ACTIVITY PREDECESSORS TIME ESTIMATES (WEEKS)

A - 10
B - 3
C - 6
D B 4
E A,C 11
F A,C 12
G C,F,H 8
H A,E,G 8
I D,G,H 6
J G,H,I 6
K I,J,K 5
L I,J,K 2
M J,K,L 4
N M 3

1. DRAW AN AON AND AOA DIAGRAM


2. COMPUTE FOR ES, EF, LS, LF
3. COMPUTE FOR SLACK TIME
4. IDENTIFY CRITICAL PATH OF THE PROJECT