start(1) A(2) B(3) E(6) F(7) H(9) J(11)

C(4) G(8) I(10)

D(5)
K(12) End(13)
Network EjemploYoutube

Activity on Node Network


Sorted Activity Nodes Sorted Precedence Arcs
From To From To Critical
Index Sort Name Level Depth Index Index Index Name Name Arc
1 1 Start 0 0 1 1 2 Start A 1
2 2 A 1 0 2 2 3 A B 1
3 3 B 2 0 3 2 4 A C 1
4 4 C 2 1 4 2 5 A D 1
5 5 D 2 2 5 3 6 B E 1
6 6 E 3 0 6 4 7 C F 1
7 7 F 4 0 7 4 8 C G 1
8 8 G 4 1 8 5 11 D J 1
9 9 H 5 0 9 6 7 E F 1
10 10 I 5 1 10 6 8 E G 1
11 11 J 6 0 11 7 9 F H 1
12 12 K 7 0 12 7 10 F I 1
13 13 End 8 0 13 8 11 G J 1
14 9 11 H J 1
15 10 12 I K 1
16 11 12 J K 1
17 12 13 K End 1