You are on page 1of 2

O I L A N D G A S FA C T S H E E T

Barrier management

Selecting suitable Safety Critical


Elements (SCE) / barriers to control
major accident risks, setting
appropriate performance
standards and designing effective

Bow tie diagram - each control requires mix of plant, process and people.
verification schemes.

Major accidents in the process industry typically A set of assurance activities are then specified to
involve failure of several protective layers, so the verify the performance standards are being met. A
integrity of each SCE (barrier) is vital to ensuring number of controls are required to ensure that the
safe operations. SCE’s / barriers are physical or non- SCE / barrier is suitable, sufficient and available to
physical elements designed to prevent, control or deliver it’s expected risk reduction function. It’s
mitigate of a major accident hazard. Barriers are necessary to use Hazard Identification (HAZID)
often displayed in the form of a bow tie diagram. studies to select a suitable range of barriers, as too
many may become unmanageable during the
A typical management process for SCE’s is shown verification stage.
below; firstly SCE’s need to be identified, a
performance standard is then set for each SCE to For an offshore platform there are likely to be 20-30
ensure it fulfils its purpose. SCE’s / barriers, for example:

-- Pressure vessels
Inputs Outputs -- Structural integrity
-- Process shutdown
Identification of SCE -- Pressure relief
Safety case / HAZID / -- Ignition control
Equipment and
hazard register / Bow tie analysis
MAH scenarios systems to prevent or -- Fire protection
limit effect of MAH
-- Emergency communication
-- Escape routes

Expertise from a number of engineering disciplines


Functionality
- what it does is required to set appropriate performance
Availability standards and develop schemes of verification to
Setting performance - when required
ensure each SCE / barrier performs the required
Criteria to assess
standards Reliability
suitability of SCE function throughout the facility lifecycle. Such
throughout lifecycle For SCE to fulfil - SIL / PFD
its purpose Survivability standards are essential aspects of the maintenance,
- robustness
testing and assurance arrangements for the facility.
Interactions
- other systems

Written scheme of
verification
Assurance and
Independent competent Record of time
verification and findings
person / independent
verification body Maintaining
Awareness of
integrity of SCE non-functional SCE’s
Addressing deficiencies
What we offer Why ABB?
ABB provides specialists with expertise in process ABB offers a broad range of services for SCE /
safety and integrity management covering all barrier management using specialists with a
aspects of SCE / barrier management. pragmatic approach based on extensive experience
in the operation of high hazard facilities.
We can offer a wide range of services to support
effective systems for SCE management: Our consultants have extensive experience of:

Overall system assessment and improvement plans -- Leading HAZID and HAZOP studies for offshore
-- Carrying out an overall review of the system to installations
identify areas for improvement and to make -- Analysis of major accident hazards to identity
recommendations safety critical elements, using a range of risk
assessment techniques including LOPA and QRA
Identifying SCE’s / barriers -- Displaying key risk controls on bow tie diagrams
-- Determining requirements using team based utilising proprietary software
HAZID studies -- Undertaking integrity assessments in high hazard
-- Preparing registers based on existing safety cases process industries both onshore and offshore with
/ reports fundamental understanding of ageing issues
-- Presentation using bow tie diagrams -- UKAS accredited risk based inspections, using a
well established methodology which takes into
Setting performance standards for SCE’s / barriers account operating conditions and deterioration
-- Setting performance standards covering mechanisms
functionality (what it does), availability (when it is
required), reliability (probability it will function), ABB believes that good safety management must
survivability (during or after an incident) and embrace the way in which people, plant and systems
interactions (dependency on other systems) inter-relate:
-- Developing effective written schemes of
verification to assure integrity throughout the -- Plant and equipment must be of an appropriate
lifecycle design standard / integrity and be adequately
-- Writing procedures covering recording of maintained
verification activities, tracking non-functioning -- Systems / procedures must be fit for purpose and
elements, and addressing deficiencies practicable
-- People must be adequately competent and work
Benefits within a positive cultural framework that
-- Provides assurance that major accident hazard encourages safe behaviour and a belief that
risks are under control accidents can be prevented
-- Provides assurance of equipment integrity using a
well proven risk based methodology Our approach to barrier management is designed to
-- Compliance with legal requirements comply with these beliefs and best practices in
-- Compliance with global best practice guidance published guidance from across the globe.
-- Provide consistency with existing safety case /
report and HAZID studies
-- Effective communication of hazards and key risk
controls to non-specialist staff through bow tie
diagrams
Process safety/PRS192a/03/18

— —
ABB Limited We reserve the right to make technical We reserve all rights in this document and
Daresbury Park, Daresbury changes or modify the contents of this in the subject matter and illustrations
Warrington, Cheshire document without prior notice. With contained therein. Any reproduction,
WA4 4BT United Kingdom regard to purchase orders, the agreed disclosure to third parties or utilisation of
Phone: +44 (0)1925 741 111 particulars shall prevail. ABB does not its contents – in whole or in parts – is
E-Mail: contact@gb.abb.com accept any responsibility whatsoever for forbidden without prior written consent of
potential errors or possible lack of ABB. Copyright© 2018 ABB
information in this document. All rights reserved
abb.com/consulting

You might also like